Top Banner
CIVIL AND ARCHITECTURAL SPECIFICATIONS JUNE 2014
716
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript

CIVIL AND ARCHITECTURAL SPECIFICATIONS

JUNE 2014

CIVIL /ARCHITECTURAL SPECIFICATIONS

OVER ALL INDEX

Division 01 00 00 -General Requirements -01 32 16 - Construction Progress Schedule -01 32 33 - Photographic Documentation -01 35 29 - Health, Safety, and Emergency Response Procedures -01 52 00 - Construction Facilities -01 57 19 - Construction Environment Management Plan -01 74 00 - Cleaning & Waste Management -01 81 13 - Sustainable Design Requirements

Division 02 00 00 -Existing Conditions -02 32 00 - Geo Technical Investigation

Division 03 00 00 -Concrete -03 11 00 -Concrete Forming -03 15 00 -Concrete Accessories -03 21 00 -Reinforcement -03 30 00 -Cast In Place Concrete -03 30 50 -Concrete for Water retaining Structures -03 35 00 -Concrete Floor Finishing -03 41 00 -Precast Structural Concrete -03 45 00 -Precast Architectural Concrete

Division 04 00 00 -Masonry -04 22 00 - Concrete Unit Masonry

Division 05 00 00 -Metals -05 50 00 -Metal Fabrications

Division 06 00 00 -Wood, Plastic and Composites -06 10 00 - Rough Carpentry -06 20 00 - Finish Carpentry -06 41 16 - Plastic Laminated Architectural cabinets -06 61 16 - Solid Surfacing Fabrications

Division 07 00 00 -Thermal and Moisture Protection -07 10 00 - Water proofing/Thermal Insulation -07 10 50 - Underground Water Tank GRP Lining -07 84 00 - Fire stopping -07 92 00 - Joint Sealants

INDEX CIVIL & ARCHITECTURAL SPECIFICATIONS PAGE 1 OF 2

Division 08 00 00 -Openings -08 11 00 -Metal Doors and Frames -08 11 16 -Aluminium Doors and Frames -08 14 00 -Wood doors -08 32 13 -Automatic sliding doors -08 51 13 -Aluminum Windows -08 62 13 -Domed Unit Skylights -08 71 00 -Door Hardware -08 81 00 -Glass and Glazing

Division 09 00 00 -Finishes -09 21 16 -Gypsum Board Assemblies -09 24 00 -Cement Plastering -09 30 13 -Ceramic Tiling -09 30 33 -Stone Tiling -09 51 13 -Acoustical Panel Ceilings -09 66 16 - Terrazzo Tiles -09 68 16 - Sheet carpeting -09 90 00 - Painting -09 96 00 - High Performance coating

Division 10 00 00 -Specialties -10 14 00 - S i gn ag e -10 14 53 - Traffic signage -10 28 13 - Toilet Accessories

Division 13 00 00 -Special Construction -13 31 23 - Tensioned Fabric Structures

Division 31 00 00 -Earth Work -31 23 16 - Excavation -31 23 23.13 - Backfill -31 31 16 - Termite control

Division 32 00 00 -Site Construction

-32 14 13.13 - Interlocking Precast Concrete Unit Paving -32 17 23 - Pavement Marking

CIVIL & ARCHITECTURAL SPECIFICATIONS

Division 01 00 00 -General Requirements

-01 32 16 -Construction Progress Schedule -01 32 33 -Photographic Documentation -01 35 29 -Health, Safety, and Emergency Response Procedures -01 52 00 -Construction Facilities 01 57 19 Construction Environment Management Plan -01 74 00 -Cleaning & Waste Management 01 81 13 Sustainable Design Requirements

DIVISION ONE - GENERAL REQUIREMENTS 01 32 16 - CONSTRUCTION PROGRESS SCHEDULE

1. Section Includes

A. Measurement And Payment B. General C. Scheduling format. D. Submittals E. Four-week plan F. Monthly progress status report. G. Review, updates, and revisions.

2. Measurement And Payment

A. Separate measurement or payment will not be made for work required under this Section. All costs in connection with the work specified herein will be considered to include with the related item of work in the Bid Schedule of the Bid Form, or incidental to the Work.

3. General

A. Progress schedules shall represent a practical plan to complete the Work within the Contract time(s) of completion indicated, and shall convey the Contractor's intent in the manner of prosecution and progress of the Work.

B. The scheduling and execution of construction in accordance with the Contract Documents are the responsibility of the Contractor. The Contractor shall involve and coordinate all Subcontractors and material Suppliers in the development and updating of progress schedules.

C. The submittal of progress schedules shall be understood to be the Contractor's representation that the progress schedule meets the requirements of the Contract Documents and that the Work will be executed in the sequence and duration indicated in the progress schedule.

4. Scheduling Format

A. The Project Schedule shall be computer produced in the Critical Path Method (CPM) format. The schedule shall be computer produced utilizing project scheduling software such as Primavera, Microsoft Project or other equivalent software as approved by the CLIENT.

B. The Project Schedule shall be updated monthly and submitted as indicated in Article 1.05, Submittals.

C. The schedule shall show Contract tasks, percent complete, progress bars, baseline schedules, milestones, start and finish dates, and other breakdowns as required by the CLIENT.. The schedules shall show clearly the sequence of activities and shall list specifically the following activities:

1. Interim milestone completion dates. Phasing and staging of the Work as specified shall be prominently identified.

2. Submittals and the Architect's review of submittals.

3. District inspection of the Work, including Preliminary Final Inspection, Final Inspection, punch list(s), and Acceptance.

4. Acquisition of permits.

5. Any long lead time (over 60 days) orders for material and equipment.

6. Work to be performed by other contractors or agencies.

7. Delivery of District-furnished equipment and materials indicated for incorporation in the Work.

D. Descriptions of scheduled activities shall include sufficient detail to identify the work that is to be accomplished.

1. The schedule shall contain sufficient activities to clearly show the sequence and interdependencies of the Work. The schedule shall be prepared in such a way that an activity or group of activities will correspond directly with the bid item breakdown and/or the breakdown of lump sum bid items. The CLIENT may request that additional activities be added.

2. Activity durations shall be expressed in whole days. Work that is to be performed by Subcontract shall be clearly defined.

3. Float suppression techniques, such as preferential sequencing (crew movement, equipment use, and form reuse), extended duration, imposed dates, scheduling of work not required for the Contract, and others, shall not be used to affect or limit float in the schedule. The use of constraint dates should be minimized, and must be approved by the CLIENT..

4. Critical Path activities are those activities with a total float equal to or less than zero. Schedules with negative total float may be found to be impractical by the CLIENT.

E. A schedule showing that Work that is completed in less than the completion time specified may be found to be impractical by the CLIENT.

F. A schedule showing that Work that is completed in less than the completion time specified, that is found to be practical by the CLIENT shall be considered to have float. The float shall be

the time between the scheduled completion of the Work and the Contract completion date. Float time shall not be for the exclusive benefit of either the District or the Contractor. Float shall be a resource available to both parties.

G. A schedule found to be impractical for the preceding reasons or any other reasons shall be revised by the Contractor and resubmitted.

5. Submittals

A. 1Refer to Section 01 33 00 - Submittal Procedures, for submittal requirements and procedures.

B. Schedules shall be submitted in time-scaled bar-chart (Gantt) format with logic lines shown on sheets no smaller than 22 inches wide by 34 inches long or larger than 34 inches wide by 44 inches long. A time-scaled logic network diagram may also be required by the CLIENT. An activity report in a tabular form showing the following information shall be submitted with bar-chart: activity ID, description, duration, total float, early start, early finish, late start, late finish, predecessors, successors, constrains, percent complete, and remaining duration.

C. All schedule submittals shall include one reproducible and six full-size copies.

D. Schedule submittals will be reviewed by the CLIENT. and shall be updated and revised as indicated in Article 1.08, Review, Updates, and Revisions. Re submittal shall conform to the same requirements as original submittals.

E. The Contractor shall prepare and submit all schedules and schedule analysis reports in electronic format as well as hard copies.

F. All progress schedule submittals are subject to review and approval by the Architect. The Architect retains the right to withhold progress payments until the Contractor submits an acceptable progress schedule and progress schedule updates.

G. The Contractor shall submit the schedule within 14 days after the date of the Notice to Proceed or as mentioned by the condition of contract.

H. The first of each type of schedule and the first Progress Status Report submitted by the Contractor will be reviewed for format, as well as content. The CLIENT may request format changes. Once the format has been approved, all subsequent Schedules and Progress Status Reports shall be submitted in the approved format.

6. Four-Week Work Plan

A. A schedule in calendar time-scaled bar chart format depicting the Contractor's intended work activities for the upcoming four-week period shall be submitted on a weekly basis and shall be due on the first working day of each week. Each activity of one day or more in duration shall be indicated.

B. Any deviations, such as sequences of work, timing, and durations of activities from the approved Project Schedule, shall be noted and explained in writing.

