Frame and Cornice Construction Sequence
12

Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Dec 15, 2015

Download

Documents

Joseph Raynor
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Frame and Cornice Construction Sequence

Page 2: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Top Plate

Double Plate

Wall Stud (top half)Corner Post

Frame and Cornice Construction SequenceWalls & Partitions Framed

(Cut-away view of corner of a larger structure)

Page 3: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Wall Sheathing

Frame and Cornice Construction SequenceExterior Sheathing Applied

Page 4: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Ceiling Joist

Frame and Cornice Construction SequenceCeiling Joists Placed

Page 5: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Frame and Cornice Construction SequenceRoof Rafters – Gable Lookouts Installed

Common Rafter

(bottom half)

Lookout

RafterTail

Barge Rafter (sometimes called a Fly

Rafter)

Page 6: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

False Facia (Sometimes

called Rough

Facia)

Frame and Cornice Construction SequenceFalse Facia Installed

Page 7: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Roof Sheathing

covered with Shingles

Frame and Cornice Construction Sequence

“Dry-in” achieved. The

remainder of the process occurs

under the covered roof.

Roof Sheathing & Shingles Installed

Page 8: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Gable Studs

Lookouts

Frame and Cornice Construction Sequence

Roof covering removed for

clarity

Lookouts – Lookout Ledger – Gable Studs – Gable Sheathing Installed

Lookout Ledger

Page 9: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Soffit(Sometimes called

Plancier)

Frame and Cornice Construction Sequence

Roof covering removed for

clarity

The Underside of Cornice (Soffit) installed

Page 10: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Finish Facia

Frame and Cornice Construction Sequence

Roof covering removed for

clarity

Facia Installed

Page 11: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Frame and Cornice Construction Sequence

All Cut-aways viewed together

Facia Work Completed

Page 12: Frame and Cornice Construction Sequence. Top Plate Double Plate Wall Stud (top half) Corner Post Frame and Cornice Construction Sequence Walls & Partitions.

Frame and Cornice Construction Sequence

Presentation Complete