Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

Aug 19, 2018

Download

Documents

dotram
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree
Page 2: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

Fortaleza - Ceará - Northeastern Brazil

Page 3: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree
Page 4: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

• Political Entity: Municipality of Fortaleza

• Geographic location: Northeast Region

• Population: 2,571,896 (CE: 1º /BR: 5º - IBGE/2014)

• Gross Domestic Product : R$ 43.402.190 (BR: 10º - IBGE/2012)

• End of current mayor’s term: December 31, 2016

• Human Development Index (2010): 0,754 (CE: 1º) - High - PNUD/2010

• Gross Domestic Product per capita: R$ 17.359,53 (IBGE/2012)

• Population's education level: Elementary Education 25,64% / SecondaryEducation 23,42% / Higher Education 8,96% (IBGE/2010)

• Main economic activities: Commerce / Service Provision / Construction

• 2015 annual budget : R$ 6.425.962.864,00

Page 5: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

• Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011;Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree nº13,158, of may 14, 2013.

• There are no contracts signed.

• Public Funding Limit (5% of Current Net Revenue): R$ 193.000.000,00/year

• What are the three PPP priority projects?– Revitalization of Fortaleza Historic Center

– Restructuring Public Parking Areas in Fortaleza

– New Government Center Building of Fortaleza

• Project time schedule: have not yet been presented by the new companies authorized to develop the project feasibility studies.

• Priority procedure for project studying: Private Initiative

Page 6: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

Revitalization of Fortaleza Historic Center

• Estimated investment: yet to be presented

• Contract model: administrative concession (no user fees / private partner reward comes frompublic funds)

• Situation: studies in progress

• Next step of the project: public hearing

Page 7: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

Center area of the city expanded: 500 Ha Estimated number of passers: 1.000.000/dayEstimated number of inhabitants: 27.000

Page 8: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

• The project target area is a urban center withintense popular commerce, also hostingtouristical, historical and architecturallandmarks.

• The area has been suffering from serious urbanmobility issues and other infrastructureproblems.

Page 9: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

Restructuring Public Parking Areas in Fortaleza

• Estimated investment: yet to be presented

• Contract model: administrative concession (no user fees / private partner reward comes frompublic funds)

• Situation: studies in progress

• Next step of the project: public hearing

Page 10: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree
Page 11: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

• The fleet of vehicles in Fortaleza grew 104.43% from2003 to 2013, which generated a huge parking issue,both public and private.

Project:• Connect the diferent types of transportation;

• Regulation of parking in priority areas;

• New system for public parking.

Page 12: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

New Government Center Building of Fortaleza

• Estimated investment: yet to be presented

• Contract model: administrative concession (no user fees / private partner reward comes frompublic funds)

• Situation: studies in progress

• Next step of the project: public hearing

Page 13: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree
Page 14: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

• Reduce time for citizen serving;

• Share common services among departments;

• Improve information flow;

• Reduce costs of operation.

Project:• Construct a building for hosting the 31 public

departments of the Municipality, with capacity for6,000 servers;

• Facilities management.

Page 15: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

What do we expect from companies and British investors?

Involvement in all stages concerning a Public-Private Partnership:

• Training the Government staff;

• Structuring the standard procedure to be followed by the Government for the projects;

• Structuring the stages of the project.

Page 16: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree

Contact

Laízi de Moraes Fracalossi

[email protected]

+55 85 98755.4785 / +55 85 3265.5114

Patrícia Macêdo – Special Coordinator of International Relations

[email protected]

+ 55 85 3105.2627 / +55 85 98970.3027

Alexandre Pereira – Public-Private Partnerships Coordinator

[email protected]

+55 85 99983.5952

Page 17: Fortaleza - Ceará - Northeastern Brazil · • Local Legislation on PPP: Municipal Law nº 9,783, of june 13, 2011; Municipal Decree nº 13,157, of may 14, 2013 and Municipal Decree