Top Banner
SULTANATE OF OMAN MINISTRY OF TRANSPORT AND COMMUNICATIONS DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT MUSCAT UPGRADING OF FALAJ AL QABAIL ROUNDABOUT TENDER NO. 51/2012 MONTHLY PROGRESS REPORT NO. 11 NOVEMBER 2014 CONSULTANT: RENARDET S.A. & PARTNERS CONSULTING ENGINEERS LLC. P.O. Box 579, Muscat, P.C. 100, Sultanate of Oman CONTRACTOR: CONSOLIDATED CONTRACTORS CO. LLC P.O. Box 614, Muscat, P.C. 100, Sultanate of Oman
59

FQI-MPR-2014-11

Sep 28, 2015

Download

Documents

muneerpmh

Monthly Progress Report for a major Interchange project in Oman for the month of September 2014.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • SULTANATE OF OMAN

    MINISTRY OF TRANSPORT AND COMMUNICATIONS DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT

    MUSCAT

    UPGRADING OF FALAJ AL QABAIL ROUNDABOUT TENDER NO. 51/2012

    MONTHLY PROGRESS REPORT NO. 11

    NOVEMBER 2014

    CONSULTANT:

    RENARDET S.A. & PARTNERS CONSULTING ENGINEERS LLC. P.O. Box 579, Muscat, P.C. 100, Sultanate of Oman

    CONTRACTOR:

    CONSOLIDATED CONTRACTORS CO. LLC P.O. Box 614, Muscat, P.C. 100, Sultanate of Oman

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 1

    Table of Contents

    1. PROJECT PARTICULARS .............................................................................................................................................. 2

    2. SCOPE OF WORK ....................................................................................................................................................... 3

    3. TYPICAL CROSS SECTIONS .......................................................................................................................................... 4

    4. SITE VISITS/ MEETINGS .............................................................................................................................................. 6

    5. ENGINEERS SITE STAFF ............................................................................................................................................. 7

    6. PROGRESS S-CURVE ................................................................................................................................................... 8

    7. STATUS OF MAJOR ACTIVITIES ................................................................................................................................ 10

    8. BRIDGE PROGRESS SCHEDULE ................................................................................................................................. 11

    9. MSE WALLS PROGRESS SCHEDULE ........................................................................................................................... 12

    10. BOX CULVERTS PROGRESS SCHEDULE ...................................................................................................................... 15

    11. PROGRESS STATUS OF UTILITY CROSSING DUCTS .................................................................................................... 19

    12. PROJECT PROGRESS STRIP CHART ........................................................................................................................... 22

    13. FINANCIAL STATUS OF PAYMENTS .......................................................................................................................... 28

    14. DETAILS OF EQUIPMENT AVAILABLE AT SITE ........................................................................................................... 29

    15. DETAILS OF MANPOWER AVAILABLE AT SITE .......................................................................................................... 31

    16. QA/QC REPORTS ...................................................................................................................................................... 33

    17. STATUS OF MATERIAL APPROVALS .......................................................................................................................... 38

    18. ENGINEERS COMMENTS ......................................................................................................................................... 40

    19. PROGRESS PHOTOGRAPHS ...................................................................................................................................... 41

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 2

    1. Project Particulars

    Client: Ministry of Transport & Communications

    P.O. Box 684, Muscat, Postal Code 113

    Directorate General of Roads

    Sultanate of Oman.

    Consultant: Renardet S.A & Partners L.L.C.

    P.O. Box 579, Muscat, Postal Code 100

    Sultanate of Oman.

    Contractor: Consolidated Contractors Company L.L.C.

    P.O. Box 614, Muscat, Postal Code 100

    Sultanate of Oman.

    Project Commencement Date: 30.10.2013

    Mobilization Period: 60 Days

    Construction Period: 548 Days

    Completion date: 29.06.2015

    Original Contract Value:

    (Including Contingencies) R.O. 17,884,403.000

    Amount of Contingencies: R.O. 1,402,155.613

    Original Contract Value:

    (Excluding Contingencies) R.O. 16,482,247.387

    Planned Physical Progress for November

    2014 7.98%

    Actual Physical Progress for November

    2014 6.02%

    Planned physical progress cumulative up to

    end of November 2014

    55.53%

    Achieved physical progress cumulative up

    to end of November 2014 51.41%

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 3

    2. Scope of Work

    This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and

    consists of construction of an interchange in place of existing roundabout along with allied works.

    Total length of the project along Batinah highway is about 4.0 km which shall be converted from four

    lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of

    work is the construction of service roads, pedestrian underpasses.

    The work also includes expropriation of properties, relocation/protection of services (sewerage,

    telephone, electricity, water, irrigation) road lighting works and traffic signals.

    Major items within the scope of work consist of but not limited to the following:

    Removal of existing asphalt surface, extension of existing embankment and earthwork to

    achieve the designed profile and gradient.

    Removal of existing drainage structures and construction of new ones including protection

    works as shown on construction drawings and as directed.

    Expropriation of open/built up properties and removal of existing structures thereupon.

    Construction of interchange ramps, Box Girder Bridge, roundabout, pedestrian underpasses and

    service roads.

    Provision of new street lighting system/traffic signals and removal/disposal of existing street

    light poles including conductors/cables, transformers, feeder pillars, foundations etc., all for the

    proper completion of the job.

    Construction of earthen embankment/sub grade, sub-base, aggregate base course, bituminous

    base course and bituminous wearing course as per details on the construction drawings.

    Installation of road side furniture (traffic signs, road marking etc.) and protection works on

    embankment slopes.

    Relocation/Protection of existing LT, 11KV and 33KV transmission lines and allied items

    (transformers etc.) as per the requirements of concerned authority.

    Relocation/Protection of existing utilities (sewerage, telephone, electricity, water lines and

    irrigation) as per the requirements of concerned authorities.

    Provision of ducts for future utilities as per the requirements of utility operator.

    Construction of concrete safety barriers, fixing of guard rails and paving tiles.

    Provision of traffic diversion in coordination with concerned authorities.

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 4

    3. Typical Cross Sections

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 5

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 6

    4. Site visits/ Meetings

    S. No. Details of Site Visit/ meeting Date Final Outcome/ Decisions

    1 Visit to Independent Laboratory in

    Italy for witnessing the testing of Pot

    Bearings

    09.11.2014

    to

    14.11.2014

    One Fixed Bearing and one

    Guided Bearing are tested and

    found in compliance with standard

    requirements.

    2 Monthly review meeting at Project

    Office

    24.11.2014 Various project issues are discussed.

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 7

    5. Engineers Site Staff

    S.

    No. Name Designation

    Date of

    Joining

    1. Roberto Benigni Head Supervision Projects

    2. Muneer Abdul Resident Engineer 19.03.2014

    3. Hussein Shah Material Engineer 04.01.2014

    4. Ernesto B. Paredes Bridge Engineer 16.04.2014

    5. Sande H Tangaras Civil Engineer 08.06.2014

    6. Danilo Quantity Surveyor 19.06.2014

    6. Mohamed Safie Land Surveyor 04.01.2014

    7. Aseef Iqbal Site Inspector 10.02.2014

    8. Alaa Aldin Abdelfatah Site Inspector 30.03.2014

    9. Walid Samy Abdoh Mostafa Material Inspector 01.04.2014

    10. Haneefa Mohmmed Al Zadjali Secretary 13.04.2014

  • 6. Progress S-Curve

    2013

    Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

    0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -

    0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 7.69 7.98 8.32 6.96 6.50 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62

    - 0.28 0.18 1.01 3.20 5.35 5.18 7.36 7.30 9.33 6.20 6.02 - - - - - - - - - - -

    0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00

    0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00

    - 0.28 0.45 1.46 4.66 10.01 15.19 22.55 29.86 39.18 45.39 51.41

    CUMULATIVE PROGRESS

    CL14 Org Plan Cumulative %

    Actual Cumulative

    2014 2015

    MONTHLY PROGRESS

    CL14 Org Plan per Month %

    Actual per Month

    Revised Sch. per Month %

    Revised Sch. Cummulative %

    0.00

    20.00

    40.00

    60.00

    80.00

    100.00

    120.00

    -

    2

    4

    6

    8

    10

    12

    Dec

    Jan

    Fe

    b

    Ma

    r

    Apr

    Ma

    y

    Jun

    Jul

    Aug

    Sep

    Oct

    Nov

    Dec

    Jan

    Fe

    b

    Ma

    r

    Apr

    Ma

    y

    Jun

    Jul

    Aug

    Sep

    Oct

    2013 2014 2015

    % C

    um

    ula

    tive

    % M

    ON

    TH

    LY

    MONTHS

    UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMANMONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS

    CL14 Org Plan per Month % Revised Sch. per Month % Actual per Month CL14 Org Plan Cumulative % Revised Sch. Cummulative % Actual Cumulative

  • REV.: 0

    PERIOD ENDING: Nov-14

    2013

    Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

    CL14 Plan % 0.30 8.67 19.23 26.89 31.77 36.64 41.51 46.39 51.26 56.13 61.01 65.88 70.76 75.63 80.50 85.38 90.25 95.13 100.00 100.00 100.00 100.00 100.00

    Revised Plan % 4.11 9.30 17.58 24.18 30.90 35.16 38.97 42.78 46.60 50.41 54.23 58.04 61.86 65.67 69.48 73.30 77.11 80.93 84.74 88.56 92.37 96.18 100.00

    Actual - 6.62 13.03 22.36 37.31 43.00 44.11 51.21 56.24 60.13 65.67 69.96

    CL14 Plan % 0.00 0.00 0.38 20.37 47.70 48.33 48.33 48.33 48.33 48.33 48.33 48.33 48.33 59.91 77.84 90.27 94.93 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - 7.40 29.85 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 78.13 80.66 87.59 88.57 100.00 100.00 100.00

    Actual - 10.09 10.09 17.59 19.52 77.42 69.96 70.18 70.18 70.18 83.49 84.12

    CL14 Plan % 0.00 0.00 0.00 0.78 6.58 16.76 29.38 41.37 58.64 66.60 74.18 82.85 84.75 84.75 85.24 92.34 92.34 98.36 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - 3.32 12.89 28.83 43.89 60.03 74.82 90.03 95.24 95.95 95.95 96.09 98.30 99.46 99.54 100.00 100.00

    Actual - - - - 4.35 4.89 - 5.27 14.93 29.52 47.15 47.31

    CL14 Plan % 0.00 0.00 1.01 9.21 29.30 45.91 56.90 62.24 64.59 67.94 69.08 69.08 75.05 82.85 93.48 98.64 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - 4.26 8.17 16.03 32.68 53.13 67.05 67.47 67.47 67.90 68.32 68.32 68.32 81.11 93.02 97.11 100.00 100.00 100.00

    Actual - - - 5.00 5.00 53.23 62.16 74.91 78.29 91.86 98.62 115.33

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 11.07 26.27 41.98 59.98 78.73 79.90 79.90 85.20 89.45 92.60 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - - - - - 3.58 17.42 31.37 51.32 75.82 75.82 75.82 75.82 87.25 87.25 98.60 100.00

    Actual 1.26 3.19 5.42

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.08 7.77 19.32 31.22 44.94 51.98 52.14 90.14 90.14 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - - - - - - - 0.08 8.44 22.42 46.57 51.97 51.97 86.66 90.05 93.03 100.00

    Actual

    CL14 Plan % 0.00 0.00 0.23 1.43 2.97 10.17 23.65 36.51 51.47 63.06 74.26 75.97 77.37 80.05 82.40 88.97 92.13 98.55 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - 0.26 2.64 7.33 20.62 35.14 50.06 62.76 68.40 72.78 74.07 74.67 83.42 84.04 84.30 87.32 95.58 98.11 99.44 100.00 100.00

    Actual - - - 0.48 1.26 5.59 14.93 27.72 40.08 55.38 66.20 71.35

    CL14 Plan % 0.00 0.00 4.02 15.21 34.62 57.89 69.26 81.40 83.38 83.46 84.50 92.89 99.96 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - 2.77 7.75 13.76 22.09 29.64 39.02 49.64 59.51 71.33 85.14 87.00 93.50 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Actual - - - 0.01 6.05 14.73 18.14 22.33 26.30 30.75 34.14 46.19

