FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES Western Cape Informal Settlement Strategic Framework (ISSF): Implementation Plan 2016-2030 Final September 2016 in partnership with
32

FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Jun 27, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

FROMPRECARIOUSSETTLEMENTSTODIGNIFIEDCOMMUNITIES

WesternCapeInformalSettlementStrategicFramework(ISSF):ImplementationPlan2016-2030

FinalSeptember2016

inpartnershipwith

Page 2: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

-37-

The Implementation Framework accompanies the Western Cape Informal Settlement Strategic Framework (ISSF). The implementation period for theWesternCapeInformalSettlementStrategicFramework(ISSF)is2016-2030.ThisalignstheImplementationPlanwiththeNationalDevelopmentPlan2030.Itisdeliberatelyintendedtobeambitious,giventheurgencywithwhichProvinceandmunicipalitiesoughttoaddressthelivingconditionsandlivelihoodchallengesofpeoplelivingininformalsettlements.

TheISSFspecifiesthreestrategicobjectives:

1. Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

2. Enhancedqualityoflifeandactivecitizenship

3. Strengthenedsectorcapability,governanceandresources

Eachstrategicobjectivehasasub-setofstrategiestorealisethevisionandmissionoutlinedintheISSF.Foreachstrategy,asetofactionsatprovincialandmunicipallevelisidentified,aimedatachievingspecificoutcomesatmunicipalandsettlementlevelrespectively.Theidentifiedactionsareinterdependentandneedtobeimplementedinparalleltotransforminformalsettlementsintovibrant,resilientanddignifiedneighbourhoodsthatarewellintegratedintothemunicipalfabricandthelocaleconomy.

The Implementation Plan provides a rationale for each action and summarises key milestones to assist in determining whether the action is beingimplemented.Becausetheactionsareinterlinked,italsoindicateshowaspecificactionmaydependon,beenabledby,orrelatetootheractions.Finally,theImplementationPlanassignsresponsibilityforprovincialactionstospecificprovincialdepartments.

WhilsttheISSFandtheImplementationPlanoutlinemanyactionsaimedatguidingprovincialdepartmentsandmunicipalitiestowardsanorientationthatadvances the vision and mission of the ISSF, it should not be interpreted in a minimalist or prescriptive manner. Where there are other, possiblycomplementary,meanstoachievetheintendedoutcomesinamoreeffective,inclusiveandsustainablemanner,theseshouldbepursued.Critically,bothpolitical will and strong leadership across all levels and spheres of government is required to bring about the necessary redirection of resources andpractice.

AlogicmodelunderpinningtheISSFissummarisedindiagram1.Itisintendedtoassistinimplementingtheactionsandmonitorchange.

Page 3: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Diagram1

Page 4: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-39-

1 Prioritiseemergencyandbasicserviceprovision

Provincialactions Rationale Keysteps Linkages Departmentresponsible

1.1 AdvocateforflexiblenormsandstandardsforprovisionofbasicandemergencyservicesasindicatedintheRedBook

Manysettlementsdonothaveaccesstobasicservicesduetorestrictiveengineeringnormsandstandardsasoutlinedintheredbook.Thisactionisinessentialtoachieveahigherlevelofservicesininformalsettlements.

• Conductashortsurveywithselectivemunicipalitiestoidentifyimpedimentstoservicedeliveryrelatingtoengineeringnormsandstandards

Thisactionenablesactions1.4and1.5.

DoHS

• DevelopToRforinfrastructureandtechnologyservicestool• DevelopProvincialengineeringnorms,standardsandrecommendations • Prepareandsubmitbriefingdocumentwithrecommendationsinordertoadvocateforamendingtheredbook

1.2 Developandfinanceatrainingprogrammeformunicipalengineersadvocatingtorevisitmunicipalnormsandstandardby-lawsforservicinginformalsettlements

Manysettlementsdonothaveaccesstobasicservicesduetorestrictivemunicipalby-lawswithregardstoengineeringnormsandstandardsasoutlinedintheredbook.Thisactionisinessentialtoachieveahigherlevelofservicesininformalsettlements.

• Conductasurveywithselectivemunicipalitiestoidentifyspecificstandardsadoptedbymunicipalitiesthatareimpedimentstoservicedelivery

Thisactionenablesactions1.4and1.5.

DoHS

• DevelopProvincialengineeringnorms,standardsandrecommendations• Distributememowithprovincialengineeringnormsandstandardstoallmunicipalities• OrganiseonceofftrainingledbyProvincetargetingmunicipalengineerstoadoptmoreflexibilityinnormsandstandards

Page 5: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-40-

1.3 EngageNationalTreasuryaboutthespecificMFMAprovisionsand/orGRAPstandardspreventingservicingonprivateland

Informalsettlementslocatedonprivatelandareunabletoaccessbasicservices.Thisactionallowsforadvocatingfordeliveringbasicservicestoinformalsettlementsonprivateland.

• Preparealistofallsettlementsthatarelocatedonprivatelandincludingtheageofthesettlement(Usingrapidappraisaldata)

Thisactionenablesactions1.4and1.5.

Provincialtreasury

• Developapreliminarydocumentmotivatingforprovisionofbasicservicesonprivateland• OrganiseaninterdepartmentalmeetingalongwithProvincialTreasurytoexplorelegislativerestrictionsonservicingprivateland• ProvincialTreasurytosubmithighlevelbriefingdocumenttoNationaltreasurymotivatingdeliveryofservicesonprivateland

1.4 Settargetsandprovideoversightonbringingserviceratiosininformalsettlementsuptonationalstandards(particularlyrelatingtoO&Mandindigentgrant)

Therearenoservicedeliverytargetsorpreferredstandardsattheprovinciallevelthatgivescleardirectiontothemunicipalities.

• Distilrapidappraisaldataofcurrentserviceshortfallspermunicipality

Thisactionenablesactions1.4and1.5.Thisactionisdependentonaction11.2.

DoHS

• Identifykeyimpedimentsforservicedeliverypermunicipalityinordertomeetnationalstandards(includinglackofbulkservicesandpooroperationsandmaintenance)• Establishtargetspermunicipalitiestoatleastcomplywithnationalstandards• Distributetargetstoeachmunicipality

Page 6: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-41-

Municipalactions Rationale Keysteps Linkages Departmentresponsible

1.5 Adoptservicedeliverytargetsandimplementservicedeliveryprojectsand‘quickwins’,preferablythroughcommunitycontractorsinasustainablemanner(communalorindividualservices)

Servicedeliveryandcommunityprioritiesarenotaddressedadequatelyinmunicipalplanning.Thisactionallowsmunicipalitiestoimprovebasicservicesininformalsettlements

• Review the rapid appraisal datarelating to community needs/quick wins and provincial targetsforservicedelivery

Thisactionisdependentonactions1.1,1.2,1.3and1.4.Thisactionlinkstoaction7.1.

• Align municipal resources withcommunity priorities andprovincialtargets

• Advertise the implementation oftheprojectinthelocalcommunityandencouragelocalcontractorstoapply

1.6 DevelopandincorporatecommunityactionplansintotheIDPprocessaspertheISSPdesignandtenureoptions

CommunityneedsarenotadequatelyrepresentedandresourcedintheIDPprocess.Thisactionallowscommunity‘quickwin’andlongtermprioritiestobeplanned,budgetedandimplemented.

• Conduct a community ledsettlement level enumeration andmapping to identify communityneeds

Thisactionsupportsactions4.1and6.1.Thisactionlinkstoactions7.6and8.5.

