INTERSTATE 57 ADD LANE FROM I-24 TO I-64
24

From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Mar 28, 2015

Download

Documents

Kamryn Taplin
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

INTERSTATE 57 ADD LANE FROM I-24 TO I-64

Page 2: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Add the 3rd lane to Interstate 57

From I-24 (MP 44) to I-64 (MP 92) is 48 miles

ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck Traffic = 30% or 10,000

Trucks per day

Estimated Cost to Widen to 6 lanes = $350 M (does not include rehabilitation of the exist. Pavement)

Page 3: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

IDOT conducted a Feasibility Study in Franklin County to investigate adding the

3rd lane to I-57

Page 4: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Feasibility Study in Franklin County Conclusions

Yes, the I-57 traffic warrants an additional lane Widening should be accomplished by widening to the

inside: minimizes right of way cost and impacts includes closed drainage where median is less than

64’ requires widening of bridges does not impact overhead structures and interchanges

Costs (excludes structures & rehabilitation of the existing pavement) Inside Alternate (50’ existing median): $890/ft Inside Alternate (64’ existing median): $1,030/ft Inside Alternate (80’ existing median): $790/ft

Page 5: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Typical Sections : Inside Widening with 64’ median (closed drainage in median)

Typical Sections : Inside Widening with 80’ median (open drainage in median)

Page 6: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Photo Rendering – Adding 3rd lane to the inside with barrier wall

Page 7: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Photo Rendering – Adding 3rd lane to the inside with barrier wall

Page 8: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Can District 9 fund a $350 M project?

Page 9: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

HISTORICAL ANNUAL PROGRAMS2002 – 2010 PUBLISHED BOOK – STATE ONLY

2002 2003 2004 2005 2006 2007 2008 2009 2009 ADJ

2010 2010 ADJ

$0

$20,000,000

$40,000,000

$60,000,000

$80,000,000

$100,000,000

$120,000,000

$140,000,000

$160,000,000

$76,172,000

$54,738,000

$48,831,000

$31,425,000

$25,231,000

$62,435,000

$68,797,000

$90,978,000

$158,413,000 $78,300,000

$152,104,000

DISTRICT 9

INCLUDES: FED. STIMULUS AND 2009 JUMP START PROJECTS

Page 10: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

How can we accomplish?

1. When replacing I- 57 Structures add the 3rd lane … Underway

2. Rehabilitate I- 57 Pavement ….Underway

3. Begin design work on small fundable contracts to add the third lane, begin to introduce into the program or have ready for new funding initiatives ….Underway

Page 11: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

#1. When replacing I- 57 Structures add the 3rd lane … Underway

Bridges completed that accommodate 3 lanes MP 51, I-57 over Crab Orchard Creek (S of Marion) MP 53, I-57 over old IL 13 in Marion MP 53, I-57 over the Crab Orchard and Egyptian RR MP 59, I-57 over Lake Creek (S of Johnston City) MP 90, I-57 over Casey Fork Creek (S of Mt. Vernon)

Bridges in the program that will be built and will accommodate 3 lanes MP 54, I-57 over new IL 13 MP 65, I-57 over 7th Street in West Frankfort MP 71, I-57 over the UP Railroad

Page 12: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

PROJECT LOCATION ON INTERSTATE 57 IN FRANKLIN COUNTY

REMOVAL AND REPLACEMENT OF TWO STRUCTURES OVER 7TH ST. AND THE

ABANDONED C&EI RAILROAD.

LOCATED 0.7 MILES NORTH OF IL. RTE. 149

June 11, 2010 Letting

Page 13: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

PROJECT LOCATION ON INTERSTATE 57 IN FRANKLIN COUNTY

REMOVAL AND REPLACEMENT OF TWO STRUCTURES OVER THE UNION PACIFIC

RAILROAD.