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.38 1.21 2.63 3.42 4.23 5.50 6.08 6.08 34.35 99.38 99.76 99.76 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - - - - 8.09 26.17 57.85 78.53 94.70 94.70 94.70 94.70 98.41 100.00 100.00 100.00 100.00

    Actual - - - 2.50 36.38 14.39 13.24 16.19 16.72 27.56 21.22 41.44

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.80 17.87 43.85 61.59 72.98 81.15 83.94 84.42 85.35 92.86 96.39 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - - - - 7.02 20.33 38.29 50.60 59.52 72.89 81.07 83.55 86.89 90.26 95.34 98.27 100.00

    Actual - - - - - 2.61 4.98 6.42 8.31 10.67 12.36 14.45

    CL14 Plan % 0.00 0.00 0.00 4.43 17.23 33.36 49.13 65.07 80.79 93.82 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - 0.99 2.30 17.26 33.64 49.01 64.70 79.88 95.44 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00

    Actual - - - 6.16 9.87 17.63 25.69 35.90 49.03 65.95 72.27 72.29

    CL14 Plan % 0.00 0.00 0.00 0.00 0.00 0.17 0.79 1.43 5.65 13.41 21.84 30.56 32.94 70.94 75.04 94.02 96.43 100.00 100.00 100.00 100.00 100.00 100.00

    Revised Plan % - - - - - - - 0.33 2.34 9.42 17.07 23.51 31.40 41.66 47.49 47.55 47.55 83.28 93.95 97.61 100.00 100.00 100.00

    Actual - - - 0.13 5.52 9.26 13.38 16.87 17.75 20.45 14.38 26.70

    Revised Plan 0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00

    Actual Cum - 0.28 0.45 1.46 4.66 10.01 15.19 22.55 29.86 39.18 45.39 51.41 - - - - - - - - - - -

    2013

    Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct

    0.01 0.25 1.42 4.23 7.25 10.06 9.42 9.73 10.21 9.79 8.49 5.72 4.55 3.56 2.79 3.83 3.55 3.47 1.67 - - - -

    0.11 0.14 0.23 0.28 1.71 3.18 6.84 9.16 9.14 9.08 7.69 7.98 8.32 6.96 6.50 4.68 3.59 3.34 4.42 3.29 1.64 1.11 0.62

    - 0.28 0.18 1.01 3.20 5.35 5.18 7.36 7.30 9.33 6.20 6.02

    0.01 0.26 1.67 5.91 13.15 23.21 32.64 42.37 52.58 62.37 70.86 76.59 81.13 84.69 87.48 91.31 94.86 98.33 100.00 100.00 100.00 100.00 100.00

    0.11 0.25 0.48 0.76 2.47 5.64 12.48 21.64 30.78 39.87 47.55 55.53 63.86 70.81 77.31 81.99 85.59 88.93 93.35 96.64 98.27 99.38 100.00

    - 0.28 0.45 1.46 4.66 10.01 15.19 22.55 29.86 39.18 45.39 51.41

    2014 2015

    MONTHLY PROGRESS

    CL14 Org Plan per Month %

    Actual per Month

    CUMULATIVE PROGRESS

    CL14 Org Plan Cumulative %

    Actual Cumulative

    MMEP Works &

    Ducts#REF!

    TOTAL #REF!

    Revised Sch. per Month %

    Revised Sch. Cummulative %

    #REF!

    #REF!

    L MSE walls #REF!

    J Drainage Works #REF!

    KIncidental

    Construction#REF!

    #REF!

    #REF!

    #REF!

    IConcrete for

    Bridge#REF!

    H

    Concrete for

    Box Culvert

    /Underpas

    #REF!#REF!

    #REF!

    GBituminous

    Pavement#REF!

    FSubbase &

    Aggregate Base#REF!#REF!

    #REF!

    EStructural

    Excavation#REF!

    D Embankment #REF!#REF!

    #REF!

    C

    Clearing &

    Removal of

    Obstructions

    #REF!

    2015

    B Road Diversions #REF!

    Budgeted

    Man-Hrs

    #REF!

    #REF!

    UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN

    MANHOURS OVERALL PROJECT S-CURVE

    Item Description Wtd.

    %

    Plan/

    Actual

    2014

  • 7. Status of Major Activities

    Sl. No.

    Description Unit BOQ Qty.

    (Revised)

    Actual Qty.

    % Completion

    1 Clearing & Grubbing M2 162,000 129,901 80.19%

    2 Borrow Excavation (to embankment)

    M3 340,000 155,167 45.64%

    3 Granular Sub-base M3 28,700 6,449 22.47%

    4 Concrete for Culverts M3 15,000 12,805 85.37%

    5 Concrete for Bridge M3 13,805 3,991 28.91%

    6 Steel reinforcement Fixing ton 4,900 2,477 50.55%

    7 Working Piles M3 2,826 2,826 100.00%

    8 Mortared Stone Riprap M3 5,210 0.00 0.00%

    9 MSE Walls M2 13,200 7,389 55.97%

    11 RCC Drainage Pipes LM 4,530 1,035 22.85%

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 11

    8. Bridge Progress Schedule

    ACTIVITY AB1 L P1L P2L P4L P5L AB2 LPEDESTAL/POT

    BEARING9-Nov-14 9-Nov-14 9-Nov-14 15-Nov-14 - - -

    PIER N/A - - - - N/A

    2nd Lift - 13-Aug-14 19-Aug-14 29-Sep-14 4-Sep-14 -

    Height (m) - 6.920 6.920 6.920 6.920 -

    1st Lift - 23-Jul-14 7-Aug-14 15-Sep-14 10-Aug-14 -

    Height (m) - 1.153 1.210 1.248 1.225 -

    BIT. PAINTING - 28-May-14 26-Jun-14 4-Sep-14 23-Jun-14 -

    PILE CAP (Pier &

    Abut.)4-Nov-14 17-May-14 18-Jun-14 25-Aug-14 11-Jun-14 -

    F/P & BLINDING 21-Oct-14 11-May-14 11-Jun-14 17-Aug-14 3-Jun-14 -

    ACTIVITY AB1 R P1R P2R P4R P5R AB2 RPEDESTAL/POT

    BEARING16-Oct-14 14-Oct-14 14-Oct-14 16-Oct-14 - - - -

    PIER N/A - - - - N/A

    2nd Lift - 9-Jun-14 28-Jun-14 20-Sep-14 10-Jul-14 -

    Height (m) - 6.920 6.920 6.920 6.920 -

    1st Lift - 20-May-14 11-Jun-14 10-Sep-14 22-Jun-14 -

    Height (m) - 0.366 0.423 0.461 0.438 -

    BIT. PAINTING - 12-May-14 25-May-14 4-Sep-14 31-May-14 -

    PILE CAP (Pier &

    Abut.)9-Oct-14 4-May-14 13-May-14 27-Aug-14 20-May-14 -

    F/P & BLINDING 2-Oct-14 27-Apr-14 7-May-14 20-Aug-14 14-May-14 -

    BRIDGE SUB-STRUCTURE PROGRESS SCHEDULE

    SUB-STRUCTURE WORK PROGRESS (RHS)

    SUB-STRUCTURE WORK PROGRESS (LHS)

    P3L

    24-Jul-14

    6.920

    29-Jun-14

    1.440

    17-May-14

    -

    8-May-14

    1-May-14

    0.649

    8-May-14

    30-Apr-14

    22-Apr-14

    P3R

    -

    22-Jun-14

    6.920

    26-May-14

    AB1 L P1L P2L P3L P3L P4L P5L AB2 L

    EXPANSION JOINT - - - - - - - -

    CONCRETE BARRIER - - - - - - - -

    TOP SLAB (DECK) - - - - - - - -

    WEB: - - - - - - - -

    W1 - - - - - - - -

    W2 - - - - - - - -

    W3 - - - - - - - -

    W4 - - - - - - - -

    BOTTOM SLAB

    (BASE)- - - - - - - -

    AB1 R P1R P2R P3R P3R P4R P5R AB2 R

    EXPANSION JOINT - - - - - - - -

    CONCRETE BARRIER - - - - - - - -

    TOP SLAB (DECK) 26-Nov-14 26-Nov-14 26-Nov-14 26-Nov-14 - - - -

    WEB: - - - - - - - -

    W1 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -

    W2 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -

    W3 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -

    W4 10-Nov-14 10-Nov-14 10-Nov-14 10-Nov-14 - - - -

    BOTTOM SLAB

    (BASE)28-Oct-14 28-Oct-14 28-Oct-14 28-Oct-14 - - - -

    ACTIVITY (RHS)SUPER-STRUCTURE (SPAN 1 - RHS) SUPER-STRUCTURE (SPAN 2 - RHS)

    BRIDGE SUPER-STRUCTURE PROGRESS SCHEDULE (BOX GIRDER)

    SUPER-STRUCTURE (SPAN 4 - LHS) SUPER-STRUCTURE (SPAN 3 - LHS)ACTIVITY (LHS)

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 12

    9. MSE Walls Progress Schedule

    DATE Elevation DATE

    FROM TOFOUNDATION

    /BLINDINGFROM TO

    FOUNDATION

    /BLINDING

    22+702.653 22+760 2-Oct-14 22+718.936 22+810 17-Sep-14

    3-Oct-14 18-Sep-14

    22+760 22+825 30-Sep-14 22+810 22+893.032 9-Aug-14

    1-Oct-14 10-Aug-14

    22+825 22+840 13-Jul-14 22+893.032 22+976.294 13-Aug-14

    14-Jul-14 14-Aug-14

    22+840 22+880 6-Jul-14 22+976.294 23+040 18-Aug-14

    13-Jul-14 19-Aug-14

    22+880 22+908.387 10-Aug-14 23+040 23+088.046 26-Jul-14

    11-Aug-14 27-Jul-14

    22+908.38722+969.478 3-Jul-14 23+088.046 23+130 21-Jul-14

    5-Jul-14 22-Jul-14

    22+969.478 23+000 4-Aug-14 23+130 23+191.774 7-Jul-14

    5-Aug-14 10-Jul-14

    23+000 23+025 20-Jul-14 23+191.774 23+270.800 26-Jun-14

    21-Jul-14 27-Jun-14

    23+025 23+070 17-Jul-14

    18-Jul-14

    23+070 23+140 30-Jun-14

    1-Jul-14 DATE

    23+140 23+164.573 16-Jun-14 FROM TOFOUNDATION

    /BLINDING

    17-Jun-14 23+270.762 (L)23+270.800 (R ) 26-Jun-14

    23+164.57323+237.536 23-Jun-14 27-Jun-14

    24-Jun-14

    23+237.53623+270.762 17-Jun-14

    18-Jun-14

    PREVIOUSP R EVIOUS

    M ON T HTHIS MONTH

    MSE WALL MONTHLY SCHEDULE (FOUNDATION @ APPROACH 1)

    El. 21.20

    LOCATION (AB 1)

    Elevation

    Elevation

    LOCATION (LHS)

    El. 21.20

    El. 22.00

    El. 22.00

    LOCATION (RHS)

    El. 20.40

    El. 22.00

    El. 22.00

    El. 22.80

    El. 22.00

    El. 20.40

    El. 22.80

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 13

    22+840 22+880 22+908.387 22+969.478 22+991 23+084 23+164.573 23+237.536 23+270.762

