DESIGN-BUILD FROM ALL ANGLES July 9, 2015 Long Beach, CA 1
61

FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Dec 12, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

DESIGN-BUILD FROM ALL ANGLES

July 9, 2015 Long Beach, CA

1

Page 2: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Overview • Housekeeping & Introductions

• Planning – Delivery Method Selection

• Planning – Program & Criteria

• Procurement & Competition

• Design Phase

• Construction Phase

• Questions

2

Page 3: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Overview • Housekeeping & Introductions

• Planning – Delivery Method Selection

• Planning – Program & Criteria

• Procurement & Competition

• Design Phase

• Construction Phase

• Questions

3

Page 4: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Housekeeping • Cellphones and Pagers Off or Silent • Safety Moment- Note Egress from Facility • CMAA – Membership! • Questions –15 mins reserved at end • Concluding at 10:30 am • PowerPoint to be Posted on Website

www.cmaasc.org

4

Page 5: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Panel Introductions David Hart - Steinberg Architects

Rebekah Gladson - rggroup, inc.

Todd Cozolino - Spire Consulting Group, LLC.

Marc Kersey – Clark Construction Group

Barbara Gadbois – Gibbs Giden Locher Tuner Senet & Wittbrodt LLP

5

Page 6: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Design-Build From All Angles

6

Page 7: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Discussion Format • Presented in four lifecycle phases:

– Planning and Program/ Criteria Phase – Procurement & Competition Phase – Design Phase – Construction Phase

• Presented from four perspectives: – Designer’s Perspective – David Hart – Owner’s Perspective – Rebekah Gladson – Project/ Program Manager’s Perspective –Todd Cozolino – Contractor’s Perspective – Marc Kersey – Legal Perspective Throughout – Barbara Gadbois

7

Page 8: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Overview • Housekeeping & Introductions

• Planning – Delivery Method Selection

• Planning – Program & Criteria

• Procurement & Competition

• Design Phase

• Construction Phase

• Questions

8

Page 9: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Planning Phase Delivery Model Selection Process • Assessment of Objectives

– Risk Shifting, Cost Savings, Schedule, Best Value Selection – Special Design Requirements

• Assessment of Enabling Legislation/Limitations for Public Entities

• Budget and Funding Parameters

9

Page 10: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Planning Phase Delivery Model Selection Process • Comparison with Other Alternative Delivery Options

– Design-Bid-Build – CM At-Risk – Lease-Leaseback

• Licensing Requirements – Contractor – Designer

• Insurance and Bonding Requirements

10

Page 11: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Overview • Housekeeping & Introductions

• Planning – Delivery Method Selection

• Planning – Program & Criteria

• Procurement & Competition

• Design Phase

• Construction Phase

• Questions

11

Page 12: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Planning Phase D/B Trend – moving beyond risk shifting, schedule and cost control to design excellence, innovation, and strategic partner.

12

Page 13: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Planning Phase Three basic types of Criteria Packages: • General Program with Guidelines

• Detailed Project Program with Standards (sometimes with

a concept design)

• Bridging Design with Schematic Design (or Design Development)

13

Page 14: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Program

1. Whole Project Program (Building, Site, Equipment) 2. Project Requirements 3. Areas of Flexibility 4. Room Data & Diagrams 5. Code Analysis 6. Operational Issues

Criteria

1. Guidelines and Standards 2. Building Systems Requirements 3. Project Data (soils, surveys, CEQA) 4. Site Requirements (fire + service access, setbacks,

easements) 5. Infrastructure + Scope Requirements 6. Sustainable + Energy Efficiency Goals 7. Schedule

Cost 1. Cost Tied to Program, Criteria, and Aspirations

2. Develop Full Project Budget 3. Look for Gaps

14

Planning Phase

Page 15: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Planning Phase Key Foci a. Master Plan, Design Guidelines, and Standards –

Compliance or Guide? b. Describe project aspirations clearly to get the best

design (link value add points to those aspirations) c. Tie project requirements, goals, and aspirations back to

the scoring, evaluation, and selection process

15

Page 16: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

16

Goal: To develop criteria documents that bring focus to the Design/Build team.

