REKAPITULASI BIAYA ( ENGINEER ESTIMATE ) KEGIATAN : Pembangunan Gapura LOKASI : Jalan M. Said Gang. 4 NO U R A I A N P E K E R J A A N A PEKERJAAN PERSIAPAN B PEKERJAAN TANAH DAN PASIR C PEKERJAAN PANCANGAN D PEKERJAAN PASANGAN DAN PLESTERAN E PEKERJAAN BETON BERTULANG F PEKERJAAN CAT CATAN a J U M L A H b PPN 10 % c TOTAL d DIBULATKAN Terbilang : Tujuh Juta Lima Ratus Dua Puluh Tiga Ribu NIP. 110 048 077 Samari Marce
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
REKAPITULASI BIAYA( ENGINEER ESTIMATE )
KEGIATAN : Pembangunan GapuraLOKASI : Jalan M. Said Gang. 4
NO U R A I A N P E K E R J A A NJUMLAHHARGA
(RP)
A PEKERJAAN PERSIAPAN Rp 4,452.50 B PEKERJAAN TANAH DAN PASIR Rp 46,370.00 C PEKERJAAN PANCANGAN Rp 825,825.00 D PEKERJAAN PASANGAN DAN PLESTERAN Rp 2,197,524.28 E PEKERJAAN BETON BERTULANG Rp 3,669,806.70 F PEKERJAAN CAT CATAN Rp 95,320.90
a J U M L A H Rp 6,839,299.38 b PPN 10 % Rp 683,929.94 c TOTAL Rp 7,523,229.32 d DIBULATKAN Rp 7,523,000.00
Terbilang :
Tujuh Juta Lima Ratus Dua Puluh Tiga Ribu Rupiah
NIP. 110 048 077
Samarinda, 22 Juli 2012Dibuat
Marcekal Hilyan Bernae
RENCANA ANGGARAN BIAYA[ ENGGINER ESTIMATE ]
KEGIATAN : Pembangunan GapuraLOKASI : Jalan M. Said Gang. 4
NO. URAIAN PEKERJAAN SAT. VOLUME HARGA SAT. JML.HARGA
A PEKERJAAN PERSIAPAN1 Pembersihan Lapangan dan Perataan M² 0.650 6,850.00 4,452.50
PEKERJAAN PERSIAPAN 4,452.50 B PEKERJAAN TANAH DAN PASIR1 Galian tanah pondasi M³ 0.882 28,800.00 25,401.60 2 Pemadatan tanah M³ 0.650 31,000.00 20,150.00 3 Urugan pasir bawah pondasi dan lantai M³ 0.044 18,600.00 818.40
PEKERJAAN TANAH DAN PASIR 46,370.00 C PEKERJAAN PANCANGAN 1 Pancang ulin 10/10x 1 m' Ttk 5.000 88,065.00 440,325.00 2 Kalang ulin 5/10 M³ 0.150 2,500,000.00 375,000.00 3 Papan ulin 5/20 M³ 0.004 2,500,000.00 10,500.00
PEKERJAAN PANCANGAN 825,825.00 D PEKERJAAN PASANGAN DAN PLESTERAN1 Pasang batu gunung 1 : 4 M³ 1.180 498,650.00 588,407.00 3 Pasang batu bata tebal ½ bata 1 : 4 M² 0.936 67,518.00 63,196.85 5 Plesteran 1 : 4 M² 0.683 29,627.00 20,220.43 7 Pasangan batu alam dinding M² 4.250 150,000.00 637,500.00 8 Tanam rumput + tanaman M² 8.882 100,000.00 888,200.00 I PEKERJAAN PASANGAN DAN PLESTERAN 2,197,524.28 E PEKERJAAN BETON BERTULANG2 Cor sloof 25/30 M³ 0.158 5,341,555 841,294.91 3 Cor kolom praktis 20/20 M³ 0.520 5,341,555.00 2,777,608.60 4 cor beton sirip 5cm M³ 0.078 652,605.00 50,903.19
