-
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 1 of
45
This document is the confidential property of Chevron U.S.A.
Inc. Neitherthe whole nor any part of this document may be
disclosed to any thirdparty without the prior written consent of
Chevron U.S.A. Inc. Neither thewhole nor any part of this document
may be reproduced, stored in anyretrieval system or transmitted in
any form or by any means (electronic,mechanical, reprographic,
recording or otherwise) without the priorwritten consent of Chevron
U.S.A. Inc.
GEN-SU-5209
FLANGE GASKETS AND BOLTING
APPLICATION: ONSHORE, TOPSIDES
Rev Date Description Author Sponsor6/09 GR-800 conversion to CES
DREE JROF
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 2 of
45
CONTENTS
1.0 Scope
..........................................................................................................................42.0
References
..................................................................................................................4
2.1 ......Purchaser Documents
......................................................................................42.2
......Industry Codes and Standards
.........................................................................4
3.0 Terminology
................................................................................................................43.1
......Acronyms
.........................................................................................................43.2
......Definitions
.........................................................................................................5
4.0 General
........................................................................................................................65.0
Inspection and Repair Flanges
.................................................................................6
5.1 ......General
.............................................................................................................65.2
......Gasket Surface Inspection
...............................................................................65.3
......Warped Flanges and Gasket Surfaces
............................................................75.4
......Gasket Surface Repairs
...................................................................................8
6.0 Installation of Gaskets
...............................................................................................97.0
Gasket Applicability
...................................................................................................9
7.1 ......Corrugated Gasket Graphite Covered (CGG) Gaskets
....................................97.2 ......Kamprofile Gaskets
........................................................................................107.3
......Spiral Wound Gaskets with Inner and Outer Rings
........................................107.4 ......Octagonal Ring
Joint (ORJ)
...........................................................................117.5
......Solid Metal Gaskets with Nubbins
..................................................................117.6
......Other Applications
..........................................................................................117.7
......Gasket Specifications and Acceptable Brands
...............................................12
8.0 Bolting Up
.................................................................................................................128.1
......General
...........................................................................................................128.2
......Stud Material
..................................................................................................138.3
......Spring Washers
..............................................................................................138.4
......Hardened Washers
........................................................................................138.5
......Stud Loads
.....................................................................................................148.6
......Stud Length
....................................................................................................158.7
......Lubrication
......................................................................................................158.8
......Studs Exposed to Steam or Boiler Feed Water
..............................................178.9 ......Piping
Flange Assembly
.................................................................................178.10
....Piping Flange Alignment
................................................................................178.11
....Stud Tightening Practice
................................................................................188.12
....Cold Pull Alignment
........................................................................................188.13
....Hot Bolting or Single Stud Replacement
........................................................198.14
....Flange Joints in Vibrating Service (Including Liquid Packed
Pressure Relief
Devices)
.........................................................................................................19
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 3 of
45
9.0 Torqued Joints
.........................................................................................................209.1
......General
...........................................................................................................209.2
......Joints to be Torqued
.......................................................................................219.3
......Calculating Torque Values
.............................................................................219.4
......Piping and Pressure Vessels
.........................................................................229.5
......Shell and Tube Heat Exchanger Body Flange Joints
.....................................229.6 ......Torquing Hard to
Reach Nuts
.........................................................................229.7
......Hot Torquing Shell and Tube Exchanger Body Flange Joints
........................229.8 ......Shell and Tube Heat Exchanger
Leaks on Startup or on the Run .................23
10.0 Tensioned Joints
......................................................................................................2510.1
....General
...........................................................................................................2510.2
....Joints to Be Tensioned
...................................................................................2510.3
....Tensioning Procedure
....................................................................................2510.4
....Hot Tensioning of Heat Exchanger Joints
......................................................2610.5
....Tensioning Hard to Reach Nuts
.....................................................................26
11.0 Boiler Manways and Hand Holes
............................................................................2611.1
....General
...........................................................................................................2611.2
....Procedure
.......................................................................................................26
12.0 Flange Insulation
......................................................................................................2712.1
....General
...........................................................................................................2712.2
....Inclement Weather
.........................................................................................2712.3
....Assembly
........................................................................................................2712.4
....Tags
...............................................................................................................2712.5
....Fixed Equipment, Rotating Equipment, and Valve Bonnet Flanges
...............2812.6 ....Temperatures Between 700F and 850F (370C
and 455C) ......................2812.7 ....Temperatures Above 850F
(455C)
..............................................................2812.8
....Under Insulation Corrosion Protection
...........................................................28
Appendix A Piping
............................................................................................................29Appendix
B Shell and Tube Exchangers (Existing)
.......................................................39
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 4 of
45
1.0 SCOPE1. This specification defines practices for selection,
inspection, repair, and torquing/tensioning of
flanged joints.2. This specification is applicable to existing
ASME flanges, shell and tube heat exchangers, and
air cooled heat exchangers. 3. This specification does not cover
specialty equipment and piping systems with full-faced
gaskets, hub-type connectors, such as Grayloc, Reflange, LTS,
and Taperloc, or specialty equipment, such as hair-pin or
double-pipe exchangers that require equipment specific sealing
materials and assembly procedures. Recommended general bolting
practices in this specification do apply.
4. The following are not covered by this specification:a. Small
utility, lubrication, and skid mounted heat exchangers that use a
sheet type gasket
material.b. Air cooler plugs and gaskets. This service will be
addressed on an individual basis.c. API 6B and API 17D flanges,
although the practices in this specification may be applied.
2.0 REFERENCES1. The following documents are referenced herein
and are considered part of this specification.2. Use the edition of
each referenced document in effect on the date of the publication
of this
specification
2.1 Purchaser DocumentsEXH-SU-2583 Shell and Tube Heat
Exchangers for General Refinery ServiceException to
API 660, 8th EditionEXH-SU-5150 Graphite-Covered Corrugated
Metal CGG-Style GasketsEXH-SU-5151 Kamprofile Graphite Covered KAG
Style GasketsGEN-DG-5209 Design Guide for Flange Closure Design
Calculation SpreadsheetGEN-DS-5209 Data Sheets for Flange Gasket
and Bolting
Purchaser DrawingsGD-L1264 Gasket Specifications and Acceptable
BrandsGF-C87280 Standard Manholes and Covers for Pressure
Vessels
2.2 Industry Codes and StandardsAmerican Petroleum Institute
(API)Std 660 Shell-and-Tube Heat Exchangers, Eighth Edition
3.0 TERMINOLOGY
3.1 AcronymsCGGCorrugated gasket graphite cover made
specifically to EXH-SU-5150
CMGCorrugated metal graphite (gaskets - generalized industry
term for a CGG)
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 5 of
45
ETGISEvaluation, torquing, gaskets, installation, studs
(Purchaser sealing program)
EWOEngineering work order
HFHydrofluoric acid used in Alkylation plants
IDInside diameter
KAGKamprofile gasket graphite covered made specifically to
EXH-SU-5151
KAMSerrated gasket sealing surface covered with graphite (such
as a KAG gasket)in accordance with EXH-SU-5151
MAWPMaximum allowable working pressure
MOCManagement of change
MPTMinimum pressurizing temperature
NBICNational Board Inspection Code
ODOutside diameter
OEMOriginal equipment manufacturer
ORJOctagonal ring joint
PEGPressure energized gasket (mostly used in reactor heads)
PRDPressure relief device
RADRegulated air drive (air driven torquing tool)
RFRaised face
RMSRoot mean square (refers to surface finish)
RTJRing tongue and groove joint
SCCStress corrosion cracking
SGASheet gasket aramid fiber (also called paper gasket in the
field)
SSCSulfide stress cracking
SWSpiral wound (gasket)
T>ongue and groove
VOCVolatile organic compound
3.2 DefinitionsGrip LengthThe load carrying length of a
fastener, from the center of one nut to the center of the opposing
nut. For studs in blind holes, the length from the flange face to
the top of the nut.
Heat ExchangersWhere used in this document and all attachments
the term refers to shell and tube heat exchangers.
Hot Bolting1.) Removal of every other stud on live (pressurized)
equipment, prior to a shutdown, in preparation for opening
equipment or 2.) Installation of only half of the flange studs
prior to a pressure test.
Screw Plug Exchanger (also referred to as a Breech Lock) High
pressure heat exchanger with a screw plug closure.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 6 of
45
Single Stud Replacement1.) Removal, lubrication, and
reinstallation of a single stud on live equipment, prior to a
shutdown, in preparation for opening equipment or 2.) Single stud
replacement on live equipment.
4.0 GENERALGaskets for raised face and flat face flanges, as
well as recessed exchanger flanges, shall always be
self-centering.
5.0 INSPECTION AND REPAIR FLANGES
5.1 GeneralThis section outlines post construction inspection
and repair procedures for exchanger, piping, boiler, and vessel
manway flanges and shall apply to all types of flanges, i.e.; flat
face, raised face, ring joint, and tongue and groove, as outlined
in Section 5.2 through Section 6.0.
5.2 Gasket Surface Inspection
5.2.1 General1. Flange gasket seating surfaces shall be
cleaned.2. Gasket surfaces shall be inspected for the
following:
a. Gasket surface finish to verify proper flange finish.b. If
needed, a surface finish gauge comparator shall be used to
determine gasket
surface finish to achieve pipe flange and exchanger gasket
seating surface finish of 125 root mean square (RMS) to 250
RMS.
c. Cracks, corrosion, erosion, mechanical damage, or other
defects remaining after cleaning. Minor damage (scratches, pits,
etc.) shall not extend more than 50 percent across the radial width
of the gasket landing area.
d. Ring Joints1) Amount of coining (lip or ridge) at the bottom
of the groove shall be minimal. 2) Amount of coining shall
generally be determined by visual inspection and
noting depth using fingernail. 3) Sealing surfaces shall not
have any deep pits, gouge marks, corrosion damage,
or sufficient coining to hang a fingernail.4) If there is any
concern regarding the condition of the groove, a machinist
bluing compound shall be used to check the contact between the
groove and a new gasket. Contact shall be continuous around the
circumference of both inner and outer sealing surfaces and at least
70 percent of the height of the sealing surface.