Page 17: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Overview • Housekeeping & Introductions

• Planning – Delivery Method Selection

• Planning – Program & Criteria

• Procurement & Competition

• Design Phase

• Construction Phase

• Questions

17

Page 18: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase • Primary Considerations

• Decision Makers

• Prequalification

• Primary Considerations

• Design Competition Considerations

• Cost Competition

• Project Management Competition

• Process Content

18

Page 19: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase Primary Considerations

–Policy Parameters • Public Agencies – Statutes, Regulations, Codes • All Entities – Institutional Policies & Procedures

–Project Goals • Product Performance – Does the function of the

project drive decision making? • Schedule Criticality – Is delivery speed paramount?

Speed to Operation – Revenue drivers.

19

Page 20: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase Primary Considerations (continued) • Cost Sensitivity

• What’s the funding nature? •use it or lose it vs. re-allocable

• Is it program at lowest cost? •Commodity (e.g. parking) •Level of Program Criteria Package

• Most Bang for the Buck? •most square footage, most amenities or best finishes within the budget?

• Capital Cost vs. Lifecycle/ Operational Cost?

20

Page 21: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase • Decision Makers

– Participant familiarity with capital works • Have those charged with selection been exposed to construction

project before? • What level of preparation, education and presentation is

warranted?

– Participant roles and skill sets • Will all participants evaluate all aspects of the proposals?

• Will the maintenance manager evaluate the courtroom security considerations of the layout?

• Will the history professor evaluate the quality of the mechanical system?

21

Page 22: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase • Prequalification

– Which Team Members to Prequalify? • Depending on the Project Typology (e.g. Concrete for Parking

Structure) • Depth of Specialty Market

– Multi-use pool or single project shortlist? • Custom Team versus Efficiency of Process • Frequent Updating or Open RFQ can Sacrifice Efficiency Gains

– Size of shortlist? • Inclusiveness and Competition versus Administration and Cost

– Serial Project Considerations • Prime and Subcontractor Depth • Relevance of Experience – “Cherry Picking”/ Own-Agency

22

Page 23: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase

• Design Competition Considerations – Design Quality

• Compliance with purpose, space efficiency, architectural • value, solutions to challenges, compliance with program, • flow and use, operation and function, flexibility

– Technical Quality • Equipment & materials, longevity, maintainability, durability

– Lifecycle Cost • energy consumption, anticipated service life, replacement

cost/ deferred maintenance, consumables, obsolescence risk/ horizon

23

Page 24: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase • Cost Competition Considerations

– Approach • MAC, Lump Sum, GMAX, Shared Savings

– Weighting • Typically 30-50%

– Scoring • e.g. “Must” system – lowest $ gets all points, reduce

proportionally in excess, % under stated budget, Cap – Flexibility Tools

• Alternates • Unit Pricing • Allowances

24

Page 25: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase • Management Competition Considerations

– Resumes of Key Personnel • Serial project availability • Depth and Adequacy • Must enforce!

– Detailed CPM Schedule • Phasing and Internal Milestones • Cost & Resource Loading, • Logic and Quality Metrics

• Lead/Lags, Constraints, • Get the P6 File and Analyze! • Completion date, assumptions

– Site Logistics Plan by Phase – Safety / Management Plan

25

Page 26: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase • Management Competition Considerations (continued)

– Site Logistics Plan by Phase • Pedestrian path of travel • Traffic management/ protections • Lay down, Facilities, Parking • In Process Aesthetics – Community

– Safety Record and HASP • EMR , TRIR, Fatalities • OCIP/ CCIP, Self Insured Retention

– Management Plan • Quality Management Plan • eTools (familiarity for your system?) • BIM/ coordination tools, As Built approach • Commissioning