• Package the enumeration,mappingdatawithkeycommunitypriorities as a community actionplan• Circulate the community actionplan across various departmentswithin the municipality and ifneeded to relevant provincialdepartments• Adopt the community action planintotheIDPandallocatenecessaryresources to meet settlementneeds

Page 7: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-42-

2 Strengthenplanningforneighbourhooddevelopment Provincialactions Rationale Keysteps Linkages Department

responsible2.1 Prepareneighbourhood

developmentandcommunityactionplanningstrategyusingNUSPresources

Municipalitiesfocusondevelopinggreenfieldhousingprojects,ratherthantargetinginvestmentsinbuildingstrongerneighborhoodsthatareintegratedintothecity/townfabric.Thisinformationenablesmunicipalitiestodeepenparticipationandreducecommunityprotestwithintheprovince

• CirculateNUSPresourcesonneighborhooddevelopmentandcommunityactionplanning,alongwiththerelatedISSPdocumentstoallmunicipalitiesintheWesternCape.

Thisactionenablesactions2.3,2.4and2.5.Thisactionlinkstoaction14.6.

TheISSPservesasareferencetothisaction.

DoHS

• Organiseregularinterdepartmentalmeetings(preferablyquarterly)toalignresourcesandlong-terminvestmentsinsettlementsinordertoimproveaccesstohealth,education,transport,civicamenitiesandlivelihoodopportunities.

2.2 Disseminate and train municipalofficialsontheprioritisationtool

Municipalitiesoftenstruggletoprioritisekeyinformalsettlementsthatrequireurgentintervention.Thetoolallowsmunicipalitiestoprioritiseinformalsettlementinterventionsandtheprovincetotrackprogress,particularlythemostvulnerablesettlements.

• Circulatetheprioritizationtooltoallmunicipalitiesalongwiththebriefingdocument

Thisactionenablesaction2.6.

DoHS

• Provideonceoftrainingtomunicipalitiestousetheprioritizationtool

Municipalactions Rationale Keysteps Linkages Departmentresponsible

2.3 Prepareplansforallinformalsettlementneighbourhoods,includingcommunityactionsplans,tobeincorporatedintotheIDPinto

Municipalitiesoftendonotincorporatebroaderneedsofthecommunityrelatingtohealth,education,transport,civic

• Preparealistandmapsofallsettlementswithinthemunicipalitybasedontherapidappraisaldata

Thisactionenablesactions2.4and2.5.Thisactionlinkstoactions7.4and

Page 8: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-43-

e amenities,openspaceandlivelihoodinsettlementplanningandIDP’s.Thisactionallowsmunicipalitiestakealong-termperspectivetodevelopmentandpursueanincrementalapproach.

• Organisecommunityforumswithcommunityleaders/eldersandwardcouncillorstoidentifyneedswithinthebroaderneighbourhoodplanwithaparticularfocusonaccesstohealth,education,transport,civicamenities,openspaceandlivelihoodopportunities

14.6.

• IncorporateallneighbourhoodplansintotheIDP• CirculatethedocumenttoProvincebringingvariousaspectstotheattentionofrelevantdepartments

2.4 Identifyandplanfornewsettlementformationwithinexistingneighbourhoodsbasedonexpectedgrowth

Municipalitiesareunabletomanagepressuresofurbanisationandin-migration.Thereisaneedforproactiveandforwardplanningtoaccountforgrowthandurbanisation.

• DevelopalandownershipinventoryofalllandincludedinthecurrentSDF

Thisactionisdependentonactions3.2,3.3,3.4,3.5and3.6.

• Earmarkwelllocatedlandforhumansettlementdevelopment,usingthelandinventorydatabase,avoidingfloodplainsandenvironmentallysensitiveareas• Servicelandinordertoproactivelymanagein-migration

2.5 Applyprioritisationtoolalongwithitweightingcriteriaforallinformalsettlementsinordertoprogrammeinterventions

Municipalitiesoftenstruggletoprioritisekeyinformalsettlementsthatrequireurgentintervention.Thetoolallowsmunicipalitiestoprioritiseinformalsettlementinterventionsandtheprovincetotrackprogress,particularlythemostvulnerablesettlements.

• Createaweightingsystemwithinthemunicipality

Thisactionislinkedtoaction2.2andrelatestothePrioritisationModel.

• Seekcouncilapprovalontheweightingsystem

• Implementandutilisetheprioritisationmodel

Page 9: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-44-

3 Unlockpublicandprivatelandassetsthataresuitablefordevelopmentandservingthelivelihoodneedsofthecommunity

Provincialactions Rationale Keysteps Linkages Departmentresponsible

3.1 Fasttrackfundingandapprovalsforsettlementupgradingprojectsthatactivelydevelopwelllocatedlandinwellestablishedneighbourhoods

Projectsthatactivelytargetwell-locatedlandandareinnovativeandprecedentsettinghavelongapprovalperiods.

• Identifyallsettlementprojectsonthepipelineandbusinessplan

Thisactionenablesaction1.5.

DoHSandDEADP

• Shortlistsettlementprojectsthatareactivelytargetingneighbourhooddevelopmentonwelllocatedlandwithstrongcommunityparticipation• Circulatelistofshortlistedprojectsacrossthevariousdepartmentsintheprovince• Fasttrackprovincialapprovalsandfundingforshortlistedprojectsthroughvariousdepartments

3.2 Developalandreleasestrategyregardingtheoptimaluseofland,incollaborationwithHDA

Inmanyinstances,welllocatedlandinmunicipalitiesisownedbyotherspheresofgovernmentorparastatalsandcannotbereleasedforhumansettlementdevelopment

• Prepareaguidingdocumentthatexplainstheimperativeoflandreleasefromvariousspheresofgovernment

Thisactionenablesaction2.4.

HDA+DoHS

• OrganiseaseriesofmeetingsandworkshopswithHDAtoagreeonlandreleasestrategy• Preparealandreleasestrategydocument

• Circulatethedocumenttomunicipalities

Page 10: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-45-

Municipalactions Rationale Keysteps Linkages Departmentresponsible

3.3 Releasewelllocatedlandforhumansettlementdevelopment

Welllocatedin-situandgreenfieldlandisseldomutilisedforhumansettlementdevelopmentandoftenusedforprivatedevelopments.Thereisaneedtointegrateinformalsettlementneighborhoodsintothetownfabricavoidinglandwithnaturalhazards.

• DevelopalandownershipinventoryofalllandincludedinthecurrentSDFandwithintheurbanedge

Thisactionenablesaction2.4.

• Earmarkandreleasewelllocatedin-situandgreenfieldlandforhumansettlementdevelopment

3.4 Developwelllocatedlandlocatedinestablishedneighbourhoodsforlowincomehousingandotherpublicamenities

ManymunicipalitiescontinuetodevelophumansettlementprojectsontheoutskirtsofthemunicipalboundariesoroutsidethecurrentSDF,furtherreinforcingtheapartheidspatialorder.

• DevelopalandownershipinventoryofalllandincludedinthecurrentSDFandwithintheurbanedge

Thisactionenablesaction2.4.

• Implementtheservicingofsuchland• Directotherprovincialresourcesandprogrammesrelatingtohealth,education,transport,civicamenities,openspaceandlivelihoodwiththeintentiontostrengthenneighbourhooddevelopment

3.5 Identifyanddevelopnewparcelsoflandwithinestablishedneighbourhoodsfornewsettlementformationwiththeintentforspatialintegration

Thisactionenablestheproactivemanagementofgrowthandin-migration.

• DevelopalandownershipinventoryofalllandincludedinthecurrentSDFandwithintheurbanedge

Thisactionenablesaction2.4.

