PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
Provided by
www.pm-exam-simulator.com
This presentation showcases free sample
questions to help you study for the PMP exam
You are performing Earned Value Management
on your project. The Cost Baseline in Earned
Value Management is also a part of:
A. Cost Estimating Baseline
B. Performance Baseline
C. Cost Measurement Baseline
D. Budget Baseline
The keyword to look here is
'performance'.
B. Performance Baseline
A Cost Baseline is a part of the Performance
Baseline.The Performance Baseline is an
approved plan for the project work to which the
project execution is compared, and deviations
are measured for management control. The
Performance Baseline typically integrates the
scope, schedule and cost parameters of a
project.
You are developing your project's Human
Resource Management Plan. Your sponsor
asked you to take the historical information
from previous projects to determine this
project's human resource roles and
responsibilities. Which of the following sources
contains this information?
A. Organizational Process Assets
B. Enterprise Environmental Factors
C. Project Management Plan
D. Project Charter
Look for the keyword phrase
'historical information'. Only one of
these options contains historical
information.
A. Organizational Process Assets
Organizational Process Assets
contain historical information
about previous projects.
According to Philip Crosby, which of the
following is a correct statement about
quality?
A. The definition of quality is non-conformance to
requirements
B. The system of quality is Defect Control
C. The measurement of quality is the price of non-
conformance
D. The performance standard is zero defects
Philip Crosby proposed the zero
defects theory.
D. The performance standard is
zero defects
According to Philip Crosby, the
performance standard is zero defects.