Top Banner

of 101

Geo5 Engineering Manuals

Apr 03, 2018

Download

Documents

Franklyn Merino
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/28/2019 Geo5 Engineering Manuals

    1/101

  • 7/28/2019 Geo5 Engineering Manuals

    2/101

    Engineering manuals for GEO5 programs

    Chapter 1. Analysis settings and settings administrator 2

    Chapter 2. Design of Cantilever wall 11

    Chapter 3. Verification of gravity wall 22

    Chapter 4. Design of non-anchored restraint retaining wall 30

    Chapter 5. Design of anchored retaining wall 39

    Chapter 6. Verification of retaining wall with one anchor row 44

    Chapter 7. Verification of multi-anchored wall 53

    Chapter 8. Analysis of slope stability 64

    Chapter 9. Stability of slope with retaining wall 73

    Chapter 10. Design of geometry of spread footing 82

    Chapter 11. Settlement of spread footing 87

    Chapter 12. Analysis of consolidation under embankment 92

  • 7/28/2019 Geo5 Engineering Manuals

    3/101

    2

    Introduction

    Engineering manuals are new teaching material for GEO5 software. They were developed as a reaction

    to hotline and frequently asked questions of users. The objective of each chapter is to explain how to solve the

    concrete engineering problems using GEO5 software.

    Each chapter is divided to a few sections:

    Introductiontheoretical introduction to the problem

    Assignmenthere the problem is described with all input data needed for solving the problem in selected the

    program

    Solutionin this section, the problem is solved step by step

    Conclusion has the conclusion of the problem and the final verification of the construction. It tells if the

    structure is satisfactory or not and if there are any modifications needed.

    In each chapter there are also notes, which explain the problem in general as well as links to other materials.

    The basic educational materials of GEO5 software suite (from FINE s r.o.) are:

    Context helpexplains the functions of the program in detail Video tutorialsshow the basic work with the software and its effective use Engineering manualsexplain how concrete engineering problems are solved Verification manualsverify the satisfaction of the results, by comparing the results from programs

    with hand calculation or other programs

    The first chapter explains how to set standards and chose an analysis method, which is the same for all GEO5

    programs. In further chapters one standard is selected, by which the construction is verified.

  • 7/28/2019 Geo5 Engineering Manuals

    4/101

    3

    Chapter 1. Analysis settings and settings administrator

    This chapter explains the correct use of Settings administrator that serves to choose standards, partial

    factors and verification methodology. It is the basic step needed for all GEO5 programs.

    Introduction

    GEO5 software is used in 90 countries worldwide. Engineering tasks are the same everywhere to

    prove that the construction is safe and well designed.

    The basic characteristic of structures (eg. geometry of wall, terrain, localization of anchors etc.) are the

    same all over the world; the way of proving that the construction is safe and the theory of analysis used are

    different. Large quantities of new theories and mainly partial factors of analysis lead to input of large amounts

    of data and complicated programs. The Settings administrator was created in GEO5 for version 15 to simplify

    this process.

    In the Settings administrator are defined all input parameters, including standards, methods and

    coefficients for the current country. The idea is that each user will understand the Settings defined in the

    program (or will define a new Setting of analysis), which the user then uses in their work. To the Settings

    administrator and Settings editor the user then goes only occasionally.

    Assignment:

    Perform an analysis of a gravity wall per the picture below for overturning and slip according to these

    standards and procedures:

    1) CSN 73 00372) EN 1997DA13) EN 1997DA24) EN 1997DA35) Safety factor on SF=1.6

  • 7/28/2019 Geo5 Engineering Manuals

    5/101

    4

    Scheme of the gravity wall for analysis

    Solution

    Firstly, input the data about the construction and geological conditions in the frames: Geometry,

    Assign and Soils. Skip the other frames because they are not important for this example.

    Frame Geometry input of dimensions of the gravity wal

  • 7/28/2019 Geo5 Engineering Manuals

    6/101

    5

    Table with the soil parameters

    Soil

    (Soil classification)

    Unit weight

    3mkN

    Angle of

    internal friction

    ef

    Cohesion

    of soil

    kPacef

    Angle of friction

    structure soil

    MG Gravelly silt,

    firm consistency19,0 30,0 0 15,0

    In the frame Assign, the first soil will be assigned automatically to the layer or layers. This can be

    changed when necessary.

    When the basic input of construction is done, we can choose standards, and then finally run the analysis

    of the gravity wall.

    In the frame Settings click the button Select and choose number 8 Czech Republic old

    standards CSN (73 1001, 73 1002, 73 0037).

    Dialog window Settings list

    Note: The look of this window depends on standards that are currently active in the Settings administrator

    more information in the help of the program (press F1). If the setting you want to use isn`t on the list in the

    dialog window Settings list, you can activate it in the Settings administrator.

    Now, open up the frame Verification and after analyzing the example record the utilization of

    construction (in the frame Verification) - 53,1% resp. 66,5%.

  • 7/28/2019 Geo5 Engineering Manuals

    7/101

    6

    Frame Verification results of the analysis using CSN 73 0037 standard

    Then return to the frame Settings and choose number 3 Standard EN 1997DA1.

    Dialog window Settings list

  • 7/28/2019 Geo5 Engineering Manuals

    8/101

    7

    Again, open the frame Verification and record the result (55,6% and 74,7%) for EN 1997, DA1.

    Frame Verification results of analysis for EN 1997, DA1

    Repeat this procedure for settings number 4 Standard EN 1997DA2 and number 5Standard

    EN 1997DA3.

    The analyzed utilization of constructions is (77,8% and 69,7%) for EN 1997, DA2 or (53,5% and

    74,7%) for EN 1997, DA3.

  • 7/28/2019 Geo5 Engineering Manuals

    9/101

    8

    Variant 5 (analysis using Safety factors) is not as simple. In the frame Settings click on Edit. This

    will show you the current analysis settings. Change the verification methodology to Safety factors (ASD) and

    then input safety factor for overturning and sliding resistance as 1.6.

    Dialog window Edit current settings: Gravity wall

    Press OK and run the analysis. (69,0% and 77,1%).

    Frame Verification analysis results for SF = 1.6

  • 7/28/2019 Geo5 Engineering Manuals

    10/101

    9

    If you would like to use this setting more often, it is good to save this setting by clicking on Add to

    administrator, rename is as shown below, and next time use it as a standard setting.

    Dialog window Add current settings to the Administrator

    Dialog window Settings list then looks like this

    Dialog window Settings list

  • 7/28/2019 Geo5 Engineering Manuals

    11/101

    10

    Verification

    Utilization in percentage using each standard is:

    Overturning Slip

    1) CSN 73 0037 53,1 66,52) EN 1997DA1 55,6 74,73) EN 1997DA2 77,8 69,74) EN 1997DA3 53,3 74,75) Safety factor on SF=1.6 69,0 77,1

    The analysis is satisfactory using the selected analysis standards.

    Note: This simple method can be used to compare retaining structures or stability analyses. When analyzing

    foundations, the load (basic input data) must be computed according to relevant standards. That is the reason

    why it doesnt make sense, to compare foundation design by various standards with the same values of load

    (nominal values).

  • 7/28/2019 Geo5 Engineering Manuals

    12/101

    11

    Chapter 2. Design of Cantilever wall

    In this chapter, the design of cantilever wall and its overall analysis is described.

    Assignment

    Design a cantilever wall with a height of 4,0 m and analyze it by EN 1997-1 (EC 7-1, Design approach

    1). The terrain behind the structure is horizontal. The ground water table is 2,0 meters deep. Behind the wall acts

    a strip surcharge with a length of 5,0 meters and with a magnitude of 10 kN/m2. The foundation soil consists of

    MSSandy silt, stiff consistency, 8,0rS , allowable bearing capacity is 175kPa. The soil behind the wall will

    consist of S-F Sand with trace of fines, medium dense soil. The cantilever wall will be made of reinforced

    concrete of class C 20/25.

    Scheme of the cantilever wall - Assignment

    Solution:

    For solving this problem, we will use the GEO5 program, Cantilever wall. In this text, we will explain

    solving this example step by step.

    In the frame Settings click on Select and then choose analysis setting Nr. 3 Standard EN 1997

    DA1.

  • 7/28/2019 Geo5 Engineering Manuals

    13/101

    12

    Dialog window Settings list

    In the frame Geometry choose the wall shape and enter its dimensions.

    Frame Geometry

  • 7/28/2019 Geo5 Engineering Manuals

    14/101

    13

    In the frame Material enter the material of the wall.

    Frame Material Input of material characteristics of the structure

    Then, define the parameters of soil by clicking Add in the frame Soils. Wall stem is normally

    analyzed for pressure at rest. For pressure at rest analysis, select Cohesionless.

    Dialog window Add new soils

  • 7/28/2019 Geo5 Engineering Manuals

    15/101

    14

    Note: The magnitude of active pressure depends also on the friction between the structure and soil. The friction

    angle depends on the material of construction and the angle of internal soil friction normally entered in the

    interval ef 3231

    Table with the soil parameters

    Soil

    (Soil classification)

    Profile

    m

    Unit weight

    3mkN

    Angle of

    internal

    friction

    ef

    Cohesion

    of soil

    kPacef

    Angle of

    friction

    structuresoil

    S-FSand with trace of

    fines, medium dense soil0,04,0 17,5 28,0 0,0 18,5

    MSSandy silt, stiff

    consistency, 8,0rS from 4,0 18,0 26,5 30,0 17,5

    In the frame Terrain choose the horizontal terrain shape.