C. The Four-Week Work Plan shall be submitted on sheets not less than 8-1/2 inches by 11 inches, or as approved by the CLIENT.

7. Monthly Progress Status Report

A. The Monthly Progress Status Report shall be a narrative report that describes work activities accomplished in the reporting period, intended work activities for the upcoming reporting period, problems and actions intended by the Contractor to mitigate the problems, work that is being performed out of sequence with approved schedules, status of Change Orders, Notices of Potential Claims, status of submittals, and status of Contractor procurement items.

B. The Contractor shall submit the report format and obtain the CLIENT's approval of the format.

C. The Monthly Progress Status Report shall be submitted neither monthly on sheets no larger than 11 inches by 17 inches, nor any smaller than 8-1/2 inches by 11 inches.

8. Review, Updates, and Revisions

A. The CLIENT will review and return the Contractor's schedule submittals with written comments according to the following schedule from the date of receipt.

Project CPM Schedule: 10 calendar days

Four-Week Work Plan: 5 calendar days

B. The Contractor shall make all corrections to the Project Schedule requested by the CLIENT and resubmit the schedule for approval. If the Contractor does not agree with the CLIENT's comments, the Contractor shall provide written notice of disagreement within five days from the receipt of the Architect's comments. The Architect's comments on the Four-Week Work Plan for which the Contractor disagrees shall be resolved in a meeting held for that purpose, if necessary.

C. At least once each month, or as often as deemed necessary by the Architect, the Contractor shall submit an updated schedule showing the progress of the Work to date and anticipated activities to be worked on, and the Monthly Progress Status Report as specified in Article 1.07. The submittal of the Project Schedule update and Monthly Progress Status Report shall be at least five days prior to the submittal of a payment invoice. No invoice will be accepted nor payment made if there is not an approved current update in place.

D. If, according to the approved Project Schedule, the Contractor is thirty or more days behind the Contract completion date of any milestone indicated, or the schedule contains 30 or more days of negative float, considering all approved time extensions, the Contractor shall submit a revised schedule, showing a practical plan to complete the Work within the specified Contract completion time. The District may withhold progress payments until a revised schedule, acceptable to the CLIENT, is submitted by the Contractor.

END OF SECTION

DIVISION ONE - GENERAL REQUIREMENTS

01 32 33 - PHOTOGRAPHIC DOCUMENTATION

1. Section Includes

A. B. C. D. E.

Measurement And Payment Stages of construction. Quality and quantity of photographs. Identification of photographs. Disputes, and potential claims.

2. Measurement and Payment

A. Separate measurement or payment will not be made for work required under this Section. All costs in connection with the work specified herein will be considered to be included with the related item of work in the Bid Schedule of the Bid Form, Drawings or incidental to the Work.

3. Stages of Construction

A. The Contractor shall take photographs at all construction milestones and at each of the following stages of construction:

1. Before commencement of clearing and demolition;

2. Upon completion of clearing and demolition;

3. Monthly during performance of the Work; and

4. Upon completion of the Work.

5. Anytime a problem arises that may result in a Notice of Potential Claim and the problem can be illustrated by photographs.

B. Furnish at least three different views or vantage points of each milestone and stage of construction.

4. Quality And Quantity of Photographs

A. All photographs shall be standard commercial quality, colour prints, on single weight glossy paper.

B. Photographs shall be 5 by 7 inches in size.

C. Digital photographs stored on CD-ROM or DVD may be substituted for standard photographs addressed above. Digital photographs shall be in pdf, jpg, or tif format.

5.

6.

Identification of Photographs

A. The following information shall be typed on the back of each print furnished and furnished for each digital photograph in a manner approved by the CLIENT.

1. Title of Contract and Contract Number;

2. Identification of subject shown;

3. Time and date taken.

Disputes and Potential Claims:

A. In the event a problem arises or dispute occurs which may result in a Notice of Potential Claim under the General Conditions and the problem or dispute can be illustrated by photographs and video recordings, the Contractor shall provide such photographs and video cassettes.

END OF SECTION

DIVISION ONE - GENERAL REQUIREMENTS 01 35 29 - HEALTH, SAFETY AND EMERGENCY RESPONSE PROCEDURES

1. Section Includes

A. Measurement And Payment B. Submittals C. Contractor's safety program. D. First aid. E. Emergencies and emergency procedures. F. Protecting the general public. G. Specific requirements H. Inspections by outside agencies. I. Inspections by the District. J. Work performed near existing operating right-of-way K. Hazardous materials encountered during construction.

2. Measurement and Payment

A. Separate measurement or payment will not be made for work required under this Section. All costs in connection with the work specified herein will be considered to be included with the related item of work in the Bid Schedule of the Bid Form, Drawings or incidental to the Work.

3. Submittals

A. Within 5 days of Execution of Contract:

1.

Submit for review and approval, the Contractor's proposed Safety representatives resume identifying his or her work experience and qualifications. The minimum qualifications shall be five years of diversified construction safety experience, and two years experience related to the Contract's scope of work. The Contractor shall have received the CLIENT's approval of the Contractor's proposed Safety Representative prior to submitting the first monthly progress payment.

B. Within 7 days of Notice to Proceed:

1. Submit two copies of the Contractor's Safety Program for review and approval. The Contractor shall have received the CLIENT's approval of the Contractor's proposed Safety Program prior to submitting the first monthly progress payment.

4. Contractor's Safety Program

A. The Contractor's Safety Program shall incorporate the Contractor's safety practices and procedures, as well as the requirements described herein including the following:

1. A disciplinary program.

2. A policy that prohibits rough or boisterous play and activity, gambling, the use of alcohol or drugs, and the possession of weapons on the construction site.

5. First Aid

A. The Contractor shall provide emergency medical services including American Red Cross certified First Aid Representative(s) on the jobsite and an appropriate area designated for first aid to treat injured employees. First Aid Representatives shall be CPR certified.

B. Employees shall receive prompt first aid care when injured.

6. Emergencies and Emergency Procedures

A. Develop Emergency Procedures for any event that may occur for the following categories:

1.

2.

3.

4.

5.

6.

7.

8.

9.

Fire;

Employee injury;

Property damage and damage to various utilities (such as, electrical, gas, sewage, water, telephone or public roadways);

Public demonstrations;

Bomb threats;

Hazardous materials encountered;

Toxic spills;

Explosions; and

Vehicular accidents.

B. The Emergency Procedures shall include, but not be limited to, the following:

1. Identification of the person responsible for handling an emergency. 2. Establishment of teams for handling each type of emergency.

3. Identification of the person responsible for making emergency call (preferably the ranking Supervisor present).

4. 2The requirement to conspicuously post a list of an emergency phone numbers, along with information to be transmitted.

C. Update the Emergency Procedures when necessary.

D. Provide to the CLIENT copies of the above Emergency Procedures.

E. Contact the CLIENT immediately in the event a serious accident should occur.

F. Following an emergency, the Contractor shall:

1. Secure the area as expediently as possible; and

2. Provide only those authorized representatives of the District and specific governmental agencies an account of the nature of the emergency. Questions from media personnel shall be referred to the CLIENT.

G. Whenever the Contractor requires emergency services, such as ambulance, Fire Department or Police, the Contractor shall use the posted emergency numbers and also contact a District representative.

7. Protecting the General Public

A. The Contractor shall take the necessary steps to prevent injury to the general public or damage to public property. The public shall be considered as any persons not employed by the Contractor or its Subcontractors. The Contractor shall adhere to the following requirements:

1.

2.

3.

Work shall be performed outside of the designated work area only when specifically stated in writing from the CLIENT.

Necessary steps shall be taken to protect and maintain work areas that interface with public sidewalks, station entrances (lobbies, corridors and aisles), stairways, escalators, elevators, and station platforms.

All travel ways, access and egress points shall be maintained and clear of obstructions at all times.

4. Warning signs shall be conspicuously positioned and a flag person shall be assigned when the Contractor's equipment may be encountered by pedestrians or vehicles.

8. Specific Requirements

A. Work Areas: The Contractor shall provide a safe work area for its employees. When unsafe conditions do exist, immediate abatement is required.

B. Work Practices: The Contractor shall be responsible for assuring that its employees work safely and use the appropriate personal protective equipment.

C. Weekly "Tool Box" Meetings:

1.

2.

The Contractor shall conduct weekly "tool box" meetings (15 minutes minimum) for all employees. The purpose of these weekly meetings is to:

a. Discuss observed accident trends and causes.

b. Plan safety into the work activities.

c. Take action to correct workers' safety concerns.

d. Review emergency procedures with employees.

These meetings shall be documented and such documentation forwarded to the CLIENT within one week of the meeting.

D. Accident and Incident Reports: Provide CLIENT with copies of all accident and incident reports within 24 hour of occurrence.

E. Cal/OSHA Permit and Registration Requirements:

1.

Submit copies of permits from the California Division of Occupational Safety for the following:

a. Erection or demolition of any building, false work, scaffolding, or structure the equivalent of three stories or higher.

b. Performing any work related to hazardous materials.

