SISSON BROOK TUNGSTEN – MOLYBDENUM DEPOSIT NEW BRUNSWICK PRELIMINARY ECONOMIC ASSESSMENT (2009 TECHNICAL AND ECONOMIC UPDATE) FEBRUARY 25, 2009 J.M Marr M.Sc., P.Geo. VP Exploration, Geodex Minerals Ltd Geodex Minerals Ltd. TSX.v – “GXM” R 00 West Pender Street 150 Woodsi ancouver, BC,Canada,V6C-2V6 Fredericton, NB, Canada E3C 2R 89-5528 Toll Free:888-999-3500 Fax: 506- E-Mail: [email protected] Website: www.GeodexMinerals.com
51
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Geodex Report March 1 2009

SISSON BROOK TUNGSTEN – MOLYBDENUM DEPOSITNEW BRUNSWICK

PRELIMINARY ECONOMIC ASSESSMENT (2009 TECHNICAL AND ECONOMIC UPDATE)

FEBRUARY 25, 2009

J.M Marr M.Sc., P.Geo.VP Exploration, Geodex Minerals Ltd

Geodex Minerals Ltd. TSX.v – “GXM” Head Office Regional Office

Suite 450-800 West Pender Street 150 Woodside Lane Vancouver, BC,Canada,V6C-2V6 Fredericton, NB, Canada E3C 2R9

Tel:604-689-7771 Tel: 506-450-4488FX:604-689-5528 Toll Free:888-999-3500 Fax: 506-450-4422

E-Mail: [email protected] Website: www.GeodexMinerals.com

Page 2: Geodex Report March 1 2009

GEODEX MINERALS LTDMANAGEMENT & DIRECTORSJack M. Maris, President, Director Jack M. Marr, V.P. Exploration, Director Jack Patterson, Director Neil D. Humphreys, Chief Geologist, Director Clem Pelletier, DirectorDavid M. Buckle, DirectorNeil S. Seldon, DirectorBlaine Bailey, Chief Financial OfficerDavid Martin, Regional Manager New

BrunswickChristopher R. Anderson, V.P. Business

Development

ADVISORY BOARDDavid Sinclair, Ph.D William Gardiner, M.Sc. Raymond Dujardin, P.Eng.

SHARE STRUCTURE JANUARY 2009

CASH ON HAND•General Account $1,003,000

•Flow Through Account $1,729,000SHARES OUTSTANDING

87,453,349

Page 3: Geodex Report March 1 2009

Table of Contents

Executive Summary…………………………………………………………………………………………………………..4

1 A. Introduction………………………………………………………………………………………………………5

1 B. Purpose of this report……………………………………………………………………………………….6

1 C. Background, History and Geology……………………………………………………………………..6

1 D. Present Project Development Status…………………………………………………………………102. Updated Resource (block) model…………………………………………………………………………………

113. Pit Design/Grade Scheduling…………………………………………………………………………………………

154. Metallurgical Results, Process Development Basis, Operating Costs…………………………….205. Capital Cost Estimation…………………………………………………………………………………………………

256. Waste /Tailings Management………………………………………………………………………………………..

337. Financial Model – Spreadsheet……………………………………………………………………………………..

378. Recommendations to Pre-Feasibility …………………………………………………………………………..449. After Pre-feasibility – What happens next?......................................................................

46

Page 4: Geodex Report March 1 2009

Executive Summary

The last document on the economic status of the Sisson Brook tungsten-molybdenum project north of Fredericton, New Brunswick was a Preliminary Economic Assessment carried out by Wardrop Engineering in November 2007. A robust NPV and IRR led to the recommendation that work proceed to the next development stage. Infill drilling, geotechnical work and environmental/community studies took place in 2008 and have continued since that time.The present study, compiled mainly by consultants as described herein, is based largely on new data, particularly an expanded block model which has recently undergone preliminary pit design and grade scheduling and a program of metallurgical work at SGS in Vancouver. Parallel testing indicated that a pre-concentration circuit would profoundly benefit operating and capital costs. This upfront ore-sorting process concentrates 96.0% of the tungsten and 83.8% of the molybdenum in slightly more than half of the rock mined, which increases grade to the mill and reduces capital and operating costs. A plant layout and process equipment list was prepared and costed by an independent engineering group to reflect this revised concept. The report spreadsheet uses a mining rate of 20,000 tonnes/day for a mine life of 20 years. Overall recoveries (sorter and mill) are 74% for tungsten and 70% for molybdenum. Tungsten is priced at an APT price of $US 220/tonne of WO3 in concentrate, with a blended $US 50/tonne reduction (gravity/flotation) for offsite costs. Molybdenum uses a long term price of $US 15/lb with an 8% assessment for offsite costs and roasting. Mine Operating Costs remain at $Can 1.30/tonne ($US 1.11), beneficiation costs are re-assessed at $Can 4.66/tonne ($US 3.96) with G &A costs at $Can 0.66/tonne ($US 0.56). The re-calculated pre-production Capital Costs from the new process concept are slightly reduced at $US 339 million which includes a 30% contingency. Owner’s costs include $US 1.0 million for environmental costs during construction. Sustaining (and sinking fund provision for reclamation) costs are assessed at 2.5% of original capital per production year.Spreadsheet analysis indicates that the project has an Unleveraged IRR from Year -2 of 23%. The pre-tax NPV at an 8% discount rate is $US 372 million, $US 277 million at 10%. Payback is in Year 4. Cumulative cash flow is $US 1.18 billion.It has long been recognized that New Brunswick offers a mining-friendly environment, good access and excellent infrastructure. The economics of open pit development linked to the large size of the deposit suggest that much flexibility will exist in mine planning. Reaction to changes in metal prices can occur by constraining supply to increase margins or increasing daily volume.The recommendation within this report is that the company moves to completion of a Pre-Feasibility study by Q4 2009. The present report is a ‘baseline’ study or directional concept produced in a worldwide trough of mining finance. It requires refinement and upgrading in several areas to bring it to the stage of a commercial concept.

Page 5: Geodex Report March 1 2009

1 A. Introduction

Sisson Brook is a bulk tonnage tungsten/molybdenum deposit amenable to the cost benefits of open-pit mining. It is located in rolling ‘bush’ country (crown land) about 100 km north of Fredericton, N.B. within easy reach of several small towns. Logistics are excellent. The property is crossed by a network of logging roads connecting into main access routes. A power line passes south of the proposed pit area and a rail line exists north of the claims through the town of Napadogan. Water is readily available at the site and there is highway access to tidewater at the port of Saint John.A Scoping Study was prepared for an open-pit deposit by Wardrop Engineering on November 9, 2007 which is available on SEDAR. This report concluded that the deposit had positive economic characteristics. Using the normal Scoping Study combination of available data and industry assumptions, including metal prices current at that time, the report produced an NPV of $Can 693 million and an IRR of 29.8%. The recommendation was made to proceed to Pre-Feasibility. The decision at that time was therefore made to proceed to Pre-Feasibility, the next stage in mine development. Contractors were hired as shown in the ‘development’ section below to assist in collecting all the engineering, economic and environmental data necessary to reach Pre-Feasibility and subsequent stages. Drilling continued on the property in 2008 (11,800 m) to infill the most prospective part of the deposit (Zone III) and to check for higher grade areas such as the molybdenum-rich East Flank Zone which was discussed in various 2007 News Releases. The 2008 program also led to discovery of the Ellipse Zone south of Zone III. An aggressive regional campaign was also carried out to look for other nearby deposits (six properties) which could potentially provide ore to be trucked to the millsite to help the overall economics.Zone III and possibly its attached Ellipse zone (as shown in Section 2) are the only sources of tonnage for this study. The higher sulphide chalcopyrite-wolframite Zones I and II are not presently in the mine plan and their potential remains unexamined at this stage.Although work is continuing, enough of the Zone III data is now in hand for an updated economic study. A new Resource model incorporating the 2008 drilling with revised resource categories (Measured/Indicated/Inferred) was received from Mercator Geological Services Limited, an independent consulting group, in January 2009. These resource tonnage tables are shown in Section 2. This block model then underwent preliminary pit design analysis (Section 3) to schedule mine grades in the twenty years of anticipated mine life with optimal grades in the first few years. New metallurgical results from SGS (Vancouver) have led to a revised plant layout, most importantly incorporating a new pre-concentration option (Section 4). Metal prices, particularly molybdenum, have been lowered in line with the commodity downturn.Capital cost estimation has been reviewed in detail (Section 5) and the present status of waste/tailings management in Section 6. These factors are pulled together into an economic evaluation and spreadsheet in Section 7.

