Page 1
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-1 Structures
13 STRUCTURES
13.1 General
The Design-Builder shall conduct all Work necessary to meet the requirements of permanent and temporary
Structures, including bridges, retaining walls, barriers, box culverts, circular pipes, precast concrete
structures, long-span structures, protection of utilities, temporary construction access structures, shoring and
false work, cofferdams, form travelers, gantries, cranes, sign structures, lighting structures, and structure
renovations.
13.2 Administrative Requirements
13.2.1 Standards
The Design-Builder shall perform the Structures work in accordance with the manuals and documents listed
in Book 3. In the event of a conflict among the standards set forth in Book 3, the order of precedence shall be
as set forth below, unless noted otherwise:
13.2.1.1 All Structures, Structural Appurtenances, and Retaining Walls
Agency Title
Caltrans California Amendments to the AASHTO LRFD Bridge Design Specifications
AASHTO LRFD Bridge Design Specifications, 4th Edition
Caltrans Seismic Design Criteria
Caltrans Guide Specifications for Seismic Design of Steel Bridges
AASHTO LRFD Bridge Design Specifications, 5th Edition
AASHTO LRFD Guide Specifications for Design of Pedestrian Bridges
AASHTO Guide Manual for Condition Evaluation and Load and Resistance Factor Rating
(LRFR) of Highway Bridges
Caltrans Bridge Memo to Designers
Caltrans Bridge Design Aids
Caltrans Bridge Design Details
Caltrans Bridge Design Practice Manual
Caltrans Bridge Standard Detail Sheets
AASHTO Guide Specifications for LRFD Seismic Bridge Design
Caltrans Structural Detailing Standards
Various Special Provisions
Caltrans Standard Plans
Caltrans Standard Specifications*
Caltrans Bridge Design Specifications
Caltrans New Product Evaluation Guidelines
Caltrans A Test Plan for the Characterization and Qualification of Highway Bridge Seismic
Isolator and Damping Devices
Page 2
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-2 Structures
Caltrans A Test Plan for the Characterization and Qualification of Highway Bridge Seismic
Isolation Bearing Devices
AASHTO Guide Specifications for Design and Construction of Segmental Concrete Bridges
AASHTO Guide Specifications for Seismic Isolation Design
AASHTO Guide Specification for Highway Bridge Fabrication with HPS70W (HPS 485W)
Steel
PTI Recommendations for Stay Cable Design, Testing and Installation
CEB-FIP Model Code for Concrete Structures, Appendix E: Time Dependent Behavior of
Concrete, Creep and Shrinkage
TRB NCHRP Report 645, Blast-Resistant Highway Bridges: Design and Detailing
Guidelines
ACI Building Code Requirements for Structural Concrete (ACI 318-08) and Commentary
AISC Seismic Design Manual
AISC Steel Construction Manual
AASHTO/AWS D1.5M/D1.5 Bridge Welding Code
ANSI/AASHTO/AWS D1.1M/D1.1 Structural Welding Code
ATC-32 Improved Seismic Design Criteria for California Bridges: Provisional
Recommendations
TRB NCHRP Report 472, Comprehensive Specification for the Seismic Design of
Bridges
ASCE/SEI Minimum Design Loads for Buildings and Other Structures
ASCE Guidelines for the Design of Cable-Stayed Bridges
Caltrans Bridge Deck Construction Manual
Caltrans Falsework Manual
Caltrans Foundation Manual
Caltrans Office of Special Funded Projects (OSFP) Information and Procedures Guide
Caltrans Prestress Manual
Caltrans Construction Manual
Caltrans Bridge Construction Records and Procedures Manual
Caltrans Trenching and Shoring Manual
Caltrans Plans Preparation Manual (PPM)
AASHTO Manual for Bridge Evaluation
Caltrans Highway Design Manual (HDM)
Various Remaining standards set forth in Book 3
*Document modified for design-build.
Page 3
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-3 Structures
13.2.1.2 Sign and Lighting Structures
Caltrans Standard Plans
AASHTO Standard Specifications for Structural Supports for Highway Signs, Luminaires and
Traffic Signals
Various Remaining standards set forth in Book 3
13.2.2 Definitions
Main Span Bridge — That portion of the Project that consists of the bridge structure that carries Ocean
Boulevard over the Back Channel and extends between deck expansion joints on either side of the Back
Channel. The Main Span Bridge includes the cable-stayed bridge superstructure, towers, adjacent end bents,
and adjacent expansion joints.
Approach Bridges — Those portions of the Project that consist of the bridge structures not included as part
of the Main Span Bridge.
Seismic Energy Product – A seismic response modification devices or element that dissipates or otherwise
handles seismic energy that is subject to compliance with the Caltrans California Department of
Transportation New Product Evaluation Guidelines.
Energy Dissipating Shear Link – An element with no moving parts that dissipates seismic energy.
Seismic Energy Fuse – An element that dissipates seismic energy and does not include Energy Dissipating
Shear Links or elements that would fall under the Caltrans California Department of Transportation New
Product Evaluation Guidelines.
The term ―AASHTO LRFD Bridge Design Specifications, 4th Edition, with California Amendments‖ shall
mean the requirements contained in the AASHTO LRFD Bridge Design Specifications, 4th Edition as
amended by the Caltrans California Amendments to the AASHTO LRFD Bridge Design Specifications. If the
Caltrans California Amendments to the AASHTO LRFD Bridge Design Specifications do not contain a
modification or amendment to AASHTO LRFD Bridge Design Specifications, 4th Edition for a given
section, the Design-Builder shall comply with the requirements in AASHTO LRFD Bridge Design
Specifications, 4th Edition. Interim updates to the AASHTO LRFD Bridge Design Specifications, 4th Edition
are included via the Caltrans California Amendments to the AASHTO LRFD Bridge Design Specifications.
13.2.3 Meetings
The Design-Builder shall meet with the Port and the Department at Department Headquarters in Sacramento,
CA prior to creating load rating models to discuss and understand the requirements related to these models
and their future use.
Prior to submitting the Painting Quality Work Plan required herein, a pre-painting meeting including the
Port, the Design-Builder, the Design-Builder’s Quality Control Manager, a representative from each entity
performing painting for this Project, and a representative from the paint manufacturer, shall be held to
discuss the requirements for the Painting Quality Work Plan.
The Design-Builder shall conduct a three-day accident and terrorist risk analysis workshop per Exhibit 2-13-
F (Accident and Terrorist Vulnerability Assessment (ATVA) Requirements).
Unless noted otherwise, the Design-Builder shall complete the following tasks associated with meetings:
Schedule the meeting
Have present the staff will be directly involved in the topic of the meeting
Invite the staff from the Port and the Department, as required per the Port
Facilitate and run the meeting
Page 4
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-4 Structures
Provide an agenda for the meeting, draft meeting minutes within three Days of the meeting and final
meeting minutes within three Days of receiving comments to the draft minutes
Provide a location for the meeting
13.2.4 Software Requirements
The Design-Builder shall use the commercially accessible computer bridge analysis programs, CSI BRIDGE
or MIDAS, to complete bridge load ratings.
The Design-Builder shall use the commercially accessible computer bridge analysis program, ADINA, for
either the original seismic nonlinear time-history design model or the independent check seismic nonlinear
time-history design model.
Unless otherwise specified in the Contract Documents, the Design-Builder shall ensure the most current
version of the required software as of the date listed in Book 1, Section 1.5 (Referenced Standards and
Specifications) is used.
13.3 Design Requirements
13.3.1 Bridge Names and Numbers
The Design-Builder shall request a bridge or structure number and name from the Department for new and
replacement bridges and wall structures. The request shall include:
County and State Route Identification Number for the roadway carried by the bridge or supported by the
wall.
Post Mile at beginning of bridge or wall (to the nearest .01 Post Mile).
Site map or strip map of sufficient detail to clearly indicate the relationship of the street names and
names of the pertinent features in the vicinity of the bridge or wall site.
The assigned bridge or wall name and number shall be painted on all structures. Locations indicating where
to paint the number and name on a structure shall be shown on the General Plan in accordance with the
Caltrans Bridge Design Details.
13.3.2 Concept Design Submittal and Technical Advisory Panel Review
13.3.2.1 Concept Design Submittal
The Design-Builder shall prepare a Concept Design Submittal that contains a Preliminary General Plan and
Type Selection Report for each structure requiring a type selection process. Preliminary General Plan and
Type Selection Report shall be prepared in accordance with preliminary data checklists provided in Caltrans
Bridge Design Aids and Bridge Memo to Designers 1-29. Each Type Selection Report shall include the
following:
Evaluation and location of deck drains for widened structures.
Recommended maintenance work reflected in structure maintenance records, if applicable.
A quantitative seismic retrofit evaluation of all existing structures to be widened, modified, or replaced. For existing structures to be widened, the Type Selection Report shall include a summary of the seismic
evaluation of the existing bridge, the potential retrofit strategies with supporting documentation, and other
pertinent details.
Preliminary foundation reports, geotechnical reports, and other applicable documents
Each Type Selection Report shall clearly delineate aesthetic features the Design-Builder has or will
incorporate into the structure type. The bridge aesthetic treatments shall be reviewed and Approved as part of
the Visual Quality Management Process outlined in Section 15.
Page 5
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-5 Structures
All Concept Design Submittal Meetings will be scheduled after the Port has Approved the Project geometrics
and a minimum of five Working Days following receipt of a complete Concept Design Submittal and all
related documents. At the meeting, the Design-Builder shall present the proposed structure and shall briefly
discuss issues pertinent to the selection of the structure type, particularly requirements for foundations,
hydraulics, construction (including falsework), seismic design, retrofit strategy, aesthetics, traffic handling,
and other information needed, as applicable, to support the structure type.
After the meeting, the Design-Builder shall prepare a meeting summary and provide a copy to the Port within
three Working Days. The meeting summary may be used to update or supplement the information in the
Concept Design Submittal to address comments raised at the meeting. Provided all comments are
satisfactorily addressed, the Port will provide Approval or denial of the proposed structure type within five
Working Days of receiving the final meeting summary.
