Page 1
CASE STUDY
GABCIKOVO-NAGYAMAROS PROJECT CASE (HUNGARY V.SLOVAKIA) 1993 Official citation- I.C.J. reports 1997,p.7
TABLE OF CONTENTS
Chapter No. Topics
Chapter-1 Background of the case .............................................
Chapter-2 Facts of the case.........................................................
Chapter-3 Issues raised by both the parties................................
Chapter-4 Judgement..................................................................
Chapter-5 Contribution...............................................................
Chapter-6 Abstract......................................................................
Page 2
Chapter-1
BACKGROUND OF THE CASE
The joint Hungarian-Czechoslovak project was agreed upon on 16 SEPTEMBER 1977 in
BUDAPEST TREATY concerning the construction and operation of the Gabcikovo-
Nagymaros ’System of Locks’ as a joint investment. It was a large barrage project on
Danube. The 1977 Treaty entered into force on 30 June 1978. According to its Preamble, the
system was designed to attain ‘the broad utilization of the natural resources of the Bratislava-
Budapest section of the Danube River for the development of water resources energy,
transport, agriculture and other sectors of the national economy of the Contracting Parties’.
The joint investment was thus essentially aimed at the production of hydroelectricity, the
improvement of navigation on the relevant section of the Danube and the protection of the
areas along the banks against flooding. At the same time, by the terms of the Treaty, the
contracting parties undertook to ensure that the quality of water in the Danube was not
impaired as a result of the Project, and that compliance with the obligations for the protection
of nature arising in connection with the construction and operation of the System of Locks
would be observed.
The 1977 Treaty describes the principal works to be constructed in pursuance of the Project.
It provided for the building of two series of locks, one at Gabcikovo (in Czechoslovak
territory) and the other at Nagymaros (in Hungarian territory), to constitute ‘a single arid
indivisible operational system of works’ to prevent floods, improve river navigability and
hydro-electricity production. The Treaty further provided that the technical specifications
concerning the system would be included in the ‘Joint Contractual Plan’ which was to be
drawn up in accordance with the Agreement signed by the two Governments for this purpose
on 6 May 1976. It also provided for the construction, financing and management of the works
on a joint basis in which the Parties participated in equal measure.
This case raise some significant questions for the first time that the parties to the dispute
raised a plea for orders of specific performance before the Court and this was the first ever
dispute in which the Court was directly asked to consider the consequences of the legal
developments in the field of environmental protection. Even though the relationship between
Page 3
the law of treaties and the law of State responsibility had generated much general concern,
the Court in the past, had not been presented with an occasion to pronounce on these issues.
Page 4
Chapter-2
FACTS OF THE CASE
This gabcikovo-nagyamaros project intiated by the Budapest treaty of 1977 between the
Hungarian people’s republic and czechoslavik socialist republic for the construction on
Danube river. The four main purpose of this project are electricity production, navigation,
flood protection and regional development. The project was to consist of a bypass canal on
the Slovak territory which was designed to produce peak flow electricity, and the downstream
step on the Hungarian territory which was designed to produce a constant flow of electricity.
In order to provide for the adverse impact that a project of this scale was likely to have on the
environment, the 1977 Treaty contained provisions specifically to limit the extent of the
possible adverse environmental impact. The Treaty had categorically provided that the
construction of the project should not in any way impair the quality of water in the Danube,
preservation of the natural environment was to be ensured and the fishing interests were to be
secured. The detailed implementation of the project was to be carried out in accordance with
a series of interrelated agreements, out of which the most crucial was the joint contractual
plan. The said plan contained provisions with regard to the technical details of the project as
also the financial responsibility for its construction. In fact, after the emergence of the
dispute, both the disputing parties commissioned various studies as to the scientific impact of
the project, however, it became abundantly clear from the pleadings of both the contesting
States that no serious environmental impact assessment had been carried out before the
conclusion of the Treaty.