    Frame Terrain

    The ground water table is at a depth of 2,0 meters. In the frame Water select the type of water close to

    the structure and its parameters.

  • 7/28/2019 Geo5 Engineering Manuals

    16/101

    15

    Frame Water

    In the next frame define Surcharge. Here, select permanent and strip surcharge on the terrain acting as

    a dead load.

    Dialog window New surcharge

    In the frame FF resistance select the terrain shape in front of the wall and then define other parameters

    of resistance on the front face.

  • 7/28/2019 Geo5 Engineering Manuals

    17/101

    16

    Frame FF resistance

    Note: In this case, we do not consider the resistance on the front face, so the results will be conservative. The

    FF resistance depends on the quality of soil and allowable displacement of the structure. We can consider

    pressure at rest for the original soil, or well compacted soil. It is possible to consider the passive pressure if

    displacement of structure is allowed. (For more information, see HELPF1)

    Then, in the frame Stage settings choose the type of design situation. In this case, it will be

    permanent. Also choose the pressure acting on the wall. In our case, we will choose active pressure, as the wall

    can move.

    Frame Stage settings

    Now, open up the frame Verification, where you analyze the results of overturning and slip of the

    cantilever wall.

  • 7/28/2019 Geo5 Engineering Manuals

    18/101

    17

    Frame Verification

    Note: The button In detail in the right section of the screen opens a dialog window with detailed information

    about the analysis results.

    Analysis results:

    The verification of slip is not satisfactory, utilization of structure is

    Overturning: 52,8 % 97,10933,208 klvzd MM [kNm/m] SATISFACTORY. Slip: 124,6 % 94,8178,65 posvzd HH [kN/m] NOT OK.

    Now we have several possibilities how to improve the design. For example, we can:

    - Use better soil behind the wall- Anchor the base- Increase the friction by bowing the footing bottom- Anchor the stem

    These changes would be economically and technologically complicated, so choose the easiest alternative. The

    most efficient way is to change the shape of the wall and introduce a wall jump.

    Change of the design: change of the geometry of the wall

    Return to the frame Geometry and change the shape of the cantilever wall. For increasing the

    resistance against slip we introduce a base jump.

  • 7/28/2019 Geo5 Engineering Manuals

    19/101

    18

    Frame Geometry (Changing dimensions of cantilever wall)

    Note: A base jump is usually analyzed as an inclined footing bottom. If the influence of the base jump

    is considered as front face resistance, then the program analyses it with a straight footing bottom, but FF

    resistance of the construction is analyzed to the depth of the down part of the base jump (More info in HELPF1)

    Thenanalyze the newly designed construction for overturning and slip.

    Frame Verification

  • 7/28/2019 Geo5 Engineering Manuals

    20/101

    19

    Now, the overturning and slip of the wall are both satisfactory.

    Then, in the frame Bearing capacity, perform an analysis for design bearing capacity

    of the foundation soil 175kPa.

    Frame Bearing capacity

    Note: In this case, we analyze the bearing capacity of the foundation soil on an input value, which we can get

    from geological survey, resp. from some standards. These values are normally highly conservative, so it is

    generally better to analyze the bearing capacity of the foundation soil in the program Spread footing that takes

    into account other influences like inclination of load, depth of foundation etc.

    Next, in the frame Dimensioning chose wall stem check. Design the main reinforcement into the stem

    6pcs. 12 mm, which satisfies in point of bearing capacity and all design principles.

  • 7/28/2019 Geo5 Engineering Manuals

    21/101

    20

    Frame Dimensioning

    Then, open up the frame Stability and analyze the overall stability of the wall. In our case, we will use

    the method Bishop, which result in conservative results. Perform the analysis with optimization of circular

    slip surface and then leave the program by clicking OK. Results or pictures will be shown in the report of

    analysis in the program Cantilever wall.

    Slope stability program

    Conclusion/ Result of analysisbearing capacity:

    Overturning: 49,5 % 16,10852,218 klvzd MM [kNm/m] SATISFACTORY

  • 7/28/2019 Geo5 Engineering Manuals

    22/101

    21

    Slip: 64,9 % 47,6427,99 posvzd HH [kN/m] SATISFACTORY Bearing capacity: 86,3 00,17506,151 dR [kPa] SATISFACTORY Wall stem check: 81,5 % 88,8413,104 EdRd MM [kNm] SATISFACTORY Overall stability: 40,8 % MethodBishop (optimization) SATISFACTORY

    This cantilever wall is SATISFACTORY.

  • 7/28/2019 Geo5 Engineering Manuals

    23/101

    22

    Chapter 3. Verification of gravity wall

    In this chapter an analysis of an existing gravity wall for permanent and accidental design situations is

    performed. Construction stages are also explained.

    Assignment

    Using EN 1997-1 (EC 7-1, DA2) standard, analyze an existing gravity wall for stability, overturning, and slip .

    Road traffic acts on the wall with magnitude of 10 kPa. Check the possibility to install the barrier on the top of

    the wall. An accidental load from a car crash is considered as 50 kN/m and it acts horizontally at 1,0 m.

    Dimensions and shape of the concrete wall can be seen in the picture below. Inclination of the terrain behind the

    construction is 10 , the foundation soil consists of silty sand. The friction angle between the soil and wall

    is 18 .

    Determination of bearing capacity and dimensioning of the wall is not part of this task. In this analysis, consider

    effective parameters of soil.

    Scheme of the gravity wallassignment

    Solution:

    For analyzing this task, use the GEO5 programGravity wall. In this text, we will describe the steps of

    analyzing this example in two construction stages.

    1st construction stageanalyzing the existing wall for road traffic. 2nd construction stageanalyzing impact of vehicle to the barrier on the top of the wall.

    Basic input: Stage 1

  • 7/28/2019 Geo5 Engineering Manuals

    24/101

    23

    In the frame Settings click on Select and choose Nr. 4 Standard EN 1997DA2.

    Dialog window Settings list

    Then, in the frame Geometry, select the shape of the gravity wall and define its parameters.

    Frame Geometry

  • 7/28/2019 Geo5 Engineering Manuals

    25/101

    24

    In the next step, input the material of the wall and geological profile. Unit weight of wall is

    324 mkN . Wall is made from concrete C 12/15 and steel B500. Then define parameters of soil and assign

    them to the profile.

    Table with the soil parameters

    Soil

    (Soil classification)

    Unit weight

    3mkN

    Angle of

    internal friction

    ef

    Cohesion

    of soil

    kPacef

    Angle of friction

    structuresoil

    MSSandy silt,firm consistency

    18,0 26,5 12,0 18,0

    Dialog window Add new soils

    Note: The magnitude of active pressure depends also on friction between the structure and soil in the angle

    ef 32

    31 . In this case we consider the influence of friction between the structure and soil with

    value of ef32 (d =18), when analyzing earth pressure. (More info in HELPF1).

    In the frame Terrain select the shape of terrain behind the wall. Define its parameters, in terms of

    embankment length and slope angle as shown below.

    Frame Terrain

    In the next frame, define Surcharge. Input the surcharge from road traffic as Strip, with its location on

    terrain, and as a type of action select Variable.

  • 7/28/2019 Geo5 Engineering Manuals

    26/101

    25

    Dialog window Edit surcharge

    In the frame FF resistance choose the shape of the terrain in front of the wall and define the other

    parameters of front face resistance.

    Frame Front face resistance

    Note: In this case, we do not consider resistance on the front face, so the results will be conservative. The FF

    resistance depends on the quality of soil and allowable displacement of the structure. We consider pressure at

    rest for the original soil or well compacted soil. It is possible to consider passive pressure only if displacement

    of structure is allowed. (More info in HELPF1).

  • 7/28/2019 Geo5 Engineering Manuals

    27/101

    26

    In the frame Stage settings select the type of design situation. In the first construction stage,

    consider the permanent design situation.

    Frame Stage settings

    Now open up the frame Verification, where we analyse the gravity wall for overturning and slip.

    Frame Verification stage 1

    Note: The button In detail in the right section of the screen opens a dialog window with detailed information

    about the results of the analysis.

  • 7/28/2019 Geo5 Engineering Manuals

    28/101

    27

    Dialog window Verification (in detail)

    Note: For analyses based on EN-1997, the program determines if the force acts favorably or unfavorably. Next

    each force is multiplied by the corresponding partial factor which is them on the report.

    Then, open up the frame Stability and analyze the overall stability of the wall. In our case, we will use

    the method Bishop, which results in conservative results. Perform an analysis with optimization of circular

    slip surface and then validate everything by clicking OK. Results or pictures will be shown in the report of

    analysis in the program Gravity wall.

    Program Slope stability stage 1

    Analysis results: Stage 1When analyzing bearing capacity, we are looking for values of overturning and slip of the wall on the

    footing bottom. Then we need to know its overall stability. In our case, the utilization of the wall is:

    Overturning: 70,0 % 73,26391,376 klvzd

    MM [kNm/m] SATISFACTORY.

    Slip: 90,6 % 17,13853,152 po svzd HH [kN/m] SATISFACTORY.

    Overall stability: 72,3 % MethodBishop (optimization) SATISFACTORY.