Within two weeks after receiving written Approval of the structure type, the Design-Builder shall update the
Preliminary General Plan and submit the required number of reduced copies to Port for comment.
Additional Concept Design Submittal information to complete the structure type selection process for each
structure shall follow Section 4-2 of the OSFP Information and Procedures Guide and the applicable
portions of the Bridge Memo to Designers.
13.3.2.2 Technical Advisory Panel Review
The Design-Builder shall assemble and convene a Technical Advisory Panel (TAP) to in accordance with
Exhibit 2-13-C (Technical Advisory Panel Charter and Review Process).
13.3.3 Not Used
13.3.4 Not Used
13.3.5 Not Used
13.3.6 Temporary Structures
The Design-Builder shall provide temporary walls, access bridges, cofferdams, formwork, falsework,
environmental containment, shoring, protection of Utilities, protection and shoring of existing structures,
cranes, form travelers, and any other temporary structures needed to perform the Work.
13.3.7 Demolition of Structures
The Design-Builder shall demolish the bridges listed in Table 13-1 and associated substructures,
superstructures, wall structures and appurtenances. Demolished materials and miscellaneous items associated
with the bridge being removed, such as guardrail and backfill, shall also be removed from the Site.
Table 13-1: Existing Bridges To Be Removed
Existing Bridge No. Approximate Limits
53C-0065
(Existing Gerald Desmond Bridge)
Removal of substructures and superstructures from
Pier 34 to Abutment 50 including Pier 34, Abutment
50, associated appurtenances at Abutment 50 and the
span between Pier 33 and 34, as required, to
complete the Work
53C-0884 Entirely remove
53C-2049 Entirely remove
Page 6
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-6 Structures
53C-2050 Entirely remove
Existing substructure units shall be removed to at least 2 feet below finished grade, and more if required for
the Work.
If existing structures are to be partially removed to allow construction of the Project, the Design-Builder shall
maintain sufficient structural capacity in accordance with the Contract Documents. The Design-Builder shall
ensure existing facilities support all loading conditions anticipated to occur and are modified as necessary
prior to transfer of traffic from the existing facility to the new facility. If temporary elements are needed, the
Design-Builder shall, at a minimum, design the elements for seismic resistance of 10 percent of the tributary
dead load being supported.
Design documents must show the location(s) of equipment used for demolition, sequence of removal,
loading limits, allowable location of loads, equipment specifications including their weight, and any other
material, which will be placed on the structure during or prior to demolition for all structures.
13.3.8 Bridge Structure Element Products
13.3.8.1 Seismic Energy Product Evaluation
All manufactured bridge element products including bearings, joint seal assemblies, dampers, seismic and
isolation devices shall be on a Caltrans Pre-qualified List or become pre-qualified for this Project through the
Caltrans New Product Evaluation process, unless specifically exempt by Port. The Design-Builder is
responsible for obtaining any necessary pre-qualification of products.
All Seismic Energy Products, including isolation bearings and dampers, shall be pre-qualified in accordance
with the requirements of Caltrans New Product Evaluation Guidelines and shall be tested in accordance with
Caltrans A Test Plan for the Characterization and Qualification of Highway Bridge Seismic Isolator and
Damping Devices and Caltrans A Test Plan for the Characterization and Qualification of Highway Bridge
Seismic Isolation Bearing Devices.
The design and testing of Seismic Energy Products shall reflect the actual load conditions and load
combinations in accordance to the AASHTO LRFD Bridge Design Specifications, 4th Edition, with
California Amendments.
The design of seismic isolation devices shall follow the AASHTO Guide Specifications for Seismic Isolation
Design.
13.3.8.2 Energy Dissipating Shear Link Evaluation
If the Design-Builder elects to use Energy Dissipating Shear Links, the Design-Builder shall comply with the
requirements for Energy Dissipating Shear Links in Exhibit 2-13-A (Design Criteria), except that the Design-
Builder shall modify (cycles, loading, etc) the testing protocol for their specific situation.
13.3.8.3 Seismic Energy Fuse Evaluation
If the Design-Builder elects to use Seismic Energy Fuses, the Design-Builder shall provide a Seismic Energy
Fuse Testing Protocol that, at a minimum, contains the same information required for Energy Dissipating
Shear Links in Exhibit 2-13-A (Design Criteria), except that the Design-Builder shall create a new testing
protocol for their specific situation.
13.3.8.4 Viscous Dampers
If viscous dampers are used, the Design-Builder shall design the dampers for operating loads and seismic
loads according to the AASHTO LRFD Bridge Design Specifications, 4th Edition, with California
Amendments and as follows, at a minimum:
Page 7
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-7 Structures
The design of the dampers shall conform to the AASHTO Guide Specifications for Seismic Isolation if
the dampers are for resisting seismic forces.
The number of cycles for damper movement, velocity, and displacement for the seismic design shall all
be based on the bridge model prepared by the Design-Builder.
The dampers shall have a port for recharging the fluid inside the piston chamber, an additional port for
bleeding air from the chamber, and a glass window to observe the fluid level inside the chamber or an
instrument to measure the volume of fluid in the piston chamber.
The Design-Builder shall provide a minimum of three pressure gages for measuring fluid pressure inside
the piston chamber.
The dampers shall be coupled or connected with force transducer for measurement of actual forces
applied into the dampers. The transducer shall not interfere with the damper’s performance during seismic
events.
Viscous dampers shall have a minimum of a ten-year warranty starting from Final Acceptance. The
warranty shall cover and list explicitly all the potential defects that will affect the damper’s performance.
13.3.9 Special Wind Loads
13.3.9.1 Testing and Design
The Design-Builder shall perform sectional model wind tunnel testing to verify satisfactory performance of
the Main Span Bridge.
The Design-Builder shall use Exhibit 2-13-B (Wind Climate Data) for the required wind speeds for stability
and structural design of the Main Span Bridge. A 20-year design wind load shall be used for construction
stage analysis instead of that shown in Exhibit 2-13-B.
The Design-Builder shall submit a Wind Tunnel Test Report containing the following information, at a
minimum:
Introduction
Wind climate and site analysis, including introduction, data sources, methodology, results, conclusions,
and recommendations
Section model test information, including objectives and criteria, model description, wind tunnel test
procedures, aerodynamic stability results, and static force and moment coefficients
Results to wind buffeting, including background information, mean and background fluctuation wind
loads, inertial loads due to wind-induced bridge motions, and simplified wind load distributions for
structural design
Static aerodynamic coefficients (lift, drag, and moment), aeroelastic flutter coefficients, and vortex-induced
aerodynamic motions shall be obtained from wind tunnel tests using a detailed 1:45 sectional model of the
bridge. Static aerodynamic coefficients shall be determined for a +/-10-degree angle of attack. Dynamic
response shall be determined for a +/-5-degree angle of attack.
The Design-Builder shall perform full aeroelastic model testing of the Main Span Bridge, including at least
one Approach Bridge frame, but not less than 700 feet of Approach Bridge, adjacent to each end of the Main
Span Bridge in the bridge’s completed form and throughout all critical stages of construction. A frame is
defined as those portions of a bridge bounded by superstructure expansion joints. Critical construction stages
shall be determined by the Design-Builder, but at a minimum, shall include two construction stage conditions
consisting of a stand-alone tower and fully extended cantilever conditions just prior to mid-span and bent
closures. The Design-Builder shall prepare a Wind Engineering Study Report with the results of the full
aeroelastic model testing of the bridge to determine wind design forces based on the wind tunnel tests
findings. The Wind Engineering Study Report shall contain the following, at a minimum:
Page 8
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-8 Structures
Description of the aeroelastic model
Description of the wind tunnel simulation
Description of the wind tunnel test and instrumentation
Aerodynamic stability from wind tunnel test results
Response to turbulent winds from wind tunnel test results
Response comparisons between the stability and buffeting analysis and the test results
Comparison of simultaneous peak moments at the base of the tower
Conclusions and recommendations
Wind analysis shall be performed by the Design-Builder in accordance with AASHTO LRFD Bridge Design
Specifications, 4th Edition, with California Amendments, Section 3.8, ASCE/SEI 7, and the Wind
Engineering Study Report using the resulting wind component combinations included in the report. Both
static and dynamic wind effects shall be considered, utilizing computer models of the bridge that incorporate
the results of wind tunnel tests of sectional models of the deck. Wind tunnel tests shall include smooth and
turbulent flow, and 0.5 percent to 1.5 percent damping.
The Design-Builder shall provide a cable dampening system per Exhibit 2-13-D (Stay Cable System).
13.3.9.2 Wind Events
The Design-Builder shall complete wind analysis and design considering both a high-probability
Serviceability Event and a lower-probability Aerodynamic Stability Event. The wind analysis and design
shall consider two scenarios:
1) Bridge railings required by the Contract Documents
2) A 10-ft high fence with a 2-inch opening mesh located on each exterior side of the Main Span Bridge.
The Serviceability Wind Event shall have a probability consistent with a mean return period of 100 years as
defined in ASCE/SEI 7, but the resulting mean-hourly wind speed shall not be less than specified in Exhibit
2-13-B (Wind Climate Data). During all phases of construction, a 20-year mean return period shall be
assumed with a mean-hourly wind speed of not less than that specified in Exhibit 2-13-B. For these wind
events, the load combinations specified in Exhibit 2-13-A shall be used.
Vertical deck accelerations shall not exceed 0.03g for winds up to 30 mph and 0.10g for winds between 30
mph and 45 mph. The completed bridge shall show no signs of flutter instability up to a wind velocity of
1.35 times the one-hour mean Serviceability Wind Event and during all phases of construction for the 20-
year wind event. If the bridge shows any sign of aerodynamic instability during the Serviceability Wind
Event or does not meet deck acceleration limits when subjected to these wind velocities, the cross-section or
other bridge design features shall be revised. All revisions are subject to Port Approval. During construction,
temporary remedial measures to counteract any distress shall be implemented as required without obstructing
river navigation.
