SULTANATE OF OMAN
MINISTRY OF TRANSPORT AND COMMUNICATIONS DIRECTORATE GENERAL OF
ROADS & LAND TRANSPORT
MUSCAT
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT TENDER NO. 51/2012
MONTHLY PROGRESS REPORT NO. 11
NOVEMBER 2014
CONSULTANT:
RENARDET S.A. & PARTNERS CONSULTING ENGINEERS LLC. P.O. Box
579, Muscat, P.C. 100, Sultanate of Oman
CONTRACTOR:
CONSOLIDATED CONTRACTORS CO. LLC P.O. Box 614, Muscat, P.C. 100,
Sultanate of Oman
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 1
Table of Contents
1. PROJECT PARTICULARS
..............................................................................................................................................
2
2. SCOPE OF WORK
.......................................................................................................................................................
3
3. TYPICAL CROSS SECTIONS
..........................................................................................................................................
4
4. SITE VISITS/ MEETINGS
..............................................................................................................................................
6
5. ENGINEERS SITE STAFF
.............................................................................................................................................
7
6. PROGRESS S-CURVE
...................................................................................................................................................
8
7. STATUS OF MAJOR ACTIVITIES
................................................................................................................................
10
8. BRIDGE PROGRESS SCHEDULE
.................................................................................................................................
11
9. MSE WALLS PROGRESS SCHEDULE
...........................................................................................................................
12
10. BOX CULVERTS PROGRESS SCHEDULE
......................................................................................................................
15
11. PROGRESS STATUS OF UTILITY CROSSING DUCTS
....................................................................................................
19
12. PROJECT PROGRESS STRIP CHART
...........................................................................................................................
22
13. FINANCIAL STATUS OF PAYMENTS
..........................................................................................................................
28
14. DETAILS OF EQUIPMENT AVAILABLE AT SITE
...........................................................................................................
29
15. DETAILS OF MANPOWER AVAILABLE AT SITE
..........................................................................................................
31
16. QA/QC REPORTS
......................................................................................................................................................
33
17. STATUS OF MATERIAL APPROVALS
..........................................................................................................................
38
18. ENGINEERS COMMENTS
.........................................................................................................................................
40
19. PROGRESS PHOTOGRAPHS
......................................................................................................................................
41
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 2
1. Project Particulars
Client: Ministry of Transport & Communications
P.O. Box 684, Muscat, Postal Code 113
Directorate General of Roads
Sultanate of Oman.
Consultant: Renardet S.A & Partners L.L.C.
P.O. Box 579, Muscat, Postal Code 100
Sultanate of Oman.
Contractor: Consolidated Contractors Company L.L.C.
P.O. Box 614, Muscat, Postal Code 100
Sultanate of Oman.
Project Commencement Date: 30.10.2013
Mobilization Period: 60 Days
Construction Period: 548 Days
Completion date: 29.06.2015
Original Contract Value:
(Including Contingencies) R.O. 17,884,403.000
Amount of Contingencies: R.O. 1,402,155.613
Original Contract Value:
(Excluding Contingencies) R.O. 16,482,247.387
Planned Physical Progress for November
2014 7.98%
Actual Physical Progress for November
2014 6.02%
Planned physical progress cumulative up to
end of November 2014
55.53%
Achieved physical progress cumulative up
to end of November 2014 51.41%
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 3
2. Scope of Work
This project is located in Batinah Region on existing Batinah
Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing
roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0
km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on
plans. Also included in the scope of
work is the construction of service roads, pedestrian
underpasses.
The work also includes expropriation of properties,
relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works
and traffic signals.
Major items within the scope of work consist of but not limited
to the following:
Removal of existing asphalt surface, extension of existing
embankment and earthwork to
achieve the designed profile and gradient.
Removal of existing drainage structures and construction of new
ones including protection
works as shown on construction drawings and as directed.
Expropriation of open/built up properties and removal of
existing structures thereupon.
Construction of interchange ramps, Box Girder Bridge,
roundabout, pedestrian underpasses and
service roads.
Provision of new street lighting system/traffic signals and
removal/disposal of existing street
light poles including conductors/cables, transformers, feeder
pillars, foundations etc., all for the
proper completion of the job.
Construction of earthen embankment/sub grade, sub-base,
aggregate base course, bituminous
base course and bituminous wearing course as per details on the
construction drawings.
Installation of road side furniture (traffic signs, road marking
etc.) and protection works on
embankment slopes.
Relocation/Protection of existing LT, 11KV and 33KV transmission
lines and allied items
(transformers etc.) as per the requirements of concerned
authority.
Relocation/Protection of existing utilities (sewerage,
telephone, electricity, water lines and
irrigation) as per the requirements of concerned
authorities.
Provision of ducts for future utilities as per the requirements
of utility operator.
Construction of concrete safety barriers, fixing of guard rails
and paving tiles.
Provision of traffic diversion in coordination with concerned
authorities.
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 4
3. Typical Cross Sections
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 5
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 6
4. Site visits/ Meetings
S. No. Details of Site Visit/ meeting Date Final Outcome/
Decisions
1 Visit to Independent Laboratory in
Italy for witnessing the testing of Pot
Bearings
09.11.2014
to
14.11.2014
One Fixed Bearing and one
Guided Bearing are tested and
found in compliance with standard
requirements.
2 Monthly review meeting at Project
Office
24.11.2014 Various project issues are discussed.
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 7
5. Engineers Site Staff
S.
No. Name Designation
Date of
Joining
1. Roberto Benigni Head Supervision Projects
2. Muneer Abdul Resident Engineer 19.03.2014
3. Hussein Shah Material Engineer 04.01.2014
4. Ernesto B. Paredes Bridge Engineer 16.04.2014
5. Sande H Tangaras Civil Engineer 08.06.2014
6. Danilo Quantity Surveyor 19.06.2014
6. Mohamed Safie Land Surveyor 04.01.2014
7. Aseef Iqbal Site Inspector 10.02.2014
8. Alaa Aldin Abdelfatah Site Inspector 30.03.2014
9. Walid Samy Abdoh Mostafa Material Inspector 01.04.2014
10. Haneefa Mohmmed Al Zadjali Secretary 13.04.2014
-
6. Progress S-Curve
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Apr May Jun Jul Aug Sep Oct
0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72
4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -
0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 7.69 7.98 8.32
6.96 6.50 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62
- 0.28 0.18 1.01 3.20 5.35 5.18 7.36 7.30 9.33 6.20 6.02 - - - -
- - - - - - -
0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86
76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00
100.00 100.00
0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55
55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38
100.00
- 0.28 0.45 1.46 4.66 10.01 15.19 22.55 29.86 39.18 45.39
51.41
CUMULATIVE PROGRESS
CL14 Org Plan Cumulative %
Actual Cumulative
2014 2015
MONTHLY PROGRESS
CL14 Org Plan per Month %
Actual per Month
Revised Sch. per Month %
Revised Sch. Cummulative %
0.00
20.00
40.00
60.00
80.00
100.00
120.00
-
2
4
6
8
10
12
Dec
Jan
Fe
b
Ma
r
Apr
Ma
y
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Fe
b
Ma
r
Apr
Ma
y
Jun
Jul
Aug
Sep
Oct
2013 2014 2015
% C
um
ula
tive
% M
ON
TH
LY
MONTHS
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMANMONTHLY CL
14 PLANNED VS. ACTUAL MANHOURS
CL14 Org Plan per Month % Revised Sch. per Month % Actual per
Month CL14 Org Plan Cumulative % Revised Sch. Cummulative % Actual
Cumulative
-
REV.: 0
PERIOD ENDING: Nov-14
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Apr May Jun Jul Aug Sep Oct
CL14 Plan % 0.30 8.67 19.23 26.89 31.77 36.64 41.51 46.39 51.26
56.13 61.01 65.88 70.76 75.63 80.50 85.38 90.25 95.13 100.00 100.00
100.00 100.00 100.00
Revised Plan % 4.11 9.30 17.58 24.18 30.90 35.16 38.97 42.78
46.60 50.41 54.23 58.04 61.86 65.67 69.48 73.30 77.11 80.93 84.74
88.56 92.37 96.18 100.00
Actual - 6.62 13.03 22.36 37.31 43.00 44.11 51.21 56.24 60.13
65.67 69.96
CL14 Plan % 0.00 0.00 0.38 20.37 47.70 48.33 48.33 48.33 48.33
48.33 48.33 48.33 48.33 59.91 77.84 90.27 94.93 100.00 100.00
100.00 100.00 100.00 100.00
Revised Plan % - - - - - 7.40 29.85 78.13 78.13 78.13 78.13
78.13 78.13 78.13 78.13 78.13 78.13 80.66 87.59 88.57 100.00 100.00
100.00
Actual - 10.09 10.09 17.59 19.52 77.42 69.96 70.18 70.18 70.18
83.49 84.12
CL14 Plan % 0.00 0.00 0.00 0.78 6.58 16.76 29.38 41.37 58.64
66.60 74.18 82.85 84.75 84.75 85.24 92.34 92.34 98.36 100.00 100.00
100.00 100.00 100.00
Revised Plan % - - - - - - - 3.32 12.89 28.83 43.89 60.03 74.82
90.03 95.24 95.95 95.95 96.09 98.30 99.46 99.54 100.00 100.00
Actual - - - - 4.35 4.89 - 5.27 14.93 29.52 47.15 47.31
CL14 Plan % 0.00 0.00 1.01 9.21 29.30 45.91 56.90 62.24 64.59
67.94 69.08 69.08 75.05 82.85 93.48 98.64 100.00 100.00 100.00
100.00 100.00 100.00 100.00
Revised Plan % - - - - - 4.26 8.17 16.03 32.68 53.13 67.05 67.47
67.47 67.90 68.32 68.32 68.32 81.11 93.02 97.11 100.00 100.00
100.00
Actual - - - 5.00 5.00 53.23 62.16 74.91 78.29 91.86 98.62
115.33
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.07 26.27
41.98 59.98 78.73 79.90 79.90 85.20 89.45 92.60 100.00 100.00
100.00 100.00 100.00
Revised Plan % - - - - - - - - - - - 3.58 17.42 31.37 51.32
75.82 75.82 75.82 75.82 87.25 87.25 98.60 100.00
Actual 1.26 3.19 5.42
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08
7.77 19.32 31.22 44.94 51.98 52.14 90.14 90.14 100.00 100.00 100.00
100.00 100.00
Revised Plan % - - - - - - - - - - - - - 0.08 8.44 22.42 46.57
51.97 51.97 86.66 90.05 93.03 100.00
Actual
CL14 Plan % 0.00 0.00 0.23 1.43 2.97 10.17 23.65 36.51 51.47
63.06 74.26 75.97 77.37 80.05 82.40 88.97 92.13 98.55 100.00 100.00
100.00 100.00 100.00
Revised Plan % - - - 0.26 2.64 7.33 20.62 35.14 50.06 62.76
68.40 72.78 74.07 74.67 83.42 84.04 84.30 87.32 95.58 98.11 99.44
100.00 100.00
Actual - - - 0.48 1.26 5.59 14.93 27.72 40.08 55.38 66.20
71.35
CL14 Plan % 0.00 0.00 4.02 15.21 34.62 57.89 69.26 81.40 83.38
83.46 84.50 92.89 99.96 100.00 100.00 100.00 100.00 100.00 100.00
100.00 100.00 100.00 100.00
Revised Plan % - - - - 2.77 7.75 13.76 22.09 29.64 39.02 49.64
59.51 71.33 85.14 87.00 93.50 100.00 100.00 100.00 100.00 100.00
100.00 100.00
Actual - - - 0.01 6.05 14.73 18.14 22.33 26.30 30.75 34.14
46.19
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.38 1.21 2.63 3.42 4.23
5.50 6.08 6.08 34.35 99.38 99.76 99.76 100.00 100.00 100.00 100.00
100.00 100.00
Revised Plan % - - - - - - - - - - 8.09 26.17 57.85 78.53 94.70
94.70 94.70 94.70 98.41 100.00 100.00 100.00 100.00
Actual - - - 2.50 36.38 14.39 13.24 16.19 16.72 27.56 21.22
41.44
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.80 17.87 43.85
61.59 72.98 81.15 83.94 84.42 85.35 92.86 96.39 100.00 100.00
100.00 100.00 100.00
Revised Plan % - - - - - - - - - - 7.02 20.33 38.29 50.60 59.52
72.89 81.07 83.55 86.89 90.26 95.34 98.27 100.00
Actual - - - - - 2.61 4.98 6.42 8.31 10.67 12.36 14.45
CL14 Plan % 0.00 0.00 0.00 4.43 17.23 33.36 49.13 65.07 80.79
93.82 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
100.00 100.00 100.00 100.00 100.00
Revised Plan % - - - - - 0.99 2.30 17.26 33.64 49.01 64.70 79.88
95.44 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
100.00 100.00
Actual - - - 6.16 9.87 17.63 25.69 35.90 49.03 65.95 72.27
72.29
CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.17 0.79 1.43 5.65 13.41
21.84 30.56 32.94 70.94 75.04 94.02 96.43 100.00 100.00 100.00
100.00 100.00 100.00
Revised Plan % - - - - - - - 0.33 2.34 9.42 17.07 23.51 31.40
41.66 47.49 47.55 47.55 83.28 93.95 97.61 100.00 100.00 100.00
Actual - - - 0.13 5.52 9.26 13.38 16.87 17.75 20.45 14.38
26.70
Revised Plan 0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78
39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64
98.27 99.38 100.00
Actual Cum - 0.28 0.45 1.46 4.66 10.01 15.19 22.55 29.86 39.18
45.39 51.41 - - - - - - - - - - -
2013
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Apr May Jun Jul Aug Sep Oct
0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72
4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -
0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 7.69 7.98 8.32
6.96 6.50 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62
- 0.28 0.18 1.01 3.20 5.35 5.18 7.36 7.30 9.33 6.20 6.02
0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86
76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00
100.00 100.00
0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55
55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38
100.00
- 0.28 0.45 1.46 4.66 10.01 15.19 22.55 29.86 39.18 45.39
51.41
2014 2015
MONTHLY PROGRESS
CL14 Org Plan per Month %
Actual per Month
CUMULATIVE PROGRESS
CL14 Org Plan Cumulative %
Actual Cumulative
MMEP Works &
Ducts#REF!