  • 7/28/2019 Geo5 Engineering Manuals

    29/101

    28

    Basic input: Stage 2

    Now, add construction stage 2 using tool bar in the upper left corner of the screen.

    Toolbar Stage of construction

    In this stage, define the load from the impact of the vehicle to the barrier, using the frame

    Inputforces. The load is accidental and considers the impact of a vehicle with a weight of 5 tons.

    Dialog window Edit force construction stage 2 (accidental design situation)

    Then open the frame Stage settings change the design situation on accidental.

    Frame Stage settings

    The data in the other frames that we entered in stage 1 has not changed , so we dont have to open these

    frames again. Select the frame Verification to perform the verification on overturning and slip again.

  • 7/28/2019 Geo5 Engineering Manuals

    30/101

    29

    Frame Verification stage 2

    Analysis results: Stage 2From the results, we see, that the existing wall is not satisfactory for impact of a vehicle to the barrier.

    In this case, utilization of the wall is:

    Overturning: 116,3 % 13,56862,488 klvzd MM [kNm/m] NOT OK. Slip: 102,9 % 35,14239,138 po svzd HH [kN/m] NOT OK.

    Conclusion

    The existing gravity wall in case of bearing capacity satisfies only for the first construction stage, where

    road traffic acts. For the second construction stage, which is represented as impact to the barrier on the top of

    the wall by a vehicle of 5 tons, the wall is not satisfactory.

    As a solution to increase bearing capacity for overturning and slip it is possible to introduce soil

    anchors. alternatively it is possible to place a barrier on the edge of the road, so the wall is not loaded by a force

    from the crashing car.

  • 7/28/2019 Geo5 Engineering Manuals

    31/101

    30

    Chapter 4. Design of non-anchored restraint retaining wall

    In this chapter is the design of non-anchored retaining wall for permanent and accidental loads (flooding)

    Assignment

    Design non-anchored retaining wall from pile sheeting using the EN 1997-1 (EC 7-1, DA3) standard in

    non-homogenous geologic layers. The depth of excavation is 2,5 m. The ground water table is at a depth of 1,0

    m. Analyze the construction also for flooding; when the water is 1,0 m above the top of the wall (mobile anti-

    flood barriers should be installed.)

    Scheme of non-anchored wall from pile sheetingassignment

    Solution:

    For solving this problem, we will use the GEO5 program, Sheeting design. In this text, we will explain

    each step to solve this example:

    1st construction stage: permanent design situation 2nd construction stage: accidental design situation Design of geometry of the pile sheeting Analysis result (conclusion)

    Basic input: Construction stage 1

    In the frame Settings click on Select and then choose Nr. 5 Standard EN 1997DA3.

  • 7/28/2019 Geo5 Engineering Manuals

    32/101

    31

    Dialog window Settings list

    Then, input the geological profile, parameters of soil and assign them to the profile.

    Dialog window Add new soils

  • 7/28/2019 Geo5 Engineering Manuals

    33/101

    32

    Table with the soil parameters

    Soil

    (Soil classification)

    Profile

    m

    Unit weight

    3mkN

    Angle of

    internal

    friction

    ef

    Cohesion

    of soil

    kPacef

    Angle of friction

    structuresoil

    S-FSand with traceof fines, medium

    dense soil

    0,01,5 17,5 29,5 0,0 14,0

    SCClayey sand,medium dense soil

    1,52,5 18,5 27,0 8,0 14,0

    CL, CIClay withlow or medium

    plasticity,

    firm consistency

    from 2,5 21,0 19,0 12,0 14,0

    In the frame Geometry, select the shape of bottom of the excavation and input its depth.

    Frame Geometry

    Note: coefficient of reduction of earth pressure below the ditch is considered while analyzing braced sheeting

    (retaining wall with soldier beams) only; for a standard sheeting pile wall it equals 1,0 For more information,

    see HELP (F1).

    In this case, we do not use the frames Anchors, Props, Supports, Pressure determination,

    Surcharge and Applied forces. The frame Earthquake also has no influence for this analysis, because the

    construction is not located in seismic-active area. In the frame Terrain, it remains horizontal.

  • 7/28/2019 Geo5 Engineering Manuals

    34/101

    33

    In the frame Water input the GWT value 1,0 m.

    Frame Water 1stconstruction stage

    Then, in the frame Stage settings, select the design situation as permanent.

    Frame Stage settings

    Now, open up the frame Analysis and click on the button Analyze. This will perform the analysis ofthe retaining wall.

    Frame Analysis

  • 7/28/2019 Geo5 Engineering Manuals

    35/101

    34

    Note: For cohesive soils is recommended by many standards to use minimal dimensioning pressure acting on

    the retaining wall. The standard value for the coefficient of minimal dimensioning pressure is Ka = 0,2.

    It means that minimum pressure on the structure is 0,2 of geostatic stressnever less.

    Within the design of pile sheeting retaining wall, we are interested in the depth of construction in the

    soil and internal forces on the structure. For the 1st

    construction stage, the results of analysis are:

    Length of structure: m83,4 Needed depth in the soil: m33,2 Maximum bending moment: mkNmM 21,28max,1 Maximum shear force: mkNQ 98,56max,1

    In the next stage, we are going to show you how to analyse the minimum depth in soil and internal

    forces in the soil for the accidental design situationfloods.

    Basic inputConstruction stage 2

    Now, select stage 2 on the toolbar Stage of construction on the upper left corner of your screen. (If

    needed, add a new one)

    Toolbar: Stage of construction

  • 7/28/2019 Geo5 Engineering Manuals

    36/101

    35

    In the frame Water, change the GWT behind the structure to a value -1,0 m. We will not consider

    water in front of the structure.

    Then, in the frame Stage settings, select the design situation Accidental.

    Frame Stage settings

  • 7/28/2019 Geo5 Engineering Manuals

    37/101

    36

    All other values are the same as in the 1 st construction stage, so we dont have to change data in other

    frames, so we go on to the frame Analysis and click again on the button Analyze.

    Frame Analysis

    In the 2nd

    construction stage the analysis results are:

    Length of structure: m56,6 Needed depth in the soil: m06,4 Maximum bending moment: mkNmM 00,142max,2 Maximum shear force: mkNQ 17,185max,2 Using the maximum bending moment, we will design pile sheeting.

    The minimum length of pile sheeting is set as the maximum of necessary length from construction stage 1

    and construction stage 2 .

  • 7/28/2019 Geo5 Engineering Manuals

    38/101

    37

    Design of pile sheeting:

    We design the pile sheeting based on the maximum bending moment using the table of pile sheeting with

    allowable bearing capacities shown below.

    Task 'Fine - LATAM - Sending' reported error (0x80042109) : 'Outlook is unable to connect to your

    outgoing (SMTP) e-mail server. If you continue to receive this message, contact your server administrator

    or Internet service provider (ISP).'

    Design of pile sheeting using SN EN 10 248-1 standards.

    Based on the chart, we will select the pile sheeting VL 503 (500 340 9,7 mm), the steel grade S 270

    GP, of which the maximum bending moment is mkNM 0,224max

    .

    Safe designof structure is verified by equation:

    mkNmMmkNMdov 142224 max

    mkNmMmkNMdov142224

    max

    Analysis result:

    In the design of non-anchored restraint retaining wall, we are verifying values of minimum depth of the

    structure in the soil, and the internal forces in the structure:

    Minimum depth of the structure in first stage: 2,33 m Minimum depth of the structure in second stage: 4,06 m

    So, we will design a pile sheeting with depth in the soil of 4,1 m and overall length of 6,6 meters.

  • 7/28/2019 Geo5 Engineering Manuals

    39/101

    38

    Conclusion:

    The designed pile sheeting retaining wall VL 503 from S 270 steel with length of 6,6 meters satisfies.

  • 7/28/2019 Geo5 Engineering Manuals

    40/101

    39

    Chapter 5. Design of anchored retaining wall

    In this chapter, we will show you how to design a retaining wall with one row of anchors.

    Assignment:

    Design a retaining wall with one anchor row made from pile sheeting using EN 1997-1 (EC 7-1, DA3)standard. The depth of ditch is 5,0 m. The anchor row is 1,5 m below the surface. The soils, geological profile,

    ground water table and shape of terrain are the same as in the last task. Remove construction stage two so as

    to not consider flooding.

    Scheme of the anchored wall from pile sheetingassignment

    Solution:

    For solving this problem, we will use a GEO5 program, Sheeting design. In this text, we will explain

    each step of this example:

    Analysis 1: permanent design situation - wall fixed at heel Analysis 2: permanent design situation - wall hinged at heel Analysis result (conclusion)

  • 7/28/2019 Geo5 Engineering Manuals

    41/101

  • 7/28/2019 Geo5 Engineering Manuals

    42/101

    41

    In our case, we need to know the sheet pile embedment depth and also the anchor force. For the wall fixed at

    heel, the values are:

    Length of construction: m72,10 Depth in soil: m72,5 Anchor force: kN77,165 Maximum moment: mkNm /16,89 Maximum shear force: mkN/27,128

    Now, perform an analysis for wall hinged at heel (construction stage 2). Then, compare the results

    and, depending on comparison, design the embedment depth.

    Basic input: Analysis 2

    Now, add a new verification in the upper left corner of the frame.

    Select the option Wall hinged at heel and perform the analysis.

