1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23, 2010 Jeff Mechenbier Director Transmission & Distribution Planning and Contracts
30

Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

May 23, 2018

Download

Documents

lenhi
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

1

Generation and Transmission System Overview

RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEENovember 23, 2010Jeff Mechenbier

Director Transmission & Distribution Planning and Contracts

Page 2: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

2

Agenda

Transmission GridsSystem Map OverviewA Few Facts…PNM Transmission System UsesSystem RepresentationLoad Characteristics and Load GrowthExisting Queues Transmission Development IssuesRenewable Resources and Wind Energy Potential in NM

Page 3: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

33

Three Transmission/Grids Exist In The US

Page 4: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

44

The Western Transmission GridCovers the 14 western United States and parts of Canada and Mexico

PHOENIXMOJAVE

CRANBROOK

SAN FRANCISCO

CORNERSNAVAJO

PINTO

SHASTA

BUCKLEY

SUNDANCE

FT. PECK

KEMANO

PEACE CANYON

MICA

VANCOUVER

SEATTLE

PRINCE RUPERT

AREA

AREA

COLSTRIP

BOISE

PORTLANDAREA

MALIN

TABLE MTN

ROUND MTN

SALT LAKECITY AREA

MEXICO

EL PASOAREA

PALO

LUGO

MIDPOINT

AREA

LOS ANGELESAREA

ALBUQUERQUEAREA

VERDE

DENVERAREA

HOOVER

AREA

LANGDON

HOT SPRINGS

HELLSCANYON

CHIEF JOSEPH

GRAND

BURNS

FOUR

HVDC TERMINAL

COULEE

DEVERS

7 HVDC ( asynchronous) interconnections) between Eastern and Western Grids-1470 MW

2 HVDC interconnections between Eastern grid and ERCOT-820 MW

No interconnections between Western grid and ERCOT

Page 5: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

5

System Map Overview

PNM Transmission Dependant

Other Systems

PNM Retail Service Area

PNM Owned Electric Lines

Other Electric Lines

SPPWECC• Lines shown in red are the primary backbone transmission lines in NM

•The main function of transmission is to deliver power from generating resources to load centers

•Lower voltage lines serve as backup to the backbone lines and to distribute power to outlying smaller load areas distant from Albuquerque and El Paso

Page 6: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

6

A Few System Facts……

Line mileage (incl. jointly owned lines)• 165 miles of 500 kV (Outlet lines from Palo Verde)• 1556 miles of 345 kV• 180 miles of 230 kV• 1000 miles of 115 kV

“Backbone” transmission lines (345 kV and 230 kV) are 150 to 200 miles in length.Majority of transmission lines built in late 1960s through the mid 1970s. PNM has not built any backbone transmission since 1984

Page 7: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

7

PNM Transmission System Uses

PNM Balancing Authority Load• Retail-PNM customers represent about 60% to 65% of

system use

• Wholesale-Transmission customers (network customers and P-to-P) represent 35% to 40% of system use

Page 8: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

8

System RepresentationPeak Load

Four Corners43.3% of Generation

3% of Load

Southern NM20.7% of Generation

10% of Load

North/Central NM18.6% of Generation

87% of Load

WECC11.1% of

Generation

SPP6.3% of

Generation

Page 9: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

9

Load Characteristics and Load GrowthPNM System Load

900

1100

1300

1500

1700

1900

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Hour

Loa

d (M

W)

PNM SYSTEM FIRM LOAD 7/24/2008

PNM SYSTEM FIRM LOAD 8/4/2009

PNM SYSTEM FIRM LOAD 7/19/2010

Peak LoadHome ~4000 watts or 4kw or 0.004MW300 residential homes ~1MWCottonwood Mall ~5.5MW

System peak load is during SummerWinter peak ~90% of SummerWinter Peaking areas in Northeastern NM

Page 10: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

10

Existing Queues

Interconnection Requests41 -- 14,143 MW (12,870 MW wind & 1,273 MW solar)

4 -- 1075 MW Pending LGIA

8 – 635 MW Signed LGIA not operational (gas, wind, solar)

4 – 492 MW Operational (December 2010)

Joint Studies (EPE/TSGT)

8,416 MW

Peak Load1,973 MW (PNM)

~2,600 MW (PNM Balancing Authority)~5,000 MW Total New Mexico

Transmission Delivery Service Requests65 – 8410 MW

4 – 297 MW Signed TSA not operational

Page 11: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

11

Transmission Development Issues

• Few PPAs are being inked, projects are very slow to move forward with signed agreements

• Transmission lacking in renewable rich zones

• Congestion/ lack of transmission between NM-AZ and AZ-CA

• Transmission is a regional issue-All stakeholders in the region need to cooperate in solution

• Transmission very expensive-can’t be justified for single use

• Transmission siting is lengthy and difficult-large costs at risk on front end

• Determining who pays and how costs are recovered for long distance lines is very difficult

• Collaboration needs to begin at the federal/state level to address conflicting goals of governments. Federal and state policies are not aiming at the same targets.