TOTAL #REF!
Revised Sch. per Month %
Revised Sch. Cummulative %
#REF!
#REF!
L MSE walls #REF!
J Drainage Works #REF!
KIncidental
Construction#REF!
#REF!
#REF!
#REF!
IConcrete for
Bridge#REF!
H
Concrete for
Box Culvert
/Underpas
#REF!#REF!
#REF!
GBituminous
Pavement#REF!
FSubbase &
Aggregate Base#REF!#REF!
#REF!
EStructural
Excavation#REF!
D Embankment #REF!#REF!
#REF!
C
Clearing &
Removal of
Obstructions
#REF!
2015
B Road Diversions #REF!
Budgeted
Man-Hrs
#REF!
#REF!
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN
MANHOURS OVERALL PROJECT S-CURVE
Item Description Wtd.
%
Plan/
Actual
2014
-
7. Status of Major Activities
Sl. No.
Description Unit BOQ Qty.
(Revised)
Actual Qty.
% Completion
1 Clearing & Grubbing M2 162,000 129,901 80.19%
2 Borrow Excavation (to embankment)
M3 340,000 155,167 45.64%
3 Granular Sub-base M3 28,700 6,449 22.47%
4 Concrete for Culverts M3 15,000 12,805 85.37%
5 Concrete for Bridge M3 13,805 3,991 28.91%
6 Steel reinforcement Fixing ton 4,900 2,477 50.55%
7 Working Piles M3 2,826 2,826 100.00%
8 Mortared Stone Riprap M3 5,210 0.00 0.00%
9 MSE Walls M2 13,200 7,389 55.97%
11 RCC Drainage Pipes LM 4,530 1,035 22.85%
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 11
8. Bridge Progress Schedule
ACTIVITY AB1 L P1L P2L P4L P5L AB2 LPEDESTAL/POT
BEARING9-Nov-14 9-Nov-14 9-Nov-14 15-Nov-14 - - -
PIER N/A - - - - N/A
2nd Lift - 13-Aug-14 19-Aug-14 29-Sep-14 4-Sep-14 -
Height (m) - 6.920 6.920 6.920 6.920 -
1st Lift - 23-Jul-14 7-Aug-14 15-Sep-14 10-Aug-14 -
Height (m) - 1.153 1.210 1.248 1.225 -
BIT. PAINTING - 28-May-14 26-Jun-14 4-Sep-14 23-Jun-14 -
PILE CAP (Pier &
Abut.)4-Nov-14 17-May-14 18-Jun-14 25-Aug-14 11-Jun-14 -
F/P & BLINDING 21-Oct-14 11-May-14 11-Jun-14 17-Aug-14
3-Jun-14 -
ACTIVITY AB1 R P1R P2R P4R P5R AB2 RPEDESTAL/POT
BEARING16-Oct-14 14-Oct-14 14-Oct-14 16-Oct-14 - - - -
PIER N/A - - - - N/A
2nd Lift - 9-Jun-14 28-Jun-14 20-Sep-14 10-Jul-14 -
Height (m) - 6.920 6.920 6.920 6.920 -
1st Lift - 20-May-14 11-Jun-14 10-Sep-14 22-Jun-14 -
Height (m) - 0.366 0.423 0.461 0.438 -
BIT. PAINTING - 12-May-14 25-May-14 4-Sep-14 31-May-14 -
PILE CAP (Pier &
Abut.)9-Oct-14 4-May-14 13-May-14 27-Aug-14 20-May-14 -
F/P & BLINDING 2-Oct-14 27-Apr-14 7-May-14 20-Aug-14
14-May-14 -
BRIDGE SUB-STRUCTURE PROGRESS SCHEDULE
SUB-STRUCTURE WORK PROGRESS (RHS)
SUB-STRUCTURE WORK PROGRESS (LHS)
P3L
24-Jul-14
6.920
29-Jun-14
1.440
17-May-14
-
8-May-14
1-May-14
0.649
8-May-14
30-Apr-14
22-Apr-14
P3R
-
22-Jun-14
6.920
26-May-14
AB1 L P1L P2L P3L P3L P4L P5L AB2 L
EXPANSION JOINT - - - - - - - -
CONCRETE BARRIER - - - - - - - -
TOP SLAB (DECK) - - - - - - - -
WEB: - - - - - - - -
W1 - - - - - - - -
W2 - - - - - - - -
W3 - - - - - - - -
W4 - - - - - - - -
BOTTOM SLAB
(BASE)- - - - - - - -
AB1 R P1R P2R P3R P3R P4R P5R AB2 R
EXPANSION JOINT - - - - - - - -
CONCRETE BARRIER - - - - - - - -
TOP SLAB (DECK) 26-Nov-14 26-Nov-14 26-Nov-14 26-Nov-14 - - -
-
WEB: - - - - - - - -
W1 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -
W2 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -
W3 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -
W4 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -
BOTTOM SLAB
(BASE)28-Oct-14 28-Oct-14 28-Oct-14 28-Oct-14 - - - -
ACTIVITY (RHS)SUPER-STRUCTURE (SPAN 1 - RHS) SUPER-STRUCTURE
(SPAN 2 - RHS)
BRIDGE SUPER-STRUCTURE PROGRESS SCHEDULE (BOX GIRDER)
SUPER-STRUCTURE (SPAN 4 - LHS) SUPER-STRUCTURE (SPAN 3 -
LHS)ACTIVITY (LHS)
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 12
9. MSE Walls Progress Schedule
DATE Elevation DATE
FROM TOFOUNDATION
/BLINDINGFROM TO
FOUNDATION
/BLINDING
22+702.653 22+760 2-Oct-14 22+718.936 22+810 17-Sep-14
3-Oct-14 18-Sep-14
22+760 22+825 30-Sep-14 22+810 22+893.032 9-Aug-14
1-Oct-14 10-Aug-14
22+825 22+840 13-Jul-14 22+893.032 22+976.294 13-Aug-14
14-Jul-14 14-Aug-14
22+840 22+880 6-Jul-14 22+976.294 23+040 18-Aug-14
13-Jul-14 19-Aug-14
22+880 22+908.387 10-Aug-14 23+040 23+088.046 26-Jul-14
11-Aug-14 27-Jul-14
22+908.38722+969.478 3-Jul-14 23+088.046 23+130 21-Jul-14
5-Jul-14 22-Jul-14
22+969.478 23+000 4-Aug-14 23+130 23+191.774 7-Jul-14
5-Aug-14 10-Jul-14
23+000 23+025 20-Jul-14 23+191.774 23+270.800 26-Jun-14
21-Jul-14 27-Jun-14
23+025 23+070 17-Jul-14
18-Jul-14
23+070 23+140 30-Jun-14
1-Jul-14 DATE
23+140 23+164.573 16-Jun-14 FROM TOFOUNDATION
/BLINDING
17-Jun-14 23+270.762 (L)23+270.800 (R ) 26-Jun-14
23+164.57323+237.536 23-Jun-14 27-Jun-14
24-Jun-14
23+237.53623+270.762 17-Jun-14
18-Jun-14
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
MSE WALL MONTHLY SCHEDULE (FOUNDATION @ APPROACH 1)
El. 21.20
LOCATION (AB 1)
Elevation
Elevation
LOCATION (LHS)
El. 21.20
El. 22.00
El. 22.00
LOCATION (RHS)
El. 20.40
El. 22.00
El. 22.00
El. 22.80
El. 22.00
El. 20.40
El. 22.80
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 13
22+840 22+880 22+908.387 22+969.478 22+991 23+084 23+164.573
23+237.536 23+270.762
34.800 - - - - - - - - -34.000 - - - - - - - - -33.200 - - - - -
- - - -32.400 - - - - - - - - -31.600 - - - - - - - - -30.800 - - -
- - - - - -30.000 - - - - - - 13-Nov-14 13-Nov-14 -29.200 - - - - -
- 19-Oct-14 1-Oct-14 1-Oct-1428.400 - - - - - - 18-Oct-14 24-Sep-14
24-Sep-1427.600 - - - - - 30-Nov-14 20-Sep-14 18-Sep-14
18-Sep-1426.800 - - - - - 18-Nov-14 9-Sep-14 15-Sep-14
15-Sep-1426.000 - - - - - 20-Oct-14 4-Sep-14 28-Aug-14
28-Aug-1425.200 - - - 5-Nov-14 5-Nov-14 16-Sep-14 26-Aug-14
19-Aug-14 19-Aug-1424.400 - 25-Nov-14 25-Nov-14 29-Oct-14 29-Oct-14
4-Sep-14 18-Aug-14 6-Aug-14 6-Aug-1423.600 10-Nov-14 10-Nov-14
10-Nov-14 21-Sep-14 17-Sep-14 27-Aug-14 13-Aug-14 24-Jul-14
24-Jul-1422.800 22-Sep-14 22-Sep-14 22-Sep-14 11-Sep-14 24-Aug-14
9-Aug-14 28-Jul-14 - 13-Jul-1422.000 3-Sep-14 3-Sep-14 3-Sep-14
28-Aug-14 - - - - -21.200 28-Aug-14 28-Aug-14 28-Aug-14 - - - - -
-
20.400 - - - - - - - - -
22+81022+893.03
2
22+976.29
423+035
23+088.04
6
23+191.77
4
23+270.80
0
23+270.762
(L)
23+270.800
(R )
33.200 - - - - - - - - -32.400 - - - - - - - - -31.600 - - - - -
- - - -30.800 - - - - - - - - -30.000 - - - - - - - - -29.200 - - -
- - 16-Nov-14 30-Sep-14 28-Sep-14 28-Sep-1428.400 - - - - -
30-Sep-14 24-Sep-14 24-Sep-14 24-Sep-1427.600 - - - - - 27-Sep-14
18-Sep-14 19-Sep-14 19-Sep-1426.800 - - - 16-Nov-14 16-Nov-14
13-Sep-14 13-Sep-14 11-Sep-14 11-Sep-1426.000 - - - 20-Oct-14
20-Oct-14 2-Sep-14 31-Aug-14 28-Aug-14 28-Aug-1425.200 - -
18-Nov-14 18-Oct-14 18-Oct-14 24-Aug-14 18-Aug-14 18-Aug-14
18-Aug-1424.400 - - 23-Oct-14 20-Sep-14 20-Sep-14 13-Aug-14
6-Aug-14 7-Aug-14 7-Aug-1423.600 - 16-Nov-14 25-Sep-14 8-Sep-14
8-Sep-14 9-Aug-14 24-Jul-14 24-Jul-14 24-Jul-1422.800 - 19-Oct-14
18-Sep-14 21-Aug-14 18-Aug-14 - 13-Jul-14 13-Jul-14 13-Jul-1422.000
27-Nov-14 23-Sep-14 26-Aug-14 - - - - - -21.200 27-Nov-14 4-Sep-14
- - - - - - -
20.400 - - - - - - - - -
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
MSE WALL MONTHLY SCHEDULE (PANELS FIXING @ APPROACH 1)
RHS (AB 1), from Sta. 22+718.936 to Sta. 23+270.800
ELEV.