5.2.2 Nubbins1. Nubbins have been used in conjunction with solid
metal and jacketed gaskets and are
no longer recommended in ANY application other than some
Alkylation Unit Contactors (Reactors) (refer to Section 7.5).
2. Nubbins shall not be used with corrugated gasket graphite
covered (CGG) or Kamprofile graphite covered (KAG) gaskets.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 7 of
45
3. Nubbins shall be removed and CGG or KAG style gaskets
installed when equipment is opened.
4. A temporary management of change (MOC) shall be required if
nubbins are to be left in place until the nubbin can be removed at
the next opportunity. Contact a sealing subject matter expert for
possible gasketing after the MOC has been completed.
5.2.3 Tongue and Groove Flanges1. For tongue and groove flanges,
the old gasket material shall be removed each time the
flange is opened. 2. Gasket surfaces on tongue and groove
flanges shall be 125 RMS to 250 RMS and free
of pits and defects. If not, they shall be repaired or replaced.
Graphite (Thermiculite or Teflon for oxidizing services) covered
KAG (with a 1/16 inch [0.063 inch, 1.6 mm] thick core) or CGG style
gaskets shall be used.
5.3 Warped Flanges and Gasket Surfaces
5.3.1 General1. Flanges shall be inspected and checked for
visual warpage and damage, especially
after any stress relieving process or repair is performed.2.
Laying a straight edge across the gasket surface or setting up a
field milling machine
with a dial indicator are the two most common ways for checking
flanges for flatness.3. Flanges that are warped shall be repaired
if the warpage exceeds API Standard 660
requirements included in Appendix B. 4. Gasket surfaces shall be
flat and parallel in the circumferential and radial directions
to
ensure even seating across the gasket. 5. Unless directed by the
work order, gasket surfaces for raised face piping flanges are
not typically dial indicated.6. Refer to GEN-DS-5209 WAR for
required readings and instructions.
5.3.2 Exchanger Body Flanges (Existing)1. General
a. Exchanger flanges shall be checked for warpage by performing
dial indication readings across the flange and gasket surface as
directed by the work order.
b. A dial check shall be mandatory for exchanger and large
diameter flanges after welding or stress relieving.
c. A dial check may also be required if there has been an
indication of leakage after converting to evaluation, torquing,
gaskets, installation, studs (ETGIS) process and installing CGG/KAG
gaskets.
d. Refer to GEN-DS-5209 WAR for required readings and
instructions.2. Exchangers with CGG/KAG Gaskets
a. The following do not have to be dial indicated unless
directed by the work order:1) Exchangers previously converted to
CGG/KAG gaskets using the ETGIS
process or this specification that have operated leak free.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 8 of
45
2) Small utility exchangers.3) Small exchangers that are part of
an equipment skid.4) Exchangers that have provided leak free
service with non CGG or KAG
gaskets. b. If gasket surface repairs are performed, gasket
surfaces shall be dial indicated.
3. Chronic Leaking Heat Exchangers a. Chronic leaking exchangers
shall be checked by performing dial indication
readings radially and circumferentially in accordance with
GEN-DS-5209 WAR. b. Guidelines/tolerances for these readings are in
Appendix B.
Note Chronic leaking exchangers are ones that have a history of
leaks or ones that are leaking at the time of conversion.
5.3.3 Warpage Form1. Dial indication readings on exchanger
flanges shall be recorded using
GEN-DS-5209 WAR. 2. If warpage exceeds tolerances shown in
Appendix B the surfaces shall be machined. 3. To support the work
flow, a completed warpage form shall be completed. 4. Copies of the
required warpage forms shall be forwarded to the engineer,
inspector,
and/or the person responsible for directing repair work.
5.3.4 Weld Buildup1. Depending on flange thickness, the warped
flange may require weld buildup before
machining to maintain the minimum code required flange
thickness. 2. Flange thickness shall comply with ASME Code
requirements after machining.3. Surfaces shall be machined if the
final flange dimensions will be less than the original
equipment manufacturer (OEM) drawing shows.4. An authorized
inspector shall be consulted to determine if flange thickness that
is less
than original is considered an alteration.
5.4 Gasket Surface Repairs
5.4.1 General1. Flange gasket surfaces may be repaired by weld
buildup and remachining. 2. Weld repairs on any flange shall be
performed in accordance with an ASME qualified
weld procedure. 3. Piping flanges may be easier to replace
rather than repair.
5.4.2 Flange Refacing1. In some cases, the flange can be refaced
without weld metal buildup. 2. Flange thickness shall be verified
as thick enough to meet code requirements after
machining. (Flange strength is based on the thickness that does
not include the raised face.)
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 9 of
45
3. OEM flange dimensions shall preferably be maintained on all
equipment. Flange minimum thickness calculations shall be completed
prior to opening the heat exchanger vessel or piping if OEM
dimensions are not going to be maintained prior to machining.
4. Actual dimensions shall be verified in the field before
performing any machining.5. Repair of gasket surfaces may be
subject to a variety of purchaser, local, state,
country, ASME code, and national board requirements. Some
repairs will require a National Board R-symbol stamp. To ensure
that all requirements are properly met, the Authorized Inspector
(AI) or an appropriate subject matter expert shall be
consulted.
5.4.3 Routine Repairs1. Routine repairs as defined in the
National Board Inspection Code (NBIC) are not
recognized in California. 2. In California, inspector
involvement and stamping, shall be required for gasket
surface weld repairs on Code vessels and Code piping.
6.0 INSTALLATION OF GASKETS 1. Gaskets for existing heat
exchangers shall be installed in accordance with Appendix
Section B.2. 2. Pipe flange gaskets shall be installed in
accordance with Appendix Section A.1.3. Gasket specification and
acceptable brands shall comply with GD-L1264. 4. Pipe flange torque
values for standard ASME RF, RTJ, and tongue and grove (T&G)
flanges
shall comply with Appendix Table A-1. 5. Torque values for non
ASME/specially designed flanges, such as large diameter low
pressure
knife gate flanges, shall be provided in the work order or by
the person responsible for the work.
6. For graphite covered gaskets, if the graphite is damaged to
the point where the core is exposed, the area shall be repaired by
covering it with adhesive backed APX-2 graphite tape. Only the
minimum amount of tape needed for the repair shall be used, and
edges shall not be overlapped by more than 1/16 inch (0.063 inch,
1.6 mm).
7.0 GASKET APPLICABILITY
7.1 Corrugated Gasket Graphite Covered (CGG) Gaskets 1. CGG
gaskets shall be used in process heat exchangers, including cooling
water and screw plug
exchangers, in accordance with the following:a. In nonoxidizing
services 800F (425C) and below design if one edge of the gasket
is
exposed to air. (Inside columns, in air free nonoxidizing
service, the temperature limit is higher.)
b. Radial gasket widths of 1/2 inch (12.7 mm) and greater.c.
T&G flanges that use a 1/2 inch (12.7 mm) or wider gasket and
coke drum transition spool
flanges.2. CGG gaskets may also be used in other special closure
designs but are generally not
recommended for pipe flanges.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 10 of
45
7.2 Kamprofile Gaskets KAG Kamprofile gaskets shall be used in
the following applications:1. Process heat exchangers, including
cooling water and screw plug exchangers, in accordance
with the following:a. In nonoxidizing services 800F (425C) and
below.b. Radial gasket widths of less than 1/2 inch (12.7 mm).c.
Where a thicker gasket is required to prevent body flange faces
from touching.
2. Raised face piping flanges in class 150 and class 300
nonoxidizing services unless there is a technical reason to use
Spiral Wound.
3. Raised face piping flanges in class 600 and higher that
are:a. Chronic leakers.b. Approved for use.
4. KAG gaskets shall be considered for any raised face (RF)
piping flange over 24 inches if either:a. There is concern over the
possibility of windings popping out of spiral wound (SW) gasket
guide rings.b. The windings cannot be kept loaded.
5. Any other closure designs, such as furnace tube closure
blinds, in nonoxidizing services 800F (425C) and below.
6. Vessel manways.7. T&G flanges, if a 1/16 (0.063 inch, 1.6
mm) inch core is used.8. KAG gaskets can be used above 800F (425C)
if specially designed with a mica barrier on the
outside diameter ([OD], and inside diameter [ID], if needed) to
protect the graphite from high temperature oxidation, where one
edge of the gasket is exposed to air.
7.3 Spiral Wound Gaskets with Inner and Outer Rings SW gaskets
with inner and outer rings shall be used in the following
applications:1. Raised face piping flanges in services 800F (425C)
and below for class 600, class 900, and
class 1500. For large SW gaskets, tape (including graphite tape)
shall not be used to hold the windings in place. The tape will
prevent the windings from being properly loaded.
2. Raised face piping flanges in class 150 and class 300, if
volatile organic compound (VOC) emissions are not a concern, KAG
gaskets are not available, or there is a technical reason to use
this gasket to over a KAG.
3. Raised face piping flanges in 150 and 300 class lube and seal
oil service, if there is concern of contaminating oil system with
small graphite pieces.
4. Hydrofluoric Acid (HF) Alkylation Units that have
successfully used SW gaskets with Monel windings and inner rings
and either Teflon or graphite filler may stay with this gasket
design for HF service. (KAG gaskets are a recommended upgrade.)
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 11 of
45
7.4 Octagonal Ring Joint (ORJ)1. ORJ (oval rings are not
recommended) and KAM-ORJ gaskets shall be used in the following
applications:a. Ring joint piping flanges in class 2500.b. Ring
joint piping flanges for service temperatures above 800F (425C).c.
Existing ring joint piping flanges in class 300, 600, class 900,
and class 1500.
2. ORJ gaskets shall be used in flanges with ring joint grooves
that are in as new condition and have no history of leaks. ORJ
gaskets shall be replaced each time the flange is opened.
3. KAM-ORJ gaskets shall be used in:a. Flanges with ring grooves
that are slightly damaged.b. Flanges that are broken apart at a
frequency greater than once every five (5) years.c. Flanges with a
history of leaking (such as reactor companion flanges on the top
and
bottom ells).4. For KAM-ORJ gaskets in service temperatures
above 800F (425C), a mica based or
Thermiculite covering shall be specified in lieu of APX-2
graphite on the gasket edge that is exposed to air. See GD-L1264
for a complete list of approved materials.