• Identifyanddevelopnewparcelsoflandwithinestablishedneighbourhoodsfornewsettlementformationwiththeintentforspatialintegration

Page 11: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-46-

4 Enablealternativeformsoftenuresecurity

Provincialactions Rationale Keysteps Linkages Departmentresponsible

4.1 Developandoperationaliseprovincialguidelinesonincrementaland/oralternativetenureoptions

Tenurerightsarecriticalforinformalsettlementsandthecurrentformoffreeholdtitleisexclusionaryandlimiting.Municipalitieswillbenefitfromalternativeformsoftenurewillallowforincrementalupgrading.

• Inconsultationwithprovinciallegaldepartment,prepareabriefingdocumentontenureoptionsbasedonISSPandNUSPguidelines

Thisactionenablesactions4.3and4.4andlinkstoaction14.1.

DoHS

• Circulatebriefingdocumenttomunicipalities• InviteNUSPtoworkshoptenureguidelinesataPUSPmeeting• Basedonthebriefingdocument,prepareaToRforamunicipaltrainingprogramme

Municipalactions Rationale Keysteps Linkages Departmentresponsible

4.2 ProvideformoftenuretoinformalsettlementresidentsincategoryAandB1settlements

SettlementslocatedoncategoryAandB1donothavetenurerightsandthus,cannotusetheirownresourcestodeveloptopstructure.

• Basedonprovincialbriefingdocument,discussandagreeonappropriatetenureoptionswithcommunityleadership/membersandwardcouncillors

Thisactionisdependentonaction4.1.

• ImplementtenurerightsforcommunitymembersresidingincategoryAandB1settlements

4.3 ProvidealternativeformsoftenuretoinformalsettlementresidentsincategoryB2andCsettlements

SettlementslocatedoncategoryB2andCareearmarkedforrelocationbutnoalternativeformoftenureisofferedtothem.

• Basedonprovincialbriefingdocument,discussandagreeonappropriatetenureoptionswithcommunityleadership/membersandWardCouncillors

Thisactionisdependentonaction4.1.

• ImplementtenurerightsforcommunitymembersresidingincategoryB2andCsettlements

Page 12: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-47-

5 Resettlepeopleselectivelywithappropriatechoiceswithinamunicipalwidedevelopmentframework

Provincialactions Rationale Keysteps Linkages Departmentresponsible

5.1 Prepareprovincialguidelinesforrelocatingcommunitiesfacingserioushazardsandrisksanddecantingfromhigh-densitylocations

Settlementsthatneedtoberelocatedoftenduetoseverehazardsorrisksarerelocatedwithoutadequatelyunderstandingthesocio-economicimpactsonthecommunities.Resettlementcanbedoneinaparticipatoryandtransparentmannerinordertoreduceconflictandstrife.

• Prepareaprovincialguidelinesdealingwithrelocationsincludingclearrationalewhythesettlementisbeingrelocated,doesthewholesettlementneedtoberelocated(oronlypartially),jointlyidentifylandwithcommunities,identifytransportneedsandpossiblecompensationandanyotherpostrelocationsupport.

Thisactionlinkstoactions2.2and4.2.

DoHS

Municipalactions Rationale Keysteps Linkages Departmentresponsible

5.2 Engageaffectedsectionsofcommunitiesthathavetoberelocatedasperprovincialguidelinesandimplementsuchrelocations

Settlementsthatneedtoberelocatedoftenduetoseverehazardsorrisksarerelocatedwithoutadequatelyunderstandingthesocio-economicimpactsonthecommunities.Resettlementcanbedoneinaparticipatoryandtransparentmannerinordertoreduceconflictandstrife.

• Identifyjointlywithcommunityresidentsreasonswhythesettlementorsectionsthereofhastoberelocated

Thisactionlinkstoactions2.5and4.3.

DLG+DEDAT

• Establishaprocessofjointlandidentificationwithcommunityresidentswithregardstoproximitytohealthfacilities,schoolsandemploymentopportunities• Identifythetransportneedstotheidentifiedrelocationsite• Debateanddiscusscompensationforrelocatingandresettlingcommunities,ifany• Ensureappropriatepostrelocationsupporttocommunities

Page 13: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-48-

6 Supportincrementalandaffordablehousingopportunitiesforpeoplelivingininformalsettlements

Provincialactions Rationale Keysteps Linkages Departmentresponsible

6.1 Advocateforflexiblenormsandstandardsregardingstandsizesandbuildingregulationsforincrementalhousing

Thisactionenablesmunicipalitiestoadoptflexiblestandsizesandbuildingregulationsthataremoresuitableforincrementalandselfbuilddevelopments.

• Provincetoprepareaguidingdocument(suggestingflexiblenormsandstandards)includingmultiplecriteriabutnotlimitedtodensities,potentialtoreorganisethespacebetter,alternativelandavailability,consultationandpreferenceofcommunityresidents,minimizerelocationsanddisruptionstocommunityresidents

Thisactionlinkstoactions1.1and7.1.

DoHS

6.2 OperationaliseinnovativemodelsforhousingconsolidationandtransitionalhousingmodelsemergingfromtheCCDIBLCreportandISSP

Newformsofincrementalhousingareneededtomoveawayfromcurrentparadigmoflowdensitysubsidisedhousing.

• CirculatetheISSPdesignandtenureoptionstoallmunicipalities

Thisactionissupportedbyaction7.1andlinkstoaction14.1.

DoHS

• CirculateBetterLivingChallenge(BLC)casestudiestomunicipalities• OrganiseaPUSPsessiontotrainmunicipalitiesinadoptinginnovativemodelsofhousingconsolidation

6.3 Seeklegaladviceonhousingconsolidationfornon-qualifiers

ThereisambiguitywithintheUISPdocumentthatneedstoberesolvedtofindsolutionsfornonqualifiers.

• OrganisemeetingwithNUSPandprovinciallegaldepartmentwithregardstononqualifiersforsubsidywithregardstoUISPproject

DoHS

• Circulateabriefingdocumentanddirectivetoallmunicipalities

Page 14: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective1:Upgradesettlementsthroughaccesstoland,services,publicinfrastructureandincrementalhousingopportunities

-49-

Municipalactions Rationale Keysteps Linkages Departmentresponsible

6.4 Establishamunicipalresourcecentretoassistcommunitiesincapacitydevelopment,selfbuildandaccessingfinanceandplanapprovals

Bureaucraticredtapecausesinefficiencies,includingdelaysinregistrationandimplementation,andcanbecostly,particularlyforsmallcontractorsandbusinesses.A‘one-stop-shop’canofferadviceandsupporttofast-tracktheregistrationprocess.

• Developthescopeforamunicipalresourcescentre

Thisactionissupportedbyaction7.4.

• Identifyfinancialandhumanresourcerequirements

• Identifyasuitablelocation/buildingforthecentretooperatefrom

Page 15: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective2:Enhancedqualityoflifeandactivecitizenship

-50-

7 Supportlocalentrepreneurismandlivelihoodstrategies

Provincialactions Rationale Keysteps Linkages Departmentresponsible

7.1 ConductSupplierDevelopmentWorkshops(compliance/registration)withlocalserviceproviders

Usinglocalcontractorsandserviceprovidersenhancesthelocaleconomyandlivelihoodstrategies.Thereareresidenthomebuildingandextensioncontractorsinallmunicipalities,althoughtheymaynotalwayshavetherequisiteknowledge,skillsandbusinessacumen(e.gofregulations,programmes,materialsestimationandmanagement,basicbusinessmanagement).

• Conductasamplesurveyoflocalcontractorstoassessavailableknowledgeandcapabilities(andgaps)

Thisactionislinkedtoactions6.2,6.5and7.3.