Page 6: Geodex Report March 1 2009

1 B. Purpose of this report

This report is intended to present a ‘snapshot’ economic portrait of the Sisson Brook tungsten-molybdenum deposit north of Fredericton, New Brunswick. It is a ‘point in time’ spreadsheet evaluation incorporating much new data (particularly metallurgical results), revising previous studies and using a new pricing structure for the two main metals. It is not intended to be a detailed or complex review although much analysis (Sections 4, 5) has gone into a new processing concept, plant layout and necessary equipment lists and costing. It will provide a summary and valuation for the deposit at this time and will point the way forward to the Pre-Feasibility stage.

1 C. Background, History and Geology

The Sisson brook deposit was periodically explored by various companies after the mid 1950s, much of this directed to VMS targets of Bathurst type, a completely different style of mineralization. The present Zone III (Scheelite/molybdenite) and the adjacent Zones I and II (chalcopyrite, wolframite) were discovered and drilled by Texasgulf Sulphur/ Kidd Creek Mines Ltd. in the period 1978 to 1982. Extensive surface exploration was done and 40 holes were drilled at that time.By a Letter of Agreement dated October 25, 2004, Geodex optioned a 70% interest in the property from Champlain Resources Inc., a private company based in Nova Scotia. A formal agreement was concluded on July 6, 2006. There are no royalties. Terms and conditions of that agreement have now been met and Geodex’s 70% interest has been earned. The agreement allowed Champlain to be carried to production, its share of production costs to be recovered from the first proceeds of commercial production.In November 2007, Champlain’s 30% interest was the subject of competing bids from Geodex and from Rockport Mining Corp., a private New Brunswick-based company. By acquiring 54% control of Champlain (which is still in existence under Geodex direction), Geodex now owns an effective 86% interest in the Sisson Brook deposit.At the time of the Letter Agreement in 2004, the property comprised 141 claims. Additions over the years have led to a present total of 631 claims in eight groups, protecting the deposit and surrounding land required for development. The overall block is about 12 km north-south and about 4 km wide, reflecting the trend of Zone III. The claim map is attached on the following page.

Page 7: Geodex Report March 1 2009

As referred to above, the Sisson Brook deposit comprises four wide and steeply-dipping zones of porphyry-style, vein and fracture-controlled tungsten, molybdenum and copper mineralization. The deposit straddles the strongly sheared contact of the Howard Peak granodiorite, one of a group of Siluro-Devonian intrusions in New Brunswick hosting important deposits of tungsten, tin, molybdenum and antimony. The focus Zone III and the new Ellipse zones are the largest and best explored of the deposits and are characterized by sheeted quartz veins and stockworks carrying molybdenite and scheelite. Zones I and II to the north of Zone III are younger vein systems with chalcopyrite, wolframite and increased pyrite and pyrrhotite. The presence of mineralized and altered felsic dykes in Zone III (one at least of which is Late Devonian in age) suggest the presence of a buried granitic stock at depth which supplied the heat source for the hydrothermal system and most of the metals in the deposit.

Page 8: Geodex Report March 1 2009

The local geology and the distribution of the mineralized zones are shown on the next page. A comprehensive, updated geological report is available from the company on request (Humphreys, 2009).

Page 9: Geodex Report March 1 2009
Page 10: Geodex Report March 1 2009

1 D. Present Project Development Status

Following the successful Scoping Study in November 2007, the decision was made to proceed to Pre-Feasibility. Contracts were let to Wardrop Engineering for reporting/engineering studies, to SGS Canada Inc. for metallurgical testing, to Rescan Environmental for environmental and community relations and to TerrAtlantic Engineering Inc. for geotechnical work. Infill and expansion drilling in 2008 (11,800 m) was carried out by Geodex.These contracts were suspended in late 2008 with the downturn in market activity and the lack of financing for mining projects. Much work has already been completed and these contracts can be re-established at any time. Rescan registered the project on September 5th 2008 under the NB Clean Environment Act and on October 24th 2008, Geodex was informed that, as expected, a comprehensive Environmental Impact Assessment (EIA) would be required. Environmental monitoring has been maintained over this period. The environmental work has not as yet disclosed any major problems and several community/town hall meetings have introduced the project to the local population. Acid rock drainage (ARD) studies are underway. The very low sulphur value in the Zone III head assay composite (0.45% S) is an encouraging indication. Preliminary rock mechanics studies suggest very favourable 50 degree to 60 degree bench face slopes. Waste and tailings management studies are proceeding.The provincial government of New Brunswick has expressed strong support for the project due to the general ‘have-not’ state of the economy and the de-commissioning of the Bathurst mine in 2010. This large underground zinc mine, a major tax contributor to the provincial economy, has been in operation since 1964.

Page 11: Geodex Report March 1 2009

2. Updated Resource (block) model.

Contributor: Mercator Geological Services Limited.65 Queen Street, Dartmouth, N.S.

B2Y 1G4NEWS RELEASE (Distributed January 27, 2009.)Geodex updates Zone III Resource Model at Sisson Brook, New Brunswick and adds new Resources from the adjacent

‘Ellipse’ Zone.Geodex Minerals Ltd., (the ‘Company’) is pleased to report receipt of an updated resource model for its Sisson Brook

tungsten-molybdenum deposit, located north of Fredericton, New Brunswick. This resource estimate incorporates an additional 11,800 m of infill and expansion drilling (48 angle holes) carried out on the deposit during the summer of 2008. It therefore adds substantial new data to the previous resource estimate, published in a News Release of June 5, 2008.

As in previous resource estimates, this study was independently prepared by Mercator Geological Services Limited (Mercator) of Dartmouth, Nova Scotia under supervision of Mr. Michael Cullen, P. Geo. and Mercator staff geologist Mr. Matthew Harrington. Mr. Cullen is a ‘Qualified Person’ as defined under National Instrument 43-101 (NI 43-101). The estimate is considered compliant with NI 43-101 and a Technical Report supporting the estimate will be posted on SEDAR within 45 days.

The present resource estimate differs from previous estimates which were based solely on the southern half of the Sisson Brook deposit, the area referred to as Zone III. It includes for the first time a resource calculation for a new zone called Ellipse which lies a few hundred metres to the south of the central ‘core’ zone of Zone III. The two zones intersect at the south end of Zone III. Details of the nature and size of the Ellipse Zone are set out in a News Release of September 30, 2008. Main differences from Zone III are that Ellipse lies entirely within diorite on the west side of the property and in addition appears to have a northwesterly orientation. It appears to be relatively enhanced in molybdenum, otherwise mineralogy and vein characteristics are similar.

Updated January 2009 Mineral Resource Estimate and Classification.

Mineral Resources for Zone III and Ellipse are shown in the following tables. These are Mineral Resources and not Mineral Reserves, as economic viability has not yet been demonstrated.