13.3.10 Bridge Load Rating
The Design-Builder shall load rate the bridges according to the latest AASHTO Guide Manual for
Condition Evaluation and Load and Resistance Factor Rating (LRFR) of Highway Bridges. The ratings
shall be based on the final As-Built Documents of the bridges and be prepared and submitted in accordance
with the Standards. Complete and detailed as-built structural models shall be provided to the Port for all
bridge structures.
Prior to developing load rating models, the Design-Builder shall meet with the Port to discuss the details of
model development.
Page 9
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-9 Structures
The load rating models shall be developed by a California-licensed Civil Engineer experienced in developing
load rating models and checked by a California licensed Civil Engineer and shall consider effects of
construction staging. Load rating models shall be provided for each Project bridge.
The load rating model shall be constructed in three orthogonal directions or axes (X, Y, and Z), and shall
consist of a three-dimensional description of the structure using shell or grillage elements. The true
horizontal and vertical alignment of the superstructure shall be defined. The location of the substructure
elements including the columns and pile cap shall be included in the model. The stiffness of these elements
for the purposes of distributing load shall be the same as used in the design of the structure.
The model shall be capable of distributing loads based on the geometry and stiffness of the structural
elements. Nonstructural elements, such as barrier rail, shall not be modeled as load-carrying elements. In
performing the load rating, the distribution of loads shall be the same as that used in the design of the
structure.
HL-93 and Permit Design Loads shall be used in the models to generated load rating results for
superstructure elements of the bridges that carry live loads and for bent caps.
The overall rating shall be the lowest rating of any individual component, segment, or type. The final rating
and each component rating shall be accompanied by the location of the rating, limit state, and impact factor.
Each separate bridge component, segment, or element constructed or modified under this Project shall be
rated and reported to the Port in a Bridge Load Rating Report. At a minimum, ratings shall be computed for
moment and shear at the one-tenth points of each bridge span. The Bridge Load Rating Report shall also
include the load rating analysis computer model electronic files as an attachment.
The Design-Builder shall provide a Bridge Load Rating Manual for the Main Span Bridge and the
Approach Bridges. This manual shall include the methods and software, if applicable, used to load rate the
bridge, such as influence lines or surfaces.
13.3.11 Bridge Security
13.3.11.1 Technical Requirements
The Design-Builder shall obtain Approval from FHWA on the design and approaches taken regarding bridge
security and meet the requirements of this Section 13.3.11.
The Design-Builder shall assess accident and terrorist vulnerabilities and incorporate mitigation measures in
the design of the cable-stayed bridge as specified in Exhibit 2-13-F (Accident and Terrorist Vulnerability
Assessment Requirements).
At a minimum, the Design-Builder shall meet the requirements of NCHRP Report 645- Blast-Resistant
Highway Bridges: Design and Detailing Guidelines shall be used. Localized spall and breach damage shall
be accounted for when designing bridge components for blast forces (see guidelines from U.S. Department of
Defense for spall and breach damage estimated for non-column structural components). The blast load
analysis of the structure shall consider inertial effects, and dynamic analysis shall be used for the design of
any structural member subjected to blast loads.
The Design-Builder shall provide a Lead Blast Specialist who meets the requirements of Exhibit 2-13-F
(Accident and Terrorist Vulnerability Assessment Requirements) and has experience completing blast
evaluations and design of blast protection systems on at least three structures. Experience on a building can
be used to meet this requirement. The Lead Blast Specialist shall be responsible for completing accident and
terrorist vulnerability assessments.
Page 10
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-10 Structures
13.3.11.2 Safeguarding Documents
All Project documents shall include the necessary information for satisfactory construction of the structure,
system, or component, and training necessary to operate any security system. These documents shall not
indicate that the construction, structure, system, or component shown meets any security standard, or contain
any reference to the limits or capabilities of the construction, structure, system, system operation, or
component.
13.3.12 Bridge Design Service Life and Corrosion Protection Plan
The Design-Builder shall provide bridges that meet the required design service life either by selecting
materials with reduced corrosion potential, by selecting materials and details which resist degradation or by
other mean acceptable to the Port. The Design-Builder shall prepare a detailed Corrosion Protection Plan for
the Main Span Bridge and the Approach Bridges. Each Corrosion Protection Plan must not exceed 25 pages
in length. If the Approach Bridges differ in material or configuration then the Design-Builder shall separate
the bridges into similar groupings and provide a Corrosion Protection Plan for each group.
At a minimum, each Corrosion Protection Plan shall:
Include an executive summary describing the overall approach to achieving the required design service
life for the primary load carrying members, including stay cables, of the Project bridges.
Identify each bridge component with the corresponding environmental exposure conditions for each
component (e.g., buried, submerged, exposed to atmosphere, exposed to corrosive chemicals). Some
elements may be exposed to more than one environmental condition (e.g., foundations in water table,
foundations in area with petroleum contamination), which might require different corrosion
considerations for each exposure.
Identify relevant degradation and protective mechanisms for each bridge component. Quantify
degradation processes and resistances to these processes with respect to time. Models shall use a
probabilistic approach to evaluate the time-related changes in performance depending on the component,
environmental conditions, and any proposed protective measures. Models shall be listed in the plan.
Identify the expected design service life of each bridge component, based on the proposed material,
exposure condition, relevant degradation mechanism, and any proposed protective measures, taking into
account the proposed inspection/maintenance schedule. List any corrosion allowances and thresholds
used. Coordinate with the Operations and Maintenance Manual requirements elsewhere in the Contract
Documents. Include the level of reliability or probability of the predicted design service life of each
element as well as the expected interval of replacement or renewal of the protective measures within the
design service life duration (e.g., number of times to recoat paint that protects steel members).
Explain what will be done during construction to ensure the highest quality products are achieved, (e.g.,
ensure uniform compaction of the concrete, adequate concrete cover, proper curing for the element, etc.).
Summarize the above information, for each component, in a tabular format and perform an estimate of
life-cycle costs for the bridge. The life-cycle cost analysis for bridge components shall use a discount rate
of 2.9 percent per year to convert future costs to present worth.
Additional specific requirements for the Corrosion Protection Plan shall include:
List of the manufacturers of all proposed coatings, inhibitors, sealers, and membranes
Schedule for corrosion inspection of the bridge components
Proposed maintenance schedule for items/materials that could be affected by corrosion
Direct electrical current and sacrificial materials (cathodic protection) shall not be used to mitigate for
expected corrosion effects.
Page 11
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-11 Structures
For each Approved Corrosion Protection Plan, the Design-Builder shall prepare an As-Built Corrosion
Protection Report. The Accepted As-Built Corrosion Protection Report shall be included in the Operations
and Maintenance Manual and consist of the Approved Corrosion Protection Plan with updates and/or as-built
information that identifies changes to the Approved Corrosion Protection Plan.
The Design-Builder shall maintain at Design-Builder’s expense, all newly installed dampers and shall
perform work as necessary to ensure dampers’ proper function for the entire 10-year warranty period.
No asphalt concrete shall be applied to the polyester concrete wearing surface at any time during
construction or in the future.
13.3.13 Erection Manuals
The Design-Builder shall develop an Erection Manual for the Main Span Bridge and Approach Bridges that
includes complete detailed erection sequence drawings; erection stresses in permanent and temporary
members; bent and falsework reactions determined for each construction stage; and moments, shears, axial
loads and other forces computed and tabulated for the towers and the superstructure of the Main Span
Bridge at a sufficient number of points to demonstrate the load demand will not exceed the capacity and
allowable stresses for erection and service conditions.
The Design-Builder shall include step-by-step erection procedures with complete details of stay-cable
fabrication, erection, and monitoring of stressing operations. Details of contemplated elevations, cable
lengths, adjustments, and shims required shall be shown for each erection stage. The geometry control
section shall identify the special survey and monitoring to be implemented for bridge construction.
An Erection Manual is not required for cast-in-place post-tensioned concrete box girder bridge
superstructures erected on continuously supported false work.
13.3.14 Operations and Maintenance Manuals
The Design-Builder shall develop an Operations and Maintenance Manual that includes recommended
inspection procedures for the Main Span Bridge and Approach Bridges. The Design-Builder shall evaluate
inspection access and maintainability during the initial design phase and provide best practices in the bridge
Released For Construction Documents and not delay this effort to when developing these manuals.
The Design-Builder shall conduct Operations and Maintenance office and field training sessions with the
Port. The training shall, at minimum, review the contents of the Operations and Maintenance Manual. The
Design-Builder shall coordinate with the Port on the required attendees, schedule the meeting, provide a
location and facilities for the office meeting and provide each attendee with the Approved Operations and
Maintenance Manual for the bridge or group of bridges training is provided for. Field training shall be held
on the structure for each bridge or group of bridges for which an Operations and Maintenance Manual is
created.
13.3.14.1 General Requirements
The manuals shall consist of permanent, hardback three-ring binders not exceeding 3 inches thick,
separated into multiple volumes as necessary. The Design-Builder shall obtain Approval for the
composition and content of each volume.
Information shall include published literature and detailed shop drawings, 8.5 inches by 11 inches or
accordion-folded to this size. Technical literature shall be original and not photocopied.
Instructions shall be in continuous narrative form, not fragmented sections as prepared by individual
equipment manufacturers.
Information shall be arranged and identified with divider sheets and identifying tabs for separation of
information. A complete table of contents shall be included in each binder.
Page 12
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-12 Structures
Information shall cover the exact equipment provided and shall not contain marked-up general catalog
data.
A complete set of shop drawings and/or As-Built Documents shall be incorporated in each manual,
including control and wiring diagrams and piping diagrams, if applicable. Due to the volume of as-built
information, only the general plans, elevations and pertinent views or details are required to
communicate maintenance issues and orientate maintenance personnel or inspection staff.
