Top Banner
Alcatel-Lucent GSM 9120 BSC Commissioning Manual BSC & TC Document Commissioning Manual Release B10 3BK 17430 3001 RJZZA Ed.03
54

G2 BSC comm

Jan 04, 2016

Download

Documents

M A Ebeid

telecommunication
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: G2 BSC comm

Alcatel-Lucent GSM

9120 BSC Commissioning Manual

BSC & TC Document

Commissioning Manual

Release B10

3BK 17430 3001 RJZZA Ed.03

Page 2: G2 BSC comm

Status RELEASED

Short title Com

All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel-Lucent.

BLANK PAGE BREAK

2 / 54 3BK 17430 3001 RJZZA Ed.03

Page 3: G2 BSC comm

Contents

Contents

Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

1.1.1 Hardware Description - Racks Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.2 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.1.3 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.1.4 Initial State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151.1.5 Final State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.1.6 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.1.7 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 181.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 181.2.2 Site-Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 191.4 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20

1.4.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 201.4.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 201.4.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

2 Commissioning Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.1 Before Going On Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242.2 Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

2.3 Check Hardware . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 262.4 Check Power Supply and Power Up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

2.4.1 Check the Fuse Ratings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272.4.2 Discharge Capacitors in Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272.4.3 Check Polarity of Power Supply Line, Branch A . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272.4.4 Check Polarity of Power Supply Line, Branch B . . . . . . . . . . . . . . . . . . . . . . . . . . . . 282.4.5 Power Up BSC Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28

2.5 Install BSC Terminal and X.25 Board . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.5.1 Install X.25 Communication Board and BSC Terminal Software . . . . . . . . . . . . . 292.5.2 Install the Craft Terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292.5.3 Install the BSS Software . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

2.6 Commissioning Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.6.1 Relocate System-CPRCs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.6.2 Load and Activate BSC Software . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312.6.3 Check Battery Backup of S-CPRC Boards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 412.6.4 Correct BSC Date and Time . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 422.6.5 Test External Alarms (O1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42

2.7 BSC Hardware Test (C1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 432.7.1 Reboot BSC in Off-Line Test Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 432.7.2 Network Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 442.7.3 Broadcast Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 442.7.4 Clock Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 452.7.5 Reboot BSC in OPERATIONAL Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45

2.8 Check BSC-TC Link (O2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 462.8.1 Remove Ater Mux Loops . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 462.8.2 Check Alarms on the ASMB Boards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 462.8.3 Check Status of A Trunk SBLs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47

2.9 Set and Check BSC - 9153 OMC-R Link . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 482.9.1 Connect Modem to CPRC Board . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 482.9.2 Test the Communication Link . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48

3BK 17430 3001 RJZZA Ed.03 3 / 54

Page 4: G2 BSC comm

Contents

2.10 Before You Leave . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 482.11 Supplemental Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49

2.11.1 Connect Inter-Rack Cables (Example) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 492.11.2 Disable / Enable Alarm Reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51

2.12 Workaround: Exit / Connect WinBSC Terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52

Appendix A : Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53

4 / 54 3BK 17430 3001 RJZZA Ed.03

Page 5: G2 BSC comm

Preface

Preface

Purpose This document describes the commissioning procedure for the 9120 BSC,release B10, of the Alcatel-Lucent BSS.

What’s New In Edition 03Update for new equipment naming.

In Edition 02Update of system title.

In Edition 01First official delivery of the document for B10 release.

Audience This document is intended for:

Site administrators

Project managers

Field service technician

Supervisors

Occasional users (e.g. subcontractors).

Assumed Knowledge You must have a basic understanding of the following:

Alcatel-Lucent Operations & Maintenance concepts for the Base StationSubsystem

Commissioning tools

Personal Computers using the Windows 2000/XP environment.

3BK 17430 3001 RJZZA Ed.03 5 / 54

Page 6: G2 BSC comm

Preface

6 / 54 3BK 17430 3001 RJZZA Ed.03

Page 7: G2 BSC comm

1 Overview

1 Overview

This Overview gives information needed by projet managers and foremen, forpresentation to the customer and for site planning.

3BK 17430 3001 RJZZA Ed.03 7 / 54

Page 8: G2 BSC comm

1 Overview

1.1 Presentation

1.1.1 Hardware Description - Racks Configuration

The layout of the equipment fitted in each rack for each BSC configuration isgiven in the sections below. Figures are provided to assist the visual checkprocedure.

The key used in the figures is as follows:

CE number at a CPRC unit. = Network address

AB = OSI- CPRC

AC= SYS- CPRC

AA= BC- CPRC

- number at a DTCC unit = Network address

- number at a TCUC unit = Network address

NE number at an QA unit = Qmux address

SWCH number at a AS unit AS = Access Switch Number

number at a GS unit GS1/n = Group Switch Stage 1/Plane +SwitchElement Number

GS2/n = Group Switch Stage 2/Plane +SwitchElement Number

number at a BCLA unit SYS = System Variant

M = Master

RACK = Rack Variant

S = Slave

8 / 54 3BK 17430 3001 RJZZA Ed.03

Page 9: G2 BSC comm

1 Overview

1.1.1.1 Rack Layout: Rack 1, Configuration 1

01

SWCH

0

DC

03

SWCH

1

DC

05

SWCH

2

07

SWCH

3

09

SWCH

4

11

SWCH

5

13

SWCH

6

15

SWCH

7

17

DC

19

DC

21

SWCH

0

23

SWCH

1

25

SWCH

2

27

SWCH

3

29

SWCH

4

31

SWCH

5

33

SWCH

6

35

SWCH

7

37

DC

39

DC

41

SWCH

0

43

SWCH

1

45

SWCH

2

47

SWCH

3

49

SWCH

4

51

SWCH

5

53

SWCH

6

55

SWCH

7

57

DC

59

DC

61 63

CB A01 . . . . . . . . . . . CB A09 CB B71 . . . . . . . . . . . . . CB B78top rack unit for the fuses SAU01

SAU02

SAU03

SAU04

SAU05

FuseA01

FuseB72

FuseB71

GS2/1 . . . . . . . . . . . GS2/1 GS2/2 . . . . . . . . . . . GS2/2 GS2/3 . . . . . . . . . . GS2/3

air baffle

FuseA02

A TERTO

N+1

01

DC

03

DC

05 07 09

SWCH

11

SWCH

13

DTCC

15

DTCC

17

DTCC

19

DTCC

21

ASMB

23

DTCC

25

DTCC

27

DTCC

29

DTCC

31

ASMB

33

DC

35

DC

37 39 41

SWCH

43

SWCH

45

DTCC

47

DTCC

49

DTCC

51

DTCC

53

ASMB

55

DTCC

57

DTCC

59

DTCC

61

DTCC

63

ASMB SAU

06

SAU07

SAU08

FuseA08

FuseB76

FuseB75

GS1/0 . . . . . . . . . . . GS1/0

FuseA05

A TERTO

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

5

SWCH

6

SWCH

7

DC

DC

DC

DC

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

DC

DC

BCLA

M

BCLA

S

FuseA07

FuseA06

B GSA TO

A TERTO

ABIS TO BSCY05

RACKN+1

GS2/0 . . . . . . . . . . . GS2/0

DC

DC

TSCA

CPRC

CPRC

CPRC

CPRC

CPRC

SWCH

SWCH

DC

DC

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

7

DC

B GSA TOSYSB00

CPRC

SWCH

5

SWCH

6SYSA TO

DC

FuseB77

FuseB78

FuseA09

B GSATO B GSATO B GSATO

AS

2

AS

6

020

021

022

023

QA

4

024

025

026

027

QA

5

AS

3

AS

7

030

031

032

033

QA

6

034

035

036

037

QA

7

QA

2

010

011

012

013

014

015

016

017

AS1

AS

5

000

001

002

003

004

005

AS1

AS

5

BCLA

M

BCLA

SSYS

3BK 17430 3001 RJZZA Ed.03 9 / 54

Page 10: G2 BSC comm

1 Overview

1.1.1.2 Rack Layout: Rack 1, Configurations 2, 3, 4, 5, 6

01

SWCH

0

DC

03

SWCH

1

DC

05

SWCH

2

07

SWCH

3

09

SWCH

4

11

SWCH

5

13

SWCH

6

15

SWCH

7

17

DC

19

DC

21

SWCH

0

23

SWCH

1

25

SWCH

2

27

SWCH

3

29

SWCH

4

31

SWCH

5

33

SWCH

6

35

SWCH

7

37

DC

39

DC

41

SWCH

0

43

SWCH

1

45

SWCH

2

47

SWCH

3

49

SWCH

4

51

SWCH

5

53

SWCH

6

55

SWCH

7

57

DC

59

DC

61 63

CB A01 . . . . . . . . . . . CB A09 CB B71 . . . . . . . . . . . . . CB B78top rack unit for the fuses SAU01