  • 7/28/2019 Geo5 Engineering Manuals

    43/101

    42

    Frame Analysis

    For the wall hinged at heel, the values are:

    Length of construction: m85,7 Depth in soil: m85,2 Anchor force: kN68,201 Maximum moment: mkNm/35,119 Maximum shear force: mkN/84,69

    The results of analysis

    The overall length of the structure should be in the interval of HfixedHhinged. For wall fixed at heel is

    the length of the structure is longer, but the anchor force is smaller. For wall hinged at heel, it is the opposite,

    so larger anchor force and shorter length of the construction. It is the users task to design the dimensions of

    the structure.

    Conclusion

    In our design, we will use pile sheeting VL 503 from steel S 270 with an overall length of 9,0 m,

    anchors with size of force 240 kN with anchor spacing of 2,5 m. In the next chapter, we will check this

    structure in the program Sheeting check.

  • 7/28/2019 Geo5 Engineering Manuals

    44/101

    43

    Note: The design cannot be taken as the final and it needs to be checked in the Sheeting check program,

    because on the real structure there is redistribution of earth pressure due to anchoring.

  • 7/28/2019 Geo5 Engineering Manuals

    45/101

    44

    Chapter 6. Verification of retaining wall with one anchor row

    In this chapter, we will show you how to verify a designed retaining wall with verification of inner stability of

    the anchors and overall stability of the structure.

    Assignment

    Verify the retaining wall that you designed in task 5.

    Solution:

    For solving this problem, we will use the GEO5 program, Sheeting check. In this text, we will explain

    each step to solve this task:

    Construction stage 1: excavation of ditch to a depth of 2,0 m + geometry of the wall Construction stage 2: anchoring of the wall + excavation of ditch to a depth of 5,0 m.

    Basic input: Construction stage 1

    To make our work easier, we can copy the data from the last task, when we designed the wall in the

    Sheeting design program by clicking in this program on Edit on the upper toolbar and selecting Copy

    data. In Sheeting check program click on Edit and then Paste data. Now we have most of the important

    data from the last task copied in to this program, so we dont have to input much of the needed data.

    Dialog window Insert data

  • 7/28/2019 Geo5 Engineering Manuals

    46/101

    45

    In the frame Settings, select again the number 5 Standard EN 1997, DA3. Select the analysis of

    depending pressures as Reduce according to analysis settings. Leave the coefficient for minimum

    dimensioning pressure as 0,20.

    Frame Settings (Analysis of pressures)

    Note: the selection Analysis of depending pressures do not reduce allows the analysis of limit pressures

    (active and passive) without the reduction of input parameters by partial factors. This is better for estimation of

    real behavior of construction. On the other hand, it does not follow EN 1997-1 Standard. (More info in HELP

    F1)

    Then, open up the frame Modulus hk , and choose the selection analyze Schmitt. This method

    for the determination of modulus of subsoil reaction depends on the oedometric modulus and stiffness of the

    structure. (More info in HELP F1)

    Frame Modulus hk

    Note: the modulus of subsoil reaction is an important input when analyzing a structure by the method of

    dependent pressures (elastic-plastic nonlinear model). The modulus hk affects the deformation, which is

    needed to reach active or passive pressures. (More info in HELP F1)

    In the frame Soilsenter the following values for each soil type. Poissons ratio and the oedemetric modulus

    were not entered in the previous program, so they must be entered here.

  • 7/28/2019 Geo5 Engineering Manuals

    47/101

    46

    Soil Type

    (Soil classification)

    Poissons ratio

    Oedometric Modulus

    MPaEoed

    SF - Sand with trace of fines,

    medium dense0,30 21,0

    SC - Clayey sand, medium dense 0,35 12,5

    CL - Clay with low or medium

    plasticity, firm consistency0,40 9,5

    In the frame Geometry define the parameters ofthe sheet pile type of wall, section length,

    coefficient of pressure reduction below ditch bottom, geometry and material of the construction. From the

    sheet pile database, select the VL 503 (500 340 9,7 mm).

    Dialog window Edit section

  • 7/28/2019 Geo5 Engineering Manuals

    48/101

    47

    Now, in the frame Excavation define the first ditch depth 2,50 m for the first construction stage.

    Frame Excavation

    Now, go to frame Analysis. In the left part of the frame, you can see the modulus of subsoil reaction,

    in the right section earth pressures and displacement. (For more information, see HELP F1)

    Frame Analysis

  • 7/28/2019 Geo5 Engineering Manuals

    49/101

    48

    Basic input: Construction stage 2

    Add another construction stage as indicated below. Here we define the anchoring of the wall and

    overall excavation. We cannot change the frames Settings, Profile, Modulus Kh, Soils and Geometry,

    because these data are the same for all construction stages. We will only change data in the frames

    Excavation and Anchors.

    In the frame Excavation, change the depth of the ditch to the final depth 5,0 m.

    Frame Excavation

    Then, go to the frame Anchors and click on the button Add. For this structure, we will add a row of

    anchors to a depth 1,5 m below the top of the wall (below the surface). Also define other important

    parameters: overall length of the Anchor input as 10 m, slope angle as 15 and anchor spacing as 2,5 m. Enter

    a prestress force equal to 240 kN and the diameter of the anchor.

    Frame Anchors

  • 7/28/2019 Geo5 Engineering Manuals

    50/101

    49

    Note: The stiffness of the anchors is taken into account in next stages of construction. Due to the deformation

    of construction the forces in anchors are changing. (More info in HELP F1).

    We dont change any other input data. Now, perform the analysis to view the maximums of internal

    forces and maximum displacement of the anchored structure.

    Frame Analysis

    Frame Analysis (Internal forces)

  • 7/28/2019 Geo5 Engineering Manuals

    51/101

    50

    Frame Analysis construction stage 2 (Deformation and pressure on the structure)

    Verification of material and cross section:

    Maximum moment behind the construction is 116,03 kN/m

    Sheet pile VL 503 (500 340 9,7 mm), quality of steel S 270 GP satisfies.

    (Allowable moment = mkNmMmkNMu 0,1160,224 max )

    Maximum displacement of structure 30,1 mm is also satisfactory.

  • 7/28/2019 Geo5 Engineering Manuals

    52/101

    51

    Verification of anchor stability

    Now, open the frame Inter. stability. You can see, that the internal stability of anchors is not satisfactory. This

    means, that the anchor could tear from the soil.

    .

    Frame Internal stability not satisfactory result

    The reason for this is that the anchor is too short, so in the frame Anchors, change its length to 12

    meters. This newly designed anchor then satisfies the internal stability requirements.

    Frame Internal stability satisfactory result

  • 7/28/2019 Geo5 Engineering Manuals

    53/101

    52

    The last needed check is overall stability of the structure. Click on the button External stability. This

    will open the Slope stability program. In the frame Analysis click on Analyze. We can now see, that the

    slope stability is acceptable.

    Frame External stability

    Analysis results - conclusion:

    Analysis done:

    Bearing capacity of cross section:51.8 % mkNmMmkNMu 0,1160,224 max SATISFACTORY.

    Internal stability: 87,5 % kNFkNFvzd 2404,274 SATISFACTORY. Overall stability: 84.8 % MethodBishop (optimization) SATISFACTORY.

    In this case, the designed construction satisfies in all checked parameters.

  • 7/28/2019 Geo5 Engineering Manuals

    54/101

    53

    Chapter 7. Verification of multi-anchored wall

    In this chapter, we are showing how to design and verify a multi-anchored wall.

    Assignment

    Verify a multi-anchored wall made from steel soldier piles I 400 with a length of 21,0 m. Depth

    of the ditch is 15,0 m. The terrain is horizontal. The surcharge acts at the surface and is permanent with

    size of2

    0,25 mkN . The GWT behind the construction is 10,0 m below the surface.

    Scheme of the wall anchored in multiple layers

    Table with the soil and rock parameters

    Soil, rock

    (classification)

    Profile

    m

    Unit

    Weight3mkN

    Angle of

    internal

    friction

    ef

    Cohesion

    of soil

    kPacef

    Deformation

    modulus

    MPaEdef

    PoissonsRatio

    CL, CIClaywith low or

    medium

    plasticity,

    firm consistency

    0,02,0 19,5 20 16 6,0 0,4

    CSSandyclay,

    firm consistency

    2,04,5 19,5 22 14 7,0 0,35

    R4 (good rock),

    low strength4,512,0 21 27,5 30 40,0 0,3

    R3 (good rock),

    medium

    12,016,6 22 40 100 50,0 0,25

  • 7/28/2019 Geo5 Engineering Manuals

    55/101

    54

    strength

    R5 (poor rock),

    very low

    strength

    16,617,4

    19 24 20 40,0 0,3

    R5 (poor rock),

    very low

    strength

    17,425,0

    21 30 35 55,0 0,25

    R5 (poor rock),

    very low

    strength

    from 25,0 21 40 100 400,0 0,2

    Angle of friction between structure and soil is 5,7 for all layers. Also, the Saturated Unit

    weight equals the Unit Weight above.

    Note that the Modulus of deformation is being used for soil materials.

    Table with position and geometry of the anchors

    Anchor

    no.

