Walker's Building Estimator's Reference, 29th Edition1.
An average percent of work performed by subcontractors cannot be precisely determined, butsurveys conducted by the Associated General Contractors of America indicate from ______
percent of the building industry work force is employed by subcontractors.
a) 70 to 80% b) 70 to 75%c) 40 to 70%d) 50 to 60%
Answer: C Solution: Page 4, The Role of the Contractor Question ID: 20125
2.Construction Manager's (CM) flat fees are determined by ___________.
a) A stated number of dollars plus expenses b) An agreed upon fixed feec) A percentage of the total construction costd) Any of the above described methods
Answer: D Solution: Page 6, Construction Management Question ID: 20126
3.The American Institute of Architects form AIA A-101 is __________.
a) The cost of the work plus a fee agreement b) The stipulated sum agreementc) Agreement between contractor and subcontractord) The general condition of the contract
Answer: B Solution: Page 10, Contract Documents Question ID: 20127
4.If a front-end loader consumes 4.6 gallons of fuel per hour and can load three cubic yards of debrisevery 1-1/2 minutes, approximately how much fuel will be consumed while loading 976 cubicyards of debris? (Consider only the information given).
a) 7.4 gallons b) 17.4 gallons
c) 27.4 gallonsd) 37.4 gallonsAnswer: D Solution: chapter 24 Mathematical, Proportion: 976 x 1.5 / 3 = 488 min. x 60 = 8.1333 hours x 4.6 gall= 37.41 Question ID: 20128
8/17/2019 GBRWalkers
2/45
© Contractors Institute February 20132 of 45
5.A backhoe can excavate 25 cubic yards of in-bank material per hour from a trench. The backhoecan backfill and grade the same trench at the rate of 35 cubic yards per hour. The backhoe costs$72. per hour to rent including the operator and fuel. The rental company has a pickup anddelivery charge equal to the total cost of 1-1/2 hours rental.
Without considering any displaced volume of pipe, the total cost to excavate and then backfill atrench that is 2 feet wide by 4 feet deep by 243 feet long is between ____ ?
a) $430 and $450 b) $451 and $470c) $471 and $490d) $491 and $ $510
Answer: B Solution: Chapter 24, Mathematical,
243 x 2 x 4 1944cf / 27 = 72 cy72 / 35 = 2.05772 / 25 = 2.88Total = 4.944.94 x 72 = 355.461.5 x 72 = 108.00Total = 463.46 Question ID: 20129
6.Most working drawings for buildings are based on ___________.
a) Oblique drawings b) Cavalier drawingsc) Isometric projectionsd) Orthographic projections
Answer: D
Solution: Page 35, General Requirements Question ID: 20130
7.The standard abbreviation letters, DTS, represents __________.
a) Draft to scale b) Dovetail anchor slotc) Drain through sewerd) Door threshold seal
Answer: B Solution: Page 52, Abbreviations
Question ID: 20131
8.The general conditions of the contract are AIA document _______.
a) A-101 b) A-201c) A-401d) A-701
8/17/2019 GBRWalkers
3/45
© Contractors Institute February 20133 of 45
Answer: B Solution: Page 13 Question ID: 20132
9.The _____________ is the most important person in a contractor's organization, simply becausetheir work will either make or break the contractor.
a) Financially responsibility officer b) Primary qualifying agentc) Estimatord) Superintendent / foreman
Answer: C Solution: Page 2 Question ID: 20133
10.What is the Maximum allowable slope for excavations in loamy sand (Type C) soil less than 20feet deep?
a) 34 degree b) 45 degreec) 53 degreed) 90 degree
Answer: A Solution: Walkers, Appendix B Table B-1 Table B-1 Maximum Allowable Slopes, or supart P OSHA Question ID: 20134
11 .It is standard practice to base equipment rates upon one shift of 8 hours per day or 40 hours perweek or ___ hours per month.
a) 176 b) 172c) 168d) 160
Answer: A Solution: Page 146, determine hourly rate Question ID: 20135
12.
A contractor has purchased new equipment, a large tractor, and has determined the following asreasonable costs:
Capital investment - - $ 80,000.00Depreciation - - - 90%Taxes, insurance, interest, and storage - - 65%
8/17/2019 GBRWalkers
4/45
© Contractors Institute February 20134 of 45
Using Walker's 29th edition, the maintenance allowance for most equipment will be ____.a) 50%
b) 60%c) 70%d) 80%
Answer: C Solution: Page 147, will fall between 65% and 75% Question ID: 20136
13.An arch having horizontal or nearly horizontal upper and lower surfaces is referred to as a:
a) trimmer arch b) jack archc) back archd) minor arch
Answer: B Solution: Walkers, Glossary Page 1590 Question ID: 20137
14.The Construction Specifications Institute is referred to as _________.
a) CRSI b) CSIc) CSSId) CSPI
Answer: B Solution: Page 59, Specifications Question ID: 20138
15.The CSI masterformat specification 07810 is work item ________.
a) Water repellents b) Plastic unit skylightsc) Skylightsd) Door hardware
Answer: B Solution: Page 70 Question ID: 20139
16.The CSI masterformat specification 03345 is work item _________.
a) Low density concrete b) Plant cast concretec) Concrete finishingd) Post tension concrete
Answer: C Solution: Page 66 Question ID: 20140
8/17/2019 GBRWalkers
5/45
© Contractors Institute February 20135 of 45
17.The type of drawing often used for piping diagrams is _________.
a) cabinet b) orthographicc) isometricd) cavalier
Answer: C Solution: Page 39, Types of Drawings Question ID: 20141
18.A scale, with the inch divided into tenths, is an __________ scale.
a) Abbreviated b) SI - metricc) Architect'sd) Engineer's
Answer: D Solution: Page 39, Scale Question ID: 20142
19.Lines consisting of short dashes usually indicate ________.
a) hidden lines b) outlinesc) dimensionsd) center lines
Answer: A Solution: Page 41, Interpreting Lines Question ID: 20143
20.Because bids are invited by advertisement, a bidder may have to submit a certified check with a
bid in lieu of a bid bond. The amount of the check is usually __ percent of the bid.a) 5%
b) 10%c) 15%d) 50%
Answer: A Solution: Page 128, Bid Bonds Question ID: 20144
8/17/2019 GBRWalkers
6/45
© Contractors Institute February 20136 of 45
21.The Federal government, under the _____ act, requires that a contractor furnish 2 separate bonds,1 for performance and 1 for payment of labor and materials on Federal projects.
a) FLSA b) Taftc) Millerd) Columbia
Answer: C Solution: Page 129, Performance & Payment Bond Question ID: 20145
22.Of the following choices, _______ is not a method of construction time scheduling.