PEKERJAAN BETON BERTULANG 3,669,806.70 F PEKERJAAN CAT CATAN1 Cat dinding M² 8.200 11,624.50 95,320.90
PEKERJAAN CAT CATAN 95,320.90
DAFTAR ANALISA PEKERJAAN
KEGIATAN : Pembangunan Gapura LOKASI : Jalan M. Said Gang. 4
HARGA JUMLAH NO URAIAN PEKERJAAN KOEFISIEN SATUAN SATUAN HARGA
(RP) (RP)
A PEKERJAAN PERSIAPAN1 Pembersihan Lapangan dan Perataan 1.000 M¹
69,515.32 6 Pasang list gypsum/cornice Plafond 1 M¹
List gypsum 1.000 M¹ 55,000.00 55,000.00 Lem gypsum 0.200 Kg 0.00 Pekerja 0.200 Oh 55,000.00 11,000.00 Mandor 0.010 Oh 70,000.00 700.00 Tukang kayu 0.060 Oh 60,000.00 3,600.00 Kepala tukang kayu 0.010 Oh 65,000.00 650.00
70,950.00 HARGA JUMLAH
NO URAIAN PEKERJAAN KOEFISIEN SATUAN SATUAN HARGA (RP) (RP)
I PEKERJAAN PENUTUP LANTAI & DINDING1 Pasang lantai keramik 40x40 cm 1
Keramik 40 x 40 cm 6.000 Bh 7,500.00 45,000.00 Semen 14.150 Kg 1,160.00 16,414.00 Pasir pasang 0.039 96,000.00 3,744.00 Semen warna 2.000 Kg 1,500.00 3,000.00 Pekerja 0.620 oh 55,000.00 34,100.00 Mandor 0.030 oh 70,000.00 2,100.00 Tukang batu 0.350 oh 60,000.00 21,000.00 Kepala tukang batu 0.035 oh 65,000.00 2,275.00
127,633.00 2 Pasang lantai keramik 30 x 30 cm 1
keramik 20 x 20 cm 20.000 Bh 5,000.00 100,000.00 Semen 14.150 Kg 1,160.00 16,414.00 Pasir pasang 0.039 96,000.00 3,744.00 Semen warna 2.000 Kg 1,500.00 3,000.00 Pekerja 0.620 OH 55,000.00 34,100.00 Mandor 0.030 OH 70,000.00 2,100.00 Tukang batu 0.350 OH 60,000.00 21,000.00 kepala tukang batu 0.035 OH 65,000.00 2,275.00
182,633.00
M²
M²M²
M²
M³
M²
M³
HARGA JUMLAH NO URAIAN PEKERJAAN KOEFISIEN SATUAN SATUAN HARGA
(RP) (RP)3 Pasang lantai keramik 25 x 25 cm 1
keramik 25 x 25 cm 16.000 Bh 2,250.00 36,000.00 Semen 9.300 Kg 1,160.00 10,788.00 Pasir pasang 0.018 96,000.00 1,728.00 Semen warna 1.500 Kg 1,500.00 2,250.00 Pekerja 0.600 OH 55,000.00 33,000.00 Mandor 0.030 OH 70,000.00 2,100.00 Tukang batu 0.100 OH 60,000.00 6,000.00 kepala tukang batu 0.045 OH 65,000.00 2,925.00
94,791.00 4 Pasang lantai keramik km/wc 20 x 20 cm 1
keramik 20 x 20 cm 25.000 Bh 2,250.00 56,250.00 Semen 11.380 Kg 1,160.00 13,200.80 Pasir pasang 0.042 96,000.00 4,032.00 Semen warna 1.500 Kg 1,500.00 2,250.00 Pekerja 0.600 OH 55,000.00 33,000.00 Mandor 0.030 OH 70,000.00 2,100.00 Tukang batu 0.100 OH 60,000.00 6,000.00 kepala tukang batu 0.045 OH 65,000.00 2,925.00
119,757.80 5 Pasang dinding keramik km/wc 10 x 10 cm 1