7.5 Solid Metal Gaskets with Nubbins 1. Solid metal gaskets and
nubbins are approved for use in Alkylation Unit Contractors
(Reactors) if:a. Contractors operate at ambient temperature or
below.b. The Contractors were originally built with this sealing
system.
2. Nubbins and solid metal or clad gaskets shall not be allowed
on equipment operated at elevated temperatures.
7.6 Other Applications
7.6.1 Metal Jacketed (Clad) Gaskets Metal jacketed (clad)
gaskets and solid flat metal gaskets (except air cooler plug
gaskets) shall not be used except as discussed in Section 7.5.
7.6.2 Reactor Pressure Energized Gaskets (PEGs) and Screw Plug
Heat Exchangers 1. Reactor PEGs and screw plug heat exchangers are
covered by specific instructions
that pertain to the individual piece of equipment. 2. Sections
of this specification regarding gasket selection and bolting
technique are
consistent with specifications specific to this equipment.
7.6.3 Heat Exchangers That Do Not Use CGG or KAG GasketsHeat
exchangers that comply with service, code, and temperature
requirements but do not currently use CGG or KAG gaskets shall be
converted using the conversion process as covered by this
specification.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 12 of
45
7.6.4 Glass Reinforced Epoxy (GRE) Gaskets for Electrical
IsolationGRE gaskets are no longer recommended for use. For
Electrical isolation of flanges, use coated metal core gasket only
such as Pikotek VCS or VCDFS (firesafe); or equal.
7.7 Gasket Specifications and Acceptable Brands1. Refer to
drawing GD-L1264 for gasket specifications and acceptable brands
information. 2. Sheet gaskets in accordance with gasket code sheet
gasket aramid fiber (SGA) shall be
acceptable for temporary isolation blinds. 3. The same sheet
material and temporary flat plate isolation blinds used in raised
face flanges
may also be used in ORJ flanges. 4. ALL gaskets used in columns
shall be rated for the maximum temperature of the column.
Generally, SGA gaskets are not to be used in columns and should
be replaced by KAG, SWG, or SGG materials. Refer to GD L1264 for
additional guidance.
5. EXH-SU-5150 contains the complete specification for CGG (CMG)
gasket style, andEXH-SU-5151 contains the complete specification
for Kamprofile (KAG) gasket style.
8.0 BOLTING UP
8.1 General1. This specification generally applies to the
bolting up of all flanged piping, exchanger, and
other pressure vessel connections. Bolting is a generic term
that describes the use of either a threaded fastener with a fixed
head (a bolt) or a stud (a threaded rod), on which one or two nuts
are used to retain the load.
2. The ideal choice for ensuring the accuracy of stud loads is
to replace the studs and nuts in kind with new ones each time the
connection is opened and torque the nuts to a desired stud load
that will achieve the required gasket stress.
3. Studs that are tensioned (the stud is stretched with a
tensioning head) do not need to be replaced, as long as the nut can
be turned by hand, and the stud can still carry the load.
4. In the case of special alloys, studs that are threaded into
blind holes and are difficult to remove (e.g., reactor studs) or
specially made fasteners (e.g., screw plug jacking screws), it may
be more economical to recondition the threads and reuse the
fastener.
5. The following options (in order of effectiveness) shall be
acceptable for reconditioned threads as long as the result allows
the threads to run freely over each other using only the fingers
and the load carrying requirements of the fastener have not been
reduced:a. Recondition studs and nuts using taps and dies. This
approach is the most effective at
protecting the load carrying ability of the existing threads as
the taps and dies generally just remove surface contamination on
the threads. In some cases, it may be easier to use dies on the
stud threads and replace the nuts.
b. Recondition studs and nuts using a light bead blast. A close
check for corrosion or mechanical damage shall be required after
blasting. In some cases, additional reconditioning with taps and
dies may be required. If the bead blast results in metal loss that
increases the clearance between male and female threads, the
threaded component(s) shall be replaced.
6. Threads on studs and nuts that are to be retorqued shall not
be reconditioned by wire brushing. Wiring brushing may be used on
studs that are to be tensioned, as the frictional differences
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 13 of
45
between studs will not affect the accuracy of the final load.
The tensioner puller bar and nuts must run freely on the stud. If
not, a tap and die nut shall be used to correct the problem or the
components shall be replaced.
7. For special closures (screw plug exchangers, reactor heads,
the packed glands on exchanger distance pieces, etc.), the
equipment specific procedures and instructions included in the work
order shall be followed.
8.2 Stud Material1. If the stud metallurgy is not adequate to
withstand environmental or process conditions, a
review shall be performed and the metallurgy changed to a more
suitable material. 2. A change in metallurgy may require a code
review and calculations, along with a review of the
operating gasket stress for leak tight operation, e.g., changing
from SA-193 B7 in a floating head application to SA-193 B8 stud
material, which has a lower yield strength.
3. For a listing of available bolting material, yield strength,
temperature limits, and applications, refer to Appendix Table
A-2.
8.3 Spring WashersInstallation of spring washers (Belleville
washers) shall not be allowed for flanged joints because they:1. Do
not provide an advantage on a heat exchanger or piping joints.2.
Are susceptible to hydrogen stress corrosion cracking from contact
with water (if they are
made from high strength carbon steel).3. Are expensive.4. Are
susceptible to cracking. 5. Are difficult to reinstall in the right
configuration (cup to cup or cone to cone).6. Usually require use
of multiple washers (three to five or more) to gain any
advantage.
8.4 Hardened Washers
8.4.1 General1. Hardened washers shall be installed under nuts
to be torqued on all exchanger body
flange joints that use SA-193-B7 or B16 stud material. 2.
Washers shall be ASTM F-436 class 1 specification. 3. Washer
thickness shall be at least 1/8 inch (3.17 mm) and compatible with
the stud
size. 4. Hardened washer, if reused, shall not have any galling,
grooving, or burrs. 5. Pipe flange studs being wrench tightened
shall not require hardened washers, if the
nuts contain an integral washer that is installed face down
against the bearing surface. 6. Washers are optional on manways and
pipe flanges that have to be torqued, provided
that the bearing surface is in reasonably good shape. 7. Washers
shall be used on manways and pipe flanges if the bearing surface is
badly
worn, galled, or if the corners of the nuts are in danger of
hitting the flange face due to an excessively deep pocket that has
been worn into the flange.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 14 of
45
8. Glass reinforced epoxy washers (G10) are no longer
recommended for electrical isolation of flange joints. Use coated
metal core washers only such as Pikotek HCS or equal.
8.4.2 Materials1. Changes in washer material or use of hardened
washers with stud materials other than
SA-193-B7 or B16 shall be reviewed by a material engineer or
other qualified person. 2. In some cases, standard washers cannot
be used (e.g., with fine thread floating head
studs, as the washer will protrude past the flange OD).
8.4.3 Placement of Washers1. For safety considerations, if the
nut is accessible from either end of the stud, the
hardened washer shall be installed under the appropriate nut to
be torqued such that the torque wrench will be pulled in a downward
direction during the torquing operation.
2. For exchanger channel cover flanges, washers shall be placed
on the channel cover. 3. For other exchanger body flanges, washers
shall be placed on the flange to the left
when facing the connection from either side of the exchanger.
For channel to shell connections, this will result in washers being
place on the channel flange on the right side of the exchanger
(when facing the front of the exchanger) and on the shell flange on
the left side of the exchanger.
4. For vertical reboilers, on which studs are initially
tightened in the horizontal position and hot torqued in the
vertical positions, washers can be placed under both nuts. (Some
facilities do this on all exchangers to simplify washer
placements.)
8.5 Stud Loads
8.5.1 Shell and Tube Heat Exchangers1. Stud loads for heat
exchangers shall generally range from 50 percent to 90 percent
of
the minimum code yield strength of 105,000 psi (724 Mp, 7,240
Bar) (for B7 and B16 stud material, 52,500 psi (362 Mp, 3,620 Bar)
to 94,500 psi (652 Mp, 6,516 Bar).
2. Stud loads shall be adjusted to obtain a targeted gasket
stresses of 20,000 psi (138 Mp, 1,379 Bar), with a maximum of
40,000 psi (276 Mp, 2,758 Bar) and a minimum of 10,000 psi (69 Mp,
689 Bar).
3. If a gasket stress is to too high, the radial width of the
gasket shall be increased by reducing the ID (making the gasket
wider and increasing the contact area) to reduce the gasket stress.
This is usually required for gaskets on the low pressure side of
tubesheets that have a differential pressure that is 300 psi (2 Mp,
20.68 Bar) or higher.
4. If the gasket stress is too low, the radial width shall be
reduced. If the radial width is less than 1/2 inch (12.7 mm), a KAG
gasket shall be used. KAG gaskets are not recommended with radial
widths below 3/8 inch (9.5 mm) but have been used down to a 1/4
inch (6.35 mm) radial width if no other option is available.
5. To calculate a torque value, a nut or K factor of 0.17 shall
be used. 6. GEN-DS-5209 FCD shall be used to calculate gasket
stresses and torque values for
heat exchangers. For more on GEN-DS-5209 FCD please see
GEN-DG-5209.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 15 of
45
8.5.2 Pipe Flanges1. Stud loads for pipe flanges shall be set to
obtain an approximate 25,000 psi (172 Mp,
1.724 Bar) gasket stress. A summary of pipe flange torque values
are found in Appendix Table A-1.
2. Gasket stresses and torque values for ASME pipe flanges have
been calculated using the GEN-DS-5209 FTS for both RF and RTJ
flanges. This document also contains the maximum stud load that can
be used with each flange size and class.
3. For flanges over 24 inches, the GEN-DS-5209 LGF shall be
used. 4. To calculating a torque value, a nut or K factor of 0.15
shall be used.
8.6 Stud Length1. Studs shall be long enough to ensure that all
threads in the nuts are fully engaged. 2. Studs shall be flushed
with the nut, with a maximum of two threads exposed past the nut
that
should break first during disassembly. 3. Extra stud length may
extend past the non-breaking nut. 4. Studs shall not be butterflied
where extra threads are distributed evenly past both nuts.