a) CPM - Critical Path Method b) CSF - Construction Scheduling Formatc) PERT - Project Evaluation Review Techniqued) Gantt - bar chart scheduling
Answer: B Solution: Page 138 Scheduling Methods/Tools Question ID: 20146
23.In CPM scheduling, an activity with zero float time is a ___ activity, and therefore on the ___ pathand must be completed on time. The _____ path is the longest path of activities.
a) Critical b) Forwardc) Averaged) Backward
Answer: A
Solution: Review 138 to 151, page 148 Total Float Question ID: 20147
24.Which of the following statements is false?
a) The amount a contractor forfeits is $200, if a 5% bid bond was furnished, thecontractor failed to enter into a contract for $10,000 and the next bid $10,200
b) Phased construction allows the project to start earlierc) the cost of a bid bond is a cost borne by the contractord) the usual range of points is from 1 - 8%
Answer: D
Solution: a: page 128; b: page 10; c: page 9; d: page 27 Question ID: 20149
8/17/2019 GBRWalkers
7/45
© Contractors Institute February 20137 of 45
25.Which of the following statements is true?
a) AIA document B432 Architect's Qualification Statement b) Storage shelving is found in CSI masterformat, Division 9, Finishesc) A performance specification describes what work is required to produce resultsd) AFF is the abbreviation for "above first floor"
Answer: C Solution: (a - 15) (b -79) (c - 90) (d - 50) Question ID: 20150
26.Which of the following statements is false?
a) A/C contractors may find installation floaters suitable b) A forklift is covered under property damage insurancec) A contractor's temporary structure, on site, is covered under a builders risk policyd) Injuries caused by a subcontractor would be covered under the contractor's protectiveinsurance
Answer: B Solution: a: Page 127; b: Page 133; c: Page 134; d: Page 132 Question ID: 20151
27.The method of subsurface exploration which has been found to yield the least disturbed soilsamples is ______________.
a) Hand auger boring b) Split spoon samplingc) Slurry boring methodd) Thin-wall tube sampling
Answer: D
Solution: Page 151 Question ID: 20155
28.When excavating undisturbed material, assuming no water exists, the slope for an excavation inordinary clay is _____.
a) 1:1 b) 1:2c) 1:3d) 1:4
Answer: B
Solution: Page 168 Question ID: 20156
8/17/2019 GBRWalkers
8/45
© Contractors Institute February 20138 of 45
29.Regarding methods of excavating, hand excavation of heavy soil and clay from trenches 3' to 4' indepth will yield an average of ____ cubic yards per eight hour day per person.
a) 4 b) 5c) 6d) 10
Answer: B Solution: Page 181 Question ID: 20157
30.The approximate diesel fuel consumption for a 100 hp crawler type tractor is ________ gallons
per hour with a factor of 59%.a) 3.3
b) 4.0c) 6.8d) 8.0
Answer: B Solution: Page 194, read formula & example Question ID: 20158
31.Because in-bank materials swell when excavated or blasted, it is necessary to understand swellfactors for various soils. The swell factor for well blasted rock is _______.
a) 50% b) 30%c) 25%d) 20%
Answer: D Solution: Page 170 Question ID: 20159
32.A dragline working in the optimum depth of cut for maximum efficiency is a dragline which isworking ____ minutes per hour.
a) 45 b) 50c) 55d) 60
Answer: D Solution: Page 195 *second footnote Question ID: 20160
8/17/2019 GBRWalkers
9/45
© Contractors Institute February 20139 of 45
33.The degree of fill compaction usually called for in fills under paving and in government work is
_____ of maximum density and may take 12 passes with a sheepsfoot roller.a) 75%
b) 80%c) 90%d) 95%
Answer: D Solution: Page 234 Question ID: 20161
34.A sheepsfoot roller is 5' wide, moves 2-1/2 mph, compacts 12" fill layers, and is 100% efficient.Compacting medium clay with 6 passes will yield _____ cubic yards per hour.
a) 260 b) 285c) 326d) 367
Answer: C Solution: Page 234, 6 passes, medium clay, 80% Question ID: 20162
35.A contractor is compacting 12,000 cubic yards of loam in 9" lifts by using a 5 foot widesheepsfoot roller moving 2-1/2 mph. There are to be 6 passes at 83% efficiency and 10% loss intime due to turning. The time required to compact the loam is __________ hours.
a) 48 - 52 b) 52 - 56c) 56 - 60
d) 60 - 64Answer: C Solution: Page 235 Question ID: 20163
36.A sheepsfoot roller is engaged in compaction. The rate of compaction will be _____.
tractor drawn, double drum, 10 foot widefill layers - - 12"number of passes - - 8
soil type, medium clay - - 80%efficiency, 50 minutes per hour - -83%lost time for turning - - -10%
a) 183 cy / hr. b) 203 cy / hr.c) 366 cy / hr.d) 407 cy / hr.
8/17/2019 GBRWalkers
10/45
© Contractors Institute February 201310 of 45
Answer: C Solution: Page 234,235
Step 1.8 passes, medium clay 80%:( chart )= 245step 2.10 wide = double production( 245 x 2 )= 490step 3.50 minutes of 60 minutes = .83( 490 x .83 )= 406step 4.10% turning, 90% remains( 406 x .90 )= 366 cy / hr. Question ID: 20164
37.Estimate the time required to drive 40 - 28' long wood pilings to grade after the pile driver is setup and ready to operate. The time will be approximately _____ hours.
a) 4 b) 6c) 8d) 10
Answer: D Solution: Page 25540 piles / 4 per hour = 10 hours Question ID: 20165
38.An excavation measuring 120 feet by 80 feet is shored with 2 x 10 sheet piling timbers having a 91/4" width and a length of 10 feet. The shoring supports the vertical sides of the excavation. Thetotal amount of lumber required will be ____________ board feet.
a) 8,600 b) 8,800c) 10,800d) 12,800
Answer: A Solution: Page 288, 215 bf per 100 sf120' + 80' + 120' + 80' = 400' x 10' long = 4,000 sf / 100 x 215 = 8,600 bf Question ID: 20166
39.An excavation measuring 130 feet by 100 feet is shored with U.S. sheet piling section number PS-31. The sheets, each 30 feet long, are used to support the vertical sides of the excavation. Theweight of the steel sheet piling will be ________ tons.
a) 214 b) 294
c) 441d) 588Answer: A Solution: Page 293, PS-31, 31# per sf130 + 100 + 130 + 100 = 460 lf x 30 = 13,800 sf x 31 = 427,800 lbs / 2000 = 213.9 tons Question ID: 20167
8/17/2019 GBRWalkers
11/45
© Contractors Institute February 201311 of 45
40.The finishing of concrete pavements is a series of operations performed in which order?