keramik 10 x 10 cm 100.000 Bh 1,250.00 125,000.00 Semen 11.380 Kg 1,160.00 13,200.80 Pasir pasang 0.042 96,000.00 4,032.00 Semen warna 2.000 Kg 1,500.00 3,000.00 Pekerja 0.600 OH 55,000.00 33,000.00 Mandor 0.030 OH 70,000.00 2,100.00 Tukang batu 0.100 OH 60,000.00 6,000.00 kepala tukang batu 0.045 OH 65,000.00 2,925.00
189,257.80
J PEKERJAAN CAT-CATAN1
1 M³
Plamir 0.1000 Kg 22,000.00 2,200.00 Cat dasar 0.1000 Kg 11,000.00 1,100.00 Cat penutup 2 kali 0.2600 Kg 11,000.00 2,860.00 Pekerja 0.0200 Org/hari 55,000.00 1,100.00 Mandor 0.0025 Org/hari 70,000.00 175.00 Tukang cat 0.0630 Org/hari 60,000.00 3,780.00 kepala tukang cat 0.0063 Org/hari 65,000.00 409.50
11,624.50 2
1 M³
Cat meni 0.2000 Kg 25,000.00 5,000.00 Dempul kayu 0.1500 Kg 15,000.00 2,250.00 Cat dasar kayu / kilap 0.1700 Kg 36,500.00 6,205.00 Cat kilap penutup 2 kali 0.2600 Kg 36,500.00 9,490.00 Pekerja 0.0700 Org/hari 55,000.00 3,850.00 Mandor 0.0250 Org/hari 70,000.00 1,750.00 Tukang batu 0.0900 Org/hari 60,000.00 5,400.00 kepala tukang batu 0.0060 Org/hari 65,000.00 390.00
Kloset jongkok 1.0000 Bh 150,000.00 150,000.00 Semen 6.0000 Kg 1,160.00 6,960.00 Pasir pasang 0.0100 96,000.00 960.00 Pekerja 1.0000 Org/hari 55,000.00 55,000.00 Mandor 0.0160 Org/hari 70,000.00 1,120.00 Tukang batu 1.5000 Org/hari 60,000.00 90,000.00 Kepala tukang batu 0.3000 Org/hari 65,000.00 19,500.00
323,540.00
HARGA JUMLAH NO URAIAN PEKERJAAN KOEFISIEN SATUAN SATUAN HARGA
(RP) (RP)2 1 Buah
Batu bata 200.0000 Bh 550.00 110,000.00 Semen 120.0000 Kg 1,160.00 139,200.00 Pasir pasang 0.3000 M³ 96,000.00 28,800.00 Keramik 20 x 20 cm 28.0000 Bh 2,250.00 63,000.00 Semen putih 6.0000 Kg 1,500.00 9,000.00 Pekerja 6.0000 OH 55,000.00 330,000.00 Mandor 0.3000 OH 70,000.00 21,000.00 Tukang batu 3.0000 OH 60,000.00 180,000.00 Kepala tukang bat 0.3000 OH 65,000.00 19,500.00
900,500.00 3 Memasang pipa PVC AW ½" 1 M¹
Pipa PVC AW ½" 1.2000 M¹ 3,500.00 4,200.00 Perlengkapan 1.0000 Ls 15,000.00 15,000.00 Pekerja 0.0360 OH 55,000.00 1,980.00 Mandor 0.0018 OH 70,000.00 126.00 Tukang batu 0.0600 OH 60,000.00 3,600.00 Kepala tukang batu 0.0060 OH 65,000.00 390.00
25,296.00 4 1 M¹
1.2000 M¹ 15,000.00 18,000.00 Perlengkapan 1.0000 Ls 15,000.00 15,000.00 Pekerja 0.0360 OH 55,000.00 1,980.00 Mandor 0.0018 OH 70,000.00 126.00 Tukang batu 0.0600 OH 60,000.00 3,600.00 Kepala tukang batu 0.0060 OH 65,000.00 390.00
39,096.00
M³
Membuat bak mandi batu bata 0,3 m³
Memasang pipa PVC Ø 2"Pipa PVC Ø 2"
HARGA JUMLAH NO URAIAN PEKERJAAN KOEFISIEN SATUAN SATUAN HARGA
