ID Task Mode Task Name Duration Start Finish 1 Start Unit 4, 5 & 62 Assignment 2 66 days Tue 06/11/12 Tue 05/02/13 2 Task 1 8 days Tue 06/11/12 Thu 15/11/12 3 A - Gant Chart 4 days Tue 06/11/12 Fri 09/11/12 4 B - Schedule 2 days Mon 12/11/12 Tue 13/11/12 5 C - Risk Assessment 2 days Wed 14/11/12 Thu 15/11/12 6 Task 2 19 days Fri 16/11/12 Wed 12/12/12 7 A - Research 6 days Fri 16/11/12 Fri 23/11/12 8 B - Primary Content Research 6 days Mon 26/11/12 Mon 03/12/12 9 C - Planning 8 days Mon 03/12/12 Wed 12/12/12 10 Task 3 20 days Thu 13/12/12 Wed 09/01/13 11 A - Proposal 6 days Thu 13/12/12 Thu 20/12/12 12 B - Pitch 3 days Mon 07/01/13 Wed 09/01/13 13 Task 4 3 days Thu 10/01/13 Mon 14/01/13 14 A - Production Meeting 3 days Thu 10/01/13 Mon 14/01/13 15 Task 5 5 days Tue 15/01/13 Mon 21/01/13 16 A - Video Assets 5 days Tue 15/01/13 Mon 21/01/13 17 Task 6 7 days Tue 22/01/13 Wed 30/01/13 18 A - Shoot Video 7 days Tue 22/01/13 Wed 30/01/13 19 20 Additional Buffer Time 2 days Thu 31/01/13 Fri 01/02/13 M T W T F S S M T W T F S S M T W T F S S 05 Nov '12 12 Nov '12 19 Nov '12 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 1 Project: Project Plan Date: Wed 07/11/12
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
ID Task Mode
Task Name Duration Start Finish
1 Start Unit 4, 5 & 62 Assignment 2
66 days Tue 06/11/12 Tue 05/02/13
2 Task 1 8 days Tue 06/11/12 Thu 15/11/123 A - Gant Chart 4 days Tue 06/11/12 Fri 09/11/124 B - Schedule 2 days Mon 12/11/12Tue 13/11/125 C - Risk Assessment 2 days Wed
14/11/12Thu 15/11/12
6 Task 2 19 days Fri 16/11/12 Wed 12/12/127 A - Research 6 days Fri 16/11/12 Fri 23/11/128 B - Primary Content
Research6 days Mon
26/11/12Mon 03/12/12
9 C - Planning 8 days Mon 03/12/12Wed 12/12/1210 Task 3 20 days Thu 13/12/12 Wed 09/01/1311 A - Proposal 6 days Thu 13/12/12 Thu 20/12/1212 B - Pitch 3 days Mon 07/01/13Wed 09/01/1313 Task 4 3 days Thu 10/01/13 Mon 14/01/1314 A - Production
Meeting3 days Thu 10/01/13 Mon
14/01/1315 Task 5 5 days Tue 15/01/13 Mon 21/01/1316 A - Video Assets 5 days Tue 15/01/13 Mon 21/01/1317 Task 6 7 days Tue 22/01/13 Wed 30/01/1318 A - Shoot Video 7 days Tue 22/01/13 Wed 30/01/1319
20 Additional Buffer Time 2 days Thu 31/01/13 Fri 01/02/13
M T W T F S S M T W T F S S M T W T F S S M05 Nov '12 12 Nov '12 19 Nov '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1
Project: Project PlanDate: Wed 07/11/12
ID Task Mode
Task Name Duration Start Finish
21 End Unit 4, 5, & 62 Assignment 2
2 days Mon 04/02/13
Tue 05/02/13
22
23 Start Unit 4, 5, & 62 Assignment 3
66 days Mon 18/02/13
Mon 20/05/13
24 Task 1 2 days Mon 18/02/13Tue 19/02/1325 A - Import Video
with Diary2 days Mon
18/02/13Tue 19/02/13
26 Task 2 15 days Wed 20/02/13Tue 12/03/1327 A - Edit Video 15 days Wed 20/02/13Tue 12/03/1328 Task 3 11 days Wed 13/03/13Wed 27/03/1329 A - Export Video 2 days Wed 13/03/13Thu 14/03/1330 B - Gather Feedback 4 days Fri 15/03/13 Wed
20/03/1331 C - Create a Report 5 days Thu 21/03/13 Wed 27/03/1332 Task 4 7 days Thu 28/03/13 Fri 05/04/1333 A - Create a
Questionnaire4 days Thu 28/03/13 Tue 02/04/13
34 B - End of Project Meeting with Client
3 days Wed 03/04/13
Fri 05/04/13
35 Task 5 10 days Mon 08/04/13Fri 19/04/1336 Evaluation 10 days Mon 08/04/13Fri 19/04/1337
M T W T F S S M T W T F S S M T W T F S S M05 Nov '12 12 Nov '12 19 Nov '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 2
Project: Project PlanDate: Wed 07/11/12
ID Task Mode
Task Name Duration Start Finish
38 End Unit 4, 5, & 62 Assignment 3
2 days Mon 22/04/13
Tue 23/04/13M T W T F S S M T W T F S S M T W T F S S M05 Nov '12 12 Nov '12 19 Nov '12
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 3
Project: Project PlanDate: Wed 07/11/12
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 07 Jan '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 4
Project: Project PlanDate: Wed 07/11/12
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 07 Jan '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 5
Project: Project PlanDate: Wed 07/11/12
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 07 Jan '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 6
Project: Project PlanDate: Wed 07/11/12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 7
Project: Project PlanDate: Wed 07/11/12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 8
Project: Project PlanDate: Wed 07/11/12
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 9
Project: Project PlanDate: Wed 07/11/12
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W18 Feb '13 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 10
Project: Project PlanDate: Wed 07/11/12
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W18 Feb '13 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 11
Project: Project PlanDate: Wed 07/11/12
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W18 Feb '13 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 12
Project: Project PlanDate: Wed 07/11/12
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 13
Project: Project PlanDate: Wed 07/11/12
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 14
Project: Project PlanDate: Wed 07/11/12
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13