    Depth

    mz Length

    ml Root

    mlk Slope

    Spacing

    mb Anchor force

    kNF

    1 2,5 19,0 0,01 15,0 4,0 300,0

    2 5,5 16,5 0,01 17,5 4,0 350,0

    3 8,5 13,0 0,01 20,0 4,0 400,0

    4 11,0 10,0 0,01 22,5 4,0 400,0

    5 13,0 8,0 0,01 25,0 4,0 400,0

    All anchors have a diameter mmd 0,32 , modulus of elasticity GPaE 0,210 . Anchor

    spacing is mb 0,4 .

    Solution

    For solving this task, use the GEO5 programSheeting Check. The analysis will be performed

    in the classical way without reduction of input data so the real behavior of the structure will be

    grasped. Internal stability of the anchor system and overall stability will be checked with a safety

    factor of 1,5. This solution assumes you have entered the soil types and profiles, and permanent load

    as listed above.

    In the frame Settings select option nr. 1 Standardsafety factors.

    Then, go to frame Geometry and input the basic dimensions of the section, and also the coefficient

    of pressure reduction below the ditch bottom, which is in this case 0,4.

  • 7/28/2019 Geo5 Engineering Manuals

    56/101

    55

    Dialog window New section

    Note. The coefficient of reduction of earth pressures below the excavation reduces the pressures in the

    soil. For classical retaining walls this is equal 1,0. For braced sheeting it is less than or equal to one.

    It depends on size and spacing of braces (More info in help - F1).

    Now, we will describe the building of the wall stage by stage. It is necessary to model the task

    in stages, to reflect how it will be constructed in reality. In each stage it is necessary to look at values

    of internal forces and deformation. If the sheeting is not stable in some stage of construction or if the

    analyzed deformation is too large, then we need to change structurefor example to make the wall

    embedment longer, make the ditch shallower, increase the anchor forces etc.

    In construction stage 1, the ditch is made to depth of 3,0 m. In the stage 2, anchor is placed at a

    depth of 2,5 m. The GWT behind the structure is at a depth of 10,0 m beneath the surface.

  • 7/28/2019 Geo5 Engineering Manuals

    57/101

    56

    Frame Anchors Construction stage 2

    In the 3rd construction stage, the ditch is excavated to a depth of 6,5 m. In the 4th stage, anchor

    is placed at a depth of 5,5 m. The GWT is not changed so far.

    Frame Anchors Construction stage 4

    In the 5th construction stage, the ditch is excavated to a depth of 9,0 m. In the 6th stage, anchor

    is placed at the depth of 8,5 m. The depth of GWT is not changed.

  • 7/28/2019 Geo5 Engineering Manuals

    58/101

    57

    Frame Anchors Construction stage 6

    In 7th construction stage, the ditch is excavated to a depth of 11,5 m. In 8th construction stage,

    an anchor is placed at the depth of 11,0 m. The GWT in front of the wall is now at a depth of 12,0 m

    below the surface. The GWT behind the structure is not changed.

    Frame Anchors Construction stage 8

  • 7/28/2019 Geo5 Engineering Manuals

    59/101

    58

    In the 9th construction stage, the ditch is excavated to a depth of 13,5 m. In the 10th stage, an

    anchor is placed at the depth of 13 m. The GWT in front of the structure is 15,5 m below the surface.

    Frame Anchors Construction stage 10

    In the 11th, and last, construction stage, the ditch is excavated to a depth of 15,0 m. We will not add

    new anchors. The GWT in front of the wall is at a depth of 15,5 m. Behind the wall it is at a depth of

    10,0 m.

    Frame Anchors Construction stage 11

    Note: Due to deformation of the structure the forces in anchors are changing. These changes depend

    on the stiffness of the anchors and the deformation of the anchors head. The force can decrease (due

  • 7/28/2019 Geo5 Engineering Manuals

    60/101

    59

    to loss of prestress force) or increase. The forces can be prestressed in any stage of construction again

    to the required force.

    Results of analysis

    On the pictures below are the analysis results of the last, 11th construction stage.

    Frame Analysis (Kh + pressures)

    Frame Analysis (Internal forces)

  • 7/28/2019 Geo5 Engineering Manuals

    61/101

    60

    Frame Analysis (Deformation + stresses)

    All the stages are satisfactorily analyzedthat means that the structure is stable and functional in all

    stages of the construction. The deformation must also be checked that it is not too large, as well as that

    the anchor force does not exceed the bearing capacity of the anchor (The user must check this as this is

    not checked by the program Sheeting check).

    Maximum displacement of the wall is 28,8 mm, which is satisfactory.Note: If the program does not find a solution in some of the construction stages, then the data must be

    revisede.g. to make the structure longer, make the forces in anchors larger, change the number or

    position of anchors, etc.

  • 7/28/2019 Geo5 Engineering Manuals

    62/101

    61

    Verification of cross-section of the structure

    Open the frame Envelopes in the 1st construction stage, where you see the maximum and

    minimum values of variables.

    Maximum shear force: mkN24,237

    Maximum bending moment: mkNm80,220

    Frame Envelopes

    The bending moment is calculated per one meter (foot) of structure, so we have to calculate the

    moment acting on the soldier beam. The spacing of soldier beams in our example is 2,0 m, so the

    resulting moment is 220,80 * 2,0 = 441,6 KNm.

    Users can perform the verification of cross-section I 400 manually or using another program such as

    FIN ECSTEEL.

  • 7/28/2019 Geo5 Engineering Manuals

    63/101

    62

    Verificationcross-sections I 400output from FIN EC STEEL program

    Overall utilization of cross-section: %8,72 Verification of bearing capacity: kNmMkNmM Ry 6,441582,606 max,

    This designed cross-section satisfies analysis criteria.

    Note: Dimensioning and verification of concrete and steel walls is not part of the program Sheeting

    Check, but is planned for a future version.

    Analysis of internal stability

    Go to the frame Internal stability in the last construction stage and look at maximum allowable force

    in each anchor and the specified safety factor. The minimum safety factor is 1.5.

    Frame Internal stability

    Note : The verification is done this way. At first we iterate the force in the anchor, resulting in an

    equilibrium of all forces acting on the earth wedge. This earth wedge is bordered by construction,

    terrain, the middle of the roots of anchors and the theoretical heel of structure. If an anchor is not

    satisfactory the best way to resolve the issue is to make it longer or decrease the prestressed force.

  • 7/28/2019 Geo5 Engineering Manuals

    64/101

    63

    Verification of external stability

    The last required analysis is external stability. The button will automatically open the

    program Slope stability, where youperform overall stability analysis.

    Program Slope stability

    Conclusion

    The structure was successfully designed with a maximum deformation of 28,8 mm. This is

    satisfactory for this type of construction. Additionally, the limits of forces in anchors were not

    exceeded.

    Verification of bearing capacity of cross-section - SATISFACTORY Internal stabilitySATISFACTORY

    Anchor nr. 4 (analyzed safety factor): 50,1>34,5 amin SFSF .

    External stabilitySATISFACORYSafety factors (Bishopoptimization): 50,1>92,2 sSFSF

    The designed sheeting satisfies evaluation criteria

  • 7/28/2019 Geo5 Engineering Manuals

    65/101

    64

    Chapter 8. Analysis of slope stability

    In this chapter, we are going to show you how to verify the slope stability for critical circular

    and polygonal slip surfaces (using its optimization), and the differences between methods of analysis

    of slope stability.

    Assignment

    Perform a slope stability analysis for a designed slope with a gravity wall. This is a permanent

    design situation. The required safety factor is SF = 1,50. There is no water in the slope.

    Scheme of the assignment

    Solution

    For solving this problem, we will use the GEO5 program, Slope stability. In this text, we will

    explain each step to solve this problem:

    Analysis nr. 1: optimization of circular slip surface (Bishop) Analysis nr. 2: verification of slope stability for all methods Analysis nr. 3: optimization of polygonal slip surface (Spencer) Analysis result (conclusion)

  • 7/28/2019 Geo5 Engineering Manuals

    66/101

    65

    Basic inputAnalysis 1:

    In the frame Settings click on Select and choose option nr. 1 Standard safety factors.

    Dialog window Settings list

    Then model the interface layers, resp. terrain using these coordinates:

    Adding interface points

    Firstly, in the frame Interface input the coordinate range of the assignment. Depth of deepest

    interface point is only for visualization of the exampleit has no influence on the analysis.

  • 7/28/2019 Geo5 Engineering Manuals

    67/101

    66

    Then, input the geological profile, define the parameters of soil, and assign them to the profile.

    Dialog window Add new soils

    Note: In this analysis, we are verifying the long-term slope stability. Therefore we are solving this task

    with effective parameters of slip strength of soils (efef c, ). Foliation of soilsworse or different

    parameters of soil in one direction - are not considered in the assigned soils.

  • 7/28/2019 Geo5 Engineering Manuals

    68/101

    67

    Table with the soil parameters

    Soil

    (Soil classification)

    Unit weight3mkN

    Angle of internal

    friction ef Cohesion of soil

    kPacef Assigned Soil

    Region

    MGGravelly silt,firm consistency

    19,0 29,0 8,01

    S-FSand with traceof fines, dense soil

    17,5 31,5 0,03

    MSSandy silt, stiffconsistency, 8,0rS

    18,0 26,5 16,04

    Model the gravity wall as a Rigid Body with a unit weight of30,23 mkN . The slip surface

    does not pass through this object because it is an area with large strength. (More info in HELP F1)

    In the next step, define a surcharge, which we consider as permanent and strip with its location

    on the terrain surface.

