FRC - Public Transport Strategy Presentation to SEStran Board Friday 13 August 2010.
Jan 04, 2016
FRC - Public Transport Strategy
Presentation to SEStran Board
Friday 13 August 2010.
FRC - Public Transport Strategy
The Proposed Works
Public Transport Strategy
Inverkeithing
Ferrytoll
North Queensferry
South Queensferry
Queensferry Junction
Kirkliston
M9 Jtcn 1A
Public Transport Strategy
• Bill Progress
• Developing a Public Transport Strategy
Public Transport Strategy
• Developing a Public Transport Strategy
• Cross Forth demands analysed
• Scenarios considered
• Action Plan has been prepared.
TEMPORARY
SCHEMES AND MEASURES BEING CONSIDERED TO SUPPORT THE MANAGED CROSSING STRATEGY IN DELIVERING THE PUBLIC TRANSPORT STRATEGY
Intervention Timescale for Delivery
Indicative Cost (£) Lead Authority
Halbeath Park and Choose Short term(<5 years)
£7-10 m (from Fife Council work)
Fife Council
Rosyth Park and Choose Short term(<5 years)
£4-6m (from Fife Council work) Fife Council
Temporary Southbound Hard Shoulder Running for buses on M90 north of Admiralty (Included in Fife ITS scheme)
Short term(<5 years)
£5m Transport Scotland
Bus Priority Improvements at Admiralty Junction
Short term(<5 years)
£0.5m - £1M Fife Council/Transport Scotland
Hard Shoulder Running for buses on M9 approach to Newbridge
Short term(<5 years)
£0.5m - £1M City of Edinburgh Council/ Transport Scotland
Improvements to Newbridge Interchange Medium term(5 – 10 years)
£4.5m (from Halcrow work for City of Edinburgh Council)
City of Edinburgh Council/Transport Scotland
New slips from B800 to M9 Spur including dedicated right turn lane.
Medium term(5 – 10 years)
£2m - £3M City of Edinburgh Council/Transport Scotland
Hard Shoulder Running for buses on M90 north of Admiralty (corridor enhancement)
Medium term(5 – 10 years)
£10M Transport Scotland
Bus lanes on A8 westbound Bus Lane on A89 Eastbound
Short term(<5 years)
£7.2m (from Halcrow work for City of Edinburgh Council)A8 Westbound £2m - £2.5MA89 Eastbound £0.5m -£1M
Progress to date
Works Include Progress Timescale
MainWorks
Cable – stayed bridge
Trunk roadconnections
ITS
Two consortia of major international civil engineering companies have been selected.
Award Spring 2011
Completed by 2016
Junction 1A
Widening M9
New slip roads
ITS
Advertised 8 June 2010.
Expect four tenderers
Estimated between £46m &£55m
Start July 2011
Completed byDecember 2013
ITS –Fife
Admiralty to Halbeath
Procurement started. Scheme estimate is £15 to£22m
Start May 2011
Completed by July 2012
Summary
• Main works on target
• Ongoing partnership working for PTS.