    34.800 - - - - - - - - -34.000 - - - - - - - - -33.200 - - - - - - - - -32.400 - - - - - - - - -31.600 - - - - - - - - -30.800 - - - - - - - - -30.000 - - - - - - 13-Nov-14 13-Nov-14 -29.200 - - - - - - 19-Oct-14 1-Oct-14 1-Oct-1428.400 - - - - - - 18-Oct-14 24-Sep-14 24-Sep-1427.600 - - - - - 30-Nov-14 20-Sep-14 18-Sep-14 18-Sep-1426.800 - - - - - 18-Nov-14 9-Sep-14 15-Sep-14 15-Sep-1426.000 - - - - - 20-Oct-14 4-Sep-14 28-Aug-14 28-Aug-1425.200 - - - 5-Nov-14 5-Nov-14 16-Sep-14 26-Aug-14 19-Aug-14 19-Aug-1424.400 - 25-Nov-14 25-Nov-14 29-Oct-14 29-Oct-14 4-Sep-14 18-Aug-14 6-Aug-14 6-Aug-1423.600 10-Nov-14 10-Nov-14 10-Nov-14 21-Sep-14 17-Sep-14 27-Aug-14 13-Aug-14 24-Jul-14 24-Jul-1422.800 22-Sep-14 22-Sep-14 22-Sep-14 11-Sep-14 24-Aug-14 9-Aug-14 28-Jul-14 - 13-Jul-1422.000 3-Sep-14 3-Sep-14 3-Sep-14 28-Aug-14 - - - - -21.200 28-Aug-14 28-Aug-14 28-Aug-14 - - - - - -

    20.400 - - - - - - - - -

    22+81022+893.03

    2

    22+976.29

    423+035

    23+088.04

    6

    23+191.77

    4

    23+270.80

    0

    23+270.762

    (L)

    23+270.800

    (R )

    33.200 - - - - - - - - -32.400 - - - - - - - - -31.600 - - - - - - - - -30.800 - - - - - - - - -30.000 - - - - - - - - -29.200 - - - - - 16-Nov-14 30-Sep-14 28-Sep-14 28-Sep-1428.400 - - - - - 30-Sep-14 24-Sep-14 24-Sep-14 24-Sep-1427.600 - - - - - 27-Sep-14 18-Sep-14 19-Sep-14 19-Sep-1426.800 - - - 16-Nov-14 16-Nov-14 13-Sep-14 13-Sep-14 11-Sep-14 11-Sep-1426.000 - - - 20-Oct-14 20-Oct-14 2-Sep-14 31-Aug-14 28-Aug-14 28-Aug-1425.200 - - 18-Nov-14 18-Oct-14 18-Oct-14 24-Aug-14 18-Aug-14 18-Aug-14 18-Aug-1424.400 - - 23-Oct-14 20-Sep-14 20-Sep-14 13-Aug-14 6-Aug-14 7-Aug-14 7-Aug-1423.600 - 16-Nov-14 25-Sep-14 8-Sep-14 8-Sep-14 9-Aug-14 24-Jul-14 24-Jul-14 24-Jul-1422.800 - 19-Oct-14 18-Sep-14 21-Aug-14 18-Aug-14 - 13-Jul-14 13-Jul-14 13-Jul-1422.000 27-Nov-14 23-Sep-14 26-Aug-14 - - - - - -21.200 27-Nov-14 4-Sep-14 - - - - - - -

    20.400 - - - - - - - - -

    PREVIOUSP R EVIOUS

    M ON T HTHIS MONTH

    MSE WALL MONTHLY SCHEDULE (PANELS FIXING @ APPROACH 1)

    RHS (AB 1), from Sta. 22+718.936 to Sta. 23+270.800

    ELEV.

    ELEV.

    AB 1 Face

    LHS (AB 1), from Sta. 22+702.653 to Sta. 23+270.762

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 14

    DATE DATE

    FROM TOFOUNDATION

    /BLINDINGFROM TO

    FOUNDATIO

    N /BLINDING

    23+508.239 23+520 15-Sep-14 23+508.239 (L)23+508.197 (R )15-Sep-14

    16-Sep-14 16-Sep-14

    23+520 23+580.87720-Aug-14

    21-Aug-14

    23+580.87723+650 26-Aug-14 Elevation LOCATION (RHS) DATE

    27-Aug-14 FROM TOFOUNDATIO

    N /BLINDING

    23+650 23+735 1-Sep-14 23+508.197 23+607.6348-Sep-14

    2-Sep-14 9-Sep-14

    23+735 23+790 19-Sep-14 23+607.63423+740 22-Sep-14

    20-Sep-14 23-Sep-14

    23+790 23+827.63510-Oct-14 23+740 23+750 16-Oct-14

    11-Oct-14 17-Oct-14

    23+827.63523+949.89515-Oct-14 23+750 23+950.1533-Nov-14

    16-Oct-14 4-Nov-14

    MSE WALL MONTHLY SCHEDULE (FOUNDATION @ APPROACH 2)

    El. 23.30

    El. 24.90

    El. 24.10

    El. 23.30

    LOCATION (LHS) LOCATION (AB 2)Elevation

    El. 24.10

    Elevation

    El. 23.30

    23+520 23+580.877 23+650 23+703 23+730 23+827.635 23+949.895

    29.700 - - - - - - -28.900 - - - - - - -28.100 - - - - - - -27.300 - - - - - - -26.500 8-Nov-14 8-Nov-14 15-Nov-14 15-Nov-14 24-Nov-14 - -25.700 29-Oct-14 29-Oct-14 1-Nov-14 1-Nov-14 16-Nov-14 - -24.900 13-Oct-14 13-Oct-14 26-Sep-14 26-Sep-14 13-Nov-14 - -24.100 25-Sep-14 25-Sep-14 - - - - -23.300 - - - - - - -

    23+508.239 (L)23+508.197 (R ) 23+607.634 23+690 23+740 23+950.15329.700 - - - - - -28.900 - - - - - -28.100 - - - - - -27.300 - - - - - -26.500 26-Nov-14 26-Nov-14 19-Nov-14 29-Nov-14 29-Nov-14 -25.700 5-Nov-14 5-Nov-14 11-Nov-14 25-Nov-14 25-Nov-14 -24.900 16-Oct-14 16-Oct-14 15-Oct-14 15-Oct-14 21-Nov-14 -24.100 30-Sep-14 30-Sep-14 9-Oct-14 - - -23.300 - - - - - -

    PREVIOUSP R EVIOUS

    M ON T HTHIS MONTH

    MSE WALL MONTHLY SCHEDULE (PANELS FIXING @ APPROACH 2)

    RHS (AB 2), from Sta. 23+508.197 to Sta. 23+950.153ELEV.

    AB 2 Face

    LHS (AB 2), from Sta. 23+508.239 to Sta. 23+949.895ELEV.

  • 10. Box Culverts Progress Schedule

    Rebars Concrete Rebars Concrete Rebars Concrete

    1 21+260 3 cells - 2.0 x 1.5 25.546 0 - - - - - - - -LHS Block 1 3 cells - 2.0 x 1.5 19.526 0 19-Oct-14 26-Oct-14 27-Oct-14 9-Nov-14 9-Nov-14 9-Nov-14 9-Nov-14 -RHS Block 2 3 cells - 2.0 x 1.5 14.473 0 19-Oct-14 4-Nov-14 4-Nov-14 15-Nov-14 15-Nov-14 15-Nov-14 15-Nov-14 -RHS Block 3 3 cells - 2.0 x 1.5 6.000 0 - - - - - - - -

    2 21+485 1 cell - 2.0 x 1.5 39.750 0 - - - - - - - -Block 1a 1 cell - 2.0 x 1.5 3.000 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 17.290 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2a 1 cell - 2.0 x 1.5 7.710 0 1-Jul-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 1-Sep-14Block 2b 1 cell - 2.0 x 1.5 10.000 0 19-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14 25-Oct-14Block 2C 1 cell - 2.0 x 1.5 11.730 0 - - - - - - - -

    3 21+838 2 x 4 cells (8) - 2.0 x 1.5 57.210 0 - - - - - - - -Block 1a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 -Block 1b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 4-Sep-14 5-Sep-14 13-Oct-14 13-Oct-14 13-Oct-14 13-Oct-14 -Block 2 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 20-Aug-14 20-Aug-14 30-Oct-14 30-Oct-14 30-Oct-14 30-Oct-14 -Block 3 1 x 4 cells - 2.0 x 1.5 11.970 0 - - - - - - - -

    Block 4a 1 x 4 cells - 2.0 x 1.5 5.000 0 21-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14 -Block 4b 1 x 4 cells - 2.0 x 1.5 17.600 0 3-Jul-14 10-Sep-14 12-Sep-14 18-Oct-14 19-Oct-14 18-Oct-14 19-Oct-14Block 5 1 x 4 cells - 2.0 x 1.5 22.600 0 3-Jul-14 23-Sep-14 24-Sep-14 24-Oct-14 25-Oct-14 24-Oct-14 25-Oct-14 -Block 6 1 x 4 cells - 2.0 x 1.5 11.970 0 - - - - - - - -

    4 21+972.4 11 x 4 cells (44) - 3.0 x 2.0 57.629 0 - - - - - - - -Block 1 1 x 4 cells - 3.0 x 2.0 28.038 0 24-May-14 5-Jun-14 5-Jun-14 24-Jun-14 24-Jun-14 15-Jul-14 16-Jul-14 16-Aug-14Block 2 1 x 4 cells - 3.0 x 2.0 28.031 0 24-May-14 9-Jul-14 10-Jul-14 3-Aug-14 4-Aug-14 13-Aug-14 14-Aug-14 8-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 28.026 0 17-May-14 25-May-14 25-May-14 3-Jun-14 3-Jun-14 23-Jun-14 23-Jun-14 8-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 28.022 0 18-May-14 12-Jul-14 13-Jul-14 5-Aug-14 6-Aug-14 18-Aug-14 19-Aug-14 1-Oct-14Block 5 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 29-May-14 29-May-14 8-Jun-14 8-Jun-14 2-Jul-14 2-Jul-14 1-Oct-14Block 6 1 x 4 cells - 3.0 x 2.0 28.018 0 18-May-14 31-Jul-14 31-Jul-14 12-Aug-14 13-Aug-14 27-Aug-14 28-Aug-14 1-Oct-14Block 7 1 x 4 cells - 3.0 x 2.0 28.019 0 18-May-14 10-Jun-14 10-Jun-14 1-Jul-14 1-Jul-14 23-Jul-14 24-Jul-14 5-Oct-14Block 8 1 x 4 cells - 3.0 x 2.0 28.022 0 26-May-14 9-Aug-14 10-Aug-14 25-Aug-14 26-Aug-14 9-Sep-14 10-Sep-14 -Block 9 1 x 4 cells - 3.0 x 2.0 28.026 0 26-May-14 15-Jun-14 15-Jun-14 7-Jul-14 8-Jul-14 4-Aug-14 5-Aug-14 -

    Block 10 1 x 4 cells - 3.0 x 2.0 28.031 0 28-May-14 17-Aug-14 18-Aug-14 14-Sep-14 14-Sep-14 24-Sep-14 25-Sep-14 -Block 11 1 x 4 cells - 3.0 x 2.0 28.038 0 28-May-14 19-Jun-14 19-Jun-14 20-Jul-14 20-Jul-14 2-Sep-14 3-Sep-14 25-Sep-14Block 12 1 x 4 cells - 3.0 x 2.0 21.015 0 10-Aug-14 25-Aug-14 26-Aug-14 2-Sep-14 3-Sep-14 1-Oct-14 1-Oct-14 -Block 13 1 x 4 cells - 3.0 x 2.0 21.010 0 27-Jul-14 22-Sep-14 22-Sep-14 29-Sep-14 29-Sep-14 18-Oct-14 19-Oct-14 -Block 14 1 x 4 cells - 3.0 x 2.0 21.006 0 27-Jul-14 12-Oct-14 12-Oct-14 15-Oct-14 15-Oct-14 26-Oct-14 27-Oct-14 -Block 15 1 x 4 cells - 3.0 x 2.0 21.003 0 25-Jul-14 23-Aug-14 23-Aug-14 8-Sep-14 8-Sep-14 18-Sep-14 19-Sep-14 -Block 16 1 x 4 cells - 3.0 x 2.0 21.001 0 16-Jun-14 27-Jul-14 27-Jul-14 14-Aug-14 14-Aug-14 3-Sep-14 4-Sep-14 -Block 17 1 x 4 cells - 3.0 x 2.0 21.000 0 16-Jun-14 14-Sep-14 15-Sep-14 23-Sep-14 24-Sep-14 14-Oct-14 15-Oct-14 -Block 18 1 x 4 cells - 3.0 x 2.0 21.001 0 12-Jun-14 24-Oct-14 24-Oct-14 30-Oct-14 31-Oct-14 7-Nov-14 7-Nov-14 -Block 19 1 x 4 cells - 3.0 x 2.0 21.003 0 12-Jun-14 16-Oct-14 17-Oct-14 21-Oct-14 21-Oct-14 30-Oct-14 30-Oct-14 -Block 20 1 x 4 cells - 3.0 x 2.0 21.006 0 8-Jun-14 29-Sep-14 30-Sep-14 1-Oct-14 1-Oct-14 21-Oct-14 21-Oct-14 -Block 21 1 x 4 cells - 3.0 x 2.0 21.010 0 8-Jun-14 1-Sep-14 2-Sep-14 21-Sep-14 21-Sep-14 30-Sep-14 30-Sep-14 -Block 22 1 x 4 cells - 3.0 x 2.0 21.015 0 8-Jun-14 25-Jun-14 25-Jun-14 30-Jul-14 30-Jul-14 16-Sep-14 17-Sep-14 25-Sep-14

    TOP SLAB Bituminous Paint (2 Coats)

    LENGTH (m) SKEW ( )F/P &

    BLINDING

    LHS

    RHS

    TYPE & DIMENSIONSTATIONBASE SLAB WALL

    NO.