The part of project which had generated in Hungary, the Hungarian Government suspended
the works in 1989 alleging grave risk to Hungarian’s environment and Budapest water
supply. The Slovak Republic/Slovakia, which succeeded Czechoslovakia as a party to the
Project, denied these allegations and undertook an alternate project wholly on Slovak
territory. Czechoslovakia decided to continue with the implementation of the project in a
limited form on its territory (which was referred to as the so-called “Variant C”). This
arrangement involved a unilateral diversion of the waters of the Danube and was forcefully
opposed by Hungary. Hungary finally terminated the 1977 treaty with effect from 25 May,
1992. Czechoslovakia proceeded with Variant C and dammed the Danube on 23 October,
Page 5
1992. On 1 January 1993 Slovakia became an independent state. A series of negotiations
were carried under the aegis of the European Communities and in April 1994 the “Special
Agreement for Submission to the International Court of Justice of the Differences between
the Republic of Hungary and the Slovak Republic Concerning the Gabcikovo-Nagymaros
Project”. Under Article 2 of the special agreement, the Court was requested to decide the
dispute on the basis of the 1977 Treaty and the rules and principles of general international
law, as well as such other treaties as the Court might find applicable.
This unilateral operation, has allegedly had, and will continue to have, significant detrimental
effects on Hungary’s environment and access to the water of the River Danube. Despite
efforts at mediation by Commission of the European Committees, Hungary and Slovakia
were unable to resolve their differences, and in 1993 the dispute that referred to the
International Court of Justice for adjudication. At this point of time, it would also be
interesting to note that this case was noted internationally as the first environmental case to
be decided by the ICJ.
Page 6
Chapter-3
ISSUES RAISED BY BOTH THE PARTIES
ISSUES PRESENTED
(1) Whether the environmental concerns expressed by Hungary created a ‘state of
necessity’ under customary international law;
(2) Whether Slovakia was legally entitled to unilaterally plan and operate an alternative
project; and;
(3) Whether Hungary’s notification of the termination of the treaty of 1977 was legal.
HUNGARIAN ARGUMENTS
The Danube River is capable of supplying approximately 60% of Hungary’s drinking
water. Water from the Danube River is of particularly high quality because of a bank-
filtering process in which water seeps from the Danube through a naturally filtering bio-
active pebble bed into an area aquifer hundreds of meters deep. The reservoir will
substantially reduce the rate of water flow, causing sediment to accumulate along both the
floor of the reservoir and river. Toxins such as iron, manganese, and other industrial
pollutants that would normally be transported downstream will settle along the floor of
the reservoir. The sediment will also provide a breeding ground for harmful bacteria.
Both the toxins and the bacteria will infiltrate the aquifer and enter drinking water
supplies, polluting the ground water reserves within ten years.
As the sediment accumulates, it will have to be dredged. Dredging of the reservoir and
riverbed will reintroduce the harmful pollutants into the surface water, while also
destroying the bioactive pebble bed responsible for the natural filtration of the river water.
Destruction of the pebble bed will permit additional organic micro pollutants and
microbes to enter and contaminate the aquifer. Leaching of hydrocarbon compounds from
the asphalt layer lining the power canal will further pollute the river water. The diversion
of the river channel will disconnect the main river from a complex system of tributaries
Page 7
that play an essential role in the self-purification of the Danube River. The water table
upstream of the Dunakiliti Dam will rise, causing soil saturation and reducing the
productivity of farm land.
Below the dam, the water table will lower, reducing crop production and increasing
drought susceptibility. The corresponding fluctuation in the water table will affect the
forest habitat of the region and potentially result in the destruction of 50,000 acres of
floodplain. The loweringof the aquifer will also jeopardize the freshwater supply of local
inhabitants. The complex ecological nature of the river basin in the area of the G-N
Project means that the basin serves as a fertile ground for the development of an
extremely diverse collection of flora and fauna.The complex ecological nature of the area
also renders the flora and fauna highly susceptible to changes in the environment.
Extensive ecological disruption caused by diverting the river from its natural channel for
25 kilometers will likely destroy an estimated 80-90% of the 5000 animal species that
inhabit the area. The fish population alone is likely to fall by 25%. Commercial fish
yields will likely fall by a staggering 90%.