a) consolidation, floating, straight-edging and brooming b) strike-off, floating, brooming and straight-edgingc) floating, strike-off, straight-edging and broomingd) strike-off and consolidation, straight-edging, floating, brooming, and edging
Answer: D Solution: Page 311 Question ID: 20168
41.PZ27 U.S. Steel sheet piling, 25 feet long is used in an excavation measuring 50 feet by 50 feet.The total weight will be ____ tons.
a) 45 b) 67.5c) 80d) 135
Answer: B Solution: Page 293, PZ27, 27# psf, 1 ton = 2,000 #50' + 50' + 50' + 50' = 200' x 25' = 5,000 sf x 27# psf / 2,000 = 67.5 tons Question ID: 20169
42.An 80 horsepower diesel bulldozer engine will consume _____ gallons of fuel per hour.
a) 3.2 b) 4.0c) 7.3d) 8.0
Answer: A
Solution: Page 19480 hp x .04 = 3.2 gph Question ID: 20170
43.PZ-27 U.S. Steel sheet piling has a width of _____ inches per sheet.
a) 16" b) 18"c) 21"d) 38"
Answer: B
Solution: Page 293 Question ID: 20171
8/17/2019 GBRWalkers
12/45
© Contractors Institute February 201312 of 45
44.An excavation measuring 60 feet by 40 feet will be shored using PS-31 steel sheet piling in 28'lengths. How many tons will be required?
a) 86.80 b) 75.60c) 80.20d) 44.80
Answer: A Solution: Page 293, PS-31, 31# psf, 1 ton = 2,000 #60' + 40' + 60' + 40' = 200' x 28' = 5,600 sf x 31 psf / 2,000 = 86.80 tons Question ID: 20172
45.A 2:1 slope indicates _____________.
a) 2 inches horizontal to 1 foot vertical b) 2 feet horizontal to 1 inch verticalc) 2 feet horizontal to 1 foot verticald) 2 feet vertical to 1 foot horizontal
Answer: C Solution: Page 169, horizontal to vertical Question ID: 20173
46.The weight of a 20 foot length of PZ27 steel sheet piling is ____.
a) 540 lbs b) 640 lbsc) 800 lbs.d) 810 lbs
Answer: D
Solution: Page 293, PZ27, 27# psf or 40.5# plf20 lf x 40.5 plf = 810 lbs.Or 20' x 1.5' x 27 psf = 810 lbs. Question ID: 20174
47.A grade of 5-1/2% is the equivalent of approximately _________.
a) 0.66' vertical rise per running foot b) 6.60" vertical rise per running footc) 0.55" vertical rise per running footd) 0.66" vertical rise per running foot
Answer: D Solution: Math, 5.5% is .055 x 12" = .66 inches of rise per foot Question ID: 20175
8/17/2019 GBRWalkers
13/45
© Contractors Institute February 201313 of 45
48.In the selective cutting and removal of trees, a 12" round by 25' high tree will require ______hours to cut and remove by hand.
a) 3 b) 8c) 12d) 15
Answer: C Solution: Page 153 Question ID: 20176
49.Which of the following four choices are true?
1. When hand excavating small footings in sandy loam, you can expect a laborer to move 6cubic yards per 8 hours.
2. A 1/2 cubic yard backhoe can move 150 cubic yards per 8 hour day when placingmaterial into waiting trucks.
3. When backfilling and compacting stockpiled material by hand, a laborer should move 12cubic yards per 8 hours.
4. A 1 cubic yard crawler mounted backhoe with operator will cost approximately $15,492a month in rental fees.
a) Only 1 is correct b) Only 2 is correctc) Only 3 is correctd) All 4 are correct
Answer: D Solution: (1 - 183) (2 - 183) (3 - 183) (4 - 189) Question ID: 20177
50.What is the easiest and most frequently used method of computing grading cuts and fills?
a) The End Area Method b) The Excess and Borrow Methodc) The Average Grade Methodd) The Cross-Sectional Method
Answer: D Solution: Page 172 Question ID: 20178
51. If interest, insurance, taxes and storage are based on 20% of the average investment of a powershovel, the annual amount will be ______, if a $150,000 shovel has an 8 year life.
a) $16,875 b) $18,750c) $84,375d) $ 3,750
Answer: A Solution: Page 192, find figure for 8 years Question ID: 20179
8/17/2019 GBRWalkers
14/45
© Contractors Institute February 201314 of 45
52.Repairs, maintenance and supplies for a 2 cubic yard, $106,000 power shovel, with an 8 year lifeis ____________ per hour.
a) $6.62 b) $66.20c) $662.50d) $82.81
Answer: A Solution: Page 193$106,000.00 x .00625% = $6.62/hr Question ID: 20180
53.The average useful life of a 1-1/2 cubic yard backhoe is _____.
a) 5 years b) 6 yearsc) 7 yearsd) 8 years
Answer: C Solution: Page 191 Question ID: 20181
54.A trench 150 feet long by 20 feet wide is to be shored on 4 sides using PZ-40 steel sheet piling.How many sheets are required?
a) 170 b) 227c) 256d) 207
Answer: D Solution: 293,PZ-4019.70" wide / 12" = 1.64' wide150' + 20' + 150' + 20' = 340' / 1.64' wide = 207 sheets Question ID: 20182
55.A 70 hp bulldozer is used to clear 5 acres of light brush, vegetation and tree saplings. The
bulldozer is 83% efficient. The time required to complete the clearing will average ____.a) 30 hours b) 36 hoursc) 182 hoursd) 230 hours
8/17/2019 GBRWalkers
15/45
© Contractors Institute February 201315 of 45
Answer: D Solution: Page 225900 - 1000 sf per hour = 950 sf averagesection 24.2, 1 acre = 43,560 sf43,560 x 5 acres = 217,800 sf / 950 sf = 229.3 hrs Question ID: 20183
56.If 3 men are using pneumatic tampers for backfill tamping, the number of men required to do themanual backfill is ___. Assume excavated earth is shoveled directly into trenches.
a) 3 men b) 6 menc) 9 mend) 12 men
Answer: B Solution: Page 246, 2 men per tamper, 3 x 2 = 6 Question ID: 20184
57.A contractor installs chain link fence at the rear of a 48 foot wide residence. The fence will extend60 feet to the rear property line enclosing the back yard on 3 sides. Chain link fence costs $15.00
per yard, including posts, and 1 - 3 foot required gate, including posts, costs $42.00. What will thefencing system for the residence cost?
a) $825.00 b) $867.00c) $882.00d) $1,107.00
Answer: B Solution: Page 312 and problem solving
60' + 48' + 60' = 168'/ 3 = 56 yards - 1(gate) = 55 x 15.00 = $825.00 + $42.00(gate) = $867.00 Question ID: 20185
58.A tremie is used where care must be exercised to reduce shock loading of concrete against formmaterial and should be used when the "free fall" distance is more than ____.