ELEV.
AB 1 Face
LHS (AB 1), from Sta. 22+702.653 to Sta. 23+270.762
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 14
DATE DATE
FROM TOFOUNDATION
/BLINDINGFROM TO
FOUNDATIO
N /BLINDING
23+508.239 23+520 15-Sep-14 23+508.239 (L)23+508.197 (R
)15-Sep-14
16-Sep-14 16-Sep-14
23+520 23+580.87720-Aug-14
21-Aug-14
23+580.87723+650 26-Aug-14 Elevation LOCATION (RHS) DATE
27-Aug-14 FROM TOFOUNDATIO
N /BLINDING
23+650 23+735 1-Sep-14 23+508.197 23+607.6348-Sep-14
2-Sep-14 9-Sep-14
23+735 23+790 19-Sep-14 23+607.63423+740 22-Sep-14
20-Sep-14 23-Sep-14
23+790 23+827.63510-Oct-14 23+740 23+750 16-Oct-14
11-Oct-14 17-Oct-14
23+827.63523+949.89515-Oct-14 23+750 23+950.1533-Nov-14
16-Oct-14 4-Nov-14
MSE WALL MONTHLY SCHEDULE (FOUNDATION @ APPROACH 2)
El. 23.30
El. 24.90
El. 24.10
El. 23.30
LOCATION (LHS) LOCATION (AB 2)Elevation
El. 24.10
Elevation
El. 23.30
23+520 23+580.877 23+650 23+703 23+730 23+827.635 23+949.895
29.700 - - - - - - -28.900 - - - - - - -28.100 - - - - - -
-27.300 - - - - - - -26.500 8-Nov-14 8-Nov-14 15-Nov-14 15-Nov-14
24-Nov-14 - -25.700 29-Oct-14 29-Oct-14 1-Nov-14 1-Nov-14 16-Nov-14
- -24.900 13-Oct-14 13-Oct-14 26-Sep-14 26-Sep-14 13-Nov-14 -
-24.100 25-Sep-14 25-Sep-14 - - - - -23.300 - - - - - - -
23+508.239 (L)23+508.197 (R ) 23+607.634 23+690 23+740
23+950.15329.700 - - - - - -28.900 - - - - - -28.100 - - - - -
-27.300 - - - - - -26.500 26-Nov-14 26-Nov-14 19-Nov-14 29-Nov-14
29-Nov-14 -25.700 5-Nov-14 5-Nov-14 11-Nov-14 25-Nov-14 25-Nov-14
-24.900 16-Oct-14 16-Oct-14 15-Oct-14 15-Oct-14 21-Nov-14 -24.100
30-Sep-14 30-Sep-14 9-Oct-14 - - -23.300 - - - - - -
PREVIOUSP R EVIOUS
M ON T HTHIS MONTH
MSE WALL MONTHLY SCHEDULE (PANELS FIXING @ APPROACH 2)
RHS (AB 2), from Sta. 23+508.197 to Sta. 23+950.153ELEV.
AB 2 Face
LHS (AB 2), from Sta. 23+508.239 to Sta. 23+949.895ELEV.
-
10. Box Culverts Progress Schedule
Rebars Concrete Rebars Concrete Rebars Concrete
1 21+260 3 cells - 2.0 x 1.5 25.546 0 - - - - - - - -LHS Block 1
3 cells - 2.0 x 1.5 19.526 0 19-Oct-14 26-Oct-14 27-Oct-14 9-Nov-14
9-Nov-14 9-Nov-14 9-Nov-14 -RHS Block 2 3 cells - 2.0 x 1.5 14.473
0 19-Oct-14 4-Nov-14 4-Nov-14 15-Nov-14 15-Nov-14 15-Nov-14
15-Nov-14 -RHS Block 3 3 cells - 2.0 x 1.5 6.000 0 - - - - - - -
-
2 21+485 1 cell - 2.0 x 1.5 39.750 0 - - - - - - - -Block 1a 1
cell - 2.0 x 1.5 3.000 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5
17.290 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14
31-Aug-14 1-Sep-14Block 2a 1 cell - 2.0 x 1.5 7.710 0 1-Jul-14
31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14
1-Sep-14Block 2b 1 cell - 2.0 x 1.5 10.000 0 19-Oct-14 25-Oct-14
25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14Block 2C
1 cell - 2.0 x 1.5 11.730 0 - - - - - - - -
3 21+838 2 x 4 cells (8) - 2.0 x 1.5 57.210 0 - - - - - - -
-Block 1a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 4-Sep-14
5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 -Block 1b 1 x 4
cells - 2.0 x 1.5 17.600 0 3-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14
13-Oct-14 13-Oct-14 13-Oct-14 -Block 2 1 x 4 cells - 2.0 x 1.5
22.600 0 3-Jul-14 20-Aug-14 20-Aug-14 30-Oct-14 30-Oct-14 30-Oct-14
30-Oct-14 -Block 3 1 x 4 cells - 2.0 x 1.5 11.970 0 - - - - - - -
-
Block 4a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 10-Sep-14
12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14 -Block 4b 1 x 4
cells - 2.0 x 1.5 17.600 0 3-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14
19-Oct-14 18-Oct-14 19-Oct-14Block 5 1 x 4 cells - 2.0 x 1.5 22.600
0 3-Jul-14 23-Sep-14 24-Sep-14 24-Oct-14 25-Oct-14 24-Oct-14
25-Oct-14 -Block 6 1 x 4 cells - 2.0 x 1.5 11.970 0 - - - - - - -
-
4 21+972.4 11 x 4 cells (44) - 3.0 x 2.0 57.629 0 - - - - - - -
-Block 1 1 x 4 cells - 3.0 x 2.0 28.038 0 24-May-14 5-Jun-14
5-Jun-14 24-Jun-14 24-Jun-14 15-Jul-14 16-Jul-14 16-Aug-14Block 2 1
x 4 cells - 3.0 x 2.0 28.031 0 24-May-14 9-Jul-14 10-Jul-14
3-Aug-14 4-Aug-14 13-Aug-14 14-Aug-14 8-Sep-14Block 3 1 x 4 cells -
3.0 x 2.0 28.026 0 17-May-14 25-May-14 25-May-14 3-Jun-14 3-Jun-14
23-Jun-14 23-Jun-14 8-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 28.022
0 18-May-14 12-Jul-14 13-Jul-14 5-Aug-14 6-Aug-14 18-Aug-14
19-Aug-14 1-Oct-14Block 5 1 x 4 cells - 3.0 x 2.0 28.019 0
18-May-14 29-May-14 29-May-14 8-Jun-14 8-Jun-14 2-Jul-14 2-Jul-14
1-Oct-14Block 6 1 x 4 cells - 3.0 x 2.0 28.018 0 18-May-14
31-Jul-14 31-Jul-14 12-Aug-14 13-Aug-14 27-Aug-14 28-Aug-14
1-Oct-14Block 7 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14
10-Jun-14 10-Jun-14 1-Jul-14 1-Jul-14 23-Jul-14 24-Jul-14
5-Oct-14Block 8 1 x 4 cells - 3.0 x 2.0 28.022 0 26-May-14 9-Aug-14
10-Aug-14 25-Aug-14 26-Aug-14 9-Sep-14 10-Sep-14 -Block 9 1 x 4
cells - 3.0 x 2.0 28.026 0 26-May-14 15-Jun-14 15-Jun-14 7-Jul-14
8-Jul-14 4-Aug-14 5-Aug-14 -
Block 10 1 x 4 cells - 3.0 x 2.0 28.031 0 28-May-14 17-Aug-14
18-Aug-14 14-Sep-14 14-Sep-14 24-Sep-14 25-Sep-14 -Block 11 1 x 4
cells - 3.0 x 2.0 28.038 0 28-May-14 19-Jun-14 19-Jun-14 20-Jul-14
20-Jul-14 2-Sep-14 3-Sep-14 25-Sep-14Block 12 1 x 4 cells - 3.0 x
2.0 21.015 0 10-Aug-14 25-Aug-14 26-Aug-14 2-Sep-14 3-Sep-14
1-Oct-14 1-Oct-14 -Block 13 1 x 4 cells - 3.0 x 2.0 21.010 0
27-Jul-14 22-Sep-14 22-Sep-14 29-Sep-14 29-Sep-14 18-Oct-14
19-Oct-14 -Block 14 1 x 4 cells - 3.0 x 2.0 21.006 0 27-Jul-14
12-Oct-14 12-Oct-14 15-Oct-14 15-Oct-14 26-Oct-14 27-Oct-14 -Block
15 1 x 4 cells - 3.0 x 2.0 21.003 0 25-Jul-14 23-Aug-14 23-Aug-14
8-Sep-14 8-Sep-14 18-Sep-14 19-Sep-14 -Block 16 1 x 4 cells - 3.0 x
2.0 21.001 0 16-Jun-14 27-Jul-14 27-Jul-14 14-Aug-14 14-Aug-14
3-Sep-14 4-Sep-14 -Block 17 1 x 4 cells - 3.0 x 2.0 21.000 0
16-Jun-14 14-Sep-14 15-Sep-14 23-Sep-14 24-Sep-14 14-Oct-14
15-Oct-14 -Block 18 1 x 4 cells - 3.0 x 2.0 21.001 0 12-Jun-14
24-Oct-14 24-Oct-14 30-Oct-14 31-Oct-14 7-Nov-14 7-Nov-14 -Block 19
1 x 4 cells - 3.0 x 2.0 21.003 0 12-Jun-14 16-Oct-14 17-Oct-14
21-Oct-14 21-Oct-14 30-Oct-14 30-Oct-14 -Block 20 1 x 4 cells - 3.0
x 2.0 21.006 0 8-Jun-14 29-Sep-14 30-Sep-14 1-Oct-14 1-Oct-14
21-Oct-14 21-Oct-14 -Block 21 1 x 4 cells - 3.0 x 2.0 21.010 0
8-Jun-14 1-Sep-14 2-Sep-14 21-Sep-14 21-Sep-14 30-Sep-14 30-Sep-14
-Block 22 1 x 4 cells - 3.0 x 2.0 21.015 0 8-Jun-14 25-Jun-14
25-Jun-14 30-Jul-14 30-Jul-14 16-Sep-14 17-Sep-14 25-Sep-14
TOP SLAB Bituminous Paint (2 Coats)
LENGTH (m) SKEW ( )F/P &
BLINDING
LHS
RHS
TYPE & DIMENSIONSTATIONBASE SLAB WALL
NO.