    Dialog window New surcharges

    Note: A surcharge is entered on 1 m of width of the slope. The only exception is concentrated

    surcharge, where the program calculates the effect of the load to the analyzed profile. For more

    information, see HELP (F1).

  • 7/28/2019 Geo5 Engineering Manuals

    69/101

    68

    Skip the frames Embankment, Earth cut, Anchors, Reinforcements and Water. The

    frame Earthquake has no influence on this analysis, because the slope is not located in seismically

    active area.

    Then, in the frame Stage settings, select the design situation. In this case, we consider it as

    Permanent design situation.

    Frame Stage settings

    Analysis 1circular slip surface

    Now open up the frame Analysis, where the user enters the initial slip surface using

    coordinates of the center( x, y ) and its radius or using the mouse directly on the desktopby clicking

    on the interface to enter three points through which the slip surface passes.

    Note: In cohesive soils rotational slip surfaces occur most often. These are modeled using circular slip

    surfaces. This surface is used to find critical areas of an analyzed slope. For non-cohesive soils, an

    analysis using an polygonal slip surface should be also performed for slope stability verification (see

    HELPF1).

    Now, select Bishop as the analysis method, and then set type of analysis as Optimization. Then

    perform the actual verification by clicking on Analyze.

  • 7/28/2019 Geo5 Engineering Manuals

    70/101

    69

    Frame Analysis Bishopoptimization of circular slip surface

    Note: optimization consists in finding the circular slip surface with the smallest stabilitythe critical

    slip surface. The optimization of circular slip surfaces in the program Slope stability evaluates the

    entire slope, and is very reliable. For different initial slip surfaces, we get the same result for a critical

    slip surface

    The level of stability defined for critical slip surface when using the Bishop evaluation method is

    satisfactory :

    50,182,1 sSFSF SATISFACTORY.

    Analysis 2:

    Now select another analysis on the toolbar in upper right corner of your Analysis frame in

    GEO5.

    Toolbar Analysis

    In the frame Analysis, change the analysis type to Standard and as method select All

    methods. Then click on Analyze.

  • 7/28/2019 Geo5 Engineering Manuals

    71/101

    70

    Frame Analysis All methodsstandard type of analysis

    Note: Using this procedure, the slip surface made for all methods corresponds to critical slip surface

    from the previous analysis scenario using the Bishop method. For better results the user should choose

    the method and then perform an optimization of slip surfaces.

    The values of the level of slope stability are:

    Bishop: 50,182,1 sSFSF SATISFACTORY. Fellenius / Petterson: 50,161,1 sSFSF SATISFACTORY. Spencer: 50,179,1 sSFSF SATISFACTORY. Janbu: 50,180,1 sSFSF SATISFACTORY. Morgenstern-Price: 50,180,1 sSFSF SATISFACTORY. achuanc: 50,163,1 sSFSF SATISFACTORY.

    Note: the selection of method of analysis depends on experience of the user. The most popular methods

    are the method of slices, from which the most used, is the Bishop method. The Bishop method does

    yield conservative results.

    For reinforced or anchored slopes other rigorous methods (Janbu, Spencer and Morgenstern-Price)

    are preferable. These more rigorous methods meet all conditions of balance, and they better describe

    real slope behavior.

    It is not needed (or correct) to analyze a slope with all methods of analysis. For example, the Swedish

    method FelleniusPetterson yields very conservative results, so the safety factors could be

    unrealistically low in the result. Because this method is famous and in some countries required for

    slope stability analysis, it is a part of GEO5 software.

  • 7/28/2019 Geo5 Engineering Manuals

    72/101

    71

    Analysis 3polygonal slip surface

    In the last step of analysis, input the polygonal slip surface. As a method of analysis, select

    Spencer, as analysis type select optimization, enter a polygonal slip surface and perform the

    analysis.

    Frame Analysis Spenceroptimization of polygonal slip surface

    The values of the level of slope stability are:

    50,158,1 sSFSF SATISFACTORY.

    Note: Optimization of a polygonal slip surface is gradual and depends on the location of the initial slip

    surface. This means that it is good to make several analyses with different initial slip surfaces and with

    different numbers of sections. Optimization of polygonal slip surfaces can be also affected by local

    minimums of factor of safety. This means the real critical surface does need to be found. Sometimes it

    is more efficient for the user to enter the starting polygonal slip surface in a similar shape and place

    as an optimized circular slip surface.

  • 7/28/2019 Geo5 Engineering Manuals

    73/101

    72

    Local minimums

    Note: We often get complaints from users that theslip surface after the optimization disappeared.

    For non-cohesive soils, where kPacef 0 the critical slip surface is the same as the most inclined line

    of slope surface. In this case, the user should change parameters of the soil or enter restrictions in

    which the slip surface cant pass.

    Conclusion

    The slope stability after optimization is:

    Bishop (circular - optimization): 50,182,1 sSFSF SATISFACTORY. Spencer (polygonal - optimization): 50,158,1 sSFSF SATISFACTORY.

    This designed slope with a gravity wall satisfies stability requirements.

  • 7/28/2019 Geo5 Engineering Manuals

    74/101

    73

    Chapter 9. Stability of slope with retaining wall

    In this chapter, we are going to describe the stability analysis of an existing slope, then how to model a

    sheeting wall being built, and how to check its internal and external stability.

    Assignment:

    Perform an analysis of an existing slope and then verify the design of an underground wall for

    construction of parking areas. When performing the analysis, consider the permanent design situation

    in all construction stages. Verify the stability using safety factors. The safety factor needed is

    50,1sSF . All stability analyses are performed using the Bishop method with optimization of circular

    slip surface.

    Scheme of assignment

    The wall is made from concrete class C 30/37, the thickness of the wall is mh 5,0 . The

    calculated shear resistance of the wall is mkNVRd 325 .

    Solution:

    For solving this task, use the GEO5 programSlope Stability. In this text, we will describe the

    solution of this task step by step.

    Construction stage 1: slope modeling, determination of safety factor of the existing slope; Construction stage 2: making the earth cut for the parking (only as a working stage) Construction stage 3: construction of the wall, analysis of internal and external stability;

  • 7/28/2019 Geo5 Engineering Manuals

    75/101

    74

    Analysis results (Conclusion).

    Construction stage 1: slope modeling

    In the frame Settings, click on Select and then choose analysis settings nr. 1 Standard safety factors.

    Then, model the interface of layers, resp. terrain using these coordinates.

    Interface coordinates

    Note: If data is entered incorrectly, it can be undone using the button UNDO (shortcut Ctrl-Z). In the

    same manner, we can use the opposite function REDO (Shortcut Ctrl-Y).

    Buttons Undo and Redo

  • 7/28/2019 Geo5 Engineering Manuals

    76/101

    75

    Then define the soil parameters and assign them to the profile.

    Table with the soil parameters

    Soil(Soil classification)

    Unit weight3mkN Angle of internal

    friction ef Cohesion of soil kPacef

    SMSilty sand,medium dense soil

    18,0 29,0 5,0

    ML, MISilt with low ormedium plasticity, stiff

    consistency, 8,0rS 20,0 21,0 30,0

    MSSandy silt,firm consistency

    18,0 26,5 12,0

    In the frame Stage settings choosepermanent design situation.

    Analysis 1stability of existing slope

    Now open up the frame Analysis and run the verification of stability of the original slope. As

    a verification method select Bishop and thenperform the optimization of circular slip surface. How

    to input slip surface and optimization principle is described in more detail in the previous chapter and

    in HELP (F1).

  • 7/28/2019 Geo5 Engineering Manuals

    77/101

    76

    Analysis 1stability of the original slope

    The factor of safety of the original slope as analyzed by Bishop is:

    50,126,2 sSFSF Satisfactory.

    Construction stage 2: earth cut modeling

    Now add the second construction stage using the button in the upper left corner of the window.

    Toolbar Construction stages

    Add the earth cut to the interface by adding individual points of the considered earth cut (similar to

    adding points to the current interface) in the frame Earth cut. The excavation for the sheeting wall is

    0,5 m wide. After you are done with adding the points click on OK.

  • 7/28/2019 Geo5 Engineering Manuals

    78/101

    77

    Coordinates of the earth cut

    Note: If you define two points with same x coordinate (see picture), the program asks if you want to

    add the new point to the left or right. The scheme of resulting input of the point is highlighted with red

    and green color in the dialog window.

    Frame Earth cut

    Construction stage 3: construction of the retaining wall

    Now design the sheeting wall. In the frame Embankment add the points of the interface of

    the embankment. With these we actually model the face of the structure of the wall (see picture).

  • 7/28/2019 Geo5 Engineering Manuals

    79/101

    78

    The points of embankment

    Frame Embankment

    Analysis 2internal stability of retaining wall

    To verify the internal stability on the circular slip surface it is necessary to model the

    structure as a stiff soil with fictitious cohesion, and not as rigid body. If it is modeled as a rigid body,

    the slip surface cannot intersect the structure.

    Note: shear resistance of the RC retaining wall is modeled with help of fictitious cohesion, which we

    can determine as:

    kPah

    Vc Rdfict 650

    5,0

    0,325

    where: mh width of the wall,

    mkNVRd shear resistance of the wall.