Although this Project was intended to increase the flood control level of the region, there
is concern that the quality of the reservoir embankments and the walls of the canal do not
meet international standards of structural stability. Concern also exists that the Project
lacks measures to prevent accidental flooding or to protect the surrounding area from
floodwaters. This Project facilities are constructed ‘in the area of a geologically young
fault.’ Geological and seismological characteristics of the region were little understood at
the time the Project was conceived. In fact, at the time of conception, no geological or
geophysical evaluations of the impact of the G-N Project had been conducted. The
complicated nature of the region has, however, become apparent during the course of
preliminary construction. Without further studies to determine the necessary
modifications to this Project, the parties would be risking ‘human and economic disaster’
with financial losses running ‘ten times the cost of the whole investment.’ The economic
costs of maintaining and operating this Project, coupled with the costs of measures to
moderate environmental damage and the value of lost agricultural production will dwarf
the value of energy produced over the life of the Project.
Diversion of the Danube into the power canal will physically isolate the villages of
Dobrohost, Vojca, and Bodiky from the rest of Slovakia. The physical separation, coupled
Page 8
with the environmental devastation and the reduced agricultural production will cause a
rural exodus from these villages. The diversion into the power canal will also deprive
Hungary of access to the economic resources of 25 kilometers of the Danube River. This
access was one of the primary rationales for locating the international border along the
median of the Danube river.
SLOVAKIA ARGUMENTS
Slovakia asserts that Hungary has grossly exaggerated the environmental dangers of the
G-N Project. It contends that it is not only possible to mitigate much of the Project’s
feared environmental damage, but the Project will have significant environmental
benefits. Slovakiaasserts, for example, that the Dunakiliti reservoir will actually improve
water quality by slowing erosion and slowing the rate of the Danube, thereby permitting
larger quantities of water to pass through the bio-active pebble layer and dilute the
currently polluted aquifer.
According to Slovakia, the Hungarian projections of reduced water quality due to the
decrease in oxygen content of the river, the increasing silt of the reservoir, and the
infiltration of toxins are based on scant scientific research and are contrary to reports from
international experts. Slovakia also notes that the current water table in the Danube
Region may fluctuate by as much as seven meters, creating less than ideal conditions for
agricultural production.
The G-N Project will reduce the fluctuations in the aquifer level, raise the water table
where crops have been susceptible to drought, and lower the water table where crops have
been damaged by inundation. The harm caused by the change of the hydraulic regime will
most likely alter the wildlife habitat in the meadow-forests and fish habitat. Slovakia
argues that the impact on the meadow forest can be mitigated by timing discharge of
water from the Dunakiliti reservoir and the construction of ‘low stony barrages’ in the old
river bed. In fact, the Project will bring water to regions of the Danube meadow-forests in
Hungary that are currently drought-ridden throughout much of the year. The G-N Project
is also the most economically efficient means of controlling floods in this region of
theDanube. Further, Slovakia asserts that a number of comprehensive studies attest to the
geological stability ofthe region and the structural integrity of the Project facilities.
Page 9
Chapter-4
JUDGEMENT
With respect to the first issue, the Court held that for the ‘state of necessity’ exception to
apply with respect to the Gabcikovo-Nagymaros project, the following factors would
have to be established by Hungary:
The environmental concerns constituted an ‘essential interest’ of Hungary.
Hungary’s environmental concerns were threatened by ‘grave and imminent peril’.
Suspension and abandonment of construction works was the only way Hungary could
have safeguarded its environmental concerns.
Hungary’s suspension and abandonment of construction works did not impair
the‘essential interests’ of Slovakia.
Hungary’s obligation under the 1977 treaty did not arise out a peremptory norm of
general international law.
The 1977 treaty did not, either explicitly or implicitly, exclude the possibility of
invoking the ‘state of necessity’ exception with respect to Hungary’s obligations
under it
Hungary not contributed to the occurrence of the ‘state of necessity’
However, the fifteen judge bench standard found it difficult to conclude that Hungary’s
environment was in fact threatened by ‘grave and imminent peril’; and held that a mere
apprehension of a possible peril is not sufficient to meet this, as it must simultaneously be
‘grave’ and ‘imminent’. The court also noted that the dangers Hungary outlined were mostly
of a long term nature and uncertain. Moreover, suspension and abandonment were not found
to be the only means available to Hungary to safeguard its environmental concerns. Thus, the
‘state of necessity exception was found to be inapplicable in the instant matter.
