This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661, the State of Michigan and Michigan State University. Michigan State University designs and establishes FRIB as a DOE Office of Science National User Facility in support of the mission of the Office of Nuclear Physics. Paul Mantica Deputy Laboratory Director and Project Manager 11 September 2016 FRIB Construction Status
26

FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Mar 26, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661, the State of Michigan and Michigan State University. Michigan State University designs and establishes FRIB as a DOE Office of Science National User Facility in support of the mission of the Office of Nuclear Physics.

Paul ManticaDeputy Laboratory Director and Project Manager

11 September 2016

FRIB Construction Status

Page 2: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Funded by U.S. Department of Energy Office of Science (DOE-SC) supporting the mission of the Office of Nuclear Physics in DOE-SCServing over 1,350 usersKey feature is 400 kW

beam power for all ions(5x1013 238U/s)Separation of isotopes

in-flight• Fast development time

for any isotope• Suited for all elements

and short half-lives• Fast, stopped, and

reaccelerated beams

Facility for Rare Isotope BeamsA Future DOE-SC Scientific User Facility for Nuclear Physics

P. Mantica, WG.9 Meeting, September 2016, Slide 2

Page 3: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

8 June 2009 – DOE-SC and MSU sign Cooperative AgreementSeptember 2010 – CD-1 approved, DOE issues NEPA FONSIApril 2012 – Lehman review, baseline and start of civil

constructionAugust 2013 – CD-2 approved (baseline), CD-3a approved (start

civil construction pending FY2014 federal appropriation)March 2014 – Start civil constructionAugust 2014 – CD-3b approved (technical construction)12-14 Jan 2016 DOE Operations Cost Review6-8 December 2016 DOE Office of Project Assessment ReviewJune 2022 – CD-4, managing to early completion in FY21

»First beam from ECR in 2016»Beneficial occupancy of FRIB building in March 2017

FRIB Project is on Track

P. Mantica, WG.9 Meeting, September 2016, Slide 3

Page 4: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

FRIB Facility Layout

P. Mantica, WG.9 Meeting, September 2016, Slide 4

Rare isotope production target Driver linear accelerator

Page 5: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

FRIB Accelerator Systems Superconducting RF Driver Linac

P. Mantica, WG.9 Meeting, September 2016, Slide 5

Accelerate ion species up to 238U with energies of no less than 200 MeV/u

Provide beam power up to 400kW

Energy upgrade to 400 MeV/u for 238U by filling vacant slots with 12 SRF cryomodules

Provisions for ISOL upgrade

Page 6: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Three-stage fragment separator for production and delivery of rare isotope with high rates and high purities to maximize FRIB science reach

Primary beam power of 400 kW and beam energies of ≥ 200 MeV/u

Fragment Separator

P. Mantica, WG.9 Meeting, September 2016, Slide 6

Page 7: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Target hot cell, subterranean• Production target• Fragment preseparator• Primary beam dump• Remote handling equipment

Target Facility OverviewEquipment Installation Underway

Target facility building high bay• Second and third stage of

fragment separator• 50 ton bridge crane• Magnet power supplies

Support areas, 3 subterranean levels• Cascade ventilation• Remote handling gallery and control room• Non-conventional utilities• Waste handling

P. Mantica, WG.9 Meeting, September 2016, Slide 7

Page 8: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Facility for Rare Isotope Beams in 2021

P. Mantica, WG.9 Meeting, September 2016, Slide 8

Page 9: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Aerial View - Progress to Date

P. Mantica, WG.9 Meeting, September 2016, Slide 9

Page 10: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

FRIB Schedule Critical and Near-critical Elements

P. Mantica, WG.9 Meeting, September 2016, Slide 10

Lower cold box

Warm compressors

He transfer lines

Beta=0.53 cold mass

Front-end HV platform

CM assembly area

SC magnet assemblyFloat forecast: 15 weeks

Page 11: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Target Facility Civil Construction ProgressAhead of Schedule

P. Mantica, WG.9 Meeting, September 2016, Slide 11

Remote handling gallery

Hot-cell south viewHot-cell north view

Page 12: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Experimental Systems DivisionVacuum Vessel Fabrication Progressing Well

P. Mantica, WG.9 Meeting, September 2016, Slide 12

Wedge Vessel loaded on Truck in Camden, NJ

Wedge Vessel Seal Retainer

Wedge vessel arrival in Cincinnati, OH

Fabrication is making good progress • Target: Final assembly complete, final

machining underway• Beam dump: Assembly 48% complete• Wedge: Wedge vessel shipped to

machine shop in Cincinnati, OH, final machining completed

Vessel seals procured and in house First vacuum test of Wedge vessel

underway

Page 13: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Cryoplant Construction on Schedule4 K Cold Box; Warm Compressors; Cold Compressors

Warm compressor installed

4 K cold box installation underway• Started in July 2016 with upper coldbox• Lower coldbox delivery in September

Cold compressor• Delivery expected January 2017

4 K upper cold box installed at FRIBWarm compressors installed at FRIB

4 K upper cold box transported to FRIB on a 140’ flatbed truck

P. Mantica, WG.9 Meeting, September 2016, Slide 13

Page 14: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

FRIB Construction ProgressFront End Technical Work Underway – Area Controlled by Technical Staff