DoHS+DEDAT

• DevelopaTORforatoolkittocapacitatecommunitycontractors

• SubmitanapplicationforEPWPfundingtofinancecontractortraining

• Providetrainingofcommunitycontractors,basedonthetoolkit

7.2 IncorporateneighbourhoodplanningintoLED/IDPAssessmentFramework

Residentsofinformalsettlementsengageinarangeoflivelihoodstrategiestogenerateincomeandgetby.Upgradingstrategiesneedtostrengthen,ratherthanundermine,theselivelihoodstrategies.Municipalitiesneedguidanceonhowtoincorporateaneconomicandlivelihoodsperspectiveintosettlementandneighbourhoodplanning.

• ReviewtheprovincialLEDStrategytoidentifystrategicactionsforinformalsettlementsandupgradinginitiatives

Thisactionneedstoinformactions2.1,2.3and2.4andenablesactions7.6and7.7.Itcouldbelinkedtoaction7.2.

DEDAT+DLG

• DraftaguidancenoteformunicipalitiesonlinkingLEDintosettlement/neighbourhoodplanningandIDP

DEDAT+DLG

7.3 Incorporateprovincialfoodsecuritystrategyactionsintoneighbourhoodplanningguidelines

Foodinsecurityandmalnutritioncontinuetobeprevalentininformalsettlements,whichcanbeaddressedinaproactivemanneriftakenintoaccountaspartofupgradinginterventions.

• DevelopaguidancenoteformunicipalitiesonincorporatingrecommendationsfromtheProvincialFoodSecurityStrategyintosettlement/neighbourhoodplanningandIDP

Thisactionlinkstoaction2.1andcouldbelinkedtoaction7.2.

DoP+DoHS

Page 16: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective2:Enhancedqualityoflifeandactivecitizenship

-51-

Municipalactions Rationale Keysteps Linkages Departmentresponsible

7.4 Incorporateprovinciallocaleconomicdevelopment(LED)andfoodsecuritystrategyactionsintoneighbourhoodplanninglinkedtotheIDP

Residentsofinformalsettlementsengageinarangeoflivelihoodstrategiestogenerateincomeandgetby.Upgradingstrategiesneedtostrengthen,ratherthanundermine,theselivelihoodstrategies.Municipalitiesneedtoincorporateaneconomicandlivelihoodsperspectiveintosettlementandneighbourhoodplanning.

• DiscusstherecommendationsfromtheprovincialguidancenotesonLEDandfoodsecuritywithcommunityforums• IncorporatelocallyappropriateactionsintotheneighbourhoodplansandIDP

Thisactionisdependentonactions7.2and7.3.Itislinkedtoaction2.3.

7.5 Createadatabaseoflocalcommunitybasedcontractorsandorganisationsthatcanimplementinformalsettlementprojects,withappropriateregulationsspecificallylabourlaws

Municipalitiesareoftennotfullyawareoftheresidentskillsandcompetenciesintheirlocalitythatcanassistininformalsettlementprojectsand/orhomebuilding.Adatabasecanspeedupthecontractingprocess,withbetterresultsforthemunicipalityandsettlement(s)concerned.

• Developaregistrationtool• Setupandmanagethedatabase

Thisactioncansupportaction7.1andislinkedtoaction7.4.

7.6 Establishamunicipalresourcescentretoassistbusinessesandlocalcontractorswithregistration

Bureaucraticredtapecausesinefficiencies,includingdelaysinregistrationandimplementation,andcanbecostly,particularlyforsmallcontractorsandbusinesses.A‘one-stop-shop’canofferadviceandsupporttofasttracktheregistrationprocess.

• Developthescopeforamunicipalresourcescentre• Identifyfinancialandhumanresourcerequirements• Identifyasuitablelocation/buildingforthecentretooperatefrom

Thisactioncanbelinkedtoaction6.6andisrelatedtoactions6.2and6.5.

7.7 CreateadatabaseoflocalenterpriseandSMMEsinthemunicipality

Municipalitiesareoftennotfullyawareofthelocalbusinessesactiveintheirlocality,whichhinderstheirabilitytodesignsuitablesupportiveinterventions.

• Developaregistrationtool• Setupandmanagethedatabase

Thisactionislinkedtoaction7.6.

Page 17: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective2:Enhancedqualityoflifeandactivecitizenship

-52-

7.8 Recogniseinformaleconomicactivityundertheland-useschemeandimprovethemoverthelongterm

Landusemanagementandplanningschemes,suchaszoning,canhaveanenablingorunderminingimpactonlocaleconomicactivities.

• Usetheprovincialguidancenotetodeveloplocallyappropriateprojectsandprogrammes• Conductanassessment/surveyofhowthelanduseschemeimpedes/supportslocaleconomicactivity• Reviewandreviseby-lawsandzoningschemeswithaneyeonenablinglocaleconomicactivity

Thisactionissupported/enabledbyaction7.2andlinkedto7.5.

7.9 Supportlocalfoodproductionandfoodsecuritythrough,amongstothers,LEDprogrammes

Foodinsecurity,hungerandmalnutritionareveryhighininformalsettlements.Municipalitiescansupportpeopleingrowingfood(incl.incommunalgardens),supportcommunityserviceorganisationsthatofferrelief(e.g.throughfoodkitchens,crèchesorhome-basedcare)andcreateincentivesforlocalfoodproducerstooffernutritiousfood.

• Usetheprovincialguidancenotetodeveloplocallyappropriateprojectsandprogrammes(including,amongstothers,supportforcommunityserviceorganisations,localfoodproductionandfoodpreparation)

Thisactionissupported/enabledbyactions7.3and7.2.

Page 18: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective2:Enhancedqualityoflifeandactivecitizenship

-53-

8 Promoteholistichumandevelopmentwithafocusonyouthdevelopmentandsocialcohesion

Provincialactions Rationale Keysteps Linkages Departmentresponsible

8.1 Provideaccuratedata,researchandanalysistomunicipalitiestohelpthemplanforgrowthindemandofsocialserviceslikeeducation,trainingandhealth

Informalsettlementupgradinghastoaddresssocialandhumandevelopmentdimensions.Municipalitiesrelyonprovincialgovernmenttoprovidethenecessaryinformationandresourcestoensurethatthesedevelopmentdimensionsareadequatelyaddressed.

• Developandupdatesectorplansregardingplannedfacilitiesandservicesandsharewithmunicipalities(forinclusionintheIDPandSDF)

Thisactionneedstoinformactions2.1,2.3and2.4.

DSD,withDoHandWCED

8.2 Incorporateprovincialsocialdevelopmentstrategyactionsintosettlementandneighbourhoodplanning

Municipalitiesneedguidanceonhowtoincorporateasocialdevelopmentperspectiveintosettlementandneighbourhoodplanning,basedontheprovincialstrategy.

• ReviewtheprovincialSocialDevelopmentStrategytoidentifystrategicactionsforinformalsettlementsandupgradinginitiatives

Thisactionenablesactions2.3and2.5andcansupportaction8.5.

DHS

• Draftaguidancenoteformunicipalitiesonincorporatingsocialdevelopmentactionsintosettlement/neighbourhoodplanning

8.3 Prioritiseandsupportneighbourhoodwatchesininformalsettlements,linkedintocommunitypolicingforumsand/orcommunitysafetyforums

Crimeandsafetyconcernsareoftenveryhighininformalsettlements.Toaddressthese,thepoliceneedstoworkwithlocalcommunityrepresentativeswhocanbemoreeffectiveinreducingcrimeandviolenceintheircommunities.

• Offertrainingandequipmenttoneighbourhoodwatches

Thisactionlinkstoaction8.7andcansupportaction8.5.