With respect to the second issue, the court held that while Slovakia was entitled to
unilaterally plan and construct its alternative solution to the project, it did not have the right
to put that alternative solution into operation, because it violated the express purpose of the
Page 10
1977 treaty, as well as Hungary’s territorial integrity and sovereign independence. Moreover,
Slovakia’s operation of the alternative solution did not constitute a lawful countermeasure
under international law, because the deprivation of Hungary’s right to an equitable share of
the use of the Danube River was in excess of the injury suffered by Slovakia.In light of the
arguments put forth by Hungary vis-à-vis the existence of state necessity,impossibility of
performance of the 1977 treaty, the occurrence of fundamental change of circumstances,
material breach of the 1977 treaty by Slovakia; the ICJ found that Hungary’s notification of
termination of the 1977 treaty was at best premature, and did not have the effect of
terminating the 1977 treaty under International law.
LEGAL CONSEQUENCES OF JUDGMENT
It is of cardinal importance that the Court has found that the 1977 Treaty is still in force
and consequently governs the relationship between the Parties. That relationship is also
determined by the piles of other relevant conventions to which the two States are party,
by the rules of general international law and, in this particular case, by the rules of State
responsibility; but it is governed, above all, by the applicable rules of the 1977 Treaty as a
lex specialis. The Court observes that it cannot, however, disregard the fact that the
Treaty has not been fully implemented by either party for years, and indeed that their acts
of commission and omission have contributed to creating the factual situation that now
exists. Nor can it overlook that factual situation - or fine practical possibilities and
impossibilities to which it gives rise - when deciding on the legal requirements for the
future conduct of the Parties.
What is essential, therefore, is that the factual situation as it has developed since 1989
shall be placed within the context of the preserved and developing treaty relationship, in
order to achieve its object and purpose insofar as that is feasible. For it is only then that
the irregular state of affairs which exists as the result of the failure of both Parties to
comply with their treaty obligations can be remedied. The Court pointed out that the 1977
Treaty is not only a joint investment project for the production of energy, but it was
designed to serve other objectives as well: the improvement of the navigability of the
Danube, flood control and regulation of ice-discharge, and the protection of the natural
environment. In order to achieve these objectives the parties accepted obligations of
conduct, obligations of performance, and obligations of result.
Page 11
It is clear that the Project's impact upon, and its implications for, the environment are of
necessity a key issue. In order to evaluate the environmental risks, current standards must
be taken into consideration. This is not only allowed by the wording of Articles 15 and
19, but even prescribed, to the extent that these articles impose a continuing - and thus
necessarily evolving – obligation on the parties to maintain the quality of the water of the
Danube and to protect nature. The Court is mindful that, in the field of environmental
protection, vigilance and prevention are required on account of the often irreversible
character of damage to the environment and of the limitations inherent in the very
mechanism of reparation of this type of damage. New norms and standards have been
developed, set forth in a great number of instruments during the last two decades. Such
new norms have to be taken into consideration,and such new standards given proper
weight, not only when States contemplate new activities but also when continuing with
activities begun in the past. For the purposes of the presentcase, this means that the
Parties together should look afresh at the effects on the environment of the operation of
the Gabcikovo power plant. In particular they must find a satisfactory solution for the
volume of water to be released into the old bed of the Danube and into the side-arms on
both sides of the river.
In the Judgment, the Court concluded that both Parties committed internationally
wrongful acts, and it has noted that those acts gave rise to the damage sustained by the
Parties; consequently, Hungary and Slovakia are both under an obligation to pay
compensation and are both entitled to obtain compensation. The Court observed,
however, that given the fact, that there have been intersecting wrongs by both Parties, the
issue of compensation could satisfactorily be resolved in the framework of an overall
settlement if each of the Parties were to renounce or cancel all financial claims and
counterclaims. At the same time, the Court wishes to point out that the settlement of
accounts for the construction of the works is different from the issue of compensation,
and must be resolved in accordance with the 1977 Treaty and related instruments. If
Hungary is to share in the operation and benefits of the Cunovo complex, it must pay a
proportionate share of the building and running costs.