Each binder shall be identified on the outside binding edge with Project name and number, and bridge
name(s) and number(s).
13.3.14.2 Manual Content
The Operations and Maintenance Manual shall cover the following subjects, at a minimum:
Principal elements of the bridge.
Bridge design considerations including bridge design criteria and any changes made during construction.
Structural role of major bridge elements.
Sequence and methods of bridge construction, including design modifications and problems or repairs
encountered during construction.
Recommended inspection personnel qualifications and equipment beyond the equipment already
provided as part of the Project.
Recommended inspection and maintenance program and schedule.
Inspection procedures or focus areas including as-built conditions that differ from the design plans.
Known bridge deficiencies shall include why it is a deficiency, why it was not addressed during
construction, field information description (–e.g., photos, measurements, notes, and dates), and
assessment of compliance with the National Bridge Inspection Standards for the deficient element.
Operation and maintenance of bridge appurtenances, including travelers, elevators, Utilities, lighting and
navigation elements, buildings and equipment such as compressors, supervisory control and data
acquisition (SCADA) equipment, and lighting controls.
Procedures for future maintenance and repairs, including maximum anticipated deflections during design
service life. Future work shall include work customary of the bridge type and design service life and
must include, at a minimum, stay cable adjustment/ replacement, painting if applicable, and mechanical
or electrical element repairs.
If seismic energy dissipation elements are provided, procedures for the future replacement of seismic
energy dissipation elements and criteria to determine when elements must be replaced.
At a minimum, each manual shall also compile the manufacturer's data and specific Project data, and shall
include the following, if applicable:
Complete instructions on the operations of all equipment, including control settings, switch positions,
timer operation, and starting and stopping sequences
Complete instructions regarding maintenance of all equipment including periods and frequencies of all
inspections, lubrications and filter replacements, type of lubricants required; and exact description of
performance of such maintenance and full description of inspections and corrections on a step-by-step
basis
Complete nomenclature of all replaceable parts, their part numbers, and the name and address of the
nearest vendor
Copies of all guarantees and warranties issued for system components, showing all expiration dates
Copies of test and balancing reports made on the equipment installed
Page 13
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-13 Structures
13.3.14.3 Submittal And Review
One unbound copy of each Operations and Maintenance Manual shall be submitted not less than 120 Days
before Final Acceptance. Comments shall be incorporated, and three copies of each volume in final form
shall be submitted to the Port. The final submittal shall be made not less than 25 Days before projected
Final Acceptance of the Contract. Approval of the Operations and Maintenance Manuals and completing
the training shall be a prerequisite to Final Acceptance of the Work.
13.3.15 Main Span Bridge
13.3.15.1 Design Criteria
The Design-Builder shall comply with the requirements of Exhibit 2-13-A (Design Criteria) and the
following:
The new Main Span Bridge shall be a three-span cable-stayed bridge. The center span shall measure at
least 1,000 feet between tower centerlines and span the Back Channel. The center of the 1,000-foot span
shall be at ―A‖ Line (Ocean Boulevard) Station 298+55.
A clear distance of at least 5 feet shall be provided between the existing Gerald Desmond Bridge (Bridge
No. 53C-0065) and the Main Span Bridge.
A lightning protection system shall be provided. All exposed metallic objects on the bridge, including
structural steel, stay cable anchorages, poles, luminaires, handrails, fencing, handhole covers, pedestals,
conduits and supports shall be bonded to a bare steel collector cable. All terminations and splices shall be
made by exothermic welding, except connections to handrails may be bolted using compression lugs.
Bar reinforcement in barrier railings, towers from bottom of pile cap to top of tower, and end bents from
bottom of pile cap to 20 feet above mean highest high water elevation shall conform to Standard Special
Provision 52-650. The bar reinforcement of the structural deck shall be epoxy coated (green) in
conformance with the Standard Specifications.
Fiber-reinforced polymer reinforcing is not allowed as a replacement to steel reinforcing.
An enclosed drainage system shall be used. Drain pipes shall be placed inside of substructure units. The
Design-Builder shall provide cleanouts as required for future maintenance.
Substructure Pile Cap
Top of pile caps shall be a minimum of 2 feet below finished grade elevation.
Foundations shall be deep foundations, such as piling, drilled shafts or caissons.
Substructure Tower/Bent
For the purposes of defining substructure requirements the following definitions shall apply:
Tower – The element or elements that support either side of the center span of the Main Span Bridge.
End Bent – The elements or columns supporting the respective end span of the Main Span Bridge.
Column – The element or system of shafts that make up bents that support superstructures.
Shaft – Elements connected together to make up a Column or Tower
Towers shall be vertically plumb on either side of the Back Channel to support the Main Span Bridge.
Above-deck tower configurations shall not extend in the transverse direction to stationing outside vertical
lines located at the back face of the median barriers.
End bents shall consist of two columns.
Towers may consist of identical twin vertical shafts and end bent columns, where each column consists of
two identical twin vertical shafts. The shafts shall be connected with seismic energy dissipation elements that
cause the twin shafts to act as lateral force resisting frames. If the Design-Builder elects this option, the
Page 14
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-14 Structures
seismic energy dissipation elements shall be used in all substructure units in the Main Span Bridge. Should
the Design-Builder elect to use a twin-shaft approach for towers and end bent columns, the Design-Builder
shall:
Be responsible for meeting the requirements of seismic energy dissipation elements including the design,
fabrication, testing, and installation.
Tower Shafts shall be connected with horizontal diaphragms above the stay cable anchorage zone, below
the stay cable anchorage zone, and at the deck level. The stay cable anchorage zone is defined as the zone
along a tower that contains all stay cable anchorages.
Stay cable anchorages in one tower shaft shall be connected to the opposite stay cable anchorage in the
opposite tower shaft by elements that transfer the tension forces from one anchorage to the other.
End bent column shafts shall be connected at the top with a horizontal diaphragm.
Landings shall be placed in tower shafts at seismic energy dissipation elements, tension elements between
stay cable anchorages, and diaphragms, as well as at access entrance points.
Landings shall be placed in end bent column shafts at seismic energy dissipation elements and diaphragm
as well as at access entrance points.
Outrigger style bents will not be allowed.
Superstructure General
Under all service load combinations, the bridge superstructure shall provide the required vertical and
horizontal navigational clearances.
Long term effects of concrete creep and shrinkage shall be accounted for to ensure required vertical
clearances and residual cambers are maintained for the design service life of the bridges.
Inserts or other hardware shall be shown on the plans and provided in the bridge deck for all anticipated
structural connections to Utilities, drainage, and other facilities. Drilling into the bridge superstructure is not
allowed.
Stay Cable System
Stay cables shall meet the requirements of Exhibit 2-13-D (Stay Cable System).
The superstructure shall be supported by a stay-cable system anchored to the edge girders and the towers.
Stay cables and anchorages shall be symmetric about the towers and shall be supplied by VSL, Freysinett,
DSI, or Approved equal.
The stay connections to the edge girders shall be located outside the edge girders. The stays shall be
adjustable for length throughout the design service life of the bridge. Anchorages must not penetrate the
vertical clearance envelope for vehicles, pedestrians, or bikes at any point in the design service life of the
bridge.
Location of future stay cable maintenance and provisions for future stay cable adjustment shall be located at
the deck end of each stay.
Framing
The superstructure shall consist of transverse floor beams, longitudinal edge girders, and longitudinal steel
stringers between floor beams.
Floor beams shall be variable-depth steel-plate I girders.
Page 15
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-15 Structures
Edge girders shall be steel box girders with an inclined outside web. The depth of edge girders shall be
constant, except within 35 feet from the end span bearings, where the depth may increase linearly, but not be
greater than the depth of the Approach Bridge superstructure.
No elements or portions of elements of the bridge or systems attached to the bridge shall project below the
bottom of the edge girders, except the floor beams, maintenance traveler, maintenance traveler support rails
and elements such as navigation lighting.
Deck
The deck shall be concrete or steel orthotropic deck.
If the Design-Builder elects to use a concrete deck, the physical properties of the concrete in the deck shall
be the same throughout the deck, including closure pours and pours over edge girders. Concrete decks shall
be reinforced or prestressed lightweight concrete (LWC) deck panels. Deck panels shall be precast and post-
tensioned together longitudinally. Joints between precast elements shall be completed with closure pours at
the floor beams and stringers. Concrete deck panels shall be overlaid with a 2-inch polyester concrete
wearing surface per the Caltrans Standard Special Provisions.
If a steel orthotropic deck is used, the Design-Builder shall provide a deck with waterproofing membrane and
asphalt overlay that can both be replaced in the future.
The surface of the Class I bikeways shall be finished to meet Department standards for bridge decks,
including smoothness/rideability and surface friction. If precast deck panels are used, the Class I bikeway
shall be overlaid with a 2-inch polyester concrete wearing surface per the Caltrans Standard Special
Provisions.
Barrier or Railing
Concrete barrier Type 736 shall be used to separate roadway shoulders from the towers and the stay cables.
The back face of this barrier at the towers shall be vertical. Barrier shall be modified as required for the
Project.
Bridge railing or barrier shall not be used in determining capacity.
13.3.15.2 Foundation
The Design-Builder shall comply with Exhibit 2-13-A (Design Criteria).
13.3.15.3 Seismic Design
The Design-Builder shall comply with Exhibit 2-13-A (Design Criteria).
13.3.15.4 Maintenance Design
Maintenance elements shall be accounted for in the design and provided for and installed as part of the
Project and be fit for use prior to Substantial Completion. The Design-Builder shall prepare a Main Span
Bridge Maintenance Concept Plan that includes the following:
13.3.15.4.1Maintenance Traveler
Access to the bridge for maintenance and inspection shall be provided by a pneumatic trolley, motor-driven,
traveler system meeting the following requirements:
The traveler shall be capable of accessing the full underside of the bridge from end bent to end bent.