a) 4' b) 6'c) 8'd) 12'
Answer: A
Solution: Page 332 Question ID: 20186
8/17/2019 GBRWalkers
16/45
© Contractors Institute February 201316 of 45
59.When installing lightweight high-strength corrugated steel forms, the ends of the sheets should lapa minimum of ________.
a) 1" b) 2"c) 3"d) 4"
Answer: B Solution: Page 414 Question ID: 20187
60.13,360 pounds of #4 reinforcing bars, 20' long, are required on a project. The material supplier has20' long #5 bars available. If the same length #5 bars are used as the #4 bars required, theadditional weight of the bars would be _____ pounds.
a) 7,500 b) 13,360c) 20,860d) 7.5
Answer: A Solution: Page 447, #4 = .668 plf, #5 = 1.043 plf Question ID: 20188
61.#5 reinforcement bars are lapped 30 diameters. The length of the lap will be at least ___.
a) 15 inches b) 18.75 inchesc) 22.5 inchesd) 30 inches
Answer: B Solution: Page 447, #5 = .625" x 30 = 18.75" Question ID: 20189
62.The weight of 6x6-8x8 steel mesh to be placed in a 20' x 100' concrete driveway will be ______
pounds.a) 320
b) 490c) 580d) 1040
Answer: C Solution: Page 396, 29 pounds per 100 sf20' x 100' = 2,000 / 100 x 29 = 580 pounds Question ID: 20190
8/17/2019 GBRWalkers
17/45
© Contractors Institute February 201317 of 45
63.Sand nearly always contains surface moisture, usually about ______ percent by weight.
a) 1 or 2 b) 2 or 3c) 4 or 5d) 9 or 10
Answer: C Solution: Page 470 Question ID: 20191
64.The recommended maximum concrete slump for plain footings and slabs is ___ inches.
a) 1 b) 2c) 3d) 4
Answer: C Solution: Page 474 Question ID: 20192
65.The water-cement ratio, by weight, for non-air-entrained 3,000 psi concrete is _____.
a) 0.48 b) 0.57c) 0.59d) 0.68
Answer: D Solution: Page 477, Table 4 (a) Question ID: 20193
66.200 lengths of rebar are used on a project. The plans are provided with metric measure. The plansindicate a 16m bar for the concrete footings. The bar diameter will be ___ mm.
a) 11.3 mm b) 13 mmc) 15.90 mmd) 16 mm
Answer: C Solution: Page 447 Question ID: 20194
67.Ready-mixed concrete using high early strength Portland cement will develop the same strength in
____ hours as is obtained with normal Portland cement in 7 to 10 days.a) 24
b) 36c) 48d) 72
8/17/2019 GBRWalkers
18/45
© Contractors Institute February 201318 of 45
Answer: D Solution: Page 488 Question ID: 20195
68.The 16" thick second floor slab of a 2-story building is to be concrete construction using the 10"deep, 30" x 30" Ceco steel dome system. The 42' x 82' building will have 8 bays per floor and 49steel domes per bay. The total volume concrete required to construct the second floor only is ____cubic yards.
a) 64 cy b) 101 cyc) 170 cyd) 240 cy
Answer: B Solution: Page 550 Question ID: 20196
69.The volume of concrete required to pour a slab 50' x 60' over 30" wide flange type Ceco steelforms with an 8" depth, a 5" joist width, and 3" of concrete over the form is ___ cy.
a) 45 cy b) 47 cyc) 75 cyd) 88 cy
Answer: A Solution: Page 54850 x 60 = 3,000 x .408 = 1,224 / 27 = 45.33 Question ID: 20197
70.When bonding old concrete and new concrete, 5 gallons of weld-crete, when sprayed, will coverabout _____ square feet.
a) 200 - 300 b) 400 - 600c) 1,000-1,500d) 2,000
Answer: C Solution: Page 581 (200 x 5 = 1,000) (300 x 5 = 1,500) Question ID: 20198
71.The weight of #5 reinforcing bar is _____ pounds per linear foot.
a) 5.000 b) 1.043c) 1.502d) 0.625
8/17/2019 GBRWalkers
19/45
© Contractors Institute February 201319 of 45
Answer: B Solution: Page 447 Question ID: 20199
72.The basic relationship of concrete proportions states that the wetness of concrete, measured interms of slump is ___________.
a) Workability b) Consistencyc) Strengthd) Durability
Answer: B Solution: Page 472 Question ID: 20200
73.According to Walkers, The maximum slump for pavement and slabs when consolidated bymethods other than vibration is listed as _________.
a) 5" b) 4"c) 3"d) 2"
Answer: A Solution: Page 474, Table 1, * Footnote, + 1" Question ID: 20201
74. _______ pounds of water is recommended for a cubic yard of air entrained concrete with 1"aggregate and a slump of 3"- 4".
a) 295 b) 325c) 310d) 340
Answer: A Solution: Page 476, Table 3, 295 # per cy Question ID: 20202
75.
ASTM C-94, specification for ready-mixed concrete, states ready mixed concrete must bedelivered and discharged from the truck mixer within ___ after the introduction of water.a) 1 hour
b) 1.25 hoursc) 1.5 hoursd) 2 hours
Answer: C Solution: Page 487, 1-1/2 hours Question ID: 20203
8/17/2019 GBRWalkers
20/45
© Contractors Institute February 201320 of 45
76.Mesh reinforcing weighs _______ per 100 square feet for style 6x6 - 4x4.
a) 42 lbs. b) 58 lbs.c) 62 lbs.d) 85 lbs.
Answer: B Solution: Page 463 Question ID: 20204
77.In reference to building materials, roofing gravel weighs ______ pounds per cubic yard.
a) 2,500 b) 2,600c) 2,700d) 2,800
Answer: C Solution: Page 468 Question ID: 20205
78.If the outside dimensions of a square concrete slab are 120', the diagonal distance from corner tocorner will be ______.
a) 140'- 2" b) 156'- 4"c) 160'- 6"d) 169'- 8"
Answer: D Solution: Math formula Question ID: 20206
79. _____ sacks of cement will yield 1 cubic yard of concrete when mixed with 3/4" maximumaggregate. Assume a slump of 3" to 4".
a) 4.00 b) 5.75c) 6.00
d) 6.25Answer: D Solution: Page 516, chart, 3/4", under cubic yard Question ID: 20207
8/17/2019 GBRWalkers
21/45
© Contractors Institute February 201321 of 45
80.With regard to color for concrete floors, for 1" topping, use no more than _____ gallons of mixingwater, including water in aggregates
a) 9 b) 5c) 2d) 10
Answer: B Solution: Page 522 Question ID: 20208
81.Post-tensioning anchorages are typically designed to permit the stressing of tendons when theconcrete reaches a strength of _________.