RHS
RHS
LHS
LHS
RHS
LHS
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS
Rebars Concrete Rebars Concrete Rebars Concrete
Block 23 1 x 4 cells - 3.0 x 2.0 6.635 0 - - - - - - - -Block 24
1 x 4 cells - 3.0 x 2.0 6.782 0 - - - - - - - -Block 25 1 x 4 cells
- 3.0 x 2.0 6.819 0 - - - - - - - -Block 26 1 x 4 cells - 3.0 x 2.0
7.217 0 - - - - - - - -Block 27 1 x 4 cells - 3.0 x 2.0 7.975 0 - -
- - - - - -Block 28 1 x 4 cells - 3.0 x 2.0 8.571 0 - - - - - - -
-Block 29 1 x 4 cells - 3.0 x 2.0 9.267 0 - - - - - - - -Block 30 1
x 4 cells - 3.0 x 2.0 9.949 0 - - - - - - - -Block 31 1 x 4 cells -
3.0 x 2.0 10.260 0 - - - - - - - -Block 32 1 x 4 cells - 3.0 x 2.0
10.262 0 - - - - - - - -Block 33 1 x 4 cells - 3.0 x 2.0 10.265 0 -
- - - - - - -
5 22+655 2 x 4 cells (8) - 2.0 x 2.0 95.482 45 R - - - - - - -
-(9 cells) 1 cell - 2.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells -
2.0 x 2.0 9.675 45 R 24-Nov-14 29-Nov-14 29-Nov-14 - - - - -Block 2
1 x 4 cells - 2.0 x 2.0 32.711 45 R 30-Jun-14 6-Aug-14 7-Aug-14
1-Sep-14 2-Sep-14 1-Sep-14 2-Sep-14 13-Oct-14Block 3 1 x 4 cells -
2.0 x 2.0 32.711 45 R 24-Jun-14 21-Jul-14 21-Jul-14 17-Aug-14
18-Aug-14 17-Aug-14 18-Aug-14 13-Oct-14Block 4 1 x 4 cells - 2.0 x
2.0 11.850 45 R 11-Sep-14 12-Oct-14 13-Oct-14 22-Oct-14 22-Oct-14
22-Oct-14 22-Oct-14 -
Block 4a 1 x 4 cells - 2.0 x 2.0 13.130 45 R - - - - - - -
-Block 5 1 x 4 cells - 2.0 x 2.0 19.035 45 R 24-Nov-14 - - - - - -
-Block 6 1 x 4 cells - 2.0 x 2.0 32.711 45 R 29-Jun-14 27-Jul-14
28-Jul-14 13-Sep-14 14-Sep-14 13-Sep-14 14-Sep-14 13-Oct-14Block 7
1 x 4 cells - 2.0 x 2.0 32.711 45 R 24-Jun-14 28-Aug-14 28-Aug-14
24-Sep-14 26-Sep-14 24-Sep-14 26-Sep-14 13-Oct-14Block 8 1 x 4
cells - 2.0 x 2.0 10.95 45 R - - - - - - - -Block 9 1 cell - 2.0 x
2.0 25.03 45 R 24-Nov-14 - - - - - - -
Block 10 1 cell - 2.0 x 2.0 32.711 45 R 28-Jun-14 20-Aug-14
23-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 11 1
cell - 2.0 x 2.0 32.711 45 R 29-Jun-14 3-Aug-14 4-Aug-14 2-Oct-14
3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 12 1 cell - 2.0 x 2.0
4.960 45 R - - - - - - - -
6 23+492 1 x 4 cells (4) - 3.0 x 2.0 79.065 15 R - - - - - - -
-(5 cells) 1 cell - 3.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells -
3.0 x 2.0 6.457 15 R - - - - - - - -Block 2 1 x 4 cells - 3.0 x 2.0
31.546 15 R 24-Jun-14 9-Jul-14 9-Jul-14 30-Jul-14 30-Jul-14
16-Aug-14 17-Aug-14 6-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 31.546
15 R 24-Jun-14 14-Jul-14 15-Jul-14 3-Aug-14 3-Aug-14 21-Aug-14
21-Aug-14 6-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 7.982 15 R
9/172014 23-Sep-14 24-Sep-14 28-Sep-14 28-Sep-14 1-Oct-14 2-Oct-14
18-Oct-14Block 5 1 cell - 3.0 x 2.0 7.039 15 R - - - - - - - -Block
6 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 5-Aug-14 5-Aug-14 9
& 20/8/2014 9 & 23/8/2014 28-Aug-14 28-Aug-14
4-7/9/2014Block 7 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 6-Aug-14
6-Aug-14 11 & 25/8/2014 11 & 26/8/2014 31-Aug-14 1-Sep-14
4-7/9/2014Block 8 1 cell - 3.0 x 2.0 5.525 15 R 17-Sep-14 28-Sep-14
28-Sep-14 2-Oct-14 2-Oct-14 11-Oct-14 11-Oct-14 18-Oct-14
11-Oct-14 11-Oct-14 - - -
BASE SLAB WALL TOP SLAB Bituminous Paint (2 Coats)
LHS
LHS
STATION TYPE & DIMENSION LENGTH (m) SKEW ( )F/P &
BLINDING
RHS
LHS
RHS
NO.
LHS
RHS
RHS
LHS
RHS
RHS
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS
Rebars Concrete Rebars Concrete Rebars Concrete
7 23+756.5 1 cell - 2.0 x 1.5 67.550 0 - - - - - - - -Block 1 1
cell - 2.0 x 1.5 12.090 0 - - - - - - - -Block 2 1 cell - 2.0 x 1.5
20.180 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14
23-Jul-14 23-Jul-14 24-Jul-14
Block 3a 1 cell - 2.0 x 1.5 14.430 0 12-Jul-14 23-Jul-14
23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b
1 cell - 2.0 x 1.5 8.700 0 11-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14
26-Aug-14 26-Aug-14 26-Aug-14 28-Aug-14Block 4 1 cell - 2.0 x 1.5
12.090 0 - - - - - - - -
8 23+997 1 cell - 2.0 x 1.5 70.268 0 - - - - - - - -Block 1 1
cell - 2.0 x 1.5 16.128 0 - - - - - - - -
Block 2a 1 cell - 2.0 x 1.5 4.933 0 - - - - - - - -Block 2b 1
cell - 2.0 x 1.5 13.860 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14
23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3a 1 cell - 2.0 x 1.5
16.300 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14
23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 4.942 0 10-Aug-14
26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14
31-Aug-14Block 4a 1 cell - 2.0 x 1.5 7.848 0 10-Aug-14 26-Aug-14
26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4b
1 cell - 2.0 x 1.5 6.197 0
9 24+235 1 cell - 2.0 x 1.5 59.106 0 - - - - - - - -Block 1a 1
cell - 2.0 x 1.5 15.566 0 - - - - - - - -Block 1b 1 cell - 2.0 x
1.5 15.000 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14
23-Jul-14 23-Jul-14 24-Jul-14Block 2a 1 cell - 2.0 x 1.5 8.900 0
12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14
23-Jul-14 24-Jul-14Block 2b 1 cell - 2.0 x 1.5 15.600 0 10-Aug-14
26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14
31-Aug-14Block 2c 1 cell - 2.0 x 1.5 4.020 0 - - - - - - - -
10 24+570 1 cell - 2.0 x 1.5 51.953 0 - - - - - - - -LHS Block 1
1 cell - 2.0 x 1.5 25.846 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14
25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
Block 2a 1 cell - 2.0 x 1.5 13.500 0 14-Aug-14 25-Aug-14
25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14Block 2b
1 cell - 2.0 x 1.5 12.587 0 24-Nov-14 - - - - - - -
Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m
PREVIOUS PREVIOUS MONTH THIS MONTH
RHS
WALL TOP SLAB Bituminous Paint (2 Coats)
LHS
RHS
F/P &
BLINDING
BASE SLAB
LHS
NO. STATION TYPE & DIMENSION LENGTH (m) SKEW ( )
LHS
RHS
RHS
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS
Rebars Concrete Rebars Concrete Rebars Concrete
1 21+300 2 cells - 4.0 x 3.0 37.700 0 - - - - - - - -LHS Block 1
2 cells - 4.0 x 3.0 15.780 0 19-Oct-14 26-Oct-14 27-Oct-14 1-Nov-14
2-Nov-14 12-Nov-14 2-Nov-14 -RHS Block 2 2 cells - 4.0 x 3.0 21.900
0 - - - - - - - -
2 24+600 2 cells - 4.0 x 3.0 44.051 0 - - - - - - - -LHS Block 1
2 cells - 4.0 x 3.0 21.620 0 22-Oct-14 3-Nov-14 3-Nov-14 11-Nov-14
12-Nov-14 19-Nov-14 20-Nov-14 -RHS Block 2 2 cells - 4.0 x 3.0
22.411 0 - - - - - - - -
Rebars Concrete Rebars Concrete Rebars Concrete
1 23+284.40, SOL-1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -LHS
Block 1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -RHS Block 2 1 cells
- 4.0 x 4.0 - 0 - - - - - - - -
2 24+360, SOL-1 1 cells - 4.0 x 4.0 59.614 0 - - - - - - - -LHS
Block 1 1 cells - 4.0 x 4.0 9.000 0 - - - - - - - -LHS Block 2 1
cells - 4.0 x 4.0 20.777 0 15-Sep-14 1-Oct-14 1-Oct-14 19-Oct-14
19-Oct-14 30-Oct-14 31-Oct-14 -RHS Block 3 1 cells - 4.0 x 4.0
22.777 0 - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0 7.000 0 - -
- - - - - -
3 0+050, SOL-3 1 cells - 4.0 x 4.0 83.223 0 - - - - - - - -LHS
Block 1 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 2 1
cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 3 1 cells - 4.0
x 4.0 17.721 0 - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0
30.000 0 11/55/2014 - - - - - - -
PREVIOUSPREVIOUS
MONTHTHIS MONTH
WALLNO.
