Top Banner
Final Report CRC Project #40 Formwork pressures for Self Consolidating Concrete. N.J. Gardner October 7, 2010 Effectively this project has been on hold since 2008. The project depended upon access to construction projects of the co-investigators (Ellis-Don Construction) using Self Consolidating Concrete. Unfortunately the current construction situation has not resulted in any suitable projects. The results to date were summarized in a presentation at Los Angeles (spring 2008). A pdf of the presentation, titled LosAngeles4, is attached. All figures in this report are taken from the Los Angeles presentation. The major, labor intensive and expensive part of the project involved measuring form pressures at 4 sites operated by Ellis-Don Construction in Charleston, London Ontario, Peterborough Ontario and Toronto. Obviously industry is most interested in the maximum form pressures for formwork design; which are determined by the rate of concrete placement versus the rate/development of concrete stiffness/strength. Unfortunately the term ―Self Consolidating Concreteis a non-unique, generic description. Indentifying and characterizing the flow/stiffening properties of the concrete relevant to the magnitude of the lateral pressure envelope would be very useful. Material characterization evolved over the course of the project. Mix design and qualification should be done prior to start of construction. However on-site quality control is required to ensure mix compliance and consistency. Preconstruction mix testing is usually limited to ensuring that specified strength and slump flow can be achieved using the available materials and admixtures. Slump flow loss and rheometer tests can be done conveniently, in the luxury of a laboratory environment, at this time. Lessons learned Discontinuous placement, by bucket or programmed interruptions of pumping, allows the concrete to gain shear strength, reducing the maximum form pressures. For formwork pressure purposes, the ideal admixture combination would produce a concrete that flows under agitation and immediately stiffens when agitation ceases. The SCC mixture design has to be done with care and admixtures can not be changed or substituted without diligent consideration. In addition changes to the water content of the aggregates can significantly affect the stability of the mixture and strict control for moisture compensation needs to be instituted at the ready-mix plant. Testing for production, mixture selection/qualification and formwork selection must be done in concert and concrete control parameters must be established to ensure compliance. Rheometer Studies Flow behaviors are measured by devices called a rheometers. Measurements can be taken using linear movement (falling ball),or axisymetric, planetary or annular rotational movement.
11
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • Final Report CRC Project #40

    Formwork pressures for Self Consolidating Concrete.

    N.J. Gardner October 7, 2010

    Effectively this project has been on hold since 2008. The project depended upon access to

    construction projects of the co-investigators (Ellis-Don Construction) using Self Consolidating

    Concrete. Unfortunately the current construction situation has not resulted in any suitable

    projects.

    The results to date were summarized in a presentation at Los Angeles (spring 2008). A

    pdf of the presentation, titled LosAngeles4, is attached. All figures in this report are taken from

    the Los Angeles presentation.

    The major, labor intensive and expensive part of the project involved measuring form

    pressures at 4 sites operated by Ellis-Don Construction in Charleston, London Ontario,

    Peterborough Ontario and Toronto. Obviously industry is most interested in the maximum form

    pressures for formwork design; which are determined by the rate of concrete placement versus

    the rate/development of concrete stiffness/strength. Unfortunately the term Self Consolidating Concrete is a non-unique, generic description. Indentifying and characterizing the flow/stiffening properties of the concrete relevant to the magnitude of the lateral pressure

    envelope would be very useful. Material characterization evolved over the course of the project.

    Mix design and qualification should be done prior to start of construction. However on-site

    quality control is required to ensure mix compliance and consistency.

    Preconstruction mix testing is usually limited to ensuring that specified strength and

    slump flow can be achieved using the available materials and admixtures. Slump flow loss and

    rheometer tests can be done conveniently, in the luxury of a laboratory environment, at this time.

