FETESTI PHOTOVOLTAIK PARKS
15

Fotovoltaic Project Romania 48 MW (Fetesti)

Apr 13, 2015

Download

Documents

stratakism

solar project in Romania
phase ready to build
with connection contract
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Fotovoltaic Project Romania 48 MW (Fetesti)

FETESTI PHOTOVOLTAIK PARKS

Page 2: Fotovoltaic Project Romania 48 MW (Fetesti)

Index

₃ Executive Summary

₃ Localization

₃ Land Status

₃ Obtained licenses

₃ Licenses to obtain

₃ Solar data & Production

Page 3: Fotovoltaic Project Romania 48 MW (Fetesti)

₃ Romania and Europe Solar map ₃ Opportunity Background ₃ Index Technical and financial reports ₃ Index Authorizations

Page 4: Fotovoltaic Project Romania 48 MW (Fetesti)

Executive Summary

₃ Strong, technically proficient team with almost 4 years of cumulated experience in the renewable energy sector ₃ Balanced blend of project management experience and solar energy technical expertise ₃ Involved in Solar projects development and implementation over 170 MW in Romania. ₃ Solid network of contacts in all Romanian institutions connected to renewable energy

sector ₃ Specialist technical background

₃ Strategy is to develop projects, ready to build for investors, construct and operate the solar farms.

₃ Professional team, including a technical consultant with a large experience, over 40

years concerning the Romanian energetic system; member of the management team of main important energetic companies.

Page 5: Fotovoltaic Project Romania 48 MW (Fetesti)

Localization

₃ Will have an installed power of totally 48 MWp, being developed over a land of 95 ha; connection to national grid is 8km from site. The project have solution of connection on high voltage to 110KV with a substation.

₃ The Project is developed near Bucharest, 130 km distance (on the highroad A2) in Fetesti City – Ialomita County

₃ Access is assured through national road DN A3

₃ The land is near the substation 20 KV/110 KV in Fetesti

Page 6: Fotovoltaic Project Romania 48 MW (Fetesti)
Page 7: Fotovoltaic Project Romania 48 MW (Fetesti)
Page 8: Fotovoltaic Project Romania 48 MW (Fetesti)

Land status

₃ The land is flat without shading areas.

₃ Total land surface is : 95 Ha.

₃ The land is the property of the company . ₃ The distance to the connection point is 8 km.

₃ Access road to Project location; No river across the land.

Page 9: Fotovoltaic Project Romania 48 MW (Fetesti)

Obtained Licenses

₃ Urbanity planing certificated

₃ Topographic and geotechnical study.

₃ Environmental License

₃ Public health license

₃ Enel opinion

₃ OCPI license.

₃ P.U.Z (urbanistic plan to change the destination of the land from agricola to industrial)

₃ DTAC. (The technical project for the construction needed to obtain the permit for construction)

Page 10: Fotovoltaic Project Romania 48 MW (Fetesti)
Page 11: Fotovoltaic Project Romania 48 MW (Fetesti)

Licenses to obtain

₃ Construction License

₃ ATR (connexion license).

₃ READY TO BUILD.

₃ Connexion Contract

Page 12: Fotovoltaic Project Romania 48 MW (Fetesti)

Solar Data & Production

₃ Over 210 sunny days per annum and 1,154.4 kWh / m² / yearly solar flux energetic (average solar energy from solar radiation which is considered on incidental horizontal plan)

₃ Centre for Renewable Energy Sources-approved software used – Photovoltaic

Geographical Information Systems (PVGIS).

₃ The figures are submitted in kWh (mp/year), in horizontal plan, the most used calculation method for energetic application.

₃ The solar map related for Giurgiu area is developed and offered by Energy Research

Institute, Italy - entity under coordination of EU

Page 13: Fotovoltaic Project Romania 48 MW (Fetesti)

Romania & Europe– Solar map

Page 14: Fotovoltaic Project Romania 48 MW (Fetesti)

Technical proposed solution ₃ Fixed system technology. ₃ Polycrystalline-Silicon Cells, the best solution taking into consideration the PV surface project

and the equipment costs acquisition which offer a production yield of 15-17%.The power of the panel is 230 W from Swiss Watt.

₃ Inverter Power One, SMA 500 TL. ₃ Aluminum fixed structure with the inclination of the panel to the horizontal of

30º and azimuth 0º.

Page 15: Fotovoltaic Project Romania 48 MW (Fetesti)

Opportunity Background

₃ Romania rated as the 3rd fastest growing country in the EU for gaining planning permission for wind turbine developments (according to European Wind Energy Association); After the coming into force of Renewable Energy Law it is expected a similar growth.

₃ For the next 2-3 years at least, the revenues from green energy projects (MWh price plus GC price) will be higher than the current price situation (no external market factors are considered).

₃ Capacity power solar energy in Romania predicted to reach 1.2 TWh by 2020 (currently

the power installed is a little bit lower than 2GWh)

₃ Romania estimated to have a very high solar energy potential in Europe. Romania ranks 11

th place in the 30 EU countries (included Turkey, Croatia and Macedonia) as a potential

of global yearly irradiation, from horizontal & optimum angle and vertical mounting. The best positions are “occupied” by the south countries, like Turkey, Spain or Greece.