P. Mantica, WG.9 Meeting, September 2016, Slide 14

RFQ cold test assembly at vendor

ARTEMIS RT Ion Source

High voltage platforms in the Front End

Page 15: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Production Cryomodules Being AssembledFour Assembly Lines Proceeding in Parallel; Five at Peak

β=0.085 cryomodule #3 being assembled at MSU

β=0.041 cryomodule #1 being assembled at MSU

P. Mantica, WG.9 Meeting, September 2016, Slide 15

Page 16: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

FRIB early completion in FY2021 NSF cooperative agreement for period

2017-2021 forthcoming Transition from NSCL to FRIB

operations can be accomplished in less than a year

» Especially important for experimental nuclear science

NSCL-FRIB Integration Plan Minimal disruption of world-leading science and education program

P. Mantica, WG.9 Meeting, September 2016, Slide 16

Plan enables continued world-class science for LE Community

Page 17: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Transition to Operations Plan

P. Mantica, WG.9 Meeting, September 2016, Slide 17

Users form collaborations, commission detectors and do science with NSCL beams FRIB is commissioned through target before NSCL shutdown Transition from NSCL to FRIB operations in less than a year

• Reconfigure fragment separator• Complete FRIB commissioning

Page 18: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Operate a world-class DOE-SC national user facility• Goal 5,500 hrs/year • Operate 24 hrs/day• Goal of > 90% availability

Cryogenic plant • Operates 6,000 hrs/year at 15 kilowatt (kW) at 4 K• Operates remaining time at lower cooling power

Provide users with • Rare isotope beams characterized on an event-by-event basis• Support to operate permanently-installed experimental equipment• Support to install non-permanently-installed experimental equipment• MSU Department of Environmental Health and Safety (EHS) support• Support for research is not included

Cost estimation developed by FRIB project team and was vetted by United States Department of Energy Office of Nuclear Physics in the Operations Cost Review held 12-14 January 2016

Operations Requirements Assumptions

P. Mantica, WG.9 Meeting, September 2016, Slide 18

Page 19: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

High power accelerator [SNS, PSI, ISIS]• Path to full power (400 kW)• Configuration management• Machine protection• Root cause analysis of failure modes

Heavy ion accelerator [RHIC]• Variety of primary beams• Dynamic range on diagnostics

Full-scale Superconducting RF accelerator [SNS]• Cryoplant• SRF infrastructure for maintenance

In-flight rare isotope beam production at high power [FAIR, RIBF]• Variable targets• Many secondary beams• Fast, stopped, and reaccelerated beams• Safety analysis for each beam, due to high production rates

Remote handling [PSI, SNS, ESS, ISIS]• High radiation levels• Personnel protection• Waste handling and waste reduction• Non-conventional utilities

Maintenance of physical infrastructure, including non-conventional utilities• All systems under one roof - interdependencies create complexity

FRIB Key Features

, Slide 19P. Mantica, WG.9 Meeting, September 2016

While there are facilities world-wide that have a subset of these key features, FRIB is the only facility that comprises such a level of complexity

Page 20: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

FRIB Enables Scientists to Make Discoveries

, Slide 20

Properties of atomic nuclei • Develop a predictive model of nuclei and their interactions• Many-body quantum problem has intellectual overlap to mesoscopic

science, quantum dots, atomic clusters, etc.

Astrophysics: Nuclear processes in the cosmos• Origin of the elements, chemical history• Explosive environments: novae,

supernovae, X-ray bursts …• Properties of neutron stars

Tests of laws of nature• Effects of symmetry violations are

amplified in certain nuclei

Societal applications and benefits• Medicine, energy, material

sciences, national security

P. Mantica, WG.9 Meeting, September 2016

Page 21: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Community Works Together to Define National Priorities

P. Mantica, WG.9 Meeting, September 2016, Slide 21

“Expeditiously completing the Facility for Rare Isotope Beams (FRIB) construction is essential. Initiating its scientific program will revolutionize our understanding of nuclei and their role in the cosmos.” (Recommendation I, Sec. 1)

Long Range Plan for Nuclear Science completed October 2015

Page 22: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Users are organized as part of the independent FRIB Users Organization (FRIBUO) www.fribusers.org• Chartered organization with an elected executive committee • 1,348 members (98 U.S. colleges and universities, 12 national laboratories,

52 countries) as of 31 August 2016• 19 working groups on instruments• 12-13 August 2016, Low Energy Community Meeting, U Notre Dame

“FRIB remains our top priority. The community eagerly anticipates the completion of FRIB and the forefront science this facility will enable”

Science Advisory Committee • Considerations for initial science program (8-9 December 2016)