DCS

• IdentitymunicipalitiesthatdonotyethaveacommunitypolicingforumandworkwithlocalstationcommanderinestablishingaCPF

DCS

• Developandofferatrainingcourseforcommunitypolicingforums/communitysafetyforums

DCS

8.4 OperationalisetheMODProgrammeacrossallmunicipalitiestotargetyouthprogrammes

Youthareavulnerablepopulation,facingtheriskofschooldropout,unemployment,exposuretocrimeandgangs,amongstothers.

• ExpandtheMODProgrammeacrossallmunicipalities

Thisactionrelatestoaction8.6andcansupportaction8.5.

DCAS

Page 19: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective2:Enhancedqualityoflifeandactivecitizenship

-54-

Municipalactions Rationale Keysteps Linkages Departmentresponsible

8.5 Developamunicipalprogrammeofaction,includingtheestablishmentofahelpdesk,toaddresssexism,xenophobiaandintoleranceusingEPWPprogrammeinpartnershipwithlocalNGOs

• Conveneameetingwithlocalserviceproviders,interestgroups,NGOsandEPWPprogrammetodiscussaprogrammeofaction

Thisactioncansupportaction8.7.

• Agreeonrolesandresponsibilitiesforprogrammeimplementation• Identifysuitablevenues(possiblyownedbythemunicipality)forhelpdesktooperatefrom

8.6 SupporttherolloutoftheMODProgrammeinordertopromoteyouthdevelopment

AlthoughtheMODCentresareestablishedandsupportedbyDCASandareusuallybasedatschools,municipalitiescanhelpidentifysettlementsthatarenotyetcoveredbytheMODProgrammeandcanalsomakemunicipalvenuesavailable.

• MapinformalsettlementswheretheMODProgrammeisnotyetactiveandcanberolledout

Thisactionlinkstoaction8.4.

• IdentifysuitablevenuesownedbythemunicipalityforMODCentrestooperatefrom

8.7 ConnectallcommunityforumstoSAPSandensurethatSAPSparticipatesinthequarterlysettlementpartnershipmeetingswithcommunityandmunicipality

DirectcommunicationandlinkagebetweencommunityforumsandSAPSisvitaltoensurerapidresponsestocrimeandviolenceandtoimprovesafety.

• Convenequarterlycommunityforumsfocusingonsafetyandcrimeprevention• InvitelocalSAPStoquarterlymeetings• Documentthemeetingsandagreementsmade

Thisactionlinkstoaction8.3andcansupportaction8.5.

Page 20: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective2:Enhancedqualityoflifeandactivecitizenship

-55-

9 Supportandenhancecitizencapabilityinplanning,decisionmaking,implementationandmonitoring

Provincialactions Rationale Keysteps Linkages Departmentresponsible

9.1 Develop,implementandresourceaprogrammeofcommunitycapacitydevelopmentandactionplanninginpartnershipwithintermediaryorganisations

Intermediaryorganisationsoftenhavetriedandtestedapproachestocommunitycapacitydevelopmentandpre-existingrelationshipswithcommunityrepresentatives.

• Scanexistingtrainingprogrammesandmaterialsoncommunityplanning

Thisactionsupportsactions2.3and2.5.

DoHS

• Developacurriculumforthecapacitydevelopmentprogramme

DoHSwithDoLG

• Pilottheprogrammeandevaluate/revise

DoHSwithDoLG

• Developafundraising/resourcemobilisationstrategyfortheprogramme

DoHSwithDoLG

9.2 Providetrainingtocommunityleadersincludingcouncillorsandwardcommitteesregardingtheinstitutionalframeworkforhumansettlements

Communityleadershipisoftennotfullyinformedabouttheinstitutionalframeworkforhumansettlements,whichmeansthattheyareunabletoprovidecommunitieswithcorrectinformationandguidance.

• Developatrainingprogrammeforcommunityleadership,councillorsandwardcommittees

Thisactioncancomplementaction9.1.Itcansupportaction9.4andenableaction9.5.

DoHSwithDoLG

• Rolloutthetrainingprogrammeinmunicipalitiesacrosstheprovince

DoHSwithDoLG

9.3 InconsultationwithDPME,developandimplementacitizen-basedmonitoring(CBM)approachtoinformalsettlementupgrading

Theroleofcommunitiesinmonitoringprogressandresultsisvital.TheDPMEhasacitizen-basedmonitoringprogramme,whichhasnotyetbeenappliedtothehumansettlementscontext.

• SetupanengagementwiththeDPMEtodiscusshowCBMcanbetakenforward

Thisactioncanbelinkedto9.4.

• DevelopaToRforaserviceprovidertosupportthedevelopmentofaCBMpilot• Pilottheapproachinatleast2sites

Page 21: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective2:Enhancedqualityoflifeandactivecitizenship

-56-

Municipalactions Rationale Keysteps Linkages Departmentresponsible

9.4 EstablishaninterdepartmentalquarterlypartnershipmeetingthroughIDPandwardforumswitheachinformalsettlement

Quarterlymeetingsbetweendifferentmunicipaldepartmentsandcommunityforumscangreatlyenhancecommunication,communityoversightandoptimisationofsettlementresources.

• PrepareaCouncilresolutiontoensuredepartmentalcommitmentandparticipation

Thisactioncanbesupportedthrough(andinturnsupport)action9.3.Itcanbesupportedbyaction9.5.

• Draftastandardmeetingagenda• Identifyandinviteparticipants• Minutethemeetingsanddecisionstaken

9.5 AllocateresourcesforeachsettlementinthebudgetingprocessandsharethisinformationwithsettlementCBOsandleaders

Transparencyregardingresourceallocationforsettlementdevelopmentiscriticaltoensureinformedengagementwithcommunitystructuresandeffectiveutilisationofresources.

• PrepareaCouncilresolutionregardingtheamount/proportionoffundsallocatedtoeachsettlement

Thisactionislinkedtoaction9.4.

• Summarisethebudgetinformationinasimplifiedmannerfordisseminationtocommunityrepresentatives.• Discussresourceallocationandutilisationatthequarterlypartnershipforum

9.6 Convenecommunitytrainingprogrammesonlegislation,policy,by-laws,planningandbudgetprocesses

Communityrepresentativesneedtounderstandthelegislative,institutionalandregulatorycontextoflocalgovernmenttoenablethemtobeeffectiveintheirengagementwithmunicipalitiesondevelopmentmatters.

• Developatrainingprogrammeforcommunityrepresentativesandcommunitystructures

Thisactioncansupportmostothermunicipalactions,mostnotably1.6,2.3,2.4and2.5.

• Identifyparticipants• Implementthetrainingprogramme

9.7 Conductamunicipalwidecommunityledrapidappraisaltomonitorandoverseeimprovementsatasettlementlevel

Arapidappraisalisaneffectiveparticipatorytooltoassessservicesanddeliveryprogressthatallowthemunicipalitysolveproblemsmorequickly.Italsogeneratesasenseofownershipofdevelopmenteffortsinthecommunity.

• Review,ifnecessaryrevise,thesurveyusedfortheprovincialrapidappraisalofinformalsettlementsin2016

Thisactioncansupport/informactions2.3,4.3,4.4,5.3,7.6and7.7.Itislinkedto/enabledbyaction14.2and14.4.

• Offertrainingandequipmenttocommunitystructuresthatcanconducttherapidassessment• Collateandreviewthefindingstoinformappropriateresponses

Page 22: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective2:Enhancedqualityoflifeandactivecitizenship

-57-

10 Shiftmindsetsingovernmentandsocietytowardsrecognisingcommunityagencyandcivicresponsibility

Provincialactions Rationale Keysteps Linkages Departmentresponsible

10.1 Developandimplementalearningprogrammeonparticipatoryandincrementalsettlementdevelopmentforlocalgovernmentofficialsprogrammes(includingsitevisits,peerlearningandpairing/twinningofmunicipalities)

Participatoryandincrementalsettlementdevelopmentrequiresadifferentmind-setandapproach.Municipalofficialstendtolearnbestfrompeersandfrompractice(asopposedtoaprescriptiveapproachthatseekstoinstilcompliance).