Page 12
Chapter-5
CONTRIBUTION
Gabcikovo-Nagymaros project prompted the constitution of a Special Environmental
Chamber of the ICJ. It also clarified the Court’s jurisprudence with respect to the state and
non-state components of environmental protection in as much the Court held that these were
grounded in general international law. The Court confirmed customary nature of at least part
of International Environmental Law, although without referring to any specific norm. The
following paragraph of the Court’s judgment confirms this contention:
The Court has no difficulty in acknowledging that the concerns expressed by Hungary for
its natural environment in the region affected by the Gabcikovo- Nagymaros project
related to an ‘essential interest’ of that State, within the meaning given to that expression
in Article 33 of the Draft of the International Law Commission.
Neither of the Parties contended that new peremptory norms of environmental law had
emerged since the conclusion of the 1977 Treaty, and the Court will consequently not be
required to examine the scope of Article 64 of the Vienna Convention on the Law of
Treaties. On the other hand, the Court wishes to point out that newly developed norms of
environmental law are relevant for the implementation of the Treaty and that the parties
could, by agreement, incorporate them through the application of Articles 15, 19 and 20
of the Treaty. These articles do not contain specific obligations of performance but
require the parties, in carrying out their obligations to ensure that the quality of water in
the Danube is not impaired and that nature is protected, to take new environmental norms
into consideration when agreeing upon the means to be specified in the Joint Contractual
Plan.
Thus, confirmation of the customary nature of at least part of International Environmental
Law was given in three ways. Firstly, it was acknowledged that environmental interests
may amount to “essential interests” in the meaning of the customary rule providing for
the state of necessity defense. While an interest is conceptually different from a norm, the
existence of a legally protected interest assumes that such interest has legal relevance
Page 13
irrespective (in this case) of any treaty. Secondly, the Court talked of newly developed
norms of environmental law relevant for the implementation of the Treaty. This seems a
clear reference to norms belonging to international customary law. Thirdly, in order to
support its conclusion that environmental interests can in fact amount to “essential
interests”, the Court expressly referred to paragraph 29 of its Advisory Opinion on the
Legality of Nuclear Weapons, thus suggesting that the general obligation mentioned in
paragraph 29 had the same basis as the essential character of environmental protection.
Therefore it can possibly be inferred from these observations that a new dimension was
added to the Court’s jurisprudence vis-a-vis International Environmental Law.
Further, the case concerning Gabcikovo- Nagymaros project is an apt example of how the
International Court of Justice, tries to achieve a result that is acceptable to both litigants
and that, consequently, stands the best chance of being complied with by the two
sovereign litigants. The case highlighted the unique role that the ICJ may play when two
interdependent states have reached a deadlock after lengthy negotiations. Through their
special agreement, Hungary and Slovakia asked the Court to define and resolve the legal
aspects of their dispute. But the special agreement also provided that the parties shall
“immediately after the transmission of the Judgment enter into negotiations on the
modalities for its execution” and that, “if they were unable to reach agreement within six
months, either Party may request the Court to render an additional Judgment to determine
the modalities for executing its Judgment.” In this way, both parties were actively using
the principal judicial organ of the United Nations to assist them in defining the
fundamental legal parameters of a process of on-going negotiations that was directed
towards achieving a political result that was mutually acceptable.
Gabcikovo- Nagymaros Project prompted the constitution of a Special Environmental
Chamber of the ICJ. It also clarified the Court’s jurisprudence with respect to the state
and non-state components of environmental protection in as much the Court held that
these were grounded in general international law. The Court confirmed customary nature
of at least part of International Environmental Law, although without referring to any
specific norm. The following paragraph of the Court’s judgment confirms this contention:
The Court has no difficulty in acknowledging that the concerns expressed by Hungary for
its natural environment in the region affected by the Gabcikovo- Nagymaros Project
Page 14
related to an ‘essential interest’ of that State, within the meaning given to that expression
in Article 33 of the Draft of the International Law Commission.
Neither of the Parties contended that new peremptory norms of environmental law had
emerged since the conclusion of the 1977 Treaty, and the Court will consequently not be
required to examine the scope of Article 64 of the Vienna Convention on the Law of
Treaties. On the other hand, the Court wishes to point out that newly developed norms of
environmental law are relevant for the implementation of the Treaty and that the parties
could, by agreement, incorporate them through the application of Articles 15, 19 and 20
of the Treaty. These articles do not contain specific obligations of performance but
require the parties, in carrying out their obligations to ensure that the quality of water in
the Danube is not impaired and that nature is protected, to take new environmental norms
into consideration when agreeing upon the means to be specified in the Joint Contractual
Plan.