a) 1,500 psi b) 2,500 psic) 3,000 psid) 3,500 psi
Answer: C Solution: Page 584 Question ID: 20209
82.How long would it take to cut off 120 - 16" square precast concrete piles?
a) 130 manhours b) 156 manhoursc) 120 manhoursd) 204 manhours
Answer: B
Solution: Page 275, back in site work, not concrete Question ID: 20210
83.The volume of mortar required to lay 1,000 face brick, in Dutch bond, using 1/2" end joints and
bed joints is _______ cubic feet. Assume the wall the be 4" thick.a) 7
b) 11.7c) 12.1d) 12.9
Answer: D
Solution: Pages 638-639, cubic feet per 1,000 face brick1,000 face brick, 1/2" bed joints, 11.7 cf + 10% for Dutch bond = 12.87 Question ID: 20211
8/17/2019 GBRWalkers
22/45
© Contractors Institute February 201322 of 45
84.8" x 2 1/4" x 3 3/4" standard brick are used in a 10' x 20' wall. The brick will be 2 courses thickwith 1/4" vertical joints and 1/2" bed joints. The wall has a full header course every 5th course.The total number of brick required for the wall will be ____.
a) 1,266 b) 1,520c) 2,534d) 3,041
Answer: D Solution: Pages 646-647, 8" thick, 1/2" bed, 12.67 per sf10' x 20' x 12.67 = 2,534 x 1.20 = 3,041 Question ID: 20212
85.A brick wall, 24 feet by 9 feet by 4 inches thick, is constructed with 1/4" mortar joints. If anallowance of 5 percent is made for waste of mortar, the volume of mortar required in theconstruction of the wall would be _____________ cubic feet.
a) 8.17 b) 8.61c) 9.04d) 9.47
Answer: C Solution: Page 647, 4" thick, 1/4" bed, 7 per sfPage 639, 4" thick, 1/4" bed, 5.7 cf / 100024' x 9' x 7 = 1,512 brick / 1,000 = 1.512 units x 5.7 = 8.61 x 1.05 waste = 9.04 Question ID: 20213
86.4" x 4" x 12" modular face brick are used with a 3/8" mortar joint, the volume of mortar for 1,000
brick would be ______ cubic feet.a) 36.90
b) 30.00c) 12.29d) 9.99
Answer: C Solution: Page 669, 1,000 / 3 per square foot = 333.33 sq. ft.333.33 / 100 = 3.33 x 3.69 = 12.29 cubic feet of mortar Question ID: 20214
87.
When constructing a wall of twin brick, 8" x 8" x 2-1/4" in size, about _______ cubic feet ofmortar is required per 1,000 brick.a) 15
b) 18c) 20d) 25
Answer: D Solution: Page 680, 25 cubic feet per 1,000 Question ID: 20215
8/17/2019 GBRWalkers
23/45
© Contractors Institute February 201323 of 45
88.
When handling masonry by palletization, a standard pallet, 32" x 24", accommodates enough brickmaterial to build ______.
a) 10 linear feet of wall, 8 feet high and 4 inches thick b) 10 linear feet of wall, 4 feet high and 4 inches thickc) 8 linear feet of wall, 4 feet high and 6 inches thickd) 8 linear feet of wall, 6 feet high and 8 inches thick
Answer: B Solution: Page 707 Question ID: 20216
89.A 10' x 200' load bearing masonry wall is constructed with 5-5/8" x 7-5/8" x 11-5/8" concrete
blocks. The wall will require _____ blocks. Assume no waste for the block.a) 1,500
b) 2,400c) 3,000d) 4,800
Answer: C Solution: Page 716, 10' x 200' = 2,000 / 100 x 150 = 3,000Note: Block 7-5/8" x 7-5/8" x 15-5/8" requires 112.5 per 100 sf, highlight this too ! Question ID: 20217
90.A cavity wall consists of two walls separated by continuous air space and securely tied togetherwith non-corroding metal ties for each _________ square feet of wall surface.
a) 2 b) 3c) 9d) 12
Answer: B Solution: Page 725 Question ID: 20218
91.4 cf bags of vermiculite fill _____ square feet of 8" block wall.
a) 25 b) 20
c) 14.5d) 6.66Answer: C Solution: Page 736 Question ID: 20219
8/17/2019 GBRWalkers
24/45
© Contractors Institute February 201324 of 45
92. ________ standard brick, 8" x 2 1/4" x 3 3/4", with 1/2" bed joints are required per square foot ofwall area. Assume 1 brick thick.
a) 7.33 b) 7.00c) 6.67d) 6.33
Answer: D Solution: Page 647, 4" thick, 1/2" bed joints Question ID: 20220
93.A 30' long x 5' high face brick wall is constructed using 1/4" end joints and 1/2" bed joints. Therewill be _________ brick required using a full header every fifth course and a common bond.
a) 1,260 b) 1,200c) 1,140d) 950
Answer: C Solution: 647-64830' x 5' x 6.33 x 1.20 = 1,140 Question ID: 20221
94.A Flemish bond using full headers every course adds ______ percent to the brick order.
a) 33.33% b) 16.66%c) 8.33%d) 5.6%
Answer: A Solution: Page 648 Question ID: 20222
95.The specification available for Portland cement is _______.
a) ASTM C 91 b) ASTM C 150c) ASTM C 476d) ASTM C 94
Answer: B
Solution: Page 629 Question ID: 20223
8/17/2019 GBRWalkers
25/45
© Contractors Institute February 201325 of 45
96.Of the following four statements, which is true ?
1. Mortar is subdivided into types M, N, O, and P.2. Type II Portland cement is used in most mortars3. Lime products sold in bags are usually quoted by the ton4. Pressure hydrated lime is referred to as type "N"
a) 1 is true b) 2 is truec) 3 is trued) 4 is true
Answer: C Solution: Page 636-639 Question ID: 20224
97.An experienced mechanic should clean between ____ and ____ face brick per hour.
a) 625 - 688 b) 750 - 825c) 3,500 - 4,000d) 5,000 - 5,500
Answer: A Solution: Page 691, 5,000-5,500 in 8 hrs.
