Top Banner
from local operator to… Regional Operator Dr. Eng. Mihail DORUS Bulgarian Water Association– September 2016 Starosel
52

from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Jan 10, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

from local operator

to…

Regional Operator

Dr. Eng. Mihail DORUS

Bulgarian Water Association– September 2016 Starosel

Page 2: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

2

Location in Europe

Page 3: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

In the past…

3

Page 4: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

In the past…

4

• 1898 - 1911

Engineer W. H. Lindley carries out hydro-geological studies and proposes the building of a water supply system towards Iasi City from the Timişeşti commune (junction of Valea Nemţişorului with Valea Moldovei), the water source being the Ozana River.

Page 5: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

In the past…

5

The water catchment takes place in a 14 meter deep caisson-type collector that provides an average amount of 10.000-30.000 m3 water/ day.

Page 6: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

In the past…

6

1936

Founding of the “Societatea Comunală a Apelor Potabile Iași” (Iasi communal water authority).

1942

“Societatea Comunală a Apelor Potabile Iași” becomes a public commercial “regia”.

Page 7: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

In the past…

7

1948

Founding of “Întreprinderea de Electricitate, Tramvaie, Apă-Canal, Salubritate” (a power/tramways/water-sewerage/sanitation public enterprise)

Page 8: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

In the past…

8

1955-1957

Due to an insufficient flow rate provided by the Timișești source, a new investment is carried out: the designing and the construction of the Prut River water supply towards Iasi City (a surface water source).

The water and sewerage activity is taken in charge by the public enterprise “Întreprinderea Comunală Apă-Canal-Băi Iași.”

Page 9: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

In the past…

9

1968-1973

Extension of the Timișești source main water collector (design and execution).

The services provided by the public enterprise “Întreprinderea Comunala Apă-Canal-Băi Iași” are taken by the “Grupul întreprinderilor de Gospodărie Comunală și Locativă Iași (I.G.C.L. Iași” (a group of public enterprises for several utilities).

Page 10: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

In the past…

10

• 1991

Founding of the ”Regia Autonomă Județeană Apă Canal Iași” (public autonomous water and sewerage “regia” of Iasi County)

• 1995

The “Regia Autonoma Județeana Apă Canal Iași” commences a vast investment program in all sectors (MUDP I - EBRD)

• 2000-2001

Financing contracts are signed by representatives of the European Community and Romania (EBRD loan)

Page 11: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

In the past…

11

• 2001-2009 The ISPA Program

• 2008 - Founding of joint-stock company ApaVital S.A. Iași (societate comercială), having as share holders the Iasi County Council and the county mayoralties.

• 2009 - On 14th of July 2009 the document named “Management Delegation Contract” is signed with the ARSACIS Inter-community Development Association (Asociația de Dezvoltare Intercomunitară)

• 2011-2012 The SOP Environment Program

Page 12: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

The SOP Environment - Institutional Frame

Viability and functionality of the SOP Environment institutional frame - key-elements for the assessments carried out by the European Commission on projects submitted towards Bruxelles.

The Institutional Analysis (included in FC) – ensuring an adequate and sufficiently powerful institutional frame for project implementation and for the subsequent sound operation of the infrastructure that is to be achieved with European funds

The legal frame – primary and secondary legislation in force regarding the sectors: water and sewerage, waste, district heating etc.

12

Page 13: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

• Beneficiary –Regional Operator (RO);

• Regionalization – The only solution for increasing the efficiency of water and sewerage services and for the fulfillment in due time of all commitments assumed by Romania via the Adhesion Treaty

• Institutional elements – a sine-qua-non condition for project approval :

• IDA (intercommunity development association) – A co-operation based structure that shall allow local authorities to control the water operator and to better monitor and supervise the implementation process;

• RO – Must demonstrate their capacity to operate in a durable manner

• Single delegation contract - to be signed by the IDA and the RO;

• The need to create a Project Implementation Unit (PIU) inside the RO;

13

The SOP Environment - Institutional Frame

Page 14: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

The “in-house rules”

The similar control - The territorial administrative units perform, via the association (IDA), upon the regional operator, a control similar to the one performed upon their own structures and a decisive influence upon all RO’s strategic and/or significant decision within the project area.