Page 12: Geodex Report March 1 2009

‘Zone III’ Mineral Resource Estimate

*WO3 Equivalent % Cutoff Resource Category Rounded Tonnes WO3% Mo%

0.025 Measured 26,600,000 0.072 0.025

0.075 Measured 19,400,000 0.086 0.030

0.125 Measured 11,000,000 0.109 0.037

0.175 Measured 5,100,000 0.135 0.044

0.225 Measured 1,800,000 0.168 0.053

0.025 Indicated 257,300,000 0.062 0.019

0.075 Indicated 151,100,000 0.082 0.026

0.125 Indicated 69,100,000 0.107 0.034

0.175 Indicated 26,700,000 0.131 0.045

0.225 Indicated 9,300,000 0.152 0.058

0.025 Inferred 223,600,000 0.055 0.018

0.075 Inferred 118,700,000 0.073 0.027

0.125 Inferred 47,800,000 0.097 0.036

0.175 Inferred 15,900,000 0.120 0.049

0.225 Inferred 5,400,000 0.138 0.064

Page 13: Geodex Report March 1 2009

*WO3 Equivalent % Cutoff Resource Category Rounded Tonnes WO3% Mo%

0.025 Measured 1,100,000 0.082 0.023

0.075 Measured 900,000 0.092 0.027

0.125 Measured 500,000 0.112 0.034

0.175 Measured 200,000 0.135 0.044

0.225 Measured 100,000 0.146 0.068

0.025 Indicated 28,300,000 0.072 0.024

0.075 Indicated 22,500,000 0.081 0.027

0.125 Indicated 10,400,000 0.105 0.038

0.175 Indicated 4,600,000 0.121 0.050

0.225 Indicated 1,500,000 0.139 0.067

0.025 Inferred 36,500,000 0.061 0.019

0.075 Inferred 23,400,000 0.073 0.026

0.125 Inferred 8,600,000 0.091 0.041

0.175 Inferred 3,400,000 0.102 0.057

0.225 Inferred 900,000 0.094 0.094

* WO3% EQ = WO3% + (Mo% * 2.02) from current Geodex Mo and WO3 base case pricing All resource grades based on 3 meter composites capped at 0.60% WO3 and 0.35% Mo.

Page 14: Geodex Report March 1 2009

All the tonnage in the lowest threshold category in Zone III (including Ellipse) attests to the large size of the deposit, which has not yet been totally defined. New contributions come chiefly from the Ellipse Zone, from peripheral drilling on the east side of Zone III to define the East Flank Zone, which remains open to the east, and to expansion of the overall resource at depth. The company projects that grades at the mid-level threshold (0.125% WO3 Equiv.) will be the base case situation, as presently understood. These are highlighted in the attached tables.The ‘Measured and Indicated’ resource in both zones shown above at this mid-level (0.125%) WO3 Equivalent threshold is 91.0 million tonnes. This is somewhat reduced from the 102.8 million tonnes reported in the June 5 News Release but reflects only use of a reduced molybdenum price in the WO3 Equivalent conversion formula. In view of recent volatility in world molybdenum prices, the conversion molybdenum price was reduced by 30% (to $US15/lb) from the base case pricing in the 2007 Scoping Study. This is indicated in the formula attached to the table. Much tonnage in the Inferred category remains to be upgraded.By contrast, grades have significantly improved in these mid-level grade areas. In the base case Zone III, 0.125% WO3 ‘Measured and Indicated’ category, WO3 grade has increased from 0.088% to 0.107%, an increase of 21.6%. The new tonnage/grade combination indicates a 7.6% increase in contained metal at this threshold.

Project Status

The Company will be assessing these results in the near term and particularly incorporating other new data which has been appearing this winter. Aside from the expanded block model discussed above, the company has preliminary results from the SGS metallurgical program and will be embarking this month on pit design (starter pits) and plant design layouts, including a new pre-concentration option. The company feels these will substantially revise the 2007 Wardrop Scoping Study and will point the way forward to the Pre-Feasibility study which is the next stage in the Sisson Brook development program. Metal prices have recently been very volatile, particularly that of molybdenum. The company cautions that current metal prices may not be maintained for the development period or the life cycle of any resulting mine. However, it remains confident that the near-surface, open-pittable nature of the deposit and the excellent access/power structure in New Brunswick offer very positive encouragement.Jack Marr, M.Sc., P.Geo., is the in-house QP for this project and Mr. Michael Cullen, P. Geo. of Mercator is responsible for the resource estimate presented in this press release.

Page 15: Geodex Report March 1 2009

Estimation Methodology

The resource estimate was carried out using Surpac® 6.1.1 modeling software, inverse distance squared grade interpolation and 3.0 meter down hole assay composites capped at 0.35% Mo and 0.6% WO3. Metals were separately interpolated. Block size was 10 meters (x) by 10 meters (y) by 10 meters (z) with sub-blocking at 5 meters (y) by 5 meters (x) by 5 meters (z). Grade interpolation in Zone III utilized multiple search ellipse passes constrained by grade shell wireframes oriented along the primary north-south mineralization trend (010 to 020 azimuth) in a vertical plan, with a major axis range of 175 meters, a major/semi major axis ratio of 1 (175 meters) and a major/minor axis ratio of 10 (17.5 meters). Grade interpolation in the Ellipse Zone utilized multiple search ellipse passes constrained by grade shell wireframes, oriented along the northwest-southeast mineralization trend (130 to 135 azimuth) with a 60 degree dip to the southwest and the same range and ratio parameters applied in Zone III. The entire model is fully constrained within a peripheral three dimensional solid. A specific gravity factor of 2.87 grams/centimeter3 was used for mineralization hosted by gabbro, a factor of 2.77 grams/centimeter3 was used for mineralization hosted by mixed volcanic and sedimentary lithologies, a factor of 2.82 grams/centimeter3 was used for mineralization hosted by diorite, and a factor of 2.70 grams/centimeter3 was used for mineralization hosted by granitic lithologies. A WO3 Equivalent (WO3 Eq.) factor of WO3 Eq.% = WO3% +(Mo%*2.02) was developed on the basis of client-supplied market pricing forecasts and 70% WO3 recovery and 85% Mo recovery factors reported in the project Scoping Study by Wardrop Engineering Inc. dated November 7, 2007 Measured resources were defined as any block having 12 included assay composites, with not more than four from a single drill hole, showing averaged distance from the block of 25% of the major axis range (43.75 meters), with the block being 30 meters or less from at least one included composite. Indicated resources were defined as any block having 12 included assay composites, with not more than four from a single drill hole, showing averaged distance from the block of 50% of the major axis range (87.5 meters), with the block being 60 meters or less from at least one included composite. Inferred resources were defined as all blocks within the peripheral deposit constraint not identified as Indicated or Measured resources.

Page 16: Geodex Report March 1 2009

3. Pit Design/Grade Scheduling

Contributor: Robert Sim P. GeoSIM Geological Inc. 6810 Cedarbrook Place.Delta, B.C. V4E 3C5

This memo describes the approach taken in generating a series of phased pit shells on the Sisson Brook deposit.The resource model was provided by Mercator as a comma delimited ASCII format file containing X,Y,Z (block centres), block size, Mo%,

WO3%, WO3eq%, SG, geology code and resource class. This one file covers both the Zone III and Ellipse areas of the Sisson Brook deposit. Note that Mercator’s original model uses variable block sizes of 10x10x10m and 5x5x5m which is not compatible with the MineSight® system. As a result, the model was standardized to 10x10x10m blocks prior to import into MineSight®. This block size is believed to represent an appropriate selective mining unit (SMU) size for a deposit of this type and scale.

Mercator also provided a file in dxf format containing the surface topography in both 3d contour lines and a 3d triangulated surface.The project area was expanded in MineSight® to account for the lateral extent of the pit shells. The project limits are defined below.

Min Max block size #blocksX 649000 651200 10 220Y 5135500 5137800 10 230Z -250 330 10 58The block model file and surface topography were imported into MineSight® (V 4.50). The topo surface, which is relatively flat in this

area, was extended laterally in order to cover the complete project area.Grade and bulk density (SG) data occurs only in model blocks defined as being in the measured, indicated or inferred categories. Zero

grades (for Mo%, WO% and Weq%) and a default SG value of 2.77t/m3 have been assigned to all undefined blocks below the topo surface (i.e. defining the grade and density of waste material surrounding the deposit area).