5,000 / 8 = 6255,500 / 8 = 688
Question ID: 20225
98.According to Walkers Estimating, when laying glass block, mortar joints shall not be less than
_____, for Type S mortar.a) 1/8"
b) 3/16"c) 1/4"d) 3/8"
Answer: B Solution: Page 767 Question ID: 20226
99.When constructing an 8' high glass block wall panel, expansion joint shall be placed ___.
a) on the head and sill of the panel only b) on both side jambs of the panel onlyc) on the head and both jambs of the panel onlyd) on the sill of the panel only
Answer: C Solution: Page 766 Question ID: 20227
8/17/2019 GBRWalkers
26/45
8/17/2019 GBRWalkers
27/45
© Contractors Institute February 201327 of 45
Answer: A Solution: Page 825W = I beam, 12 = deep, 45 = # lf Question ID: 20232
105.A welder fillet welds 200' of 3/8" steel plates in the horizontal position, the total weight ofelectrode required is ___ pounds.
a) 30 b) 40c) 50d) 60
Answer: D Solution: Page 818200' x .30# per foot = 60 Question ID: 20233
106.A one inch square bar of steel, 1'- 0" long weighs ______ pounds.
a) 3.40 b) 13.60c) 15.40d) 30.40
Answer: A Solution: Page 829 Question ID: 20234
107.When steel joists are used in fireproof construction, it's necessary to place a __ reinforced slabover the joists and a fire resistant ceiling beneath the joists to obtain the rating.
a) 2" to 2-1/2" b) 3" to 3-1/4"c) 3" to 3-1/2"d) 4" to 4-1/2"
Answer: A Solution: Page 846 Question ID: 20235
108. The weight of 8d split-less wood siding nails to install 2,000 bf of 3/4" x 8" siding is ___.a) 5 pounds
b) 6 poundsc) 10 poundsd) 12 pounds
Answer: D Solution: Page 8793/4" x 8", 8d, 6 pounds per 1,000 bf Question ID: 20236
8/17/2019 GBRWalkers
28/45
© Contractors Institute February 201328 of 45
109.Square cap roofing nails with a full 15/16" square head are used on a job. The length of the nail is1". What is the approximate number of nails in a 50 pound box?
a) 78 b) 780c) 3,900d) 5,300
Answer: C Solution: Page 88478 nails per pound x 50 Question ID: 20237
110 .11 gauge nails are used for 3/4" plywood sub-floors. 2,700 nails for a job will weigh __ pounds.
a) 20 b) 23c) 25d) 27
Answer: B Solution: Page 8852,700 / 118 nails per pound = 23 pounds Question ID: 20238
111 .Which connector is a malleable iron casting of a grid-like structure with teeth protruding from
both faces?a) Toothed Rings
b) Spike Gridsc) Shear Platesd) Wedge-Fit Split Rings
Answer: B Solution: Page 896 Question ID: 20239
112 .Hardware accessories used for wood framing include H-clips for plywood support and spacing.1,000 H-clips would cost ________.
a) $45.00 b) $50.00c) $55.00d) $75.00
Answer: D Solution: Page 893$7.50 per 100 Question ID: 20240
8/17/2019 GBRWalkers
29/45
© Contractors Institute February 201329 of 45
113 .Where it is necessary to place wood furring strips on brick before lathing, a carpenter should placean average ________ linear feet of furring in an 8 hour day.
a) 325 b) 450c) 525d) 775
Answer: C Solution: Page 938500 to 550 lf per day, average 525 lf Question ID: 20242
114 .Of the following four statements, which is false?
1. Electric saws cut 10 to 20 times faster than a handsaw.2. The board foot formula is W" x T" x L" / 123. When estimating stud quantities for a wall, remember to always add one.4. 2" x 12" rough sawn cedar has two board feet per linear foot
a) 1 is false b) 2 is falsec) 3 is falsed) 4 is false
Answer: B Solution: (1 - 861) (2 - 862) (3 - 867) (4 - 873) Question ID: 20243
115 .Rafter length for a 5:12 rise and run can be figured by using a factor of ___ times the run.
a) 1.031 b) 1.054c) 1.083d) 1.118
Answer: C Solution: Page 8745/24 = 5:12 Question ID: 20244
116 .
A roof having a 5/12 pitch _________________.a) rises 5 inches for every 12 inches of run b) rises 7 inches for every 12 inches of runc) rises 9 inches for every 12 inches of rund) rises 10 inches for every 12 inches of run
Answer: D Solution: Page 874a 5:12 pitch is a 10:12 rise and run Question ID: 20245
8/17/2019 GBRWalkers
30/45
© Contractors Institute February 201330 of 45
117 .Which truss develops movement at its bearing points when under load?
a) a Cantilever truss b) a Clerestory trussc) a Mono pitch trussd) a Scissors truss
Answer: D Solution: Page 904 Question ID: 20246
118 .Top chord bearing parallel chord trusses should have a maximum gap of ____ between the insideof the bearing wall and the first diagonal or vertical web.
a) 1/8 inch b) 1/4 inchc) 1/2 inchd) 3/4 inch
Answer: C Solution: Page 910 Question ID: 20247
119 .An 18'- 9" wood roof truss should not deflect more than ______ for the bottom chord.
a) 1/8 inch b) 1/4 inchc) 3/8 inchd) 1-1/8 inches
Answer: D Solution: Page 90918 x 12 = 216 + 9 = 225 / 200 = 1.125" Question ID: 20248
120.For walls or floors, the single thickness of felt membrane waterproofing should lap ____,depending on specifications.
a) 2"- 4" b) 4"- 6"
c) 6"- 8"d) 8"- 12"Answer: B Solution: Page 1047 Question ID: 20249
8/17/2019 GBRWalkers
31/45
© Contractors Institute February 201331 of 45
121.One coat of Dehydratine 10 heavy dampproof paint is applied to one side of a masonry wall. Themasonry wall is 10' x 100'. _______ gallons of the paint would be required.
a) 10 b) 25c) 33 1/3d) 35
Answer: C Solution: Page 105610' x 100' = 1,000 / 30 = 33.33 gallons Question ID: 20250
122.A common building material, 8" cinder block, has an R-value of
a) 8.88 b) 5.33c) 1.11d) 2.00
Answer: C Solution: Page 1068 Question ID: 20251
123.The surface area, 3 1/2" thick, covered by 1 bag of 8 cubic foot density loose insulating woolweighing 40 pounds, including the area covered by studs or joists, is __ square feet.
a) 16.2 b) 17.2c) 18.3d) 19.7
Answer: C Solution: Page 10723 1/2", 8# density Question ID: 20252
124.A 32' x 32' building has a rise and run of 8 in 12. The roof slope factor will be _____.
a) 1.118 b) 1.158c) 1.202d) 1.564
Answer: C Solution: Page 1087multiply flat area by 1.202 Question ID: 20253
8/17/2019 GBRWalkers
32/45
© Contractors Institute February 201332 of 45
125.Refer to the Master Plan Set, Sheet A-05. The total roof area for the residence is ______ squarefeet.
a) 2,910 sf b) 3,067 sfc) 3,373 sfd) 4,228 sf
Answer: B Solution: Pages 1083-1087the factor for a 4:12 slope is 1.054 Question ID: 20254
126.Refer to the Master Plan Set, Sheet A-05. The total length of the hips for the roof is ________.