The traveler system shall provide one electric or pneumatic-driven scissor lift with a platform at least 4
feet by 6 feet. The traveler system shall allow the scissor lift to traverse from one side of the bridge to the
other on a rail system. The scissor lift shall have a minimum safe working load of 1,000 pounds.
Page 16
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-16 Structures
The traveler shall extend past the outside of the edge girder a sufficient distance to allow the scissor lift to
rise to the top of the edge girder.
The traveler must be able to move past the towers without undue delay or reconfiguration.
Traveler elements shall function as a system, and the Design-Builder shall provide training to the Port on
proper use of the system.
The traveler shall have a 5-foot horizontal clear width.
The walking surface of the traveler shall be between 4 feet and 6 feet from low structural steel.
The pneumatic trolley motor(s) shall have a double brake system for each motor.
Lines for wastewater, potable water, compressed air, electrical, and communications shall be accessible
from the maintenance traveler. Access points shall not exceed 100-foot spacing and be no further than
every other floor beam, if applicable. Potable water lines shall consist of hot-dip galvanized steel pipe.
Hose connections shall include an industrial grade, angle pattern globe valve or ball valve. For the potable
water connection, the valve shut off shall be the claw type (similar to the air hose connection). All pipes
shall be clearly marked.
The traveler platform shall be provided with a sealed/waterproof floor with a sump and sump pump for
discharging wastewater into a drain pipe. The drain pipe shall allow gravity flow into a water clarifier and
then discharge into city sewer lines.
The traveler system shall be able to be stored at either end bent. When stored, the traveler system shall be
secured from moving and have accommodations for securing loose or movable elements.
The connection of the traveler system to the superstructure shall be redundant (i.e., if support was lost at
one connection, the traveler shall remain stable).
The traveler shall be engineered and certified as man-rated and designed specifically for maintenance,
inspection, and painting operations.
13.3.15.4.2 Maintenance Walkways
A continuous catwalk system shall be provided near the center of the bridge from end bent to end bent.
The catwalk shall have a horizontal clear width of at least 3 feet and vertical clearance of at least 5 feet to the
underside of bridge elements, not including the floor beam.
Openings in the floor beams shall accommodate the required horizontal catwalk clearance and have at least a
4-foot vertical clearance.
One column in each end bent shall provide access to the catwalk and the traveler.
13.3.15.4.3 Maintenance Access and Openings
A door shall be provided at the base of each hollow end bent column or tower to gain access inside the
column and shall coincide with the lowest level of travel of the elevator, if an elevator is present.
Doors shall be weatherproof, steel, tamper-proof, and lockable. The Design-Builder shall determine the
locking scheme for each door so it can be locked and opened under the locked condition from the appropriate
side.
Lower door thresholds shall be between 25 feet and 35 feet above finished grade. Each door shall have a
landing on the inside of the column or tower if the column or tower is hollow.
Doors shall have a clear opening of at least 2 feet wide by 4 feet tall.
Access openings are not allowed in towers near deck level or in the deck.
Access shall be provided in the top of each tower.
Hatches shall be weatherproof, and include a spring-assisted hinged cover that either helps lift the cover or
helps resist the cover from falling, depending on the horizontal location and application. The Design-Builder
shall determine the locking scheme for each hatch so it can be locked and opened under the locked condition
from the appropriate side.
Page 17
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-17 Structures
A minimum of five access hatches shall be spaced evenly along the edge girder from end bent to end bent.
Hatches shall be placed on the floor beam side of the edge girder. Each access hatch cover shall have an
overall ventilation opening at least 1 square foot.
The Design-Builder shall account for removal of an injured worker in the design of maintenance access.
Hooks shall be provided at the top of each tower and end bent column for boatswain chairs to access the
exterior surfaces of the tower or end bent column.
Access shall be provided to bearings at the top of end bent columns.
If a tower or end bent column is comprised of one or more shafts, the Design-Builder shall provide access
from the top of all Shafts that make up a tower or end bent to the elevator of that tower or end bent.
13.3.15.4.4 Maintenance Ladders
Ladders shall be provided inside hollow towers or end bent columns from top of footing to top of tower or
column void. Landings shall be provided per the Standards and/or at locations of elements that will require
future inspection. Ladders shall connect landings together.
Ladder support elements shall be galvanized steel, but grating may be fiber-reinforced polymer.
13.3.15.4.5 Maintenance Equipment and Housing
Hoists
Electric or pneumatic hoists shall be provided at the top of each tower with a minimum safe working load of
1,000 pounds. The hoist shall be able to access the top extents of the tower, the outside faces of the tower
from the bridge deck to the top of the tower, and inside the tower from the top of the elevator to the top of the
tower. Hoists shall also be accessible by maintenance workers. Hoists shall be able to access and remove and
replace seismic devices.
Elevator
One elevator that allows accommodations to carry three people and a minimum safe working load of 1,000
pounds shall be provided at each tower and one column of each end bent. If a tower or end bent column is
comprised of one or more shafts, the Design-Builder shall provide one elevator per tower or end bent in one
of the shafts. Elevators shall allow for travel from the lowest landing area or access door up to the bottom of
the stay-cable anchorage zone in the towers or top of void in the end bent columns. Elevators shall be located
inside the tower and capable of stopping at each landing.
Air Compressor
Compressed air lines shall be provided along the Main Span Bridge. The compressed air lines shall be
accessible from the maintenance traveler system, with fixtures at every other floor beam, minimum, along
the length of the bridge.
An electric-driven air compressor with associated air tanks shall be provided at the base of each tower. The
air compressors shall have a minimum output of 800 cfm and a maximum of 1,200 cfm at any given point on
the bridge to operate the traveler platform and other pneumatic equipment used for maintenance.
Minimum compressed air pressure at any point on the main span bridge shall be 120 psi. The air line shall be
equipped with ¾-inch crow foot fittings and ball valve.
Each compressor shall be remote-controlled from the Maintenance Facility defined in Section 24.
Water Pump
The Design-Builder shall provide a water pump that capable of supplying a minimum pressure of 120 psi at
any given point on the bridge.
Page 18
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-18 Structures
Air Dryer
The Design-Builder shall provide an electrical coil air dryer.
Water Clarifier
The Design-Builder shall provide a water clarifier at each end bent for maintenance, painting, and cleaning
operations. The Design-Builder shall size the clarifier for how much water is required to contain for future
maintenance activities and shall submit the method for sizing the clarifier in the Main Span Bridge
Maintenance Concept Plan. The maximum size the Port will require is 5,000 gallons. Clarifier piping system
shall be connected to the sewer system.
Housing
A permanent concrete block building with minimum dimensions of 20 feet x 30 feet shall be provided at or
near the base of each tower to house the air compressor, air storage tank, water pump, and air-dryer.
The block building shall accommodate 24/7 use, with interior lighting, electrical outlets on each wall,
electrical power for specific equipment needs and water and air piping systems.
The building shall provide sufficient room for servicing equipment, with a roll-up door for equipment
removal. Building locations and size shall be shown in the Main Span Bridge Maintenance Concept Plan.
The Design-Builder is responsible for the associated permits.
13.3.15.4.6 Maintenance Lighting
Electrical outlets shall be spaced a maximum of 100 feet within tower and end bent columns.
13.3.15.4.7 Maintenance General
The Design-Builder shall include elements from the Approved Main Span Bridge Maintenance Concept Plan
in the final design of the Project.
The Design-Builder shall provide background data or designs, as applicable, with the Main Span Bridge
Maintenance Concept Plan showing the components proposed meet the requirements of the Contract
Documents.
13.3.16 Approach Bridges
13.3.16.1 Design Criteria
The Design-Builder shall comply with the requirements of Exhibit 2-13-A (Design Criteria) and the
following:
A clear distance of at least 5 feet shall be maintained between existing bridges and the Approach Bridges.
Horizontal and vertical clearance requirements shall be met for existing and proposed railroads.
Long-term effects of concrete creep and shrinkage shall be accounted for to ensure required vertical
clearances and residual cambers are maintained for the design service life of the bridges.
A lightning protection system shall be provided. All exposed metallic objects on the bridge, including
poles, luminaires, handrails, hand hole covers, pedestals, conduits, and supports shall be bonded to a bare
steel collector cable. All terminations and splices shall be made by exothermic welding, except that
connections to handrails may be bolted using compression lugs.
No elements of the bridge or systems attached to the bridge shall encroach on the required vertical and
horizontal clearances.
Bar reinforcement in barrier railings shall conform to Standard Special Provision 52-650. Bents and
abutments from bottom of pile cap or shallow foundation to 20 feet above mean highest high water
elevation shall conform to Standard Special Provision 52-650.
Page 19
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-19 Structures
Fiber-reinforced polymer reinforcing is not allowed as a replacement to steel reinforcing.
An enclosed drainage system shall be used. Drain pipes shall be placed inside substructure units.
Cleanouts shall be provided as required for future maintenance.
Substructure Pile Cap
Top of footings shall be a minimum of 2 feet below finished grade elevation.
Foundations shall be deep foundations, such as piling, drilled shafts, or caissons.
Substructure Column/Bent
Substructure columns shall be integral with the superstructure. Bent caps that project below the
superstructure soffit are not allowed.
The maximum number of columns per bent location (includes both directions of Ocean Boulevard traffic)
shall be as follows:
For bent locations in the area from ―A‖ Line (Ocean Boulevard) Station 269+50 to the west end of the
Main Span Bridge, the maximum number of columns per bent location is two.
For bent locations in the area from the east end of the Main Span Bridge to Station 320+00 along ―B‖
Line (EB Ocean Boulevard to NB SR 710) or ―C‖ Line (SB SR 710 to WB Ocean Boulevard), the
maximum number of columns per bent location is two.
The number of columns for other bent locations shall be determined by the Design-Builder.
Under all service load combinations, the bridge superstructure shall provide the required vertical and
horizontal clearances.
Integral-type abutments are not allowed on the Project.
Seat-type abutments shall not be supported on MSE embankments or walls.
Outrigger style bents will not be allowed.