LOCATED 1.1 MILES SOUTH OF IL. RTE. 14 IN BENTON

September 17, 2010 letting

(pending ruling by IL commerce commission)

Page 14: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

2. Rehabilitate I- 57 Pavement ….Underway and near completion

Complete – I-57 NB IL 13 to Williamson/Franklin Co. Line

Complete – I-57 NB & SB IL 14 to Franklin Co. Line

Rubblization of I-57 will be complete in 2011 from IL 13 (Marion) to 1 mile north of Bonnie (south of Mt. Vernon)

Page 15: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Upcoming I-57 Rubblization Contracts

I-57 Rubblization in Williamson and Franklin County, 2nd Federal Stimulus (“Jobs for Main St. Act”: NB – Williamson/Franklin County line to IL 14 SB – IL 14 to north of IL 13 NB – 9.9 miles SB – 16.2 miles Estimated Cost - $32.7 M Summer 2010 - work should begin in May and

be complete in September Lane closures and delays expected

Page 16: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Upcoming I-57 Rubblization Contracts

I-57 Rubblization in Jefferson County, Construction Now program: NB & SB - from the Franklin County line to 1

mile north of Bonnie 6.6 miles Estimated Cost - $15.8 Work in late 2010 and 2011 Work may begin in September, 2010 and be

completed by July 1, 2011 Lane closures and delays expected

Page 17: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

RUBBLIZATION EQUIPMENT

Page 18: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

3. Add 3rd lane to I- 57 in fundable, usable segments/contracts….

3rd Lane Complete – Marion; South of MP 53 to north of MP 53- (not open to traffic)

Funded in MYP- MP 92, I-64 south of Mt. Vernon, to MP 96, I-64 north of Mt. Vernon; design under way to add third lane and replace the pavement. Construction planned for 2011.

Funded in MYP - MP 54 Marion, design underway to complete the 3rd lane through Marion

Page 19: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Add 3rd lane to I- 57 in fundable, usable segments/contracts

Unfunded ---- 1st priority: add third lane for 12.7 miles from north of IL 13 in Williamson County to south the Middle Fork Big Muddy River in Franklin County (north of Benton)

Total Cost = $65 M 12.7 miles of 3rd lane = $56 M I-57 over Pond Creek, SN 028-0001&0002,

replacement, $6.0 M I-57 over Lake Creek Branch, SN 100-0010 &

0011, widen structure and superstructure replacement, $3.0 M

Page 20: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Or

Unfunded – 2nd choice: add third lane for 8 miles from north of IL 13 in Williamson County to the Williamson / Franklin County Line

Total Cost = $36.5 M 8 miles of 3rd lane (80’ median, open

drainage) = $33.5 M I-57 over Lake Creek Branch, SN 100-0010 &

0011, widen structure and superstructure replacement, $3.0 M

May be ready for a September, 2010 letting

Page 21: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Job Supported by Highway Investments

The Federal Highway Administration (FHWA) estimates that a $1 billion of Federal highway expenditure supports 30,000 jobs which includes direct, supporting, and induced positions, defined as:

Construction oriented employment, includes all jobs created by the construction firms that work directly on the project or by the firms that provide direct inputs (paving materials, steel, concrete, etc.) to the construction project;

Supporting industries' employment, includes jobs in firms that provide inputs to the industries that directly provide materials and equipment used in highway construction. For example, a firm that produces guard rails is counted as 'construction oriented' employment but the firm that provides the sheet steel to make the guard rails is considered part of 'supporting industries' employment; and

Induced employment, includes all of the jobs supported by consumer expenditures resulting from wages to 'construction oriented' and 'supporting industries' employment.

Page 22: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

Job Supported by Highway Investments

$1 billion of Federal-aid expenditure supported: 10,300 construction oriented jobs; 4,600 supporting industries' jobs; and 15,000 induced employment jobs

$350 M in highway expenditures, according to FHWA, should translate into: 3600 construction oriented jobs; 1600 supporting industries' jobs; and 5250 induced employment jobs

Page 23: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

IDOT MYP Public Meeting

Tuesday, January 26, 2010, from 4:00 p.m. to 6:00 p.m. at the Williamson County Pavilion, 1602 Sioux Drive, Marion, IL

IDOT is seeking additional public feedback on development of its proposed Multi-Year Program for Highway Improvements

Page 24: From I-24 (MP 44) to I-64 (MP 92) is 48 miles ADT 2009 ADT = 30,000 vehicles per day @ 2.2% growth rate 2030 ADT = 48,000 vpd 2009 Average Daily Truck.

IDOT’S WEBSITEwww.dot.il.gov