The criterion of exclusivity - The regional operator performs its activities in the field of water and sewerage services, exclusively for the public authorities associated within the IDA.

The operator’s fully public capital - The involvement of private capital in the operator’s share capital is strictly excluded, since founding stage, and along the whole duration of delegation contract

14

Page 15: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Motives behind the need for regionalization

The rationale related to the European integration: compliance to environment standards, within dead-lines defined by the Adhesion Treaty;

The economic rationale: use of scale savings for decreasing investment and operation costs

The solidarity rationale:

Small and average communities do not have the capacity to prepare and implement projects, nor the capacity to operate the investments.

Great cities have the capacity to support, from their own investments, the needed investments (without getting associated to smaller localities, the cities cannot access financial grants)

The viability rationale (the BCA result) - Cannot be proved for most of small localities (having historical debts and lacking of needed expertise).

15

Page 16: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Institutional Eligibility

16

IDA

• Founded on the 1st of July 2005 (conversion in compliance to the law in force in 2007)

• Members: 102

• Registered at Iasi County Court in January 2008

ROC

• Founding date as Regia Autonoma Apa canal Iasi – RAJAC IASI – January 1991

• Conversion in joint-stock company SC APAVITAL SA in 2008

• Shareholders structure: 100% Territorial Administrative Units (90 shareholders)

• Covered area: Iasi County and a part of Neamt and Vaslui County

• Registered at the Register of Commerce Iasi on 24th April 2008

DC

• Being in finalization process:

• approved by the ARSACIS General Shareholders Assembly in 14.07.2009

• approved by Decision of Local Council in all Territorial Administrative Units being members

Page 17: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Diagram of Relations

17

Te

rrito

rial A

dm

inis

trative

Units

IDA PRESIDENT

General assembly of shareholders

Board

General assembly of shareholders

Board

Page 18: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

THE LEGAL FRAME

• Law of public local administration n0. 215/2001, with subsequent addenda and completions;

• Law of public utilities communitary services no. 51/2006;

• Law of water and sewerage services no. 241/2006,

• Govt. emergency ordinance no. 30/1997 related to the re-structuring of “autonomous regia” privind reorganizarea regiilor autonome, with subsequent addenda and completions;

• Govt. ordinance no. 26/2000 related to associations and foundations, with subsequent addenda and completions;

• Law of commercial enterprises no. 31/1990, re-published, with subsequent addenda and completions;

18

Page 19: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

The founding of the communitary development association

The steps performed for the founding of the association are the FOLLOWING:

• Reserving the association’s name at the Ministry of Justice

• Drafting the project for the Association’s Constitutive Act and Status, and their submittal for approval towards local authorities.

• Approval of the Association’s Constitutive Act and Status, by the local authorities, members of the association.

• Preparing of the documents needed for the acquiring of legal personality at Iasi City Law Court (competent law court for Association’s head-quarters)

• Registering the Association in the Iasi Law Court’s register of associations and foundations.

19

Page 20: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Creating the Regional Operator

• The regional operator was founded by the conversion of the “Regia Autonoma” in a company (“societate comerciala”) in compliance to Govt. ordinance no. 30/1997, on the re-structuring of “regiile autonome”, with subsequent addenda and completions, corroborated with the Law for “societati comerciale” companies. no.31/1990, re-published, with subsequent addenda and completions, and the Law no. 51/2006 for public utilities communitary services.

• There were recommendations that the newly created company should be a joint-stock company. Moreover, in order to directly delegate the public water services to this new company, it was mandatory for the territorial administrative units, members of the Association, to participate to the company’s equity capital. The participation threshold at the future company’s equity capital can be limited to a certain minimum amount.