• DevelopaTORforacomprehensiveadultlearningprogrammeonparticipatoryandincrementalsettlementdevelopment

Thisactionenablesaction10.4andsupportsmostotheractions.

DoHS,DoLGandDoP

• Sourceserviceprovider(s)todesignandsupport/implementthemulti-facettedlearningprogramme• Identifypartners/serviceprovidersforimplementationofprogrammecomponents• Implement&evaluateprogrammecomponents

10.2 Developknowledgeproductsthatpromotethevalueofcommunityagencyandcivicresponsibility

Municipalitiesdonotnecessarilylackthewillingnesstoworkwithcommunities,butoftendonotknowhowtoinitiate,supportorsustaincivicinvolvement.

• DevelopaTORforrelevantproductdevelopment(themesortopics,format,frequency,targetanddistribution)

Thisactioncansupport10.1andmostotheractions.

DoLGandDoHS

• Developandmonitorproductdevelopmentstrategy

10.3 Recognisewellperformingmunicipalitiesandcommunityparticipationthroughanannualawardforneighbourhooddevelopment

Recognisinggoodpractice(and/orthewillingnesstotryoutnewapproachesandlearnfrommistakes)caninstilbehavioural/institutionalchange.

• Developcriteriatoevaluatepractice Thisactionsupportsactions10.1and10.2.Itsupportsmostotheractions.

DoPwithDoHSandDoLG

• Developacallfornominations• Setupareviewpanel• Organiseanawardceremony• DevelopandimplementaPR&communicationstrategy

Page 23: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective2:Enhancedqualityoflifeandactivecitizenship

-58-

Municipalactions Rationale Keysteps Linkages Departmentresponsible

10.4 Municipalitiestoparticipatein‘pairing/twinningprogrammes’(offeredbyprovince/otherstakeholders)thatallowforsharedlearningonparticipatoryandincrementalsettlementdevelopment

Municipalofficialstendtolearnbestfrompeersandfrompractice(asopposedtoaprescriptiveapproachthatseekstoinstilcompliance).

• Applyforatwinningprogramme Thisactionisenabledby10.1.

• Whereappropriate,identifycommunityrepresentativestojointhelearningexchange• Participateinrelevantactivities• Reportbackandsharelessonslearned

10.5 SupportCSOsinhostingdialoguesbetweenmunicipalofficialsandcommunitymemberstomanageconflictsandincreaseparticipation

Settlementdevelopment,likeanyotherdevelopmentintervention,islikelytoinvolvecontestationandconflict.Relationshipsofrespectandtrustarecriticalinminimisingthenegativemanifestationsandconsequencesofcontestation.CSOsoftenfulfiltherolesofintermediaries.

• DevelopaTORforadialogueprogramme

Thisactionsupportsmostotheractions,mostnotably2.3-2.5,4.3,4.4and5.2.

• IdentifyqualifiedCSOsforprogrammeimplementation• Identifyparticipantsandensuretheirparticipation(especiallyofmunicipalofficials)

10.6 Documentbestpracticesinmunicipalareasthatimprovecitizenshipandqualityoflifeofcommunitiesininformalsettlements

Government/municipalitiesarenotalwaysgoodatdocumentingpractices,lessonsandmistakesforinternal/peer/externallearningandreplication.

• Developaproductdevelopmentandcommunicationstrategy

Feedsintoactions10.2and10.3.

• Developtemplatesforknowledgeproducts• Secureatexteditortoreviewknowledgeproducts• Applybasicdesignanddisseminate

Page 24: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective3:Strengthenedsectorcapability,governanceandresources

-59-

11 Makeadequateandappropriatefinancialresourcesavailableforinformalsettlementupgrading

Provincialactions Rationale Keysteps Linkages Departmentresponsible

11.1 ConveneanannualNeighbourhoodInvestmentForumwithprivatesectordevelopers,civilsocietyandfinanceinstitutionsinordertoidentifyfinanceandinvestmentopportunitiesinneighbourhooddevelopment

Non-stateactorscanbringvaluableexpertiseandresourcestobearthatcanleadtomoreinclusiveandeffectivedevelopmentsolutions.Conveningaregularforumenablesjointproblem-solvingandbuildsmutuallyconstructiverelationships.

• Developaconceptnotedeterminingtheobjectives,scope,intendedoutcomesandagendaoftheforum

Thisactioncanresultin/contributetoaction11.6andenhanceaction11.7.

DoHSwithDoPandPT

• Preparediscussiondocumentonexpenditure&financerequirementsforneighbourhooddevelopment• Organiselogistics

11.2 RedirectprovincialbudgetallocationinfavourofUISP

Thebudgetisavitaltoolinshiftingprovincialandmunicipalapproachesfromgreenfieldsprojectstoupgradingprojects,whichallowsformorehouseholdstobeservicedand,overtime,integratedfullyintothemunicipalfabric.TheunderutilisationoftheUISPneedstobeaddressed.

• DevelopanearlywarningmonitoringsystemregardingUISPunderexpenditure

ThisactioncouldenablemostactionsoutlinedintheISSFandimplementationplan.

DoHS

• ReallocateresourcesfromIRDPtowardsUISPinaccordancewithsettargetsforupgrading

DoHS

11.3 NegotiatewithNDoHSwithregardstoreviewofgrantconditionsandperformancemanagement

Inflexiblegrantconditionslimitmunicipaldiscretiontowardscontextuallyappropriate,yetprogressiveandlasting,solutions.

• Developaconceptnoteonblockages/restrictivegrantconditions

DoHS

• SetupmeetingwithNDoHStodiscusstheidentifiedblockagesandproposedsolutions

11.4 Implementaperformancemanagementsystemthatallowstopupfundingordiscretionaryinnovationfundingforbetterperformingmunicipalities

Positiveincentivescanbemoreeffectiveinchangingmindsetsandpracticethancompliance-oriented(and/orpunitive)approaches.

• Developcriteriaandoutcome-basedindicatorstoqualifyfortopup/discretionaryfunding

Thisactioncouldbelinkedtoaction3.1.

DoHS

• DevelopaTORforareview(ofapplications)andmonitoringsystem• Advertisetheincentive-basedsystemanditsuptake

Page 25: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective3:Strengthenedsectorcapability,governanceandresources

-60-

11.5 Developanexpendituremonitoringsystemtomonitorbudgetallocationandexpenditureoninformalsettlementupgrading

Municipalandprovincialbudgetingandexpenditureoninformalsettlementupgradingneedstobetrackedtoensurethatfundsareutilisedasintendedandnotdivertedtootherhumansettlementprogrammes.

• Developthetechnicalspecificationsoftheexpendituremonitoringsystem,clarifyingwhichdataisrequiredandwhichdepartment/unitwillbeassignedresponsibilitytoimplementit

Thisactionislinkedto,andcanenableaction11.7.Itcanalsobelinkedtoactions8.2,8.3and8.4.

DoHS

11.6 Prepareguidelinesformunicipalitiesforleveragingprivatesectorfunding

Thefinancialcontributionoftheprivatesectorremainsunderexploredandunderutilised.Municipalitieswouldbenefitfromguidanceonco-financingandcrowdsourcingmechanisms.

• Discusspossibilitiesforco-financingandcrowdsourcingattheannualNeighbourhoodInvestmentForum

Thisactionlinkstoaction11.1.