8.7 Lubrication
8.7.1 General1. Stud threads shall be thoroughly lubricated on
both ends during final assembly. 2. Bearing surfaces between the
nut and hardened washer or the nut and flange on the
end that will be torqued shall be lubricated to ensure that the
proper torque load is applied. This can easily be accomplished by
filling the threads with antiseize in the area where the nut will
rest and then allow the antiseize to squeeze out as the nut makes
contact.
3. Studs may be lubricated only on one end for flanges that are
being blinded during a shutdown.
4. The antiseize on the complete assembly shall be easily
visible.
8.7.2 Lubricants1. Only Jet-Lube 550 antiseize lubricant shall
be used for flange temperatures up to
600F. 2. For blind stud holes and temperatures above 600F (516C)
(i.e., reactor heads and
coker drums, delta valves), Jet-Lube Riser and Superior Plant
Services Molly- B are approved. If Hot Torquing is required, see
Section 8.7.3.
3. These products are molybdenum disulfide based. 4.
Substitutions shall not be allowed, unless approved in writing by
the person
responsible for the job.
8.7.3 Hot Torquing1. If hot torquing is required after using
Molly-B or Jet-Lube Riser, a new temperature
based torque value shall be calculated, as the friction factor
drops substantially when the temperature rises. (Refer to Figure 1
and Figure 2) This can cause the studs to be
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 16 of
45
over loaded if the torque value is not reduced to compensate for
the change in temperature.
2. Figure 1 shows Jet-Lube 550 (MO2) is fairly temperature
stable. The nut or K factor changes little with temperature, so the
original torque value can be used for the hot torque.
3. Figure 2 shows the significant change in nut or K factor,
with the change in temperature for Molly-B and Jet-Lube Riser.
Figure 1: Nut Factor Results - MO2 (This graph comes from
original product testing on nut factors at the TTRL Laboratory in
Montreal and is published with permission from the author, Dr.
Warren Brown.)
Figure 2: Nut Factor Results - MO1 (This graph comes from
original product testing on nut factors at the TTRL Laboratory in
Montreal and is published with permission from the author, Dr.
Warren Brown.)
Average 95% Percentile5% Percentile Range (% of Average)
0.05
0.07
0.09
0.11
0.13
0.15
0.17
0.19
0.21
0.23
0.25
25C 100C 200CTest Temperature (C)
K F
acto
r
0
4
8
12
16
20
24
28
32
36
4075F 210F 390F
Ran
ge (
% o
f A
vera
ge)
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 17 of
45
8.7.4 Gasket SurfacesAnti-seize lubricant shall not be applied
to the gasket surface.
8.8 Studs Exposed to Steam or Boiler Feed WaterStuds in flanges
that have leaked boiler feed water, steam, condensate, or caustic
over an extended period of time shall be replaced when the flange
leak is repaired and gasket replaced. Studs in these conditions are
prone to failure due to caustic embrittlement where caustic is
sometimes used to treat boiler feedwater and condensate
systems.
8.9 Piping Flange Assembly 1. Also refer to Appendix A. 2. Flat
faced or raised face piping flanges shall be assembled as
follows:
a. Flanges shall be faced together.b. Studs shall be installed
in half of the flange to help center the gasket.c. The gasket and
remaining studs shall then be installed.
3. On tongue and groove and ring joint flanges, the gasket shall
be inserted before the flanges are faced together. If the tongue
and groove gasket will not stay in place while facing the flanges
together, several dabs of heavy grease or 3M Super 77 spray
adhesive may be used on the seating surface to hold the gasket in
position.
4. When assembling cast iron flanges or RFP (fiberglass), flange
faces shall be full faced and not mated to RF flanges. Only full
faced gaskets shall be used when assembling these flanges.
5. Flat face flanges made of ductile iron, carbon steel or
stainless steel can be mated with raised face flanges. The
appropriate raised face ring gaskets shall be used for these
applications.
8.10 Piping Flange Alignment
8.10.1 General1. Pipe flanges shall be properly aligned before
bolting. 2. If alignment cannot be corrected by loosening adjacent
flanges and shifting the ends
of connecting pipe spools, the piping shall be cut and fit up
properly.
8.10.2 After Final Assembly1. After final assembly, RF and RTJ
flanges less than 24 inches in diameter shall be less
than 1/32 inch of an inch (0.032, 0.813 mm) of parallel (cocked)
as measured across any flange outside diameter.
2. The flange gap shall be checked after final assembly of all
flanges.
8.10.3 Small Gaps1. Small gaps, up to 1/16 inch, due to
unparallel piping flange faces, may be tightened by
pulling up on the studs at the widest flange separation point
and then tightening all the studs.
2. The pipe shall have enough flexibility to allow the flanges
to pull together.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 18 of
45
8.10.4 Alignment Procedure1. Flanges shall be aligned by
inserting a spud wrench bar in an open bolt hole and
installing two studs opposite each other to hold the flanges in
position. 2. Excessive force, if required to align the flanges,
shall be corrected. 3. Forces shall be considered excessive if
either:
a. Come alongs, cranes, hoists, or jacks are needed to align the
flanges.b. Bolting is needed to pull the flanges together, i.e.,
excessive gap between the
flanges. 4. The piping shall be inspected to determine if it
needs to be redesigned to reduce forces
in the piping and/or equipment. 5. A stress analysis may need to
be performed.
8.11 Stud Tightening Practice1. Studs shall be hand tightened
and torqued in the specified pattern around the flange until
all
the studs have the same tension. Refer to Appendix Section A.3
for piping joint torque patterns.
2. Persuaders or handle extensions shall not be used on
wrenches. This practice can result in broken wrenches, bent
flanges, and personal injury.
3. Short Stiff Manifoldsa. On short stiff manifolds, such as at
pumps, equipment nozzles, compressors, turbines,
control and valves, flanges shall fit squarely without cold pull
or line strain. b. Custom Made Spacers
1) In some cases, a custom made spacer may be used to correct
misalignment. 2) These spacers shall be constructed with a tab
welded to the spacer. 3) The tab shall stick out past the flanges
and insulation. 4) The location of the spacer shall be etched on
the tab, e.g., P 8400C suction piping
spacer.5) Metallurgy and design details of the spacer shall be
consistent with the piping
specification.4. Bending piping spools into alignment by heating
and pulling into place with the studs is not
recommended, as residual line stresses remain after heating. The
root cause of the problem shall be determined and corrected.
8.12 Cold Pull Alignment1. Review
a. If flanges are in alignment but require cold pull to make up
the gap between the flanges, the installation shall be reviewed to
determine if modifications are required.
b. Cold spring or pull shall not normally be used in a refinery
to compensate for line expansion.
c. If cold spring or pull is noted, checks shall be performed to
see whether:1) Piping is properly anchored.2) Piping has moved or
shifted on the pipe supports due to repeated thermal expansion.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 19 of
45
3) A pipe shoe slipped off the pipe support and is hung up on a
support holding the line.4) There are other line restraints holding
the line.
2. If the line cannot be made up without cold spring, a stress
analysis shall be performed on the line to determine whether the
line can either:a. Be pulled into place.b. Needs to be redesigned
to fit up without line strain.
3. Misalignment from Cold Stress Movementa. In some cases, in
high temperature applications, such as reactor inlet and outlet
piping,
flanges may be misaligned due to cold stress movement.
Note Cutting and rewelding of flanges will not resolve this
issue, as flanges will return to normal alignment when operating
temperature is reached.
b. In these cases, flanges shall be aligned and squared using a
come along and high side bolting to square flange before making
contact with gasket. After the line is in service, the studs should
be retightened. Outside flange and nut temperatures above 250F may
be too hot for hydraulic torque equipment to perform this
operation.
8.13 Hot Bolting or Single Stud Replacement
8.13.1 General
Note Hot bolting (using only half the studs for a pressure or
hydrotest or removing studs in operating equipment prior to a
shutdown) and single stud replacement on operating equipment shall
not be allowed, unless the procedure outlined in Section 8.13.2 is
followed.
8.13.2 Procedure1. Hot bolting of any equipment may only proceed
after completing the MOC process,
including a job safety review, an engineering review, and
issuance of a written operating procedure specifying allowable
temperature and pressure limits. An example is when feed has been
pulled and plant is being steamed out to relief with less than 15
psig pressure buildup and flange temperature is below 200F
(93C).
2. Single stud replacement shall be subject to the same approval
process as hot bolting in Section 8.13.1.
8.14 Flange Joints in Vibrating Service (Including Liquid Packed
Pressure Relief Devices)
1. Equipment reliability can be significantly affected if it is
subjected to constant or high levels of vibration.
2. Immediate operational changes should be made to eliminate
unexpected vibration that suddenly develops in equipment.
3. Engineering analysis shall be performed on lines subject to
vibration to define the extent of the problem, and design changes
or plant modifications shall be made to reduce the level of
vibration to safe levels.
4. Piping sections that are allowed to vibrate may potentially
lead to the following:a. Flange leaks
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 20 of
45
b. External thinning of piping rubbing on supportsc. Fatigue
failure, depending on frequency and amplitude of displacement
5. Typical locations where piping vibration may occur are in the
vicinity of the following:a. Reciprocating compressorsb.
Reciprocating pumpsc. Control valve manifoldsd. Let down stationse.
Power recovery turbinesf. Pressure relief device (PRD)
6. Observed Vibration of Piping Sectionsa. Piping sections in
the plant that exhibit vibration shall be brought to the
attention
of the responsible engineer. b. Such piping sections shall be
reviewed to determine whether they have previously
been analyzed and all corrective actions completed. c. For
piping sections not previously analyzed, a dynamic stress analysis
study can
be performed and in most cases relocation of supports can reduce
vibration intensity.
7. Check for Missing or Loose Nuts on Flangesa. Piping sections
continually exposed to vibration for which analysis has shown
are
within allowable stresses shall be walked down periodically or
at least once a year to check for missing or loose nuts on
flanges.
b. Missing or loose nuts that are discovered shall be reported
to the responsible engineer, as they may indicate a system wide
problem and a precursor to one or more potential flange leaks.
c. This is especially true for relief systems that are liquid
packed if the PRD has a tendency to lift and close repeatedly
(chatter) or systems subject to cavitation due to change in fluid
phase.
d. A plan of action shall be determined and, as a minimum, the
studs and nuts at the missing or loose nut locations shall be
replaced before retightening.
e. Piping sections that continue to experience vibration, even
after mitigation attempts are performed, shall be flagged for
replacement of gaskets and studs in flanges during planned
turnarounds at 10-year intervals.
f. Gasket and stud replacement on vibrating PRD piping sections
shall be coordinated during PRD removal for repair and
recertification.