SAU02

SAU03

SAU04

SAU05

FuseA01

FuseB72

FuseB71

GS2/1 . . . . . . . . . . . GS2/1 GS2/2 . . . . . . . . . . . GS2/2 GS2/3 . . . . . . . . . . . GS2/3

air baffle

FuseA02

A TERTO

N+1

01

DC

03

DC

05

SWCH

07

SWCH

09

SWCH

11

SWCH

13

DTCC

15

DTCC

17

DTCC

19

DTCC

21

ASMB

23

DTCC

25

DTCC

27

DTCC

29

DTCC

31

ASMB

33

DC

35

DC

37

SWCH

39

SWCH

41

SWCH

43

SWCH

45

DTCC

47

DTCC

49

DTCC

51

DTCC

53

ASMB

55

DTCC

57

DTCC

59

DTCC

61

DTCC

63

ASMB SAU

06

SAU07

SAU08

FuseA08

FuseB76

FuseB75

GS1/0 . . . . . . . . . . . GS1/0

GS1/1 GS1/1

FuseA05

A TERTO

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

5

SWCH

6

SWCH

7

DC

DC

DC

DC

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

DC

DC

BCLA

M

BCLA

S

FuseA07

FuseA06

B GSA TO

A TERTO

ABIS TO BSCY05

RACKN+1

GS2/0 . . . . . . . . . . . GS2/0

DC

DC

TSCA

CPRC

CPRC

CPRC

CPRC

CPRC

SWCH

SWCH

DC

DC

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

7

DC

B GSA TOSYSB00

CPRC

SWCH

5

SWCH

6SYSA TO

DC

FuseB77

FuseB78

FuseA09

B GSATO B GSATO B GSATO

SWCH

SWCH

SWCH

SWCH

DTCC

DTCC

DTCC

DTCC

ASMB

DTCC

DTCC

DTCC

ASMB

DC

DC

SWCH

SWCH

SWCH

SWCH

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

BIUA

GBISTO

DC

DC

DC

GS1/1

4 5 AS

10

AS

14

120

121

122

123

QA

12

124

125

126

127

QA

13FuseB73

DTCC

TCUC

TCUC

QA

14

GS1/1

6 7 AS

11

AS

15

130

131

132

133

134

135

136

137

FuseA03

A BISTO

N+1

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

DC

DC

QA

8

100

101

102

103

104

105

106

107

AS

8

AS

12

SWCH

FuseA04

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

DC

QA

10

110

111

112

113

114

115

116

117

AS

9

AS

13

SWCH

FuseB74

A BISTO

0 1 AS

2

AS

6

020

021

022

023

QA

4

024

025

026

027

QA

5

2 3 AS

3

AS

7

030

031

032

033

QA

6

034

035

036

037

QA

7

QA

2

010

011

012

013

014

015

016

017

AS1

AS

5

000

001

002

003

004

005

AS

0

AS

4

BCLA

M

BCLA

SSYS

10 / 54 3BK 17430 3001 RJZZA Ed.03

Page 11: G2 BSC comm

1 Overview

1.1.1.3 Rack Layout: Rack 2, Configuration 3

01

SWCH

0

DC

03

SWCH

1

DC

05

SWCH

2

07

SWCH

3

09

SWCH

4

11

SWCH

5

13

SWCH

6

15

SWCH

7

17

DC

19

DC

21

SWCH

0

23

SWCH

1

25

SWCH

2

27

SWCH

3

29

SWCH

4

31

SWCH

5

33

SWCH

6

35

SWCH

7

37

DC

39

DC

41

SWCH

0

43

SWCH

1

45

SWCH

2

47

SWCH

3

49

SWCH

4

51

SWCH

5

53

SWCH

6

55

SWCH

7

57

DC

59

DC

61 63

CB A01 . . . . . . . . . . . CB A09 CB B71 . . . . . . . . . . . . . CB B78top rack unit for the fuses SAU01

SAU02

SAU03

SAU04

SAU05

FuseA01

FuseB72

FuseB71

GS2/5 . . . . . . . . . . . GS2/5 GS2/6 . . . . . . . . . . . GS2/6 GS2/7 . . . . . . . . . . . GS2/7

air baffle

FuseA02

A TERTO

N+1

01

DC

03

DC

05 07 09

SWCH

11

SWCH

13

DTCC

15

DTCC

17

DTCC

19

DTCC

21

ASMB

23

DTCC

25

DTCC

27

DTCC

29

DTCC

31

ASMB

33

DC

35

DC

37 39 41

SWCH

43

SWCH

45

DTCC

47

DTCC

49

DTCC

51

DTCC

53

ASMB

55

DTCC

57

DTCC

59

DTCC

61

DTCC

63

ASMB SAU

06

SAU07

SAU08

FuseA08

FuseB76

FuseB75

GS1/2 . . . . . . . . . . . GS1/2

GS1/3 GS1/3

FuseA05

A TERTO

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

5

SWCH

6

SWCH

7

DC

DC

DC

DC

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

DC

DC

BCLA

M

BCLA

S

FuseA07

FuseA06

B GSA TO

A TERTO

ABIS TO BSCY05

RACKN+1

GS2/4 . . . . . . . . . . . GS2/4

DC

DC

TSCA

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

7

DC

B GSA TOSYSB00

TCUC

SWCH

5

SWCH

6SYSA TO

DC

FuseB77

FuseB78

FuseA09

BGSATO BGSATO BGSATO

AS

18

AS

22

220

221

222

223

QA

4

224

225

226

227

AS

19

AS

23

230

231

232

233

QA

6

234

235

236

237

QA

2

210

121

212

213

214

215

216

217

AS

17

AS

21

QA

0

200

201

202

203

204

205

206

207

AS

16

AS

20

QA

5

QA

7

3BK 17430 3001 RJZZA Ed.03 11 / 54

Page 12: G2 BSC comm

1 Overview

1.1.1.4 Rack Layout: Rack 2, Configurations 4, 5, 6

01

SWCH

0

DC

03

SWCH

1

DC

05

SWCH

2

07

SWCH

3

09

SWCH

4

11

SWCH

5

13

SWCH

6

15

SWCH

7

17

DC

19

DC

21

SWCH

0

23

SWCH

1

25

SWCH

2

27

SWCH

3

29

SWCH

4

31

SWCH

5

33

SWCH

6

35

SWCH

7

37

DC

39

DC

41

SWCH

0

43

SWCH

1

45

SWCH

2

47

SWCH

3

49

SWCH

4

51

SWCH

5

53

SWCH

6

55

SWCH

7

57

DC

59

DC

61 63

CB A01 . . . . . . . . . . . CB A09 CB B71 . . . . . . . . . . . . . CB B78top rack unit for the fuses SAU01