Pit Shells“Phased” pit shells are created using a floating cone algorithm and a series of variable metal prices calculated about the recoverable

tungsten equivalent (RWeq) grades in the block model. The RWeq grade is estimated to be 72% of the Weq% grades previously calculated in each block in the model. This assumption is based on the following assumptions:

Recoveries WO3 MoSorting 96% 83.8%Mill 77% 84%Overall 73.9% 70.4%(Average applied to WO3 Eq% is 72%)

Page 17: Geodex Report March 1 2009

Note that the objective is to produce a series of phased shells which extract the higher-grade material during the initial production years. This sequence occurs whether or not the recovery factors are implemented. It is only the extent of the “ultimate” pit shell that is affected by the recovery factor.The following operating and technical parameters were also used in the floating cone calculations (note that costs were initially provided in CDN$ by Geodex which were converted to US$ using a 0.85 exchange rate):Mining cost: US$1.11/t ore and wasteMilling costs: $4.53/t G&A: $0.93/tPit slope: 50 degrees For the purposes of this study, pits have been generated about all classes of material. As defined in the CIM definitions, only measured and indicated resources can be converted to (proven and probable) “reserves”. However, since this is an initial evaluation of the economic potential of the deposit (scoping study level), inferred resources have been included in the calculations and resources are presented within a series of pit shells. The resources listed within pit shells include inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that this preliminary assessment will be realized.A series of pit shells were tested at varying metal prices beginning at a minimum of $1.00/lbWO3 to a maximum of $9.00/lbWO3. The objective here was to produce a series of 10 shells which were somewhat evenly spaced down through the deposit (i.e. the volume from each shell produced a tonnage of material of approximately 10-25kt). This would allow for some reasonable degree of selectivity during the generation of the mining schedule.Although the actually prices used in the generation of each shell is of little significance, I have listed them below. During the floating cone calculations, the low price of $2.50/lbWO3 used for the first shell, forces the extraction of only the higher-grade material. Subsequent price increases allows for the shells to dig deeper into the deposit (the higher prices can support the extraction of more waste material).

Shell12345678910

Price ($/lbWO3) $2.502.753.003.253.504.004.505.006.009.00The tonnage and grade of material between each pit shell has been summarized in a spreadsheet at cut-off increments from 0 through

0.25%Weq. From this list, one can determine the amount of waste that has to be extracted from each phase when a projected cut-off threshold is applied.

Page 18: Geodex Report March 1 2009

Plan showing limit of phased pits

Page 19: Geodex Report March 1 2009

Section 5136800 showing WO3Eq block grades and phased pit shells

Page 20: Geodex Report March 1 2009

Section 5136400 showing WO3Eq block grades and phased pit shells

Page 21: Geodex Report March 1 2009
Page 22: Geodex Report March 1 2009

4. Metallurgical Results, Process Development Basis, Operating Costs

Contributor: H.M. Bolu P. Eng.Bolu Consulting Engineering Inc.#301-304 West Cordova St.,Vancouver, B.C., V6B 1E8

Initial scoping level of metallurgical testing on Sisson Brook was initiated in December 2007 and was conducted by SGS Lakefield using drill core samples. Testing was conducted on four sample types and was focused on various analyses, grindability of various rock types, mineralogy (modal analyses), and some scoping level gravity and flotation tests for the recovery of tungsten and molybdenum. Process development for Sisson Brook Tungsten-Molybdenum project for the current Technical and Economic Update Study was based on the results of subsequent preliminary metallurgical test work conducted at SGS Vancouver. Samples for this program were shipped to SGS in September 2008, and consisted of 2.8 tonnes of split drill core (~2’ dia). This metallurgical sample was a composite of six samples provided by Geodex. Each of the sub-samples came from within the higher grade central ‘core’ zone of Zone III and was selected to represent typical metal values within the gabbro, the central volcanic-hosted section and the new East Flank Zone. Each was selected from several holes in their particular area. The composite is judged to be representative of the central part of Zone III. Assays by SGS showed this composite to contain 0.096% WO 3

and 0.038% Mo. The sample also contained 0.45% total sulphur.The testing program to date covered investigations in various areas including the pre-concentration of the feed materials by ore sorting and other techniques, recovery of tungsten by gravity methods, flotation recovery of both molybdenum and tungsten, as well as other determinations. Results of the preliminary bench-top ore sorting tests that used ~1 inch rock samples indicated that potential exists to reject low grade rocks from the feed materials thereby a significant upgrade in WO3 and Mo grades using Ultraviolet fluorescence (UV) and dual energy X-Ray tomography (DEXRT) sorting techniques. Further, results of bench scale mineral dressing tests on non-sorted samples demonstrated that high grade concentrates could be produced by conventional flotation (for molybdenum and tungsten) and gravity (for tungsten) techniques. These results led to the development of conceptual process flowsheets as discussed below.Process Description:The process developed for Sisson Brook for this update study involves crushing and ore sorting of feed materials, where a low grade material is rejected into a waste stockpile, followed by further comminution of the upgraded product to a size suitable for grinding; ~10 mm. Grinding is followed by molybdenum and bulk sulphide flotation including a regrind and a cleaner circuit to produce marketable molybdenum concentrate. Tailings from this circuit will be sized and sent to a gravity circuit for the recovery of coarse tungsten values while the fines proceed to tungsten flotation. All three types of concentrates; molybdenum and tungsten (gravity and flotation) will be dewatered and bagged for shipment to markets. Please see process block diagram below. Process flowsheets are available on request.

Page 23: Geodex Report March 1 2009

CRUSHING &

SIZING

SULPHIDE FLOTATION

MOLY FLOTATION

GRINDING &

CLASSIFICATION

ORE SORTING

TUNGSTEN FLOTATION

TUNGSTEN GRAVITY

SEPARATION

WO3 Flot’n Con To Markets

Mo ConTo Markets

WO3 Gravity Con To Markets

REJECTS

SULPHIDE CON TO DISPOSAL

WO3 FLOT’N TAILS TO DISPOSAL

ROM FEED

SISSON BROOK PROCESS BLOCK DIAGRAM – CONCEPTUAL STUDY

Page 24: Geodex Report March 1 2009

Proposed plant design is based on a nominal 20,000 t/d of processing rate through the crushing and ore sorting plant, and on 10,150 t/d of milling and processing capacity through the grinding and flotation/gravity plant as described below.Crushing and Ore Sorting: ROM feed material will be crushed to nominal 200-mm before screening into three size ranges for ore sorting. The two coarse size ranges will use UV sorting while the finer size range will use the DEXRT sorting technique. Ore sorting utilizing various sort technologies based on attributes such as colour/translucence, x-ray and conductivity, has been used successfully in mineral industries for many years. Their potential use in tungsten processing has recently found renewed interest as several projects world wide are reported to be in the testing and development stage. Using the ore sorting test results as the basis, it is predicted that nearly one-half of the feed material by weight may be separated as a low grade reject stream with reasonably low metal losses. This results in an upgraded feed at nearly half the tonnage for further processing through the grinding and concentration plant. Please see table below for the predicted metallurgical recoveries for ore sorting and the subsequent processing through the concentrator. Grinding and Classification: The upgraded feed material (with reduced tonnage) will then be ground to the required liberation size of approximately 300 m through a two-stage rod milling and screening circuit. Rod mills and screens are selected for this duty in order to maximize tungsten recovery (both gravity and flotation) while minimizing the generation of slimes. This approach is commonly used in the industry as the tungsten bearing mineral, particularly scheelite, is considered to be friable and highly prone to sliming in comminution circuits. Ground material will be thickened to a density suitable for the subsequent molybdenum flotation as described below.Molybdenum and Bulk Sulphide Flotation: Thickened material will be subjected to molybdenum and bulk sulphide flotation using a conventional reagent scheme as widely practised in the industry. Molybdenum rougher concentrate will be reground and upgraded in a ball mill-column cleaner flotation circuit to produce molybdenum concentrates (+53% Mo) which will be dewatered and packaged for shipment to markets. Molybdenum flotation tailings will proceed to bulk sulphide flotation where the rougher concentrate will be cleaned once and the cleaner concentrate will be sent to the tailings pond for disposal while the sulphide tailings will proceed to the gravity circuit for tungsten recovery.