F. Personal Protective Equipment (PPE): The Contractor's personnel, without exception, are required to wear certain PPE. Among these are:

2.

3.

4.

5.

6.

7.

8.

Hard hats and orange safety vests - mandatory.

Hearing protection - mandatory in all operations creating noise above 80dBA.

Eye protection - mandatory when performing tasks producing flying debris or when handling any chemicals.

Safety harness - meeting ANSI A10.14 and shall be worn and used when exposed to any fall of 4 feet or more in height, where the height cannot be properly guarded with rails or other means.

Shoes - made of leather (if tunnelling is performed, shoes shall be made of rubber with steel toes).

Shirts - only those with sleeves allowed; no tank tops or mesh shirts are allowed.

Respiratory protection - when required by law.

9.

Inspections by Outside Agencies

A. The Contractor shall be subject to inspections by outside agencies, including Cal/OSHA. The Contractor shall notify the CLIENT immediately should citations, warnings or safety violations be issued. Copies of same shall be provided to the CLIENT within 48 hours.

10. Inspections by the District

A. The Contractor shall cooperate with designated District representatives when conducting site inspections.

B. The District may periodically make quality assurance audits of the Contractor's Safety Program.

11. Work Performed Near Existing Operating Right-Of-Way

A. For any construction equipment (such as cranes, concrete pump trucks, back hoes, and the like) that could encroach into the District's operating right-of-way, the Contractor shall submit, and obtain approval by the CLIENT, a plan describing the use of such equipment, and the necessary precautions to be taken to preclude any accidental encroachment of the right-of-way.

12. Hazardous Materials Encountered During Construction

A. If unidentified contaminated materials are encountered during construction or an accident results in the release of hazardous materials, work shall be stopped and the area evacuated and secured. The Contractor shall immediately notify the CLIENT. If necessary, the Contractor shall take precautions to limit the contamination to the jobsite.

END OF SECTION

DIVISION ONE - GENERAL REQUIREMENTS 01 52 00 - CONSTRUCTION FACILITIES

1. Section Includes

A. B. C. D. E. F. G. H. I. J.

Measurement And Payment Governing Laws Temporary sanitary facilities. Engineer's field office. Contractor's field office. Storage and parking areas. Enclosed storage and shops. Protective barricades and safety precautions. Temporary fencing. Security. Close -out

2. Measurement and Payment

A. Separate measurement or payment will not be made for work required under this Section. All costs in connection with the work specified herein will be considered to be included with the related item of work in the Bid Schedule of the Bid Form, Drawings or incidental to the Work.

3. Governing Laws

A. Temporary facilities shall be in compliance with applicable federal, state, county, municipal and local utility laws, rules, and regulations. Nothing in these Contract Documents shall be construed to permit work not conforming to such codes and regulations.

4. Temporary Sanitary Facilities

A. Provide adequate temporary toilet conveniences, washing facilities, and drinking water for the use of all employees and persons engaged on or about the Work, including Subcontractors and their employees. Drinking water shall be potable, and drinking water facilities shall be clean and sanitary.

B. Locate sanitary facilities where approved by authorities having jurisdiction and maintain in a clean and sanitary condition during the course of the Work. Keep such facilities adequately supplied with toilet paper, paper towelling, paper cups, and related supplies as required.

C. At completion of the Work, sanitary facilities shall be properly disinfected and all evidence of same removed from the site.

5. Engineer's Field Office

A. Requirements:

1.

2.

3.

Provide mobile units or temporary buildings, with water, sanitary facilities, electrical power, and parking facilities, hereinafter called the "Engineer's field office," for use of the Engineer and District representatives in administering the Contract. The Engineer's field office shall be situated in the work area at a location approved by the Engineer, adjacent to the Contractor's field office. The Engineers field office shall be completely furnished and ready for occupancy by the District within 30 days after the effective date of the Notice to Proceed.

The Engineer's field office shall be maintained and serviced by the Contractor, as herein specified, until the final invoice has been submitted by the Contractor and approved by the District, as set forth in General Conditions. The Contractor shall then remove or dispose of the field office off the site at Contractor's expense.

Mobile units shall have all the features specified herein. If the Contractor elects to provide a building or buildings in lieu of mobile units, the buildings shall conform to local building codes and shall have the basic features specified herein, with substitute materials allowable subject to approval of the Engineer.

B. Construction and Materials: Obtain and pay all costs for hauling, building, and connection permits. The field office shall be substantially constructed to provide office space for the construction time period specified in the Contract Specifications. All materials shall be good commercial quality. The amount of space (square feet) required for the Engineer's field office is specified in the Contract Specifications. As a minimum, provide the following features and facilities:

1.

2.

3.

4.

5.

Exterior and interior surfaces, other than factory finished, painted with two coats of an approved paint of a colour or colours approved by the Engineer. No painting will be required on aluminium or stainless steel surfaces.

Interior walls and ceilings panelled with finished plywood or gypsum wallboard of not less than one-half inch thickness, or other suitable material.

Floors covered with resilient flooring material such as vinyl composition tile or sheet vinyl flooring. Floors shall be constructed to withstand a live load of 50 psf.

Two rest rooms minimum, each with lavatory, water closet, mirror, soap holder, toilet paper holder, and paper towel dispenser. Provide one rest room (men's) with urinal. Both rest rooms shall comply with State and Federal accessibility requirements. Water supply may be from a self-contained water storage tank, and water closets may be self-contained, flushing chemical units. Lavatory, urinal, and water closet waste may drain into a self-contained holding tank.

Entrance doors shall comply with applicable State and Federal accessibility requirements.

6.

7.

8.

9.

10.

11.

Lighting of 100 foot-candles minimum at desk height uniformly in all areas except rest rooms. Provide rest rooms with adequate lighting.

Duplex electrical receptacles around interior walls at an approximate spacing of 10 feet on centre.

An electric drinking fountain for furnishing cool water. Water supply for drinking fountain may be bottled drinking water.

An automatically controlled heating/cooling system.

Water, sewer, telephone and facsimile (FAX) service (separate telephone lines), and electrical utility connections as required.

Adequate access from public streets shall be provided to the field office, together with parking spaces as specified in the Contract Specifications. Include spaces for handicapped parking stalls as specified in the Contract Specifications. The access roadway and parking area shall be graded for drainage and surfaced with temporary concrete or asphalt pavement in an approved manner.

C. Furnishings and Equipment: Provide furnishings, equipment, and appliances as specified in the Contract Specifications.

D. Services: Provide maintenance, utility, and janitorial services throughout the specified period as follows:

1.

2.

3.

4.

Repair and daily cleaning of the field office, parking, and access area.

The furnishing of drinking water, paper cups and towels, toilet paper, light bulbs, and such other basic necessities required for the operation and maintenance of the field office. For mobile units with holding tanks, provide periodic removal of waste material and cleaning of holding tank as required. Provide self-contained water storage tank with fresh, potable water as required. Refill when tank is down to 1/4 full.

Provide security measures and area protection equivalent to that used by the Contractor for the Contractor's jobsite shop and field office facilities.

Provide services for utilities indicated in Article 1.05.B.10, including monthly charges, account fees, service charges, connection fees and deposits. Telephone service shall include long distance costs.

6. Contractor's Field Office

A. The Contractor shall provide and maintain, in good condition, on the site or near the site as approved by the Engineer, a temporary field office of suitable size for construction administrative operations and consultations with representatives of the District.

B. The Contractor's field office shall contain a complete set of Contract Documents.

C. The Contractor shall make arrangements and pay all costs, including service and toll charges, until Substantial Completion of the Work, for temporary telephone service in the temporary field office, for use by the Contractor and Subcontractors, for purposes related to the Work.

7. Storage and Parking Areas

A. The Contract Drawings may indicate work areas available to the Contractor for storage of materials and for parking of construction equipment. If so indicated, these areas will be provided to the Contractor for the durations indicated in the Contract Specifications. Additional work and storage space, if required, shall be provided by the Contractor at Contractor's expense.

B. The Contractor shall provide parking facilities for the Contractor's personnel, Subcontractors, supplier's delivery vehicles, and authorized visitors. Off-site parking facilities (if any) shall not impair or interfere with existing community parking and traffic conditions, regulations, and restrictions.

8. Enclosed Storage and Shops

A. The Contractor shall provide all temporary storage and shop rooms that may be required at the jobsite for safe and proper storage of tools, materials, and equipment. Construct such rooms only in locations indicated or as approved by the Architect, and so as not to interfere with the proper installation and completion of other work.

B. Remove such rooms within three days of receipt of notices from the Architect that removal is necessary, and incur all expenses for such removal.

C. Storage of gasoline or similar fuels shall conform to regulations and local fire department regulations and shall be confined within definite boundaries apart from buildings as approved by the Architect and the jurisdictional fire marshal.