SAU02

SAU03

SAU04

SAU05

FuseA01

FuseB72

FuseB71

GS2/5 . . . . . . . . . . . GS2/5 GS2/6 . . . . . . . . . . . GS2/6 GS2/7 . . . . . . . . . . . GS2/7

air baffle

FuseA02

A TERTO

N+1

01

DC

03

DC

05

SWCH

07

SWCH

09

SWCH

11

SWCH

13

DTCC

15

DTCC

17

DTCC

19

DTCC

21

ASMB

23

DTCC

25

DTCC

27

DTCC

29

DTCC

31

ASMB

33

DC

35

DC

37

SWCH

39

SWCH

41

SWCH

43

SWCH

45

DTCC

47

DTCC

49

DTCC

51

DTCC

53

ASMB

55

DTCC

57

DTCC

59

DTCC

61

DTCC

63

ASMB SAU

06

SAU07

SAU08

FuseA08

FuseB76

FuseB75

GS1/2 . . . . . . . . . . . GS1/2

GS1/3 GS1/3

FuseA05

A TERTO

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

5

SWCH

6

SWCH

7

DC

DC

DC

DC

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

DC

DC

BCLA

M

BCLA

S

FuseA07

FuseA06

B GSA TO

A TERTO

ABIS TO BSCY05

RACKN+1

GS2/4 . . . . . . . . . . . GS2/4

DC

DC

TSCA

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

7

DC

B GSA TOSYSB00

TCUC

SWCH

5

SWCH

6SYSA TO

DC

FuseB77

FuseB78

FuseA09

B GSATO B GSATO B GSATO

SWCH

SWCH

SWCH

SWCH

DTCC

DTCC

DTCC

DTCC

ASMB

DTCC

DTCC

DTCC

ASMB

DC

DC

SWCH

SWCH

SWCH

SWCH

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

BIUA

GBISTO

DC

DC

DC

GS1/3 . . . . . . . . . . . GS1/3

4 5 AS

26

AS

30

320

321

322

323

QA

12

324

325

326

327

QA

13FuseB73

DTCC

TCUC

TCUC

QA

14

GS1/3 . . . . . . . . . . . GS1/3

6 7 AS

27

AS

31

330

331

332

333

334

335

336

337

FuseA03

A BISTO

N+1

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

DC

DC

QA

8

300

301

302

303

304

305

306

307

AS

24

AS

28

SWCH

FuseA04

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

DC

QA

10

310

311

312

313

314

315

316

317

AS

25

AS

29

SWCH

FuseB74

A BISTO

0 1 AS

18

AS

22

220

221

222

223

QA

4

224

225

226

227

QA

5

2 3 AS

19

AS

23

230

231

232

233

QA

6

234

235

236

237

QA

7

QA

2

210

211

212

213

214

215

216

217

AS

17

AS

21

QA

0

200

201

202

203

204

205

206

207

AS

16

AS

20

12 / 54 3BK 17430 3001 RJZZA Ed.03

Page 13: G2 BSC comm

1 Overview

1.1.1.5 Rack Layout: Rack 3, Configuration 5

01 03 05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63

CB A01 . . . . . . . . . . . CB A09 CB B71 . . . . . . . . . . . . . CB B78top rack unit for the fuses SAU01

SAU02

SAU03

SAU04

SAU05air baffle

01

DC

03

DC

05 07 09

SWCH

11

SWCH

13

DTCC

15

DTCC

17

DTCC

19

DTCC

21

ASMB

23

DTCC

25

DTCC

27

DTCC

29

DTCC

31

ASMB

33

DC

35

DC

37 39 41

SWCH

43

SWCH

45

DTCC

47

DTCC

49

DTCC

51

DTCC

53

ASMB

55

DTCC

57

DTCC

59

DTCC

61

DTCC

63

ASMB SAU

06

SAU07

SAU08

FuseA08

FuseB76

FuseB75

GS1/4 . . . . . . . . . . . GS1/4

GS1/5 GS1/5

FuseA05

A TERTO

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

5

SWCH

6

SWCH

7

DC

DC

DC

DC

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

DC

DC

BCLA

M

BCLA

S

FuseA07

FuseA06

B GSA TO

A TERTO

ABIS TO BSCY05

RACKN+1

DC

DC

TSCA

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

SYSB00

TCUC

SYSA TO

FuseB77

FuseA09

AS

34

AS

38

420

421

422

423

QA

4

424

425

426

427

QA

5

AS

35

AS

39

430

431

432

433

QA

6

434

435

536

437

QA

7

QA

2

410

411

412

413

414

415

416

417

AS

33

AS

37

QA

0

400

401

402

403

404

405

406

407

AS

32

AS

36

3BK 17430 3001 RJZZA Ed.03 13 / 54

Page 14: G2 BSC comm

1 Overview

1.1.1.6 Rack Layout: Rack 3, Configuration 6

01

DC

03

DC

05 07 09 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63

CB A01 . . . . . . . . . . . CB A09 CB B71 . . . . . . . . . . . . . CB B78top rack unit for the fuses SAU01

SAU02

SAU03

SAU04

SAU05air baffle

FuseA02

A TERTO

N+1

01

DC

03

DC

05

SWCH

07

SWCH

09

SWCH

11

SWCH

13

DTCC

15

DTCC

17

DTCC

19

DTCC

21

ASMB

23

DTCC

25

DTCC

27

DTCC

29

DTCC

31

ASMB

33

DC

35

DC

37

SWCH

39

SWCH

41

SWCH

43

SWCH

45

DTCC

47

DTCC

49

DTCC

51

DTCC

53

ASMB

55

DTCC

57

DTCC

59

DTCC

61

DTCC

63

ASMB SAU

06

SAU07

SAU08

FuseA08

FuseB76

FuseB75

GS1/4 . . . . . . . . . . . GS1/4

GS1/5 GS1/5

FuseA05

A TERTO

SWCH

0

SWCH

1

SWCH

2

SWCH

3

SWCH

4

SWCH

5

SWCH

6

SWCH

7

DC

DC

DC

DC

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

DC

DC

BCLA

M

BCLA

S

FuseA07

FuseA06

B GSA TO

A TERTO

ABIS TO BSCY05

RACKN+1

DC

DC

TSCA

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

SWCH

DC

DC

SYSB00

TCUC

SYSA TO

FuseB77

FuseA09

SWCH

SWCH

SWCH

SWCH

DTCC

DTCC

DTCC

DTCC

ASMB

DTCC

DTCC

DTCC

ASMB

DC

DC

SWCH

SWCH

SWCH

SWCH

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

BIUA

GBISTO

DC

DC

DC

GS1/5

4 5 AS

42

AS

47

520

521

522

523

QA

12

524

525

526

527

QA

13

FuseB73

DTCC

TCUC

TCUC

QA

14

GS1/5

6 7 AS

43

AS

47

530

531

532

533

534

535

536

537

FuseA03

A BISTO

N+1

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

DC

DC

QA

8

500

501

502

503

504

505

506

507

AS

40

AS

44

SWCH

FuseA04

BIUA

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

TCUC

SWCH

DC

QA

10

510

511

512

513

514

515

516

517

AS

41

AS

45

SWCH

FuseB74

A BISTO

0 1 AS

34

AS

38

420

421

422

223

QA

4

424

425

426

427

QA

5

2 3 AS

35

AS

39

430

431

432

433

QA

6

434

435

436

437

QA

7

QA

2

410

411

412

413

414

415

416

417

AS

33

AS

37

QA

0

400

401

402

403

404

405

406

407

AS

32

AS

36

14 / 54 3BK 17430 3001 RJZZA Ed.03

Page 15: G2 BSC comm

1 Overview

1.1.2 Cases

The following case applies:

C1: The BSC is in configuration is 3 or higher so the hardware is tested.

1.1.3 Options

The following options apply:

O1: External alarm cables are installed so they are tested.

O2: The TC is installed and connected at the DDF on the BSC site so the

BSC-TC link is checked.

1.1.4 Initial State

At the start of the commissioning:

The BSC racks are installed and wired on the customer’s site

The power supply is connected and powered up, but the racks are not

powered up (all circuit breakers at the top of each rack must be in theOFF position).

3BK 17430 3001 RJZZA Ed.03 15 / 54

Page 16: G2 BSC comm

1 Overview

1.1.5 Final State

When commissioning is finished:

The BSC is powered up and downloaded with the build requested by

the customer

The BSC is connected to the TC and 9153 OMC-R, ready for physical

connection of the BTSs.

1.1.6 Restrictions

None.

16 / 54 3BK 17430 3001 RJZZA Ed.03

Page 17: G2 BSC comm

1 Overview

1.1.7 Grouped Task Sequence

The following figure shows the task sequence for the 9120 BSC commissioningtasks.

Before Going on Site

Rellocate System CPRCs

Load and Activate BSC Software

Check Battery Backup of S−CPRC Boards

Correct BSC Date and Time

Check BSC − TC Link (O2)

Set and Check BSC − OMC−R Link

Before You Leave

Check Hardware

Check Power Supply and Power Up

Install BSC Terminal and X25 Board

Diskettes / CD−ROMInstall BSC Software from

Dikettes or CD−ROM

Alarm Cables Installed?

YesNoTest External Alarms (O1)

BSC Configuration 3 or

Higher?

BSC Hardware Test (C1)

Yes

No

Before You Start

3BK 17430 3001 RJZZA Ed.03 17 / 54

Page 18: G2 BSC comm

1 Overview

1.2 Preparation

1.2.1 Prerequisites

The following prerequisites must be fulfilled:

The site must comply with the safety rules as given in the BSS MethodsHandbook

At least two Ater Mux PCM links must be available.

1.2.2 Site-Specific Information

The following site-specific information is needed before starting thecommissioning:

SiteDDF map

Equipment

Rack configuration number (1 to 6)

X.25 routing:

Extraction at BSC site

Extraction on TRCU modules via X.25 packet switch

X.25 routed through MSC.