  • 7/28/2019 Geo5 Engineering Manuals

    80/101

    79

    Now return to the 1st

    construction stage and add a new soil with name Material of the retaining

    wall. Define the value of the fictitious cohesion as kPacef 650 , the angle of internal friction as a

    small value (for example 1ef ) since the program doesnt allow to input 0. Define the unit weight

    as3

    25 mkN , which corresponds to structure from reinforced concrete.

    Analysis 3slope stability behind the earth cut and retaining wall (internal stability)

    The analysis results of internal stability show that the slope with the earth cut and the retaining

    wall is stable:

    50,160,1 sSFSF Satisfactory.

    Analysis 3external stability of retaining wall

    Now add another analysis using toolbar in the left downward corner of the program.

    Toolbar More Analyses

  • 7/28/2019 Geo5 Engineering Manuals

    81/101

    80

    Before running the analysis of the external slope stability, add restrictions on the optimization

    procedure using lines that the slip surface cant intersect when it executes the optimization procedure

    (More info in HELPF1). In our example the restriction lines are the same as the borders of the pile

    sheeting.

    Analysis 4 - restrictions on the optimization procedure

    Note: for analysis of external slope stability it is appropriate to input the retaining wall as a solid

    body. When the wall is modeled as a solid body, the slip surface doesnt intersect itduring the

    optimization evaluation.

  • 7/28/2019 Geo5 Engineering Manuals

    82/101

    81

    Analysis 4slope stability with earth cut and retaining wall (external stability)

    From the results of external stability we can see, that the slope with the earth cut and retaining

    wall is stable:

    Conclusion

    The objective of this chapter was to verify the slope stability and design of earth cut with

    retaining wall for the construction of a car park with analysis of internal and external stability. The

    results of analyses are:

    This slope with earth cut and retaining wall from concrete (with width of 0,5 m) in terms of long-term

    stability satisfies evaluation criteria.

    Note: this designed retaining wall would need to be checked for stress from the bending moment of

    loading from active earth pressure. This bending moment can be analyzed in the GEO5 programs

    Sheeting design and Sheeting Check.

    For the same bending moment it is also necessary to design and check reinforcementsfor example in

    program FIN ECConcrete 2D.

  • 7/28/2019 Geo5 Engineering Manuals

    83/101

    82

    Chapter 10. Design of geometry of spread footing

    In this chapter, we are going to show you how to design spread footing easily and effectively.

    Assignment:

    Using EN 1997-1 (EC 7-1, DA1) standards, design the dimensions of a concentric spread footing. Forces

    from columns act on the top of foundation. Input forces are: yxyx MMHHN ,,,, . The terrain behind the

    structure is horizontal; foundation soil consists of S-FSand with trace of fines, medium dense soil. At 6,0 m is

    Slightly weathered slate. The GWT is also at a depth of 6,0 m. The depth of foundation is 2,5 m below the

    original terrain.

    Scheme of the assignmentanalysis of bearing capacity of spread footing

    Solution

    For solving this problem, we will use the GEO5 program Spread footing. Firstly, we input all the data

    in each frame, except Geometry. In the Geometry frame, we will then design the spread footing.

    Basic input

    In the frame Settings, click on Select and then choose nr. 3 Standard EN 1997DA1.

  • 7/28/2019 Geo5 Engineering Manuals

    84/101

    83

    Frame Settings list

    Also select an analysis methodin this case Analysis for drained conditions. We will not analyze

    settlement.

    Frame Settings

    Note: Usually, spread footings are analyzed for drained conditions= using the effective parameters of soil

    ( efef c, ). Analysis for undrained conditions is performed for cohesive soils and short-term performance using

    total parameters of soil ( uu c, ). According to EN 1997 total friction considered is always 0u .

    In the next step enter the geological profile, soil parameters and assign them to the profile.

    Table with the soil parameter

    Soil, rock

    (classification)

    Profile

    m

    Unit weight

    3mkN

    Angle of internal

    friction ef

    Cohesion

    of soil

    kPacef

    S-FSand with trace offines, medium dense soil

    0,06,0 17,5 29,5 0,0

    Slightly weathered slate from 6,0 22,5 23,0 50,0

  • 7/28/2019 Geo5 Engineering Manuals

    85/101

    84

    In the next step, open up the frame Foundation. As a type of foundation, choose Centric spread footing and

    fill in the dimensions such as depth from the original grade, depth of footing bottom, thickness of foundation

    and inclination of finished grade. Also, input the weight of overburden, which is the backfill of spread footing

    after construction.

    Frame Foundation

    Note: The depth of the footing bottom depends on many different factors such as natural and climatic factors,

    hydrogeology of the construction site and geological conditions. In the Czech Republic the depth of footing

    bottom is recommended to be at least 0,8 meters beneath the surface due to freezing. For clays it is

    recommended that the depth be greater, such as 1,6 meters. When analyzing the bearing capacity of a

    foundation, the depth of the foundation is considered as the minimal vertical distance between the footing

    bottom and the finished grade.

    In the frame Load enter the forces and moments acting on the upper part of foundation: yxyx MMHHN ,,,, .

    These values we obtained from a structural analysis program and we can import them to our analysis by clicking

    on Import.

    Frame Load

    Note: For design of dimensions of spread footing, generally the design load is the deciding load. , However, in

    this case we are using the analysis settings EN 1997-1 - DA1, and you must enter the value of service load too,

    because the analysis requires two design combinations.

  • 7/28/2019 Geo5 Engineering Manuals

    86/101

    85

    Dialog window Edit load

    In the frame Material, input the material characteristics of the foundation.

    Skip the frame Surcharge, as there is no surcharge near the foundation.

    Note: Surcharge around the foundation influences the analysis for settlement and rotation of the foundation,

    but not bearing capacity. In the case of vertical bearing capacity it always acts favorably and no theoretical

    knowledge leads us to analyze this influence.

    In the frame Water enter the ground water depth as 6,0 meters.

    We are not going to enter a sand gravel bed because we are considering permeable cohesionless soil at

    the of footing bottom.

    Then open up the frame Stage settings and select permanent as the design situation.

    Design of dimensions of the foundation

    Now, open the frame Geometry and apply the function Dimensions design; with which the program

    determines the minimum required dimensions of the foundation. These dimensions can be edited later.

    In the dialog window it is possible to input the bearing capacity of foundation soil Rd or select

    Analyze. We will choose Analyze for now. The program automatically analyzes the foundation weight and

    weight of soil below foundation and determines the minimum dimensions of the foundation.

  • 7/28/2019 Geo5 Engineering Manuals

    87/101

    86

    Dialog window Foundation dimensions design

    Note: Design of centric and eccentric spread footing is always performed such that that the dimensions offoundation are as small as they can be and still maintain an adequate vertical bearing capacity. The option

    Input designs the dimensions of a spread footing based on the entered bearing capacity of the foundation

    soil.

    We can verify the design in the frame Bearing cap..

    Frame Bearing capacity

    Vertical bearing capacity: 97,7 % 59.53222.545 dR [kPa] SATISFACTORY.

    Conclusion:

    The bearing capacity of designed foundation (2,0x2,0 m) is satisfactory.

  • 7/28/2019 Geo5 Engineering Manuals

    88/101

    87

    Chapter 11. Settlement of spread footing

    In this chapter, we describe how analysis of settlement and rotation of a spread footing is performed.

    Assignment:

    Analyze the settlement of centric spread footing designed in last chapter (10. Design ofdimensions of spread footing). The geometry of the structure, load, geological profile and soils are the

    same as in the last chapter. Perform the settlement analysis using the oedometric modulus, and

    consider the structural strength of soil. Analyze the foundation in terms of limit states of

    serviceability. For a structurally indeterminate concrete structure, of which the spread footing is a part,

    the limiting settlement is: 0,60lim, ms mm.

    Scheme of the assignmentanalysis of settlement of spread footing

    Solution:

    For solving this task, we will use the GEO5 programSpread footing. We will use the data

    from the last chapter, where almost all required data is already entered.

  • 7/28/2019 Geo5 Engineering Manuals

    89/101

    88

    Basic Input:

    The design of spread footing in the last task was performed using the standard EN 1997, DA1.

    Eurocodes do not order any theory for the analysis of settlement, so any common settlement theory canbe used. Check the setting in the frame Settings by clicking on Edit. In the tab Settlement select

    the method Analysis using oedometric modulus and set Restriction of influence zone to based on

    structural strength.

    Dialog window Edit current settings

    Note: The structural strength represents the resistance of a soil against deformation from a load. It is

    only used in Czech and Slovak Republic. In other countries, the restriction of the influence zone is

    described by percentage of Initial in-situ stress. Recommended values of structural strength are from

    CSN 73 1001 standards (Foundation soil below the foundation)

    In the next step, define the parameters of soils for settlement analysis. We need to edit each soil

    and add values for Poissons ratio, coefficient of structural strength and oedometric modulus, resp.

    deformation modulus.

  • 7/28/2019 Geo5 Engineering Manuals

    90/101

    89

    Table with the soil parameters

    Soil, rock

    (classification)

    Unit

    weight3mkN

    Angle of

    internal

    friction

    ef

    Coeff. of

    structural

    Strength

    m

    Deformation

    modulus MPaEdef

    Poissons

    ratio

    S-FSand withtrace of fines,

    medium dense soil

    17,5 29,5 0,3 15,5 0,3

    Slightly weathered

    slate22,5 23,0 0,3 500,0 0,25

    Analysis:

    Now, run the analysis in the frame Settlement. Settlement is always analyzed for service

    load.