9. Protective Barricades and Safety Precautions

A. Construct and maintain barricades, lights, shoring, and warning signs as required by Federal and State safety ordinances and as required to protect the District's property from injury or loss and as necessary for the protection of the public and adjacent properties. Provide walks around obstructions made in a public place for prosecuting the Work. Leave all protection in place and maintain until removal is authorized.

B. Guard and protect all workers, pedestrians, and the public from excavations, construction equipment, obstructions, and other dangers with adequate railings, guard rails, temporary walks, barricades, warning signs, directional signs, overhead protection, planking, decking, danger lights, and other suitable safeguards.

C. Flaggers shall be provided to direct or divert pedestrian or vehicular traffic when necessary as specified in Section 01 57 00 - Temporary Controls.

D. Additional safety requirements are specified in Section 01 35 24 - Construction Safety.

10. Temporary Fencing

A. The Contractor shall furnish, construct, maintain, and later remove temporary fencing around the jobsite perimeter as indicated.

B. Except as otherwise specified herein, temporary fencing shall conform to Specifications Section 32 31 13 - Chain Link Fences and Gates.

C. Used materials may be employed for temporary fencing, provided such used materials are good, sound, and are suitable for the purpose intended.

D. Fencing materials may be commercial quality, provided the dimensions and sizes of said materials are equal to, or greater than, the dimensions and sizes indicated in Specifications Section 32 31 13 - Chain Link Fences and Gates. Additional fencing options include the following:

1.

2.

3.

4.

Posts may be either metal or wood.

Galvanizing and painting of steel items will not be required.

Treating wood with wood preservatives will not be required.

Concrete footings for metal posts will not be required, except where portable footings are required for temporary anchorage of posts.

E. Temporary fencing that is damaged from any cause during the progress of the Work shall be repaired or replaced by the Contractor at no additional cost to the District.

F. When no longer required for the Work, temporary fencing shall be removed. Removed fencing and related materials shall become the property of the Contractor and shall be removed from the jobsite, except as otherwise provided herein.

11. Security

G. Holes caused by the removal of temporary fences shall be properly filled to match adjacent surfaces.

A. The Contractor shall provide for security of the Work and the jobsite until final inspection and Acceptance of the Work. Storage areas shall be suitably fenced and lighted and routinely patrolled by security guards.

B. The District assumes no responsibility for protection of structures and finished work or for loss of materials and equipment from the time that Contract operations have commenced until Acceptance of the Work.

C. If watchman service is deemed necessary by the Contractor, such protection shall be provided by the Contractor, and all costs therefore shall be paid for by the Contractor.

D. Damaged, lost, or stolen materials and equipment, whether or not stored or already installed, shall be replaced by the Contractor with new specified materials and equipment, including reinstallation where applicable, at no additional cost to the District.

12. Close-out

A. Upon completion of the Work, or prior thereto when required by the Engineer, remove temporary facilities' structures and installations from the District's property.

B. Return exterior areas utilized for temporary facilities to their original, natural state or, when called for on the Contract Documents, complete such areas as indicated.

END OF SECTION

DIVISION ONE - GENERAL REQUIREMENTS 01 57 19 - CONSTRUCTION ENVIRONMENT MANAGEMENT PLAN

PART 1 - GENERAL

1 .1

DESCRIPTION

A. This section specifies the control of environmental pollution and damage that the Contractor must consider for air, water, and land resources. It includes management of visual aesthetics, noise, solid waste, radiant energy, and radioactive materials, as well as other pollutants and resources encountered or generated by the Contractor. The Contractor is obligated to consider specified control measures with the costs included within the various contract items of work.

B. Environmental pollution and damage is defined as the presence of chemical, physical, or biological elements or agents which:

1. Adversely effect human health or welfare,

2. Unfavorably alter ecological balances of importance to human life,

3. Effect other species of importance to humankind, or;

4. Degrade the utility of the environment for aesthetic, cultural, and historical purposes.

C. Definitions of Pollutants:

1. Chemical Waste: Petroleum products, bituminous materials, salts, acids, alkalis, herbicides, pesticides, organic chemicals, and inorganic wastes.

2. Debris: Combustible and noncombustible wastes, such as leaves, tree trimmings, ashes, and waste materials resulting from construction or maintenance and repair work.

3. Sediment: Soil and other debris that has been eroded and transported by runoff water.

4. Solid Waste: Rubbish, debris, garbage, and other discarded solid materials resulting from industrial, commercial, and agricultural operations and from community activities.

5. Surface Discharge: The term "Surface Discharge" implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers, creeks, and/or "water of the United States" and would require a permit to discharge water from the governing agency.

6. Rubbish: Combustible and noncombustible wastes such as paper, boxes, glass and crockery, metal and lumber scrap, tin cans, and bones.

7. Sanitary Wastes:

a. Sewage: Domestic sanitary sewage and human and animal waste.

b. Garbage: Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.

1 .2

1 .3

1 .4

1 .5

REGULATORY REQUIREMENT

A. CEMP must be developed in accordance with the requirements of the technical Guidance Document for Construction Environmental Management Plan (CEMP) of the Environmental Agency of Abu Dhabi ver. 2010 or any available update. Any discrepancy from the specifications and the EAD requirements will be discussed with the Project Engineer.

QUALITY CONTROL

A. Establish and maintain quality control for the environmental protection of all items set forth herein.

B. Record on daily reports any problems in complying with laws, regulations, and ordinances. Note any corrective action taken.

REFERENCE

A. The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

B. U.S. National Archives and Records Administration (NARA)

SUBMITTALS

A. In accordance with Section, 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES, furnish the following:

1. Environmental Protection Plan: After the contract is awarded and prior to the commencement of the work, the Contractor shall meet with the Resident Engineer to discuss the proposed Environmental Protection Plan and to develop mutual understanding relative to details of environmental protection. Not more than 20 days after the meeting, the Contractor shall prepare and submit to the Resident Engineer and the Contracting Officer for approval, a written and/or graphic Environmental Protection Plan including, but not limited to, the following:

a. Name(s) of person(s) within the Contractor's organization who is (are) responsible for ensuring adherence to the Environmental Protection Plan.

b. Name(s) and qualifications of person(s) responsible for manifesting hazardous waste to be removed from the site.

c. Name(s) and qualifications of person(s) responsible for training the Contractor's environmental protection personnel.

d. Description of the Contractor's environmental protection personnel training program.

e. A list of Federal, State, and local laws, regulations, and permits concerning environmental protection, pollution control, noise control and abatement that are applicable to the Contractor's proposed operations and the requirements imposed by those laws, regulations, and permits.

f. Methods for protection of features to be preserved within authorized work areas including trees, shrubs, vines, grasses, ground cover, landscape features, air and water quality, fish and wildlife, soil, historical, and archeological and cultural resources.

g. Procedures to provide the environmental protection that comply with the applicable laws and regulations. Describe the procedures to correct pollution of the environment due to accident, natural causes, or failure to follow the procedures as described in the Environmental Protection Plan.

h. Permits, licenses, and the location of the solid waste disposal area.

i.

j.

Drawings showing locations of any proposed temporary excavations or embankments for haul roads, // stream crossings, // material storage areas, structures, sanitary facilities, and stockpiles of excess or spoil materials. Include as part of an Erosion Control Plan approved by the District Office of the U.S. Soil Conservation Service and the Department of Veterans Affairs.

Environmental Monitoring Plans for the job site including land, water, air, and noise.

k. Work Area Plan showing the proposed activity in each portion of the area and identifying the areas of limited use or nonuse. Plan should include measures for marking the limits of use areas. This plan may be incorporated within the Erosion Control Plan.

B. Approval of the Contractor's Environmental Protection Plan will not relieve the Contractor of responsibility for adequate and continued control of pollutants and other environmental protection measures.

1 .6

PROTECTION OF ENVIRONMENTAL RESOURCES

A. Protect environmental resources within the project boundaries and those affected outside the limits of permanent work during the entire period of this contract. Confine activities to areas defined by the specifications and drawings.

B. Protection of Land Resources: Prior to construction, identify all land resources to be preserved within the work area. Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, top soil, and land forms without permission from the Resident Engineer. Do not fasten or attach ropes, cables, or guys to trees for anchorage unless specifically authorized, or where special emergency use is permitted.

1. Work Area Limits: Prior to any construction, mark the areas that require work to be performed under this contract. Mark or fence isolated areas within the general work area that are to be saved and protected. Protect monuments, works of art, and markers before construction operations begin. Convey to all personnel the purpose of marking and protecting all necessary objects.

2. Protection of Landscape: Protect trees, shrubs, vines, grasses, land forms, and other landscape features shown on the drawings to be preserved by marking, fencing, or using any other approved techniques.

a. Box and protect from damage existing trees and shrubs to remain on the construction site.

b. Immediately repair all damage to existing trees and shrubs by trimming, cleaning, and painting with antiseptic tree paint.

c. Do not store building materials or perform construction activities closer to existing trees or shrubs than the farthest extension of their limbs.