BSS topology

BSS software version

Other

TSC firmware version

Status of the A interface cables at the TC side (connected to MSC orlooped)

Which A interface cables are connected at the MSC (if applicable)

External alarm cables (available or not).

18 / 54 3BK 17430 3001 RJZZA Ed.03

Page 19: G2 BSC comm

1 Overview

1.3 Scheduling

Time based on technical constraintsThe number of resources shown in the following table does not take intoaccount individual customer or safety requirements.

Grouped Task Time / Task:Com. 1

Time / Task:Com. 2

Total Time / Task

Before Going on Site 20 min. 20 min. 40 min.

Before You Start 20 min. 20 min. 40 min.

Check Hardware(1) 10 - 60 min.(2) 10 - 60 min.(2) 20 min. - 2 hours

Check Power Supply and Power Up(1) 25 min. 25 min. 50 min.

Install BSC Terminal and BSS Software

Install BSC Terminal Software and X.25Communication Board

45 min. - 45 min.

Install Craft Terminal 10 min. - 10 min.

Install BSS Software 10 - 20 min.(3) - 10 - 20 min.

Perform Commissioning Tests

Relocate S-CPRCs 2 min. - 2 min.

Load and Activate BSC Software 1 h 30 min. - 1 h 30 min.

Check Battery Backup of S-CPRC Boards 30 min. - 30 min.

Correct BSC Date and Time 2 min. - 2 min.

Test External Alarms (O1) 10 min. 10 min. 20 min.

BSC Hardware Test (C1) 40 min. - 40 min.

Check BSC - TC link (O2) 20 min. - 20 min.

Set and Check BSC - 9153 OMC-R Link 30 min. - 30 min.

Before You Leave 20 min. - 20 min.

Total 6 h 24 min. /

7 h 24 min.

1 h 25 min. /

2 h 15 min.

7 h 50 min. /

9 h 40 min.

Com. : Commissioner

(1) : Tasks where two people are mandatory for execution

(2) : Depending on the BSC configuration (1-6)

(3) : 10 minutes from IOMEGA zip, 20 minutes from diskettes

3BK 17430 3001 RJZZA Ed.03 19 / 54

Page 20: G2 BSC comm

1 Overview

1.4 Resources

1.4.1 Tools

The following sections describe the necessary hardware tools, software toolsand forms.

1.4.1.1 Hardware ToolsUse the following table to check the availability of the necessary tools.

Refer to the Tools Catalogue to check the contents.

Item Reference Calibration

Basic kit OUT 001 No

Test cables and plugs (9120 BSC) OUT 013 No

Digital multimeter DES 001 No

Utility PC (BTS LMT) DES 002 No

Inventory kit Nr. 7 OUT 017 No

1.4.1.2 Software ToolsUse the following table to check the availability of the necessary software. Referto the corresponding document to check the software version.

Name Check Version in

Operating system Tools Catalogue

BSC Terminal/BSCWAVxxx BSS Software List

LMT_CT/CTxxx.exe BSS Software List

BSSBUILD BSS Software List

EICON board driver for Windows 2000/XP BSS Software List

1.4.1.3 FormsNone.

1.4.2 Supplies

None.

20 / 54 3BK 17430 3001 RJZZA Ed.03

Page 21: G2 BSC comm

1 Overview

1.4.3 Applicable Documents

The following documents are needed to complete the 9120 BSC commissioning:

Document Title Reference

Catalogue of Technical and Logistic Information(ITLs)

3DF 00462 0004 AAAGA

Applicable Operation Instruction List (IO) 3DF 00300 0004 UAZZA

BSS Methods Handbook 3BK 17430 0002 RJZZA

BSC Terminal User Guide 3BK 21220 AAAA PCZZA

Transmission Terminal User Guide 3BK 21257 AAAA PCZZA

Tools Catalogue for Field Activity 3BK 20458 0001 RJZZA

Specification for Site Preparation 9120 BSC(SPP-27)

8BL 00704 0018 DRBRA

BSS Site Premises Inspections, Post Handover 8BL 00704 0016 DRBRA

Site Premises Inspections form (CEL) 8BL 00704 0015 DRBRA

Completion Check List (CCL) 3BK 17430 3001 QZZZA

CI-08 Site Equipment Inventory 3BK 17257 0001 RJZZA

BSS Software List Depends on the software version requested by thecustomer.

3BK 17430 3001 RJZZA Ed.03 21 / 54

Page 22: G2 BSC comm

1 Overview

22 / 54 3BK 17430 3001 RJZZA Ed.03

Page 23: G2 BSC comm

2 Commissioning Tests

2 Commissioning Tests

This section presents all checks needed before starting the Commissioning,and all detailed tasks to be performed on site.

3BK 17430 3001 RJZZA Ed.03 23 / 54

Page 24: G2 BSC comm

2 Commissioning Tests

2.1 Before Going On SiteBefore going on-site, you must check that the following information andsupplies are available:

All Prerequisites (Section 1.2.1) are fulfilled

The customer has been informed of the

Date

Time

Site name

Site address

Purpose of the operation.

Personnel are available and ready for operation (Refer to Scheduling(Section 1.3))

Site-Specific Information (Section 1.2.2) is available and ready for operation

Hardware Tools (Section 1.4.1.1) are available and ready for operation

Software Tools (Section 1.4.1.2) are available in the correction versionand ready for operation

Applicable Documents (Section 1.4.3) are available and ready for operation.

24 / 54 3BK 17430 3001 RJZZA Ed.03

Page 25: G2 BSC comm

2 Commissioning Tests

2.2 Before You Start

2.2.1 Checks

Perform the following operations:

Check applicable notifications and operating instructions (refer to the

Applicable Notification List (ITL) and the Applicable Operation InstructionList (IO))

Check the availability of all necessary tools and supplies

Check that all Prerequisites (Section 1.2.1) are fulfilled

Check which Cases (Section 1.1.2) and Options (Section 1.1.3) apply

Complete the header field of the CCL, noting the type of BTS (see Hardware

Description - Racks Configuration (Section 1.1.1)). The CCL is completedas each instruction is carried out

Complete the Premises Inspection Form (BSS Site Premises Inspection,

Post Handover)

Complete the Premise Inspection form (CEL)

Check that the resistance of the anti-static wrist strap is greater then

1 Mohm.

2.2.2 Required Knowledge

You must be familiar with the following:

The safety rules and precautions given in the BSS Methods Handbook

How to document faults and anomalies as described in the BSS Methods

Handbook

Grouped Task Sequence (Section 1.1.7).

3BK 17430 3001 RJZZA Ed.03 25 / 54

Page 26: G2 BSC comm

2 Commissioning Tests

2.3 Check HardwareThese hardware checks are done to:

Check that the BSC configuration corresponds to the customer’s order

Verify that the hardware level of the boards inside the BSC is as requested

by the customer, by taking the rack inventory.

Two people are mandatory when checking the hardware.

To check the hardware:

1. Verify the presence and position of the boards according to the requestedconfiguration.

Refer to the Site-Specific Information and Hardware Description - RacksConfiguration sections.

2. Perform the rack inventory.

Refer to the CI 08 - Site Equipment Inventory.

Check for “NOT IN CAL” alarms.Check that there are no alarms of the type “NOT IN CAL” when runningInventar for the BTS. This ensures that the boards inside the BSC meet therequirements of a specific customer.

26 / 54 3BK 17430 3001 RJZZA Ed.03

Page 27: G2 BSC comm

2 Commissioning Tests

2.4 Check Power Supply and Power Up

Two people are mandatory when checking the power supply and powering up.

2.4.1 Check the Fuse Ratings

To check the fuse ratings:

1. On the customer power panel (cabinet), check for the existence of two DCpower supply distribution circuits. Each distribution circuit is provided with aDC circuit breaker (fuse holder).

2. On the site power panel, disconnect the two -48V power supply lines (line Aand B) at the rack fuse holders.

3. Check that the fuse ratings are in accordance with the SPP – 27 document.

2.4.2 Discharge Capacitors in Racks

To discharge the capacitors in the racks:

1. At the customer power panel, make sure the two -48 V power supply lines forthe BSC are disconnected.

2. Close (ON position) all the rack (and extension rack if applicable) circuitbreakers for 10 seconds.

3. Open (OFF position) all the rack circuit breakers.

2.4.3 Check Polarity of Power Supply Line, Branch A

To check the polarity of the power supply line, branch A:

1. On the BSC top rack filter units for each rack (basic and extension racks ifapplicable), remove the protection caps from the power supply terminals.

