  • 8/11/2019 General Pipe Rounting Criteria

    1/13

    Yard Area Piping

    Prepared By : Akhilesh Pastor

  • 8/11/2019 General Pipe Rounting Criteria

    2/13

    1

    Contents

    v Introduction

    v Pipe Arrangement

    v Yard Area Piping

  • 8/11/2019 General Pipe Rounting Criteria

    3/13

    2

    Introduction

    Piping systems are like arteries and veins which carry

    The life blood of modern industrial civilization and provide

    protection of life and property.

  • 8/11/2019 General Pipe Rounting Criteria

    4/13

    3

    IntroductionPipe lines play major role in following industrial area

    Power Plant

    Refinery industries

    Chemical plants

    Paper mill

    Food processing

    Fire protection

  • 8/11/2019 General Pipe Rounting Criteria

    5/13

    4

    Introduction

    Pipe: Pipe can be defined as pressure tight cylinder used toconvey fluids.

    Piping: Pipe sections when connected with fitting ,valvesand other mechanical equipment/component and

    properly supported by hangers and supports

    called piping.

  • 8/11/2019 General Pipe Rounting Criteria

    6/13

    5

    Introduction

    This Figure Shows The Piping

  • 8/11/2019 General Pipe Rounting Criteria

    7/13

    6

    Piping Arrangements

    Purpose: Piping cost form a significant portion of a plant s total

    investments, the constructions , operation and maintenance

    provisions that will optimize these cost are an important aspect in

    design process.

  • 8/11/2019 General Pipe Rounting Criteria

    8/13

    7

    Piping Arrangements

    General Routing Criteria:There are some criteria that

    optimize piping cost and proper functioning of system.

    Piping from source to destination should be as short aspossible with minimum change in direction.

    Piping should not hinder any normal passage way also shouldnot encroach any equipment maintenance space.

    Preferable

    Not Preferable

  • 8/11/2019 General Pipe Rounting Criteria

    9/13

    8

    General Routing Criteria

    Valves ,strainer, instruments on pipe should be easily accessible if

    needed provide separate access platform.

    Specific requirements of straight length of pipe for some

    components to be maintained ,like for flow orifice we need to

    provide 15 D straight pipe length at up stream of orifice and 5Dpipe at down steam of orifice.

    Example of Straight length requirement for Flow Orifice

  • 8/11/2019 General Pipe Rounting Criteria

    10/13

    9

    General Routing Criteria

    For pipe line which shall carry liquid we have to make sure

    that all filled air allowed to vent out of the line when line is filled

    to achieve this a vent connection is provided on top most point

    of pipe line.

    Also arrangement is kept in the pipe line so that liquid can be

    drain out if required.

  • 8/11/2019 General Pipe Rounting Criteria

    11/13

    10

    General Routing Criteria

    VENT

    VENT

    DRAIN

    DRAIN

    DRAIN

    Not required

    Not required

    Do not provide unnecessary drain and vents

  • 8/11/2019 General Pipe Rounting Criteria

    12/13

    11

    General Routing Criteria

    To avoid air pockets inpump suction line use

    top flat eccentric

    reducer that will

    prevents chances of

    air pockets formations.

    Top flat eccentric reducer

  • 8/11/2019 General Pipe Rounting Criteria

    13/13

    12

    General Routing Criteria Check feasibility for installation of pipe supports and make full

    utilization of existing structural and concrete.

    Preferably use long radius elbows where elbow are required