20

Page 21: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Conversion in company (“societate comerciala”) (1)

• The Iasi County Council adopted a decision that included the following:

– Name of the new company;

– Statement saying the new company is a legal person;

– The juridical status of the new company;

– Address of head-quarters;

– Secondary premises stated in the new company’s structure;

– The way the new company’s patrimony is to be constituted;

– The way the new company’s equity capital is constituted;

– Nominal value of one share;

– The associates of the new company resulted from the conversion of the “regia autonoma”;

– Undertaking all the Regia’s rights and obligations;

– Identifiying the goods within the Regia’s patrimony upon which the new company will acquire ownership rights;

– The new company’s activity object;

– The obligation to conclude a delegation contract for the management of public services (via concession);

– The structure of the new company’s senior management structures;

– The transfer of the Regia’s personnel towards the new company and the transfer date;

– Statement stipulating the cessation of all other legal provisions related to RAJAC IASI.

21

Page 22: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Conversion in company (“societate comerciala”)(2)

• Defining (or not), for the administrative authorities, the minimum threshold of participation at the new company’s registered capital;

• Adoption, by the local public authorities, members of the Association, of decisions concerning: (i) The direct delegation of the public water-sewerage service management towards the new company, (ii) The empowering of the main credit release authorities to negotiate and/or sign agreements for participation at the creation of the regional operator, if such be the case

• In case that the new company’s shareholders are established, there will be need to conclude an agreement that will define the participation of each territorial administrative unit (TAU) to the regional operator’s registered capital (agreement that is to be signed by all main credit release authorities)

• Preparing the documents need for the founding of the new company;

22

Page 23: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Conversion in company (“societate comerciala”)(3)

• Approval decision for the new company’s Constitutive Act, issued by the involved territorial administrative units’ local authorities, acting as shareholders of the new company’s equity capital and the empowering of a representative for the signing of this Act and the appointment of a person that will act on the behalf of the territorial administrative unit, within the new company.

• Performing the public promotion of all adopted decisions and informing of the public in relation to these decisions.

• Signing of the new company’s Constitutive Act;

• Registering of the new company at the trade register bureau (Oficiul Registrului Comertului);

• A minimum participation amount is decided for each locality that wants to become a shareholder in the new company. However, some localities may refuse to become a shareholder, preferring to only give in concession the services towards the company.

23

Page 24: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Defining the participation quota of each local authority

• Criteria:

– The water volume supplied in the operating area of each territorial administrative unit involved in the constitution of the regional operator;

– The value of the patrimony being made available to the regional operator (public or private).

• In order to establish the participation of each local authority in the forming of the new company’s equity capital, it is recommended to determine first the intake brought by the greatest shareholder, namely the Iasi County Council, and then, on basis of previously defined percentages. by applying one of the criteria mentioned above, the contribution of each local authority is to be determined.

24

Page 25: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

The regional operator’s Constitutive Act

Mainly, the following aspects should be considered:

• The company’s activity, mentioning the field and main activity;

• The amount of authorized capital stock, if any;

• Any restriction on shares transfer;

• Provisions regarding the management, the administration, the operation and the management/control of the company by statutory bodies, and the number of Board members;

• The powers conferred to administrators and, if applicable, to directors, and if they are to perform them together or separately (classical or unitary management system); or

• The powers conferred to the administrators and, if applicable, directors, respectively the members of the directorate;

• The distribution of profits and losses;

• The dissolution and the liquidation of the company;

• The total amount or at least estimates of all expenses for constitution.

25

Page 26: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Issues subsequent to the creation of the regional operator

• Ensuring the transfer / the hiring of staff in the new company;

• Obtaining all the operating licenses / permits / authorizations (by transferring them from the previous operators, where applicable);

• Establishing the organizational structure of the new regional operator;

• Finalization and approval of the organization and functioning regulations of the new structure;

26

Page 27: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Delegation of the water-sewerage services management

• The Law of water and sewerage no. 241/2006, according to Art. 21 para. (2) and under application of the sentence in paragraph II. (3) of Article 4 of Govt. ord. no. 30/1997 regarding the reorganization of “regia autonoma’, with subsequent amendments

• In order to finalize the reorganization process (conversion to a commercial company) and the reorganization of regional water and sewerage services, it is necessary that at the same time with the conversion of the Regia into a company, to achieve a procedure of services management delegation:

a) With the approval of the new company’s Constitutive Act there is need to finalize and approved, by a decision of the local public administration, a management delegation contract for public services, through concession.

b) The representatives of the territorial administrative units empowered to sign the service management delegation contract are to be appointed.