  • 7/28/2019 Geo5 Engineering Manuals

    91/101

    90

    Frame Settlement

    In the frame Settlement it is also needed to input other parameters:

    - Initial in-situ stress in the footing bottom is considered from the finished gradeNote: the value of in-situ stress in the footing bottom has influence on the amount of settlement and the

    depth of influence zonea larger initial in-situ stress means less settlement. The option of in-situ

    stress acting on the footing bottom depends on the time the footing bottom is open. If the footing

    bottom is open for a longer period of time, the soil compaction will be less and it is not possible to

    consider the original stress conditions of the soil.

    - In Reduction coefficient to compute settlement, select the option Consider foundation thicknesseffect (1).

    Note: the coefficient 1

    reflects the influence ofthe depth of the foundation and gives more realistic

    results of the settlement

    Results of analysis

    The final settlement of the structure is 16,9 mm. Within an analysis of limit states of

    serviceability we compare the values of the analyzed settlement with limit values, which are

    permissible for the structure.

    Note: The stiffness of structure (soil-foundation) has a major influence on the settlement. This stiffness

    is described by the coefficient kif k is greater then 1, the foundation is considered to be stiff and

    settlement is calculated under a characteristic point (located in 0,37l or 0,37b from the center of the

    foundation, where l and b are dimensions of foundation). If coefficient k is lower then 1, the settlementis calculated under the center of foundation.

    - Analyzed stiffness of foundation in direction is 10,137k . The settlement is computed underthe characteristic point of foundation.

    Note : Informative values of allowable settlement for different kinds of structures can be found in

    various standardsfor example CSN EN 1997-1 (2006) Design of geotechnical structures.

  • 7/28/2019 Geo5 Engineering Manuals

    92/101

    91

    The Spread footing program also provides results for the rotation of the foundation, which is analyzed

    from the difference of settlement of centers of each edge.

    Rotation of the foundationprinciple of the analysis

    Rotation in direction x : )1000(tan75,0 Rotation in direction y : )1000(tan776,1

    Conclusion

    This spread footing in terms of settlement satisfies evaluation criteria.

    Settlement: 9,160,60lim, ssm [mm].

    It is not necessary to verify rotation of this foundation.

  • 7/28/2019 Geo5 Engineering Manuals

    93/101

    92

    Chapter 12. Analysis of consolidation under embankment

    In this chapter, we are going to explain how to analyze consolidation under a constructed

    embankment.

    Introduction:

    Soil consolidation takes into account the settlement time (calculation of earth deformation)

    under the effect of external (constant or variable) loads. The surcharge leads to an increase in earth

    formation stress and the gradual extrusion of water from pores, i.e. soil consolidation. Primary

    consolidation corresponds to the situation in which there is a complete dissipation of pore pressures in

    soil, secondary consolidation affects rheological processes in the soil skeleton (the so called "creep

    effect"). This is a time-dependent process influenced by a number of factors (e.g. soil permeability

    and compressibility, length of drainage paths, etc.). With regards to the degree of consolidation we

    distinguish the following cases of ground settlement: final settlement corresponding to 100% consolidation from the respective surcharge partial settlement corresponding to a particular degree of consolidation from the respective

    surcharge

    Assignment:

    Determine the settlement value under the centre of an embankment constructed

    on impermeable clay one year and ten years after its construction. Make the analysis using CSN 73

    1001 standards (using oedometric modulus), limit of influence zone consider using coefficient of

    structure strength.

    Scheme of the assignmentconsolidation

  • 7/28/2019 Geo5 Engineering Manuals

    94/101

    93

    Solution:

    The GEO 5 Settlement program will be used to solve this task. We are going to model this

    example step by step:

    1st construction stageinterface modeling, calculation of the initial geostatic stress. 2nd construction stageadding a surcharge by means of an embankment. 3rd up to 5th construction stagescalculation of embankment consolidation at various time

    intervals (according to the assignment).

    Evaluation of results (conclusion).

    Basic assignment (procedure): Stage 1Check the "Perform consolidation analysis" field in the "Settings" frame. Then select specific

    settings for calculation of the settlement from "Settings list". This setting describes the analysis method

    for calculation of the settlement and restriction of influence zone.

    Frame "Settings"

    Note: This calculation considers the so called primary consolidation (dissipation of pore pressure).

    Secondary settlement (creep), which may occur mainly with non-consolidated and organic soils, is not

    solved within this example.

    Then we enter the layer interface. The objective is to select two layers between which

    the consolidation takes place.

  • 7/28/2019 Geo5 Engineering Manuals

    95/101

    94

    Frame "Interface"

    Note: If there is a homogeneous soil, then in order to calculate the consolidation, it is necessary toenter a fictitious layer (use the same parameters for the two soil layers that are separated by the

    original interface), preferably at the depth of the deformation zone.

    Then we define the "Incompressible subsoil" (IS) (at a depth of 10 m) by means of entering

    coordinates similarly to interface modeling. No settlement takes place under the IS.

    The soil parameters are entered in the next step. For soils being consolidated, it is required to

    specify either the coefficient of permeability " k" or the coefficient of consolidation " vc ".Approximate values can be found in HELP (F1).

    Dialog window "Modification of soil parameters"

  • 7/28/2019 Geo5 Engineering Manuals

    96/101

    95

    Table with the soil parameters

    Soil

    (Soil classification)

    Unit weight

    3mkN

    PoissonsRatio

    Oedometric

    modulus

    MPaEoed

    Coeff. of

    structural

    strength

    m

    Coeff. of

    permeability

    daymk

    Clayey soil 18,5 0,3 1,0 0,1 5100,1

    Embankment 20,0 0,35 30,0 0,3 2100,1

    Sandy silt 19,5 0,35 30,0 0,3 2100,1

    Then we assign the soils to the profile. The frame surcharge in the 1st construction stage

    is not taken into consideration, since in this example it will be represented by the actual embankment

    body (in stages 2 to 5). In the next step, we shall enter the ground water table (hereinafter the "GWT")

    using the interface points, in our case at ground level.

    In the frame Stage settings, you can only modify layout and refinement of holes, so leave the

    standard settings.

    The first "Calculation" stage represents the initial geostatic stress at the initial construction

    time. However, it is necessary to specify the basic boundary conditions for the consolidation

    calculation in further stages. The top and bottom interface of the consolidating soil is entered, as well

    as the direction of water flow from this layeri.e. the drainage path.

  • 7/28/2019 Geo5 Engineering Manuals

    97/101

    96

    "Analysis"Construction stage 1

    Note: If you enter "Incompressible subsoil", you shall then consider the direction of flow of water from

    the consolidating soil only upwards

    Basic assignment (procedure): Stages 2 to 5Let's now move to the 2nd construction stage by tool bar at the top left of the desktop.

    Toolbar Construction stage

    We define the embankment itself by entering coordinates. A specific soil type is assigned to the

    embankment.

    "Stage 2Embankment interface points"

  • 7/28/2019 Geo5 Engineering Manuals

    98/101

    97

    "Stage 2Embankment + Assignment"

    Note: The embankment acts as a surcharge to the original ground surface. It is assumed that a well-

    executed (optimally compacted) embankment theoretically does not settle. In a practice, settlement

    may occur (poor compaction, soil creep effect), but the program Settlement does not address this.

    In the "Analysis" frame enter the time duration of the 2nd stage corresponding to the actual

    embankment construction time. The actual calculation of the settlement cannot be performed yet

    because, when determining consolidation, it is first necessary to know the whole history of the

    earthwork structure loading, i.e. all construction stages.

    Frame "AnalysisConstruction Stage 2"

  • 7/28/2019 Geo5 Engineering Manuals

    99/101

    98

    Since the embankment is built gradually, we are considering the linear load growth in the 2nd

    construction stage. In subsequent stages, the duration of the stage is entered (1 year i.e. 365 days 3rd

    stage, 10 years i.e. 3,650 days 4th stage and the overall settlement 5th stage) and the whole

    loading is introduced at the beginning of the stage.

    The calculations are performed after enter the last construction stage, which is on the "Overallsettlement", is turned on (you can check it at any stage apart from the first one).

    Frame "CalculationConstruction Stage 5"

    Analysis results

    Upon the calculation of the overall settlement, we can observe partial consolidation values

    below the centre of the embankment. We have obtained the following maximum settlement values in

    individual construction stages:

    Stage 1: only geostatic stresssettlement not calculated. Stage 2 (surcharge by embankment): for 30 days 29.2 mm Stage 3 (unchanged): for 365 days 113.7 mm Stage 4 (unchanged): for 3,650 days 311.7 mm Stage 5: the overall settlement 351.2 mm

  • 7/28/2019 Geo5 Engineering Manuals

    100/101

    99

    "AnalysisConstruction stage 5 (Overall settlement)"

    As we are interested in the embankment settlement after its construction, we will switch to theresults view in the 3rd and 4th stages (the button "Values") to "compared to stage 2" which subtracts

    the respective settlement value.

  • 7/28/2019 Geo5 Engineering Manuals

    101/101

    "AnalysisSettlement (differences compared to previous stages)"

    Conclusion:

    The embankment settlement (under its centre) within one year from its construction is 84.5 mm

    (= 113.729.2) and after ten years 282.5 mm (= 311.729.2).