9.0 TORQUED JOINTS
9.1 General1. Many joints, depending on service and size, shall
require torquing to ensure even stud loading
and prevent leaks.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 21 of
45
2. Joints that are to be torqued shall be subject to the
following:a. For shell and tube heat exchangers, studs shall be new
or reconditioned (using taps and
dies) and hardened washer shall be placed under the nut that is
to be torqued.b. For pipe flanges, the nuts shall run freely with
the fingers, or the stud and nut shall be
replaced. Hardened washers are only required under the nut that
is being tightened if the flange face is galled (such that there is
not a smooth surface for the nut to tighten against) or if the
flange is worn to the point where the corners of the nut are
contacting the flange face.
c. Both ends of the studs shall be lubricated with antiseize. 3.
Tensioning is also an option and may be required if studs are
reused. See Section 10.0.
9.2 Joints to be TorquedThe following joints shall be torqued:1.
All shell and tube exchanger body flange connections.2. Piping and
equipment flanges that require 200 ft-lb (270 Nms) of torque or
more.3. Reactor top and bottom manways that use standard octagonal
ring (ORJ/RTJ) or KAM/ORJ
gaskets.
9.3 Calculating Torque Values1. Stud loads shall be calculated
first to achieve the targeted gasket stress under operating
conditions for the specific gasket material that is being used.
2. Torque values and gasket stresses for all shell and tube
exchangers stress shall be calculated
using the GEN-DS-5209 FCD.3. Torque values and gasket stresses
for all pipe flanges up to 24 inches were calculated using the
GEN-DS-5209 FTS.4. Torque values and gasket stresses for all API
and MSS flanges from 26 inches to 60 inches
(66 cm153 cm) shall be calculated using the GEN-DS-5209 LGF on a
case by case basis to reflect operating pressure.
Studs in Tapped Holes1. For studs threaded into tapped holes,
torque values shall be limited by the weakest set of
threads. While tapped holes are usually in materials with lower
yield strengths than B7 or B16 stud material, additional thread
length can offsets this discrepancy. See the Stud Stuff tab in the
GEN-DS-5209 FCD spreadsheet for calculating stripping loads.
2. If some of the tapped hole threads are damaged, the length of
thread engagement in the calculation shall be reduced by the
percent of damaged threads (e.g., if the threaded hole was 2-inches
deep and 50 percent of the threads damaged, 1.0 inch of thread
engagement can be used for the calculation).
3. To calculate thread stripping loads, the Stud Stuff tab in
GEN-DS-5209 FCD can be used.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 22 of
45
9.4 Piping and Pressure Vessels
9.4.1 General1. For piping and vessel manway flanges that are
either a standard ASME ring joint or a
standard ASME raised face flange, torque values supplied in
Appendix Table A-1 and torque procedure in Appendix Section A.3
shall be used.
2. If manway flanges are a different type, such as GF-C87280,
the gasket stress and torque shall be calculated using the
appropriate spreadsheet.
9.4.2 Leaks1. If a torqued joint leaks after using the proper
assembly procedure, lubrication and
torquing value, the connection shall be retorqued back to the
original torque value. (Do NOT increase the torque value at this
point.)
2. If the joint continues to leak, the feasibility of using a
higher torque value shall be determined after using the proper
spreadsheet and evaluating the impact of higher stud loads on
gasket stress and flange strength.
3. Torque shall not be increased without approval following a
technical review.
9.5 Shell and Tube Heat Exchanger Body Flange Joints1. Heat
exchanger joints (body flanges, floating heads, cover plates, etc.)
shall be torqued using
the torque values and procedure supplied in the work order or
approved data base. 2. The procedure in Appendix Section A.3 (for
less than 24 studs) or Appendix Section B.3
(24 studs or more) shall be followed. 3. If the connection leaks
during the hydrotest, studs shall be retorqued to their original
target
load in accordance with the applicable procedure. 4. If the
joint continues to leak, the requirements in Section 9.4.2 above
shall be followed.
9.6 Torquing Hard to Reach NutsIf torque wrench access to nuts
is blocked by equipment nozzles or other obstructions, the
following procedure shall be used: 1. After all the accessible
studs have been torqued to their final load, start by backing off
one nut
that is easy to reach and then hand tighten. 2. Mark one of the
corners on the nut against the flange and then count the number of
flats the nut
is moved by the time it is fully torqued. 3. Use a slug wrench
or other appropriate tool to move the hard to reach nut(s) the same
number
of flats after they have been hand tightened. Remember to hold
the slug wrench with a device and not your hands.
9.7 Hot Torquing Shell and Tube Exchanger Body Flange Joints
9.7.1 General1. Exchanger body flanges shall be hot torqued
during startup to reload the gasket to the
proper seating stress. 2. Hot torquing shall be performed in a
circular pattern and typically requires one pass,
plus the four studs that are past the point where the torque
pattern was started.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 23 of
45
3. In hot torquing, each nut shall move or be broken loose to
apply the correct torque value. (Torque is measured on a rotating
fastener, not a stationary one.)
4. Studs and nuts tend to stick together (thread embedment)
after sitting for awhile, and additional torque may be required to
overcome this added friction. Contact Engineering before increasing
torque values.
5. Refer to Appendix B Section B.2 for additional
information.
9.7.2 Before Startup1. Before startup, the joint shall be
retorqued to the original specified torque value if the
joint has been pressure tested with hot water or steam or heated
in any way.2. For new exchangers, all studs shall be torqued before
startup to recover any gasket
relaxation that might have occurred while the exchanger was in
storage or transit.
9.7.3 After Startup1. After startup, the joint shall be
retorqued to the specified torque value when the cooler
of the two mating flanges is between 250F and 400F (120C and
205C) on the coolest part of the flange.
2. If the exchanger flange does not reach 250F (120C), hot
torque shall be performed after the exchanger has been in service
for 3 days.
3. If some exchangers have a section of the flange that will
remain below the 250F (120C) minimum hot torque temperature (this
is often a problem on steam generators):a. Hot torque the rest of
the flange if minimum temperature of either mating flange is
over 250F (120C).b. Come back after three (3) days and hot
torque the section of the flange that was
below 250F (120C). The torque pattern shall extend far enough
past the studs that were previously hot torqued such that no nut
movement is observed.
4. Exchanger flange temperature at time of the hot torque shall
be verified with a temperature gun or magnetic thermometer 360
around the perimeter of the flange, and all safety concerns shall
be addressed.
5. The order in which the exchangers will heat up shall be
identified by operations. This order shall be followed for hot
torquing.
6. If there is a concern that the hot torque might have been
done too soon, additional hot torques can be performed with no
impact on gasket performance.
9.7.4 Shell and Tube Body Flange Temperatures Over 400F
(205C)Hot torquing shall preferably not be performed at
temperatures over 400F (205C) as the stud and nut friction factor
increase substantially as the lubricant burns off. This reduces the
accuracy of the stud loads.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 24 of
45
9.8 Shell and Tube Heat Exchanger Leaks on Startup or on the
Run
9.8.1 General1. This step shall require approval before
proceeding with retorquing a leaking joint
during startup or on the run. 2. After approval, exchanger
joints that leak during startup or on the run shall be hot
torqued in accordance with Section 9.8.2.
9.8.2 Procedure1. Lower temperatures where the grease in the
antiseize has not burned off the threads
a. If the grease in the antiseize has not burned off, the joint
shall be retorqued using a circular pattern, plus four studs past
the starting point. Use the original specified torque values and
wait long enough to determine if this stops the leak.
b. Original specified torque value shall not be exceeded without
completing a technical review in accordance with Section 9.4.2.
2. Higher temperatures where the grease in the antiseize has
burned off the threadsa. If the grease in the antiseize has burned
off the turn of the nut method shall be
used. (e.g.,turn each nut the same amount.) b. An engineering
work order shall be issued outlining when to use the turn of
the
nut method and how far each nut should be turned. c. The extent
to which the nut should be moved shall be calculated as a small
amount
of movement can increase the stud load significantly. See the
formula below.
To calculate the change in stud stress per one full flat of nut
rotation:
Stud Stress, psi = 1 / (threads per inch) / (6, total flats on a
hex nut) (Modulus of Elasticity, psi) / (Grip Length, inches)
To calculate the change in stud length:
Change in Length = (Stud Stress, psi) (Grip Length, inches) /
(Modulus of Elasticity, psi)Modulus of Elasticity for B7 Studs =
29,700,000 psi
d. For shell and tube heat exchangers, turning nuts one half
flat can add up to approximately 15,000 psi additional stud load,
assuming 8 threads per inch and a grip length of 20 inches. Note
that this also equals 0.010 inches of stud stretch. Since some of
the mechanical movement can go into flange rotation, some into
gasket relaxation (depending on how long the gasket has been in
service) and some goes into additional stud load, it is difficult
to say exactly how much load will actually go into the stud. Field
data shows that in some cases (e.g. new gaskets during original
assembly) as little as 50 percent of nut rotation actually
transfers into higher stud load.
However, experience has shown that when flange leaks develop,
these are usually the result of low gasket stress (and thus low
stud stress). The 15,000 psi of additional stud stress is enough to
add sufficient gasket stress to reseal the gasket reliably without
having a detrimental effect on the flanges function or reliability.
If there is concern about the level the gasket stress might
increase as the stud load is raised, the gasket stress shall be
recalculated with the new targeted stud stress using the
appropriate spreadsheet.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 25 of
45
All bolted connections relax when heated, and if the connection
is leaking, it is an indication that the gasket and stud stresses
are below what is required to maintain the seal. Adding 15,000 psi
stud stress will raise gasket stresses above the minimum values
needed to seal usually without approaching flange yield values.
Even if we assume that the flange does yield, using the example
above the entire amount of flange roll at the bolt circle would be
limited to the amount that the nut is moved, or 0.010 of an inch.