    RHS

    RHS

    LHS

    LHS

    RHS

    LHS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS

    Rebars Concrete Rebars Concrete Rebars Concrete

    Block 23 1 x 4 cells - 3.0 x 2.0 6.635 0 - - - - - - - -Block 24 1 x 4 cells - 3.0 x 2.0 6.782 0 - - - - - - - -Block 25 1 x 4 cells - 3.0 x 2.0 6.819 0 - - - - - - - -Block 26 1 x 4 cells - 3.0 x 2.0 7.217 0 - - - - - - - -Block 27 1 x 4 cells - 3.0 x 2.0 7.975 0 - - - - - - - -Block 28 1 x 4 cells - 3.0 x 2.0 8.571 0 - - - - - - - -Block 29 1 x 4 cells - 3.0 x 2.0 9.267 0 - - - - - - - -Block 30 1 x 4 cells - 3.0 x 2.0 9.949 0 - - - - - - - -Block 31 1 x 4 cells - 3.0 x 2.0 10.260 0 - - - - - - - -Block 32 1 x 4 cells - 3.0 x 2.0 10.262 0 - - - - - - - -Block 33 1 x 4 cells - 3.0 x 2.0 10.265 0 - - - - - - - -

    5 22+655 2 x 4 cells (8) - 2.0 x 2.0 95.482 45 R - - - - - - - -(9 cells) 1 cell - 2.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells - 2.0 x 2.0 9.675 45 R 24-Nov-14 29-Nov-14 29-Nov-14 - - - - -Block 2 1 x 4 cells - 2.0 x 2.0 32.711 45 R 30-Jun-14 6-Aug-14 7-Aug-14 1-Sep-14 2-Sep-14 1-Sep-14 2-Sep-14 13-Oct-14Block 3 1 x 4 cells - 2.0 x 2.0 32.711 45 R 24-Jun-14 21-Jul-14 21-Jul-14 17-Aug-14 18-Aug-14 17-Aug-14 18-Aug-14 13-Oct-14Block 4 1 x 4 cells - 2.0 x 2.0 11.850 45 R 11-Sep-14 12-Oct-14 13-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 22-Oct-14 -

    Block 4a 1 x 4 cells - 2.0 x 2.0 13.130 45 R - - - - - - - -Block 5 1 x 4 cells - 2.0 x 2.0 19.035 45 R 24-Nov-14 - - - - - - -Block 6 1 x 4 cells - 2.0 x 2.0 32.711 45 R 29-Jun-14 27-Jul-14 28-Jul-14 13-Sep-14 14-Sep-14 13-Sep-14 14-Sep-14 13-Oct-14Block 7 1 x 4 cells - 2.0 x 2.0 32.711 45 R 24-Jun-14 28-Aug-14 28-Aug-14 24-Sep-14 26-Sep-14 24-Sep-14 26-Sep-14 13-Oct-14Block 8 1 x 4 cells - 2.0 x 2.0 10.95 45 R - - - - - - - -Block 9 1 cell - 2.0 x 2.0 25.03 45 R 24-Nov-14 - - - - - - -

    Block 10 1 cell - 2.0 x 2.0 32.711 45 R 28-Jun-14 20-Aug-14 23-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 11 1 cell - 2.0 x 2.0 32.711 45 R 29-Jun-14 3-Aug-14 4-Aug-14 2-Oct-14 3-Oct-14 2-Oct-14 3-Oct-14 13-Oct-14Block 12 1 cell - 2.0 x 2.0 4.960 45 R - - - - - - - -

    6 23+492 1 x 4 cells (4) - 3.0 x 2.0 79.065 15 R - - - - - - - -(5 cells) 1 cell - 3.0 x 2.0 - - - - - - - -Block 1 1 x 4 cells - 3.0 x 2.0 6.457 15 R - - - - - - - -Block 2 1 x 4 cells - 3.0 x 2.0 31.546 15 R 24-Jun-14 9-Jul-14 9-Jul-14 30-Jul-14 30-Jul-14 16-Aug-14 17-Aug-14 6-Sep-14Block 3 1 x 4 cells - 3.0 x 2.0 31.546 15 R 24-Jun-14 14-Jul-14 15-Jul-14 3-Aug-14 3-Aug-14 21-Aug-14 21-Aug-14 6-Sep-14Block 4 1 x 4 cells - 3.0 x 2.0 7.982 15 R 9/172014 23-Sep-14 24-Sep-14 28-Sep-14 28-Sep-14 1-Oct-14 2-Oct-14 18-Oct-14Block 5 1 cell - 3.0 x 2.0 7.039 15 R - - - - - - - -Block 6 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 5-Aug-14 5-Aug-14 9 & 20/8/2014 9 & 23/8/2014 28-Aug-14 28-Aug-14 4-7/9/2014Block 7 1 cell - 3.0 x 2.0 31.546 15 R 24-Jun-14 6-Aug-14 6-Aug-14 11 & 25/8/2014 11 & 26/8/2014 31-Aug-14 1-Sep-14 4-7/9/2014Block 8 1 cell - 3.0 x 2.0 5.525 15 R 17-Sep-14 28-Sep-14 28-Sep-14 2-Oct-14 2-Oct-14 11-Oct-14 11-Oct-14 18-Oct-14

    11-Oct-14 11-Oct-14 - - -

    BASE SLAB WALL TOP SLAB Bituminous Paint (2 Coats)

    LHS

    LHS

    STATION TYPE & DIMENSION LENGTH (m) SKEW ( )F/P &

    BLINDING

    RHS

    LHS

    RHS

    NO.

    LHS

    RHS

    RHS

    LHS

    RHS

    RHS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS

    Rebars Concrete Rebars Concrete Rebars Concrete

    7 23+756.5 1 cell - 2.0 x 1.5 67.550 0 - - - - - - - -Block 1 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -Block 2 1 cell - 2.0 x 1.5 20.180 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14

    Block 3a 1 cell - 2.0 x 1.5 14.430 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 8.700 0 11-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 28-Aug-14Block 4 1 cell - 2.0 x 1.5 12.090 0 - - - - - - - -

    8 23+997 1 cell - 2.0 x 1.5 70.268 0 - - - - - - - -Block 1 1 cell - 2.0 x 1.5 16.128 0 - - - - - - - -

    Block 2a 1 cell - 2.0 x 1.5 4.933 0 - - - - - - - -Block 2b 1 cell - 2.0 x 1.5 13.860 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3a 1 cell - 2.0 x 1.5 16.300 0 8-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 3b 1 cell - 2.0 x 1.5 4.942 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4a 1 cell - 2.0 x 1.5 7.848 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 4b 1 cell - 2.0 x 1.5 6.197 0

    9 24+235 1 cell - 2.0 x 1.5 59.106 0 - - - - - - - -Block 1a 1 cell - 2.0 x 1.5 15.566 0 - - - - - - - -Block 1b 1 cell - 2.0 x 1.5 15.000 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2a 1 cell - 2.0 x 1.5 8.900 0 12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14Block 2b 1 cell - 2.0 x 1.5 15.600 0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14Block 2c 1 cell - 2.0 x 1.5 4.020 0 - - - - - - - -

    10 24+570 1 cell - 2.0 x 1.5 51.953 0 - - - - - - - -LHS Block 1 1 cell - 2.0 x 1.5 25.846 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14

    Block 2a 1 cell - 2.0 x 1.5 13.500 0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14Block 2b 1 cell - 2.0 x 1.5 12.587 0 24-Nov-14 - - - - - - -

    Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m

    PREVIOUS PREVIOUS MONTH THIS MONTH

    RHS

    WALL TOP SLAB Bituminous Paint (2 Coats)

    LHS

    RHS

    F/P &

    BLINDING

    BASE SLAB

    LHS

    NO. STATION TYPE & DIMENSION LENGTH (m) SKEW ( )

    LHS

    RHS

    RHS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS

    Rebars Concrete Rebars Concrete Rebars Concrete

    1 21+300 2 cells - 4.0 x 3.0 37.700 0 - - - - - - - -LHS Block 1 2 cells - 4.0 x 3.0 15.780 0 19-Oct-14 26-Oct-14 27-Oct-14 1-Nov-14 2-Nov-14 12-Nov-14 2-Nov-14 -RHS Block 2 2 cells - 4.0 x 3.0 21.900 0 - - - - - - - -

    2 24+600 2 cells - 4.0 x 3.0 44.051 0 - - - - - - - -LHS Block 1 2 cells - 4.0 x 3.0 21.620 0 22-Oct-14 3-Nov-14 3-Nov-14 11-Nov-14 12-Nov-14 19-Nov-14 20-Nov-14 -RHS Block 2 2 cells - 4.0 x 3.0 22.411 0 - - - - - - - -

    Rebars Concrete Rebars Concrete Rebars Concrete

    1 23+284.40, SOL-1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 - 0 - - - - - - - -RHS Block 2 1 cells - 4.0 x 4.0 - 0 - - - - - - - -

    2 24+360, SOL-1 1 cells - 4.0 x 4.0 59.614 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 9.000 0 - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 20.777 0 15-Sep-14 1-Oct-14 1-Oct-14 19-Oct-14 19-Oct-14 30-Oct-14 31-Oct-14 -RHS Block 3 1 cells - 4.0 x 4.0 22.777 0 - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0 7.000 0 - - - - - - - -

    3 0+050, SOL-3 1 cells - 4.0 x 4.0 83.223 0 - - - - - - - -LHS Block 1 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 2 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -LHS Block 3 1 cells - 4.0 x 4.0 17.721 0 - - - - - - - -RHS Block 4 1 cells - 4.0 x 4.0 30.000 0 11/55/2014 - - - - - - -

    PREVIOUSPREVIOUS

    MONTHTHIS MONTH

    WALLNO.

    LENGTH (m) SKEW ( )F/P &

    BLINDINGTYPE & DIMENSION

    PEDESTRIAN UNDERPASS PROGRESS SCHEDULE (BARREL)

    TYPE & DIMENSION LENGTH (m) SKEW ( )TOP SLAB Bituminous

    Paint (2 Coats)STATION

    STATIONBASE SLAB WALL

    F/P &

    BLINDING

    BASE SLAB

    NO.