LENGTH (m) SKEW ( )F/P &
BLINDINGTYPE & DIMENSION
PEDESTRIAN UNDERPASS PROGRESS SCHEDULE (BARREL)
TYPE & DIMENSION LENGTH (m) SKEW ( )TOP SLAB Bituminous
Paint (2 Coats)STATION
STATIONBASE SLAB WALL
F/P &
BLINDING
BASE SLAB
NO.
VEHICLE UNDERPASS PROGRESS SCHEDULE (BARREL)
TOP SLAB Bituminous Paint (2 Coats)
-
11. Progress Status of Utility Crossing Ducts
NO. OF
DIA TYPE WAYS LAY CONCRETE BACKFILL
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 9/24/14 9/24/14 10/18/14 UTL-LAY- 104 UTL-CON-131A
MIDDLE
RIGHT
LEFT 5/15/14 5/15/14 5/18/14 6/12/14 UTL-LAY- 81 UTL-CON- 65
UTL-BF- 01
MIDDLE 6/11/14 6/11/14 6/12/14 7/10/14 UTL-LAY- 104 UTL-CON- 83
UTL-BF- 20
RIGHT
LEFT 5/19/14 5/19/14 5/20/14 6/4/14 UTL-LAY- 87 UTL-CON- 66
UTL-BF- 03
MIDDLE 6/14/14 14/06/014 6/14/14 6/21/14 UTL-LAY- 108 UTL-CON-
84 UTL-BF- 21
RIGHT
LEFT 5/19/14 5/19/14 5/20/14 5/31/14 UTL-LAY- 85 UTL-CON- 63
UTL-BF- 02
MIDDLE 6/15/14 6/15/14 6/15/14 UTL-LAY- 107 UTL-CON- 85
RIGHT
LEFT 5/20/14 5/20/14 5/25/14 6/4/14 UTL-LAY- 86 UTL-CON- 64
UTL-BF- 05
MIDDLE 6/15/14 6/15/14 6/15/14 7/8/14 UTL-LAY- 109 UTL-CON- 87
UTL-BF- 23
RIGHT
LEFT 5/25/14 5/25/14 5/25/14 6/4/14 UTL-LAY- 90 UTL-CON-68
UTL-BF- 07
MIDDLE 6/16/14 6/16/14 6/17/14 7/10/14 UTL-LAY- 111 UTL-CON- 88
UTL-BF- 28
RIGHT
LEFT 6/17/14 6/17/14 6/18/14 7/9/14 UTL-LAY- 112 UTL-CON- 89
UTL-BF- 33
MIDDLE 7/20/14 7/20/14 7/21/14 7/27/14 UTL-LAY- 131 UTL-CON- 106
UTL-BF-44
RIGHT
LEFT 6/19/14 6/19/14 6/19/14 7/6/14 UTL-LAY- 114 UTL-CON- 92
UTL-BF- 31
MIDDLE 7/20/14 7/20/14 7/21/14 7/17/14 UTL-LAY- 132 UTL-CON- 107
UTL-BF-46
RIGHT
LEFT 6/19/14 6/19/14 6/19/14 7/5/14 UTL-LAY- 113 UTL-CON- 91
UTL-BF- 30
MIDDLE 7/20/14 7/20/14 7/21/14 7/17/14 UTL-LAY- 133 UTL-CON- 108
UTL-BF-45
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 5/26/14 5/26/14 5/26/14 6/8/14 UTL-LAY- 88 UTL-CON- 69
UTL-BF- 08
MIDDLE 6/11/14 6/11/14 6/11/14 7/22/14 UTL-LAY-106 UTL-CON- 81
UTL-BF-26
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 6/16/14 6/16/14 6/16/14 7/20/14 UTL-LAY- 102 UTL-CON-
UTL-BF-19
MIDDLE 7/8/14 7/8/14 7/9/14 7/27/14 UTL-LAY- 125 UTL-CON-99
UTL-BF-42
RIGHT
LEFT 5/25/14 5/25/14 5/26/14 6/14/14 UTL-LAY- 91 UTL-CON- 71
UTL-BF- 06
MIDDLE 11/06/201 6/11/14 6/11/14 6/23/14 UTL-LAY- 105 UTL-CON-
82 UTL-BF- 25
RIGHT
LEFT 5/27/14 5/27/14 5/27/14 6/17/14 UTL-LAY- 92 UTL-CON- 72
UTL-BF- 09
MIDDLE
RIGHT
LEFT 5/28/14 5/28/14 5/28/14 6/17/14 UTL-LAY- 93 UTL-CON- 70
UTL-BF- 10
MIDDLE
RIGHT
LEFT 5/29/14 5/29/14 5/29/14 6/17/14 UTL-LAY- 94 UTL-CON- 73
UTL-BF- 11
MIDDLE 7/30/14 8/12/14 7/30/14 8/26/14 UTL-LAY-142 UTL-CON- 115
UTL-BF-48
RIGHT
LEFT 5/29/14 6/2/14 6/2/14 6/17/14 UTL-LAY- 95 UTL-CON- 75
UTL-BF- 15
MIDDLE 7/14/14 7/14/14 7/14/14 8/20/14 UTL-LAY- 124 UTL-CON- 102
UTL-BF- 36
RIGHT
LEFT 5/29/14 6/2/14 6/2/14 6/17/14 UTL-LAY-97 UTL-CON- 76
UTL-BF- 13
MIDDLE 7/14/14 7/14/14 7/15/14 8/20/14 UTL-LAY- 127 UTL-CON- 101
UTL-BF- 38
RIGHT
LEFT
MIDDLE 8/10/14 8/11/14 8/11/14 8/26/14 UTL-LAY-149A UTL-CON-
120A UTL-BF- 58
RIGHT 10/27/14 10/27/14 10/27/14 UTL-LAY- 206 UTL-CON- 153
3
2
3
3
3
2
2
2
3
1
1
3
4
3
4
3
1
23+820
23+900
200
200
200
150
300
900
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
UPVC
150
150
RC
UPVC
UPVC20 CCC/FQI/EL/13
CCC/FQI/EL/0821
CCC/FQI/EL/0922
UPVC
UPVC
UPVC
RC
23+060
23+210
23+240
23+560
CCC/FQI/EL/1023
CCC/FQI/WA/0324
150
150
150
150
600
BACKFILLI
NG
RFI REF.S.
NO.CHAINAGE
PIPE
2
2UPVC
INSTALLA
TION
CONCRET
E
1CCC/FQI/IR/06
SERVICE ROAD-30+030 200 UPVC
2CCC/FQR/IR/11 SOL-
20+150 300
SETOUT/EX
CV/BED
PREP
STAGESDRAWING No.
2
3
2
4CCC/FQR/WA/05
SR-10+600 300 UPVC
6 CCC/FQI/EL/01
10 CCC/FQI/EL/03 21+880
CCC/FQI/EL/04 22+260
12
2
300 UPVC
8 CCC/FQI/EL/02 21+660
11
150
7 CCC/FQI/IR/01 21+460
UPVC
9 CCC/FQI/IR/02 21+780 300
CCC/FQI/EL/05 22+510 150
15
CCC/FQI/IR/05
JUNCTION
CROSSING
22+587 LHS
13 CCC/FQI/IR/03
21+360 150 UPVC
25 CCC/FQI/SL/11 23+960 150 UPVC
19 CCC/FQI/EL/07
16 CCC/FQI/EL/06
22+520
14
CCC/FQI/IR/04
JUNCTION
CROSSING
22+520 LHS
CCC/FQI/WA/01
CCC/FQI/WA/02
JUNCTION17
18
23+008 LHS
23+020
22+760
150
23CCC/FQR/IR/10 SOL-
30+300 200 UPVC
CCC/FQI/SL/01 21+160 150 UPVC 45
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 20
NO. OF
DIA TYPE WAYS LAY CONCRETE BACKFILL
LEFT 5/29/14 6/2/14 6/3/14 6/19/14 UTL-LAY- 98 UTL-CON- 77
UTL-BF- 14
MIDDLE 8/6/14 8/6/14 8/9/14 8/13/14 UTL-LAY- 134-R1 UTL-CON-
109A UTL-BF- 53
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 6/3/14 6/4/14 6/4/14 6/23/14 UTL-LAY- 99 UTL-CON- 78
UTL-BF- 16
MIDDLE 8/11/14 8/11/14 8/19/14 8/26/14 UTL-LAY-140 R1
UTL-CON-114 UTL-BF- 52
RIGHT
LEFT 6/4/14 6/5/14 6/10/14 23/06/201 UTL-LAY- 100 UTL-CON- 79
UTL-BF- 17
MIDDLE 7/23/14 7/24/14 8/19/14 8/26/14 UTL-LAY-139
UTL-CON-112-R1UTL-BF- 47
RIGHT
LEFT 6/9/14 6/9/14 6/10/14 6/23/14 UTL-LAY- 101 UTL-CON- 80
UTL-BF- 18
MIDDLE 8/6/14 8/6/14 8/6/14 8/26/14 UTL-LAY-138-R1 UTL-CON-111-B
UTL-BF- 56
RIGHT
LEFT 7/5/14 7/5/14 7/5/14 8/19/14 UTL-LAY- 123 UTL-CON- 94
UTL-BF- 39R1
MIDDLE
RIGHT
LEFT 7/16/14 7/16/14 7/17/14 11/6/14 UTL-LAY- 130 UTL-CON- 105
UTL-BF- 41R1
MIDDLE 10/27/14 10/27/14 10/27/14 10/27/14 UTL-LAY-190R1
UTL-CON- 148 UTL-BF- 72
RIGHT
LEFT 9/14/14 9/14/14 10/14/14 10/20/14 UTL-LAY- 166 UTL-CON-125
UTL-BF-81
MIDDLE 10/27/14 10/30/14 10/27/14 UTL-LAY- 205 UTL-CON- 150
RIGHT
LEFT 9/16/14 9/20/14 UTL-LAY- 173
MIDDLE 10/27/14 10/27/14 10/27/14 11/9/14 UTL-LAY- 203 UTL-CON-
149 UTL-BF-100
RIGHT
LEFT 11/3/14 11/10/14 11/4/14 11/26/14 UTL-LAY- 211 UTL-CON- 155
UTL-BF-106
MIDDLE
RIGHT
LEFT 5/21/14 5/21/14 5/21/14 6/4/14 UTL-LAY- 89 UTL-CON- 67
UTL-BF- 04
MIDDLE 6/16/14 6/16/14 6/18/14 7/10/14 UTL-LAY- 110 UTL-CON- 90
UTL-BF- 29
RIGHT
LEFT 5/29/14 5/31/14 5/31/14 6/17/14 UTL-LAY- 96 UTL-CON- 74
UTL-BF- 12
MIDDLE 7/10/14 7/10/14 8/13/14 8/26/14 UTL-LAY- 120 R1 UTL-CON-
95 UTL-BF- 49
RIGHT
LEFT 7/21/14 8/4/14 8/5/14 UTL-LAY-137-R1 UTL-CON- 118
MIDDLE 8/8/14 8/9/14 8/9/14 9/22/14 UTL-LAY-148A UTL-CON- 117
UTL-BF- 57
RIGHT 9/16/14 9/16/14 9/16/14 UTL-LAY-172 UTL-CON- 126
LEFT 7/7/14 7/8/14 7/8/14 UTL-LAY-103A UTL-CON-98
MIDDLE 8/12/14 8/13/14 8/14/14 8/15/14 UTL-LAY-150 UTL-CON-122A
UTL-BF- 37A
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 7/9/14 7/9/14 7/9/14 UTL-LAY- 116 UTL-CON-100
MIDDLE 8/12/14 8/13/14 8/14/14 9/25/14 UTL-LAY-151 UTL-CON-121
UTL-BF-81
RIGHT 10/12/14 10/13/14 10/12/14 11/8/14 UTL-LAY-187 UTL-CON-137
UTL-BF-99
LEFT 7/2/14 7/3/14 7/3/14 UTL-LAY-122 UTL-CON-93R1
MIDDLE 7/10/14 7/10/14 7/14/14 UTL-LAY-126 UTL-CON-103
RIGHT 7/22/14 7/22/14 7/23/14 8/20/14 UTL-LAY-136 UTL-CON-110
UTL-BF- 50
LEFT 8/30/14 8/31/14 9/14/14 9/30/14 UTL-LAY-158 UTL-CON-96
UTL-BF-64
MIDDLE 11/27/14 11/27/14 11/29/14 UTL-EXC-63 UTL-CON-162
UTL-BF-115
RIGHT
LEFT 9/7/14 9/7/14 10/14/14 10/27/14 UTL-LAY-162 UTL-CON-124
UTL-BF-69
MIDDLE 9/15/14 9/15/14 11/4/14 UTL-LAY-162R1 UTL-BF-94
RIGHT 10/27/14 10/28/14 11/17/14 11/17/14 UTL-LAY-207
UTL-CON-152 UTL-BF-92
LEFT 9/16/14 9/17/14 9/30/14 11/8/14 UTL-LAY-174 UTL-CON-127
UTL-BF-83R1
MIDDLE 10/14/14 10/18/14 10/14/14 UTL-LAY-188 UTL-CON-138
RIGHT 10/27/14 10/27/14 10/27/14 UTL-LAY-204 UTL-CON-151
LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-184 UTL-CON-135
MIDDLE
RIGHT
LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-164 R1 UTL-CON-134
MIDDLE
RIGHT
LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-185 UTL-CON-136
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 11/4/14 UTL-EXC-55
MIDDLE
RIGHT
UPVC 2-4WAY150CCC/FQI/SL/01
21+620 450
24+220
24+340
24+520
UPVC
UPVC
45
46
47
450
CON
C PI
PE
50
CCC/FQI/SD 23+400 60049
CON
C PI
PE
4
3
2
3
2
3
2
UPVC150
23+980
24+000
24+020
24+120
23+740 150
UPVC
UPVC
UPVC
150
UPVC
39CCC/FQI/OMANTEL
.1
35
CCC/FQI/OMANTEL
.2100
150
40 0+140 SOL-3
22+810 100
100
21+870
23+580
24+720
150
100
100
15042 22+990
UPVC300
150
300
CCC/FQI/WA/0427
CCC/FQI/IR/0728
36
37
38
CCC/FQI/EL/14
CCC/FQI/IR/08
CCC/FQI/EL/15
CCC/FQI/EL/16
CCC/FQI/IR/09
CCC/FQI/EL/17
CCC/FQI/NAW.2
CCC/FQI/NAW.3
CCC/FQI/NAW.4
CCC/FQI/EL/1229
S.
