ISO-NE PUBLIC Al McBride, Fei Zeng SYSTEM PLANNING Forward Capacity Market Zonal Demand Curves JANUARY 20, 2016 | MILFORD, MA Reliability Committee
36

Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

Jun 14, 2018

Download

Documents

lecong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

Al McBride, Fei Zeng S Y S T E M P L A N N I N G

Forward Capacity Market Zonal Demand Curves

J A N U A R Y 2 0 , 2 0 1 6 | M I L F O R D , M A

Reliability Committee

Page 2: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

2

FCM Zonal Demand Curves

Proposed Effective Date: FCA 11

• ISO is proposing new zonal demand curves for the FCA – Improve locational price signals in the FCM – Better reflect incremental reliability impact of capacity than existing

(fixed) zonal requirements – Derived using a methodology that satisfies three core design principles – Robust to zonal configuration changes – Comply with FERC Order requiring zonal curves for FCA 11

• This meeting: – Discuss stakeholder and filing schedule in light of Dec. 28 FERC Order – Explain zonal transfer capability treatment in ISO’s proposed Zonal

Source Demand Curves – Reliability impacts of ISO’s proposed demand curves

Page 3: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

Agenda For Today

• December 28 FERC Order – Requires ISO to file sloped zonal demand curves by March 31, 2016

• Key Reliability Elements of ISO’s Proposal

• Local Sourcing approach – Zonal transfer capability assumptions for import-constrained zonal

demand curves

• Quantitative Reliability Impacts and Modeling for Proposed Demand Curves

3

Page 4: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

Additional Materials Available

• Markets Committee materials – October 2015

• Overview of ISO’s revised approach – November 2015

• Details of ISO’s method; assumptions and computed demand curves for FCA 10 zones; process and timing for annual updates

– December 2015 • ISO’s results for other zonal possibilities (e.g., FCA10 zones with an added

export zone); initial results for alternate, stakeholder approaches – January 2016

• Local sourcing approach; robustness; new results on price volatility; removal of administrative pricing rules

• Indicative curve data and spreadsheets

• ISO technical memo on FCM Demand Curve Methodology (Dec 7, 2015)

http://www.iso-ne.com/static-assets/documents/2015/12/a09_iso_memo_12_07_15.pdf

4

Page 5: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC ISO-NE PUBLIC

DECEMBER 28 FERC ORDER Requires ISO to file sloped zonal demand curves by March 31, 2016

5

Page 6: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

6

December 28 FERC Order

• FERC Order requires “ISO-NE to submit Tariff revisions by March 31, 2016 providing for zonal sloped demand curves to be implemented beginning in FCA 11”

• Previous project schedule had the ISO filing shortly after the April PC

• To adhere to the Order, the schedule needs to be modified to meet the March 31st deadline set by FERC

Page 7: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

Updated Committee Schedule (1 of 3)

Jan. 2016 Discussion of reliability outcomes and zonal capacity transfer capability assumptions under ISO proposal

Feb. 2016 Continued discussion; Tariff language

March 2016 Reliability Committee vote

Tentative 2016 RC Schedule

7

Page 8: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

Potential Project Schedule 2016 (2 of 3)

Jan. 2016 Administrative pricing rules; further quantitative and qualitative results for ISO’s and stakeholders’ proposals

Feb. 2016 Continued discussion and results; Tariff language; potential amendments raised

March 2016 Continued discussion and results; final Tariff language (ISO proposal and amendments); Markets Committee vote

Tentative 2016 MC Schedule

8

Page 9: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

Potential Project Schedule (3 of 3)

Late March 2016 PC vote (additional meeting)

March 31 FERC filing. Tent. effective date June 2016. Implementation February 2017

Tentative Filing Schedule

9

Page 10: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC ISO-NE PUBLIC

APPROACH OVERVIEW Reliability foundation for deriving demand curves

10

Page 11: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

11

What Principles Should the FCM’s Sloped Demand Curves Aim to Satisfy?

1. Reliability. Meet the ISO’s reliability planning obligations

– System LOLE of 0.1 or less, on average (over the long-term) – An objective in previous design efforts

2. Sustainability. Over the long-term, the FCA’s average clearing price should be sufficient to attract entry when needed – Competitive new suppliers recover their fixed entry costs (Net CONE) – Both in the system and import-constrained zones – An objective in previous design efforts

3. Cost-Effectiveness. Procure capacity in zones cost-effectively

– Zonal curves should allocate capacity purchases among zones, given bid prices, to meet the system’s reliability requirements at least-cost

– Ensuring this objective is satisfied is more complex with zonal demand curves than in the system demand curve design

Page 12: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

12

Capacity Market’s Reliability Foundation

• To satisfy these principles, demand curves seek to balance capacity and reliability

• Capacity helps avoid ‘lost load’