(RP) (RP)5 1 M¹
1.2000 M¹ 20,000.00 24,000.00 Perlengkapan 1.0000 Ls 15,000.00 15,000.00 Pekerja 0.0360 OH 55,000.00 1,980.00 Mandor 0.0018 OH 70,000.00 126.00 Tukang batu 0.0600 OH 60,000.00 3,600.00 Kepala tukang batu 0.0060 OH 65,000.00 390.00
45,096.00 6 Memasang kran diameter ½" 1 Ttk
Kran 1.0000 Bh 12,500.00 12,500.00 Seal tape 0.0250 Set 1,000.00 25.00 Pekerja 0.0100 OH 55,000.00 550.00 Mandor 0.0050 OH 70,000.00 350.00 Tukang batu 0.0600 OH 60,000.00 3,600.00 Kepala tukang batu 0.0100 OH 65,000.00 650.00
17,675.00 7 Memasang floor drain 1 Buah
Floor drain 1.0000 Bh 20,000.00 20,000.00 Pekerja 0.0100 OH 55,000.00 550.00 Mandor 0.0050 OH 70,000.00 350.00 Tukang batu 0.1000 OH 60,000.00 6,000.00 Kepala tukang batu 0.0100 OH 65,000.00 650.00
27,550.00
Memasang pipa PVC Ø 4"Pipa PVC Ø 4"
HARGA SATUAN UPAH DAN BAHAN
KEGIATAN :
LOKASI : Jalan Jakarta
1. U P A H
NO JENIS U R A I A N SATUAN HARGA
(Rp.)
PEKERJAAN TANAH1 Tenaga Pekerja Biasa Orang 55,000.002 Tenaga Mandor Orang 70,000.00
PEKERJAAN BATU1 Tenaga Pekerja Biasa Orang 55,000.002 Tenaga Tukang Batu Orang 60,000.003 Tenaga Kepala Tukang Batu Orang 65,000.004 Tenaga Mandor Orang 70,000.005 Tenaga Tukang GRC Orang 60,000.00
PEKERJAAN KAYU1 Tenaga Pekerja Biasa Orang 55,000.002 Tenaga Tukang Kayu Orang 60,000.003 Tenaga Kepala Tukang Kayu Orang 65,000.004 Tenaga Mandor Orang 70,000.00
PEKERJAAN BESI1 Tenaga Pekerja Biasa Orang 55,000.002 Tenaga Tukang Besi Orang 60,000.003 Tenaga Kepala Tukang Besi Orang 65,000.004 Tenaga Mandor Orang 70,000.00
PEKERJAAN LAS1 Tenaga Pekerja Biasa Orang 55,000.002 Tenaga Tukang Las Orang 60,000.003 Tenaga Kepala Tukang Las Orang 65,000.004 Tenaga Mandor Orang 70,000.00
PEKERJAAN CAT1 Tenaga Pekerja Biasa Orang 55,000.002 Tenaga Tukang Cat Orang 60,000.003 Tenaga Kepala Tukang Cat Orang 65,000.004 Tenaga Mandor Orang 70,000.00
Pembangunan Rumah Tinggal Type 135m² / 300 m²
2. B A H A N
HARGA SATUANNO J E N I S B A H A N SATUAN BAHAN KETERANGAN
( Rp )
A. AGREGAT KASAR, BAHAN PEREKAT DAN BAHAN JADINYA
1 Tanah urug M³ Rp 50,000.00 Di Proyek2 Pasir urug M³ Rp 79,000.00 Di Proyek3 Pasir Beton M³ Rp 175,000.00 Di Proyek4 Pasir pasang M³ Rp 96,000.00 Di Proyek5 Batu kerikil / koral M³ Rp 225,000.00 Di Proyek6 Batu gunung M³ Rp 120,000.00 Di Proyek7 Bata merah bh Rp 550.00 Di Proyek8 Semen 50 kg/zak Zak Rp 58,000.00 Di Proyek9 Semen warna 50 kg/zak Zak Rp 75,000.00 Di Proyek