This is insignificant.
If the connection continues to leak after the 15,000 psi stud
stress has been added, additional analysis to find and correct the
root cause shall be performed, the connection clamped or the gasket
replaced.
e. Start by marking the location of one of the nut corners
against the flange surface and then turn the nut the prescribed
number of flats as directed by the work order.
10.0 TENSIONED JOINTS
10.1 General1. Tensioning the studs is always an option. 2.
Tensioning shall be employed if very accurate stud loads are
required or if studs are going to
be reused (such as reactor and coke drum transition spool flange
studs). 3. Only specific pieces of equipment shall require
tensioning (as specified in the work order),
including some pipe flanges, such as reactor companion
flanges.4. At least one stud diameter shall extend above the nut
for tensioning to be performed.5. Tensioning shall be performed in
accordance with the procedure that will be included with the
work order.
10.2 Joints to Be TensionedThe following shall be tensioned:1.
All reactor inlet and outlet connections with PEG gaskets,
regardless of stud size.2. Coke drum top and bottom transition
spool flanges.3. Applications in which studs are threaded into
blind holes and going to be reused, such as
reactor heads and manways.
10.3 Tensioning Procedure1. At least one fourth of all the studs
shall be tensioned simultaneously. Preferably, half of the
studs should be tensioned at one time if enough tensioning heads
are available.2. Studs have to be pulled to a stud load that is in
excess of the final desired load to compensate
for strain loss when the load is transferred from the tensioning
device to the nut. Some companies over pull by 25 percent to
compensate for this strain loss, but it is recommended that the
additional load requirement be calculated based on the stud grip
length for the specific connection.
3. Tensioning shall be performed by outside contractors that
specialize in tensioning operations. The Supplier usually provides
all the equipment. Tensioning can also be done by specially trained
company mechanics if a facility already owns the equipment.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 26 of
45
4. General written tensioning procedures shall be included in
the work order that cover routine tensioning work. Special
equipment specific written instructions shall be provided if
necessary.
10.4 Hot Tensioning of Heat Exchanger Joints1. After careful
review, hot tensioning on heat exchanger flanges over 250F (122C)
shall be
performed only by qualified personnel.2. Multiple heads shall be
used and rotated in and out of service, or the heads shall be
cooled
between tensioning passes such that the internal seals will not
over heat and fail.3. The O-ring seals in tensioning heads are
rated for approximately 250F (120C) and may fail
due to overheating and leaking hydraulic fluid on to hot flange
surfaces.
10.5 Tensioning Hard to Reach NutsIf access to nuts with
tensioning heads is blocked by equipment nozzles or other
obstructions, the following procedure shall be used: 1. After all
accessible studs have been tensioned to their final load, start by
backing off one nut
that is easy to reach and then hand tighten.
2. Mark one of the corners on the nut against the flange, and
then, count the number of flats the nut is moved by the time it has
been fully retensioned.
3. Tighten the hard to reach nut by hand, and then use a slug
wrench or other appropriate tool to move the nut(s) the same number
of flats. Use a device to hold the slug wrench in place and not
your hands.
11.0 BOILER MANWAYS AND HAND HOLES
11.1 GeneralMost oval boiler manways and hand inspection holes
use boiler pressure to help seat the gasket as the pressure pushes
the cover against the gasket. 1. Oval shaped CGG (1/2 inch (12.7
mm) or greater radial width) or KAG (any radial width)
style gaskets shall be used in these applications. 2. Gasket
stress shall be calculated to ensure that proper gasket seating
loads are achieved.3. The GEN-DS-5209 FCD Oval Gaskets tab, can be
used to calculate oval gasket stresses.
11.2 ProcedureBased on experience, to properly seat oval gaskets
and prevent leakage, the following procedure shall be employed:1.
Tighten the strong back up to the calculated torque value.2. Check
and retighten the strong back, if necessary, during hydrotest.3.
Check and retighten the strong back before starting up the
equipment to recover any gasket
relaxation. 4. Monitor the manways and hand holes for 1 to 2
weeks for leakage. If the joint leaks, it is
unlikely that the strong back will provide enough load to seal
the connection, given that the internal pressure is providing most
of the gasket stress. The unit may have to come down for
repairs.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 27 of
45
12.0 FLANGE INSULATION
12.1 General1. In general, flange joints shall not be
insulated.
Insulating flange joints may cause a joint to leak during a
thermal upset. 2. For personnel protection, a perforated steel
enclosure shall be placed around flanges that pose
a safety concern.3. Exceptions to the not insulating flange rule
are specified in Section 12.2 through
Section 12.6.
12.2 Inclement Weather1. At some facility locations, inclement
weather can have a direct impact on plant operation in
certain piping systems with un-insulated flanges. In such cases,
an analysis or energy audit shall be performed to identify the
reason and justify the cost and risk for insulting the flanges.
2. The insulation plan shall be subject to approval. The
additional risk that comes with the insulation of pipe flanges
shall be considered.
3. The report shall be signed and kept in the inspection files
for the identified system. 4. Insulated flanges shall be checked by
operations for leaks when the plant is back online after a
significant plant upset which results in a sudden drop in
temperature.
12.3 Assembly1. Flanges can be insulated only if assembled in
accordance with this specification. 2. If flanges in piping system
are to be insulated, all flanges shall be broken apart during a
turnaround and all aspects of this specification followed,
including visual inspection of flange faces, proper assembly,
alignment, proper selection of stud and gasket materials, and
torquing to the right stud load.
3. A tag in accordance with Section 12.4 shall be attached as
soon as the flange has been assembled and the QA/QC operation has
been completed.
12.4 Tags1. Flanges in piping systems designated for insulation
and assembled in accordance with this
specification shall be identified with a permanent steel tag
stating that the flange has been assembled in accordance with this
specification and is approved for insulation.
2. Tags shall not be attached unless the person performing the
QA/QC step can verify compliance with this specification.
3. Flanges without tags shall not be insulated. 4. The following
is a sample of the required tag:
5. The tag shall be affixed to the insulation jacket next to the
associated flange such that it is visible after the flange is
insulated.
Assembled per GEN-SU-5209 (date) QA/QC performed by:
_____________
Approved for Insulation
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 28 of
45
12.5 Fixed Equipment, Rotating Equipment, and Valve Bonnet
Flanges1. Fixed equipment, rotating equipment, and valve bonnet
flanges shall not be insulated, unless:
a. Gasket seating stress calculations are performed.b. Gasket
target loads have been met.c. Flanges are broken apart, and all
aspects of this specification are followed.
2. A tag in accordance with Section 12.4 shall be attached as
soon as the flange has been assembled and QA/QC operation has been
completed.
12.6 Temperatures Between 700F and 850F (370C and 455C)Flanges
subject to process service temperatures between 700F and 850F (370C
and 455C) may be insulated only if:1. ASTM A193 Gr. B16 stud
bolting with ASTM A194 Gr.7 nuts are used.2. Flanges comply with
Section 12.2 and Section 12.3.
12.7 Temperatures Above 850F (455C)1. Flanges used in process
service temperatures above 850F (455C) shall never be insulated.2.
Flanges can be covered with weather shields to minimize weather
impact.
12.8 Under Insulation Corrosion ProtectionFlanges shall be
coated or have some method of protection for the following service
conditions:1. Stainless steel piping and flanges if process service
temperatures are less than 400F (205C).2. All other piping and
flanges if process service temperatures are less than 300F
(150C).
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 29 of
45
APPENDIX A
PIPING
A.1 GeneralPipe flange joints shall be assembled in accordance
with this entire appendix.
A.2 Pipe Flange Inspection and Assembly Procedure1. General
Instructions
a. Select the right gasket for the flange class and process
conditions in accordance with this specification, drawing GD-L1264,
and piping class requirements. If there is a conflict, this
specification and drawing GD-L1264 shall govern.
b. For hydrotesting or general flange makeup, all the studs
shall be installed and correctly loaded in accordance with Table
A.1 and Table A.2
c. For hydrotesting, the gasket style intended for final
assembly shall be used. WRI-RJ gaskets may be used to test ring
joint flanges.
d. Gaskets shall be replaced each time a connection is opened.
Exceptions can be made for gaskets that have a graphite covering
which can be replaced, such as some KAG, Kam/PEG, and Kam/ORJ
gaskets, but not SW gaskets.
e. Gaskets for raised face and flat face flanges shall always be
self centering.2. Inspection
a. Cleaning1) Clean the gasket surfaces with a suitable scraper
or wire wheel/brush, as required, to
remove rust/corrosion products, old gasket material, etc. 2)
Wipe the surface clean. 3) Some graphite remaining in flange face
serrations after scraping and wiping clean
shall be acceptable. b. Inspect flanges visually to ensure that
they are free of mechanical damage, radial tool
marks, scratches, corrosion products, pitting, scale, etc. c.
Report any damage. A work order may be issued that outlines further
measurements or
machining of the flange and gasket surfaces that might be
required by the shop or in plant machining company to repair
damaged surfaces.
3. Assemblya. Check flange alignment in accordance with Section
8.10.b. Lubrication and Cleaning of Threads
1) Lubricate the threads (using Jet-Lube 550) on both ends of
the studs and between the nut and bearing surface.
2) Well lubricated used studs and nuts in good condition can be
installed on piping flanges.
3) If the nuts do not run down easily on both ends of the stud
by using only the fingers, clean the threads using a tap and/or die
to fix the problem or replace the stud or nut.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 30 of
45
4) Loose material can be removed from the threads with a wire
brush, but this procedure shall not be used for removing galling or
restoring the friction between the nut and stud back to like new
condition because it is ineffective.
c. Hardened Washer1) Install an ASTM F-436 washer under the nut
to be tightened if the flange area under
the nut has evidence of galling, grooving, or the nut does not
have an integral washer built in.
2) Install the washer under the nut on the side of the flange
such that the torque wrench can be pulled in a down direction
during torquing.
3) Ensure that the integral washer side of nut is face down and
raised letters are faced up.4) Install half the studs around one
side of the flange and insert the gasket.