2. Connect the -48 V power supply (branch A) at the fuse holder.

Branch A is connected.

Branch A is associated with the fuse holder marked BAT A.

3. Using the multimeter, check the presence of -48V DC between BAT A andBATRET for all racks (basic and extensions).

4. Check that no voltage is present between BAT B and BATRET for all racks.

5. Switch all the rack circuit breakers to ON.

The DC/DC converters A01-A09 for all racks are powered up.

The DC/DC converters B71-B78 for all racks are not powered up.

Note : Converters B72 and B78 are removed starting from rack variant3BK 06796 AAAC.

6. Switch all the rack circuit breakers to OFF.

No board in the racks is powered up.

7. At the customer power panel, disconnect the -48 V power supply (branch A)at the fuse holder.

Branch A is disconnected.

3BK 17430 3001 RJZZA Ed.03 27 / 54

Page 28: G2 BSC comm

2 Commissioning Tests

2.4.4 Check Polarity of Power Supply Line, Branch B

To check the polarity of the power supply line, branch B:

1. Discharge the capacitors in the rack.

See Discharge Capacitors in Racks (Section 2.4.2).

2. On the BSC top rack filter units for each rack (basic and extension racks ifapplicable), remove the protection caps from the power supply terminals.

3. Connect the -48 V power supply (branch B) at the fuse holder.

Branch B is connected.

Branch B is associated with the fuse holder marked BAT B.

4. Using the multimeter, check the presence of -48V DC between BAT B andBATRET for all racks (basic and extensions).

5. Check that no voltage is present between BAT A and BATRET for all racks.

6. Switch all the rack circuit breakers to ON.

The DC/DC converters B71-B78 for all racks are powered up.

The DC/DC converters A01-A09 for all racks are not powered up.

Note : Converters B72 and B78 are removed starting from rack variant3BK 06796 AAAC.

7. Switch all the rack circuit breakers to OFF.

No board in the racks is powered up.

8. At the customer power panel, disconnect the -48 V power supply (branch B)at the fuse holder.

Branch B is disconnected.

2.4.5 Power Up BSC Racks

To power up the BSC racks:

1. Switch ON the two power supply lines on the customer power panel.

2. Switch ON the B71 to B78 rack circuit breakers.

Note: Converters B72 and B78 are removed starting from rack variant3BK 06796 AAAC.

3. Switch ON the A1 to A9 rack circuit breakers.

The boards take about one minute to run their self-tests.

4. Refer to the BSS Methods Handbook to check the LED states.

28 / 54 3BK 17430 3001 RJZZA Ed.03

Page 29: G2 BSC comm

2 Commissioning Tests

2.5 Install BSC Terminal and X.25 Board

2.5.1 Install X.25 Communication Board and BSC Terminal Software

You must first install the X.25 communications board and then the BSCTerminal Software.

2.5.1.1 Install EICON C91 BoardTo install the EICON C91 (for LMT) board in Windows environment, referto the BSC Terminal User Guide.

2.5.1.2 Install Windows BSC TerminalTo install the BSC Terminal software for Windows, refer to the BSC TerminalUser Guide.

2.5.2 Install the Craft Terminal

To install the LMT-CT Craft Terminal software on the PC, refer to theTransmission Terminal User Guide.

2.5.3 Install the BSS Software

The build is produced with POLO, and must be transferred to the BSC TerminalPC. The transfer can be performed directly through a network if available atthe BSC site. If not, the build can be delivered on diskettes, CD-ROM or anIOMEGA ZIP disk.

2.5.3.1 Build Delivered on Diskettes or CD-ROMTo install a build delivered either on diskettes or a CD-ROM:

1. On the LMT, create the following directories:

C:\BUILDBSS\B10\<Name of the customer build>

2. Copy all the build delivery compressed files (gzip) from the diskettes or theCD-ROM to the newly-created directory (all files in same directory).

3. Copy gzip.exe from C:\Program Files\Alcatel\WINBSC\B10 toC:\BUILDBSS\B10\<Name of customer build>

4. Open a command prompt window:

Start –> Programs –> Command Prompt

5. In the command prompt window, enter the following commands:cd \BUILDBSS\B10\Name of customer buildgzip -dvN *.gz

Note : *.gz means all the files in the current directory with the extension gz.

All the gzip files are uncompressed.

6. Using a text editor (e.g. Notepad) open the CONTENTS.LSTfile.

7. Check the BSC master file (i.e., bscmxXxx) version specified inCONTENTS.LSTagainst the requested customer version.

Refer to the BSS Software List.

3BK 17430 3001 RJZZA Ed.03 29 / 54

Page 30: G2 BSC comm

2 Commissioning Tests

2.5.3.2 Build Delivered on IOMEGA ZIP Disk

In this case, the LMT must have an IOMEGA ZIP drive installed.

To install a build delivered on an IOMEGA ZIP disk:

1. On the LMT, create the following directory(ies):

C:\BUILDBSS\B10\<Name of the customer build>

2. Copy all the build delivery files from the IOMEGA ZIP disk to thenewly-created directory.

3. Copy gzip.exe from C:\Program Files\Alcatel\WINBSC\B10 toC:\BUILDBSS\B10\<Name of customer build>

4. Open a command prompt window:

Start –> Programs –> Command Prompt

5. In the command prompt window, enter the following commands:cd \BUILDBSS\B10\Name of customer buildgzip -dvN *.gz

Note : *.gz means all the files in the current directory with the extension gz.

All the gzip files are uncompressed.

6. Using a text editor (e.g., Notepad), open the CONTENTS.LSTfile.

7. Check the BSC master file (i.e., bscmxXxx) version specified inCONTENTS.LSTagainst the requested customer version.

Refer to the BSS Software List.

30 / 54 3BK 17430 3001 RJZZA Ed.03

Page 31: G2 BSC comm

2 Commissioning Tests

2.6 Commissioning Tests

2.6.1 Relocate System-CPRCs

Use the anti-static wrist strap.Use the anti-static wrist strap when working in contact with the BSC boards.Otherwise permanent damage can be caused to the boards.

Move the S-CPRC PBAs from their transport positions to their operationalpositions as follows:

1. PBA in position 23 (transport) to position 21 (operational).

2. PBA in position 27 (transport) to position 25 (operational).

The S-CPRCs are in operational position. The boards run their self-testsfor about one minute. When the bottom LED is blinking, they are readyto be loaded.

Refer to the BSS Methods Handbook for a description of the LEDs.

2.6.2 Load and Activate BSC Software

2.6.2.1 Prepare X.25 Configuration LinkPrepare the X.25 configuration link as follows:

1. Connect the COM1 port of the BSC Terminal to the 9–pin connector ofS-CPRC 1 (SAU 08 position 21) using the CPRC serial cable.

Refer to the Tools Catalogue for the cable reference.

2. To start the BSC Terminal, follow the menu path:

Start -> Programs -> WinBSC -> B10 -> Windows BSC Terminal B10The following window appears:

3BK 17430 3001 RJZZA Ed.03 31 / 54

Page 32: G2 BSC comm

2 Commissioning Tests

3. In the BSC Communication Control window, select a serial connection and’Logging’ and click on [ Connect ].

4. In the Windows BSC Terminal window, follow the menu path:

Utilities -> Minibuild Loading

The Minibuild Loading window opens:

5. Enter the path of the minibuild directory in the ’Directory’ field (as shown inthe figure), using the [ Browse... ] button.

6. In the ’Available’ field, select the ‘bssmini.*’ files and click on [ Go! ].

Refer to the BSS Methods Handbook to monitor the progress of thedownload by observing the LEDs on the CPRC PBA.

The files are automatically downloaded.

When the download is complete, a successful report message appears.

Check the lower right corner in the Windows BSC Terminal windows to monitorcommunication between the PC and the BSC equipment. Check for ’the

message has been sent to BSC...’ and that a reply has been received).

7. Click on the shortcut exit button (top right corner in the Windows BSCterminal window).

8. Click on[ Yes ] to confirm the close connection message.

32 / 54 3BK 17430 3001 RJZZA Ed.03

Page 33: G2 BSC comm

2 Commissioning Tests

2.6.2.2 Check and Upgrade TSCA Firmware

This upgrade MUST be performed if the TSCA firmware does notcorrespond to release B6, B7 or B8!