26

Page 27: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Procurement Phase General Process Considerations • Stipend/ Honorarium

– Amount, internal messaging, Intellectual Property

• Interview Frequency, Duration, Participation – Cost/Burden versus Responsiveness – “Cross-Pollination” Avoidance

• Proposal Deliverables – Renderings, Drawings, Models, Copies, Boards, Electronic, Format

• Confidential Review Comments – Best and Final Offer Opportunity

• Debriefing Policy, timing and content

27

Page 28: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Overview • Housekeeping & Introductions

• Planning – Delivery Method Selection

• Planning – Program & Criteria

• Procurement & Competition

• Design Phase

• Construction Phase

• Questions

28

Page 29: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

29

DESIGN AND EXCELLENCE

Rebekah G. Gladson, FAIA, DBIA, President,

Page 30: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

30

Humanities Building 74,919 GSF

Page 31: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

31

UCIMC Clinical Laboratory Building 48,000 GSF

Page 32: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

32

Arts Building 59,492 GSF

Page 33: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

33

Douglas Hospital 480,000 GSF

Page 34: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

36

Common Pitfalls • Design Build: Interpretation of what you

defined! • What is Design Excellence? • Interpretation is not uniform in industry.

– I didn’t know you wanted or expected THAT!

• Design Builder really does want to provide what they think/understand the client needs,

• Quality and Cost: No common understanding, • Communication of Ideas is Difficult.

Page 35: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

37

Pre-Qualify Your Team/Owner

• Experience with Design Build • All the Typical Pre-Qual Requirements • Know who you are working with and how they

work! - BOTH SIDES • What is DB Team and Owner’s understanding

of Excellence?

Page 36: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

38

Example: Contract Design Clarity • Clearly define program for project

– Get buy-in from final user group (client) – Understand impacts of technology changes

• Identify & allocate funds for DB interface – Program to Final Design

• Clearly define role of owner • Define time for your decisions

– Days / Hours • Define dispute resolution process • What does the contract say, What does the

client expect?

Page 37: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

39

Example: Need to Know?

• Strategic Business Plan – Market – Clients – Budget – Schedule

• Design Criteria • Performance Required/Expected • Business Model • Communicate

Page 38: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

40

Example: Design Criteria - Program

• Indoor/Outdoor Spaces – Use, Quantity, Requirements, Etc. • Size – Special Dimensions

• Room Data Sheets with Equipment Req’d – Detailed Information

• Specific Room Diagrams • Functional Requirements • Infrastructure

Page 39: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

41

Example: Know Your Budget

Page 40: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

42

Example: Requirements

Page 41: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

43

Example: Design Criteria • Design Standards

– Architectural Vocabulary • Words, Photos, Bridging Documents, Etc.

– Quality • Refer to other projects

– Object or Community • Vision Statement

– Communicate Image • What do you want to accomplish

Page 42: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

44

Example: “Best Practice” Visits

Page 43: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

45

Performance Required/Expected

• Community engagement • Innovation and Value - “Iron Sharpens Iron”

– Subcontractors – Specialty, etc.

• Competition versus Progressive – Contract Requirements

• Flexibility and Multiple Solutions • Excellence - Motivated and Driven

Page 44: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

46

Page 45: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

47

Page 46: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Overview • Housekeeping & Introductions

• Planning – Delivery Method Selection

• Planning – Program & Criteria

• Procurement & Competition

• Design Phase

• Construction Phase

• Questions

48

Page 47: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Construction Phase

1. Contractor Input during Prior Phases (Planning/Procurement/Design)

2. How to Deliver what was Agreed to in prior Phases

49

Page 48: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Construction Phase 1. Early Contractor Involvement

A. Detailed Cost Model

B. Scope Differentiation

C. Risk Assessments & Allocation

D. Employ LEAN practices – Pull Planning & TVD (target value design)

E. Subcontracting Options

F. Schedule for the Project

G. Constructability Reviews

50

Page 49: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Early Contractor Involvement – A. Starts w/Cost Model