Page 25: Geodex Report March 1 2009

Tungsten Gravity Separation: Tailings from the sulphide flotation circuit will be classified into two size ranges through hydrosizers(s) ahead of gravity separation. The coarse and (de-slimed) fine products from hydrosizing will be treated through a series of spirals to produce their respective tungsten rougher concentrates which will then be upgraded on shaking tables to produce a final table concentrate. This concentrate will further be upgraded through a sulphide flotation and two magnetic separation circuits to produce high grade (+65% WO3) tungsten gravity concentrates which will be

dried and bagged for shipment to markets. A regrind circuit will provide further liberation and recycling of gravity middlings. Gravity tailings will proceed to tungsten flotation feed thickener.

Tungsten Flotation: Gravity tailings will be densified and sent to tungsten flotation for the recovery of fine tungsten values not recovered by the preceding gravity circuit. Flotation will take place in a conventional rougher-scavenger-cleaner circuit. Further, it will utilize a conventional reagent scheme and a circuit of mechanical and column cells also as commonly used in the industry. Final cleaner tungsten concentrate (~50% WO3) will be dewatered, dried and packaged

for shipment to markets.

Tailings disposal and Fresh Water Supply: The two main tailing streams, namely the bulk sulphide concentrate and tungsten flotation tailings will be combined and pumped to a proposed tailings pond located approximately 2.5 km from the mill site. Tailings supernatant water will be recycled to the mill as process make-up water via a pump-and-pipeline system. Fresh water source for potable, reagent mixing and other process make-up purposes will be the Napadogan river located approximately 1 km distance from the proposed mill site.

Process Metallurgy and RecoveriesThe metallurgical prediction provided in the following table is based on results of preliminary test work to date. As the table indicates, the plant will receive 20,000 t/d or a nominal 7M t/a of feed from the open pit at average grades of 0.098% WO3 and 0.031% Mo (grades over 20 year mine life). Ore sorting, as discussed above, will result in an upgraded

product constituting about 50.7% or 3.55M t/a of the feed mass while carrying with it approximately 94% of the tungsten and 83% of the molybdenum content in the ROM feed. The low grade “throw-away” reject product will be stockpiled or may be used in tailings facility construction.Feed to the proposed concentrator, ie: from grinding through to tailings disposal, is predicted to be 10,150 t/d at average grades of 0.185% WO3 and 0.052% Mo. Mill recoveries are predicted to be 77% for tungsten (combined gravity and

flotation concentrates) and 84% for molybdenum, resulting in overall plant recoveries (from ROM to concentrate packaging) of approximately 74% for tungsten and 70% for molybdenum.

Page 26: Geodex Report March 1 2009

SISSON BROOK TUNGSTEN-MOLYBDENUM PROJECTTECHNICAL AND ECONOMIC UPDATE STUDY

PRELIMINARY OVERALL METALLURGICAL SUMMARY

Tungsten Molybdenum Tonnage

ROM FEED

ROM Grades and Tonnes 0.098 %WO3 0.031 %Mo 7,000,000 t/a

ROM Contained Metal WO3: 686,000 MTU/a Mo: 4,873,000 Lb/a

SORTING

Recoveries into Sorter Concentrate 96.0 % 83.8 % 50.7%

Sorter Concentrate Grades and Tonnes 0.185% WO3 0.052% Mo 3,550,000 t/a

PROCESSING PLANT

Mill Recoveries 77% 84%

Overall (Sorter+Mill) Recoveries 74% 70%

Mill Products - Grades 60% WO3 53% Mo

Mill Products - Contained Metal 507,000 MTU/a 3,397,000 Lb/a

Mill Products - Tonnage 8,449 t/a 2,907 t/a

Page 27: Geodex Report March 1 2009

Operating Cost Estimate

Process operating cost estimate below includes costs for operating and maintaining the process plant from coarse ROM feed dump pocket at the primary crusher through to concentrate load out facilities, tailings management, tailings ponds plus process and fresh water pumping. Average Life-of-Mine process operating costs and unit costs in both Canadian and USA dollars are provided in table below. The basis for these costs includes previous experience of similar operations on such areas as manning levels and reagent prices; test results on power and reagents’ consumption levels; in-house data for prices on consumables; and other rules of thumb as used in the industry. Power cost is an estimate only at this stage.

Page 28: Geodex Report March 1 2009

Cost CentreAnnual Cost

(CAD$)Unit Cost

(CAD$ /t ROM)Unit Cost

(US$ /t ROM)

LABOUR

Supervisory Staff $910,000 $0.13 $0.11

Operatig Labour $2,721,440 $0.39 $0.33

Maintenance Labour $1,746,000 $0.25 $0.21

SUB-TOTAL $5,377,440 $0.77 $0.65

POWER

Process Power $7,487,000 $1.07 $0.91

SUB-TOTAL $7,487,000 $1.07 $0.91

CONSUMABLES

Reagents $9,865,439 $1.41 $1.20

Grinding Steel $4,009,847 $0.57 $0.49

Maintenance Supplies $3,047,059 $0.44 $0.37

Freight to site $1,419,600 $0.20 $0.17

SUB-TOTAL $16,922,345 $2.62 $2.23

OTHER

Reject Haulage $414,120 $0.06 $0.05

Other Expenses $1,000,000 $0.14 $0.12

SUB-TOTAL $414,120 $0.20 $0.17

TOTAL PROCESS OPERATING COST $30,496,585 $4.66 $3.96

Page 29: Geodex Report March 1 2009

5. Capital Cost Estimation

Contributors: Mark Dobbs P. Eng., Peter McNiven P. Eng., Larry Robinson P. Eng.Axxent Engineering Ltd.312, 7485 – 130th Street,Surrey, B.C., V3W 1H8

This portion of the report outlines the design work and estimating performed by Axxent Engineering Ltd (Axxent) as part of the current project update. Changes from the 2007 Wardrop scoping study are due to new data from metallurgical and pre-concentration testing (Section 4).Crushing, Screening and Ore SortingRecent advances in Ore Sorting have made it feasible to sort ore prior to the concentrator grinding circuit to eliminate approximately 50% of very low grade ore from needlessly being processed. The attached figure shows the new crushing, screening and ore sorting layout prior to fine ore stockpiling. In general terms, the process involves screening crushed ore into 3 streams which are then sorted via UV and X-ray methods to reject low grade ore and send acceptable ore for further crushing and stockpiling as feed for the concentrator. Crushing power is reduced due to reject ore bypassing the secondary and/or tertiary crushers. The quaternary crusher is eliminated.ConcentratorReduced throughput in the concentrator due to ore sorting and a general rework of the flow sheets has led to the following changes (see attached figure).Direct feed from fine ore stockpile into 2 primary rod mills eliminating 4 feed bins and 8 feed conveyors•2 Primary and 2 Secondary Rod Mills replace the 4 Primary and 4 Secondary Mills•Primary and secondary rod mills share pump boxes and pumps eliminating 4 pumpboxes and pumps•Primary and Secondary grinding horsepower has been decreased from 20,000 hp to 9200 hp•Addition of Grinding Thickener•Two regrind mills have been added with 460 hp (Moly) and 600 Hp (Tungsten).•Reduction in number and increase in size of Flotation cells•Simplification of concentrate load-out areaCapital Cost EstimationThis Technical and Economic Update addresses the changes to the Capital Cost Estimate of the Sisson Brook Tungsten / Molybdenum project that have been made since the November 2007 Scoping Study done by Wardrop Engineering Inc. (WEI). Process flowsheets for this current update are based on preliminary metallurgical test work conducted at SGS during the second half of 2008, and are developed by Bolu Consulting Engineering Inc. Further details on process development are covered in Section 4 of this report.