3. Reduction of Exposure of Unprotected Erodible Soils: Plan and conduct earthwork to minimize the duration of exposure of unprotected soils. Clear areas in reasonably sized increments only as needed to use. Form earthwork to final grade as shown. Immediately protect side slopes and back slopes upon completion of rough grading.

4. Temporary Protection of Disturbed Areas: Construct diversion ditches, benches, and berms to retard and divert runoff from the construction site to protected drainage areas approved under paragraph 208 of the Clean Water Act.

a. Sediment Basins: Trap sediment from construction areas in temporary or permanent sediment basins that accommodate the runoff of a local storm. After each storm, pump the basins dry and remove the accumulated sediment. Control overflow/drainage with paved weirs or by vertical overflow pipes, draining from the surface.

b. Reuse or conserve the collected topsoil sediment as directed by the Resident Engineer. Topsoil use and requirements are specified in Section 31 20 00, EARTH MOVING.

c. Institute effluent quality monitoring programs as required by Federal, State, and local environmental agencies.

5. Erosion and Sedimentation Control Devices: The erosion and sediment controls selected and maintained by the Contractor shall be such that water quality standards are not violated as a result of the Contractor's activities. Construct or install all temporary and permanent erosion and sedimentation control features // shown. // on the Environmental Protection Plan. Maintain temporary erosion and sediment control measures such as berms, dikes, drains, sedimentation basins, grassing, and mulching, until permanent drainage and erosion control facilities are completed and operative.

6. Manage borrow areas on and off Government property to minimize erosion and to prevent sediment from entering nearby water courses or lakes.

7. Manage and control spoil areas on and off Government property to limit spoil to areas // shown on the Environmental Protection Plan and prevent erosion of soil or sediment from entering nearby water courses or lakes.

8. Protect adjacent areas from despoilment by temporary excavations and embankments.

9. Handle and dispose of solid wastes in such a manner that will prevent contamination of the environment. Place solid wastes (excluding clearing debris) in containers that are emptied on a regular schedule.

Transport all solid waste off Government property and dispose of waste in compliance with Federal, State, and local requirements.

10. Store chemical waste away from the work areas in corrosion resistant containers and dispose of waste in accordance with Federal, State, and local regulations.

11. Handle discarded materials other than those included in the solid waste category as directed by the Resident Engineer.

C. Protection of Water Resources: Keep construction activities under surveillance, management, and control to avoid pollution of surface and ground waters and sewer systems. Implement management techniques to control water pollution by the listed construction activities that are included in this contract.

1. Washing and Curing Water: Do not allow wastewater directly derived from construction activities to enter water areas. Collect and place wastewater in retention ponds allowing the suspended material to settle, the pollutants to separate, or the water to evaporate.

2. Control movement of materials and equipment at stream crossings during construction to prevent violation of water pollution control standards of the Federal, State, or local government.

3. Monitor water areas affected by construction.

D. Protection of Fish and Wildlife Resources: Keep construction activities under surveillance, management, and control to minimize interference with, disturbance of, or damage to fish and wildlife. Prior to beginning construction operations, list species that require specific attention along with measures for their protection.

E. Protection of Air Resources: Keep construction activities under surveillance, management, and control to minimize pollution of air resources. Burning is not permitted on the job site. Keep activities, equipment, processes, and work operated or performed, in strict accordance with the State of insert Name of State and title of State Air Pollution Statue, Rule, or Regulation and Federal emission and performance laws and standards. Maintain ambient air quality standards set by the Environmental Protection Agency, for those construction operations and activities specified.

1. Particulates: Control dust particles, aerosols, and gaseous by-products from all construction activities, processing, and preparation of materials (such as from asphaltic batch plants) at all times, including weekends, holidays, and hours when work is not in progress.

2. Particulates Control: Maintain all excavations, stockpiles, haul roads, permanent and temporary access roads, plant sites, spoil areas, borrow areas, and all other work areas within or outside the project boundaries free from particulates which would cause a hazard or a nuisance. Sprinklering, chemical treatment of an approved type, light bituminous treatment, baghouse, scrubbers, electrostatic precipitators, or other methods are permitted to control particulates in the work area.

3. Hydrocarbons and Carbon Monoxide: Control monoxide emissions from equipment to Federal and State allowable limits.

4. Odors: Control odors of construction activities and prevent obnoxious odors from occurring.

F. Reduction of Noise: Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the Resident Engineer. Maintain noise-produced work at or below the decibel levels and within the time periods specified.

1. Perform construction activities involving repetitive, high-level impact noise only between 8:00 am and 6:00 pm unless otherwise permitted by local ordinance or the Resident Engineer. Repetitive impact noise on the property shall not exceed the following dB limitations:

Time Duration of Impact Noise

More than 12 minutes in any hour

Less than 30 seconds of any hour

Less than three minutes of any hour

Less than 12 minutes of any hour

Sound Level in dB

70

85

80

75

2. Provide sound-deadening devices on equipment and take noise abatement measures that are necessary to comply with the requirements of this contract, consisting of, but not limited to, the following:

a. Maintain maximum permissible construction equipment noise levels at 15 m (50 feet) (dBA):

EARTHMOVING

FRONT LOADERS

BACKHOES

DOZERS

TRACTORS

SCAPERS

GRADERS

TRUCKS

PAVERS, STATIONARY

PUMPS

GENERATORS

75

75

75

75

80

75

75

80

75

75

MATERIALS HANDLING

CONCRETE MIXERS

CONCRETE PUMPS

CRANES

DERRICKS IMPACT

PILE DRIVERS

JACK HAMMERS

ROCK DRILLS

PNEUMATIC TOOLS

BLASTING

SAWS

75

75

75

75

95

75

80

80

//--//

75

COMPRESSORS 75 VIBRATORS 75

b. Use shields or other physical barriers to restrict noise transmission.

c. Provide soundproof housings or enclosures for noise-producing machinery.

d. Use efficient silencers on equipment air intakes.

e. Use efficient intake and exhaust mufflers on internal combustion engines that are maintained so equipment performs below noise levels specified.

f. Line hoppers and storage bins with sound deadening material.

g. Conduct truck loading, unloading, and hauling operations so that noise is kept to a minimum.

3. Measure sound level for noise exposure due to the construction at least once every five successive working days while work is being performed above 55 dB(A) noise level. Measure noise exposure at the property line or 15 m (50 feet) from the noise source, whichever is greater. Measure the sound levels on the A weighing network of a General Purpose sound level meter at slow response. To minimize the effect of reflective sound waves at buildings, take measurements at 900 to 1800 mm (three to six feet) in front of any building face. Submit the recorded information to the Resident Engineer noting any problems and the alternatives for mitigating actions.

G. Restoration of Damaged Property: If any direct or indirect damage is done to public or private property resulting from any act, omission, neglect, or misconduct, the Contractor shall restore the damaged property to a condition equal to that existing before the damage at no additional cost to the Government. Repair, rebuild, or restore property as directed or make good such damage in an acceptable manner.

H. Final Clean-up: On completion of project and after removal of all debris, rubbish, and temporary construction, Contractor shall leave the construction area in a clean condition satisfactory to the Resident Engineer. Cleaning shall include off the station disposal of all items and materials not required to be salvaged, as well as all debris and rubbish resulting from demolition and new work operations.

PART 2 - PRODUCTS

2 .1 SILT FENCE

A. Geotextile fabric and support system complying with the requirements, except geotextile fabric shall have a maximum flow rate of 10 gal/minute/sq ft at 50 mm constant head as determined by multiplying permittivity in 1/second as determined by ASTM D4491 by a conversion factor of 74.

PART 3 - EXECUTION

3 .1

3 .2

EROSION CONTROL

A. Applicable Standards: Unless otherwise shown or specified, erosion control measures shall comply with:

1. "Wisconsin Pollutant Discharge Elimination System (WPDES) General Permit" for storm water discharges associated with construction activities.

2. WDNR "Stormwater Management Technical Standards" (available on the WDNR website)

B. General: Maintain erosion control measures to protect the project site and prevent sediment pollution of adjacent water courses and properties. At a minimum, provide erosion control measures as indicated on Drawings.

C. Time Period: Install erosion control measures prior to start of construction and maintain them until final completion of work. Unless otherwise instructed, remove temporary erosion control measures prior to final application for payment.

D. Stripping: Strive to limit stripping of sod and vegetation to a period that will expose bare soil to the least possibility of erosion that construction requirements will allow.

E. Storm Drain Protection: Protect storm drain inlets by using inlet protection of the type shown on Drawings. If not shown, use inlet protection fabric, silt fence barriers, erosion bale barriers, or equivalent.

F. Tracking Pads: Prevent tracking of soils and sediments onto public and private streets by constructing temporary graveled access roads and parking areas as needed at the construction site. Remove at the end of each work day soils and sediment reaching public and private streets not part of the construction site.

G. Re-establishment of Vegetation: Re-establish temporary or permanent vegetation on disturbed areas within the time limits allowed by applicable standards.