Note DO NOT coat gaskets with antiseize. Install the remaining
studs and pull the flanges down evenly.
d. Tightening Tolerances1) Tighten the studs either with hand
wrenches, Regulated Air Drive (RAD) tools, or air
impacts to snug to hold the components in place. 2) Measure the
gap around the flange with a flange gap tool or caliper. 3) After
final assembly, RF and Tongue and Groove and Ring Joint (RTJ)
flanges less
than 24 inches in diameter shall be less than 1/32 inch of
parallel (cocked) as measured across any flange outside
diameter.
e. Tightening Pattern1) Tighten the studs using a star pattern
with a hand wrench, RAD torque gun (air
regulated impact gun), or air impact. Use as many passes as
needed to keep the flanges parallel.
2) Do not exceed the final targeted stud load. 3) For flanges
with studs that require a torque value of 200 ft-lb (270 Nms) or
more, a
calibrated torque wrench shall be required on the final pass to
obtain the specified torque value.
4) Use hydraulic torque equipment on stud loads over 1,000 ft-lb
(1350 Nm). 5) Refer to Appendix Table A-1 and Appendix Table A-2
for pipe flange torque values
and Appendix Section A.3 for details on the tightening
pattern.
Note Torque multipliers shall not be allowed due to decrease in
accuracy.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 31 of
45
f. Final Pass1) The final pass with the torque wrench shall be
made in a circular pattern, provided that
at least 80 percent of the final stud load has already been
applied. 2) If a nut has been over tightened and will not turn
while using the torque wrench, back
off slightly on the nut and retighten it to the specified torque
value.4. Complete GEN-DS-5209 PPV for torqued flanges and sign off
on the appropriate steps.
a. Send this data sheet to the QA/QC group or the work order
originator, if a QA/QC group is not being used, or the EWO
originator.
b. Approved Supplier QA/QC process sign-off and documentation
for tightening flanges may be used in place of GEN-DS-5209 PPV, as
long as information required in GEN-DS-5209 PPV is included in
Contractor documentation.
5. Hot TorqueHot torque shall not be required on pipe flanges,
unless specified in the work order.
A.3 Star Pattern Torquing Procedure for PipingThe following
torque pattern is intended for all piping connection types,
including piping connections to vessels, regardless of the gasket
used:1. For initial tightening, the star pattern in Figure A-1
shall be used. As long as the flanges are
taken up evenly, working from one side to the other in a
rotating pattern around the flange, the actual pattern or direction
around the flange does not matter.
2. After at least 80 percent of the final load has been set, the
final load can be set in a circular pattern. The nuts should move
on this pass. If the nuts do not move, use a calibrated torque
wrench to check the final load reached. Record and report the
loads.
3. Tighten the studs to 100 percent of the specified torque
value in a circular pattern. For flanges tightened to 200 ft-lb
(270 Nm) and higher, a calibrated torque wrench shall be used to
set the final required load, and hydraulic torque wrenches or
tensioners shall be used for studs requiring ASME Pipe Flange
Torque Values 1,000 ft-lb (1350 Nm) or more. If the nuts move on
this pass, make additional passes until the nuts stop turning.
-
Flange Gaskets and Bolting GEN-SU-5209
June 2009 2009 Chevron U.S.A. Inc. All rights reserved. 32 of
45
Figure A-1:Traditional Star Pattern
TRADITIONAL STAR PATTERN
S e q u e n t i a l O r d e r
R o t a t i o n a l O r d e r
1 - 2 1 23 - 4 9 1 05 - 6 1 7 1 8 7 - 8 5 6
9 - 1 0 1 3 1 4 1 1 - 1 2 2 1 2 2 1 3 - 1 4 3 4 1 5 - 1 6 1 1 1
2 1 7 - 1 8 1 9 2 0 1 9 - 2 0 7 8 2 1 - 2 2 1 5 1 6 2 3 - 2 4 2 3 2
4
-
Flange Gaskets and B
oltingG
EN-SU
-5209
June 2009
2009 Chevron U
.S.A. Inc. A
ll rights reserved.33 of 45
Table A-1: Pipe Flange Torque Values (1 of 5)
PIPE FLANGE TORQUE VALUES
Pipe Size Qty Dia. Length Slip Bld Qty Dia. Length Slip Bld Qty
Dia. Length Slip Bld3/4 4 1/2 2 1/2 3 40 40 4 5/8 4 4 1/2 50 4 3/4
4 1/2 5 1/2 60
1 4 1/2 3 3 1/2 50 50 4 5/8 4 4 1/2 70 4 7/8 5 6 1001 1/2 4 1/2
3 3 1/2 60 60 4 3/4 4 1/2 5 130 4 1 5 1/2 6 1/2 2502 4 5/8 3 1/2 4
130 100 8 5/8 4 1/2 5 80 8 7/8 6 7 1803 4 5/8 4 4 1/2 130 130 8 3/4
5 6 150 8 1 1/8 7 1/2 8 1/2 3504 8 5/8 4 4 1/2 120 80 8 7/8 6 7 330
8 1 1/4 8 9 1/2 6005 8 3/4 4 5 200 160 8 1 6 1/2 7 1/2 480 8 1 1/2
10 11 1/2 9406 8 3/4 4 5 220 220 12 1 7 8 470 12 1 3/8 10 1/2 12
7508 8 3/4 4 1/2 5 220 220 12 1 1/8 8 9 700 12 1 5/8 12 13 1/2
1,280
10 12 7/8 5 5 1/2 350 290 16 1 1/4 8 1/2 10 840 12 1 7/8 13 1/2
15 1/2 2,03012 12 7/8 5 6 350 310 20 1 1/4 9 10 1/2 840 16 2 15 17
2,10014 12 1 5 1/2 6 1/2 530 430 20 1 3/8 9 1/2 11 940 16 2 1/4 16
1/2 18 1/2 2,48016 16 1 5 1/2 6 1/2 480 360 20 1 1/2 10 12 1,290 16
2 1/2 18 20 1/2 3,98018 16 1 1/8 6 7 750 590 20 1 5/8 11 12 1/2
1,990 16 2 3/4 19 1/2 22 1/2 5,63020 20 1 1/8 6 1/2 7 1/2 750 540
24 1 5/8 11 1/2 13 1/2 1,970 16 3 21 1/2 24 1/2 7,13024 20 1 1/4 7
8 1/2 1,130 760 24 1 7/8 13 15 2,630 16 3 1/2 24 1/2 28 11,250
1/2 7/8Pipe Size Qty Dia. Length Slip Bld Qty Dia. Length Slip
Bld Qty Dia. Length Slip Bld 5/8 1-1/16
3/4 4 5/8 3 4 50 50 4 3/4 5 6 70 3/4 1-1/41 4 5/8 3 1/2 4 70 70
4 7/8 5 1/2 6 1/2 110 7/8 1-7/161 1/2 4 3/4 4 4 1/2 130 130 4 1 1/8
7 8 300 1 1-5/82 8 5/8 3 1/2 4 1/2 70 70 8 1 7 8 200 1-1/8 1-13/163
8 3/4 4 1/2 5 140 140 8 7/8 6 7 250 8 1 1/4 9 10 1/2 450 1-1/4 24 8
3/4 4 1/2 5 1/2 220 190 8 1 1/8 7 8 450 8 1 1/2 10 1/2 12 750 1-3/8
2-3/165 8 3/4 5 5 1/2 220 220 8 1 1/4 7 1/2 9 840 8 1 3/4 13 1/2 14
1,280 1-1/2 2-3/86 12 3/4 5 6 200 190 12 1 1/8 8 9 530 8 2 14 16
1,880 1-5/8 2-9/168 12 7/8 5 1/2 6 1/2 330 310 12 1 3/8 9 10 1/2
840 12 2 15 1/2 17 1/2 1,880 1-3/4 2-3/4
10 16 1 6 1/2 7 1/2 420 420 16 1 3/8 9 1/2 11 840 12 2 1/2 19
1/2 22 3,080 1-7/8 2-15/1612 16 1 1/8 7 8 630 630 20 1 3/8 10 1/2
11 1/2 990 12 2 3/4 21 1/2 24 4,950 2 3-1/814 20 1 1/8 7 1/2 8 1/2
500 480 20 1 1/2 11 12 1/2 1,280 2-1/4 3-1/216 20 1 1/4 8 9 710 710
20 1 5/8 11 1/2 13 1,580 2-1/2 3-7/818 24 1 1/4 8 9 1/2 880 840 20
1 7/8 13 15 2,590 2-3/4 4-1/420 24 1 1/4 8 1/2 9 1/2 880 840 20 2
14 16 2,850 3 4-5/824 24 1 1/2 9 1/2 11 1,310 1,310 20 2 1/2 17 1/2
20 4,650 3-1/2 5-3/8
Slip Blind for Turnaround Isolation - No hydrotestTorque Fp's
SS
Use Washers if flange is galled or badly warn.Hydraulic Torque
RequiredASME SA-105 CS Flanges, B7 & B7M Studs Hand Tighten
Must be Torqued
Note separate Torque Values for 300 Series SS flanges!
Torque Fp's
150 RAISED FACE
Torque Fp's
Torque Fp's
600 RAISED FACE
2500 RAISED FACE
1500 RAISED FACE
Dimensions in Inches
Studs recommended for 125/150 FF Flg's. Do not mate FF Cast Iron
with RF Carbon Steel.
