Picture Project Report Project : Roll in/out 2 engines for Navigat-MaxPower at PLTMG Teluk Lembu, Pekanbaru, Riau Time : 9 – 20 November 2015 1. DESCRIPTION AND SCOPE OF WORK The main activity for this work is to replace 2 units of engine at PLTMG Teluk Lembu also to transport the replacement engines from Belawan, North Sumatera and transport the old units to PLC (Pekanbaru Logistics Center) Rumbai. The work includes the activity of loading/unloading roll out and roll in 2 sets of engines from enclosure / Power House. 2. TIME IMPLEMENTATION PLAN (Start Date and End) AND THE HOUR START AND FINISH EVERY DAY Initial Project Time Frame: The work time will be: a. Start : 08.00 WIB b. Finish : 17.30 WIB c. Over-time : 22.00 WIB The over-time schedule planned be conducted only when it is absolutely necessary and in accordance to HSE regulation and standard. In any case, we were focused on the main schedule. HSE Department
6

Gas Engine Photo

Jan 28, 2018

Download

Documents

Andry Saputra
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Gas Engine Photo

Picture Project Report

Project : Roll in/out 2 engines for Navigat-MaxPower at PLTMG Teluk

Lembu, Pekanbaru, Riau

Time : 9 – 20 November 2015

1. DESCRIPTION AND SCOPE OF WORK The main activity for this work is to replace 2 units of engine at PLTMG Teluk Lembu also to transport the replacement engines from Belawan, North Sumatera and transport the old units to PLC (Pekanbaru Logistics Center) Rumbai. The work includes the activity of loading/unloading roll out and roll in 2 sets of engines from enclosure / Power House.

2. TIME IMPLEMENTATION PLAN (Start Date and End) AND THE HOUR START AND FINISH EVERY DAY

Initial Project Time Frame:

The work time will be:

a. Start : 08.00 WIB b. Finish : 17.30 WIB c. Over-time : 22.00 WIB

The over-time schedule planned be conducted only when it is absolutely necessary and in accordance to HSE regulation and standard. In any case, we were focused on the main schedule.

HSE Department

Page 2: Gas Engine Photo

3. ENVIRONMENTAL RISK ASSESSMENT BY SURVEY

4. WORKING METHOD a. Pre-Work Safety Briefing

To ensure that every workers on the field knows what to do and how to do it safely, every day we conducted pre-work safety briefing. This briefing include socialization of JSA and Safety evaluation from yesterday’s work.

Page 3: Gas Engine Photo

b. Assembling heavy equipment (50 Ton Crawler Crane) For this project we use 50-Ton Crawler Crane, as part of safety measure and to avoid damage to concrete road we put wooden block as rail for the Crane’s track

Page 4: Gas Engine Photo

c. Clearing the working environment As per our first survey to Teluk Lembu, we have to move some of Navigat’s container office to make space for rolling work. As rolling work need a lot of space, not only to secure the engines move

but also to give a lot of space for workers to work or to evacuate in case of emergency.

Page 5: Gas Engine Photo

d. Jacking and Rolling Old Engine out

Lifting the Old Engine using jacking technique

Rolling out the old engine out

e. Unload the New Engine and Load the Old Engine to Truck To make sure that the engines were lifted properly according to Navigat’s procedure, we use adjustable spreader bar so that the weight distributed properly when conducting the lifting.

Page 6: Gas Engine Photo

f. Rolling New Engine in

g. Deliver the old Engine to PLC

Prepared by, Approved by

Adhitya Wicaksono Andriyana Saputra

HSE Coordinator Project Manager