PINOLE MIDDLE SCHOOL SOCCER FIELD FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District
10

FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

Jan 15, 2016

Download

Documents

Kory Phelps
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

PINOLE MIDDLE SCHOOL SOCCER

FIELD

FRED POWELLPOWELL & PARTNERS, ARCHITECTS

West Contra Costa Unified School District

Page 2: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

SITE PLAN

ORIGINAL CONDITION

Page 3: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

SITE PLAN

REVISED CONDITION

Page 4: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

Pinole Middle School – Main Entry

Page 5: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

Pinole Middle School

Page 6: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

Pinole Middle School - Existing Conditions

Page 7: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

CONSTRUCTION SITE PHOTOS

Page 8: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

CONSTRUCTION SITE PHOTOS

RESTROOM BUILDING

Page 9: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

BUILDING ELEVATIONS

COLOR SCHEME

Page 10: FRED POWELL POWELL & PARTNERS, ARCHITECTS West Contra Costa Unified School District.

SCHEDULE

COST & SCHEDULE STATUS

Notice to Proceed – 5/19/2014

Completion Date – 2/27/2015

CONSTRUCTION COST UPDATE

Original Contract Amount - $3,959,000

Changes Orders to Date - $13,039.00