8/14/2019 Generic Skill
1/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
UNIVERSITI TEKNOLOGI MALAYSIA
FACULTY OF CIVIL ENGINEERING
HIGHWAY ENGINEERING - SAB 2832
SEMESTER I - SESSION 2008/2009
NAME : MARDHIYAH SYAHIDA BT BERHANUDDIN
SECTION / GROUP : 2 SAW (SECTION 3) / GROUP 2
IC NO. : 870723035290
MATRIX CARD : BA 080032
LECTURER : HAJI CHE ROS BIN HAJI ISMAIL
DATE OF SUBMISSION : 29 /08 / 2008
1
8/14/2019 Generic Skill
2/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
his assignment is designed to evaluate our generic skill on problem solving or ability to
think critically, identify, formulate, and solve the civil engineering related problems.TAs a potential highway engineer in my country, I am instructed by Works Ministry to give a report
on a highway construction problem in my country.
This report is provided based on a real problem on highway construction (Highway
Engineering). The problem was occurred in a real project in Selangor. This project is known as
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE
HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN. In this report, consist that a lot of
problem occured during the construction and possible suggestions which is can overcome the
whole problems.
2
8/14/2019 Generic Skill
3/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
KERAJAAN MALAYSIA
JABATAN KERJA RAYA
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN
TERBANG SUBANG KE HOSPITAL SUNGAI BULOH,
SELANGOR DARUL EHSAN
No. Kontrak : KKR/JKR/UB/63/2003
HIGHWAY CONSTRUCTION
PROBLEMS REPORT
Provided by: MARDHIYAH SYAHIDA BT BERHANUDDINHIGHWAY ENGINEER
JABATAN KERJA RAYA MALAYSIA PERKIM (DAMANSARA UTAMA) RIRA BINA JV
CAWANGAN JALAN
Cawangan Jalan ( Tingkat 15 ), Letter Box No. 78
Ibu Pejabat JKR Malaysia, Level 18, UBN Tower
Jalan Sultan Salahuddin, No. 10, Jalan P. Ramlee
50582 Kuala Lumpur. 50250 Kuala Lumpur.
3
8/14/2019 Generic Skill
4/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
Tel : 603 2691 9011 Fax : 603 2693 6662 Tel : 603 2023 2088 Fax : 603 - 2023 1688
TABLE OF CONTENTS
No Title Page
1.0 Description of The Project
2.0 Project Information
3.0 Location & Layout Plan
4.0 Related Photo
5.0 Description of The Problems & Possible Solutions
6.0 Recommendations
7.0 Appendixes
8.0 References
1) Description of The Project
The project is a part of the Government of Malaysia plan to upgrade the existing Federal route
FT015 and B9 from Terminal 3 of Subang Airport to Sungai Buloh Hospital.
4
8/14/2019 Generic Skill
5/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
The original contract sum of the project for Phase 1 is RM 130,000,000.00 which will be
constructed over a period of twenty four (24) months. The site possession on 15th September
2003 and the original completion date shall be on 11th September 2005.
The Supplementary Agreementb No. 1 for Phase 2 has been approved by JKR dated
02/08/2006. The Phase 2 contract sum is RM 139,500,000.00 which will be constructed for a
period of 24 months. The date of possession of site for Phase 2 on 17 th July 2006 and the
original date of completion shall be on 16 th July 2008. The Extension of Time No. 3 has been
approved by JKR until 9th October 2008 due to delay on site possession caused by land
matters. The new completion date is 9 th October 2008.
Meanwhile, the remaining works under Phase 1 contract still pending due to water mains
relocation work along MCAO alignment by others and at this stage salvaging of the existing
main pipe in progress.
2) Project Information
2.1) Intoduction
The Government of Malaysia intends to upgrade the existing Federal Route FT015 and B9 from
Terminal 3 of Subang Airport to Sungai Buloh Hospital with approximately 12.0 km in length.
The previous access to the Sungai Buloh Hospital is via the state road B9, a 2-lane single
carriageway linked to the FT054 through a diamond interchange. It is also necessary to upgrade
the state road B9 from Subang Airport FT015 to linkup FT002 with FT054 in order to improve
traffic flow as heavy vehicles and other commercial vehicles heavily traverse the state road B9.
In order to ease the traffic flow, as well as to cater for the future development, the contract
Cadangan Projek Menaiktaraf Laluan B9/FT015 dari Lapangan Terbang Subang ke Hospital
Sungai Buloh has been awarded to Perkim (Damansara Utama)-Rira Bina Sdn. Bhd. JV by the
Government via Design and Build Contract comprise of Phase 1 and Phase 2.