    VEHICLE UNDERPASS PROGRESS SCHEDULE (BARREL)

    TOP SLAB Bituminous Paint (2 Coats)

  • 11. Progress Status of Utility Crossing Ducts

    NO. OF

    DIA TYPE WAYS LAY CONCRETE BACKFILL

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 9/24/14 9/24/14 10/18/14 UTL-LAY- 104 UTL-CON-131A

    MIDDLE

    RIGHT

    LEFT 5/15/14 5/15/14 5/18/14 6/12/14 UTL-LAY- 81 UTL-CON- 65 UTL-BF- 01

    MIDDLE 6/11/14 6/11/14 6/12/14 7/10/14 UTL-LAY- 104 UTL-CON- 83 UTL-BF- 20

    RIGHT

    LEFT 5/19/14 5/19/14 5/20/14 6/4/14 UTL-LAY- 87 UTL-CON- 66 UTL-BF- 03

    MIDDLE 6/14/14 14/06/014 6/14/14 6/21/14 UTL-LAY- 108 UTL-CON- 84 UTL-BF- 21

    RIGHT

    LEFT 5/19/14 5/19/14 5/20/14 5/31/14 UTL-LAY- 85 UTL-CON- 63 UTL-BF- 02

    MIDDLE 6/15/14 6/15/14 6/15/14 UTL-LAY- 107 UTL-CON- 85

    RIGHT

    LEFT 5/20/14 5/20/14 5/25/14 6/4/14 UTL-LAY- 86 UTL-CON- 64 UTL-BF- 05

    MIDDLE 6/15/14 6/15/14 6/15/14 7/8/14 UTL-LAY- 109 UTL-CON- 87 UTL-BF- 23

    RIGHT

    LEFT 5/25/14 5/25/14 5/25/14 6/4/14 UTL-LAY- 90 UTL-CON-68 UTL-BF- 07

    MIDDLE 6/16/14 6/16/14 6/17/14 7/10/14 UTL-LAY- 111 UTL-CON- 88 UTL-BF- 28

    RIGHT

    LEFT 6/17/14 6/17/14 6/18/14 7/9/14 UTL-LAY- 112 UTL-CON- 89 UTL-BF- 33

    MIDDLE 7/20/14 7/20/14 7/21/14 7/27/14 UTL-LAY- 131 UTL-CON- 106 UTL-BF-44

    RIGHT

    LEFT 6/19/14 6/19/14 6/19/14 7/6/14 UTL-LAY- 114 UTL-CON- 92 UTL-BF- 31

    MIDDLE 7/20/14 7/20/14 7/21/14 7/17/14 UTL-LAY- 132 UTL-CON- 107 UTL-BF-46

    RIGHT

    LEFT 6/19/14 6/19/14 6/19/14 7/5/14 UTL-LAY- 113 UTL-CON- 91 UTL-BF- 30

    MIDDLE 7/20/14 7/20/14 7/21/14 7/17/14 UTL-LAY- 133 UTL-CON- 108 UTL-BF-45

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 5/26/14 5/26/14 5/26/14 6/8/14 UTL-LAY- 88 UTL-CON- 69 UTL-BF- 08

    MIDDLE 6/11/14 6/11/14 6/11/14 7/22/14 UTL-LAY-106 UTL-CON- 81 UTL-BF-26

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 6/16/14 6/16/14 6/16/14 7/20/14 UTL-LAY- 102 UTL-CON- UTL-BF-19

    MIDDLE 7/8/14 7/8/14 7/9/14 7/27/14 UTL-LAY- 125 UTL-CON-99 UTL-BF-42

    RIGHT

    LEFT 5/25/14 5/25/14 5/26/14 6/14/14 UTL-LAY- 91 UTL-CON- 71 UTL-BF- 06

    MIDDLE 11/06/201 6/11/14 6/11/14 6/23/14 UTL-LAY- 105 UTL-CON- 82 UTL-BF- 25

    RIGHT

    LEFT 5/27/14 5/27/14 5/27/14 6/17/14 UTL-LAY- 92 UTL-CON- 72 UTL-BF- 09

    MIDDLE

    RIGHT

    LEFT 5/28/14 5/28/14 5/28/14 6/17/14 UTL-LAY- 93 UTL-CON- 70 UTL-BF- 10

    MIDDLE

    RIGHT

    LEFT 5/29/14 5/29/14 5/29/14 6/17/14 UTL-LAY- 94 UTL-CON- 73 UTL-BF- 11

    MIDDLE 7/30/14 8/12/14 7/30/14 8/26/14 UTL-LAY-142 UTL-CON- 115 UTL-BF-48

    RIGHT

    LEFT 5/29/14 6/2/14 6/2/14 6/17/14 UTL-LAY- 95 UTL-CON- 75 UTL-BF- 15

    MIDDLE 7/14/14 7/14/14 7/14/14 8/20/14 UTL-LAY- 124 UTL-CON- 102 UTL-BF- 36

    RIGHT

    LEFT 5/29/14 6/2/14 6/2/14 6/17/14 UTL-LAY-97 UTL-CON- 76 UTL-BF- 13

    MIDDLE 7/14/14 7/14/14 7/15/14 8/20/14 UTL-LAY- 127 UTL-CON- 101 UTL-BF- 38

    RIGHT

    LEFT

    MIDDLE 8/10/14 8/11/14 8/11/14 8/26/14 UTL-LAY-149A UTL-CON- 120A UTL-BF- 58

    RIGHT 10/27/14 10/27/14 10/27/14 UTL-LAY- 206 UTL-CON- 153

    3

    2

    3

    3

    3

    2

    2

    2

    3

    1

    1

    3

    4

    3

    4

    3

    1

    23+820

    23+900

    200

    200

    200

    150

    300

    900

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    UPVC

    150

    150

    RC

    UPVC

    UPVC20 CCC/FQI/EL/13

    CCC/FQI/EL/0821

    CCC/FQI/EL/0922

    UPVC

    UPVC

    UPVC

    RC

    23+060

    23+210

    23+240

    23+560

    CCC/FQI/EL/1023

    CCC/FQI/WA/0324

    150

    150

    150

    150

    600

    BACKFILLI

    NG

    RFI REF.S.

    NO.CHAINAGE

    PIPE

    2

    2UPVC

    INSTALLA

    TION

    CONCRET

    E

    1CCC/FQI/IR/06

    SERVICE ROAD-30+030 200 UPVC

    2CCC/FQR/IR/11 SOL-

    20+150 300

    SETOUT/EX

    CV/BED

    PREP

    STAGESDRAWING No.

    2

    3

    2

    4CCC/FQR/WA/05

    SR-10+600 300 UPVC

    6 CCC/FQI/EL/01

    10 CCC/FQI/EL/03 21+880

    CCC/FQI/EL/04 22+260

    12

    2

    300 UPVC

    8 CCC/FQI/EL/02 21+660

    11

    150

    7 CCC/FQI/IR/01 21+460

    UPVC

    9 CCC/FQI/IR/02 21+780 300

    CCC/FQI/EL/05 22+510 150

    15

    CCC/FQI/IR/05

    JUNCTION

    CROSSING

    22+587 LHS

    13 CCC/FQI/IR/03

    21+360 150 UPVC

    25 CCC/FQI/SL/11 23+960 150 UPVC

    19 CCC/FQI/EL/07

    16 CCC/FQI/EL/06

    22+520

    14

    CCC/FQI/IR/04

    JUNCTION

    CROSSING

    22+520 LHS

    CCC/FQI/WA/01

    CCC/FQI/WA/02

    JUNCTION17

    18

    23+008 LHS

    23+020

    22+760

    150

    23CCC/FQR/IR/10 SOL-

    30+300 200 UPVC

    CCC/FQI/SL/01 21+160 150 UPVC 45

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 20

    NO. OF

    DIA TYPE WAYS LAY CONCRETE BACKFILL

    LEFT 5/29/14 6/2/14 6/3/14 6/19/14 UTL-LAY- 98 UTL-CON- 77 UTL-BF- 14

    MIDDLE 8/6/14 8/6/14 8/9/14 8/13/14 UTL-LAY- 134-R1 UTL-CON- 109A UTL-BF- 53

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 6/3/14 6/4/14 6/4/14 6/23/14 UTL-LAY- 99 UTL-CON- 78 UTL-BF- 16

    MIDDLE 8/11/14 8/11/14 8/19/14 8/26/14 UTL-LAY-140 R1 UTL-CON-114 UTL-BF- 52

    RIGHT

    LEFT 6/4/14 6/5/14 6/10/14 23/06/201 UTL-LAY- 100 UTL-CON- 79 UTL-BF- 17

    MIDDLE 7/23/14 7/24/14 8/19/14 8/26/14 UTL-LAY-139 UTL-CON-112-R1UTL-BF- 47

    RIGHT

    LEFT 6/9/14 6/9/14 6/10/14 6/23/14 UTL-LAY- 101 UTL-CON- 80 UTL-BF- 18

    MIDDLE 8/6/14 8/6/14 8/6/14 8/26/14 UTL-LAY-138-R1 UTL-CON-111-B UTL-BF- 56

    RIGHT

    LEFT 7/5/14 7/5/14 7/5/14 8/19/14 UTL-LAY- 123 UTL-CON- 94 UTL-BF- 39R1

    MIDDLE

    RIGHT

    LEFT 7/16/14 7/16/14 7/17/14 11/6/14 UTL-LAY- 130 UTL-CON- 105 UTL-BF- 41R1

    MIDDLE 10/27/14 10/27/14 10/27/14 10/27/14 UTL-LAY-190R1 UTL-CON- 148 UTL-BF- 72

    RIGHT

    LEFT 9/14/14 9/14/14 10/14/14 10/20/14 UTL-LAY- 166 UTL-CON-125 UTL-BF-81

    MIDDLE 10/27/14 10/30/14 10/27/14 UTL-LAY- 205 UTL-CON- 150

    RIGHT

    LEFT 9/16/14 9/20/14 UTL-LAY- 173

    MIDDLE 10/27/14 10/27/14 10/27/14 11/9/14 UTL-LAY- 203 UTL-CON- 149 UTL-BF-100

    RIGHT

    LEFT 11/3/14 11/10/14 11/4/14 11/26/14 UTL-LAY- 211 UTL-CON- 155 UTL-BF-106

    MIDDLE

    RIGHT

    LEFT 5/21/14 5/21/14 5/21/14 6/4/14 UTL-LAY- 89 UTL-CON- 67 UTL-BF- 04

    MIDDLE 6/16/14 6/16/14 6/18/14 7/10/14 UTL-LAY- 110 UTL-CON- 90 UTL-BF- 29

    RIGHT

    LEFT 5/29/14 5/31/14 5/31/14 6/17/14 UTL-LAY- 96 UTL-CON- 74 UTL-BF- 12

    MIDDLE 7/10/14 7/10/14 8/13/14 8/26/14 UTL-LAY- 120 R1 UTL-CON- 95 UTL-BF- 49

    RIGHT

    LEFT 7/21/14 8/4/14 8/5/14 UTL-LAY-137-R1 UTL-CON- 118

    MIDDLE 8/8/14 8/9/14 8/9/14 9/22/14 UTL-LAY-148A UTL-CON- 117 UTL-BF- 57

    RIGHT 9/16/14 9/16/14 9/16/14 UTL-LAY-172 UTL-CON- 126

    LEFT 7/7/14 7/8/14 7/8/14 UTL-LAY-103A UTL-CON-98

    MIDDLE 8/12/14 8/13/14 8/14/14 8/15/14 UTL-LAY-150 UTL-CON-122A UTL-BF- 37A

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 7/9/14 7/9/14 7/9/14 UTL-LAY- 116 UTL-CON-100