    Lessons learned

    Discontinuous placement, by bucket or programmed interruptions of pumping, allows the

    concrete to gain shear strength, reducing the maximum form pressures. For formwork pressure

    purposes, the ideal admixture combination would produce a concrete that flows under agitation

    and immediately stiffens when agitation ceases. The SCC mixture design has to be done with

    care and admixtures can not be changed or substituted without diligent consideration. In addition

    changes to the water content of the aggregates can significantly affect the stability of the mixture

    and strict control for moisture compensation needs to be instituted at the ready-mix plant.

    Testing for production, mixture selection/qualification and formwork selection must be done in

    concert and concrete control parameters must be established to ensure compliance.

    Rheometer Studies

    Flow behaviors are measured by devices called a rheometers. Measurements can be

    taken using linear movement (falling ball),or axisymetric, planetary or annular rotational

    movement.

  • Flow occurs when the applied shear stress exceeds the material shear strength.

    Traditionally fluids were described as Newtonian resistance to flow proportional to velocity gradient. More recently Bingham proposed that a flow regime in which an initial shear stress has

    to be applied to initiate flow.

    At its fundamental, a rheometer has to give data at sufficient points to determine the

    initial yield strength and the dynamic viscosity. Naturally flow of real particulate materials is

    more complicated.

    ICAR rheometer

    0

    0.02

    0.04

    0.06

    0.08

    0.1

    0 2 4 6 8

    Dyn

    amic

    Vis

    cosi

    ty

    Velocity Gradient

    Viscosity

    NewtonianBingham

  • The ICAR rheometer uses a paddle rotating in the test material. The motor applies a chosen

    rotational speed and measures the torque required. The process is repeated at different angular

    velocities. Concrete is conditioned, to remove initial perturbations in the sample, by applying a

    low angular velocity for several seconds, the velocity is then increased to a chosen higher

    velocity and then the velocities are decreased to zero. Torque measurements are taken at pre-

    selected velocities. The figure below shows measured results for a trial SCC taken at different

    ages after mixing. The angular velocity was increased in steps, to enable the torque to be

    measured, from 0.05 rotations/second to 0.55 rotations/second and then decreased with torque

    measurements also taken at the same rotations. The increasing rotation speed torques are higher

    than the decreasing speed torques. The decreasing torque speed curves approximate a straight

    line (Bingham) with an intercept (yield strength) and a slope (dynamic viscosity).

    As concrete in a form is at rest the zero rotation behavior is of most of interest initial conditioning of the concrete is a complication. Using different control settings the ICAR

    rheometer can also measure the minimum displacement (yield) stress growth during

    conditioning.

    Mix 3, Lab: Stress Growth Data, Non-Agitated Samples

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    3.0

    3.5

    0 0.1 0.2 0.3 0.4 0.5 0.6

    Rotation Speed (rev/s)

    Torq

    ue

    (Nm

    )

    End Mixing20 Minutes40 Minutes80 Minutes

    Flow Curve Tests

    Mix 3, Lab: Stress Growth Data, Non-Agitated Samples

    0.0

    0.5

    1.0

    1.5

    2.0

    2.5

    0 2 4 6 8 10

    Time (s)

    Torq

    ue

    (Nm

    )

    End Mixing20 Minutes40 Minutes80 Minutes

    Stress Growth Tests

  • Slump Flow Loss

    The standard test to measure the flow potential of SCC is the slump flow easy to understand and possible to do on construction sites. Multiple samples are required to permit

    testing every 20-30 minutes or so during the time needed to cast a concrete element. As most

    SCC has a specified slump flow of 600mm (24 ins.) the loss point was chosen to be 400mm (16

    ins) and the time for the flump flow to reach 400mm was taken as the characteristic. The slump

    flow loss has been correlated to the ICAR fundamental rheological properties (which are

    rheometer dependent).

    Visualization of Casting Process

    The figure below, also shown in the LosAngeles4 pdf, is a visualization of the placing

    process to determine the required characterization properties. Concrete is agitated in the truck

    during transport and remixed at high speed upon reaching the construction site. Concrete is

    placed into the bucket where it is at rest. Concrete is discharged from the bucket and flows into

    the form. When the concrete is at rest, inter-particle bonds form creating shear strength. When

    the concrete is poured into the form the bonds are broken.