Superstructure General
Inserts or other hardware shall be shown on the plans and provided in the bridge deck for all anticipated
structural connections to Utilities, drainage, and other facilities. Drilling into the bridge superstructure is not
allowed.
Framing
Superstructure shall consist of closed concrete or steel box girder construction. No open girder superstructure
systems will be allowed. Open girder superstructure systems include steel plate girders, concrete I-girders,
and other structural systems that do not have a closed structural soffit between load-carrying superstructure
elements.
Precast concrete superstructure segments, if used, shall be match cast.
Deck
A deck shall be provided that allows for the complete future removal and replacement of bridge barrier(s).
A polyester concrete wearing surface with a minimum thickness of 2 inches shall be applied to the full width
of the bridge deck between barriers per the Caltrans Standard Special Provisions.
The surface of Class I bikeways shall be finished to meet Department standards for a bridge deck, including
smoothness/rideability and surface friction. If precast deck panels are used, the Class I bikeway shall be
overlaid with a 2-inch polyester concrete wearing surface per the Caltrans Standard Special Provisions.
Page 20
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-20 Structures
Barrier or Railing
Concrete barrier Type 736 shall be used along bridge fascias when no Class I bikeway is present. Barrier
shall be modified as required for the Project.
Bridge railing or barrier shall not be used in determining capacity.
13.3.16.2 Foundation
The Design-Builder shall comply with Exhibit 2-13-A (Design Criteria).
13.3.16.3 Seismic Design
The Design-Builder shall comply with Exhibit 2-13-A (Design Criteria).
13.3.16.4 Maintenance Design
Maintenance elements shall be accounted for in the design and provided as part of the Project. The Design-
Builder shall submit an Approach Bridge Maintenance Concept Plan that includes the following:
13.3.16.4.1 Maintenance Access and Openings
If bent columns are hollow, a door shall be provided at the base of each column.
Doors shall be weatherproof, steel, tamper-proof, and lockable.
The Design-Builder shall determine the locking scheme for each door so it can be locked and opened under
the locked condition from the appropriate sides.
Door thresholds shall be between 25 feet and 35 feet above finished grade. Each door shall have a landing on
the inside of the hollow column.
Doors shall have a clear opening of at least 2 feet wide by 4 feet tall.
One soffit access hatch shall be provided in each superstructure span. Multi-cell superstructures shall provide
access openings through interior box girder webs to allow maintenance staff access to all cells of the
superstructure.
Soffit access hatches shall be weatherproof and provided with a spring-assisted hinged cover that either helps
lift the cover or helps resist the cover from falling, depending on the horizontal location and application.
Soffit hatches located within 50 feet of finished grade shall be lockable. The Design-Builder shall determine
the locking scheme for each soffit access hatch so it can be locked and opened under the locked condition
from the appropriate sides.
13.3.16.4.2 Maintenance Ladders
If bent columns are hollow, ladders shall be provided inside hollow columns from the top of footing of each
bent column to the top of the column void.
Landings shall be provided and ladders shall connect landings together.
Ladder elements shall be galvanized steel but grating can be fiber-reinforced polymer.
13.3.16.4.3 Maintenance Equipment
Hoists shall be provided inside hollow superstructures with a minimum safe working load of 1,000 pounds.
Hoists are required at soffit access hatches only and shall be able to raise or lower items through the soffit
access hatches.
Hooks shall be provided inside each hollow bent column at the top of the tower for boatswain chairs for
access to the interior surfaces of the tower.
13.3.16.4.4 Maintenance Lighting
Hangers or hooks to support future portable maintenance lighting shall be installed in the ceiling of each
hollow superstructure cell. Hangers or hooks shall be spaced a minimum of 100 feet along the length of a
span but not further than 50 feet from the end of a span. An electrical outlet shall be provided at each future
portable maintenance lighting support.
Page 21
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-21 Structures
Electrical outlets shall be spaced a maximum of 100 feet within hollow bent columns.
13.3.16.4.5 Maintenance General
The Design-Builder shall include elements from the Approved Approach Bridge Maintenance Concept Plan
in the final design of the Project.
The Design-Builder shall provide background data or designs, as applicable, with the Approach Bridge
Maintenance Concept Plan submittal showing the components proposed meets the requirements of the
Contract Documents.
13.3.17 Permanent Retaining Walls
The Design-Builder shall determine the location(s) and types of retaining walls needed on the Project.
. The design builder shall provide walls that met the requirements of the Load and Resistance Factor Design
(LRFD) methods and not rely on design related information in the Standard Plans, which do not reflect
LRFD design methodology. The Design-Builder shall, however, follow requirements of the Standard Plans
as they relate to non-design related items such as drainage materials and sizes or earthwork criteria.
When proprietary or alternate wall systems are used, the Design-Builder shall provide site specifics to the
wall provider. Site specifics include, at a minimum: profiles, wall heights, loading conditions (e.g., dead
loads, live loads), results of foundation investigations, water conditions, all Utilities (in-place, proposed, and
future), site restrictions, expected wall cross section, and desirable wall face treatments. The Design-Builder
shall obtain Approval of any proprietary or alternate wall systems.
The selected wall type design including shape, layout pattern, surface treatment and color shall relate
aesthetically to the overall bridge architecture including both the Main Span Bridge and the Approach
Bridges. The Design-Builder shall provide an Architectural Element Report for the proposed designs that
includes retaining wall system, surface treatment and color(s).
The Design-Builder shall identify non-standard special wall types during the type selection process and
provide non-standard specifications as part of the type selection documents. For wall types currently not
included in the Caltrans Standard Specifications or Standard Special Provisions, the Design-Builder shall
submit a non-standard specification to the Port for review and Acceptance with the applicable Released For
Construction Documentation.
Base leveling pads of concrete, crushed stone, or other manufacturer-recommended material shall be
installed for proprietary or alternate wall systems, when required.
Drainage for overland flow shall be provided at the top of retaining wall systems. Drainage shall also be
provided within the wall system at the bottom rear of the backfill or reinforced fill zone and at the bottom
rear of the front face or leveling pad of the wall.
When steps in the horizontal alignment of a wall are proposed, the Design-Builder shall provide steps that
face away from traffic. Points of inflection in the horizontal alignment of retaining walls with the wall face
angling toward or away from traffic are acceptable.
The Design-Builder shall provide traffic barriers in front of retaining walls when the wall faces are within the
clear zone area of a roadway. When guardrail is used, the Design-Builder shall provide enough distance
between the guardrail and wall to absorb the deflection resulting from vehicular collision with the guardrail.
When the end of a wall is exposed to approaching traffic within the clear zone area, it shall be considered a
fixed object, and the Design-Builder shall provide either a guardrail or crash cushion as protection.
The Design-Builder shall provide traffic barriers on top of retaining walls under any of the following
conditions:
Page 22
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-22 Structures
The wall is within the roadway clear zone.
The wall is within 10 feet of the edge of roadway.
The wall constitutes a hazard to vehicles due to design speed, traffic volume, roadway geometrics, or any
other applicable factors.
The wall is outside the roadway clear zone but a car leaving the road at an angle up to 25 degrees would
have no obstruction to driving over the top of the wall.
The Design-Builder shall meet the following requirements for soldier pile retaining walls:
Corrosion protection shall be designed and constructed to provide the required design service life.
Allowable horizontal deflection at the top of the wall shall not exceed 0.5 percent of the wall height.
Wall facings shall be cast-in-place concrete.
Minimum wall thickness shall be 6 inches.
Bar reinforcement in walls from bottom of pile cap or shallow foundation to 20 feet above mean highest
high water elevation shall conform to Standard Special Provision 52-650.
Provide a list of companies who will be performing the construction work and their experience with the
construction of these wall types.
Address the issue of larger steel sections and sacrificial steel for the soldier pile.
Timber used for temporary lagging shall not be treated.
All pre-drilled pile shafts in soldier pile walls shall be encased in concrete.
Corrosion protection shall be required for any soil anchors. Anchors shall be fully encapsulated with a
non-corrosive material.
13.3.17.1 Retaining Wall Types Restricted from Use
The following permanent retaining wall types are not allowed on this Project:
Steel sheet pile or timber piles
Soil nail walls that function as bridge abutments
Mechanically stabilized earth (MSE) walls that support bridge abutments
Soldier pile walls that function as bridge abutments
Any other wall type currently not pre-approved by the Department and not included in the Standards
Wall types shall not be inter-mixed when the inter-mixing will produce interruptions in the architectural
treatment facing.
13.3.18 Utilities
13.3.18.1 General Utility Requirements
The Design-Builder shall coordinate the details of Utility installation on the bridges. The Design-Builder
shall provide the following, as required by the individual Utility:
Concrete encased longitudinal conduit duct banks.
Concrete encased or exposed galvanized steel longitudinal and transverse conduits for systems and
Utilities on the bridge for aesthetic and roadway lighting or other Utilities.
Vaults, manholes and hand holes for systems and Utilities.
Blockouts through structural elements (abutments, crossbeams, floor beams, etc.)
Anchorages (e.g., structural inserts) for systems and Utilities attachments.
Accommodate for thermal movements and seismic displacements (longitudinal and transverse)
Page 23
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-23 Structures
The Design-Builder shall provide new rigid steel conduits as indicated in Table 13-1. Conduits shall follow
the horizontal and vertical alignment of the bridges. Allowance shall be provided to account for deflection
from time of installation, including potential bearing replacement. Expansion shall be provided for on all
conduit and pipe runs.
Where conduit passes through a structural element, the conduit shall pass through a polyvinylchloride pipe
sleeve block-out installed in the parapet wall at each abutment and extend 1 foot beyond the abutment. The
polyvinylchloride pipe sleeve shall have a diameter 2 inches larger than that of the conduit. All openings
around Utility installations shall be sealed to prevent water and debris from entering the structural
components and conduit.