    MIDDLE 8/12/14 8/13/14 8/14/14 9/25/14 UTL-LAY-151 UTL-CON-121 UTL-BF-81

    RIGHT 10/12/14 10/13/14 10/12/14 11/8/14 UTL-LAY-187 UTL-CON-137 UTL-BF-99

    LEFT 7/2/14 7/3/14 7/3/14 UTL-LAY-122 UTL-CON-93R1

    MIDDLE 7/10/14 7/10/14 7/14/14 UTL-LAY-126 UTL-CON-103

    RIGHT 7/22/14 7/22/14 7/23/14 8/20/14 UTL-LAY-136 UTL-CON-110 UTL-BF- 50

    LEFT 8/30/14 8/31/14 9/14/14 9/30/14 UTL-LAY-158 UTL-CON-96 UTL-BF-64

    MIDDLE 11/27/14 11/27/14 11/29/14 UTL-EXC-63 UTL-CON-162 UTL-BF-115

    RIGHT

    LEFT 9/7/14 9/7/14 10/14/14 10/27/14 UTL-LAY-162 UTL-CON-124 UTL-BF-69

    MIDDLE 9/15/14 9/15/14 11/4/14 UTL-LAY-162R1 UTL-BF-94

    RIGHT 10/27/14 10/28/14 11/17/14 11/17/14 UTL-LAY-207 UTL-CON-152 UTL-BF-92

    LEFT 9/16/14 9/17/14 9/30/14 11/8/14 UTL-LAY-174 UTL-CON-127 UTL-BF-83R1

    MIDDLE 10/14/14 10/18/14 10/14/14 UTL-LAY-188 UTL-CON-138

    RIGHT 10/27/14 10/27/14 10/27/14 UTL-LAY-204 UTL-CON-151

    LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-184 UTL-CON-135

    MIDDLE

    RIGHT

    LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-164 R1 UTL-CON-134

    MIDDLE

    RIGHT

    LEFT 10/2/14 10/2/14 10/2/14 UTL-LAY-185 UTL-CON-136

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 11/4/14 UTL-EXC-55

    MIDDLE

    RIGHT

    UPVC 2-4WAY150CCC/FQI/SL/01

    21+620 450

    24+220

    24+340

    24+520

    UPVC

    UPVC

    45

    46

    47

    450

    CON

    C PI

    PE

    50

    CCC/FQI/SD 23+400 60049

    CON

    C PI

    PE

    4

    3

    2

    3

    2

    3

    2

    UPVC150

    23+980

    24+000

    24+020

    24+120

    23+740 150

    UPVC

    UPVC

    UPVC

    150

    UPVC

    39CCC/FQI/OMANTEL

    .1

    35

    CCC/FQI/OMANTEL

    .2100

    150

    40 0+140 SOL-3

    22+810 100

    100

    21+870

    23+580

    24+720

    150

    100

    100

    15042 22+990

    UPVC300

    150

    300

    CCC/FQI/WA/0427

    CCC/FQI/IR/0728

    36

    37

    38

    CCC/FQI/EL/14

    CCC/FQI/IR/08

    CCC/FQI/EL/15

    CCC/FQI/EL/16

    CCC/FQI/IR/09

    CCC/FQI/EL/17

    CCC/FQI/NAW.2

    CCC/FQI/NAW.3

    CCC/FQI/NAW.4

    CCC/FQI/EL/1229

    S.

    NO.DRAWING No. CHAINAGE

    PIPE

    26 CCC/FQI/EL/11 UPVC

    24+820

    24+960

    25+160

    30

    31

    32

    33

    34

    2

    3

    1

    2

    600

    300

    150

    150

    3

    3

    RC

    UPVC

    UPVC

    UPVC

    2

    4

    22+080

    UPVC 2

    CCC/FQI/SD/07

    CCC/FQI/SD/08

    UPVC

    UPVC

    UPVC

    CCC/FQI/EL/21 23+965 200 UPVC 2

    24+850

    450

    CON

    C PI

    PECO

    NC

    PIPE

    CCC/FQI/SL/04 UPVC 4

    41CCC/FQI/SL/03 Rev

    A22+820 150 UPVC 4

    CCC/FQI/SL/02 4

    21+500

    21+560

    44 CCC/FQI/EL/19

    48 CCC/FQI/SD/09

    STAGES

    SETOUT/EX

    CV/BED

    PREP

    INSTALLA

    TION

    CONCRET

    E

    BACKFILLI

    NG

    RFI REF.

    43

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 21

    LEFT 9/4/14 9/28/14 UTL-LAY-159-B UTL-CON-132

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT 9/16/14 9/17/14 9/30/14 10/18/14 UTL-LAY-167 UTL-CON-128 UTL-BF-78

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    LEFT

    MIDDLE

    RIGHT

    3 CCC/FQI/SL/08

    1 CCC/FQI/SL/23 0+020 150 UPVC 6

    2 CCC/FQI/SL/24 0+120 2

    UPVC 4

    3

    2ACCC/FQI/Omantel/

    024UPVC

    SERVICE ROAD-02

    1 1+050 150 UPVC 2

    CCC/FQI/SL/12 1+530 150 UPVC 2

    1

    0+060 4

    3 CCC/FQI/SL/08 0+600 100 UPVC 4

    2

    6

    CCC/FQI/SL/14

    CCC/FQI/SL/15

    CCC/FQI/SL/16

    CCC/FQI/SL/17

    0+415 1503

    4

    2 CCC/FQI/SL/13 UPVC 2

    BURAIMI ROAD (SOL - 03)

    SERVICE ROAD-03

    2

    0+472.8

    CCC/FQI/SL/06 UPVC150

    CCC/FQI/OMANTEL

    /04

    5CCC/FQI/OMANTEL

    /05100 UPVC 4

    6CCC/FQI/OMANTEL

    /060+648.103 100 UPVC

    4

    CCC/FQI/SL/10

    0+550

    100 UPVC 4

    2

    5

    UPVC 2

    UPVC 6

    Existing

    Road front

    SOL-3 Ch.

    150 UPVC 2

    0+054.459 150

    0+140 150

    1CCC/FQI/Omantel/

    02

    4

    SERVICE ROAD-01

    CCC/FQI/SL/07 0+530 150 UPVC

    UPVC 2

    Existing

    Road front

    SOL-3 Ch.

    150

    0+130 150

    0+138.348 110

  • 12. Project Progress Strip Chart

  • SUBGRADE IN CUT COMPLETED 21+150-21+500 As of November 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmSubgrade Layr 9Layr 8Layr 7Layr 6Layr 5Layr 4Layr 3Layr 2

    EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY

    21+0

    00

    21+0

    20

    21+0

    40

    21+0

    60

    21+0

    80

    21+1

    00

    21+1

    20

    21+1

    40

    21+1

    60

    21+1

    80

    21+2

    00

    21+2

    20

    21+2

    40

    21+2

    60

    21+2

    80

    21+3

    00

    21+3

    20

    21+3

    40

    21+3

    60

    21+3

    80

    21+4

    00

    21+4

    20

    21+4

    40

    21+4

    60

    21+4

    80

    21+5

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9Subgrade

    GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    21+500-22+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmsub gradeLayer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2

    EMBANKMENT Layer 1BED PREPRATION OGL SURVEY

    21+5

    00

    21+5

    20

    21+5

    40

    21+5

    60

    21+5

    80

    21+6

    00

    21+6

    20

    21+6

    40

    21+6

    60

    21+6

    80

    21+7

    00

    21+7

    20

    21+7

    40

    21+7

    60

    21+7

    80

    21+8

    00

    21+8

    20

    21+8

    40

    21+8

    60

    21+8

    80

    21+9

    00

    21+9

    20

    21+9

    40

    21+9

    60

    21+9

    80

    22+0

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9sub grade

    GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    RH

    S

    PROGRESS STRIP CHART FOR ROAD WORKS

    LHS

    RH

    SLH

    S

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 24

    COMPLETED 22+000-22+500 As of November 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayr 10 SUB GRADE LAYER Layr 9Layr 8Layr 7Layr 6Layr 5Layr 4Layr 3Layr 2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY

    22+0

    00

    22+0

    20

    22+0

    40

    22+0

    60

    22+0

    80

    22+1

    00

    22+1

    20

    22+1

    40

    22+1

    60

    22+1

    80

    22+2

    00

    22+2

    20

    22+2

    40

    22+2

    60

    22+2

    80

    22+3

    00

    22+3

    20

    22+3

    40

    22+3

    60

    22+3

    80

    22+4

    00

    22+4

    20

    22+4

    40

    22+4

    60

    22+4

    80

    22+5

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10 SUBGRADEGSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    22+500-23+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7 5th layer of rock soil Layer 6 layer 15Layer 5Layer 4 4th layer roock soil Layer 3Layer 2EMBANKMENT Layer 1BED PREPRATION OGL SURVEY

    22+5

    00

    22+5

    20

    22+5

    40

    22+5

    60

    22+5

    80

    22+6

    00

    22+6

    20

    22+6

    40

    22+6

    60

    22+6

    80

    22+7

    00

    22+7

    20

    22+7

    40

    22+7

    60

    22+7

    80

    22+8

    00

    22+8

    20

    22+8

    40

    22+8

    60

    22+8

    80

    22+9

    00

    22+9

    20

    22+9

    40

    22+9

    60

    22+9

    80

    23+0

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4 4th layer roock soil layer 5layer 6 layer 15layer 7 5th layer of rock soil layer 8layer 9layer 10 SUB GGSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    LHS

    RH

    SLH

    SR

    HS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 25

    COMPLETED 23+000-23+500 As of November 2014BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayr 10 rock siol layer no 3Layr 9 5th layer of rock soil layer no 28Layr 8 layer 15 of embankmentLayr 7Layr 6Layr 5Layr 4Layr 3Layr 2EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY

    23+0

    00

    23+0

    20

    23+0

    40

    23+0

    60

    23+0

    80

    23+1

    00

    23+1

    20

    23+1

    40

    23+1

    60

    23+1

    80

    23+2

    00

    23+2

    20

    23+2

    40

    23+2

    60

    23+2

    80

    23+3

    00

    23+3

    20

    23+3

    40

    23+3

    60

    23+3

    80

    23+4

    00

    23+4

    20

    23+4

    40

    23+4

    60

    23+4

    80

    23+5

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6 layer 15 of embankmentlayer 7 5th layer of rock soil layer no 28layer 8 rock siol layer no 3layer 9layer 10GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    23+500-24+000BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4 4th layer of Rock siolLayer 3 3rd layer of Rock siolLayer 2 2nd layer of Rock siolEMBANKMENT Layer 1 1st layer of Rock siolBED PREPRATION OGL SURVEY

    23+5

    00

    23+5

    20

    23+5

    40

    23+5

    60

    23+5

    80

    23+6

    00

    23+6

    20

    23+6

    40

    23+6

    60

    23+6

    80

    23+7

    00

    23+7

    20

    23+7

    40

    23+7

    60

    23+7

    80

    23+8

    00

    23+8

    20

    23+8

    40

    23+8

    60

    23+8

    80

    23+9

    00

    23+9

    20

    23+9

    40

    23+9

    60

    23+9

    80

    24+0

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1 1st layer of rock siollayer 2 2nd layer of rock siollayer 3 3rd layer of rock siollayer 4 4th layer of rock siollayer 5layer 6layer 7layer 8layer 9layer 10GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    LHS

    RH

    SLH

    SR

    HS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 26

    COMPLETED 24+000-24+500 As of November 2014

    BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2

    EMBANKMENT Layer 1 BED PREPRATION OGL SURVEY

    24+0

    00

    24+0

    20

    24+0

    40

    24+0

    60

    24+0

    80

    24+1

    00

    24+1

    20

    24+1

    40

    24+1

    60

    24+1

    80

    24+2

    00

    24+2

    20

    24+2

    40

    24+2

    60

    24+2

    80

    24+3

    00

    24+3

    20

    24+3

    40

    24+3

    60

    24+3

    80

    24+4

    00

    24+4

    20

    24+4

    40

    24+4

    60

    24+4

    80

    24+5

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10

    GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    24+500-25+000

    BWC 6 cmTack Coat BBC 12 cmPRIME COAT ABC 2 ND 15 cmABC 1 ST 15 cmGSB 20 cmLayer 10Layer 9Layer 8Layer 7Layer 6Layer 5Layer 4Layer 3Layer 2

    EMBANKMENT Layer 1BED PREPRATION OGL SURVEY

    24+5

    00

    24+5

    20

    24+5

    40

    24+5

    60

    24+5

    80

    24+6

    00

    24+6

    20

    24+6

    40

    24+6

    60

    24+6

    80

    24+7

    00

    24+7

    20

    24+7

    40

    24+7

    60

    24+7

    80

    24+8

    00

    24+8

    20

    24+8

    40

    24+8

    60

    24+8

    80

    24+9

    00

    24+9

    20

    24+9

    40

    24+9

    60

    24+9

    80

    25+0

    00

    OGL SURVEY BED PREPRATION EMBANKMENT Layer 1layer 2layer 3layer 4layer 5layer 6layer 7layer 8layer 9layer 10