a) 43.59' b) 69.74'c) 74.10'd) 95.89'
Answer: C Solution: Page 1087the factor for a 4:12 hip or valley is 1.453 Question ID: 20255
127.Refer to the Master Plan Set, Sheet A-05. The total length of the ridge for the roof is ________.
a) 99 feet b) 81 feetc) 66 feetd) 47 feet
Answer: C Solution: Page 1085 Question ID: 20256
128.If an 18" wood shingle is placed on a 6:12 roof, the exposure for the shingle should be __.
a) 4-1/4" b) 5"c) 5-1/2"d) 7-1/2"
Answer: C
Solution: Page 1093 Question ID: 20257
8/17/2019 GBRWalkers
33/45
© Contractors Institute February 201333 of 45
129.A 22" x 12" roofing slate laid with a 3" lap has _________ pieces per square.
a) 95 b) 106c) 109d) 126
Answer: D Solution: Page 1097 Question ID: 20258
130.Corrugated steel installed on a 1/4 pitch roof requires a ________ end lap.
a) 2" b) 3"c) 4"d) 5"
Answer: C Solution: Page 1109 Question ID: 20259
131.The number of corrugated aluminum roofing sheets required for 100 square feet of area is _____,for 7' long x 35" wide x 0.032".
a) 4.90 b) 5.27c) 5.71d) 6.23
Answer: A Solution: Page1114 Question ID: 20260
132.A 1,200 sf roof covered with 2 plies of No.15 felt will require ______ rolls. Allow no lap.
a) 2.77 b) 3c) 5.55d) 6
Answer: C Solution: Page 11261,200 sf x 2 / 432 = 5.55 rolls
Question ID: 20261
8/17/2019 GBRWalkers
34/45
© Contractors Institute February 201334 of 45
133.The metal flashing used in connection with a flat roof deck covered with felt or built-up roofingusually extends ___ up the side of a brick fire wall and under the roofing as well.
a) 2"- 4" b) 4"- 6"c) 6"- 8"d) 6"- 12"
Answer: D Solution: Page 1153 Question ID: 20262
134.A 5 worker crew, in an 8 hour day, should install _____ squares of 3-ply asphalt built-up roofingover a concrete roof deck on a Type A building based on first class workmanship.
a) 18 b) 22c) 24d) 17
Answer: B Solution: Page 1127 read note 4 Question ID: 20263
135.One roofer can install ______ square feet of 1/16" butyl sheet roofing material per day.
a) 225 b) 325c) 425d) 525
Answer: A
Solution: Page 1131 Question ID: 20264
136.To obtain actual valley length for a 4:12 sloped roof, multiply the roof run by ______.
a) 1.054 b) 1.083c) 1.436d) 1.453
Answer: D Solution: Page 1087
Question ID: 20265
137.To obtain actual roof area for a 9:12 rise and run, multiply the flat roof area by ______.
a) 1.118 b) 1.250c) 1.302d) 1.600
8/17/2019 GBRWalkers
35/45
© Contractors Institute February 201335 of 45
Answer: B Solution: Page 1087 Question ID: 20266
138.To obtain actual hip length for a 4:12 rise and run, multiply the roof run by ________.
a) 1.453 b) 1.500c) 1.564d) 1.612
Answer: A Solution: Page 1087 Question ID: 20267
139.When a shingler is to lay wood shingles on a difficult gable roof which is cut up with gables,dormers, hips and valleys, and the shingles are laid 4-1/2" to the weather, the actual time requiredfor the shingler to lay one square is __________ hours.
a) 2.5 b) 2.8c) 3.0d) 4.0
Answer: C Solution: Page 1092 Question ID: 20268
140.If laying wood shingles 5" to the weather, _______ pounds of 3d nails will be required.
a) 1.6 pounds, per square b) 2.0 pounds, per squarec) 2.5 pounds, per squared) 4d nails are required
Answer: B Solution: Page 1090 Question ID: 20269
141.Which of the following building materials has the closest R-value to 4" face brick?
a) 1/2" gypsum board b) a 4" concrete slabc) 8" lightweight blockd) 1" x 8" drop siding
Answer: A Solution: Page 1069 Question ID: 20270
8/17/2019 GBRWalkers
36/45
© Contractors Institute February 201336 of 45
142.When using 40 lb. bags of loose insulating wool containing 4 cubic feet, including the areacovered by ceiling joists, it will cost $ ____ to insulate a 20' x 30' ceiling using a density of 10cubic foot per pound and a thickness of 4 inches. Each bag costs $1.69.
a) $70.00 b) $80.00c) $90.00d) $98.00
Answer: B Solution: Page 107210 lb. density, 4" thick, 12.7 sf / bag20' x 30' = 600 / 12.7 = 47.24 bags x $1.69 = $79.83 Question ID: 20271
143.The approximate number of bags of vermiculite fill required for an 8" block wall with 1,000square feet of area is ________.
a) 69 b) 34c) 7d) 63
Answer: A Solution: Page 1074 Question ID: 20272
144.The rate of conductance of a combination of materials, known as its "U" factor, is the BTU perhour, per inch of thickness, per square foot, per degree temperature difference. R ratings arereciprocals of conductance and therefore, one would use the formula ____.
a) R = U / 1 b) R = 1 / Cc) R = C / 1d) R = 1 / U
Answer: D Solution: Page 1069 Question ID: 20273
145.The R-value for a wall assembly with a U-value of .075 is ______.
a) .075
b) 13.33c) 7.50d) 14.28
Answer: B Solution: Page 1069R = 1 / U1 / .075 = 13.33 Question ID: 20274
8/17/2019 GBRWalkers
37/45
© Contractors Institute February 201337 of 45
146.The maximum spacing of vertical supports when attaching flat expanded lath is ____ o.c.
a) 10" b) 12"c) 16"d) 24"
Answer: C Solution: Page 1267 Question ID: 20275
147.A suspended ceiling is installed using main runners consisting of 1-1/2", 0.475 pound, cold rolledchannels supported by 10 gauge wire hangers spaced 3'- 6" apart. What is the maximum center tocenter spacing of the main runners?
a) 2'- 0" b) 2'- 6"c) 3'- 0"d) 3'- 6"
Answer: D Solution: Page 1270 Question ID: 20276
148.The scratch and brown coats of stucco should be mixed in the proportion of 1 part Portland cementto _____ parts clean sand.
a) 1 b) 2c) 3d) 4
Answer: C Solution: Page 1323 Question ID: 20277
149.What would 80 bundles of 3/8 inch gypsum lath weigh, in tons?
a) 1 ton b) 2 tonsc) 3 tonsd) 4 tons
Answer: B
Solution: Page 126080 x 50 = 4,000 / 2,000 = 2 tons Question ID: 20278
8/17/2019 GBRWalkers
38/45
© Contractors Institute February 201338 of 45
150.Some locales mandate a flush not greater than ______ gallons, for water closets.