This task is done to upgrade the TSCA firmware from B5 to B6 (even if thecommissioning of the BSC is done in B8).

2.6.2.3 Check TSCA Board Firmware VersionCheck the TSCA board firmware version:

1. Check the LED status of the TSCA, for all TSCA boards in the BSC

Turn−button Latch

Turn−button Latch

LED 1 (Red)

LED 2 (Red)

LED 3 (Red)

LED 4 (Red)

Push Button

9−pin Connector

PBA Identifying Label

Figure 1: TSCA Front Plate

3BK 17430 3001 RJZZA Ed.03 33 / 54

Page 34: G2 BSC comm

2 Commissioning Tests

The following table gives the possible LEDs status.

The status of the LEDs is correct taken in account if the BSC is new and nodownload was done to CPRA-SYS. If the BSC is IT, the TCU terminating theTSL should be disabled (For rack 1: TCU(1), for rack 2: TCU(41), for rack3: TCU(81)).

Status Action

Lower LED (LED1) is blinking slow(300ms ON / 300 ms OFF)

TSCA is in B5 mode and needs to bemigrated

Lower 2 LEDs (LED1 and LED2) aretoggling (like TCU/DTC)

TSCA is in B5 mode and needs to bemigrated

Middle LED (LED2) is blinking slow(4 blinks ON, 1 skipped)

TSCA is in B6 mode and does notneed to be migrated

If after the LEDs check the TSCA board must be migrated continue withthe following steps.

2. Connect the LMT Terminal to the first TSCA PBA using the LMT-CTTerminal/MMI cable.

3. Start the Craft Terminal B8 (lmctavxx) by double-clicking on the LMTTerminal SW icon.

4. When the password window appears, click on [ OK ].

The Main Menu appears:

5. In the Main Menu, select:

TSC -> Download Migration Software

If the connection is not established, close the Craft terminal and try toestablish the connection again.

If after the LEDs check the upgrade must be performed but following moreattempts the connection is still not possible it could be due to a failing RS232interface. Make sure that the serial interface is ok.

If afterwards (after BSC SW loading and init) it is still not ok, an alarm will beraised on the TSCA (Access failure).

34 / 54 3BK 17430 3001 RJZZA Ed.03

Page 35: G2 BSC comm

2 Commissioning Tests

6. Upgrade the TSCA firmware to firmware B6.2, if applicable. (seeSite-Specific Information). For details refer to Upgrade TSCA Firmwarefrom B5 to B6 (If Necessary) (Section 2.6.2.4).

2.6.2.4 Upgrade TSCA Firmware from B5 to B6 (If Necessary)

Install the Software on

the PC

To install the TSCA firmware on the PC:

1. Create the directory TSC_FWon the PC.

2. Copy the firmware delivery for release B6 (TSCSAQxx.0xx - , see the BSSSoftware List) from diskettes into the TSC_FWdirectory.

3. Leave the diskettes for the installed software in the site documentation.

Upgrade TSCA to B6

Firmware

If the Craft Terminal sets up the connection with the TSCA board:

1. Then, following the command already given on the LMT CT B8, select:

TSC -> Download Migration SoftwareThe following messages appear:’Waiting for Download Request from TSC...’Download of Both Code and Data Requested. Proceed?’

2. Click on [ OK ].

The program asks for the TSC CODE file.

3. Select the file that you installed in the TSC_FWdirectory:C:/TSC_FW/TSCSAQxx.0xx

4. Click on [ OK ].

The following message appears:’TSC is currently erasing a page of memory.’

And then the download starts.

5. When ’Download of Data Requested. Proceed?’ appears, click on[ OK ].

6. Select the file with data from the LMT CT directory:.../LMT_CT/B8/Settings/g2/tsca/empty_db.tsc

7. Click on [ OK ].

8. Wait for the TSCA to download successfully.

After the TSCA board has been downloaded, wait approximately 10minutes .

During this time the TSCA will erase and reprogram the bootstrap flash. Duringthis process, either there is NO LED ON, or ONE LED STATIC ON.Do not power OFF the BSC rack. Do not remove the TSCA.Do not push the reset button on the TSCA.Be patient, wait for the process to finish and the auto-reset of the TSCA.

9. After the bootstrap has been replaced, the TSCA will auto-reset and comeup in B6 mode.

This will be visible due to the middle LED (LED 2) blinking slow, 4 timesON, one time OFF. This indicates that the TSCA is trying to establish theTSL to the BSC in the new mode (B6 and up).

The TSCA will continue like this until the BSC application SW has beendownloaded and the BSC becomes operational.

10. If the TCU was disabled in Check TSCA Board Firmware Version (Section2.6.2.3), using the BSC terminal, initialize it again.

3BK 17430 3001 RJZZA Ed.03 35 / 54

Page 36: G2 BSC comm

2 Commissioning Tests

When the TCU is initialized, the TSCA establishes the connection with the BSC.If the BSC is operational, in most cases the bootstrap and the TSC applicationsoftware will be upgraded by the BSC.

11. Apply the same procedure for each TSCA board.

2.6.2.5 Format Disk ATo format disk A:

1. Connect the X.25 number 0 port of the BSC Terminal to the 25-pin connectorof S-CPRC 1 (SAU 08 position 21) using the CPRC parallel cable.

Refer to the Tools Catalogue for the cable reference type.

2. Open a new session and select the ’X.25’ link and ’Logging’ in the BSCCommunication Control window.

3. Click on [ Connect ].

If an X.25 Link error message window appears, verify the link with the BSCequipment and repeat the last two steps.

4. From the Windows BSC Terminal window main menu, select:

Commands -> Disk operations -> Format SSD

The Format SSD window opens.

5. In the ’Directory’ field, enter the full path to the BSS directory using the[ Browse... ] button (e.g., C:\BUILDBSS\BSSS8 ).

6. Select [ Disk A. ]

A list of files that can be used to format the SSD appears.

7. Select the BSS-masterfile xxxMxWxx . xxx.

8. Click on [ Enter ].

9. Click on [ Go! ] to initiate SSD formatting.

When SSD formatting is complete, a report appears showing the resultof the formatting.

36 / 54 3BK 17430 3001 RJZZA Ed.03

Page 37: G2 BSC comm

2 Commissioning Tests

2.6.2.6 Load BSS Software onto Disk AWhen disk A is formatted, load the BSS software onto disk A:

1. From the Windows BSC Terminal window main menu, select:

Commands -> Disk operations -> File Transfer from PC to BSCThe BSS File Directory window opens:

2. In the ’Directory’ field, enter the full path to the BSS directory using the[ Browse... ] button (e.g., C:\BUILDBSS\BSSS9 ).

3. Select the BSS-masterfile xxxMxWxx . xxx.

4. Click on [ Enter ].

5. Enter Disk A in the ’Destination’ field.

In the Files To Transfer pane, the files to be transferred are displayed.

6. Click on [ Go! ] to initiate the file transfer (Start Download).

7. Check the reports.

3BK 17430 3001 RJZZA Ed.03 37 / 54

Page 38: G2 BSC comm

2 Commissioning Tests

2.6.2.7 Check Contents of Disk ATo generate and print out the contents of disk A:

1. From the Windows BSC Terminal window main menu, select:

Commands -> Disk operations -> Control SSD

2. Select the parameters as shown in the Control SSD window below.

3. Click on [ OK ].

4. In the Windows BSC Terminal window, check the command reports.

5. Compare the contents of disk A, shown in the reports window, with theCONTENTS.LSTfile.

2.6.2.8 Initialize the SystemTo initialize the system:

1. From the Windows BSC Terminal window main menu, select:

Commands -> System Activation -> System initializationThe System Initialization window opens.

2. Select the parameters as shown in the System Initialization window above.

3. Click on [ OK. ]

All BSC boards, including NE and TSCA, upload the software stored inthe CPRC board.

The loading procedure is indicated by the LEDs on the board front panels.

Refer to the BSS Methods Handbook for a description of the various LEDstates for the different boards.

After the system initialization command, the BSC Terminal loses the X.25connection with the BSC.

4. After about five minutes, re-establish the link by closing and re-openingthe BSC Terminal.

5. Wait about 20 minutes for the successful report.

The BSC is successfully initialized.