EROSION CONTROL MONITORING AND REPORTING

A. Contractor shall conduct the following inspections:

1. Weekly inspections of implemented erosion and sediment controls.

2. Inspections of erosion and sediment controls within 24 hours after a precipitation event that produces 0.5 in. of rain or more during a 24 hour period.

B. Contractor shall prepare weekly written reports of all inspections that include:

1. Date, time, and exact place of inspection.

2. Name of individual who performed inspection.

3. An assessment of condition of erosion and sediment controls.

4. A description of any erosion and sediment control implementation and maintenance performed.

5. A description of the present phase of construction at site.

3 .3

3 .4

3 .5

DUST CONTROL

A. Minimize dispersion of dust from construction operations by application of water or other dust control materials. Controls shall confine dust and dirt within the immediate area of project. Masonry and debris shall be thoroughly soaked during demolition and loading operations.

NOISE CONTROL

A. Provide noise control measures to limit the amount of noise and prevent nuisance. Properly equip all equipment with mufflers. Limit construction activities generating significant noise to normal working hours.

HAZARDOUS ENVIRONMENTAL CONDITIONS

A. If underground petroleum storage tanks, petroleum contaminated soils, or other hazardous environmental conditions are encountered, and are not identified to be part of the work, Contractor shall immediately stop all work in connection with the hazardous condition. (See the General Conditions of the Contract for specific procedures that may apply.)

END OF SECTION

DIVISION ONE - GENERAL REQUIREMENTS 01 74 00 - CLEANING & WASTE MANAGEMENT

PART 1 - GENERAL

1 .1 SUMMARY

A. CONSTRUCTION & DEMOLITION WASTE FROM THE LANDFILL

1.

2.

3.

4. 5. 6. 7.

Waste Management Goals: a minimum of 50% of the total project waste should be diverted from landfill, in order of preference 1) weight, 2) volume, whichever is most feasible to measure. Provide contract documents, including a waste management plan, to show evidence of recycling, and reuse of recovered materials. Inform Owner and architect where Construction and Demolition (C&D) Waste Management requirements could detrimentally impact C&D schedule. Provide separate itemization of cost related to C&D Waste Management. Effect optimum management of solid wastes via a materials management hierarchy. The materials management hierarchy shall be: reduce, reuse, and recycle. Prevent environmental pollution and damage.

B.

REGULATORY REQUIREMENT 1. Comply with ESTIDAMA requirements intended to achieve sustainability, measured and documented in accordance with Division 01 requirements, fully coordinated with requirements within individual specification sections.de external architectural woodwork in accordance with requirements of the Contract Documents.

1 .2 REFERENCES

A.

B.

C.

CONSTRUCTION & DEMOLITION WASTE MANAGEMENT PLAN GUIDELINES

ESTIDAMA VILLA BUILDING RATING SYSTEM (PVRS), Design & Construction V1.0 April 2010

CURRENT LAW AND LEGISLATION

1. Law No. (21) of 2005 for Waste Management in the Emirate of Abu Dhabi. 2. Abu Dhabi Environment Health and safety Management System Regulatory Framework (EHSMS) - AD EHMS Co16 - Waste Management V1.2 July 2009. 3. Federal Law No. (24) Of 1999 for the Protection and Development of the Environment. 4. Executive order of Federal Law No. (24) for Regulation for Handling Hazardous Materials, Hazardous Wastes and Medical Wastes. 5. Law No. (16) of 2005 Pertaining to the Reorganization of the Abu Dhabi Environment Agency. 6. Federal Law No. (23) of the year 1999 regarding the Exploitation, Protection and Development of the Living Aquatic Resources In the waters of the state of the United Arab Emirates. 7. Federal Law No. (1) 2002 Regarding the Regulation and Control of the Use of Radiation Sources and Protection Against Their Hazards.

1 .3 DEFINITIONS

A. Contractor shall appoint a Waste Management Contractor approved by NADAFA & the Centre of Waste Management of Abu Dhabi as soon appointed.

B. Inert Fill - A permitted facility that accepts inert waste such as asphalt and concrete exclusively.

C. Class III Landfill - A landfill that accepts non-hazardous waste such as household, commercial, and industrial waste, including construction, remodelling, repair, and demolition operations.

D. Construction and Demolition Waste - Including solid wastes, such as building materials, packaging, rubbish, debris, and rubble resulting from construction, remodeling, repair, and demolition operations. 1. Rubbish: Including both combustible and noncombustible wastes, such as paper, boxes, glass, crockery, metal and lumber scrap, tin cans, and bones. 2. Debris: Including both combustible and noncombustible wastes, such as leaves and tree trimmings that result from construction or maintenance and repair work.

E. Target estimated construction and demolition waste salvaged/recycled is 80%.

F. Deconstruction - The process of removing existing building materials from renovation and demolition projects for the purposes of reuse, and recycling, in a efficient and safe manner possible.

G. Divert - Using material for any purpose other than disposal in a landfill.

H. Waste Materials - Large and small pieces of listed materials which are excess to contract requirements and generally include materials to be recycled and/or recovered from existing construction and items of trimmings, cuttings, and damaged goods resulting from new installations, which can be effectively used in the Work.

I. Reuse - Using a material or product that is recovered from construction, renovation, or demolition activities.

J. Recycling - The process of collecting and preparing recyclable materials in their original form or in manufacturing processes that do not cause the destruction/contamination of recyclable materials in a manner that precludes further use.

K. Recovery - Any process that reclaims materials, substances, energy, or other products contained within or derived from waste on-site. It includes waste-to-energy, composting, and other processes.

L. Sources Separation - Sorting the recovered materials into specific material types with no or a minimum amount of contamination on site.

M. Time-Based Separation - Collecting waste during each phase of construction or deconstruction which results in primarily one major type of recovered material. The material is removed before it becomes mixed with the material from the next phase of construction.

N. Commingled or Off-site Separation - Collecting all material types into a single bin or mixed collection system and separating the waste materials into recyclable material types in an off-site facility.

1 .4 SUBMITTALS

A. C&D Waste Management Plan Before the start of demolition, submit a C&D waste management plan to the Owner and the architect for approval and it shall include the following:

1. Indicate how the Contractor proposes to recover at least 75% of the C&D wastes for reuse and recycling. 2. The C&D Waste Management Plan should coordinate the recovery effort with the construction, and renovation / demolition schedule. 3. Indicate compliance with section 1.5 QUALITY ASSURANCE. 4. Include a list of reuse facilities, recycling facilities and processing facilities that will be receiving the recovered materials (including take back by Owner or on-site auctions.) 5. If some of the materials will be donated or sold on-site auctions, describe the process and identify the organizations that may receive the materials. 6. Identify materials that are not recyclable or not recovered which will be disposed of in a landfill (or other means acceptable by the State of California and local ordinance and regulations) and explain why the materials are not recovered. 7. List the permitted landfill, or other permitted disposal facilities, that will be accepting the disposed waste materials. 8. Indicate instances or situations where compliance with the requirements of this specification do not apply or do not appear to be possible. 9. Identify each type of waste material to be reused or recycled and estimate the amount, by weight. 10. Provide estimate of time requirements for demolition and for the removal of valuable reusable items and materials. 11. Prepare building engineering survey and worker safety plan, assessment of building condition and all potential hazards. 12. Provide a C&D site management plan. 13. Provide final accounting of disposition of recovered materials upon completion of project for final payments.

B. C&D Waste management Summary Reports Provide the C&D Quality Manager with delivery receipts for the recovered materials and waste materials sent to the permitted recycling facilities, processing facilities, or landfill with the following information:

1. 2. 3. 4. 5. 6. 7.

Name of firm accepting the recovered materials or waste materials Specify type of facility (e.g. retail facility, recycler, processor, Class III landfill, MRF) Location of the facility Type of materials Net weights (or volume) of each type of material Date of delivery Value of the materials or tipping fee paid

1 .5 RECYCLING PROGRAM

A.

B.

The recycling program could utilize one or a combination of any of the following common waste diversion strategies: 1. Sources Separation 2. Time-Based Separation 3. Commingled or Off-site Separation 4. Back haul of packaging 5. On-site sales auctions and removal.

Waste Material management hierarchy can be viewed as: reuse on-site, recycle on-site, reuse off-site, and recycle off-site.

C.

D.

Other innovative approaches to achieve the minimum diversion rate are encouraged and should be specified and described in the C&D Waste Management Plan.

Minimum diversion rate may be achieved by recovering and recycling the following materials: 1. Asphalt 2. Concrete and concrete blocks 3. Brick, tile and masonry materials 4. Ferrous metal 5. Non-ferrous metals: copper, aluminum etc 6. Untreated lumber 7. Plywood, OSB and particle board 8. Gypsum wallboard scrap 9. Paper and cardboard 10. Beverage containers 11. Insulation 12. Rigid foam 13. Glass 14. Carpet and pad 15. Trees and shrubs 16. Soil 17. Plumbing fixtures 18. Windows 19. Doors 20. Cabinets 21. Architectural fixtures 22. Millwork, paneling and other similar interior finishes 23. Electric fixtures, motors, switch gear and other similar equipment 24. HVAC equipment, duck work, control systems, switches and other similar equipment 25. Others as appropriate

1 .6 QUALITY ASSURANCE

A.