Page 30: Geodex Report March 1 2009

The estimate update is prepared in US Dollars. There is no consideration of escalation at this time. The current state of the world economy has a significant impact on the capital costs because pricing of major equipment, steel, concrete, construction labour and shipping has been going through a period of flux over the past seven months. The estimate update is based on plant location, throughput capacity, final product, major mechanical equipment list, process flow sheets, general arrangements, plot plans and specifications for major mechanical and electrical equipment items, all on a preliminary basis. Economic RevisionsEconomic revisions include:•Capital costs of:

•Electrical Power, transmission and substation system•Primary, secondary and tertiary crushing and sorting including conveyors and stockpiling – increased costs due to ore sorting process and decreased costs due to elimination of 4 th stage of crushing•Grinding equipment and infrastructure – decreased costs due to equipment changes and to reduction in volume of grinding•Separation, flotation and dewatering equipment and infrastructure for both Molybdenum and Tungsten – decreased costs due to lower processing volumes•Reagent processing – no significant changes•Tailings processing – lower costs due to lower volume of tailings•Buildings – increased costs in crushing from new ore sorting requirements and lower costs in the concentrator building due to smaller footprint•Infrastructure – lower costs due to reduced shipping costs and significant reductions in construction management, building construction and equipment installation.

The process of ore sorting has been added to the area between the primary crusher to the stockpile. This reduces the tonnage of material going through the concentrator from 20,000 tpd to 10,000 tpd. There is more crushing and sorting equipment required in this scenario plus larger enclosures, one for the primary sorting and the other for the secondary sorting. The estimate of capital costs of this ore crushing, sorting and stockpile area has changed from $52.7 million to $54.7 million.The concentrator flow sheet has been revised to account for lower volumes of ore being processed.Economic UpdateThe Capital Cost updates are summarized in the attached table. The overall estimate of the project is expected to decrease by approximately 5% from the Wardrop estimate in the fall of 2007 due to the development of a revised process that includes ore sorting. This has resulted in reduced throughput for the grinding and processing plant as well as reduced tailings disposal requirements. These reductions are made possible by the introduction of ore sorting and the rejection of a low grade reject stream from the ROM feed materials. A capital cost contingency of 30% is applied to reflect the high level nature of the estimate and unforeseeable costs within the scope of the estimate.Mining EquipmentMining equipment is assumed to consist of relatively small sized drills (10” or less), excavation equipment and hauling equipment. Two middle-sized shovels, three loaders and four dozers are selected to provide flexibility. No changes to mine equipment size of number are proposed in this study.

Page 31: Geodex Report March 1 2009

Process EquipmentUsing current process flowsheets as the basis, an equipment list of major process and mechanical equipment was developed. Major equipment was then sized and specified using the preliminary mass balance data. Equipment prices were developed using in-house data and costs from similar recent projects to cover the following major items:•Rock breaker, crushers and screens•Ore sorters and associated equipment•Feeders and conveyors•Grinding mills•Flotation cells and conditioning tanks•Cyclones, hydrosizers, spirals and shaking tables•Thickeners•Filters and other dewatering equipment•Magnetic separators•dryersTailings pipelines, reclaim water system and fresh water pipelines were estimated using preliminary sizing and in-house pricing. Other and minor equipment including pumps were factored. Motors are included with process equipment costs. Ore Sorter equipment costs were supplied by a potential equipment vendor in Germany. New quotes have not been obtained. The current equipment list in the attached table, has been revised to reflect changes to the process as noted above.

BuildingsPreliminary general arrangement drawings were prepared. Based on these layouts, the milling and concentrator building envelope has been reduced from 19,000 m2 in the earlier estimate to 10,500 m2 in the Axxent update. The secondary / tertiary / quaternary crushing building envelopes have been increased from 4,400 m2 to 5,500 m2 in the Axxent estimate to include ore sorting and secondary and tertiary crushing stages only. The total of all building structure envelopes has been reduced from 23,400 m 2 to 16,000 m2.

LabourA comparison was made using the electrical trade wages for CLAC in BC for the period from July 1, 2009 to June 30, 2010 as the base. The comparative figure was the rate for IBEW L2166 (Electrical Workers from the high voltage transformer to the equipment) Northern NB (North of Fredericton). These figures represent the cost of an electrical trade worker at a blended rate for a 50 hr week. The IBEW figure represents a signed contract for the period. The CLAC figure represents the published wage expectations for the period.It has been established that the US$60 / hr overall labour rate in the estimate is reasonably valid for a blended 50 hour week.

Page 32: Geodex Report March 1 2009

Electrical Power / Transmission / SubstationThe 2007 assumption has been revised to a tap-off from a 138 kV NB Power transmission line that is 25 km away from the mine. The estimate now includes a tap-off cost of $2 million and 25 km of 138 kV transmission line at $200,000 per km. There will also be a higher cost of a substation at $2 million. A portion of the capital costs of the tap-off and transmission line will be paid as an operation cost by way of a tarrif.These numbers were established from emails from NB System Operator and also by comparison to a 130 km long 230 kV transmission line in British Columbia.

Site PreparationNo revisions have been made to this estimate from the 2007 Wardrop work.Direct CostsQuantities – Quantities of steel and concrete have been revised to reflect the changes to building envelopes and conveying lengths.Equipment – Equipment pricing has been revised to reflect major equipment described in the equipment list.Bulk Materials Pricing – Bulk Material pricing was unchanged from the 2007 estimate to reflect the current state of flux of commodity pricing.Labour Rate Buildup – Labour Rate Buildup follows the conventional process of converting a 35 hour wage, including benefits, to a contractor’s charge-out rate for a 5 day 50 hour workweek.Installation Man-hours – Installation Man-hours were not revised because the estimated hours from the WEI estimate appear to reflect the appropriate level of effort to install the current configuration of equipment.Ancillary Facilities – Ancillary Facilities estimate was not revised from the WEI estimate because similar facilities are required in the updated version of the project. The mill staffing requirements have not been changed from the WEI estimate and the mobile equipment estimate has not been modified.Indirect CostsConstruction and installation work is expected to follow a 5 day / 50 hour week schedule except for periods when weekend overtime is required. •Indirect costs

•Owners costs – additional estimated costs were added for regulatory, legal, permitting and sunk costs.•Land acquisition (if any)•EPCM – the standard estimating convention of 12% of direct costs was followed.•Construction indirect costs – the allowance in the WEI estimate appears to be adequate.

Spare parts – an estimate for Critical Spares was included. Otherwise spare parts and first fills was accounted for in the working capital.

Page 33: Geodex Report March 1 2009

1.Freight – the freight estimate was reduced to reflect the smaller size and weight of most of the major equipment.2.Construction camp – the estimate for the construction camp was not changed because the assumption remains that the workers will be housed off site.3.Vendor’s reps – the allowance for vendors’ representatives was retained from the WEI estimate.4.Start up and commissioning – the allowance for start up and commissioning was reduced to reflect the smaller sized equipment and lower complexity of the concentrator.5.Contingency – the allowance for contingency was increased to reflect the high level nature of this update.

