Special Purpose Local Option Sales Tax Program for Road Improvement Projects R. J. (Pete) Amos, Chairman Jim Boff, Vice Chairman Brian R. Tam, Secretary Todd Levent, Member Cindy Jones Mills, Member Doug Derrer, County Manager Tim Merritt, Deputy County Manager John Cunard, Director, Department of Engineering October, 2013
37

Forsyth County Transportation Summit Presentation 10 23 13.pdf

Oct 26, 2015

Download

Documents

brandepoulnot

.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Forsyth County Transportation Summit Presentation 10 23 13.pdf

Special Purpose Local Option Sales Tax Program for Road Improvement Projects

R. J. (Pete) Amos, Chairman Jim Boff, Vice Chairman Brian R. Tam, Secretary Todd Levent, Member

Cindy Jones Mills, Member

Doug Derrer, County Manager Tim Merritt, Deputy County Manager

John Cunard, Director, Department of Engineering

October, 2013

Page 2: Forsyth County Transportation Summit Presentation 10 23 13.pdf
Page 3: Forsyth County Transportation Summit Presentation 10 23 13.pdf
Page 4: Forsyth County Transportation Summit Presentation 10 23 13.pdf
Page 5: Forsyth County Transportation Summit Presentation 10 23 13.pdf
Page 6: Forsyth County Transportation Summit Presentation 10 23 13.pdf

• Asphalt - 1,084

• Gravel - 29

• State - 104

• City - 39

Page 7: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST III – SPLOST VI Road Improvement Summary

Since 1996, Forsyth County has completed • 4 New 4-Lane w/Median Roads –

– Market Place Boulevard, Freedom Parkway, Ronald Reagan Blvd & Windermere Parkway

• 10 Major Road Widenings – Veterans Memorial Boulevard, Castleberry Road, McFarland Parkway,

Mathis Airport Parkway, Kelly Mill Road, Old Atlanta Road, Bethelview Road, Majors Road, Hutchinson/North Old Atlanta Road & McGinnis Ferry Road

Page 8: Forsyth County Transportation Summit Presentation 10 23 13.pdf

• Completed 87 state and county intersection projects • Resurfaced approximately 760 miles of county roads

– M ore m iles than the direct distance between Cum m ing and G reen B ay, W I

• Graded, based & paved 77 gravel roads – In 1987, there were 108 m iles of county gravel roads. Today,

there are 29 m iles. • 30 road reclamation projects

• Installed first county traffic signal in 1996 at the intersection of

McFarland Road and Union Hill Road • County maintains 69 traffic signals and 37 flashing school beacons

Page 9: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VI Road Improvement Projects

Page 10: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VI – New Roads

Project Name: Ronald Reagan Blvd Length of Project: 1.25 miles Project Description: 4 lanes, median

Page 11: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VI – Road Widenings

Project Name: Road Widenings Completed: 2 • Kelly Mill Road – 1.53 • Old Atlanta Road – .54 Total Miles: 2.07

Page 12: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VI - Intersections

Project Name: Intersection Projects Completed: 26 Projects

Page 13: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VI – Bike/Pedestrian Projects

Project Name: Bike/Ped Projects Total Length: 8.2 miles

Page 14: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VI – Grade, Base & Pave

Project Name: Unpaved Roads Completed: 9 Roads Total Miles: 3.00

Page 15: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VI – Road Reclamation

Project Name: Road Reclamation Completed: 10 Projects Total Miles: 19.18 miles

Page 16: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VI - Culverts

Project Name: Culverts Completed: 18

Page 17: Forsyth County Transportation Summit Presentation 10 23 13.pdf

Project Name: SPLOST VI - 2008 Resurfacing Total Length: 64 miles Total Roads: 205

Page 18: Forsyth County Transportation Summit Presentation 10 23 13.pdf

Project Name: SPLOST VI - 2009 Resurfacing Total Length: 54 miles Total Roads: 135

Page 19: Forsyth County Transportation Summit Presentation 10 23 13.pdf

Project Name: SPLOST VI - 2010 Resurfacing Total Length: 62 miles Total Roads: 168

Page 20: Forsyth County Transportation Summit Presentation 10 23 13.pdf

Project Name: SPLOST VI - 2011 Resurfacing Total Length: 60 miles Total Roads: 190

Page 21: Forsyth County Transportation Summit Presentation 10 23 13.pdf

Project Name: SPLOST VI - 2012 Resurfacing Total Length: 55 miles Total Roads: 196

Page 22: Forsyth County Transportation Summit Presentation 10 23 13.pdf

Project Name: SPLOST VI - 2013 Resurfacing Total Length: 46 miles Total Roads: 141

Page 23: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VI - Traffic Safety Improvements • Striping - 500 miles • Guardrails – Installation & Replacement • Signs – Installation & Replacement • Intersection Improvements w/Traffic Signals – 5