Over 1,300 Users Engagedand Ready for Science

P. Mantica, WG.9 Meeting, September 2016, Slide 22

Page 23: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

FRIB Science Program: 17 Benchmarks

P. Mantica, WG.9 Meeting, September 2016, Slide 23

Representative list covers the range of capabilities needed

Based on user documents, NRC RISAC report 2007, and NSAC RIB Task Force report 2007

Used by FRIB project to check the facility capabilities

Used at FRIB project to develop the preliminary beam priority development list

Adopted by FRIBUO in 2012 and endorsed by FRIB SAC

Vetted by NSAC LRP implementation committee in 2012 and 2015 Long Range Plan

No Program RI Beams Capability1 Study of Shell

Structure60Ca, 48Ni, 100Sn Fast and reacc(elerated)

3-15 MeV/u

2 SuperheavyElements

16,17,18C, 90Kr 1010/s 6 MeV/u

3 Neutron Skins 48Ni, 84Ni Fast beams > 0.01/s

4 Pairing N=Z to 100Sn, 138Sn

N=Z, n-rich reacc12 MeV/u

5 Nuclear Symmetries 96Kr, 134Sm, 156Ba Fast <100/s, reacc >104/c

6 Equation of State 102Sn, 138Sn > 200 MeV/u

7 r-process 194Er, 195Tm, 196Yb

Fast, stopped, reacc (d,p) at 10 MeV/u

8 15O(α,γ) 15O Low-E, mass separator

9 59Fe s-process 59Fe Harvesting

10 Medical Isotopes 149Tb Harvesting, reacc (ISOL)

11 Stewardship 88,89Zr, 78Br Harvesting, reacc

12 Atomic EDM 225Ra, 229Pa Harvesting, High Z, ISOL

13 Limits of Stability 76Cr, 88Ni, 122Zr 3-stage separator

14 Halo Nuclei 76Cr Drip-line nuclei

15 Mass Surface 79Ni, 195Ta Penning Trap, TOF

16 rp-process 64Ge, 65As, 70Kr Mass separator

17 Weak Interactions 82Ge, 102Zr Fast 100-200 MeV/u

Page 24: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Experimental Equipment For Initial Science Day-one Instruments Have Already Been Commissioned and Are Ready

P. Mantica, WG.9 Meeting, September 2016, Slide 24

Device NRC Science Benchmarks

NS NA FS App

SeGA 1,4,5,14 7,17

Beta-NMR 1,2,14

BCS 1,5 7,16 12

HiRA/LASSA 1,2,4,5,6 12 10

LEBIT 15 7

MoNA-LISA 1,14 17

Neutron Walls 6

NERO/3HeN 1 7

S800 1,3-5,13-15 16,17

Sweeper Magnet 1,14 17

RFFS 1,4,5,6,13 16

TriPLEX 1,4,5,14

92-inch Chamber 1,2,6 16

Diamond Detectors 1,3-6, 13-15 7,16

BECOLA 1.3 12

LENDA/VANDLE 3 17

Device NRC Science Benchmarks

NS NA FS App

DDAS 1,4,5,14 7,16

CAESAR 1,4,5,14

AT-TPC 1,3,4,6 16

SuN/MTAS 1 7,17 10

Liquid H-Target 1,3 17

CFFD 2

JANUS 1,5 12

JENSA 16

ANASEN 1,2,4 8,16

GAMMASPHERE 1,4,5,12

GRETINA 1,2,3,4,5 16,17 12 11

He-Jet 9 12 10

superORRUBA 1,4 7,16

superCHICO 1,4,5 12

ORISS 15 7

Page 25: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

Four large detector systems identified in 2015 Nuclear Physics Long Range Plan• GRETA gamma detector array (CD0), LBNL

» Exploration of the structure of new nuclei with maximum resolving power and acceptance

• SECAR recoil separator (project underway), MSU» Direct measurement of thermonuclear reactions in

exploding and exotic stars• High Rigidity Separator (HRS) (pre-conceptual design),

MSU» Evolution of shell structure, single particle structure of

rare isotopes, limits of stability• Decay station (pre-conceptual design), UT Knoxville

» Structure of most exotic isotopes, site of the r-process

Technical interfaces and requirements are carefully considered

Experimental Equipment For Initial Science Road-map for New Major Equipment in Place

P. Mantica, WG.9 Meeting, September 2016, Slide 25

Page 26: FRIB Construction Status - TRIUMF · 2016. 9. 8. · civil construction pending FY2014 federal appropriation) March 2014 – Start civil construction August 2014 – CD-3b approved

FRIB to become a world-leading DOE-SC scientific user facility for rare isotope science• Highest-power heavy ion linac worldwide• High-performance fragment separator• Fast, stopped, and reaccelerated beams

FRIB project making appropriate progress • Civil construction ahead of schedule• Technical construction advancing well

Strong, growing, and committed FRIB user group in place• Experimental equipment used now at NSCL, ready for FRIB science• New equipment investments will enable FRIB to optimize science outcomes

Opportunities for discovery science• Aiming for a predictive model of the nuclear force• Revealing the origin of the elements in the cosmos• Harvesting isotopes for their societal benefits

Summary

, Slide 26P. Mantica, WG.9 Meeting, September 2016