Page 34: Geodex Report March 1 2009

Millions US$

Axxent Wardrop

A Overall Site 9 6 Increased Transmission

B Surface Mining & Mining Equipment 21 21

C Primary Crushing, Sorting, Secondary / Tertiary Crushing & Reclaim 53 55 Add sorting, Eliminate Quatrinary Crushing, Smaller Stockpile

Primary Crushing & overland conveyor 9 21 Eliminate significant conveying & reclaim

34 Secondary, Tertiary, Quadrinary crushing

Sorting, Secondary / Tertiary Crushing & Reject & Stockpile 44

E Grinding, Screening, Cleaning, Flotation, Thickener, Reagents, Bagging 80 105 Process 10,000 tpd instead of 20,000

E0 36 48

E1 Grinding & Classification 15 20

E2 Flotation, Regrind & Gravity Concentration 20 25

E3 Concentrate Dewatering & Loadout 7 10

E4 Reagents 2 2

F Tailings 15 24 Process smaller amount of tailings

G Water, Air & Sewage 2 2

J Auxiliary Buildings 7 7

K Plant 2 2

Direct Costs 189 222

X Project Indirect Costs 63 70

EPCM 22 32

Construction Indirects 9

Logistics & Spares 9 12 Less equipment - smaller sizes

Commissioning & Startup 23 26

Y Owner's costs 9 5 Additional Owner's Costs were Included

261 297

Z 30% Contingency 78 59 20% in previous scoping study

339 356

Net Decrease 17

4.8%

Capital Cost Comparison between Wardrop (2007) and Axxent (2009)

Page 35: Geodex Report March 1 2009
Page 36: Geodex Report March 1 2009
Page 37: Geodex Report March 1 2009

6. Waste /Tailings Management

Contributors: John Brodie P. Eng.Brodie Consulting Ltd.572 St. Andrews Place,West Vancouver, B.CTerrAtlantic Engineering Limited,515 Beaverbrook Court,Fredericton, New Brunswick, E3B 1X6

General (TerrAtlantic Engineering Limited).Waste/tailings management was part of a broader geotechnical and hydrogeological contract awarded to TerrAtlantic Engineering, based in Fredericton, New Brunswick. The waste/tailings studies were sub-contracted to Brodie Consulting Ltd. and results to date are discussed below. TerrAtlantic assembled a three dimensional RQD model for the deposit and drilled eight boreholes, fourteen screened monitoring wells and nine test pits in the area of the planned open pit. In addition, they conducted in situ hydraulic conductivity testing, core orientation in the inclined borehole and acoustic televiewer logging of five of the vertical holes. They also laboratory tested soil and rock samples, evaluated water levels in all the monitoring wells, provided analyses of twenty one groundwater samples and conducted dewatering and mapping of the main Zone III trench.TerrAtlantic was also involved in the delineation and evaluation of various tailings area options. Three boreholes, six screened monitoring wells and forty test pits were dug in the Bird Brook tailings area, the area selected and discussed by Brodie below. Eight test pits were excavated in the planned waste disposal area.This work is still at a preliminary stage and more study is clearly required.

Waste/Tailings specific (Brodie)Preliminary engineering and geo-chemical assessment, as discussed above, has been conducted to identify a waste management strategy for the Sisson Brook deposit. Key parameters are:•Tailings quantity is estimated to be 121 M m3.•The ore (based on only 5 samples) is marginally net acid generating. After flotation removal of the economic minerals, the overall tailings product is expected to be net acid consuming.•Mineral processing is expected to yield:

A coarse rejects product that is gravel to sand-sized.

Page 38: Geodex Report March 1 2009

a predominantly silt sized tailings with a low % of sand. Geo-chemical characterization of these materials has not been conducted.

•Some of the waste rock may be net acid-generating. Quantities of waste rock types have not been determined.

Background Information The Sisson Brook area has a mean annual precipitation of 1113 mm, of which 833 mm falls as rain, based upon Environment Canada climate data for the town of Woodstock, located approximately 75 km south-west of the mine site. The Sisson Brook deposit is situated in Zone 2 (on a 6 zone scale) in terms of seismic risk, based upon Natural Resources Canada information.

Site SelectionFour potential tailings sites were evaluated using the factors described below. These led to identification of the Bird Brook site as the preferred tailings disposal location. •The regional topography consists of rolling terrain with slightly more than 100 m total relief. Local relief is less than this. The regional topography is of a similar nature for a great radius (> 50 km) around the deposit location.•Infilling of a major lake would not be considered. •The ore deposit straddles the Nashwaak/Napadogan watershed. Situation of the tailings deposit in the Napadogan watershed is preferred.•Routing of tailings discharge and reclaim water lines over major rivers should be avoided.•The regional surficial geology consists of a veneer, typically in the order of 5 m, of silty till overlying bedrock. Within the Bird Brook area, the surficial soil is more granular.•The coarse ore rejects and/or some of the waste rock is expected to be suitable for use as the main construction material of the dams.•Considering the wet climate and seismic setting, the upstream construction method may not be viable. Centerline construction method for the dams has been assumed.•The tailings impoundment is expected to have a net positive water balance (discharge of accumulated water is expected).

Page 39: Geodex Report March 1 2009

•Initial dam geometry, for the purpose of determining storage efficiency, is based upon downstream slopes of 2.5:1 and upstream slopes of 1:10

Preliminary Tailings Management Concept

The Bird Brook is located about 2 km north of the deposit. See the attached map. This site is in the Napadogan watershed. There are no lakes at this potential site. Key aspects for tailings disposal here are:•Starter dams will be constructed at the eastern end of the Bird Brook area, near to the mill location. Dams would be constructed of coarse rejects and/or select waste rock.•If necessary, a sulphide flotation circuit will be operated to remove acid-generating components from the coarse ore. The sulphide float will be placed in a dedicated facility for this type of material.•Coarse ore rejects will be trucked or conveyed into the western (uphill) side of the tailings area.•Fine tailings will be pumped to the crest of the dams and discharged hydraulically onto the beach.•The Bird Brook site has capacity for 120 M m3 of tailings. It could be expanded if necessary.•At closure, the tailings surface will be covered to facilitate the re-establishment of vegetation on the area.•Operational and post-closure water treatment is not expected to be required.•The Bird Brook tailings area in relation to the planned open pit and the process plant area are outlined on the next page.

Page 40: Geodex Report March 1 2009
Page 41: Geodex Report March 1 2009

7. Financial Model – Spreadsheet

Contributor: Jack Marr M.Sc., P. GeoGeodex Minerals Ltd.,450 – 800 West Pender StreetVancouver, B.C. V6C 2V6

Sisson Brook – Technical & Economic Update

Basis of Financial ModelThis financial model incorporates the data provided by the several participants in this technical and economic update where such data updates the assumptions made in a Technical Report by Wardrop dated November, 2007 . The purpose of the model is to evaluate the effects of updated price assumptions and operational and cost factors on cash flow over a 20 year period and to calculate an internal rate of return (“IRR”) and a net present value (“NPV), enabling Geodex management to decide whether or not to proceed to pre-feasibility studies. The model takes no account of taxes or provincial royalties. The model is based on the following:•Currency is US$. Operating costs originating in CDN$ have been converted to US$ at an exchange rate of 1 CDN$ = 0.85 US$.•Tungsten is priced at an ammonium para tungstate (APT) price of US$ 220 per metric tonne unit (mtu) of WO 3 in concentrate which is about US$ 10.00 per lb. of WO3. A deduction of US$ 50.00 per mtu of WO3 (US$ 2.27/lb.) is made for offsite costs (freight, conversion by buyer to APT, sales etc.). The deduction is a weighted blend of US$ 40.00 for gravity concentrate (65% WO3 grade) and US$ 60.00 for flotation concentrate (50% WO3 grade).•Molybdenum is priced at US$ 15.00/lb. of Mo. Offsite costs (freight, conversion to MoO3 by buyer, sales etc.) are assessed at 8% of shipped gross value which amounts to US$ 1.20/lb. of Mo. •Mining rate is 20,000 tonnes/day, 350 days/year for 20 years as per the mining schedule tabled elsewhere in this report..•After crushing and sizing the ore passes through ore-sorters prior to further beneficiation, losing about 50% of its weight in the process.•Overall recoveries (mill feed to bagged concentrate) of 73.9% for tungsten and 70.4% for molybdenum – are based on a metallurgical balance provided by Bolu Consulting Engineering Inc. (“Bolu”). These recoveries the product of ore sorting (96%) and gravity plus flotation (77%) recoveries for tungsten and the product of ore sorting (83.8%) and flotation (84%) recoveries for molybdenum.•Mine operating costs have not been revisited and remain CDN$ 1.30/tonne (US$ 1.11) mined as per Wardrop 2007.•Overall beneficiation costs were provided by Bolu: CDN$ 4.66/tonne processed ( US$ 3.96).•General & administration costs were provided by Bolu: CDN$ 0.66/tonne processed (US$ 0.56).•Preproduction capital costs were provided by Axxent Engineering Limited (“Axxent”): US$ 341 million including a 30% contingency allowance. Owners costs include US$ I million for environmental costs during construction.