Table 13-1: Bridge Conduit/Piping Requirements
No. of
Conduits
Conduit Diameter
(Inches) Location Purpose
Note 1 Note 1 Note 1 Roadway Lighting
Note 1 Note 1 Note 1 Aesthetic Lighting
Note 1 Note 1 Note 1 USCG
1 2 Length of bridges along
northern edge Future Port use
1 2 Length of bridges along
southern edge Future Port use
2 4 Length of bridges Port/Department Fiber Optic
1 4 Length of bridges Port Fiber Optic
2 2 Length of bridges Port/Department power
service
To be
determined To be determined To be determined Verizon telecommunications
To be
determined To be determined To be determined SCE
Note 1) The Design-Builder shall determine what is required per the appropriate standard for the purpose
stated.
13.3.18.2 Other Utility Requirements
For the Main Span Bridge, the Design-Builder shall locate all Utility facilities either in barrier or above the
low superstructure elevation inside of the edge girders unless noted otherwise in Table 13.1.
The Design-Builder may place conduits in a duct bank on the bridge deck between the tower and back of
median barrier.
The Design-Builder shall locate all Utility facilities in the Approach Bridges in barrier or inside the closed
box girder unless noted otherwise in Table 13.1.
The Design-Builder shall locate platforms, ladders, cabinets, etc used to access Utilities in areas out of public
view. In addition, the color of these items shall match the color of their surroundings.
Page 24
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-24 Structures
The strength of beams or girders shall not be reduced by drilling. Field welding on structures is not
permitted. All supports shall be of a non-rusting material.
The Design-Builder shall clearly mark each Utility facility at each vault, manhole or handhole location with
the Utility owner’s name and the type of facility. In addition, the Design-Builder shall identify individual
conduits or conduit bundles with the Utility owner’s name and the type of facility a minimum of every 100
feet long the conduits(s). A conduit bundle containing one Utility owner’s facility need only be labeled once
if it is clear the bundled conduits belong to the Utility owner identified.
The Design-Builder shall not locate Utilities within a minimum of two times the height of an adjacent
retaining wall unless the retaining wall is founded on deep foundations. The Design-Builder shall evaluate
structural adequacy when the immediate site conditions are changed after Final Acceptance due to work on a
Utility that is in place at the time of Final Acceptance.
High voltage electrical conduits and pipes containing fluids or gases shall not be placed in bridge barrier rails
or cast into concrete.
13.3.18.3 Water Lines
The water piping system shall conform to the requirements of NSF 61, Drinking Water System Components –
Health Effects, sections 1 through 9, for potable water piping and components. The water piping system shall
have a minimum working pressure rating of 80 psig. The pipe fitting shall be hot-dipped galvanized steel,
welded and seamless wall pipe, Schedule 40, conforming to the requirements of ASTM A53Grade B.
Flanges shall be 125 pound galvanized steel conforming to the requirements of ASME B 16.5 with flange
gasket material, and ASME B 16.21.Steel piping expansion joints shall be compound, galvanized, steel
fittings with telescoping body and slip –pipe section, including packing rings, packing, limit rods, chrome-
plated finish on slip-pipe sections and flange ends. Welded joint shall have a shop applied hot dipped
galvanizing.
Piping systems shall be located in areas out of public view if at all possible but the system shall be accessible
to the users of the system.
13.3.19 Anti-Graffiti Coating
The Design-Builder shall provide an anti-graffiti coating to the following items:
Main Span Bridge and Approach Bridge substructure units and retaining walls from 1 foot below ground
to 40 feet above ground
Main Span Bridge towers from the elevation of the deck to 40 feet above the deck
Stay cable guide pipes
Concrete barriers
The anti-graffiti coating shall be selected from the Departments Prequalified Products List for Graffiti
Removal and Preventative Products list. Extra solution to treat five percent of the total surface area treated
shall be provided to the Port to address graffiti in the future. The Design-Builder shall train Port and/or
Department maintenance staff on the use of the product and method to remove graffiti. Coatings that require
re-application after initial removal of graffiti are not allowed.
13.3.20 Strong Motion Sensors Instrumentation
The Design-Builder shall provide instrumentation on the bridges to record accelerations from strong ground
motions per Exhibit 2-13-G (Strong Motion Monitoring System Requirements). The bridges shall be
designed and constructed to accommodate motion sensors and accessories.
Page 25
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-25 Structures
13.3.21 As-Built Requirements
The Design-Builder shall submit As-Built models to the Port for the Main Span Bridge and portions of the
Approach Bridges required to be analyzed for seismic nonlinear time-history. These seismic nonlinear time-
history models shall be representative of the Project bridges in the as-built condition as defined by As-Built
Documents. Submitted information shall include all input, output and auxiliary files.
13.3.22 Submitting of Models
For bridges that require seismic nonlinear time-history design, the Design-Builder shall provide the Port an
ADINA model for each bridge. The Design-Builder has the option of ADINA software being used for the
design or the independent check. If changes to the bridge occur during construction that require an update to
the model the ADINA model that is submitted to the Port shall include these changes.
13.3.23 Class I Bikeway Barrier
Class I bikeway barriers shall relate aesthetically to the overall bridge architecture including the Main Span
Bridge and Approach Bridges. The Design-Builder shall provide an Architectural Element Report for the
proposed designs that includes the proposed barrier and railing designs. Below are the requirements for the
different general barrier sections that are expected on the Project:
Typical Section 1 – Approach Bridges over non-secure property. The additional width required for the
Class I bikeway shall be achieved by widening the concrete box section with web reinforcement as
needed. Provide minimum 54-inch-high railing on both sides of the Class I bikeway. For traffic side of
bikeway, railing shall be attached to non-traffic side of Type 736 barrier. For non-traffic side of pathway
deck mounted railing to be 54-inch-high. Railing shall meet the safety requirements of AASHTO LRFD
Bridge Design Specifications, 4th Edition, with California Amendments. The barrier mounted and deck
mounted railings shall be architecturally identical except for the mounting details. The opening on
protective fencing fabric shall be a maximum of 2 inches.
Typical Section 2 – Approach Bridges over secure property. Where the proposed Class I bikeway passes
over Port secure areas between zero feet high to twenty feet high, provide an 8’ high barrier on either
side of the Class I bikeway. For traffic side of bikeway, railing shall be attached to non-traffic side of
Type 736 barrier. For non-traffic side of pathway deck mounted railing to be 8’ high. Railing shall meet
the safety requirements of AASHTO LRFD Bridge Design Specifications, 4th Edition, with California
Amendments. The barrier mounted and deck mounted railings shall be architecturally identical except
for the mounting details. The opening on protective fencing fabric shall be a maximum of 2 inches.
Typical Section 3 – Main Span Bridge. Provide minimum 54-inch high railing on both sides of Class I
bikeway. For both sides of bikeway, deck mounted railing to be 54-inch high and meet the safety
requirements of AASHTO LRFD Bridge Design Specifications, 4th Edition, with California
Amendments. The opening on protective fencing fabric shall be a maximum of 2 inches. Brackets
supporting pathway shall be designed to be an integral architectural composition with the main span edge
girder or superstructure element.
13.4 Construction Requirements
13.4.1 Bracing
Temporary wind bracing shall be required during placement and construction of structural steel in the field.
13.4.2 Surface Finishes
All concrete surfaces shall receive a surface finish in accordance with the Caltrans Standard Specifications
for Construction. All steel surfaces shall be finished following the Department’s standard painting
specifications found in the Caltrans Standard Specifications for Construction, and the Caltrans Standard
Special Provisions for particular bridge elements. Finish colors shall be selected during the Visual Quality
Management Process outlined in Section 15.
Page 26
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-26 Structures
The Design-Builder shall coat steel in the shop per Exhibit 2-13-E.
13.4.3 Permanent Retaining Wall Structures
Overall tolerances shall be within 1/2 inch in 10 feet. The total settlement of the foundation shall not exceed
1 inch.
The Design-Builder shall provide subcut, backfill, and compaction in accordance with the foundation
recommendations.
The Design-Builder shall not use salvaged bituminous material or crushed concrete in the backfill.
For all retaining walls, total settlement and overall tolerances shall be based on site-specific requirements
determined by the geotechnical engineer.
13.4.4 Bridge Decks
Deck construction of bridges shall comply with the Standard Specifications. A permanent point shall be
marked on the concrete barrier on the exterior edges of bridges at the locations of columns or bents, and at
the mid spans and each abutment. Locations of these points with their as-built elevations shall be shown on
the As-Built Documents.
Use deck construction joints as shown in the RFC drawings and following industry standards.
Drilling into bridge decks is not allowed.
Remove all temporary attachments and repair damaged areas to the satisfaction of the Port.
Miscellaneous metals for construction shall be galvanized and protected against stray current. Miscellaneous
metal attachments shall not be visibly exposed on the surface of the bridge.
13.4.5 Temporary Structures
Construct temporary walls, access bridges, cofferdams, formwork, falsework, environmental containment,
shoring, protection of existing utilities, protection and shoring of existing structures, cranes, form travelers
and any other temporary structures needed to perform the Work. Protect existing property and remove all
temporary structures prior to Final Acceptance unless noted elsewhere in the Contract Documents.
No adjustment of temporary structure grades, elevations or changes to any vertical or lateral component of
the temporary structure is allowed without the approval of, and in the presence of, the Design-Builder’s
Registered Professional Engineer.
Temporary structures shall not be adjusted, erected or removed over live traffic. Erection shall include all
adjustments or removal of temporary structure components prior to concrete placement that contribute to the
horizontal stability of the temporary structure system. Removal shall include lowering temporary structures,
blowing sand from sand jacks, turning screws on screw jacks, and removing wedges.
Temporary structures over sidewalk or pedestrian walkways shall provide lighting, handrails and overhead
cover with a width of not less than 5 feet and extending 10 feet beyond the edges of deck.
Temporary structure openings over highways and local streets shall provide a minimum width to allow for
the number of traffic lanes which must be maintained. Temporary structure openings over freeways shall
meet permanent standards for minimum vertical clearance. Vertical clearance over local streets shall be in
compliance with the requirements of the Standards or the local agency.