    However after the concrete has reached its final position in the form it is not in a state of

    flow/failure. The formwork supplies sufficient lateral constraint to hold the concrete in place. As

    more concrete is poured it is supported by the lower concrete partly by the shear strength of the

    previously placed concrete is due to cohesion and internal friction. Neither of conventional

    rheometer characterizations is an appropiate representation of the concrete placing process.

    Figure 1 Visualization of the casting process

    With the aging of concrete during placement multiple undisturbed samples of concrete

    are required.

    Dynamic Yield Stress Full Breakdown, No Thixotropy

    Static Yield Stress of Un - Agitated SCC

    No Breakdown, Full Thixotropy

    Static Yield Stress of SCC Placed by

    Bucket

    Time from Mixing

    Yield Stress

    Concrete is agitated in truck du ring transit

    Concrete is remixed at high speed upon reaching site

    Concrete is placed in bucket, where it is at rest

    Concrete is discharged from bucket and flows through formwork

    Concrete is in formwork, static yield stress increases

  • As an alternative measure of flow behavior the slump flow loss test was devised also requiring multiple undisturbed samples.

    Field Program

    Field measurements of form pressures were taken at four sites pressures at 4 sites

    operated by Ellis-Don Construction in Charleston, London Ontario, Peterborough Ontario and

    Toronto.

    Citadel, Charleston SC 2005-2006.

    Base mix design, including use of an IBB rheometer, was completed before the PI got

    involved with Ellis-Don. A base mix, a reduced w/cm, a reduced paste mix and an increased

    coarse aggregate mixes were chosen. As the project progressed modified mixes were added and

    others abandoned without field use. The project was a university residence with 6ins. and 16 ins.

    thick shear walls. A single residence unit required about 6 cubic yards of concrete placed by

    pump. With SCC the concrete placement could be completed in as few as 10 minutes the form pressure envelope was hydrostatic. With time the placement sequence was modified to place half

    the height of concrete in successive residence units and the placing the second lift some time (20

    minutes) later.

    Most of the measured pressures were close to hydrostatic. Mix proportions did not seem

    to have much effect. Splitting the pouring into lifts with a rest period between lifts did reduce the

    maximum pressures.

    Feb 2, 2006

    Mix 40SAF000

    Conc. Temp. 18C

    -20

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    9 9.25 9.5 9.75 10 10.25 10.5 10.75

    Time (Hours)

    Pre

    ss

    ure

    (k

    Pa

    )

    Cell 14 Cell 15 Cell 16

    Cell 10 Cell 11 Cell 12

  • Labatts Brewery, London, ON (Dec.2005-Jan 2006)

    Sixteen inch thick walls for a service shaft placed by bucket resulting a moderate rate of

    placement. No rheometer tests were done. Maximum measured pressures much less than

    hydrostatic.

    Regional Hospital, Peterborough ON (spring-summer 2006)

    Field testing was conducted on 3 mixtures on separate days. Mixture 1 was a base mix;

    Mixture 2 had a higher coarse aggregate to total aggregate ratio; and Mixture 3 had lower w/cm

    and different retarder and superplasticizer. The walls were 4.27 m high, 300 mm thick and were

    instrumented with 4 vibrating wire pressure gauges (4.12 m maximum head above lowest

    gauge). Concrete was placed into forms by bucket at approximately 2 m/hr. At the beginning of

    placement, concrete was sampled for rheology measurements with the ICAR rheometer and the

    slump flow test. For the rheometer, concrete was placed in the rheometer container and left

    undisturbed until the time of testing. After testing, the concrete was remixed and allowed to

    remain undisturbed in the rheometer container until the next test. For the slump flow test, an

    undisturbed sample of concrete was stored in a wheelbarrow and tested at times corresponding to

    the rheometer measurements. For brevity, the rheometer measurements are not shown in this

    paper.