2.2) Project Description
Phase 1
The combination of half-diamond interchange and the trumpet interchange implemented at the
existing Sungai Buloh Junction to provide a mainline link to the new Sungai Buloh Hospital.
5
8/14/2019 Generic Skill
6/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
A new half-diamond interchange at the existing intersection between B9 and Route 54 will
accommodate for the right turning movement from Route 54 or Jalan Hospital to Subang and
from B9 to Route 54, Kepong direction. This allow for free flow movement at the existing Route
54.
The works also involve upgrading Jalan Hospital from two (2) lane single carriageway to two (2)
dual carriageway.
The work components of the Phase 1 project shall comprise the following :-
(a) Upgrading of existing Jalan Hospital from Hospital Sungai Buloh to the Sungai Buloh
interchange.
(b) Construction of new Sungai Buloh Interchange inclusive of new half diamond and
modified trumpet interchange.
(c) Vehicular underpass at KTM access road.
(d) Pedestrian bridges.
(e) Pedestrian box culvert.
(f) Sungai Gasi river bridge inclusive river protection work.
(g) Relocation of Water Mains.
(h) Works include relocation, replacement and construction of services including TNB,
SYABAS, Telekom and all other associated works.
Phase 2
The proposed works involve the upgrading of certain stretches of existing State road B9,
Federal Route 15 and construction of new alignment of Federal Route 15 between Terminal 3
Airport to existing T-Junction Batu Tiga Sg. Buloh. The total length of works involved covers a
distance of approximately 9 km. The geometric of the upgrading road shall be design to JKR U5
Standard. The road shall be 4-lane dual carriageway and paved shoulder on both side of
carriageway. It comprises of the following major component.
(a) Upgrading of five (5) at-grade signalized junction along State Road B9 as follows:-
i. Pinggiran Subang incorporation Batu Tiga Sungai Buloh Junction.
ii. Rubber Research Institute (RRI) Junction.
iii. Sg. Buloh Industrial Park Junction.
iv. Kota Damansara Junction.
v. Sri Sg. Buloh Junction.
6
8/14/2019 Generic Skill
7/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
(b) Construction of two (2) new at-grade signalized junction along new alignment of Federal
Route 15 as follows:-
i. Kg. Muhibbah Junction.
ii. Airod Junction.
2.3) Scope Of Works
1. Roadwork
(a) Site Clearance and earthworks.
(b) Construction of approach and slip road as well as ramps including earthworks,
flexible pavement, shoulder and associated works.
(c) Provide and install street lightings, furniture, guardrails and necessary road markings
as well as landscaping works.(d) Traffic Management.
2. Drainage
(a) Construction of R. C. pipe culverts and R. C. box culverts including diversions,
excavation of unsuitable materials for foundation.
(b) Construction of ancillary drainage works including catchpits, diversions and scour
protection works.
(c) Construction of roadside drain, berm and toe interceptor drains.
3. Structures
Phase 1
(a) New Sg. Buloh Interchange inclusive of new half diamond and modified existing totrumpet interchange.
(b) Sg. Gasi River Bridge.
(c) Vehicular Underpass at KTM access road.
(d) Retaining walls of rubble type, reinforced concrete or reinforced earth wall.
(e) Pedestrian Bridges.
7
8/14/2019 Generic Skill
8/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
(f) Pedestrian Box Culvert.
Phase 2
(a) Sg. Damansara (2 nos bridges).
(b) Pedestrian Bridge.
(c) Retaining wall.
(d) River diversion at Sg. Damansara.
4. Services
Works include recolation, replacement of services including TNB, Telekom, Maxis,
Celcom and all other associated works by others whereas SYABAS water pipe
recolation for Phase 2 will be carried out by the main contractor. Meanwhile, SYABAS
water pipe recolation on Phase 1 is in progress by others.
Project Summary
NAME OF PROJECT
CADANGAN PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE
HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN.
EMPLOYER
JABATAN KERJA RAYA MALAYSIA, CAWANGAN
JALAN, JLN SULTAN SALAHUDDIN, 50582 KUALA
LUMPUR.
CONTACT PERSON:
1) Ir. Abd. Rahman Abd. Aziz
2) Ir. Sheikh Ismail Sheikh Salleh
3) En. Shukri Ishak
8
8/14/2019 Generic Skill
9/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
DESIGN & BUILT
CONTRACTOR
PERKIM (DAMANSARA UTAMA) RIRA BINA JV
LETTER BOX NO. 78,
LEVEL 18, UBN TOWER,
NO. 10, JALAN P. RAMLEE,
50250 KUALA LUMPUR.
SITE OFFICE:
NO. 3-1, 1st FLOOR, JLN DINAR E,
U3/E, SEKSYEN 3, TMN SUBANG PERDANA, 40150
SHAH ALAM, SELANGOR DARUL EHSAN.