Page 42: Geodex Report March 1 2009

•Sustaining (and sinking fund provision for reclamation) capital was assessed at 2.5% of original direct capital, per production year (starting Year 2). More detailed estimates are unavailable at this time.•Working capital was assessed at 25% of Year 1 operating costs which is recovered in Year 20. More detailed estimates are unavailable at this time.•The development of the mine starts in Year minus 2 and IRR and NPV calculations start in this year. Pre-feasibility and feasibility costs are regarded as sunk costs for the purposes of this analysis and do not show in the model. These costs are incurred to determine whether a production commitment is justified and might be incurred without such a decision being made.The following table sets out the main elements of the financial model :

Units Yearly Average 20 Year Totals

Net Revenue: Tungsten $US x 1000 79,883 1,597,657

Net Revenue: Molybdenum $US x 1000 47,806 956,117

NET REVENUE: TOTAL $US x 1000 127,689 2,553,774

OPERATING CASH FLOW $US x 1000 80,523 1,610,464

TOTAL PRE PRODUCTION CAPITAL COSTS $US x 1000 -- 341,000

Sustaining Capital $US x 1000 4,513 90,250

NET CASH FLOW $US x 1000 58,961 1,179,214

-- --

Project Unleveraged IRR from Year -2 % 23% --

NPV @ 8% from Year -2 $US x 1000 $372,341 --

NPV @10% from year -2 $US x 1000 $277,102

Preproduction Capital Repaid During Year YEAR 4

Accompanying this section are:Summary Sheet : summarizes the main ingredients of the financial modelVariables: sets our all of the variables and constants used as input for the modelModel Page 1: spreadsheet showing cash flow and financial parameters (Years 1 to 10)Model Page 2: spreadsheet showing cash flow (Years 11 to 20)What-If Tables: 12 tables each examining the sensitivity of incremental changes from + 50% to – 50% in the base case of a major parameter : W price, W overall recovery, W sorter recovery, W grade, Mo Price, Mo overall recovery, Mo sorter recovery, Mo grade, pre production capital cost, operating costs, exchange rate on operating costs, stripping ratio.Charts: graphical representation of the What-If tables.

Page 43: Geodex Report March 1 2009
Page 44: Geodex Report March 1 2009
Page 45: Geodex Report March 1 2009
Page 46: Geodex Report March 1 2009
Page 47: Geodex Report March 1 2009
Page 48: Geodex Report March 1 2009

8. Recommendations to Pre-Feasibility

Contributor: Jack Marr M.Sc., P. GeoGeodex Minerals Ltd.,450 – 800 West Pender StreetVancouver, B.C. V6C 2V6

The spreadsheet in the last section is based largely on a series of new test results for Sisson Brook and a set of independent evaluations by independent engineers. These carry the project well beyond the 2007 scoping study. The analysis indicates an NPV (8% discount rate) for the Sisson Brook deposit of $US 372 million ($Can 438 million, using an 0.85 exchange rate)) and an IRR of 23 %. Payback period is estimated to be in the fourth year. This is sufficiently robust to recommend an immediate start to the Pre-Feasibility process. At this time, completion of Pre-Feasibility by the fourth quarter (Q4) of 2009 seems reasonable.

This baseline study has demonstrated project viability and strength but will mainly position the project for later work. Potential project improvements include reducing the contingency markup with additional metallurgical and pre-concentration testing, more detailed design and costing for the site and process plant equipment and more study of the waste/tailings option. We should develop stronger cash flows by increasing cutoff grades in the high margin early years to boost revenue. We should examine the use of stockpiles to modify production as prices change in relation to the world’s steel industry. Geotechnical engineering for pit slopes and foundations should continue and the environmental work should be re-instated. The company should move more strongly into the downstream marketing/ offtake agreement/end user area.

Optimal external expenditures to the Pre-Feasibility stage (Q4 2009) are estimated as below. These do not include Geodex corporate costs or contingency.

Page 49: Geodex Report March 1 2009

Contractor Work Budget $Can

PRE-FEAS REPORT

TBD Resource/Block Model/Grades 25,000

SGS/Terravision Metallurgy/Pre-Conc. 250,000TerrAtlantic Geotech/ Waste/Tailings 150,000

Rescan Environmental 225,000Axxent Engineering/Report 200,000Bolu Engineering Process/Capex/Opex 100,000TBD Marketing 50,000

TOTAL 1,000,000

OTHER

Geodex Field Costs 2009 Drilling/Sampling 200,000

This project has the benefit of good logistics and a very benign development environment in one of Canada’s poorer provinces. It also has considerable size and a right-at-surface open pit situation which is likely to give the project long life and carry it through several metal price cycles.

Page 50: Geodex Report March 1 2009

9.After Pre-feasibility – What happens next?

Contributor: Michael MacleodMichael E MacLeod Professional Consulting Services,#7, 15188 62A Avenue, Surrey, B.C., V3S 1W7

A successful Preliminary Feasibility Study of the Sisson Brook project lays the foundation for subsequent social, environmental/regulatory, and technical work required for receipt of all government approvals and making an Investment Grade Feasibility Study (IGFS). It also provides the basis for acquiring the funding for the project (or terminating work or selling the asset in the event of an unfavorable result); and generates financial market momentum for improving the Company’s share price.

Time frame and cost for an IGFS are frequently underestimated.Overall Time Frame : 3 to 5 yearsEstimated Total Cost : $ 15.0 to $ 20 millionA great deal of work is required in three main arenas: Environmental/Regulatory, Engineering, and Financing.

The Environmental/Regulatory arena •Systematic data collection and assessment. Baseline social and environmental sampling and monitoring.•Static and kinetic testing for acid rock drainage potential, geotechnical testing for slopes, water management and

foundations.•Preparation of documents containing the required information and presented in an acceptable format for distribution

and review.•Application Review by Provincial and Federal Agencies and General Public.•Stakeholder Consultation – Public and First Nations.•Application Approval by Provincial and Federal Governments.Permitting Time : 2 to 5 years (depending on the complexity and political sensitivity of the proposed development).Estimated Cost : $ 5.0 million

The Engineering arena •Confirm the viability of the extraction process from bench to commercial size scale-up. Pilot plant test most likely.•Waste/tailings management plan.

Page 51: Geodex Report March 1 2009

•Facilities and infrastructure design. Examine in detail equipment specs and sizes and optimize to metallurgy. Produce reliable capital and operating costs.

•Product quality, marketing and project development plans.•Financial risk/reward model to support the IGFS.

Engineering Time : 1 to 3 years. (depending on sponsor’s schedule, funding and contractor availability.)

Estimated Cost : $ 6.0 million

The Financing arena : -to acquire interim program funding, and secure full project development funding, subject to a favorable IGFS and receipt of government approvals.

•Securing a Financial Advisor;•Risk/Reward Trade-Offs and Strategies;•Retail Investor and Current Stockholder Management;•Share Dilution Aspects;•Institutional Investor Acquisition and Management;•End User/Strategic Partnering or Joint Venturing Strategies;•Potential for Government Participation and/or Support;•Debt/Equity Mix. Sources to coincide with Environmental/Regulatory Approvals and IGFS report delivery.•Financing Terms; and•Investor Friendly Financial Model;

Funding Time : 1 to 3 years (depending upon management credibility, individual investor appetite, global economic conditions, political sensitivity, and competing opportunities).

Estimated Cost : $ 4.0 million (including corporate overhead).

Total Estimated Cost : $ 15.0 million

Contingency $ 3.0 millionTOTAL $ 18.0 million