10 Semen Kiloan Kg Rp 1,160.00 Di Proyek11 Semen warna kiloan Kg Rp 1,500.00 Di Proyek
B. BAHAN KAYU BERIKUT BAHAN JADINYA1 Papan Bengkirai M³ Rp 3,000,000.00 Di Proyek2 Papan Meranti ( Begesting ) M³ Rp 1,600,000.00 Di Proyek3 Papan sejenis kayu Kapur M³ Rp 2,800,000.00 Di Proyek4 Papan Ulin 5/20 - 400 cm M³ Rp 2,500,000.00 Di Proyek5 Balok Meranti M³ Rp 2,000,000.00 Di Proyek6 Balok Bengkirai M³ Rp 2,700,000.00 Di Proyek7 Balok Ulin Kuzen M³ Rp 2,500,000.00 Di Proyek8 Balok Ulin Pancang M³ Rp 3,000,000.00 Di Proyek9 Balok sejenis kayu Kapur M³ Rp 2,500,000.00 Di Proyek
10 lbr Rp 48,000.00 Di Proyek11 List Plafond kayu M Rp 7,500.00 Di Proyek12 Gypsump Board 9 mm Knauf lbr Rp 65,000.00 Di Proyek14 List gypsump Cornise trap M Rp 55,000.00 Di Proyek
C BAHAN LOGAM DAN PAKU1 Paku segala ukuran kg Rp 17,000.00 Di Proyek2 Paku atap bh Rp 1,000.00 Di Proyek3 Paku seng kg Rp 20,000.00 Di Proyek4 Paku ulin kg Rp 18,000.00 Di Proyek5 Paku kecil plywood kg Rp 20,000.00 Di Proyek7 Sekrup fixer bh Rp 1,500.00 Di Proyek8 Kawat ikat kg Rp 17,000.00 Di Proyek
Plywood ukuran + 3,6 mm
HARGA SATUANNO J E N I S B A H A N SATUAN BAHAN KETERANGAN
( Rp )9 Kawat Las kg Rp 17,000.00 Di Proyek
10 Besi beton kg Rp 12,000.00 Di Proyek11 Paku rivet kg Rp 15,000.00 Di Proyek12 Besi Plat Strip kg Rp 18,000.00 Di Proyek
D BAHAN PENUTUP ATAP1 Penutup Atap Metal Lbr Rp 49,000.00 Di Proyek2 Bubungan Atap Metal Bh Rp 25,000.00 Di Proyek3 Seng Gelombang Lbr Rp 30,000.00 Dipasang
E BAHAN LANTAI DAN PELAPIS DINDING1 Keramik 40/40 ( Roman ) bh Rp 7,500.00 Dipasang2 Keramik 30/30 ( Roman ) bh Rp 5,000.00 Dipasang3 Keramik 25 x 25 cm bh Rp 2,250.00 Dipasang4 Keramik 20 x 20 cm bh Rp 2,250.00 Dipasang5 Keramik 10 x 10 cm list dinding bh Rp 1,250.00 Dipasang
F BAHAN ELEKTRIKAL1 Lampu Phillips 13 watt bh Rp 75,000.00 Dipasang2 Lampu Phillips 21 watt bh Rp 150,000.00 Dipasang3 Lampu Phillips 18 watt bh Rp 75,000.00 Dipasang4 Pasang Saklar tunggal bh Rp 15,000.00 Dipasang5 Pasang saklar doubel bh Rp 20,000.00 Dipasang6 Pasang saklar triple bh Rp 30,000.00 Dipasang7 Pasang Stop kontak bh Rp 15,000.00 Dipasang8 Pasang MCB Box Unit Rp 200,000.00 Dipasang9 Pasang Instalasi Listrik Titik Rp 81,900.00 Dipasang
HARGA SATUANNO J E N I S B A H A N SATUAN BAHAN KETERANGAN
( Rp )G BAHAN PINTU,JENDELA DAN BV1 Daun pintu panil ulin ( 72 x 230 ) bh Rp 600,000.00 Dipasang2 Daun jendela (132 x 82 ) bh Rp 500,000.00 Dipasang3 Daun bouvenlight bh Rp 100,000.00 Dipasang