Thus, confirmation of the customary nature of at least part of International Environmental
Law was given in three ways. Firstly, it was acknowledged that environmental interests
may amount to “essential interests” in the meaning of the customary rule providing for
the state of necessity defense. While an interest is conceptually different from a norm, the
existence of a legally protected interest assumes that such interest has legal relevance
irrespective (in this case) of any treaty. Secondly, the Court talked of newly developed
norms of environmental law relevant for the implementation of the Treaty. This seems a
clear reference to norms belonging to international customary law. Thirdly, in order to
support its conclusion that environmental interests can in fact amount to “essential
interests”, the Court expressly referred to paragraph 29 of its Advisory Opinion on the
Legality of Nuclear Weapons, thus suggesting that the general obligation mentioned in
paragraph 29 had the same basis as the essential character of environmental protection.
Therefore it can possibly be inferred from these observations that a new dimension was
added to the Court’s jurisprudence vis-a-vis International Environmental Law.
Further, the case concerning Gabcikovo- Nagymaros Project is an apt example of how the
International Court of Justice, tries to achieve a result that is acceptable to both litigants
and that, consequently, stands the best chance of being complied with by the two
sovereign litigants. The case highlighted the unique role that the ICJ may play when two
interdependent states have reached a deadlock after lengthy negotiations. Through their
Page 15
special agreement, Hungary and Slovakia asked the Court to define and resolve the legal
aspects of their dispute. But the special agreement also provided that the parties shall
“immediately after the transmission of the Judgment enter into negotiations on the
modalities for its execution” and that, “if they were unable to reach agreement within six
months, either Party may request the Court to render an additional Judgment to determine
the modalities for executing its Judgment.” In this way, both parties were actively using
the principal judicial organ of the United Nations to assist them in defining the
fundamental legal parameters of a process of on-going negotiations that was directed
towards achieving a political result that was mutually acceptable.
Page 16
Chapter-6
ABSTRACT
In the case of gabcikovo-nagyamaros, hungary and Czechoslovakia entered into Budapest
treaty on 16 september 1977 by which there would be created on Danube between two
states a barrage system, a dam, a reservoir, hydro-electric power stations and a 25-
kilometre canal for diverting the Danube from its original course through a system of
locks. A dispute developed in the light of hungary’s growing environment environment
concerns and result of this hungary suspended the work on project in 1989 while
Czechoslovakia proceeded with a ‘provisional solutions’ as from 1991 which involved
damming the Danube at a point on Czechoslovakian territory. In 1992, hungary
announced the termination of treaty of 1997 and related instruments. The case came
before international court ultimately by way of special agreement in 1993 between
hungary and Slovakia. This case essentially revolved around the relationship between the
treaty and subsequent environmental concerns.
The court emphasized that newly developed norms of environmental law were relevant
for the implementation of the treaty , while the awareness of vulnerability of the
environment and the recognition that environment risks have to be assessed on the
continuous basis have become much stronger in the years since the treaty’s conclusions.
However, the court found that the treaty was still in force and hungary was not entitled to
terminate it.
Therefore, it can be concluded in the Gabcikovo- Nagymaros Project case the Court
upheld the parties to a bargain which both regarded as at an end, and no longer wanted
applied in its original terms. Principle would suggest that a contract repudiated by both
parties was a dead letter, and the Court should have been concerned only with delineating
the legal consequences of its termination. The decision can only be defended as a
pragmatic one. The Court seems to have been influenced by the serious financial and
political implications of a finding that the contractual regime had been frustrated.
Slovakia had already expended huge sums of money on the project and did not want it
abandoned. On the other hand, completion of the project in its original form was
Page 17
absolutely unacceptable to Hungary and also posed serious environmental threats. Yet by
asking the parties to negotiate a solution, possibly with the help of a third party, it was
arguable that the Court was abdicating the very responsibility that the parties had
assigned to it. However, it seems that the Court applied the Rule of pacta sunt servanda,
as reflected in Article 26 of the Vienna Convention of 1969 in letter and spirit.