LA Federal Courthouse Preliminary Cost Model

(Graves) SOM (Cobb) (NBBJ) (AECOM)

image image image

Santa Barbara Courthouse Cost Model

Div: Description: $/SF SF Extended $ LAFCH $/SF Boston $/SF Billings $/SF LB Courthouse $/SF Scope Notes for SB Courthouse Assumptions:

1 General Requirements $ 12.00 95,000 $ 1,140,000 $ 12.00 $ 13.50 $ 15.00 $ 12.00 -Includes General items: cranes, hoisting, safety, survey, security, etc.

2 Site Improvements / Earthwork $ 15.00 95,000 $ 1,425,000 $ 25.00 $ 10.15 $ 23.00 $ 27.25 -Large Excavation already made: this includes S/S, Utilities, Sitework

3 Concrete $ 22.00 95,000 $ 2,090,000 $ 22.00 $ 28.17 $ 36.00 $ 25.12 -Assumes Spread foundations

4 Masonry (Interior Only) $ 8.00 95,000 $ 760,000 $ 8.00 $ 33.40 $ 14.00 $ 6.45 -This scope would include holding cell masonry and BOH Masonry

5 Steel & Metals $ 50.00 95,000 $ 4,750,000 $ 48.00 $ 47.00 $ 37.00 $ 44.10 -Includes Steel at 18 lbs/SF @ $4,000 / ton plus deck, stairs, Misc. & Ornamental Metals

6 Woods & Plastics $ 25.00 95,000 $ 2,375,000 $ 20.00 $ 16.72 $ 11.00 $ 16.20 -Assumes Courtrooms and Chambers per RFP

7 Thermal / Moisture Protect $ 9.00 95,000 $ 855,000 $ 9.00 $ 9.09 $ 19.00 $ 8.60 - Very similar scope as LB: Membrane Roof, Below Grade WP

8 Doors / Windows (Including Skin) $ 50.00 95,000 $ 4,750,000 $ 60.00 $ 14.32 $ 37.00 $ 53.30 - Includes a Skin/Floor Area Ratio of 40% @ Avg $115/SF

9 Finishes $ 65.00 95,000 $ 6,175,000 $ 65.00 $ 38.15 $ 39.00 $ 65.00 -Hard Lid Ceilings about 35 %, Soft Ceilings @ Balance of TI space

10 Specialties $ 3.00 95,000 $ 285,000 $ 3.00 $ 1.61 $ 5.00 $ 3.32 -Flagpoles, Extinguishers, Lockers, etc.

11 Equipment $ 2.00 95,000 $ 190,000 $ 2.00 $ 2.50 $ 6.00 $ 9.80 -LA $/SF does NOT include Detention Equip - which USMS Pub 64 Provides. LB $/SF has incl.

12 Furnishings $ 3.50 95,000 $ 332,500 $ 3.50 $ 2.20 $ 5.00 $ 3.30 -Window Coverings / Entrance Grilles. LB had total FF&E - Taken out of LB number

14 Conveying Equipment $ 25.00 95,000 $ 2,375,000 $ 15.00 $ 7.77 $ 11.00 $ 14.86 - Assumes 4 passenger , 1 freight elevator

15 FP Fire Protection $ 4.50 95,000 $ 427,500 $ 4.50 $ 5.31 $ 4.00 $ 3.52 -Full sprinkler coverage, standpipes, etc.

15 P Plumbing Systems $ 12.00 95,000 $ 1,140,000 $ 12.00 $ 6.53 $ 4.40 $ 10.00 -Includes plumbing for holding cells, justice chambers, typical RR, & drains

15 M Mechanical / Controls $ 50.00 95,000 $ 4,750,000 $ 55.00 $ 37.19 $ 52.00 $ 31.40 -Assumes increased scope to meet LEED Silver