– Bethelview Road at Bennett Parkway – Buford Dam at Samples Road – Hwy 9 at Castleberry Road/Carolene – McGinnis Ferry Road at Old Alpharetta Road – SR 141 at Stoney Point Road

• Culverts – 18 Projects • Sidewalks – 4

– Caney Road-Brookwood Road (Under Design) – James Burgess Road – McFarland Road/Shiloh Road/Shiloh Road East (Under Design) – Old Atlanta Sidewalk

• Reclamation – McGinnis Ferry Road – Bethany Bend to SR 400 – McGinnis Ferry Road Turn Lanes – SR 400 to Union Drive

Page 24: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VII Transportation Projects

Page 25: Forsyth County Transportation Summit Presentation 10 23 13.pdf

Proposed SPLOST VII Major Road Widenings

Road Name From - To

Approved SPLOST

Funding Bethelview Road, Phase II Castleberry Road to SR 20 1,500,000 Brookwood Road SR 141 to McGinnis Ferry Road 200,000 Castleberry Road, Phase I City Limits to Bethelview Road 5,000,000 McFarland Parkway GA 400 to McGinnis Ferry Road 200,000 McGinnis Ferry Road Sargent Road to Union Hill Road 1,250,000 Old Atlanta Road, Phase II Sharon Road to Nichols Road 6,800,000 Old Atlanta Road, Phase III St. Marlo to McGinnis Ferry Road 3,800,000 Pilgrim Mill Road City Limits to Freedom Parkway 200,000 Sharon Road SR 141 to Old Atlanta Road 9,900,000 Union Hill Road/Mullinax Road McFarland Parkway to SR 9 16,540,000 Union Hill Road GA 400 to McFarland Road 200,000 Union Hill Road Bridge 360,000

TOTAL MAJOR ROAD WIDENINGS 45,950,000

Page 26: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VII – Old Atlanta Road, Phase II

Project: Old Atlanta Road, Phase II Sharon Road to Nichols Road Length of Project: .91 miles Project Description: 4 lanes, median

Page 27: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VII – Old Atlanta Road, Phase III

Project Name: Old Atlanta Road, Phase III McGinnis Ferry Rd to Country Club Pkway Length of Project: .78 miles Project Description: 4 lanes, median

Page 28: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VII – Sharon Road Widening

Project Name: Sharon Road Widening SR 141 to Old Atlanta Road Project Length: 1.21 miles Project Description: 4 lanes, median

Page 29: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VII – Union Hill Road/Mullinax Road

Project Name: Union Hill Rd/Mullinax Rd McFarland Parkway to SR 9 Project Length: 2.54 miles Project Description: 4 lanes, median

Page 30: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VII – McGinnis Ferry Road Widening

Project Name: McGinnis Ferry Road Widening Sargent Road to Union Hill Road Project Length: 4.58 miles Project Description: 4 Lanes, median

Page 31: Forsyth County Transportation Summit Presentation 10 23 13.pdf

McGinnis Ferry Road Widening Concept Plan

Project Name: McGinnis Ferry Road Widening Length: 4.44 miles Est. Engineering-R/W Costs - $ 8,500,000 Est. Construction Cost - $27,500,000 Total Estimated Costs - $36,000,000

Page 32: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VII – Bike/Pedestrian Sidewalks

Project Name: Bike/Pedestrian Sidewalks • Nichols Road – Old Atlanta Rd to Nichols Drive • Nichols Drive – Nichols Rd to James Burgess • Majors Road – Post Rd to Big Creek Greenway • Caney Road – Brookwood Rd to Old Alpharetta Rd • Old Alpharetta Rd – Caney Rd to SR 141 • Majors Rd – SR 141 to Ronald Reagan Blvd

Page 33: Forsyth County Transportation Summit Presentation 10 23 13.pdf

SPLOST VII – Intersections

Project Name: Intersection Projects • John Burruss Rd at Karr Rd • Bannister Rd at Elmo Rd • Wallace Tatum Rd at Burnt Bridge Rd • Wallace Tatum Rd at Wright Bridge Rd • Holbrook Rd at Burnt Bridge Rd • SR 369 at SR 9 • Settingdown Rd at Martin Rd • SR 20 at Woodland Hill Drive

Page 34: Forsyth County Transportation Summit Presentation 10 23 13.pdf
Page 35: Forsyth County Transportation Summit Presentation 10 23 13.pdf
Page 36: Forsyth County Transportation Summit Presentation 10 23 13.pdf

McGINNIS FERRY ROAD INTERCHANGE

Project Name: McGinnis Ferry Road Interchange Est. Engineering-R/W Costs - $15,752,557 Est. Construction Costs - $23,527,962 Total Project Costs - $39,260,519

Page 37: Forsyth County Transportation Summit Presentation 10 23 13.pdf

Engineering Staff: John V. Cunard, Director Tim L. Allen, Assistant Director Jason McCook, Program Manager, Moreland-Altobelli For information on Transportation Improvement Projects, please visit the county’s website:

www.forsythco.com and click on “Transportation Projects”