• The sloped demand curves should be based, in part, on the marginal reliability impact of procuring additional capacity – Prices should be commensurate to the reliability benefit of

incremental capacity

Page 13: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

13

Resource Adequacy Indices

• Indices express the expected frequency, expected duration and/or expected magnitude of possible capacity deficiency (loss of load)

• LOLE (Loss of Load Expectation) – Expected number of days per year of loss of load [days/yr] – Commonly used metric of 1 day in 10 years

• LOLH (Loss of Load Hours) – Expected number of hours per year of loss of load [hrs/yr]

• EENS (Expected Energy Not Served) – Expected amount of unserved load [MWh/yr] – Also known as EUE (Expected Unserved Energy) or LOEE (Loss of

Energy Expectation)

A reference for further reading can be found at: http://www.nerc.com/files/2012_ProbA.pdf

Page 14: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

14

Marginal Reliability Impact of Capacity

• ISO’s planning models can calculate expected energy not served (EENS) as a measure of the expected ‘lost load’ – Calculated on a MWh per year basis – EENS depends on capacity in system overall, and in each capacity zone

• Marginal reliability impact (MRI) is the decrease in EENS (expected ‘lost load’) with another 1 MW of capacity – Differs for system and each zone

• Methodology calculates the MRI at the system and zonal level for range of capacity values – May be greater in import-constrained zones where capacity can serve

system or zone

• MRI (after sign change) declines smoothly with capacity, as shown to the right

• ISO’s planning models can calculate this function

Page 15: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

15

Demand Curves Based on the Marginal Reliability Impact are (Slightly) Convex

• When the system is short, deficiencies can occur more frequently, so an additional MW of capacity significantly reduces EENS because – At low MW quantities, MRI value is high – As capacity is added, the MRI decreases quickly meaning the slope is

relatively steep

• When the system is long, deficiencies are infrequent, so an additional MW of capacity has a small impact on EENS because – At high MW quantities, MRI value is low and relatively flat

• Consistent with these properties, demand curves will be based on the MRI function are downward sloping and convex

Page 16: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

• The methodology captures the difference in relative impact of additional capacity in different zones – Especially when the transfer

levels are close to or at the transfer capabilities

16

Relative Impact

Rest-of-Pool

Import Constrained

Zone

Page 17: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC ISO-NE PUBLIC

LOCAL SOURCING DEMAND CURVES

17

Page 18: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

18

Local Sourcing Demand Curve Approach

• ISO’s modeling assumption builds on the current methodology used to generate the Local Sourcing Requirement based on both the TSA and LRA values – “For each import-constrained Capacity Zone, the Local Sourcing Requirement shall be

the amount needed to satisfy the higher of: (i) the Local Resource Adequacy Requirement as determined pursuant to Section III.12.2.1.1; or (ii) the Transmission Security Analysis Requirement as determined pursuant to Section III.12.2.1.2.”

• MRI calculations will use a capacity transfer capability of:

(N-1 limit) – max(TSA-LRA,0)

– Starts with N-1 limit, but includes adjustment based on the positive difference difference between TSA and LRA

Page 19: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

19

Example: SENE Capacity Transfer Capability

FCA 10 Input Parameters:

• N-1-1 Import Limit = 4,600 MW

• N-1 Import Limit = 5,700 MW

• Local Resource Adequacy (LRA) = 9,584 MW

• Transmission Security Adequacy (TSA) = 10,028 MW

Revised capacity transfer capability assumption for SENE zonal MRI calculations is:

5,700 MW – max(10,028 TSA - 9,584 LRA, 0) = 5,256 MW

Page 20: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

20

Page 22: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

22

Notes: LSR = 7,331 MW for CT in FCA 9.

Page 23: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

23

Notes: LSR = 3,572 MW for NEMA in FCA 9.

Page 24: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

24

Notes: LSR = 7,479 MW for SEMA/RI in FCA 9.

Page 25: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC ISO-NE PUBLIC

DERIVING CURVES FOR EXPORT-CONSTRAINED ZONES Same methodology as that used in import-constrained zones produces congestion-based demand curves in export-constrained zones

25

Page 26: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

Export-Constrained Zones Derived Using Same Methodology As Import-Constrained Zones

• Curves in all constrained zones are based on the marginal reliability impact of shifting a MW of capacity from the rest-of-system zone into the zone

• Shift of capacity into import-constrained zones improves system reliability (reduces EENS) – Resulting curve in import-constrained zone therefore pays a positive

congestion price to capacity in the zone

• Shift of capacity into export-constrained zone decreases system reliability (increases EENS) – Resulting curve in export-constrained zones must therefore pay a

negative congestion price to capacity in the zone

26

Page 27: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

Export-Constrained MRI Curve is Downward Sloping and Negative

• MRI function is zero for low MW quantities as capacity in export-constrained zone provides equal reliability value to that in rest-of-system