    GSB 20 cmABC 1 ST 15 cmABC 2 ND 15 cmPRIME COAT BBC 12 cmTack Coat BWC 6 cm

    LHS

    RH

    SLH

    SR

    HS

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 27

    COMPLETED 25+000-25+500 As of November 2014

    BWC 6 cm

    Tack Coat

    BBC 12 cm

    PRIME COAT

    ABC 2 ND 15 cm

    ABC 1 ST 15 cm

    GSB 20 cm

    Layr 10

    Layr 9

    Layr 8

    Layr 7

    Layr 6

    Layr 5

    Layr 4

    Layr 3

    Layr 2

    EMBANKMENT Layer 1

    BED PREPRATION

    OGL SURVEY

    25+0

    00

    25+0

    20

    25+0

    40

    25+0

    60

    25+0

    80

    25+1

    00

    25+1

    20

    25+1

    40

    25+1

    60

    25+1

    80

    25+2

    00

    25+2

    20

    25+2

    40

    25+2

    60

    25+2

    80

    25+3

    00

    25+3

    20

    25+3

    40

    25+3

    60

    25+3

    80

    25+4

    00

    25+4

    20

    25+4

    40

    25+4

    60

    25+4

    80

    25+5

    00

    OGL SURVEY

    BED PREPRATION

    EMBANKMENT Layer 1

    layer 2

    layer 3

    layer 4

    layer 5

    layer 6

    layer 7

    layer 8

    layer 9

    layer 10

    GSB 20 cm

    ABC 1 ST 15 cm

    ABC 2 ND 15 cm

    PRIME COAT

    BBC 12 cm

    Tack Coat

    BWC 6 cm

    LHS

    RH

    S

  • 13. Financial Status of Payments

    Sl. No. DESCRIPTIONPAYMENT FOR

    THE MONTH OF

    GROSS

    AMOUNT

    (R.O.)

    GROSS

    AMOUNT

    CLAIMED (R.O.)

    NET AMOUNT

    CLAIMED

    (R.O.)

    DATE

    SUBMITTED

    AMOUNT

    CERTIFIED (R.O.)DATE CERTIFIED

    AMOUNT

    RECEIVED

    (R.O.)

    DATE

    PAYMENT DUE

    DATE

    PAYMENT

    RECEIVED

    1PAYMENT APPLICATION No. 1

    (ADVANCE PAYMENT)Dec-13 1,648,225 1,648,225 1,648,225 23-Nov-13 1,648,225 29-Jan-14 1,648,225 6-Feb-14

    2 PAYMENT APPLICATION No. 2 Jan-14 2,291,277 643,052 514,442 12-Feb-14 514,442 02-Apr-14 513,608 10-Apr-14

    3 PAYMENT APPLICATION No. 3 Feb&Mar-14 2,808,644 517,367 504,147 06-Apr-14 434,917 03-May-14 414,674 6-Aug-14

    4 PAYMENT APPLICATION No. 4 Apr-14 3,315,692 507,048 417,900 08-May-14 407,538 05-Jun-14 395,257 6-Aug-14

    5 PAYMENT APPLICATION No. 5 May-14 4,109,460 793,768 650,802 05-Jun-14 445,708 04-Jul-14 374,172 6-Aug-14

    6 PAYMENT APPLICATION No. 6 Jun-14 4,293,764 184,304 382,116 15-Jul-14 382,116 16-Jul-14 418,721 9-Sep-14

    7 PAYMENT APPLICATION No. 7 Jul&Aug-14 5,749,546 1,455,782 1,164,626 14-Sep-14 1,123,023 18-Sep-14 1,123,023 19-Oct-14

    8 PAYMENT APPLICATION No. 8 Sep-14 6,857,752 1,108,206 928,167 21-Oct-14 928,805 06-Nov-14

    9 PAYMENT APPLICATION No. 9 Oct-14

    10 PAYMENT APPLICATION No. 10 Nov-14

    11 PAYMENT APPLICATION No. 11 Dec-14

    12 PAYMENT APPLICATION No. 12 Jan-15

    13 PAYMENT APPLICATION No. 13 Feb-15

    14 PAYMENT APPLICATION No. 14 Mar-15

    15 PAYMENT APPLICATION No. 15 Apr-15

    16 PAYMENT APPLICATION No. 16 May-15

    17 PAYMENT APPLICATION No. 17 Jun-15

    18 PAYMENT APPLICATION No. 18 Jul-15

    19 PAYMENT APPLICATION No. 19 Aug-15

    20 PAYMENT APPLICATION No. 20 Sep-15

    21 PAYMENT APPLICATION No. 21 Oct-15

    - 6,857,752 6,210,425 5,884,774 4,887,679 TOTAL AMOUNT (R.O.)

  • 14. Details of Equipment Available At Site

    Sl.

    No.CCC HIRED

    TOTAL

    AVAILABLE

    AT SITE

    1 COMPRESSOR

    2 AIR COMPRESSOR 2 1 3

    3 MILLER WELDING MECHINE 2 2

    4 GENERATOR 2 1 3

    5 CRANES -

    6 CRANES 30 TON / 25 TON / 70 TON 2 4 6

    7 VEHICLES H.D. -

    8 DIESEL TANKER -

    9 FLAT TRAILER 2 2

    10 HIAB TRUCK 2 2

    11 P/MOVER + TIPPING TRAILER 4 5 9

    12 TIPPER TRUCKS 11 4 15

    13 WATER TANKER 5000 & 10000 GAL 1 6 7

    14 EARTH MOVING PLANT

    15 BOBCAT 1 2 3

    16 EXCAVATOR 1 1

    17 JCB 4CX / 3CX 1 5 6

    18 SHOVEL / WHEEL LOADER 3 2 5

    19 DOZER D9N/D8R 2 2

    20 TELEHANDLER -

    21 CIVIL ENGINEERING EQUIPMENT

    22 GREENE STABILIZER PLANT 1 1

    23 DYNAPAC S/ROLLER -

    24 E/WORK ROLLER 1 3 4

    25 MOTOR GRADER 1 4 5

    26 TITAN PAVER MACHINE -

    27 TYRE / PTR ROLLER -

    28 PAVER MACHINE -

    29 L. D. VEHICLES & TRUCKS

    30 DYNA TRUCK 1 2 3

    31 MAINTENANCE TRUCKS 1 1

    32 ASHOK LEYLAND BUS 55 SEAT 5 5

    33 TOYOTA COASTER BUS 24 S 1 1

    34 TOYOTA COROLLA/CIVIC/YARIS 12 12

    35 TOYOTA PICKUP/ISUZU 5 8 13

    36 NISSAN PATHFINDER/X-TRAIL 5 5

    37 TOYOTA LAND CRUISER/FORTUNER 4 4

    38 Total 45 75 120

    DESCRIPTION

  • Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Total

    PLANNED TOTAL PER MONTH 47 68 87 95 93 107 110 108 102 100 98 87 82 79 77 66 53 41 1500

    REVISED PLANNED TOTAL PER MONTH 68 87 95 93 107 110 108 102 100 98 87 82 79 77 66 53 41

    PLANNED CUMULATIVE 47 115 202 297 390 458 545 640 733 840 950 1,058 1,160 1,260 1,358 1,445 1,527 1,606 1,683 1,749 1,802 1,843

    ACTUAL TOTAL PER MONTH 33 55 66 68 77 86 88 100 109 112 120 914

    ACTUAL CUMULATIVE 33 88 154 222 299 385 473 573 682 794 914

    2014 2015

    47

    68

    87

    95

    93

    107 110

    108

    102

    100

    98

    87

    82

    79

    77

    66

    53

    41

    33

    55

    66 68

    77

    86 88

    100

    109 112

    120

    68

    87

    95 93

    107110 108

    102 100 98

    8782

    79 77

    66

    53

    41

    0

    20

    40

    60

    80

    100

    120

    140

    Jan

    -14

    Feb-1

    4

    Mar-

    14

    Apr-

    14

    May-1

    4

    Ju

    n-1

    4

    Ju

    l-14

    Aug

    -14

    Sep-1

    4

    Oct-

    14

    Nov-1

    4

    Dec-1

    4

    Jan

    -15

    Feb-1

    5

    Mar-

    15

    Apr-

    15

    May-1

    5

    Ju

    n-1

    5

    Ju

    l-15

    Aug

    -15

    Sep-1

    5

    Oct-

    15

    No

    . o

    f E

    QU

    IPM

    EN

    T

    PROJECT MONTHS

    PLANNED TOTAL PER MONTH

    ACTUAL TOTAL PER MONTH

    REVISED PLANNED TOTAL PER MONTH

  • 15. Details of Manpower Available At Site

    BUDGET ACTUAL BUDGET ACTUAL BUDGET ACTUAL

    A - MANAGEMENT *** 3 3

    B - COMMERCIAL STAFF * 7 1 8

    C - ENGINEERS 6 1 7

    D - FOREMAN & C/H 22 2 24

    E - ENGINEERING TECHNICIANS ** 24 5 29

    F - DAILY RATED EMPLOYEES :

    1 - SKILLED CRAFTSMEN 144 68 212

    2 - SEMI-SKILLED/UNSKILLED 500 53 553

    TOTAL AS OF END OF THE MONTH 0 706 0 130 0 836

    G - SUBCONTRACTORS

    Number of Personnel employed by Subcontractor on Company Work : 44

    * Includes all Administrative office functions, personnel, services, camps,

    insurance, accounts, EDP, stores and purchase staff

    STAFF & LABOUR

    EXPATRIATES NATIONALS TOTAL

  • 2013Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Total

    PLANNED TOTAL PER MONTH - ( DIRECT ) 6 34 186 375 586 791 792 799 794 793 701 480 381 269 246 307 307 305 149 8301

    565 756 754 750 700 652 667 554 516 387 297 276 365 271 135 92 51 7788

    PLANNED TOTAL PER MONTH - ( INDIRECT ) 5 23 36 50 52 57 59 59 60 61 63 61 61 57 51 47 44 35 30 914

    REVISED - PLANNED TOTAL PER MONTH-(INDIRECT) 63 84 84 83 78 72 74 61 57 43 33 31 40 30 15 10 6 862

    PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) 11 57 222 425 638 848 851 858 854 854 764 541 442 326 297 354 351 340 179 9215

    REVISED - PLANNED - ( DIRECT + INDIRECT ) 627 840 838 833 778 725 741 616 573 429 330 306 406 301 150 102 57 8651

    PLANNED CUMULATIVE 11 68 291 715 1,353 2,202 3,052 3,910 4,764 5,618 6,383 6,923 7,365 7,691 7,988 8,342 8,693 9,033 9,212 9,212

    ACTUAL TOTAL PER MONTH - ( DIRECT ) 322 365 550 581 603 691 709 756 734 773 767 765 7616

    ACTUAL TOTAL PER MONTH - ( INDIRECT ) 18 26 46 49 54 57 64 69 68 70 71 71 663

    ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT ) 340 391 596 630 657 748 773 825 802 843 838 836 0 0 0 0 0 0 0 8279

    ACTUAL CUMULATIVE 340 731 1,327 1,957 2,614 3,362 4,135 4,960 5,762 6,605 7,443 8,279

    REVISED - PLANNED TOTAL PER MONTH - ( DIRECT )