M
F
G
-
7
3
0
4
(
1
2
/
0
8
)
Torque Fp's
Torque Fp's
Chevron Bolting and Torque Card
Torque in Foot Pounds
(Fp's)
Hvy Hex Nuts
Wrench Size
300 RAISED FACE Torque Fp's
Not made. Use 1500 class flanges Information
900 RAISED FACE Torque Fp's SS
-
Flange Gaskets and B
oltingG
EN-SU
-5209
June 2009
2009 Chevron U
.S.A. Inc. A
ll rights reserved.34 of 45
Table A-1: Pipe Flange Torque Values (2 of 5)
Pipe Size Ring # Qty Dia. Length Slip Bld Ring # Qty Dia. Length
Slip Bld Ring # Qty Dia. Length Slip Bld3/4 R-13 4 5/8 3 1/2 4 1/2
80 80 R-16 4 3/4 5 6 110
1 R-16 4 5/8 3 1/2 4 1/2 80 80 R-18 4 7/8 5 1/2 6 1/2 1501 1/2
R-20 4 3/4 4 1/2 5 130 130 R-23 4 1 1/8 7 8 3402 R-23 8 5/8 4 1/2 5
90 70 R-26 8 1 7 1/2 8 1/2 2003 R-31 8 3/4 5 6 160 150 R-31 8 7/8 6
7 200 R-32 8 1 1/4 9 1/2 10 1/2 4004 R-37 8 3/4 5 1/2 6 200 190
R-37 8 1 1/8 7 8 1/2 330 R-38 8 1 1/2 10 1/2 12 8105 R-41 8 3/4 5
1/2 6 1/2 230 230 R-41 8 1 1/4 8 9 470 R-42 8 1 3/4 12 1/2 14 1/2
1,4306 R-45 12 3/4 6 6 1/2 200 190 R-45 12 1 1/8 8 9 350 R-47 8 2
14 1/2 16 1/2 2,0408 R-49 12 7/8 6 1/2 7 1/2 300 300 R-49 12 1 3/8
9 10 1/2 580 R-51 12 2 16 18 1,990
10 R-53 16 1 7 8 300 300 R-53 16 1 3/8 9 1/2 11 580 R-55 12 2
1/2 20 1/2 23 3,68012 R-57 16 1 1/8 7 1/2 9 430 430 R-57 20 1 3/8
10 1/2 12 580 R-60 12 2 3/4 22 1/2 25 1/2 5,40014 R-61 20 1 1/8 8 9
400 400 R-62 20 1 1/2 11 1/2 13 97016 R-65 20 1 1/4 8 1/2 10 510
510 R-66 20 1 5/8 12 13 1/2 1,28018 R-69 24 1 1/4 8 1/2 10 490 490
R-70 20 1 7/8 13 1/2 15 1/2 2,03020 R-73 24 1 1/4 9 10 1/2 640 640
R-74 20 2 14 1/2 16 1/2 2,40024 R-77 24 1 1/2 10 1/2 12 1,200 1,200
R-78 20 2 1/2 18 1/2 21 4,350
Pipe Size Ring # Qty Dia. Length Slip Bld Ring # Qty Dia. Length
Slip Bld Pipe Size Qty Dia. Length Slip Bld3/4 R-13 4 5/8 3 1/2 4
1/2 80 R-14 4 3/4 4 1/2 5 1/2 100 3/4 4 1/2 2 1/2 3 70
1 R-16 4 5/8 4 4 1/2 90 R-16 4 7/8 5 6 130 1 4 1/2 2 1/2 3 701
1/2 R-20 4 3/4 4 1/2 5 140 R-20 4 1 5 1/2 6 1/2 200 1 1/2 4 1/2 3 3
1/2 702 R-23 8 5/8 4 1/2 5 90 R-24 8 7/8 6 7 150 2 4 5/8 3 4 1303
R-31 8 3/4 5 1/2 6 160 R-35 8 1 1/8 7 1/2 8 1/2 300 3 4 5/8 3 1/2 4
1304 R-37 8 7/8 6 7 240 R-39 8 1 1/4 8 9 1/2 460 4 8 5/8 3 1/2 4
1/2 1305 R-41 8 1 7 8 350 R-44 8 1 1/2 10 11 1/2 650 5 8 3/4 4 4
1/2 2306 R-45 12 1 7 8 280 R-46 12 1 3/8 11 12 530 6 8 3/4 4 5 2308
R-49 12 1 1/8 8 9 420 R-50 12 1 5/8 12 14 1,090 8 8 3/4 4 1/2 5
230
10 R-53 16 1 1/4 9 10 450 R-54 12 1 7/8 14 16 1,630 10 12 7/8 4
1/2 5 1/2 38012 R-57 20 1 1/4 9 10 1/2 450 R-58 16 2 16 18 2,030 12
12 7/8 5 5 1/2 38014 R-61 20 1 3/8 9 1/2 11 600 R-63 16 2 1/4 17 19
1/2 2,850 14 12 1 5 1/2 6 1/2 57016 R-65 20 1 1/2 10 1/2 12 750
R-67 16 2 1/2 19 21 1/2 3,980 16 16 1 5 1/2 6 1/2 57018 R-69 20 1
5/8 11 13 980 R-71 16 2 3/4 21 23 1/2 5,180 18 16 1 1/8 6 7 1/2
83020 R-73 24 1 5/8 12 13 1/2 1,050 R-75 16 3 23 26 6,750 20 20 1
1/8 6 1/2 7 1/2 83024 R-77 24 1 7/8 13 1/2 15 1/2 1,800 R-79 16 3
1/2 26 29 1/2 10,500 24 20 1 1/4 7 8 1/2 1,160
Note separate Torque Values for 300 Series SS flanges! Use
Washers if flange is galled or badly warn.Slip Blind for Turnaround
Isolation - No hydrotest Contact your local bolting SME for help or
David Reeves at 310-941-8827
ASME SA-105 CS Flanges, B7 & B7M Studs Hand Tighten Must be
Torqued Hydraulic Torque RequiredDimensions in Inches
Torque FP's
Torque FP's
Not made. Use 1500 class flanges Information
125/150 FULL FACE (Stud Bolts)
Torque FP's
900 RTJ 2500 RTJ
Torque FP's
Torque FP's
Torque FP's
Torque Fp's SS
300 RTJ
600 RTJ 1500 RTJ
-
Flange Gaskets and B
oltingG
EN-SU
-5209
June 2009
2009 Chevron U
.S.A. Inc. A
ll rights reserved.35 of 45
Table A-1: Pipe Flange Torque Values (3 of 5)
Pipe Size Qty Dia. Length Slip Bld Qty Dia. Length Slip Bld Qty
Dia. Length Slip Bld3/4 4 1/2 2 1/2 3 50 50 4 5/8 4 4 1/2 70 4 3/4
4 1/2 5 1/2 80
1 4 1/2 3 3 1/2 70 70 4 5/8 4 4 1/2 90 4 7/8 5 6 1301 1/2 4 1/2
3 3 1/2 80 80 4 3/4 4 1/2 5 180 4 1 5 1/2 6 1/2 3402 4 5/8 3 1/2 4
180 130 8 5/8 4 1/2 5 110 8 7/8 6 7 2403 4 5/8 4 4 1/2 180 180 8
3/4 5 6 200 8 1 1/8 7 1/2 8 1/2 4704 8 5/8 4 4 1/2 160 110 8 7/8 6
7 440 8 1 1/4 8 9 1/2 8105 8 3/4 4 5 270 220 8 1 6 1/2 7 1/2 650 8
1 1/2 10 11 1/2 1,2706 8 3/4 4 5 300 300 12 1 7 8 630 12 1 3/8 10
1/2 12 1,0108 8 3/4 4 1/2 5 300 300 12 1 1/8 8 9 940 12 1 5/8 12 13
1/2 1,720
10 12 7/8 5 5 1/2 470 390 16 1 1/4 8 1/2 10 1,130 12 1 7/8 13
1/2 15 1/2 2,73012 12 7/8 5 6 470 420 20 1 1/4 9 10 1/2 1,130 16 2
15 17 2,83014 12 1 5 1/2 6 1/2 710 580 20 1 3/8 9 1/2 11 1,270 16 2
1/4 16 1/2 18 1/2 3,34016 16 1 5 1/2 6 1/2 650 480 20 1 1/2 10 12
1,740 16 2 1/2 18 20 1/2 5,36018 16 1 1/8 6 7 1,010 790 20 1 5/8 11
12 1/2 2,680 16 2 3/4 19 1/2 22 1/2 7,58020 20 1 1/8 6 1/2 7 1/2
1,010 730 24 1 5/8 11 1/2 13 1/2 2,650 16 3 21 1/2 24 1/2 9,60024
20 1 1/4 7 8 1/2 1,520 1,020 24 1 7/8 13 15 3,540 16 3 1/2 24 1/2
28 15,150
1/2 7/8Pipe Size Qty Dia. Length Slip Bld Qty Dia. Length Slip
Bld Qty Dia. Length Slip Bld 5/8 1-1/16
3/4 4 5/8 3 4 70 70 4 3/4 5 6 90 3/4 1-1/41 4 5/8 3 1/2 4 90 90
4 7/8 5 1/2 6 1/2 150 7/8 1-7/161 1/2 4 3/4 4 4 1/2 180 180 4 1 1/8
7 8 400 1 1-5/82 8 5/8 3 1/2 4 1/2 90 90 8 1 7 8 270 1-1/8 1-13/163
8 3/4 4 1/2 5 190 190 8 7/8 6 7 340 8 1 1/4 9 10 1/2 610 1-1/4 24 8
3/4 4 1/2 5 1/2 300 260 8 1 1/8 7 8 610 8 1 1/2 10 1/2 12 1,010
1-3/8 2-3/165 8 3/4 5 5 1/2 300 300 8 1 1/4 7 1/2 9 1,130 8 1 3/4
13 1/2 14 1,720 1-1/2 2-3/86 12 3/4 5 6 270 260 12 1 1/8 8 9 710 8
2 14 16 2,530 1-5/8 2-9/168 12 7/8 5 1/2 6 1/2 440 420 12 1 3/8 9
10 1/2 1,130 12 2 15 1/2 17 1/2 2,530 1-3/4 2-3/4
10 16 1 6 1/2 7 1/2 570 570 16 1 3/8 9 1/2 11 1,130 12 2 1/2 19
1/2 22 4,150 1-7/8 2-15/1612 16 1 1/8 7 8 850 850 20 1 3/8 10 1/2
11 1/2 1,330 12 2 3/4 21 1/2 24 6,660 2 3-1/814 20 1 1/8 7 1/2 8
1/2 670 650 20 1 1/2 11 12 1/2 1,720 2-1/4 3-1/216 20 1 1/4 8 9 960
960 20 1 5/8 11 1/2 13 2,130 2-1/2 3-7/818 24 1 1/4 8 9 1/2 1,180
1,130 20 1 7/8 13 15 3,490 2-3/4 4-1/420 24 1 1/4 8 1/2 9 1/2 1,180
1,130 20 2 14 16 3,840 3 4-5/824 24 1 1/2 9 1/2 11 1,7