16 Electrical / Low Voltage $ 55.00 95,000 $ 5,225,000 $ 50.00 $ 42.31 $ 33.00 $ 54.40 -Electrical and Lighting Scope to meet new Title 24, plus LED Fixtures

$ 411.00 $ 414.00 $ 315.92 $ 351.40 $ 388.62

Subtotal of Trades $ 39,045,000 $ 608.58 $ 464.40 $ 516.56 $ 571.27 Totals to Compare to SB Courthouse Scope, escalated to 2019

- Major Trades: 8 Trades - 83% 32,490,000

Subcontractor Bonds $ 488,063

Clark General Conditions $ 3,123,600 Other Notable Courthouses:

Subtotal Cost of Work $ 42,656,663 Eugene Courthouse - LEED Gold, Morphosis - 267,000 GSF; $96M Total Cost; $360/SF

Escalation to 2019 $ 5,466,300 Comparative D/B Scope, 2019 Dollars: $475/SF

Tests and Inspections - N/A in CMAR $ - image

Contingency $ 2,342,700

Art in Architecture (by AOC) $ -

Commissioning $ 390,450

Builder's Risk Insurance $ 213,283 Seattle Courhouse - Sustainable ?, NBBJ - 650,000 GSF; $215M Construction Cost; $331/SF

General Liability Insurance $ 277,268 Comparative D/B Scope, 2012 Dollars: $480/SF

Gross Receipts Tax $ 426,567 image

GC Bond $ 533,208

GC Fee $ 2,132,833 Avg of other 7

Grand Total $ 54,439,272 $ 573.04 $559 San Diego Courthouse - Sustainable ?, R. Meier - 467,000 GSF; $300 M Construction Cost; $642/SF

per GSF per GSF Comparative D/B Scope, 2012 Dollars: $796/SF image

51

Page 50: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Early Contractor Involvement – B. Scope Differentiation – Who has What ? C. Risk Allocation – Hazardous Mat’ls, Unforeseens, Insurance

Options, Performance Guarantees, Damages for Delay D. Employ LEAN practices for Planning Design

52

Page 51: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Early Contractor Involvement – E. Review of Subcontracting Options (high performance/high tech

design = design/assist, versus d/b sub selections

F. Never too early to schedule the work

G. Constructability impact on design, scope, and cost

53

Page 52: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Early Contractor Involvement – G. Constructability impact on design, scope, and cost

54

Page 53: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Early Contractor Involvement – G. Constructability impact on design, scope, and cost

55

Page 54: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Early Contractor Involvement – G. Constructability impact on design, scope, and cost

56

Page 55: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Construction Phase 2. Delivery as Promised

A. Annotate the Criteria B. Execute the QA/QC Plan C. Subcontractor Integration D. Continue w/LEAN practices – Pull Planning E. Vendor/Supplier Integration F. Efficient use of A/E team for CA G. Avoid redesign during Construction H. Models/3-D imagery/Mockups! I. Tenant Management J. Begin w/End in Mind

57

Page 56: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Construction Phase 2. Delivery as Promised

A. Fully Annotate the Criteria w/CD input

B. Execute the QA/QC Plan w/Owner’s Input

C. Subcontractor Integration is Key

58

Page 57: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Construction Phase D. Continue w/LEAN practices – Pull Planning

E. Vendor/Supplier awareness of Project Criteria – (i.e.: performance objectives, LEED, etc.)

F. Plan for efficient use of A/E team for CA

G. How to avoid redesign during Construction

59

Page 58: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Construction Phase H. Models/Samples/3-D imagery/Mockups !

I. Planned Owner touch points during Construction – (i.e., tenant management)

60

Page 59: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

Construction Phase J. Begin w/End in Mind

61

Page 60: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

62

QUESTIONS

? ?

Page 61: FROM ALL ANGLESHousekeeping & Introductions • Planning – Delivery Method Selection ... Develop Full Project Budget 3. Look for Gaps 14 Planning Phase . Planning Phase Key Foci

63

THANK YOU!