H BAHAN PENGGANTUNG DAN KUNCI1 Engsel Pintu 4" bh Rp 30,000.00 Di Proyek2 Engsel Jendela 3 " bh Rp 20,000.00 Di Proyek3 Kunci Pintu KM/WC bh Rp 40,000.00 Di Proyek4 Grendel pintu KM/WC. bh Rp 8,000.00 Di Proyek5 Grendel Jendela bh Rp 7,000.00 Di Proyek6 Wind Hak bh Rp 20,000.00 Di Proyek7 Handel jendela bh Rp 6,000.00 Di Proyek8 Stop door bh Rp 20,000.00 Di Proyek9 Kaca bening tebal 5 mm M² Rp 80,000.00 Dipasang
I BAHAN SANITASI DAN PERPIPAAN1 Bak Mandi 100/75 tinggi 80 cm lapis keramik Unit Rp 500,000.00 Dipasang2 Kloset Jongkok setara Toto" Unit Rp 150,000.00 Di Proyek3 Floor drain bh Rp 20,000.00 Di Proyek4 Kran air Ø 1/2 inchi bh Rp 12,500.00 Di Proyek5 Gate valve Ø 3/4 inchi bh Rp 20,000.00 Di Proyek6 Gate valve Ø 1/2 inchi bh Rp 86,000.00 Di Proyek7 Shower Kran bh Rp 190,000.00 Di Proyek8 Pipa PVC Ø 1/2 " AW M Rp 3,500.00 Di Proyek
9 Pipa PVC diameter 2 M Rp 15,000.00 Di Proyek
10 Pipa PVC diameter 4 M Rp 20,000.00 Di Proyek11 Septictank dan peresapan Unit Rp 4,305,000.00 Dipasang12 Bak kontrol Unit Rp 200,000.00 Dipasang13 Perlengkapan Ls Rp 15,000.00 Dipasang
HARGA SATUANNO J E N I S B A H A N SATUAN BAHAN KETERANGAN
( Rp )J BAHAN FINISHING
1 Amplas lbr Rp 3,000.00 Di Proyek2 Plamur kg Rp 22,000.00 Di Proyek3 Dempul kayu kg Rp 15,000.00 Di Proyek4 Meni kayu Kg Rp 25,000.00 Di Proyek5 Cat Tembok Kg Rp 11,000.00 Di Proyek6 Dempul kayu Kg Rp 55,000.00 Di Proyek7 Cat kayu Kg Rp 36,500.00 Di Proyek8 Tinner A Kg Rp 19,000.00 Di Proyek9 Tinner B Kg Rp 7,000.00 Di Proyek
RENCANA ANGGARAN BIAYA[ ENGGINER ESTIMATE ]
KEGIATAN :LOKASI :
### ###### ###
NO. URAIAN PEKERJAAN SAT. VOLUMEPROSENTASE MINGGU LALU PROSENTASE MINGGU INI
Err:509B PEKERJAAN TANAH DAN PASIR1 Galian tanah pondasi M³ 0.882 0.371 2 Urugan tanah dalam bangunan + pemadatan M³ Err:509 Err:5093 Pemadatan tanah M³ 0.650 0.295 4 Urugan pasir bawah pondasi dan lantai M³ 0.044 0.012
12.075 D PEKERJAAN PASANGAN DAN PLESTERAN1 Pasang batu gunung 1 : 4 M³ 1.180 8.603 2 Pasang batu bata tebal ½ bata 1 : 2 M² Err:509 Err:5093 Pasang batu bata tebal ½ bata 1 : 4 M² 0.936 0.924 4 Plesteran 1 : 2 M² Err:509 Err:5095 Plesteran 1 : 4 M² 0.683 0.296 6 Pasang parit keliling M¹ Err:509 Err:5097 Benangan dinding M¹ Err:509 Err:5098 Benangan kolom M¹ Err:509 Err:5099 Pasangan batu alam dinding dan kolom M² 4.250 9.321 10 Tanam rumput + tanaman M² 8.882 12.987