6. Verify that all CE’s are equipped. If a CE is missing, run Hardware Teststo investigate.

38 / 54 3BK 17430 3001 RJZZA Ed.03

Page 39: G2 BSC comm

2 Commissioning Tests

2.6.2.9 Set SBLs of Declared BTSs OPRSet the SBLs of the declared BTSs OPR as follows:

1. From the Windows BSC Terminal window main menu, select:

Commands -> Equipment Handling -> SBL Disable

2. Select the parameters as shown in the SBL Disable window below:

3. In the "Unit number" field, enter the parameter number of the correspondingBTSs. (see Site-Specific Information (Section 1.2.2)).

4. Click on [ OK ] and wait for the successful report.

2.6.2.10 Check Board StatusTo generate and print out the states of the faulty SBLs:

1. From the Windows BSC Terminal window main menu, select:

Commands -> Equipment Handling -> SBL State List

2. Select the parameters as shown in the SBL State List window below.

3. Click on [ OK ].

4. In the Windows BSC Terminal window, check the reports to verify that all theCPR, DTC, TCU, TSC and SWITCH SBLs of the BSC are "In Traffic". Theyshould not appear in the State List command report.

The State List command displays the states of all SBLs that are not "In Traffic".In the Windows BSC Terminal window, use the mouse to double-click on thecompressed report message any time you want a Full Report View.

3BK 17430 3001 RJZZA Ed.03 39 / 54

Page 40: G2 BSC comm

2 Commissioning Tests

2.6.2.11 Format Disk BFormat disk B as follows:

1. Disable Alarm Reports (Disable / Enable Alarm Reports (Section 2.11.2)).

Sequence of operations is blockedIf the sequence of operations is blocked at any time, apply the Workaround:Exit / Connect WinBSC Terminal (Section 2.12) to restart the BSC Terminal.

2. From the Windows BSC Terminal window main menu, select:

Commands -> Disk Operations -> Format Duplex SSD

3. In the Format Duplex SSD window, enter the ’Source - Destination’parameter.

4. Click on [ OK ].

5. Check the reports to see if the action was successful.

6. Wait for the final report, FILE TRANSFER RESULT.

2.6.2.12 Copy BSS Software to Disk BWhen disk B is formatted, copy the BSS software files:

1. From the Windows BSC Terminal window main menu, select:

Commands -> Disk Operations -> File Transfer from BSC to BSC

2. Enter the Source and Destination disk parameters and select ’All Files’.

3. Click on [ OK ].

4. In the Windows BSC Terminal window, check the reports (check to see thatthe BOOTROOT file already exists on disk B).

2.6.2.13 Check Contents of Disk BRepeat the procedure in Section Check Contents of Disk A (Section 2.6.2.7)for Disk B.

40 / 54 3BK 17430 3001 RJZZA Ed.03

Page 41: G2 BSC comm

2 Commissioning Tests

2.6.2.14 Activate Disk BOnce the software is installed and the contents checked, activate disk B:

1. From the Windows BSC Terminal main menu, select:

Commands -> Equipment Handling -> SBL Initialize

2. Click on [ OK ].

3. Enable Alarm Reports

(See Disable / Enable Alarm Reports (Section 2.11.2)).

4. Check the message report.

2.6.3 Check Battery Backup of S-CPRC Boards

This task is done to check that the contents of the S-CPRC disks are not altered(safeguarded by the internal battery backup) by a loss of BSC power supply.

Check the internal battery backup as follows:

1. At the customer power panel, switch OFF the breakers for the two BSCbranches (A and B).

The BSC is powered down.

2. At the customer power panel, switch ON the breakers for the two BSCbranches (A and B).

The BSC is powered up and starts initialization.

3. Wait for BSC initialization to finish (follow the different LED states).

Refer to the BSS Methods Handbook for LED states.

4. Check the board status as described in Check Board Status (Section2.6.2.10).

The respective SBLs are “IT”.

5. Check the contents of the S-CPRC disks (A and B) against theCONTENTS.LSTfile. (Refer to sections Check Contents of Disk A (Section2.6.2.7) and Check Contents of Disk B (Section 2.6.2.13)).

The contents of the S-CPRC disks were not altered by the loss of powersupply.

3BK 17430 3001 RJZZA Ed.03 41 / 54

Page 42: G2 BSC comm

2 Commissioning Tests

2.6.4 Correct BSC Date and Time

To correct the BSC date and time:

1. In the Windows BSC Terminal window, select the menu path:

Commands -> Date & Time -> Modify Date & Time

2. Select the parameters as shown in the example Modify Date and Timewindow below.

3. Click on [ OK ].

2.6.5 Test External Alarms (O1)

If the external alarms are not looped at the DDF, the external alarms should beactive at the BSC Terminal.They will remain active until they are either connected or looped.If they are looped at the DDF, the procedure entails checking that they arecorrectly sent to the BSC Terminal by opening them in turn.

To check that the external alarms are sent to the BSC Terminal.

1. If the external alarms cables are installed, simulate the alarms, one by one,at the DDF side, by inserting disconnect terminals.

See Site-Specific Information (Section 1.2.2).

The corresponding alarms are reported at the BSC Terminal. Example:Alarm Class: 32 EnvironmentalAlarm type: 002-EXT-ALARM

2. Remove the disconnect terminals, one by one.

The corresponding alarms disappear.

42 / 54 3BK 17430 3001 RJZZA Ed.03

Page 43: G2 BSC comm

2 Commissioning Tests

2.7 BSC Hardware Test (C1)

This test only applies to BSCs in configuration 3 or higher, to check theinter-rack cabling.For a BSC in configuration 1 or 2, the Hardware Test is not needed.

The following hardware tests are performed in “off-line” mode and in sequence:

Network test to detect failures in the switching network cabling

Broadcast test to detect failures in the broadcast bus cabling and faulty PBAs

Clock test to detect failures in the clock distribution bus cabling. It also

detects faulty PBAs.

Before the BSC can be tested, it must be in the idle state (all software in all theControl Elements (CE) is running in idle mode).

2.7.1 Reboot BSC in Off-Line Test Mode

Reboot the BSC in off-line test mode:

1. From the Windows BSC Terminal window main menu, select:

Commands -> Commissioning Tests -> BSC System Test InitThe BSC System Test Init window opens.

2. Select the parameters as shown in the BSC System Test Init window above.

3. Click on [ OK ].

A message indicating that the command has been sent to the BSC appearsin the lower left corner of the Windows BSC Terminal window.

4. Wait about 20 minutes for BSC to run in the test mode. (Wait about fiveminutes, exit and reconnect the BSC Terminal).

When the BSC is in test mode, both top LEDs are blinking fast.

To ensure the reliability of the offline test results, it is imperative that all CE’s ofthe BSC have been activated in offline test mode.

3BK 17430 3001 RJZZA Ed.03 43 / 54

Page 44: G2 BSC comm

2 Commissioning Tests

2.7.2 Network Test

To run the Network Test:

1. From the Windows BSC Terminal main menu select:

Commands -> Commissioning Tests -> Test Facilities for G2 ->Network TestThe Network Test window opens.

2. Select the parameters as shown in the Network Test window below.

3. Click on [ OK ].

4. Wait for the report message and try to fix the problem, if there is one by:

Noting down the given address

Finding the given address in the Inter Rack Cable List

Checking the corresponding cables for their addresses on both racks.

Use the mouse to double-click on the compressed report message any timeyou want a Full Report View.If one or more BSC test reports are not successful, the report provides theidentities of the network addresses of the links on which the most errorswere detected.Refer to the BSS Methods Handbook for cable and plug descriptions.See Connect Inter-Rack Cables (Example) (Section 2.11.1).

2.7.3 Broadcast Test

To run the Broadcast Test:

1. From the Windows BSC Terminal main menu, select:

Commands -> Commissioning Tests -> Test Facilities for G2 ->Broadcast TestThe Broadcast Test window opens.

2. Select the parameters as shown in the Broadcast Test window below.

3. Click on [ OK ].

4. Wait for the successful report message.

44 / 54 3BK 17430 3001 RJZZA Ed.03

Page 45: G2 BSC comm

2 Commissioning Tests

2.7.4 Clock Test

To run the Clock Test:

1. From the Windows BSC Terminal main menu, select:

Commands -> Commissioning Tests -> Test Facilities for G2 -> ClockTestThe Clock Test window opens.

2. Select the parameters as shown in the Clock Test window below.

3. Click on [ OK ].

4. Wait for the successful report message.

If a hardware test fails, try to identify the problem and fix it. Repeat all thehardware tests if necessary. If the failure persists, check the cabling betweenthe racks (see the BSS Methods Handbook).