a) 1.0 gallon b) 1.5 gallonsc) 2.5 gallonsd) 3.5 gallons
Answer: B Solution: Page 1508 Question ID: 20279
151.Estimate the cubic yards of material to be excavated from a pit with a base dimension of 4' x 20'.The pit is 8' deep, the sides and ends are sloped at 1 to 1, which is Type B soil.
a) 23.70 b) 56.88c) 99.55d) 1,536
Answer: C Solution: Mensuration page 1565 Question ID: 20290
152.Healthy workers are productive ones, and a good safety record can mean lower workerscompensation rates, which for some contractors can be ____ to ____ of total contract amount
a) 1% - 3% b) 2% - 5%c) 5% - 10%d) 8% - 12%
Answer: C
Solution: Appendix B page 1615 Question ID: 20291
153.Masonry units that do not meet the standards or specifications and have been rejected is known as
________?a) EBM
b) eccentricityc) cullsd) collective
Answer: C
Solution: Appendix A page 1598 Question ID: 20292
8/17/2019 GBRWalkers
39/45
8/17/2019 GBRWalkers
40/45
© Contractors Institute February 201340 of 45
158.Rust proof metal ties shall be placed every ______ course and _____ on center in brick cavitywalls.
a) 6th, 30” b) 6th, 36”c) 8th, 30”d) 8th, 36”
Answer: B Solution: Page 672 Question ID: 20298
159.What is the Swell Percentage of well blasted rock?
a) 10% b) 15%c) 20%d) 25%
Answer: C Solution: Page 170 Question ID: 20299
160.Wood roof trusses are used for spans as short as ______ and can be used up to _____ .
a) 15’, 200’ b) 25’, 200’c) 15’, 250’d) 25’, 250’
Answer: B Solution: Page 897 Question ID: 20300
161.For a Contractor to get pre-qualified to bid on public work, he would generally use document:
a) AIA A701 b) AIA G706c) AIA A-305d) AIA A-904
Answer: C Solution: Page 13 Question ID: 20301
162.How many pounds are 4.5 Metric Tons?
a) 8,818 b) 9,000c) 9,921d) 9,989
8/17/2019 GBRWalkers
41/45
© Contractors Institute February 201341 of 45
Answer: C Solution: Mensuration, page 1582Tons, metric 2204.62 Pounds4.5 x 2204.62 = 9,920.79 Question ID: 20302
163.Which of the following is best at describing the relationships of project activities?
a) Bar Charts b) Gantt Chartsc) Network logic diagramsd) A/R analysis
Answer: C Solution: Page 141 Question ID: 20305
164.A contractor needs to pour 9 bollards which are 8” in diameter and 9 feet long. How many cubicyards of concrete would be required?
a) .11 b) 1.03c) 4.22d) 12.56
Answer: B Solution: 3.14 x .33 x .33 = .342 sf x 9' = 3.08 cf x 9 bollards = 27.72 / 27 = 1.03 Question ID: 20306
165.According to Walkers, If lumber costs $.39 per board foot, how much would the lumber cost toconstruct a wall 20' long, 10' high using 2 x4 studs at 16" o.c. with single top and bottom plates.Make no allowance for waste.
a) 23.23 b) 51.87c) 87.11d) 88.22
Answer: B Solution: Page 868 Section 6.7133 x .39 = 51.87 Question ID: 20307
166.According to Walker’s Building Estimator’s Reference which of the following schedule activitieswould be frozen and saved?
a) Early start b) Targetc) Baselined) Milestone
8/17/2019 GBRWalkers
42/45
© Contractors Institute February 201342 of 45
Answer: C Solution: Page 142 Question ID: 20311
167.A contractor is calculating Masonry labor costs for a building. Up to 12 stories tall a factor of100% is used. What factor would be used for the 22nd floor of the building?
a) 110% b) 112%c) 113%d) 114%
Answer: A Solution: Table, Page704 Question ID: 20312
168.In CPM calculations Total float is calculated by:
a) Early Start minus Late Start of an activity b) Late Start minus Early Start of an activityc) Probable Start minus Early Start of an activityd) Late Start minus Probable Start of an activity
Answer: B Solution: Page 141 Question ID: 20313
169.What is the most common tool for scheduling construction activities?
a) Bar Charts b) Gantt Chartsc) Critical Path Method (CPM)d) Project Evaluation and Review Technique (PERT)
Answer: C Solution: Page 138 Question ID: 20314
170.Which of the following would serve as the guide for purchase of material and the award ofsubcontracts?
a) The detailed estimate b) The preliminary estimatec) The project specificationsd) The project contract
Answer: A Solution: Page 107 Question ID: 20315
8/17/2019 GBRWalkers
43/45
8/17/2019 GBRWalkers
44/45
© Contractors Institute February 201344 of 45
Answer: B Solution: Page 827 Question ID: 20320
176.Chalkboards, whether black or green in color, are made from ________.
a) chalk b) boardsc) hardboardd) slate
Answer: C Solution: Page 1459 Question ID: 20321
177.Constructing the temporary end of a masonry wall with the end stretcher unit of every alternatecourse projecting is called __________________.
a) corbelling b) toothingc) steppingd) half-done
Answer: B Solution: Appendix A, Glossary look under the letter T Toothing. Page 1610_]_____]_]_____]_]_____]
_]_____] Question ID: 20323
178.According to Walker's Building Estimator's Reference Book, Contractors will frequently useinformation about subsurface conditions on the working drawings which include a disclaimer.Who would be responsible for the accuracy of this information?
a) The contractor b) The architectc) The engineer
d) The ownerAnswer: A Solution: Page 149 Question ID: 20324
8/17/2019 GBRWalkers
45/45
179.Which selection best represents the additional labor cost associated with handling brick and mortarfor a 22 story high building?
a) 2.5% b) 10%c) 12%d) 22%
Answer: B Solution: page 704 Question ID: 20325
180.Which of the following would indemnify the owner against loss resulting from the failure of thecontractor to complete the work in accordance with the plans and specifications?
a) Performance Bond b) Payment Bondc) Contractor Liability Insuranced) Builders Risk Insurance
Answer: A Solution: Page 129 Question ID: 20327
181.What is the difference in swell factor between “Dry Clay” and “Wet Clay”?
a) 0% b) 1%c) 10%d) 20%
Answer: A
Solution: Page 170 Question ID: 20328
182.The weight of 150' of 2-1/2" x 2-1/2" x 3/16" steel angles is tons.
a) .23 b) 3.07c) 225d) 460.5
Answer: A Solution: Walkers, Page 835, 150 x 3.07/2,000 = .23 tons
Question ID: 20543