NO.DRAWING No. CHAINAGE
PIPE
26 CCC/FQI/EL/11 UPVC
24+820
24+960
25+160
30
31
32
33
34
2
3
1
2
600
300
150
150
3
3
RC
UPVC
UPVC
UPVC
2
4
22+080
UPVC 2
CCC/FQI/SD/07
CCC/FQI/SD/08
UPVC
UPVC
UPVC
CCC/FQI/EL/21 23+965 200 UPVC 2
24+850
450
CON
C PI
PECO
NC
PIPE
CCC/FQI/SL/04 UPVC 4
41CCC/FQI/SL/03 Rev
A22+820 150 UPVC 4
CCC/FQI/SL/02 4
21+500
21+560
44 CCC/FQI/EL/19
48 CCC/FQI/SD/09
STAGES
SETOUT/EX
CV/BED
PREP
INSTALLA
TION
CONCRET
E
BACKFILLI
NG
RFI REF.
43
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 21
LEFT 9/4/14 9/28/14 UTL-LAY-159-B UTL-CON-132
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT 9/16/14 9/17/14 9/30/14 10/18/14 UTL-LAY-167 UTL-CON-128
UTL-BF-78
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
LEFT
MIDDLE
RIGHT
3 CCC/FQI/SL/08
1 CCC/FQI/SL/23 0+020 150 UPVC 6
2 CCC/FQI/SL/24 0+120 2
UPVC 4
3
2ACCC/FQI/Omantel/
024UPVC
SERVICE ROAD-02
1 1+050 150 UPVC 2
CCC/FQI/SL/12 1+530 150 UPVC 2
1
0+060 4
3 CCC/FQI/SL/08 0+600 100 UPVC 4
2
6
CCC/FQI/SL/14
CCC/FQI/SL/15
CCC/FQI/SL/16
CCC/FQI/SL/17
0+415 1503
4
2 CCC/FQI/SL/13 UPVC 2
BURAIMI ROAD (SOL - 03)
SERVICE ROAD-03
2
0+472.8
CCC/FQI/SL/06 UPVC150
CCC/FQI/OMANTEL
/04
5CCC/FQI/OMANTEL
/05100 UPVC 4
6CCC/FQI/OMANTEL
/060+648.103 100 UPVC
4
CCC/FQI/SL/10
0+550
100 UPVC 4
2
5
UPVC 2
UPVC 6
Existing
Road front
SOL-3 Ch.
150 UPVC 2
0+054.459 150
0+140 150
1CCC/FQI/Omantel/
02
4
SERVICE ROAD-01
CCC/FQI/SL/07 0+530 150 UPVC
UPVC 2
Existing
Road front
SOL-3 Ch.
150
0+130 150
0+138.348 110
-
12. Project Progress Strip Chart
-
SUBGRADE IN CUT COMPLETED 21+150-21+500 As of November 2014BWC 6
cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20
cmSubgrade Layr 9Layr 8Layr 7Layr 6Layr 5Layr 4Layr 3Layr 2
EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
21+0
00
21+0
20
21+0
40
21+0
60
21+0
80
21+1
00
21+1
20
21+1
40
21+1
60
21+1
80
21+2
00
21+2
20
21+2
40
21+2
60
21+2
80
21+3
00
21+3
20
21+3
40
21+3
60
21+3
80
21+4
00
21+4
20
21+4
40
21+4
60
21+4
80
21+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer
4layer 5layer 6layer 7layer 8layer 9Subgrade
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack
Coat BWC 6 cm
21+500-22+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15
cmABC 1 ST 15 cmGSB 20 cmsub gradeLayer 9Layer 8Layer 7Layer 6Layer
5Layer 4Layer 3Layer 2
EMBANKMENT Layer 1BED PREPRATION OGL SURVEY
21+5
00
21+5
20
21+5
40
21+5
60
21+5
80
21+6
00
21+6
20
21+6
40
21+6
60
21+6
80
21+7
00
21+7
20
21+7
40
21+7
60
21+7
80
21+8
00
21+8
20
21+8
40
21+8
60
21+8
80
21+9
00
21+9
20
21+9
40
21+9
60
21+9
80
22+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer
4layer 5layer 6layer 7layer 8layer 9sub grade
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack
Coat BWC 6 cm
RH
S
PROGRESS STRIP CHART FOR ROAD WORKS
LHS
RH
SLH
S
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 24
COMPLETED 22+000-22+500 As of November 2014BWC 6 cmTack Coat BBC
12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayr 10 SUB
GRADE LAYER Layr 9Layr 8Layr 7Layr 6Layr 5Layr 4Layr 3Layr
2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
22+0
00
22+0
20
22+0
40
22+0
60
22+0
80
22+1
00
22+1
20
22+1
40
22+1
60
22+1
80
22+2
00
22+2
20
22+2
40
22+2
60
22+2
80
22+3
00
22+3
20
22+3
40
22+3
60
22+3
80
22+4
00
22+4
20
22+4
40
22+4
60
22+4
80
22+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer
4layer 5layer 6layer 7layer 8layer 9layer 10 SUBGRADEGSB 20 cmABC 1
ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
22+500-23+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15
cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7 5th layer of
rock soil Layer 6 layer 15Layer 5Layer 4 4th layer roock soil Layer
3Layer 2EMBANKMENT Layer 1BED PREPRATION OGL SURVEY
22+5
00
22+5
20
22+5
40
22+5
60
22+5
80
22+6
00
22+6
20
22+6
40
22+6
60
22+6
80
22+7
00
22+7
20
22+7
40
22+7
60
22+7
80
22+8
00
22+8
20
22+8
40
22+8
60
22+8
80
22+9
00
22+9
20
22+9
40
22+9
60
22+9
80
23+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer
4 4th layer roock soil layer 5layer 6 layer 15layer 7 5th layer of
rock soil layer 8layer 9layer 10 SUB GGSB 20 cmABC 1 ST 15 cmABC 2
ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm
LHS
RH
SLH
SR
HS
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 25
COMPLETED 23+000-23+500 As of November 2014BWC 6 cmTack Coat BBC
12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayr 10 rock
siol layer no 3Layr 9 5th layer of rock soil layer no 28Layr 8
layer 15 of embankmentLayr 7Layr 6Layr 5Layr 4Layr 3Layr
2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
23+0
00
23+0
20
23+0
40
23+0
60
23+0
80
23+1
00
23+1
20
23+1
40
23+1
60
23+1
80
23+2
00
23+2
20
23+2
40
23+2
60
23+2
80
23+3
00
23+3
20
23+3
40
23+3
60
23+3
80
23+4
00
23+4
20
23+4
40
23+4
60
23+4
80
23+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer
4layer 5layer 6 layer 15 of embankmentlayer 7 5th layer of rock
soil layer no 28layer 8 rock siol layer no 3layer 9layer 10GSB 20
cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6
cm
23+500-24+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15
cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer
5Layer 4 4th layer of Rock siolLayer 3 3rd layer of Rock siolLayer
2 2nd layer of Rock siolEMBANKMENT Layer 1 1st layer of Rock
siolBED PREPRATION OGL SURVEY
23+5
00
23+5
20
23+5
40
23+5
60
23+5
80
23+6
00
23+6
20
23+6
40
23+6
60
23+6
80
23+7
00
23+7
20
23+7
40
23+7
60
23+7
80
23+8
00
23+8
20
23+8
40
23+8
60
23+8
80
23+9
00
23+9
20
23+9
40
23+9
60
23+9
80
24+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1 1st layer of rock
siollayer 2 2nd layer of rock siollayer 3 3rd layer of rock
siollayer 4 4th layer of rock siollayer 5layer 6layer 7layer 8layer
9layer 10GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12
cmTack Coat BWC 6 cm
LHS
RH
SLH
SR
HS
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 26
COMPLETED 24+000-24+500 As of November 2014
BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15
cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer
3Layer 2
EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY
24+0
00
24+0
20
24+0
40
24+0
60
24+0
80
24+1
00
24+1
20
24+1
40
24+1
60
24+1
80
24+2
00
24+2
20
24+2
40
24+2
60
24+2
80
24+3
00
24+3
20
24+3
40
24+3
60
24+3
80
24+4
00
24+4
20
24+4
40
24+4
60
24+4
80
24+5
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer
4layer 5layer 6layer 7layer 8layer 9layer 10
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack
Coat BWC 6 cm
24+500-25+000
BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15
cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer
3Layer 2
EMBANKMENT Layer 1BED PREPRATION OGL SURVEY
24+5
00
24+5
20
24+5
40
24+5
60
24+5
80
24+6
00
24+6
20
24+6
40
24+6
60
24+6
80
24+7
00
24+7
20
24+7
40
24+7
60
24+7
80
24+8
00
24+8
20
24+8
40
24+8
60
24+8
80
24+9
00
24+9
20
24+9
40
24+9
60
24+9
80
25+0
00
OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer
4layer 5layer 6layer 7layer 8layer 9layer 10
GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack
Coat BWC 6 cm
LHS
RH
SLH
SR
HS
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 27
COMPLETED 25+000-25+500 As of November 2014
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
25+0
00
25+0
20
25+0
40
25+0
60
25+0
80
25+1
00
25+1
20
25+1
40
25+1
60
25+1
80
25+2
00
25+2
20
25+2
40
25+2
60
25+2
80
25+3
00
25+3
20
25+3
40
25+3
60
25+3
80
25+4
00
25+4
20
25+4
40
25+4
60
25+4
80
25+5
00
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
LHS
RH
S
-
13. Financial Status of Payments
Sl. No. DESCRIPTIONPAYMENT FOR
THE MONTH OF
GROSS
AMOUNT
(R.O.)