2.7.5 Reboot BSC in OPERATIONAL Mode

To reboot the BSC:

1. From the Windows BSC Terminal window main menu, select:

Commands -> Commissioning Tests -> BSC System Test Init

The BSC System Test Init window opens.

2. Select the parameters as shown in the BSC System Test Init window below:

3. Click on [ OK ].

A message indicating that the command has been sent to the BSC appearsin the lower left corner of the Windows BSC Terminal window.

4. Wait about 15 minutes for the BSC to run in operational mode. (Exit andreconnect the BSC Terminal).

When the BSC is in operational mode, both bottom LEDs are blinking fast.

5. Check the board status. (See Check Board Status (Section 2.6.2.10)).

The CPR, DTC, TCU, TSC and SWITCH SBLs are “IT”.

3BK 17430 3001 RJZZA Ed.03 45 / 54

Page 46: G2 BSC comm

2 Commissioning Tests

2.8 Check BSC-TC Link (O2)

Apply the following procedures only if the TC is installed and connected atthe DDF on the BSC site.

2.8.1 Remove Ater Mux Loops

Remove the Ater Mux loops:

1. At the DDF on the BSC side, remove the loops for the Ater Mux PCMsconnected to the TC equipment. (See Site-Specific Information (Section1.2.2)).

2. Open the LMT Terminal application and connect the RS-232 cable to theLMT (COM).

2.8.2 Check Alarms on the ASMB Boards

For each ASMB board corresponding to the removed loop at the DDF:

1. Connect the serial cable to the board.

2. Follow the menu path:

Session -> ConnectThe message ’SM2M connection established’ appears.

3. Click on [ OK ].

4. Follow the menu path:

Services -> Alarm Collection

5. If the A interface cables are looped at the TC site, (refer to Site-SpecificInformation (Section 1.2.2)), check that the message No Alarms Detected

appears, meaning that the TC link has no alarms.

6. If the A interface cables are connected to the MSC, (refer to Site-SpecificInformation (Section 1.2.2)):

Check that for the A tributaries connected to MSC there are no alarms

Check there are no alarms for the “Highway and control module”.

46 / 54 3BK 17430 3001 RJZZA Ed.03

Page 47: G2 BSC comm

2 Commissioning Tests

2.8.3 Check Status of A Trunk SBLs

To check the status of the A trunk SBLs:

1. At the BSC Terminal, select:

Commands -> Equipment Handling -> SBL Read Status

2. Enter the following parameters:

Object class: > SBL

Unit Type: > BSC

Unit Number: > 1

SBL Type: > ATR

Nbr: > <A trunk number>

(corresponding to the number of the A trunk connected to the MSC or loopedat the TC).

SbNbr: > 255

3. Click on [ OK ].

4. Check that the ATR SBL is “In Traffic” in the report window.

5. Repeat steps 1 to 4 for all the A trunks connected to the MSC(corresponding to the Ater Mux PCMs connected to the TC).

3BK 17430 3001 RJZZA Ed.03 47 / 54

Page 48: G2 BSC comm

2 Commissioning Tests

2.9 Set and Check BSC - 9153 OMC-R Link

This procedure only applies if the BSC is linked to the 9153 OMC-R viathe X.25 network.

2.9.1 Connect Modem to CPRC Board

To connect the modem:

1. Connect the modem to the 25-way connector (reference 3BK 07784 GLAA)on the CPRC board C (subrack 8, slot 17).

On the modem, LEDs 103 and 104 must be ON.

On the CPRC C board, the top LED must be OFF.

2. At BSC Terminal, verify the alarms.

The Unsolicited Alarm Report should appear.

This message indicates that the X.25 link has been re-established.

2.9.2 Test the Communication Link

To test the communication link:

1. At the 9153 OMC-R site , ask the operator to check that the BSC - 9153OMC-R link is operational.

2. At the BSC site , check the X.25 SBL status.

The corresponding X.25 SBL is “IT”.

3. At the 9153 OMC-R site , perform a Software Audit of the BSS equipment.

Wait for the software audit report message.

4. At the 9153 OMC-R site , check for Communication Error Reports in the“BSS_xx Follow up” message window.

No communication errors must appear.

Do not switch OFF the main supply (48V) to the BSC when thecommissioning is done if the DC/DC converters with reference3BK07344AAAD02 have date code (serial number) after ZN0405XXXXXX.In case of mandatory customer requirement to switch OFF the (48V)supply of the BSC between the commissioning and the power OFF, theSystem-CPRC modules must be put in "transportation position" andthen the commissioning has to be partly re-done the day the power willbe re-established.

2.10 Before You LeaveBefore you leave, be sure to:

1. Close the doors of the racks.

2. Leave the site tidy.

3. Close the site and hand the keys to the key holder.

4. Make sure commissioning is finished and a copy of all reports from thecommissioning of the BSC equipment is left with the equipment on site.

48 / 54 3BK 17430 3001 RJZZA Ed.03

Page 49: G2 BSC comm

2 Commissioning Tests

5. Return the completed forms and the inventory files relating to the operationto base.

2.11 Supplemental Tasks

2.11.1 Connect Inter-Rack Cables (Example)

3

12

Rack B Rack A

A = Rack AB = Rack B

Figure 2: Connecting the Extension Loom

3BK 17430 3001 RJZZA Ed.03 49 / 54

Page 50: G2 BSC comm

2 Commissioning Tests

1. Run the interconnection loom at the rear of the racks (see the above figure).Use the addresses written on the end cable labels (as shown).

2. Connect the cables to the rear of the racks.

The addresses locate a locking latch (1), and the connector must be pluggedjust below it (2) (see Figure Locking Latch Address (3) below).

3. Tie the cables to the racks.

Example (shown below): 03::36BA03

Subrack 03

Slot 36

Board connector BA

Locking latch address 03

1

2

01

04

07

10

13

16

19

22

25

28

31

0103

07

10

13

16

19

22

25

28

31

AA

BA

Figure 3: Locking Latch Address

50 / 54 3BK 17430 3001 RJZZA Ed.03

Page 51: G2 BSC comm

2 Commissioning Tests

2.11.2 Disable / Enable Alarm Reports

Use this procedure to:

Disable Alarm Reports during file transfers between the PC and BSC

equipment. This measure is taken to avoid unsuccessful file transfers

Enable Alarm Reports when file transfers are finished.

2.11.2.1 Disable Alarm Reports1. From the Windows BSC Terminal main menu, select:

Commands -> Alarm Handling -> Enable PC Report

2. Select the parameters as shown in the window below.

3. Click on [ OK ].

4. In the Windows BSC Terminal window, check the report message.

2.11.2.2 Enable Alarm Reports1. From the Windows BSC Terminal main menu, select:

Commands -> Alarm Handling -> Enable PC Report

2. Select the parameters as shown in the window below.

3. Click on [ OK ].

4. In the Windows BSC Terminal window, check the report message.

3BK 17430 3001 RJZZA Ed.03 51 / 54

Page 52: G2 BSC comm

2 Commissioning Tests

2.12 Workaround: Exit / Connect WinBSC Terminal1. Click on the shortcut exit button (top corner in the Windows BSC Terminal

window).

The following message window appears.

2. To close the connection, choose [ Yes ].

3. To reconnect the BSC Terminal B10, from the Taskbar select:

Start -> Programs -> WinBSC -> B10 -> Windows BSC Terminal B10The following window appears.

4. In the BSC Communication Control window, select X.25 for ’Link Selection’and the ’Logging’ option.

5. Click on [ Connect ].

If an X25 Link error message window appears, verify the link with the BSCequipment and repeat the last three steps again.

52 / 54 3BK 17430 3001 RJZZA Ed.03

Page 53: G2 BSC comm

Appendix A : Abbreviations

Appendix A: Abbreviations

ASMC Ater submultiplexer C

Ater Interface link between TC and BSC

BSC Base Station Controller

BSS Base Station Subsystem

CCL Completion Check List

CPRC Control Processor Board

DDF Digital Distribution Frame

GSM Global System for Mobile communications

ITL-PRO Procedure technical and support information

IO Instruction Operation

NE Network Elements (i.e.: BIUA, ASMB ...)

PCM Pulse Code Modulation

SAU Subrack Unit

SR Subrack

TC Transcoder

3BK 17430 3001 RJZZA Ed.03 53 / 54

Page 54: G2 BSC comm

Appendix A : Abbreviations

BLANK PAGE BREAK

54 / 54 3BK 17430 3001 RJZZA Ed.03