B.

C.

Regulatory Requirement Comply with applicable requirements of the State of California, local ordinances and regulations concerning management of construction, clearing, and inert materials.

Disposal Site, Recyclers and waste Materials Processors Use only facilities properly permitted by the State of California, and/or by local authorities where applicable.

Pre-C&D Waste Management Meeting 1. Prior to beginning work at the site, schedule and conduct a meeting to review the C&D Waste Management Plan and discuss procedures, schedules, coordination and specific requirements for waste materials recycling and disposal. Discuss coordination and interface between Contractor, sub-contractors, architect, engineers, project manager, Owner, and other C&D activities. Identify and resolve problems of compliance with requirements. Record minutes of the meeting, identifying conclusions reached and matters requiring further resolution. Maintain waste management as an agenda item at future construction meetings. 2. Attendees: Contractor and related contractor personnel associated with work of this section, including personnel in charge of the waste management program; C&D Quality Manager; architect; engineers; material and equipment suppliers where appropriate; and such additional Owner personnel as Owner deems appropriate.

3. Plan Revision: Make revisions to C&D Waste Management Plan agreed upon during the meeting and incorporate resolutions agreed to be made subsequent to the meeting. Submit revised plan to architect or the Owner personnel as Owner deems appropriate for approval.

D.

E.

F.

G.

H.

Implementation 1. Designate an on-site party responsible for instructing workers and implementing the C&D Waste Management Plan. 2. Distribute copies of C&D Waste Management Plan to job site foreman and each subcontractor. 3. Include waste management and recycling in worker orientation. 4. Provide on-site instruction on appropriate separation, handling, recycling, and recovery methods to be used by all parties at the appropriate stages of the work at the site. 5. Also include discussion of waste management and recycling in regular job meeting and job safety meetings conducted during the course of work at the site.

The Contractor will be responsible for ensuring that the appropriate governmental entities are notified of the work.

Remove and relocate reusable materials to be reinstalled or retained in a manner to prevent damage or contamination.

Conduct construction and demolition in such a manner to minimize damage to trees, plants and natural landscape environment.

Arrange for adequate collection, and transportation to deliver the recovered materials to the approved recycling centre or processing facility. Maintain records accessible to the architect or C&D Quality Manager for verification of diversion of recovered waste materials.

1 .7 DELIVERY, STORAGE AND HANDLING

A.

B.

Site Storage 1. Remove materials for recycling and recovery from the work locations to approved containers or storage area as required. Failure to remove waste or recovered materials will be considered cause for withholding payment and termination of Contract. 2. Position containers for recyclable and recoverable waste materials at a designated location on the Project Site. If materials are sorted on site, also provide a sorting area and necessary storage containers. 3. Change-out loaded containers for empty containers, as demand requires. 4. If recovered materials are stored on-site for project duration provide adequate security from pilferage.

Handling 1. Deposit indicated recyclable, and recoverable materials in storage areas or containers in a clean (no mud, adhesive, solvents, petroleum contamination), debris-free condition. Do not deposit contaminated materials into the containers until such time as such materials have been cleaned. 2. Insure all recovered materials are made safe for handling and storage. 3. If the contamination chemically combines with the material so that it cannot be cleaned, do not deposit into the recycle containers. In such case, request resolution by the C&D Quality Manager for disposal of the contaminated material. Directions from the C&D Quality Manager do not relieve the Contractor of responsibility for compliance with all legal and regulatory requirements for disposal, nor shall such directions cause a request for modification of the Contract. levelled bearers in a manner that prevents sagging and permits free air circulation.

1 .8 PROJECT CONDITIONS

A.

B.

Environmental Requirement 1. Transport recyclable and recoverable waste materials from the Work Area to containers and carefully deposit in the containers without excess noise and interference with other activities, to minimize noise and dust. 2. The Contractor shall ensure adequate erosion control and storm water control, if required, to prevent or minimize the negative impact to its surrounding environment. 3. Provide measures to insure the containment of lead-based paint and dust, nails, asbestos-based products and any biological contaminants that may affect environmental health and safety conditions.

Site Condition 1. Signs and instructions should be clear, and easy to understand. All recycling containers should be clearly labelled and lists of acceptable and unacceptable materials will be posted throughout the site. Whenever possible, they should be in multiple-languages, especially in Spanish, and in graphic symbols. 2. The Contractor shall ensure the safety of all personnel involved in the C&D process. 3. A C&D site management plan shall be created including: work areas, materials processing areas, materials storage and disposal areas, worker hand-washing and changing stations, first aid and medical information.

PART 2 - PRODUCTS

2 .1 SALVAGED AND REUSE MATERIALS: N/A

2 .2 RECYCLED MATERIALS

A.

The following materials are collected for recycling:

1. Asphalt 2. Concrete and concrete blocks 3. Tile and masonry materials 4. Ferrous metal 5. Non-ferrous metals: copper, aluminum etc 6. Untreated lumber 7. Plywood, OSB and particle board 8. Gypsum wallboard scrap 9. Paper and cardboard 10. Beverage containers 11. Insulation 12. Rigid foam 13. Glass 14. Carpet and pad 15. Trees and shrubs 16. Soil

PART 3 - EXECUTION

N/A

END OF SECTION

SECTION - 01 81 13

SUSTAINABLE DESIGN REQUIREMENT

Table of Contents

1. General............................................................................................................................................ 2 2. Products .......................................................................................................................................... 4 3. Execution......................................................................................................................................... 5

List of Appendices

Appendix 1: Electronic copy of Estidama Pearl Building Rating System (PBRS): Design and Construction, version 1.0, April 2010, by Abu Dhabi Urban Planning Council (UPC).

Appendix 2: Design Pearl Rating Credit Points Summary

Appendix 3: Electronic copy of Full Pearl Design Rating Documentation approved by UPC

Appendix 4: Commissioning Plan

Appendix 5: Preliminary Occupant Handbook

Appendix 6: Preliminary Construction and Demolition Waste Management Plan

SECTION - 01 81 13 SUSTAINABLE DESIGN REQUIREMENT

1. General

1.1. Summary A. This Section describes general requirements and procedures to comply with Estidama Pearl Rating (2 Pearls) B. General: Read this Section in conjunction with other related specification Sections, the Design Drawings, and Bill of Quantities. C. Related Documentation: -Appendix 1: Electronic copy of Estidama Pearl Building Rating System (PBRS): Design and Construction, version 1.0, April 2010, by Abu Dhabi Urban Planning Council (UPC). -Appendix 2: Design Pearl Rating Credit Points Summary -Appendix 3: Electronic copy of Full Pearl Design Rating Documentation approved by UPC. -Appendix 4: Commissioning Plan -Appendix 5: Preliminary Occupant Handbook -Appendix 6: Preliminary Construction and Demolition Waste Management Plan

1.2. Submittals A. ESTIDAMA submittals are in addition to other submittals. If submitted item is identical to that submitted to comply with other requirements, submit duplicate copies as a separate submittal to verify compliance with indicated ESTIDAMA requirements. B. ESTIDAMA Action Plans: Provide preliminary submittals within 14 days of date established for the Notice of Award indicating how the requirements covered in this Section and its related Sections will be met. C. ESTIDAMA Progress Reports: On Bi-weekly basis, submit reports comparing actual construction and purchasing activities with ESTIDAMA action plans for the following: D. Waste reduction progress reports complying with the CDWMP. E. Regional material requirement as per the requirement stated herein F. Recycled Content requirement as per the requirement stated herein G. Estidama Documentation: H. Submit all Pearl Construction Rating stage documentation required for the UPC submission in order to achieve 2 Pearl Certification as per the Pearl Building Rating System: Design and Construction document for submittal requirements.

I. All documentation shall be based on PBRS Ver. 1.0 J. All forms/ templates, shall be approved by the PQP and the engineer.

1.3. Definitions BLB: Building Log Book

CDWMP: Construction and Demolition Waste Management Plan

CIBSE: Chartered Institution of Building Services Engineers

GWP: Global Warming Potential

HVAC: Heating, Ventilation, and Air Conditioning

IAQ: Indoor Air Quality.

km: Kilometer.

Light Pollution: Light that extends beyond its source such that the additional light is wasted in an unwanted area or in an area where it inhibits view of the night sky

MSDS: Material Safety Data Sheet

ODP: Ozone Depleting Potential

PBRS: Estidama Pearl Building Rating System

Post-Consumer Recycled Content: The percentage by weight of constituent materials that have been recovered or otherwise diverted from the solid-waste stream after consumer use

Pre-Consumer Recycled Content: Materials that have been recovered or otherwise diverted from the solid-waste stream during the manufacturing process.

ppm: parts per million.