Page 12: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

12

Renewable Resources and Wind Energy Potential in NM

Page 13: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

13

Renewable Portfolio Standards

www.dsireusa.org / November 2010

Renewable portfolio standard

Renewable portfolio goal

Solar water heating eligible *† Extra credit for solar or customer-sited renewables

Includes non-renewable alternative resources

WA: 15% x 2020*

CA: 33% x 2020

NV: 25% x 2025*

AZ: 15% x 2025

NM: 20% x 2020 (IOUs)10% x 2020 (co-ops)

HI: 40% x 2030

Minimum solar or customer-sited requirement

TX: 5,880 MW x 2015

UT: 20% by 2025*

CO: 30% by 2020 (IOUs)10% by 2020 (co-ops & large munis)*

MT: 15% x 2015

ND: 10% x 2015

SD: 10% x 2015

IA: 105 MW

MN: 25% x 2025(Xcel: 30% x 2020)

MO: 15% x 2021

WI: Varies by utility; 10% x 2015 statewide

MI: 10% + 1,100 MW x 2015*

OH: 25% x 2025†

ME: 30% x 2000New RE: 10% x 2017

NH: 23.8% x 2025

MA: 22.1% x 2020 New RE: 15% x 2020

(+1% annually thereafter)

RI: 16% x 2020

CT: 23% x 2020

NY: 29% x 2015

NJ: 22.5% x 2021

PA: ~18% x 2021†

MD: 20% x 2022

DE: 25% x 2026*

DC: 20% x 2020

VA: 15% x 2025*

NC: 12.5% x 2021 (IOUs)10% x 2018 (co-ops & munis)

VT: (1) RE meets any increase in retail sales x 2012;

(2) 20% RE & CHP x 2017

KS: 20% x 2020

OR: 25% x 2025 (large utilities)*5% - 10% x 2025 (smaller utilities)

IL: 25% x 2025 WV: 25% x 2025*†

29 states + DC and PR have

an RPS(7 states have goals)

29 states + DC and PR have

an RPS(7 states have goals)

DCOK: 15% x 2015

PR: 20% x 2035

www.dsireusa.org / November 2010

Page 14: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

14

Regional Diversity ofRenewable Resource Opportunities

3/24/2010 14LPPC

Page 15: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

15

Typical Cost to Install Wind and Solar (PV) 100 MW plant

Wind ~$235 Million

Land owner ~$3k to $5k per turbine/year

Solar (PV) ~$450 Million

Solar-Thermal (storage) ~$610 Million

Page 16: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

162

Larger, WaterLarger, Water--boundbound

Page 17: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

17

Wind Energy Potential in NM

Map By created by TrueWindSolutions from MesoMap system using historical weather data

Page 18: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

18

Existing Wind Generation in New Mexico

Installed: 698 MW

2 MW “Llano Estacado” near Clovis - Cielo Wind, SPS (1999, expanded in 2003)

204MW “NMWEC” near Fort Summer – NextEra, PNM (2003)

80MW “Caprock” near Tucumcari, Cielo Wind, PNM (2005)

120MW ”San Juan Mesa Wind Project” near Elida, Padoma Wind Power, SPS (2005)

90 MW “Aragonne Mesa” Superior Wind, west of Santa Rosa, APS (2005)

100 MW “High Lonesome Mesa” Edison Mission, near Willard, APS (2009)

102 MW “Red Mesa” – NextEra, short-term TEP (2010)

Page 19: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

19

New Mexico Wind Energy Center

•• Located in Eastern New MexicoLocated in Eastern New Mexico

•• 204 MW capacity204 MW capacity

•• Installed in 2003, in record time!Installed in 2003, in record time!

•• Owned and operated by FPL Energy (NextEra)Owned and operated by FPL Energy (NextEra)

•• PNM purchases all the outputPNM purchases all the output

Page 20: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

20

210 feet Tower Erection - 1 of 3 Tower Sections

Quick Fact: The bottom tower section has a base 16-foot diameter and weighs 39 tons.

Page 21: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

21

Tower Erection - 2nd Tower Section

Page 22: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

22

Placing Generator - 60 Tons

Page 23: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

23

Placing the Generator

Page 24: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

24

235 feet Diameter Blade Assembly

Page 25: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

25

Flying The Rotor

Quick Fact:

The 275-ton crane’s boom is 300 ft long.

Quick Fact:

The rotor and 3 blades weigh 43 tons.

Page 26: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

26

Installing the Rotor

Page 27: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

27

All 136 Turbines Erected!

Quick Fact:

It is 310 feet to top of blade

Page 28: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

28

PNM Load (08/03-08/04)

PNM Load Pattern (08/03PNM Load Pattern (08/03--08/04)08/04)Winter

Peak Load

Spring/FallLoad Valleys

Summer Peak Load

Page 29: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

29

NMWEC Output Pattern (08/03-08/04)

PNM Load Pattern (08/03PNM Load Pattern (08/03--08/04)08/04)

WinterPeak Load

Spring/FallLoad Valleys

Summer Peak Load

Page 30: Generation and Transmission System Overview 112310 Item 0 Generation and...1 Generation and Transmission System Overview RADIOACTIVE AND HAZARDOUS MATERIALS COMMITTEE November 23,

30

Questions?