CONTACT PERSON:
1) En. Md. Ismail Abd. Kader
2) Ir. Rofie Sarbini
3) En. Ahmad Ismail Nik Aman
CONSULTING
ENGINEERINGS
PERUNDING SSE
2-2, JLN IMPIAN PERDANA 1
SAUJANA IMPIAN
43000 KAJANG
SELNGOR.
SEPAKAT SETIA PERUNDING SDN BHD
WISMA SSP LEVEL 8-18
NO. 1 JLN SR 8/3
SERDANG RAYA SEKSYEN 8
43300 SERI KEMBANGAN
SELANGOR.
CONTACT PERSON:
1) Ir. Shahbudin Anuar
2) Ir. Ilyas Ibrahim
3) En. Zaini Ibrahim
1) Ir. Teh Ming Hu
2) Ir. Izam Razali
3) Ir. Shuhaimi Mohd
INDEPENDENT CHECKER
(STRUCTURE)
T-CROP ENGINEERING SDN. BHD.
NO. 80-B, JALAN SS21/39,
DAMANSARA UTAMA,
47400 PETALING JAYA,
SELANGOR.
TEL : 03-7710 1382
FAX : 03-7710 1398
CONTACT PERSON:
1) Ir. Tham Kum Weng
GEOTECHNICAL PERUNDING ZMS SDN. BHD.
NO. 50/3, LORONG 6C/91,
TAMAN SHAMELIN PERKASA,
CONTACT PERSON:
1) Ir. Saidin Abu Bakar
9
8/14/2019 Generic Skill
10/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
BATU 3 , JALAN CHERAS,
56100 KUALA LUMPUR.
TEL : 03-9200 3734
ROAD SAFETY AUDITOR PB-TRSS CONSULTING,
NO. 9, JALAN SS 15/4C,
SUBANG JAYA,
47000 PETALING JAYA,
SELANGOR.
TEL : 03-5633 6899
CONTACT PERSON:
1) Ir. Che Ali b. Che Hitam
ORIGINAL CONTRACT DETAILS
Phase Phase 1 Phase 2
Contract Sum RM 130,000,000.00 RM 139,500,000.00
Commencement Date (Original) 15 th September 2003 17 th July 2006
Completion Date (Original)
Completion Date (Revised)
11 th September 2005 16 th July 2008
9 th October 2008
Construction Period (Original)
Construction Period (Revised)
104 Weeks (24 Months) 24 Months
27 Months
Defect Liability Period 24 Months 24 Months
Road Length (km) 4.5 km 9.0 km
10
8/14/2019 Generic Skill
11/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
11
8/14/2019 Generic Skill
12/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
JABATAN KERJA RAYA
PROJECT DIRECTORS ORGANISATION CHART
12
8/14/2019 Generic Skill
13/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
Line of Communication
Reporting to
Reporting to
Awarded
Supervising
Government of Malaysia
Jabatan Kerja RayaGovernment
Structure Auditor
T-CorpGeotechnic Auditor
Perunding ZMS
Safety Auditor
Perunding TRSS
Auditing
Consultants
Traffic Management
T&D Consult S/B
Contractors
Utilities Relocation
Subcontractors
To Be Awarded
Design and Build Contractor
Perkim(Damansara Utama)-Rira Bina JVUtilities Companies
TNB, Telekom,Maxis,Time, PUAS
Design
ConsultantsDesign Co nsultant
Sepakat Setia Perunding
Supervision
Consultants
Contractor
Sub-Contractor
Landscape Contractor
TBA
Landscaping
ANZ Landscape S/B
Appointed
Specification & Construction Drawings
Specification & Construction Drawings
Appointed
Awarded
Awarded
Appointed
Supervising Consultant
Sepakat Setia Perunding
13
8/14/2019 Generic Skill
14/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
3) Location & Layout Plan
UPGRADING OF ROAD
ALIGNMENTS
4) Related Photo
14
8/14/2019 Generic Skill
15/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
Signboard Of The Project
Road Location
15
8/14/2019 Generic Skill
16/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
16
8/14/2019 Generic Skill
17/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
17
8/14/2019 Generic Skill
18/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
5) Description of The Problems & Possible Solutions
There are several problems that caused the extended period in project constructions:
Structure Component:
DAMAGED OF L-SHAPE DRAIN AT SG. DAMANSARA RIVER TRAINING WORK
The construction of L-shape structure for river training works were begin on February 2007
between Ch. 0m to Ch. 250m (LHS). The affected location by the major flood is on the down
stream (LHS) of the river alignment.