Temporary structures adjacent to traffic shall be protected by Approved barriers.
13.4.6 Structure Demolition
A civil/structure Professional Engineer registered in the State of California must be present on site during
demolition operations.
Page 27
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-27 Structures
The Design-Builder shall stop work at locations where tests of samples from the locations determine that
existing material is contaminated with asbestos until the contaminated material is removed safely.
13.4.7 General Concrete Requirements
The Design-Builder shall meet the requirements on the Standards and applicable laws and rules pertaining to
concrete sources of supply, aggregates and associated mining operations.
The Design-Builder is responsible for controlling concrete curing heat of hydration.
13.4.8 Bridge Element Products
Bridge bearings improperly installed shall be adjusted or replaced at the discretion of the Port. Use temporary
bearings as needed. For products and equipment where manufacturer will specify a conditional requirement
that they shall provide installation oversight in order for the warranty to be valid and binding, the Design-
Builder shall allow the manufacturer to provide installation oversight to have the warranties binding.
13.4.9 Navigation and Aircraft Warning
The Design-Builder shall provide US Coast Guard- and FAA-approved navigation lighting systems on
temporary and permanent structures per the applicable Standard. The systems shall be suitable for a marine
environment.
At a minimum, all housings shall be constructed of non-corrosive material and mounting brackets shall be
hot-dip galvanized steel with stainless steel hardware complete with all required accessories.
13.4.10 Protection
Construct the Main Span Bridge and Approach Bridges with appropriate protection for workers and the
public safety, including river users and aviation requirements. Install temporary protection as required by
industry standards when not explicitly stated in the Contract Documents.
The Design-Builder shall acknowledge that due to the condition of the existing bridges there is a potential for
elements or portions of elements, such as pieces of deck concrete, to fall from the existing structures. The
Design-Builder is advised to take appropriate action.
13.4.11 Water Lines
The Design-Builder shall not enclose, cover or put into operation any water piping until it is inspected. The
Design-Builder shall notify the Port for inspection of piping at least 24 hours before concealing or closing-in
after roughing in and before setting fixtures. If the Port inspects the piping and determines that piping will
not pass testing or inspection, the Design-Builder shall make the required corrections and notify the Port for
re-inspection.
The Design-Builder shall test for leaks and defects in the piping and prepare Pressure Testing Reports that
shall be submitted at the completion of the test. Pressure Testing Reports shall include the following, at a
minimum:
How the pressure was held to the static test level and where was the source of the static pressure
Document the static pressure test level
Any required corrective action, location and what the corrective action will be and when it will be
completed.
If testing is performed in segments, the Design-Builder shall include a diagram showing the portion of the
piping tested.
The Design-Builder shall cap and subject the piping to static water pressure of 50 psig above working
pressure, without exceeding the pressure rating of the piping system materials; isolate the test source; and
allow to stand for four hours. Leaks and loss in test pressure constitute defects that must be repaired. The
Page 28
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-28 Structures
Design-Builder shall repair leaks and defects with new material and retest the piping or portion thereof until
satisfactory results are obtained.
The Design-Builder shall clean the piping system. Purging and disinfecting procedures shall conform to the
requirements of AWWA C651 or AWWA C652. The interior of the water piping shall be cleaned and debris
removed as Work progresses.
13.4.12 Equipment Use
Any operation that involves using X-rays or radiation-emitting equipment shall be reviewed and Approved
by the Port and the US Department of Homeland Security. The equipment usage schedule shall be
coordinated with the Port and the US Department of Homeland Security.
13.5 Deliverables
Unless otherwise indicated, all deliverables shall be submitted in both electronic format and hardcopy
format. Acceptable electronic formats include Microsoft Word, Microsoft Excel, or Adobe Acrobat (.PDF)
files, unless otherwise indicated. Drawings shall be submitted electronically in original MicroStation format
and in Adobe Acrobat (.PDF). At a minimum, the Design-Builder shall submit the following to the Port:
Deliverable
For
Acceptance
or
Approval
Number of Copies
Submittal Schedule Reference
Section Hardcopy Electronic
Bridge or Structure
Numbers and Names Acceptance 2 1 (PDF) Acceptance prior to
RFC documents 13.3.1
Concept Design
Submittal Approval 2 1 (PDF)
Approval prior to
Intermediate Design
Submittal
13.3.2
Updated General Plan
Submittal and
Distribution
Acceptance 2 1 (PDF) Approval prior to
RFC documents 13.3.2
Wind Tunnel Test
Report Approval 2 1 (PDF)
Approval prior to
submittal of the Wind
Engineering Study
Report
13.3.9
Wind Engineering
Study Report Approval 2 1 (PDF) Approval prior to
RFC documents 13.3.9
Bridge Load Rating
Report Acceptance 2 1 (PDF) Acceptance prior to
construction 13.3.10
Bridge Load Rating
Manual Approval 2
1 (PDF) &
native
format of
software
Approval prior to
Final Acceptance 13.3.10
Corrosion Protection
Plan Approval 2 1 (PDF) Approval prior to
RFC documents 13.3.12
Page 29
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-29 Structures
Deliverable For
Acceptance
or
Approval
Number of Copies Submittal Schedule Reference
Section
As-Built Corrosion
Protection Report Acceptance 2 1 (PDF) Acceptance prior to
Final Acceptance 13.3.12
Erection Manual Acceptance 2 1 (PDF)
Acceptance two
weeks prior to
construction
13.3.13
Operations and
Maintenance Manual Approval See Section 13.3.14
Main Span Bridge
Maintenance Concept
Plan Approval 2 1 (PDF)
Submitted with
Structure Type
Selection submittal
13.3.15
Approach Bridge
Maintenance Concept
Plan Approval 2 1 (PDF)
Submitted with
Structure Type
Selection submittal
13.3.16
Architectural Element
Report
Review and
Comment –
(CQAT);
Approval –
Port
2 1 (PDF) Prior to commencing
with final design
13.3.17
and
13.3.22
As-Built Models Acceptance N/A In native
format
Acceptance prior to
Final Acceptance 13.3.21
Pressure Testing
Reports Approval 2 1 (PDF)
Approval prior to
enclosing piping or
Substantial
Completion
13.4.11
Energy Dissipating
Shear Link Testing
Protocol
Approval 2 1 (PDF) Approval prior to
commencing testing
Exhibit
2-13-A
Energy Dissipating
Shear Link Test
Report
Acceptance 2 1 (PDF) Acceptance prior to
production fabrication
Exhibit
2-13-A
Stay Cable Quality
Control Program Approval 2 1 (PDF)
Approval prior to
procuring any stay
cable materials
Exhibit 2-
13-D
Stay Cable Wind, Rain
Vibration and
Pedestrian Comfort
Study Report
Approval 2 1 (PDF)
Approval prior to
procuring vibration
dampers and RFC
documents.
Exhibit 2-
13-D
Page 30
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
RFP 13-30 Structures
Deliverable For
Acceptance
or
Approval
Number of Copies Submittal Schedule Reference
Section
Cable Damping
Evaluation Report Acceptance 2 1 (PDF)
Within two weeks of
installation of a
dampening system or
portions thereof
Exhibit 2-
13-D
Testing Reports Acceptance 2 1 (PDF) Within two weeks of
completing each test
Exhibit 2-
13-D
Stay Cable Handling
Recommendations Acceptance 2 1 (PDF)
Provide to the Port at
the same time as
provided to the
Design-Builder
Exhibit 2-
13-D
Proposed Cable Stay
Schedule Acceptance 2 1 (PDF)
Acceptance prior to
testing cables
Exhibit 2-
13-D
Stay Cable Installation
Records Acceptance 2 1 (PDF)
Within twenty-four
(24) hours of
completing each cable
stressing operation
Exhibit 2-
13-D
Painting Quality Work
Plan Approval 2 1 (PDF)
Prior to performing
any painting or paint
removal
Exhibit 2-
13-E
ATVA Report Approval 2 1 (PDF) Prior to commencing
with final design
Exhibit 2-
13-F
ATVA Participant
Nominations Approval 2 1 (PDF)
Prior to commencing
with Work on the
ATVA Report
Exhibit 2-
13-F
ATVA Disclosure and
Certification form Approval 2 1 (PDF)
With ATVA
Participant
Nominations
Exhibit 2-
13-F
ATVA Live Scan
application Approval 2 1 (PDF)
With ATVA
Participant
Nominations
Exhibit 2-
13-F
ATVA Confidentiality
Agreement Approval 2 1 (PDF)
With ATVA
Participant
Nominations
Exhibit 2-
13-F
ATVA Information
Protocol Approval 2 1 (PDF)
Prior to commencing
work on ATVA
Exhibit 2-
13-F
Strong-Motion
Monitoring Product
List
Approval 2 1 (PDF) Prior to completing
final design
Exhibit 2-
13-G
Page 31
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-A
Design Criteria
This exhibit is provided as an electronic file.
Page 32
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-B
Wind Climate Data
This exhibit is provided as an electronic file.
Page 33
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-C
Technical Advisory Panel Charter and Review Process
This exhibit is provided as an electronic file.
Page 34
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-D
Stay Cable Systems
This exhibit is provided as an electronic file.
Page 35
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-E
Painting
This exhibit is provided as an electronic file.
Page 36
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-F
Accident and Terrorist Vulnerability Assessment (ATVA) Requirements
This exhibit is provided as an electronic file.
Page 37
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-G
Strong-Motion Monitoring System Requirements
This exhibit is provided as an electronic file.
Page 38
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-H
ATVA Disclosure and Certification form
This exhibit is provided as an electronic file.
Page 39
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-I
ATVA Live Scan application
This exhibit is provided as an electronic file.
Page 40
Port of Long Beach Book 2 – Gerald Desmond Bridge Project Project Identification Number 0700000379
EXHIBIT 2-13-J
ATVA Confidentiality Agreement
(To be provided when finalized)
This exhibit is provided as an electronic file.