    2014 2015

    11

    57

    222

    425

    638

    848

    851

    858

    854

    854

    764

    541

    442

    326

    297

    354

    351

    340

    179

    340

    391

    596 6

    30 657

    748 773

    825

    802 8

    43

    838

    836

    0 0 0 0 0 0 00

    100

    200

    300

    400

    500

    600

    700

    800

    900

    Dec-1

    3

    Jan

    -14

    Feb-1

    4

    Mar-

    14

    Apr-

    14

    May-1

    4

    Ju

    n-1

    4

    Ju

    l-14

    Aug

    -14

    Sep-1

    4

    Oct-

    14

    Nov-1

    4

    Dec-1

    4

    Jan

    -15

    Feb-1

    5

    Mar-

    15

    Apr-

    15

    May-1

    5

    Ju

    n-1

    5

    Ju

    l-15

    Aug

    -15

    Sep-1

    5

    Oct-

    15

    No

    . o

    f M

    en

    PROJECT MONTHS

    PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT ) ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT ) REVISED - PLANNED - ( DIRECT + INDIRECT )

  • 16. QA/QC Reports

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 34

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 35

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 36

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 37

  • 17. Status of Material Approvals

    Date

    Submitted

    CCC/FQI/REN/MAS/001 MAS/CCC/FQI/BBC/001 Bituminous Base Course Tarmac Zawawi LLC Oman 22/12/2013 Renardet APPROVED 01/04/2014 SO/FQI/CCC/087 07/04/2014

    CCC/FQI/REN/MAS/002 MAS/CCC/FQI/GTI/002 Geotechnical Investigation Swissboring & Company LLC 26/12/2013 Renardet APPROVED 02/02/2014 SO/FQI/CCC/015 12/02/2014

    CCC/FQI/REN/MAS/003 MAS/CCC/FQI/MSE/003 MSE Wall System Freyssinet Arabian Sea LLC 26/12/2013 Renardet APPROVED 02/02/2014 SO/FQI/CCC/014 12/02/2014

    CCC/FQI/REN/MAS/004 MAS/CCC/FQI/PVC/004 UPVC Pipes Amiantit Oman 26/12/2013 Renardet APPROVED 09/02/2014 SO/FQI/CCC/019 18/02/2014

    CCC/FQI/REN/MAS/005 MAS/CCC/FQI/HDPE/005 HDPE Pipes & Fittings Amiantit Oman 26/12/2013 Renardet APPROVED 09/02/2014 SO/FQI/CCC/020 18/02/2014

    CCC/FQI/REN/MAS/006 MAS/CCC/FQI/PW/006 Piling Works APCC LLC 26/01/2014 Renardet APPROVED 19/02/2014 SO/FQI/CCC/026 25/02/2014

    CCC/FQI/REN/MAS/007 MAS/CCC/FQI/MC/007 Bitnuminous Prime Coat (MC-70) Emirates Lube Oil Co. (Muscat) 30/01/2014 Renardet APPROVED 09/03/2014 SO/FQI/CCC/069 27/03/2014

    CCC/FQI/REN/MAS/008 MAS/CCC/FQI/RS/008 Reinforcing Steel Muscat Steel Industries 02/02/2014 Renardet APPROVED 20/03/2014 SO/FQI/CCC/063 24/03/2014

    CCC/FQI/REN/MAS/009-1 MAS/CCC/FQI/PT/009-1 Post Tensioning Work - Anchorage Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/089 14/04/2014

    CCC/FQI/REN/MAS/009-2 MAS/CCC/FQI/PT/009-2 Post Tensioning Work - Duct Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/090 14/04/2014

    CCC/FQI/REN/MAS/009-3 MAS/CCC/FQI/PT/009-3 Post Tensioning Work - Strand Freyssinet Arabian Sea LLC 22/02/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/091 14/04/2014

    CCC/FQI/REN/MAS/010A-Rev.1MAS/CCC/FQI/PB/010A-Rev.1Bridge Pot Bearings Al Ammar International 07/05/2014 Renardet Not Approved --- REN/FQI/CCC/111 13/05/2014

    CCC/FQI/REN/MAS/010B MAS/CCC/FQI/PB/010B Bridge Pot Bearings Building Supplies & Services 11/05/2014 Renardet APPROVED 25/05/2014 REN/FQI/CCC/122 31/05/2014

    CCC/FQI/REN/MAS/011 MAS/CCC/FQI/HDPE/011 HDPE Water Pipes Amiantit Oman 22/02/2014 Renardet APPROVED 09/03/2014 SO/FQI/CCC/038 11/03/2014

    CCC/FQI/REN/MAS/012 MAS/CCC/FQI/RCBC/012 Single cell Precast Box Culvert Amiantit Oman 22/02/2014 Renardet APPROVED 25/03/2014 SO/FQI/CCC/064 26/03/2014

    CCC/FQI/REN/MAS/013 MAS/CCC/FQI/BP/013 Bituminous Paint Material (Rubberized) Al Inma Building Materilal LLC 02/03/2014 Renardet Not Approved 20/04/2014 REN/FQI/CCC/105 05/05/2014

    CCC/FQI/REN/MAS/013A MAS/CCC/FQI/BP/013A Bituminous Paint Material (Rubberized) Henkel Polybit Industries Ltd. 17/06/2014 Renardet APPROVED 03/07/2014 REN/FQI/CCC/146 13/07/2014

    CCC/FQI/REN/MAS/014A-Rev.1MAS/CCC/FQI/EJ/014A-Rev.1Bridge Expansion Joints Al Ammar International 07/05/2014 Renardet APPROVED 20/05/2014 REN/FQI/CCC/123 31/05/2014

    MAS/CCC/FQI/EJ/014B Bridge Expansion Joints Ocean Rubber Factory LLC 09/11/2014 Renardet

    CCC/FQI/REN/MAS/015 MAS/CCC/FQI/RC/015Reinforced Concrete Pipe (450,600,700mm

    dia)Amiantit Oman 02/03/2014 Renardet APPROVED 23/03/2014 SO/FQI/CCC/077 02/04/2014

    CCC/FQI/REN/MAS/016 B MAS/CCC/FQI/WS/016 B Water Stop G EE-25 Sika LLC Oman 25/03/2014 Renardet APPROVED 16/04/2014 REN/FQI/CCC/099 28/04/2014

    Renardet

    Letter

    Dated

    Reference No. MAR No. Material/ Work Manufacturer/Supplier/

    Subcontractor

    Submitte

    d To

    Remarks

    By MOTC

    MOTC

    Comments

    dated

    Via Renardet

    Letter Ref. No.

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS

    Date

    Submitted

    CCC/FQI/REN/MAS/017 MAS/CCC/FQI/TW/017 Telephone Works National Telephone Services 12/03/2014 Renardet APPROVED 17/03/2014 SO/FQI/CCC/082 03/04/2014

    CCC/FQI/REN/MAS/019 MAS/CCC/FQI/EW/019 Electrical Works United Engineering Projects 22/03/2014 Renardet APPROVED 29/05/2014 REN/FQI/CCC/131 16/06/2014

    CCC/FQI/REN/MAS/020 MAS/CCC/FQI/EC/020 MV & LV Cables United Engineering Projects 19/03/2014 Renardet APPROVED 27/03/2014 SO/FQI/CCC/083 03/04/2014

    CCC/FQI/REN/MAS/021 MAS/CCC/FQI/PS/021 Package Substation United Engineering Projects 22/03/2014 Renardet ---- ----

    CCC/FQI/REN/MAS/021A MAS/CCC/FQI/PS/021A Package Substation Voltamp Energy SAOG 16/09/2014 RenardetAPPROVED

    as Noted3/11/2014 REN/FQI/CCC/202 30/11/2014

    CCC/FQI/REN/MAS/022 MAS/CCC/FQI/LL/022 Street Lighting Luminaries Majees Lighting Industries LLC 27/03/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/158 17/08/2014

    CCC/FQI/REN/MAS/023A MAS/CCC/FQI/LP/023A Street Lighting Poles (Mid-Hinged)Al Babtain Power &

    Telecomunication Co., S.Arabia22/05/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/157 17/08/2014

    CCC/FQI/REN/MAS/024 MAS/CCC/FQI/FP/024 Street Lighting Feeder Pillar Stars Light LLC 27/03/2014 Renardet APPROVED 08/06/2014 REN/FQI/CCC/130 16/06/2014

    CCC/FQI/REN/MAS/025 MAS/CCC/FQI/JS/025 Joint Sealant (Polyseal) Al Inma Building Materilal LLC 27/03/2014 Renardet APPROVED 16/04/2014 REN/FQI/CCC/100 28/04/2014

    CCC/FQI/REN/MAS/026 MAS/CCC/FQI/GT/026 Geotextile Modern East Trading & Con. 21/05/2014 RenardetNo meet the

    HDS--- REN/FQI/CCC/119 27/05/2014

    CCC/FQI/REN/MAS/026A MAS/CCC/FQI/GT/026A Geotextile (Bonar NW16) Bonar Technical Fabrics 15/06/2014 Renardet APPROVED 14/08/2014 REN/FQI/CCC/159 17/08/2014

    CCC/FQI/REN/MAS/027 MAS/CCC/FQI/MS/027Masterseal 915

    (formerly known as Masterflow 410 Plus)OBasf The Chemical Company 10/08/2014 Renardet

    APPROVED

    as Noted21/10/2014 REN/FQI/CCC/196 17/11/2014

    CCC/FQI/REN/MAS/028 MAS/CCC/FQI/GG/028 Gully Gratings & Frames RBA Ferro Industries PVT. Ltd. 17/08/2014 Renardet APPROVED 25/09/2014 REN/FQI/CCC/192 15/10/2014

    CCC/FQI/REN/MAS/030 MAS/CCC/FQI/FLC/030MasterRoc FLC 100 (Cable Grout

    Admixture)BASF-The Chemical Company 02/10/2014 Renardet

    CCC/FQI/REN/MAS/032 MAS/CCC/FQI/GR/032 Guardrails GK Wire Industries LLC 29/10/2014 Renardet

    CCC/FQI/REN/MAS/033 MAS/CCC/FQI/PVC-D/033 1/2" to 8" UPVC Pipe (Class D) Oman Plast 03/11/2014 Renardet

    MAS/CCC/FQI/SS1H/034 Tack Coat (SS1H) Bitu Trade Industrial LLC 15/11/2014 Renardet

    CANCELLED

    Reference No. MAR No. Material/ Work

    Renardet

    Letter

    Dated

    Manufacturer/Supplier/

    Subcontractor

    Submitte

    d To

    Remarks

    By MOTC

    MOTC

    Comments

    dated

    Via Renardet

    Letter Ref. No.

  • 18. Engineers Comments

    The Planned progress as per the revised Project Execution Program for the month of

    November is 7.98% and the Actual progress is 6.02% which shows 1.96% of delay

    for the month of November. The actual cumulative progress up to November is

    51.41% against Planned Cumulative Progress of 55.53% showing a lagging of

    4.12%. The delayed progress is mainly due to the additional works undertaken

    during the last few months which must be recovered in the coming months.

    Sohar Airport Approach road is completed on priority basis based on the

    requirement of DGR.

    MSE Wall works are progressing well and reaching the completion stage on

    Abutment 1 side.

    The first Box Girder of Superstructure is casted during this month and works in

    progress for second Box Girder.

    Works for the 02 newly proposed Vehicular Underpasses are commenced and in

    progress.

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 41

    19. PROGRESS PHOTOGRAPHS

    Pouring o

    f C

    oncre

    te f

    or

    Deck S

    lab in B

    ox G

    irder

    of

    Fly

    over

    Bridge

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 42

    Installation of Pot Bearings

    Testing of Pot Bearings in Third Party Laboratory in Italy

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 43

    Concrete Pouring in 9 Cells Box Culvert

    Earthworks Filling in Progress in Flyover Approach on Muscat side

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 44

    Earthworks Filling in Progress in Flyover AB2 side Approach

    Earthworks Filling in Progress in Flyover AB2 side Approach

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 45

    Jointing of Electrical Cables

    Installation of Drainage Crossings

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 46

    Flood Water Crossing the Project Detour during the Rain

    DGR Representative Consulting the Local Public after Flood

  • Project: Upgrading of Falaj Al Qabail Roundabout Monthly Progress Report November 2014

    RENARDET S.A. & PARTNERS Page 47

    Installation of MSE Wall Panels in Progress

    Testing of Grouting Material for Post Tensioning Works in Progress