GROSS
AMOUNT
CLAIMED (R.O.)
NET AMOUNT
CLAIMED
(R.O.)
DATE
SUBMITTED
AMOUNT
CERTIFIED (R.O.)DATE CERTIFIED
AMOUNT
RECEIVED
(R.O.)
DATE
PAYMENT DUE
DATE
PAYMENT
RECEIVED
1PAYMENT APPLICATION No. 1
(ADVANCE PAYMENT)Dec-13 1,648,225 1,648,225 1,648,225 23-Nov-13
1,648,225 29-Jan-14 1,648,225 6-Feb-14
2 PAYMENT APPLICATION No. 2 Jan-14 2,291,277 643,052 514,442
12-Feb-14 514,442 02-Apr-14 513,608 10-Apr-14
3 PAYMENT APPLICATION No. 3 Feb&Mar-14 2,808,644 517,367
504,147 06-Apr-14 434,917 03-May-14 414,674 6-Aug-14
4 PAYMENT APPLICATION No. 4 Apr-14 3,315,692 507,048 417,900
08-May-14 407,538 05-Jun-14 395,257 6-Aug-14
5 PAYMENT APPLICATION No. 5 May-14 4,109,460 793,768 650,802
05-Jun-14 445,708 04-Jul-14 374,172 6-Aug-14
6 PAYMENT APPLICATION No. 6 Jun-14 4,293,764 184,304 382,116
15-Jul-14 382,116 16-Jul-14 418,721 9-Sep-14
7 PAYMENT APPLICATION No. 7 Jul&Aug-14 5,749,546 1,455,782
1,164,626 14-Sep-14 1,123,023 18-Sep-14 1,123,023 19-Oct-14
8 PAYMENT APPLICATION No. 8 Sep-14 6,857,752 1,108,206 928,167
21-Oct-14 928,805 06-Nov-14
9 PAYMENT APPLICATION No. 9 Oct-14
10 PAYMENT APPLICATION No. 10 Nov-14
11 PAYMENT APPLICATION No. 11 Dec-14
12 PAYMENT APPLICATION No. 12 Jan-15
13 PAYMENT APPLICATION No. 13 Feb-15
14 PAYMENT APPLICATION No. 14 Mar-15
15 PAYMENT APPLICATION No. 15 Apr-15
16 PAYMENT APPLICATION No. 16 May-15
17 PAYMENT APPLICATION No. 17 Jun-15
18 PAYMENT APPLICATION No. 18 Jul-15
19 PAYMENT APPLICATION No. 19 Aug-15
20 PAYMENT APPLICATION No. 20 Sep-15
21 PAYMENT APPLICATION No. 21 Oct-15
- 6,857,752 6,210,425 5,884,774 4,887,679 TOTAL AMOUNT
(R.O.)
-
14. Details of Equipment Available At Site
Sl.
No.CCC HIRED
TOTAL
AVAILABLE
AT SITE
1 COMPRESSOR
2 AIR COMPRESSOR 2 1 3
3 MILLER WELDING MECHINE 2 2
4 GENERATOR 2 1 3
5 CRANES -
6 CRANES 30 TON / 25 TON / 70 TON 2 4 6
7 VEHICLES H.D. -
8 DIESEL TANKER -
9 FLAT TRAILER 2 2
10 HIAB TRUCK 2 2
11 P/MOVER + TIPPING TRAILER 4 5 9
12 TIPPER TRUCKS 11 4 15
13 WATER TANKER 5000 & 10000 GAL 1 6 7
14 EARTH MOVING PLANT
15 BOBCAT 1 2 3
16 EXCAVATOR 1 1
17 JCB 4CX / 3CX 1 5 6
18 SHOVEL / WHEEL LOADER 3 2 5
19 DOZER D9N/D8R 2 2
20 TELEHANDLER -
21 CIVIL ENGINEERING EQUIPMENT
22 GREENE STABILIZER PLANT 1 1
23 DYNAPAC S/ROLLER -
24 E/WORK ROLLER 1 3 4
25 MOTOR GRADER 1 4 5
26 TITAN PAVER MACHINE -
27 TYRE / PTR ROLLER -
28 PAVER MACHINE -
29 L. D. VEHICLES & TRUCKS
30 DYNA TRUCK 1 2 3
31 MAINTENANCE TRUCKS 1 1
32 ASHOK LEYLAND BUS 55 SEAT 5 5
33 TOYOTA COASTER BUS 24 S 1 1
34 TOYOTA COROLLA/CIVIC/YARIS 12 12
35 TOYOTA PICKUP/ISUZU 5 8 13
36 NISSAN PATHFINDER/X-TRAIL 5 5
37 TOYOTA LAND CRUISER/FORTUNER 4 4
38 Total 45 75 120
DESCRIPTION
-
Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14
Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15
Jul-15 Aug-15 Sep-15 Oct-15 Total
PLANNED TOTAL PER MONTH 47 68 87 95 93 107 110 108 102 100 98 87
82 79 77 66 53 41 1500
REVISED PLANNED TOTAL PER MONTH 68 87 95 93 107 110 108 102 100
98 87 82 79 77 66 53 41
PLANNED CUMULATIVE 47 115 202 297 390 458 545 640 733 840 950
1,058 1,160 1,260 1,358 1,445 1,527 1,606 1,683 1,749 1,802
1,843
ACTUAL TOTAL PER MONTH 33 55 66 68 77 86 88 100 109 112 120
914
ACTUAL CUMULATIVE 33 88 154 222 299 385 473 573 682 794 914
2014 2015
47
68
87
95
93
107 110
108
102
100
98
87
82
79
77
66
53
41
33
55
66 68
77
86 88
100
109 112
120
68
87
95 93
107110 108
102 100 98
8782
79 77
66
53
41
0
20
40
60
80
100
120
140
Jan
-14
Feb-1
4
Mar-
14
Apr-
14
May-1
4
Ju
n-1
4
Ju
l-14
Aug
-14
Sep-1
4
Oct-
14
Nov-1
4
Dec-1
4
Jan
-15
Feb-1
5
Mar-
15
Apr-
15
May-1
5
Ju
n-1
5
Ju
l-15
Aug
-15
Sep-1
5
Oct-
15
No
. o
f E
QU
IPM
EN
T
PROJECT MONTHS
PLANNED TOTAL PER MONTH
ACTUAL TOTAL PER MONTH
REVISED PLANNED TOTAL PER MONTH
-
15. Details of Manpower Available At Site
BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL
A - MANAGEMENT *** 3 3
B - COMMERCIAL STAFF * 7 1 8
C - ENGINEERS 6 1 7
D - FOREMAN & C/H 22 2 24
E - ENGINEERING TECHNICIANS ** 24 5 29
F - DAILY RATED EMPLOYEES :
1 - SKILLED CRAFTSMEN 144 68 212
2 - SEMI-SKILLED/UNSKILLED 500 53 553
TOTAL AS OF END OF THE MONTH 0 706 0 130 0 836
G - SUBCONTRACTORS
Number of Personnel employed by Subcontractor on Company Work :
44
* Includes all Administrative office functions, personnel,
services, camps,
insurance, accounts, EDP, stores and purchase staff
STAFF & LABOUR
EXPATRIATES NATIONALS TOTAL
-
2013Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14
Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15
May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Total
PLANNED TOTAL PER MONTH - ( DIRECT ) 6 34 186 375 586 791 792
799 794 793 701 480 381 269 246 307 307 305 149 8301
565 756 754 750 700 652 667 554 516 387 297 276 365 271 135 92
51 7788
PLANNED TOTAL PER MONTH - ( INDIRECT ) 5 23 36 50 52 57 59 59 60
61 63 61 61 57 51 47 44 35 30 914
REVISED - PLANNED TOTAL PER MONTH-(INDIRECT) 63 84 84 83 78 72
74 61 57 43 33 31 40 30 15 10 6 862
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) 11 57 222 425
638 848 851 858 854 854 764 541 442 326 297 354 351 340 179
9215
REVISED - PLANNED - ( DIRECT + INDIRECT ) 627 840 838 833 778
725 741 616 573 429 330 306 406 301 150 102 57 8651
PLANNED CUMULATIVE 11 68 291 715 1,353 2,202 3,052 3,910 4,764
5,618 6,383 6,923 7,365 7,691 7,988 8,342 8,693 9,033 9,212
9,212
ACTUAL TOTAL PER MONTH - ( DIRECT ) 322 365 550 581 603 691 709
756 734 773 767 765 7616
ACTUAL TOTAL PER MONTH - ( INDIRECT ) 18 26 46 49 54 57 64 69 68
70 71 71 663
ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT ) 340 391 596 630
657 748 773 825 802 843 838 836 0 0 0 0 0 0 0 8279
ACTUAL CUMULATIVE 340 731 1,327 1,957 2,614 3,362 4,135 4,960
5,762 6,605 7,443 8,279
REVISED - PLANNED TOTAL PER MONTH - ( DIRECT )
2014 2015
11
57
222
425
638
848
851
858
854
854
764
541
442
326
297
354
351
340
179
340
391
596 6
30 657
748 773
825
802 8
43
838
836
0 0 0 0 0 0 00
100
200
300
400
500
600
700
800
900
Dec-1
3
Jan
-14
Feb-1
4
Mar-
14
Apr-
14
May-1
4
Ju
n-1
4
Ju
l-14
Aug
-14
Sep-1
4
Oct-
14
Nov-1
4
Dec-1
4
Jan
-15
Feb-1
5
Mar-
15
Apr-
15
May-1
5
Ju
n-1
5
Ju
l-15
Aug
-15
Sep-1
5
Oct-
15
No
. o
f M
en
PROJECT MONTHS
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) ACTUAL TOTAL PER
MONTH - ( DIRECT + INDIRECT ) REVISED - PLANNED - ( DIRECT +
INDIRECT )
-
16. QA/QC Reports
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 34
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 35
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 36
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 37
-
17. Status of Material Approvals
Date
Submitted
CCC/FQI/REN/MAS/001 MAS/CCC/FQI/BBC/001 Bituminous Base Course
Tarmac Zawawi LLC Oman 22/12/2013 Renardet APPROVED 01/04/2014
SO/FQI/CCC/087 07/04/2014
CCC/FQI/REN/MAS/002 MAS/CCC/FQI/GTI/002 Geotechnical
Investigation Swissboring & Company LLC 26/12/2013 Renardet
APPROVED 02/02/2014 SO/FQI/CCC/015 12/02/2014
CCC/FQI/REN/MAS/003 MAS/CCC/FQI/MSE/003 MSE Wall System
Freyssinet Arabian Sea LLC 26/12/2013 Renardet APPROVED 02/02/2014
SO/FQI/CCC/014 12/02/2014
CCC/FQI/REN/MAS/004 MAS/CCC/FQI/PVC/004 UPVC Pipes Amiantit Oman
26/12/2013 Renardet APPROVED 09/02/2014 SO/FQI/CCC/019
18/02/2014
CCC/FQI/REN/MAS/005 MAS/CCC/FQI/HDPE/005 HDPE Pipes &
Fittings Amiantit Oman 26/12/2013 Renardet APPROVED 09/02/2014
SO/FQI/CCC/020 18/02/2014
CCC/FQI/REN/MAS/006 MAS/CCC/FQI/PW/006 Piling Works APCC LLC