    Figures indicates that Mixtures 1 and 2 lost workability quickly, as indicated by the loss of

    slump flow. Consequently the formwork pressures were much lower than hydrostatic pressure,

    as shown. When concrete was first placed into the forms for these two mixtures, the pressure

    increased at the lower cells. As further lifts of concrete were added to the initial liftsas seen when pressures were registered on higher cellsthe pressure at the lower cells increased by a slight extent, if at all, because of the increased shear strength of the material at the lower cells.

    The fast loss of workability or build-up of thixotropic structure contributed to this increased

    Labatt's January 6-06

    SCC

    Conc.Temp. 17C

    T50 = 5.5 secs

    -30

    -20

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    10.6 11.0 11.3 11.7 12.0 12.3 12.6 13.0 13.3 13.6 14.0 14.3 14.7

    Time (hours)

    La

    tera

    l P

    res

    su

    re (

    KP

    a)

    Hydrostatic 104kPa

    Hydrostatic 76 kPa

    Hydrostatic 48 kPa

  • shear strength. (The results for Mixture 1 were compromised by the long delay in arrival

    between the first and second trucks, illustrating the problems of field research.)

    Figure 4: Formwork Pressure Measurements for Peterborough Mixture 1

    Second concrete truck got lost allowing earlier concrete to set up.

    Figure 5: Formwork Pressure Measurements for Mixture 2

    0

    100

    200

    300

    400

    500

    600

    700

    800

    0 10 20 30 40 50 60 70 80 90 100

    Slu

    mp

    Flo

    w (

    mm

    )

    Time (mins)

    May5,06Peterborough Trial 1 - May 5, 2006

    Concrete temperature 18C

    -10

    -5

    0

    5

    10

    15

    20

    25

    30

    12 12.5 13 13.5 14 14.5 15 15.5 16

    Time (Hour + Decimal)

    La

    tera

    l P

    res

    su

    re (

    kP

    a)

    Cell 13 (Hyd.Pres. 36.1 kPa)

    Cell 14 (Hyd.Pres. 63.5 kPa)

    Cell 15 (Hyd.Pres. 91.1 kPa)

    Cell 16 (Hyd.Pres. 98.7kPa)

    200

    300

    400

    500

    600

    700

    0 20 40 60

    Slu

    mp

    Flo

    w (

    mm

    )

    TIME (mins)

    July12/06

    Peterborough Trial 2 - July 12, 2006

    Concrete temperature 20C

    -10

    -5

    0

    5

    10

    15

    20

    25

    30

    35

    40

    11.0 11.5 12.0 12.5 13.0

    Time (Hour + Decimal)

    Lat

    eral

    Pre

    ssu

    re (

    kP

    a)

    Cell 13 (Hyd.Pres. 36.1 kPa)

    Cell 14 (Hyd.Pres. 63.5 kPa)

    Cell 15 (Hyd.Pres. 91.1 kPa)

    Cell 16 (Hyd.Pres. 98.7 kPa)

  • Figure 6: Formwork Pressure Measurements for Mixture 3

    The different retarder and superplasticizer used in Mixture 3 extended the workability

    retention. As a result, the formwork pressures were much higher than in the first two mixtures

    and nearly approached hydrostatic pressure. As further lifts of concrete were added to the lower

    lifts, the pressures at the lower cells continued to increase significantly because the lower

    concrete had not gained shear strength.

    The formwork pressure data for the 3 mixtures clearly confirm the diversity of pressure

    distributions reported in the literature for SCC.

    Bay-Adelaide, Toronto

    Measurements were carried out on several floors of the core structure of the 50 storey

    Bay Adelaide tower.

    Large jump (self climbing) form for the core structure. Outside core dimensions 33m x

    20m (100 feet x 65 feet). Various wall thicknesses but pressures measured on 350 mm (14 ins)

    and 600 mm (24 ins.) walls. Height of lift 4 metres (13 feet).