DoHSwithPT

• Distilguidelinesanddisseminate

Municipalactions Rationale Keysteps Linkages Departmentresponsible

11.7 Prepareafinancialplanforamunicipalinformalsettlementupgradingprogramme

Incrementaldevelopment(beyondprovisionofsitesandservices)requiresafinancialplanlinkedtothestrategicandspatialdevelopmentplansofthemunicipality.Afinancialplancanalsobringinthecontributionofotheractors(public/private/households).

• Developafinancialplanbasedonidentifiedneeds,setprioritiesandtargets

Thisactionislinkedtoaction11.5

• Consultaffectedcommunitiesandpossibleco-financiersinpublic/privatesector• AlignfinancialplanwithIDPandSDF• GetCouncilapproval

11.8 Developmunicipalguidelinesforleveragingprivatesectorfunding

Thefinancialcontributionoftheprivatesectorremainsunderexploredandunderutilised.

• Useprovincialguidelinestodevelopguidelinesthatsuitthemunicipalcontextandrealities

Thisactionlinkstoaction11.6.

Page 26: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective3:Strengthenedsectorcapability,governanceandresources

-61-

12 Expandtheroleofmicro-financeandcommunityfinanceforhousingconsolidation

Provincialactions Rationale Keysteps Linkages Departmentresponsible

12.1 Engagefinanceinstitutions,NGOsanddonorstoincentivisecommunitysavingsschemesasameanstoaccessfinanceforimprovingshelter

Communitysavingsschemeshaveproveneffectiveasaco-financingmechanismthatenhancesasenseofprideandownershiprelatedtoshelterimprovements.Communitysavingsschemescanbegreatlyadvancedthroughseedcapitalandresourcesforfundmanagementfromexternalsources.

• Developaconceptnoteoncommunitysavingsschemesininformalsettlementupgrading,basedonlocal/globalpractice

Thisactionsupportsstrategy6andparticularlyaction6.3.

DoHS

• Convenemeetingstodiscusstheconceptnoteandoptions• Technicaldesignoffund(s)

12.2 Developguidelinesforincentivessuchastenure,services,asperISSPdesignandtenureoptions,inordertoenablecommunityresidentswillingandabletofinancetheirownshelterimprovements

Residentsaremorelikelytoinvestinshelterimprovementswhentheyhavetenuresecurityandservicesandinfrastructureimprovementsareevident.Municipalitiescanofferdifferentincentivesinthisregard.

• Developscenarios/incentivemodels,basedonglobalandlocalpractice

Thisactionenablesaction12.5andcanbelinkedtoaction4.1.

DEADP

Page 27: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective3:Strengthenedsectorcapability,governanceandresources

-62-

Municipalactions Rationale Keysteps Linkages Departmentresponsible

12.3 Offertechnicalsupporttocommunitiesininformalsettlementsthroughamunicipalresourcecentre

Whilstencouragingself-build,municipalitiesremainresponsibleforadherencetobasicbuildingregulationssafetyrequirements.Thehousingsupportcentrecanbeaone-stopshoptoadviseresidentsandhomebuildersoftheserequirements.

• Developthescopeforamunicipalresourcescentre

Thisactionsupportsstrategy6(seealsoaction6.4).

• Identifyfinancialandhumanresourcerequirements• Identifyasuitablelocation/buildingforthecentretooperatefrom

12.4 Review/reviseby-lawsthatactasanimpedimenttohouseholdincomegenerationandinvestmentinhomeimprovements

Forpoorhouseholds,theirhomecanbeanimportantassettoenableincome-generatingand/orlivelihoodsactivities,yetby-lawscan–oftenunintentionally–berestrictiveinthisrespect

• Conductareviewofby-lawstoidentifyimpediments

Thisactionrelatestoaction7.6andsupportsaction12.5.

• Developrecommendations• Councilresolutionstoamendby-laws

12.5 Implementincentivesinordertoenablecommunityresidentswillingandabletofinancetheirownshelterimprovementsasperprovincialguidelines

Residentsaremorelikelytoinvestinshelterimprovementswhentheyhavetenuresecurityandservicesandinfrastructureimprovementsareevident.Municipalitiescanofferdifferentincentivesinthisregard.

• Useprovincialscenarios/incentivemodelstoinformcommunityengagement

Thisactionrelatestoactions12.2and12.4.

• Developagreementswithrespectivecommunities• Implementincentivemodelsaspercommunityagreements

Page 28: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective3:Strengthenedsectorcapability,governanceandresources

-63-

13 Initiatepartnershipsbetweenpublic-private-NGOs-communityorganisations

Provincialactions Rationale Keysteps Linkages Departmentresponsible

13.1 Developgenerictenderspecificationsforappropriatesocio-technicalskillsforinformalsettlementupgradingandsetupasuitablemonitoringsystem

Socialskillsareoftenundervaluedininformalsettlementupgradingandneighbourhooddevelopment,yetupgradingisasmuchaboutbuildingcohesiveandinclusivecommunitiesasitisaboutprovidingbasicservicesandpublicinfrastructure.Includingbothsocialandtechnicalskillsrequirementsinthetenderensuresthattherequisitecompetenciesaremadeavailableandcanfacilitateapartnership-basedapproach.

• Draftconceptnoteoncorefunctionsandassociatedskillsrequirementsininformalsettlementupgrading

Thisactioncanbelinkedtoaction11.4.

DoHS

• Incorporatetheseskillsrequirementswithweightingintenderspecifications• Setup(andimplement)amonitoringsystemtoreviewsocio-technicalcompetenciesintenderapplications• Conductanassessmentofnon-stateactorsincludingintermediaryorganisations

13.2 Developandmanageadatabaseofprequalifiedpanelofprofessionalresourcestodeliversocio-technicalsupporttomunicipalities

Thiscanassistprovinceinfast-trackingprocurementandsupportingmunicipalitieslackingkeyprofessional/specialistskills.

• Determineeligibilitycriteriaandapplication/reviewprocedure,aswellasnextwindowsofopportunity

DoHS

• Circulateacallforapplicationsandreviewapplications• Setupandmanagethedatabase

13.3 Preparegenericguidelinesforstakeholderpartnershipapproach

Guidanceonthetypesofpartnerships,roles&responsibilitiesofpartnersandreviewmechanismscanassistinshiftingtowardsapartnership-approachinpractice.Itcanassistmunicipalitiesastheydonothavetoreinventthewheel.

• Draftguidelinesforadaptationbymunicipalities

DoHS

Page 29: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective3:Strengthenedsectorcapability,governanceandresources

-64-

13.4 Incorporatethe3%allocationforsocialfacilitationincontractswithmunicipalitieswithreportingrequirements

TheUISPincludesaprovisionthat3%offundsaremadeavailableforsocialfacilitation,yetthereisnomechanisminplacetoensurethatthisisreflectedintenders,nortoassesswhethertheallocationisusedforitsintendedpurpose

• Includeaminimumrequirement(atleast3%)forsocialfacilitationintenders

DoHS

• Reviewtherequirementaspartoftheassessmentprocess• Revisereportingrequirementstoincludeoutcome-basedreportingrelatedtotheutilisationoffundsearmarkedforsocialfacilitation

Municipalactions Rationale Keysteps Linkages Departmentresponsible

13.5 Identifyandprepareadatabaseofallcivilsocietyorganisations

Municipalitiesareoftennotfullyawareofthetypesofcivilsocietyorganisationsandservicesofferedwithinthemunicipalarea.Theseorganisationscanbepartnersinlocaldevelopmentand/orsourcesoflocalinformation.

• Developaregistrationtool• Setupandmanagethedatabase

13.6 District/localmunicipalitiestoestablishayearlyconsultativeforumoninformalsettlementupgrading

Theconsultativeforumcreatesanopportunityforreflectionandpeerlearningacrossdifferentprojectsandinterventionsindifferentcommunities.Itcanfurtherdeepenpartnershipsandaccountabilityofallactorsinvolved.