26/01/2014 Renardet APPROVED 19/02/2014 SO/FQI/CCC/026
25/02/2014
CCC/FQI/REN/MAS/007 MAS/CCC/FQI/MC/007 Bitnuminous Prime Coat
(MC-70) Emirates Lube Oil Co. (Muscat) 30/01/2014 Renardet APPROVED
09/03/2014 SO/FQI/CCC/069 27/03/2014
CCC/FQI/REN/MAS/008 MAS/CCC/FQI/RS/008 Reinforcing Steel Muscat
Steel Industries 02/02/2014 Renardet APPROVED 20/03/2014
SO/FQI/CCC/063 24/03/2014
CCC/FQI/REN/MAS/009-1 MAS/CCC/FQI/PT/009-1 Post Tensioning Work
- Anchorage Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED
27/03/2014 SO/FQI/CCC/089 14/04/2014
CCC/FQI/REN/MAS/009-2 MAS/CCC/FQI/PT/009-2 Post Tensioning Work
- Duct Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED
27/03/2014 SO/FQI/CCC/090 14/04/2014
CCC/FQI/REN/MAS/009-3 MAS/CCC/FQI/PT/009-3 Post Tensioning Work
- Strand Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED
27/03/2014 SO/FQI/CCC/091 14/04/2014
CCC/FQI/REN/MAS/010A-Rev.1MAS/CCC/FQI/PB/010A-Rev.1Bridge Pot
Bearings Al Ammar International 07/05/2014 Renardet Not Approved
--- REN/FQI/CCC/111 13/05/2014
CCC/FQI/REN/MAS/010B MAS/CCC/FQI/PB/010B Bridge Pot Bearings
Building Supplies & Services 11/05/2014 Renardet APPROVED
25/05/2014 REN/FQI/CCC/122 31/05/2014
CCC/FQI/REN/MAS/011 MAS/CCC/FQI/HDPE/011 HDPE Water Pipes
Amiantit Oman 22/02/2014 Renardet APPROVED 09/03/2014
SO/FQI/CCC/038 11/03/2014
CCC/FQI/REN/MAS/012 MAS/CCC/FQI/RCBC/012 Single cell Precast Box
Culvert Amiantit Oman 22/02/2014 Renardet APPROVED 25/03/2014
SO/FQI/CCC/064 26/03/2014
CCC/FQI/REN/MAS/013 MAS/CCC/FQI/BP/013 Bituminous Paint Material
(Rubberized) Al Inma Building Materilal LLC 02/03/2014 Renardet Not
Approved 20/04/2014 REN/FQI/CCC/105 05/05/2014
CCC/FQI/REN/MAS/013A MAS/CCC/FQI/BP/013A Bituminous Paint
Material (Rubberized) Henkel Polybit Industries Ltd. 17/06/2014
Renardet APPROVED 03/07/2014 REN/FQI/CCC/146 13/07/2014
CCC/FQI/REN/MAS/014A-Rev.1MAS/CCC/FQI/EJ/014A-Rev.1Bridge
Expansion Joints Al Ammar International 07/05/2014 Renardet
APPROVED 20/05/2014 REN/FQI/CCC/123 31/05/2014
MAS/CCC/FQI/EJ/014B Bridge Expansion Joints Ocean Rubber Factory
LLC 09/11/2014 Renardet
CCC/FQI/REN/MAS/015 MAS/CCC/FQI/RC/015Reinforced Concrete Pipe
(450,600,700mm
dia)Amiantit Oman 02/03/2014 Renardet APPROVED 23/03/2014
SO/FQI/CCC/077 02/04/2014
CCC/FQI/REN/MAS/016 B MAS/CCC/FQI/WS/016 B Water Stop G EE-25
Sika LLC Oman 25/03/2014 Renardet APPROVED 16/04/2014
REN/FQI/CCC/099 28/04/2014
Renardet
Letter
Dated
Reference No. MAR No. Material/ Work Manufacturer/Supplier/
Subcontractor
Submitte
d To
Remarks
By MOTC
MOTC
Comments
dated
Via Renardet
Letter Ref. No.
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS
Date
Submitted
CCC/FQI/REN/MAS/017 MAS/CCC/FQI/TW/017 Telephone Works National
Telephone Services 12/03/2014 Renardet APPROVED 17/03/2014
SO/FQI/CCC/082 03/04/2014
CCC/FQI/REN/MAS/019 MAS/CCC/FQI/EW/019 Electrical Works United
Engineering Projects 22/03/2014 Renardet APPROVED 29/05/2014
REN/FQI/CCC/131 16/06/2014
CCC/FQI/REN/MAS/020 MAS/CCC/FQI/EC/020 MV & LV Cables United
Engineering Projects 19/03/2014 Renardet APPROVED 27/03/2014
SO/FQI/CCC/083 03/04/2014
CCC/FQI/REN/MAS/021 MAS/CCC/FQI/PS/021 Package Substation United
Engineering Projects 22/03/2014 Renardet ---- ----
CCC/FQI/REN/MAS/021A MAS/CCC/FQI/PS/021A Package Substation
Voltamp Energy SAOG 16/09/2014 RenardetAPPROVED
as Noted3/11/2014 REN/FQI/CCC/202 30/11/2014
CCC/FQI/REN/MAS/022 MAS/CCC/FQI/LL/022 Street Lighting
Luminaries Majees Lighting Industries LLC 27/03/2014 Renardet
APPROVED 14/08/2014 REN/FQI/CCC/158 17/08/2014
CCC/FQI/REN/MAS/023A MAS/CCC/FQI/LP/023A Street Lighting Poles
(Mid-Hinged)Al Babtain Power &
Telecomunication Co., S.Arabia22/05/2014 Renardet APPROVED
14/08/2014 REN/FQI/CCC/157 17/08/2014
CCC/FQI/REN/MAS/024 MAS/CCC/FQI/FP/024 Street Lighting Feeder
Pillar Stars Light LLC 27/03/2014 Renardet APPROVED 08/06/2014
REN/FQI/CCC/130 16/06/2014
CCC/FQI/REN/MAS/025 MAS/CCC/FQI/JS/025 Joint Sealant (Polyseal)
Al Inma Building Materilal LLC 27/03/2014 Renardet APPROVED
16/04/2014 REN/FQI/CCC/100 28/04/2014
CCC/FQI/REN/MAS/026 MAS/CCC/FQI/GT/026 Geotextile Modern East
Trading & Con. 21/05/2014 RenardetNo meet the
HDS--- REN/FQI/CCC/119 27/05/2014
CCC/FQI/REN/MAS/026A MAS/CCC/FQI/GT/026A Geotextile (Bonar NW16)
Bonar Technical Fabrics 15/06/2014 Renardet APPROVED 14/08/2014
REN/FQI/CCC/159 17/08/2014
CCC/FQI/REN/MAS/027 MAS/CCC/FQI/MS/027Masterseal 915
(formerly known as Masterflow 410 Plus)OBasf The Chemical
Company 10/08/2014 Renardet
APPROVED
as Noted21/10/2014 REN/FQI/CCC/196 17/11/2014
CCC/FQI/REN/MAS/028 MAS/CCC/FQI/GG/028 Gully Gratings &
Frames RBA Ferro Industries PVT. Ltd. 17/08/2014 Renardet APPROVED
25/09/2014 REN/FQI/CCC/192 15/10/2014
CCC/FQI/REN/MAS/030 MAS/CCC/FQI/FLC/030MasterRoc FLC 100 (Cable
Grout
Admixture)BASF-The Chemical Company 02/10/2014 Renardet
CCC/FQI/REN/MAS/032 MAS/CCC/FQI/GR/032 Guardrails GK Wire
Industries LLC 29/10/2014 Renardet
CCC/FQI/REN/MAS/033 MAS/CCC/FQI/PVC-D/033 1/2" to 8" UPVC Pipe
(Class D) Oman Plast 03/11/2014 Renardet
MAS/CCC/FQI/SS1H/034 Tack Coat (SS1H) Bitu Trade Industrial LLC
15/11/2014 Renardet
CANCELLED
Reference No. MAR No. Material/ Work
Renardet
Letter
Dated
Manufacturer/Supplier/
Subcontractor
Submitte
d To
Remarks
By MOTC
MOTC
Comments
dated
Via Renardet
Letter Ref. No.
-
18. Engineers Comments
The Planned progress as per the revised Project Execution
Program for the month of
November is 7.98% and the Actual progress is 6.02% which shows
1.96% of delay
for the month of November. The actual cumulative progress up to
November is
51.41% against Planned Cumulative Progress of 55.53% showing a
lagging of
4.12%. The delayed progress is mainly due to the additional
works undertaken
during the last few months which must be recovered in the coming
months.
Sohar Airport Approach road is completed on priority basis based
on the
requirement of DGR.
MSE Wall works are progressing well and reaching the completion
stage on
Abutment 1 side.
The first Box Girder of Superstructure is casted during this
month and works in
progress for second Box Girder.
Works for the 02 newly proposed Vehicular Underpasses are
commenced and in
progress.
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 41
19. PROGRESS PHOTOGRAPHS
Pouring o
f C
oncre
te f
or
Deck S
lab in B
ox G
irder
of
Fly
over
Bridge
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 42
Installation of Pot Bearings
Testing of Pot Bearings in Third Party Laboratory in Italy
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 43
Concrete Pouring in 9 Cells Box Culvert
Earthworks Filling in Progress in Flyover Approach on Muscat
side
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 44
Earthworks Filling in Progress in Flyover AB2 side Approach
Earthworks Filling in Progress in Flyover AB2 side Approach
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 45
Jointing of Electrical Cables
Installation of Drainage Crossings
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 46
Flood Water Crossing the Project Detour during the Rain
DGR Representative Consulting the Local Public after Flood
-
Project: Upgrading of Falaj Al Qabail Roundabout Monthly
Progress Report November 2014
RENARDET S.A. & PARTNERS Page 47
Installation of MSE Wall Panels in Progress
Testing of Grouting Material for Post Tensioning Works in
Progress