The affected portion is between Ch. 80m to Ch. 125m (WB017 to WB026) which completed with
the capping beam structure on March 2007. However, during heavy down pour dated
14/04/2007, sudden increase of water levels was happen due to accumulate volume from the up
18
8/14/2019 Generic Skill
19/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
stream section. The up stream section was widened by JPSs project. The accumulate volume
were flowing through the L-shape section at that time is under construction.
At the same time, it was created overflow condition on top of L-shape section. The problem
arises when the existing river at down stream side yet to be widened by JPSs project during
incident. Hence, this situation was created the bottleneck and scouring action and damaged the
portion of completed L-shape at down stream side especially at the bend with drain outlet
discharge points.
19
8/14/2019 Generic Skill
20/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
General View RE Wall (MCDO) towards Sungai Buloh
CAST IN-SITU DECK RIB BEAMS AND SLAB CRACKINGS (PROPOSED SG. BULOH
EXPRESSWAY UPGRADING WORKS MCAO )
Issue Date : July 2005
The content of this problem deals with the cracking of cast in-situ rib beams and deck slab top
cracking incidence observed on the Span 1 Left Hand Side deck slab from Abutment A to Pier 1.
On the morning of 18 July 2005, the side formworks of the outer faces of the decks rib beams
and cantilever flanges were stripped.
Several vertical crack lines were seen on both of the exposed surfaces. The finishing on the
concrete surfaces were considered very good without obvious blemishes. Concreting of the said
sections was done on the evening of 27th
of June from approximately 6pm until 2am thefollowing day. The total concrete volume in this single pour was 314m 3. The method of placing of
concrete was by means of concrete pump. Thus, the average speed of concreting is almost 40
m3 per hour. The weather report during the whole concreting operation was reported as fine. The
20
8/14/2019 Generic Skill
21/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
concrete supply to site was considered consistent and supply trucks were delivering and
discharging the loads in an orderly manner. The proposed concrete mix was of Grade 50
nominal strength with cement content of 460Kg/m3 and the water cement ratio is 0.37. The cube
samples taken for this batch of concrete pour were sent for testing and the results for 7-days
strength and 28-day strength were considered within the expected range. The average cube
test results show that the 7-days strength was of average 44MPa while the 28-days strengths is
not available as of this date.
The top surface of deck slab was sprayed with proprietary curing compound before the
anticipated 2-hour setting time. However, some isolated crack lines were observed on the
following day. The cracking patterns were in random and appeared to be fan-out shape. The
surface cracks observed on the vertical faces of the exposed rib beams after formwork stripping
is presented in Appendix A of this report. There were about 8-10 crack lines on each of the
vertical surface. The crack lines are almost vertical, and the maximum crack width when
measured on site is approximately 0.35mm measured by inspection with a transparent plastic
marked with varying line thicknesses and superimposed over the crack locations. Most of the
crack line extend from soffit to the underside of the cantilever flange, but some are
discontinuous and less than 750mm long either near the soffit of the rib or near to the underside
of the flanges. It is also observed that the first crack line started approximately at 5-7m from the
either end of the stop ends.
Slope Component:
SLOPE FAILURE.
Issue Date : May 2008
21
8/14/2019 Generic Skill
22/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
22
8/14/2019 Generic Skill
23/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
23
8/14/2019 Generic Skill
24/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
Traffic and Safety Management:
Issue Date : DURING CONSTRUCTION
24
8/14/2019 Generic Skill
25/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
6) Recommendations
25
8/14/2019 Generic Skill
26/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
Structure Component:
Rapid drying of the concrete will significantly increases the possibility of cracking. The chemical
reaction which causes concrete to go from the viscous or plastic state to a solid state requires
water and heat is generated in the process.
Shrinkage is a primary cause of cracking in freshly set concrete. As concrete hardens and dries,
it shrinks. This is due to the loss of water through evaporation before the complete hydration
has taken place.
Rapid cooling of external surfaces and fast building up of hydration heat within the inner core
creates a drastic thermal gradient across the concrete section. These two extreme phenomenon
poses the greatest threat to undermine the weak tensile strength within the concrete.
The effects of prestressing forces will tend to substantially close, if not complete, the cracks
present on the rib surfaces.