27

Page 28: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Conclusions

• Approval of the Association and the Association’s creation by all the local involved authorities;

• Approval by the CC of the decision on the re-organization into a new company;

• Establishing the stakeholders that will be involved together with the County Council in the creation of the company’s equity capital and defining a minimum threshold of their participation;

• Adoption of a decision for the direct public service management delegation, through a concession agreement and appointing of a representative for the local and county authorities, able to attend the negotiations that are be conducted for the establishment of the regional operator and for the drafting of the management delegation contract, by concession.

• Approval by the associated local authorities (shareholders) of documents needed to finalize the management delegation process, in its final form, this consisting of: (i) The new company’s Constitutive Act, (ii) The approval of the final form of delegation contract;

• The signing of the Constitutive Act by the representatives of local authorities and, also, of the concession contract, and also by the representative of the newly created company.

28

Page 29: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

29

Our days…

Page 30: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

The ApaVital mission is to continuously supply water and sewerage services to all consumers, with strict observance of all quality and efficiency parameters.

The ApaVital services are provided to 600.000 inhabitants and 3.000 enterprises/businesses.

The global water supply capacities can serve 1 million inhabitants and over 4.000 enterprises/businesses.

30

Goals and Mission

Page 31: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Drinking water treatment plants: 5.485 l/s – 8 units

Water pipelines: 2.812 km

Tanks: 155.538 m3 – 159 units

Wastewater treatment plants: 4.577 l/s – 17 units

Sewerage networks - 918,4 km

Drinking water pumping stations - 107 units

Wastewater pumping stations - 72 units

Re-chlorination stations - 60 units

ApaVital makes permanent efforts in order to provide a nonstop water supply and to continuously improve the water quality standards.

31

Capacities

Page 32: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

32

Turn-over : 30 million Euro

Equity capital : 18 million Euro

Number of shares: 788.723

Number of share holders: 90

Number of employees: 1194

Combined tariff (water/sewer) VAT incl. : 6,86 lei/m3

Localities with ApaVital services : 191

General Figures

Page 33: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

33

Physical Production (mil. m3)

Page 34: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

8.828.55

8.348.188.11

7.567.537.357.347.317.227.167.157.137.107.067.047.026.966.906.886.876.86

6.736.736.716.646.636.51[] 6.276.226.226.186.066.065.995.985.92

5.725.685.605.53

4.98

4.43

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

9.00WATER-SEWERAGE TARIFFS (VAT incl.) RO

AUGUST 2016

Ranking: 30 of 45

Apa Canal A+C

Page 35: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

35

1995 2015

1561 1207

Operational Areas vs. Employees

Page 36: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

36

Operational Area

Page 37: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

INTEGRATED MANAGEMENT SYSTEM

Based on a CROS ERP developed on an Oracle platform for ensuring data security, subsequently on which other Business Intelligence applications have been connected: banking interfaces, intranet for documents distribution inside the company (and the survey of performance parameters) and also the company’s webpage, where various data are uploaded (news information, communiques, water test bulletins).

IT SOLUTIONS

• ERP: client relation module

- demands input (viewing of clients data)

- SMS module

• Clients phone calls management

• ApaVital webpages (www.apavital.ro)

• Intranet (ApaVital in press etc.)

- Microsoft Office (answers to requests/complaints, graphs, various lists, presentations etc.)

• Industrial system control software (water plants, pumping stations, WWTP)

• Design software; GIS data updating software

• Software for bills of quantities, projects completion and control

• BI software

• Electronic registering system

• Various software for keeping relations with state institutions (work inspectorate, finances etc.)

• Other applications

IT Management

Page 38: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

ISO 9001:2008 – Quality Management System

ISO 14001:2005 – Environment Management System

OHSAS 18001:2007 – OHAS Management System

ISO EC 27001:2005 – IT Data Security Management System

ISO EC 22000:2005 Food safety Management System

ISO 17025: 2005 – Laboratory Management Systems

38

Quality Management System

Page 39: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

1st Class Operational License issued by the Romanian public services authority “Autoritatea Națională de Reglementare a Serviciilor Comunale din România” (ANRSC - www.anrsc.ro).