• Developaconceptnotedeterminingtheobjectives,scope,intendedoutcomesandagendaoftheforum

• Securefacilitationsupport• Organiselogistics

13.7 Alignresourceallocation,planningandcapacitywithregardstoIDP,SDBIPsandSDF

Thiswillfacilitateoverallalignmentinapproachandalong-termperspectiveoninformalsettlementupgradingandneighbourhoodplanning.

• ConductareviewoftheIDP,SDBIPandSDFtoensurealignmentwithinformalsettlementupgradingpolicyandtargets.

Thisactionenablesallmunicipalactions.

Page 30: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective3:Strengthenedsectorcapability,governanceandresources

-65-

14 Improvemunicipalcapabilityforcoordinatingandimplementingaprogrammaticapproachtoinformalsettlementupgrading

Provincialactions Rationale Keysteps Linkages Departmentresponsible

14.1 DesignandimplementaProvincialupgradingsupportprogramme(PUSP)tosharebestpractice,skillsdevelopmentandlessonslearnt

ThePUSPcanactasaprovincialforumforcoordination,learning,jointinterventionandpartnershipbuilding,whichwillservetoimprovepracticeandupscalingofinterventions.

• Developaconceptnoteontheobjective,scope,modusoperandiandresourcingofthePUSP

DoHSwithDoPandDEADP

• Implementaccordingly

14.2 Developastandardapproachtorapidappraisalsininformalsettlementstomonitorandoverseeimprovementswithininformalsettlements

The2016provincialrapidappraisalofferedinvaluabledata.Regularupdatesarenecessarytoensurethatinformationremainsuptodate.Also,insettlementswheretherapidappraisalhasnotbeendoneitisimportantthatthereisconsistencyinapproachanddatagathered.

• Developastandardisedformforrapidappraisalsatcommunitylevel

Thisactionlinkstoaction15.1andenablesaction14.4.

DoHS+DEADP

• Determinetheresource/equipmentrequirementstoconducttheappraisalandprocesstheresults• Developanoutcome-basedperformancereviewsystemtooverseeimprovementsininformalsettlements(againstappraisalfindings)

14.3 Developand/oridentifysuitabletrainingprogrammeswithregardstoupgradingformunicipalrepresentatives

Informalsettlementupgradingandneighbourhooddevelopmentisaninterdisciplinaryeffort,requiringcomplementaryaction&resourcing,collaborationandlearningacrossdisciplinesandsectors.

• DevelopanMOUwithatertiaryinstitution

Thisactionlinkstoaction15.3andisinstrumentalinenablingallmunicipalactionsoutlinedintheimplementationplan.

DoHSwithDoPandDEADP

• Developaconceptnoteregardingthetrainingprogrammeandcurriculumdesign• Programmedelivery,includinglogisticsandfacilitation

Page 31: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective3:Strengthenedsectorcapability,governanceandresources

-66-

Municipalactions Rationale Keysteps Linkages Departmentresponsible

14.4 DecentraliserapidappraisaltolocalmunicipalitiestobeconductedthroughEPWP/CWPcommunityledsurveys

Arapidappraisalisaneffectiveparticipatorytooltoassessservicesanddeliveryprogressthatallowthemunicipalitysolveproblemsmorequickly.Italsogeneratesasenseofownershipofdevelopmenteffortsinthecommunity.

• Review,ifnecessaryrevise,thesurveyusedfortheprovincialrapidappraisalofinformalsettlementsin2016

Thisactionlinkstoaction9.7(andassociatedactionslistedthere)andaction14.2.

• Offertrainingandequipmenttocommunitystructuresthatcanconducttherapidassessment• Collateandreviewthefindingstoinformappropriateresponses

14.5 Establishadequatehumanresourcesandcapacitywithadedicatedfocusonneighbourhooddevelopmentandinformalsettlementupgrading

Strongmunicipalcapabilityisrequiredtoensurecoherenceinapproach,adequateguidanceandsupporttootherdepartmentsandlocalactors,andtoimplementallmunicipalactions

• DevelopaTORforaninstitutionalapproachthatensurescoordinationandcoherence,withcapabilityrequirements,resourcingneeds,accountabilityandreportingsystems

Thisactionenablesallmunicipalactionsandislinkedtoaction15.4.

• Getpoliticalsignoff

Page 32: FROM PRECARIOUS SETTLEMENTS TO DIGNIFIED COMMUNITIES › assets › departments › ... · Circulate NUSP resources on neighborhood development and community action planning, along

Strategicobjective3:Strengthenedsectorcapability,governanceandresources

-67-

15 Enhanceprovincialcapabilityformonitoring,oversight,technicalguidance,learningandsupport

Provincialactions Rationale Keysteps Linkages Departmentresponsible

15.1 Developaninterdepartmentalmonitoringandevaluationsystemtomeasuresuccess,basedontheISSPM&Eframework

Outcome-basedmonitoringacrossalldepartmentswithrespecttoneighbourhooddevelopmentandinformalsettlementupgradingiscritical,aswellassuitablecapacityallocationforimplementation.

• DevelopaTOR/briefforadetailedoutcome-basedM&Esystem,inlinewiththeISSFM&EFramework

ISSFM&EFramework DoHSwithDoP

• Setup&maintainthesystem(includingallocatingresponsibilitiesandresources)

15.2 EstablishaprotocoltoalignMTEFtargetsrelatingtoneighbourhooddevelopmentacrossalldepartments

ActionsandresourceallocationsforneighbourhooddevelopmentneedtobeprovidedforintheMTEF,otherwisetheywillnothappen.

• ReviewneighbourhoodplansandmunicipalplanswithaviewtoidentifyingimplicationsfortheMTEF

Thisactionenablesallprovincialactionsaswellasmanymunicipalactions.

DoHS

• ConsultprovincialdepartmentsonMTEFimplications

15.3 Developaninterdisciplinarytrainingprogrammewithregardstoupgradingforprovincialrepresentatives

Informalsettlementupgradingandneighbourhooddevelopmentisaninterdisciplinaryeffort,requiringcomplementaryaction&resourcing,collaborationandlearningacrossdisciplinesandsectors.

• DevelopanMOUwithatertiaryinstitution

Thisactionlinkstoaction14.3andisinstrumentalinenablingallprovincialactionsoutlinedintheimplementationplan.

DoHSwithDoPandDEADP

• Developaconceptnoteregardingthetrainingprogrammeandcurriculumdesign• Programmedelivery,includinglogisticsandfacilitation

15.4 EstablishawellcapacitatedprovincialunitwithinthedepartmentofhumansettlementswithadedicatedfocusonneighbourhooddevelopmentandISU

Strongprovincialcapabilityisrequiredtoensurecoherenceinapproach,adequateguidanceandsupporttosectordepartmentsandmunicipalities,toimplementactionsintheISSFImplementationPlanandtoleveragecross-sectoralandmulti-stakeholderinvolvementandresources.

• DevelopaTOR/scopefortheunit,withcapabilityrequirements,resourcingneeds,accountabilityandreportingsystems

Thisactionenablesallprovincialactionsaswellasmanymunicipalactions.

DoHSandDoP

• Getpoliticalsignoffonroleandresourcingoftheunit

15.5 AlignprovincialplanslinkedtovariousdepartmentsundersuperBEPP

Thiswillfacilitateoverallalignmentinapproachandalong-termperspectiveoninformalsettlementupgradingandneighbourhoodplanning.

• ReviewofsuperBEPPanddepartmentalplansintermsofinformalsettlementupgradingandneighbourhooddevelopment

DoHSandDEADP