The recommendations are suggested as following below:
1. For the isolated cracks observed on the top of deck slab, it is required that liquid curing
compound will still be applied after completion of concreting work but not more than 2
hours after pouring on any part of the surface. In addition, covering with plastic sheets or
wet Hessian are proposed to lower the possibility of top surface cracking. It is
recommended that these additional measures be carry out for at least 5 days
continuously after concreting works.
2. It is proposed to control the speed of concrete placement carefully in order to minimizethe amount of heat trapped inside of the rib core by allowing heat to escape freely over a
reasonable larger open area. Timing of subsequent layer pour must not exceed the
anticipated setting time of the previous poured and vibrated load in order to avoid the
forming of cold joint across separately laid layers.
3. To limit the length of each pour operation to a smaller distance to reduce the possibility
or quantum of cracking, if any, but on the other hand, also achieve reasonable work
progress.
4. To carry out through inspection on the line and levels of formwork and falsework in order
to reduce the external factors to it minimum.
26
8/14/2019 Generic Skill
27/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
5. After prestressing, majority of the crack lines will be closed due to the compression
introduced to the rib. If cracks were not fully closed, it is proposed that high strength
epoxy grout be injected into the cracks to seal it off completely.
Slope Component:
Failure of slope stability such as landslides cause property damage, injury, and death and
adversely affect a variety of resources. For example, water supplies, fisheries, sewage disposal
systems, forests, dams, and roadways can be affected for years after a slide event. The
negative economic effects of landslides include the cost to repair structures, loss of property
value, disruption of transportation routes, medical costs in the event of injury, and indirect costs,
such as lost timber and fish stocks. Water availability, quantity, and quality can be affected by
landslides. Geotechnical studies and engineering projects to assess and stabilize potentially
dangerous sites can be costly.
RC Retaining Wall:
27
8/14/2019 Generic Skill
28/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
28
8/14/2019 Generic Skill
29/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
Traffic and Safety Management:
The control of vehicular traffic movement at the worksite and at public areas requires an
organized traffic management system, as some of the work will be performed at public roads.
i) At Worksite
Proper traffic signages shall be erected at the worksite to guide worker and drivers of
vehicles on speed limit and other traffic requirement.
An orderly traffic flow system shall be established for the smooth flow of vehicular
traffic in the worksite
When access roads are partially obstructed, proper traffic management signages
shall be posted (i.e detour signs shall be properly posted)
During nights hours proper flashing amber lamps and reflectorized signages (if
required flagmen) shall be posted to guide vehicular traffic.
ii) Public road29
8/14/2019 Generic Skill
30/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
Prior to commencement of work, flagmen shall be deployed and traffic signages shall
be placed at the work area to direct and caution motorist of the impending works. (ie
traffic signages safety cones, reflectorized traffic signs, flashing ambler lamps)
Flagmen shall be deployed at areas where vehicular traffic need to be guided and at
locations where trucks and heavy equipment enter and exit. Wash troughs shall be
installed at the entrance to public roads.
During the night, work areas shall be properly posted with reflectorized traffic
signages and flashing amber lamps.
All workers engaged in traffic management shall wear safety reflective vest.
Note : Traffic management method statement shall be developed.
No unauthorized usage of transport shall be tolerated. All drivers must comply with
the following basic rules.
Valid driving licences
Follow traffic rules especially load and speed limit
Never drive when tired
Make sure the vehicle is in good condition and properly maintained.
iii) Emergency Response Team (ERT)
The ERT works round the clock
Each team consists of 1 foreman cum driver and 2-traffic controller equipped with 1
no of vehicle and equipment for arranging emergency road closure.
ERT is to assist the public in case of any accident occur along the work area.
ERT is to ensure there are no potholes left unattended
ERT to control traffic flow in case of traffic light black out or malfunction until policetraffic arrived to take over or the light rectified and repaired.
ERT is also trained to intercept any incomings or emergencies at any time, place or
situation and condition.
30
8/14/2019 Generic Skill
31/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
7) Appendixes
Appendix A
31
8/14/2019 Generic Skill
32/39
8/14/2019 Generic Skill
33/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
Appendix B (SCENERY)
33
8/14/2019 Generic Skill
34/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
34
8/14/2019 Generic Skill
35/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
8) References
a) Project Report - PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN
TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
35
8/14/2019 Generic Skill
36/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
b)
PERUNDING SSE
c)
d)
e)
36
http://www.trb.org/default.asp8/14/2019 Generic Skill
37/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
37
8/14/2019 Generic Skill
38/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
38
8/14/2019 Generic Skill
39/39
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN
39