Wastewater Testing Laboratory accredited by RENAR Romania (www.renar.ro)

Drinking Water Testing Laboratory, certified by the Ministry of Health of Romania (www.ms.ro), regarding the monitoring of drinking water.

Metrological Laboratory - Authorized by the Romanian metrology authority “Biroul Român de Metrologie Legală din România” (www.brml.ro) – regarding metrological verifications.

Regarding the preparing of studies in the domain of water management, ApaVital is certified by the Romanian Ministry of Environment and Climate Changes (www.mmediu.ro).

39

Quality Management System

Page 40: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

40

Services

CALL CENTER (since 2005)

Watermeter indexes

Repairs requests

Requests for new connections

Info on invoices , contracts

Permits/approvals

Processing of various complaints

Counseling for decreasing of

water consumption

Contract signing

PR Office

CALL CENTER

24/24

Tel Verde 0800808969

Public Relations

Page 41: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

MUDP 1 1996-2000 € 14,000,000

KfW+budget 1996-2000 € 22,200,000

ISPA 2001-2008 € 51,700,000

APAVITAL funds 1996-2015 € 45,000,000

Grants (USAID, France,etc) € 150,000

Grant provided by EVD (the Netherlands) € 1,800,000

TOTAL € 135.000.000

SOP Environment I € 136,000,000

POIM € 200,000,000

41

Investments

Page 42: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Achieved steps

• Creation of the Public Relations Unit – 2001

• Creation of a Call Center - 2005

• The ApaVital website – 2007

• Social responsibility - 2007

• Branding - 2008

42

Page 43: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Achieved steps

• Conceiving and implementing an employees performances evaluation system.

• Employees professional training.

• Development of a quality-oriented organizational culture.

43

Page 44: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Achieved steps

• Providing a full compatibility between the personnel structure and the company’s needs.

• Shifting from a state-owned typical management system to a management oriented towards the corporative governance practices and principles

44

Page 45: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Achieved steps

• Investment works, especially the grant funded ones;

• Continuity of company management and all the endowments offered to the company employees (machinery, equipment, computers and other IT systems).

45

Page 46: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Achieved steps

• New tendering regulations (PRAG , EBRD regulations and policies) and contract management regulations, adopted together with the implementing of the EC funded investment program (ISPA program).

• Know-how transfer from the European Commission Delegation and consulting firms.

46

Page 47: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Achieved steps

• Co-operation with IFIs, starting with year 1995, together with the commencement of the MUDP I Program (Municipal Utilities Development Program) and the signing of the EBRD financing contract: creation of an MRD account; costs decreasing; decreasing of NRW; tariff decreasing, in real terms.

47

Page 48: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Achieved steps

• Ensuring the full quality of provided services (supplied drinking water and wastewaters released towards sewers, plus the treatment of these wastewaters), in compliance to quality ISO standards: 9001, 14001, 18001, 27001 and 22000

48

Page 49: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Achieved steps

• Adopting an Integrated Management System

• Customer water metering, at a rate of 100%

• Benchmarking - EBRD

49

Page 50: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

50

In the future Transboundary Projects

Starting with 5.12.2014, Apavital erect a new company (APAVITAL M) in Moldova Republic in order to provide water distribution services in this country. This company is 100% own by Apavital. Apavital is preparing a Project for water distribution in Moldova Republic using Romanian local water sources.

Page 51: from local operatorbwa-bg.com/wp-content/uploads/2016/10/Regionalizare-IASI.pdf · • 2001-2009 The ISPA Program ... • 2011-2012 The SOP Environment Program . The SOP Environment

Motives behind the need for regionalization

The rationale related to the European integration: compliance to environment standards, within dead-lines defined by the Adhesion Treaty;

The economic rationale: use of scale savings for decreasing investment and operation costs

The solidarity rationale:

Small and average communities do not have the capacity to prepare and implement projects, nor the capacity to operate the investments.

Great cities have the capacity to support, from their own investments, the needed investments (without getting associated to smaller localities, the cities cannot access financial grants)

The viability rationale (the BCA result) - Cannot be proved for most of small localities (having historical debts and lacking of needed expertise).

51