Recycled Content Materials: Products that contain pre-consumer or post-consumer materials as all or part of their feedstock.

Recycled Steel: Steel product from companies certified under CARES Sustainable Reinforcing Steel Appendix 01 "Production of continuously cast steel billets" and "Production of hot rolled steel bar and coil for the reinforcement of concrete" will count as recycled

Regional Materials: Materials that are extracted, harvested, recovered, and manufactured within a radius of 500km

Sealant: Any material that fills and seals gaps between other materials

SMACNA: Sheet Metal and Air Conditioning Contractor's National Association

SRI: Solar Reflectance Index

UPC: Abu Dhabi Urban Planning Council

VOC: Volatile Organic Compound.

WB: Water Based.

SB: Solvent Based

1.4. Quality Assurance: A. Pearl Qualified Professional (PQP): Engage a Pearl Qualified Professional (PQP) who has sufficient experience of sustainable and green buildings design and construction, sufficient awareness of International Organization for Standardization (ISO) documentation and who is aware of the Pearl Building Rating System - Design and Construction Version 1.0, April 2010 Issue. B. The PQP may be any of the construction team members such as Project manager, Construction Manager, Site Engineer, or HSE Officer. C. The PQP should review all documents produced during the Pearl Design Rating Stage, all approved management plans should be implemented during the project construction. Plans, handbooks and guides should be updated where required. D. The PQP needs to manage the implementation of credits' requirements, and handle the documentation process and ensure the compilation of all documents required for the Pearl Construction Rating Submission. 2. Products A. PBRS Credit Summary: Generally, the project shall comply with the requirements of all credits fulfilled during design stage as clarified in the "Credit Points Summary" document in Appendix 1.

3. Execution This section clarifies requirements of certain credits to be fulfilled by the contractor; however for full documentation requirements the PQP shall refer to the PBRS guide, shown in Appendices 1, 2 and 3. Generally, the project shall comply with the requirements of the following credits: IDP-R3: Basic Commissioning: The Contractor has to employ an independent commissioning contractor to commission the installed systems and develop a Building Log Book (BLB) in accordance to CIBSE TM31 or similar guide (Any other guide needs to be approved by the Engineer). The commissioning should be executed as per the commissioning plan approved as part of the design rating. The Commissioning Contractor shall provide Commissioning results demonstrating compliance with all associated credits (including but not limited to LBi-R1: Healthy Ventilation Delivery); the commissioning process shall cover - at minimum - the following systems: -HVAC; -On-site energy generation (including co-generation), if applicable; -Building Management System; -Lighting and lighting controls; -Domestic hot and cold water systems; -On-site water treatment systems including swimming pools (if applicable); and -Automated control features such as blinds (If applicable). IDP-6: Sustainability Communication: Update the Preliminary Occupant Handbook document which is approved during the Pearl Design Rating Stage. The Occupant Handbook should include a list of information that will enable building occupants to appreciate, understand and contribute to responsible resource use in the building. The list below indicates the minimum requirements to be included in the Occupant Handbook: -The building's energy and water efficiency measures and how occupant behaviour affects the building performance as follows: -This should give owners and occupiers information on energy-efficient features and strategies relating to the building, and also provide an overview of the reasons for their use (e.g. economic and environmental savings). -Information could include: information on the operation of innovative features such as lighting control systems etc., and guidance on the impacts of strategies covering window opening and the use of blinds, lighting and heating controls as well as impact of occupant behaviour. -Details of water saving features and their use and benefits, e.g. aerating taps, low flush WCs, water monitoring, metering etc. as well as impact of occupant behaviour on water consumption.

-Information on the building's indoor environmental quality and how it is measured, monitored and managed (e.g. thermostat location and use); -Information on materials used in the building, including environmental and social benefits, as appropriate; -Waste and recycling policies and information such as location, sorting requirements (if any) and the use of green waste (if applicable); -Locations of nearby public transport to include maps and time tables, shuttle service, carpooling and on-site bicycle facilities; and -Tenant fit-out considerations, such as low-energy lighting installations, to maximize the building performance potential and minimize environmental impacts. LBo-R3: Outdoor Thermal Comfort Strategy & LBo-1: Improved Outdoor Thermal Comfort Strategy: Improved Outdoor Thermal Comfort: Where cover is provided by structures such as canopies or other architectural elements, the outer surface of the shading element must have a minimum SRI of 29 as per the following table, Contractor shall submit Evidence that all purchased and installed covers have compliant outer surface SRIs.

Space Type

Exterior Surface Parking with more than 10 spaces

Public Open Spaces

Primary Pedestrian Walkways (based on 1.8m width within the through zone)

Secondary Pedestrian Walkways (based on 1.8m width within the through zone)

Cycle Tracks

Shading Element

PVC white colour with SRI of 109

n/a

Aluminium - White Colour (Bone White)

Aluminium - White Colour (Bone White)

n/a

LBo-8: Preferred Car Parking Spaces: The car parking includes 3Nos. car park spaces identified priority vehicles parking, 2Nos. parking spaces shall have an industrial socket/isolator convenient for plugging the charge cord for battery charging for vehicles as per specification section 16442.

LBo-10: Light Pollution Reduction: No incandescent lamps shall be installed within the project, and all internal and permanently installed fluorescent lighting installations shall incorporate high frequency electronic ballasts. All rooms intended for individual occupancy shall be equipped with occupancy sensors. For full details refer to specification section 16511. LBi-2.1: Materials Emissions Adhesives & Sealants: Contractor must submit Product Data to confirm use of low emission adhesives and sealants to encourage the desirability of spaces in relation to improved occupant health and demonstrate that a minimum of 95% (by weight) of all adhesives and sealants used on the building interior must not exceed the prescribed VOC limits in South Coast Air Quality Management District Rule 1168, some of which are reproduced in the table below. -For sealants and sealant primers used inside the weatherproofing system, documentation including printed statement of VOC content. The VOC limits of the remaining non compliant adhesives and sealants must be no more than 50% higher than values listed for each product type. -Reference: South Coast Air Quality Management District (California, U.S.) - Rule 1168 "Adhesive and Sealant Applications", (www.aqmd.gov).

Maximum grams of VOC per litre of adhesive or #Product type sealant, less water and exempt compounds

1Indoor carpet adhesive 50

2Carpet pad adhesive 50

3Wood flooring adhesive 100

4Rubber flooring adhesive 60

5Sub-floor adhesive 50

6Ceramic tile adhesive 65

7Cove base adhesive 50

8Plasterboard and wall panel adhesive 50

9Multipurpose construction adhesive 70

10 Structural glazing adhesive 100

11 Architectural sealants 250

LBi-2.2: Materials Emissions: Paints & Coatings: Contractor must submit Product Data to confirm use of low emission paints and coatings to improve occupant health to demonstrate that the interior surface area covered by paints and coatings in the project meet or are less than the maximum VOC content limits values for paints and coatings for 95% of all surface areas covered by paints and coatings per Annex II, Phase II, Table A of European Directive 2004/42/CE: 2004. -The VOC limits of the remaining non-compliant paints and coatings must be no more than 50% higher than the values listed below for each product type. All paints and coatings must have fungal resistance. -Reference: Annex II, Table A of Directive 2004/ 42/ CE of European Parliament and of The Council of 21 April 2004 (http:/ /eur-lex.europa.eu/ LexUriServ/ LexUriServ.do?uri=OJ:L:2004:143:0087:0096:EN:PDF).

Phase II

1

2

3

4

5

6

7

#

Product Category

Interior matt walls and ceilings (Gloss 25 @ 60 o )

Interior trim and cladding paints for wood and metal

Interior trim varnishes and wood stains, including opaque wood stains

Interior minimal build wood stains

Primers

Binding Primers

Type

WB SB

WB SB

WB SB

WB SB

WB SB

WB SB

WB SB

(g/l)*

30 30

100 100

130 300

130 400

130 700

30 350

30 750

Phase II

8

9

#

Product Category

One- Pack performance coatings

Two- pack reactive performance coatings for specific end use such as floors

Type

WB SB

WB SB

(g/l)*

140 500

140 500

10

11

12

Two- pack reactive performance coatings for specific end use such as floors

Multi- colored coatings

Decorative effect coatings

WB SB

WB SB

WB SB

140 500

100 100

200 200

*g/l of ready to use product LBi-2.4: Materials Emissions: Ceiling System: Product Data to confirm use of low emission ceiling systems as follows: -Suspended Ceiling Systems Demonstrate that all suspended ceiling systems comply with the requirements of BS EN 13964: 2004 section 4.5, in relation to asbestos (no asbestos) and formaldehyde content (which must meet class E1 at a minimum and be tested, classified and appropriately marked). -Non-Suspended Ceiling Systems Comply with the aforementioned requirements of LBi- 2.1 for any Adhesives and Sealants. Comply with the requirements listed in LBi-2.2 for any Paints and Coati