    Very large pour of some 380 cubic metres (42 x 9 cubic metre trucks) lasting 4 or 5

    hours. South wall concrete placed by pumping and north wall by bucket

    550

    600

    650

    700

    0 50 100 150

    Slu

    mp

    Flo

    w (

    mm

    )

    Time (mins)

    Slump Flow Sept20/06 Peterborough Trial 3 - Sept 20, 2006, Concrete temperature 21C

    -20

    0

    20

    40

    60

    80

    100

    10.0 10.5 11.0 11.5 12.0 12.5 13.0

    Time (Hour + Decimal)

    Lat

    eral

    Pre

    ssu

    re (

    kP

    a)

    Cell 13 (Hyd.Pres. 36.1 kPa)

    Cell 14 (Hyd.Pres. 63.5 kPa)

    Cell 15 (Hyd.Pres. 91.1 kPa)

    Cell 16 (Hyd.Pres. 98.7 kPa)

  • Typical results for the two instrumented wall forms are given below. Some small effect

    of wall thickness providing the rate of placements are the same logic would indicate the form pressure for thicker wall should be slightly larger.

    Bay Adelaide -- Decmber 10, 2007

    North Wall

    -20

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    17 17.5 18 18.5 19 19.5 20 20.5 21 21.5

    Time (Hours + Decimal)La

    tera

    l P

    res

    su

    re (

    kP

    a)

    Cell 6 - Bottom Cell 7 - Middle Cell 8 - Top

    Bay Adelaide -- December 10, 2007

    South Wall

    -20

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    18 18.5 19 19.5 20 20.5

    Time (Hours + Decimal)

    La

    tera

    l P

    res

    su

    re (

    kP

    a)

    Cell 9 - Top Cell 10 - Middle Cell 11 - Bottom

  • Lessons learned

    Discontinuous placement, by bucket or programmed interruptions of pumping, allows the

    concrete to gain shear strength, reducing the maximum form pressures. For formwork pressure

    purposes, the ideal admixture combination would produce a concrete that flows under agitation

    and immediately stiffens when agitation ceases. The SCC mixture design has to be done with

    care and admixtures can not be changed or substituted without diligent consideration. In addition

    changes to the water content of the aggregates can significantly affect the stability of the mixture

    and strict control for moisture compensation needs to be instituted at the ready-mix plant.

    Testing for production, mixture selection/qualification and formwork selection must be done in

    concert and concrete control parameters must be established to ensure compliance.

    Suggested lateral Pressure Equation

    The following equation was developed to fit the field measured lateral pressures. Note the

    experimental results were limited in that the maximum concrete head was 4 metres (14 feet).

    SI units

    2/14/1

    400

    8/1

    max18

    50

    60*

    5002

    cT

    tR

    dwP

    Pmax = limiting lateral pressure (kPa)

    w = unit weight of concrete (kN/m3)

    d = minimum lateral form dimension (mm)

    R = rate of placement (m/hour)

    Tc = concrete temperature (Celcius)

    t400 = time for slump flow to drop to 400 mm

    US units

    2/14/1

    400

    8/1

    max

    90

    60*

    205

    FT

    tR

    dwP

    Pmax = limiting lateral pressure (psf)

    w = unit weight of concrete (lbs/ft3)

  • d = minimum lateral form dimension (ins)

    R = rate of placement (ft/hour)

    TF = concrete temperature (Fahrenheit)

    t400 = time for slump flow to drop to 400 mm (16 ins)

    The figure below shows the comparison between the field measured pressures and the above

    equation.

    Comparison of Measured Predicted Lateral Pressures

    (100 kPa = 2100 psf)

    0

    20

    40

    60

    80

    100

    0 20 40 60 80 100

    Me

    as

    ure

    d P

    res

    su

    re (

    kP

    a)

    Calculated Pressure (kPa)

    Limiting Pres.

    Hydrostatic Pres.

    4 metres

    3 metres

    2 metres