• At higher MW quantities, MRI function slopes downward because marginal reliability impact of capacity in the zone decreases

27

Page 28: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

28

Notes: Indicative MCL = 8,830 MW for NNE in FCA 10. * November 16, 2015 Planning Advisory Committee: http://www.iso-ne.com/static-assets/documents/2015/11/a2_fcm_zonal_development_3_review_of_determinations_for_fca_10.pdf

Page 29: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC ISO-NE PUBLIC

QUANTITATIVE RELIABILITY RESULTS Fei Zeng

29

Page 30: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

30

Probabilistic Reliability Calculations under Proposed Demand Curve

• Calculations for system-wide ICR, MCL for export-constrained zones, and LRA for import-constrained capacity zones remain unchanged – Same simulation model (GE MARS) – Same calculation methodology – Same stakeholder review process for input assumptions

• Deriving Demand Curves requires a series of MARS simulations to calculate the system-wide expected energy not served (EENS) – System curve based on the same ICR case – Zonal curve based on the same LRA/MCL case

• With adjusted N-1 limit for import-constrained zones

Page 31: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

31

EENS Calculations using MARS

• MARS is a sequential Monte Carlo simulation reliability model that can calculate the standard indices of – Daily LOLE (days/year)

• Currently used for calculating ICR and related values – Hourly LOLE (hours/year) – Expected Unserved Energy (LOEE in MWh/year)

• Same as EENS

&CNV-CRIT-00 CNC * CONVERGENCE-CRITERIA *---------------------------------------------------------------------------------------------------- AREA OR POOL TO DETERMINE HOUR OF DAILY PEAK (.IPKARP.) AAAAAAAA : "ALL ”

CALCULATED INDICES FOR 2019 ********** INTERCONNECTED *********** LOLE LOLE LOEE AREA OR POOL (days/yr) (hrs/yr) (MWh/yr) ------------------ --------- -------- ---------- BHE 0.00744 0.03100 0.130 ME 0.00000 0.00000 0.000 … NEPOOL 0.06558 0.35394 346.016

Sample output file

To have MARS calculate all three indices

Page 32: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

32

Quantitative Reliability Results on Indicative System Demand Curve

• Indicative System Demand Curve from Dec 2015 MC presentation (Using FCA 10 Inputs) • LOLE calculated assuming unconstrained system

Page 33: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

33

Quantitative Reliability Results on Indicative SENE Demand Curve

Indicative SENE Demand Curve from Jan 2016 MC presentation (Using FCA 10 Inputs)

Page 34: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

34

Quantitative Reliability Results on Indicative NNE Demand Curve

Indicative NNE Demand Curve from Dec 2015 MC presentation (Using FCA 10 Inputs)

PSYS -

PSYS

PSYS

PSYS

PSYS

PSYS

PSYS

PSYS

PSYS

PSYS

PSYS

Page 35: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

35

Resource Adequacy Evaluation of Modeled Outcomes under ISO Proposed Demand Curves (FCA10 Inputs)

• NPCC Resource Adequacy Design Criterion applied – System-wide LOLE <= 0.1 days/year

• Adequate if resources more than ICR

– N-1 limits used to reflect transmission limitation • Adequate if resources more than LRA in import-constrained zones • Deliverable if resources less than MCL in export-constrained zones

• Modeled outcomes based on Jan 2016 MC presentation using FCA10 inputs

SENE: LRA=9584 MW NNE: MCL=8830 MW System: ICR=34151 MW Supply Model MW Procured

Adequacy Evaluation MW Procured

Reliability Evaluation MW Procured

Reliability Evaluation

Model 1 10840 √ 8440 √ 34151 0

Model 2a 10840 √ 8440 √ 34712 561

Model 2b 10840 √ 8440 √ 34314 163

Model 2c 10840 √ 8440 √ 34012 -139

Model 2d 9950 √ 8440 √ 34151 0

Model 3 11069 (σ =468) √(on avg.) 8805 (σ =218) √(on avg.) 34554 (σ =255) 403 (on avg.)

Model 4a 10840 √ 8440 √ 34151 0

Model 4b 10840 √ 8440 √ 34151 0

Model 5a 9816 √ 8440 √ 34389 238

Model 6a 10807 (σ =164) √(on avg.) N/A N/A 34127 (σ =75) -24 (on avg.)

Model 6b 10809 (σ =151) √(on avg.) N/A N/A 34113 (σ =119) -38 (on avg.)

Page 36: Forward Capacity Market Zonal Demand Curves€¦ · ISO-NE PUBLIC Agenda For Today • December 28 FERC Order –Requires ISO to file sloped zonal demand curves by March 31, 2016

ISO-NE PUBLIC

36

Al McBride a m c b r i d e @ i s o - n e . c o m