8/11/2019 Formwork Digest
1/58
8/11/2019 Formwork Digest
2/58
8/11/2019 Formwork Digest
3/58
8/11/2019 Formwork Digest
4/58
8/11/2019 Formwork Digest
5/58
8/11/2019 Formwork Digest
6/58
8/11/2019 Formwork Digest
7/58
8/11/2019 Formwork Digest
8/58
8/11/2019 Formwork Digest
9/58
8/11/2019 Formwork Digest
10/58
8/11/2019 Formwork Digest
11/58
8/11/2019 Formwork Digest
12/58
8 V1 N1 May 2013
Formwork - Future Approach in India
It is not the strongest of the species that survives, or the
most intelligent. It is the one that is the most adaptable tochange that does it. - Charles Darwin.
Winds of change are blowing across every sphere of
construction in India. Same is the case with the formwork
and scaffolding systems in India. An approx. data on
formwork derived from the cement consumption in India
reveals that in India, formwork executed is around 750
million Sqm. out of which formwork executed using system
or engineered formwork hardly constitutes around 10%. It
is a known fact that formwork constitutes around 6%-8% of
the cost of concrete and 60% of the time of the structure. So
it is the right time an emphasis is laid on the right approach
on formwork for the future of the Indian construction.
With the increased growth in high-rise construction,
demanding infrastructure projects shaping up the metros
and tier 2 cities in India, the questions that arise now
are - Are the formwork systems available in India today
sufficient enough for executing such demanding projects?
Are the major formwork suppliers across the world that
have entered the Indian market able to give end to end
solutions to the Indian construction industry? Though the
utilisation of formwork has gone up by leaps and bounds
over the years our approach is still old fashioned. Have we
modernized our approach is still a question to be answeredby all the stake-holders.
This paper deals with focal points which will shape up the
Future Approach of Formwork for the Indian construction
industry. They can be broadly defined as Value Chain Linkage,
Safety Integration in Formwork, Comprehensiveness in
Quality, Standardisation, Green concept and sustainability
and finally the Costing of Formwork.
Value Chain Linkage
Formwork is one of the vital links in the total Value Chain,
the other two links being reinforcement and concrete. At
present, the Indian construction industrys major concernis the stringent timelines (duration) in the projects. With the
clients demands increasing day by day, the construction
companies focus is mainly on the floor to floor cycle time
to meet the timelines of the projects. But to achieve this, a
good engineered formwork system is alone not a solution.
A good formwork system by itself might not give all the
desired results; it only enables to reduce the timelines in
one of the vital links of the value chain. There should be
a wholistic approach considering the other two links of
rebar and concrete. Also there should be emphasis on the
development of the skill levels of the supervisors, labour
and the approach of the engineers rather than just on the
A.L.Sekar, B.Murugesan and C.N.V.S. Rao
Larsen & Toubro Ltd
Focus Formwork Systems
8/11/2019 Formwork Digest
13/58
9V1 N1 May 2013
selection of the right system. To put it in a simpler way,
our future approach while selecting a formwork system
should be such that it should integrate the necessary
features to support the other two links of the value chain
i.e. rebar and concrete which will enable us to carry out
these two activities also in a fast track manner. Only sucha comprehensive approach would yield the desired results
and help us to meet the demands of the customers.
Safety
Safety in formwork is another major concern today
especially in high-rise construction and large infrastructure
projects like metros, flyovers, airports etc. It is a known
fact that in India, Safety levels are yet to catch up to the
International Standards. There is a lot of pressure on
the Indian construction companies today to improve the
same by the Govt. of India, Foreign Investors and also the
increased number of PMCs (which are basically reputedMNCs). Safety cannot be treated as a separate entity,
rather it should be an integral part of the formwork system.
Formwork & scaffolding being the major contributors to the
safety in construction sites as they are also used for the
rebar and concreting works, it is time we pay proper heed
to how these have to be integrated with safety so as to
ensure the overall safety at sites. The various areas of safety
that we need to focus and integrate with formwork are:
- Access (both Vertical & Horizontal)
- Working platforms
- Lifelines and Safety Catch Nets- Erection & Dismantling of Formwork
- Storage & Maintenance of Formwork
- Simple Tools & Tackles
- Design and Engineering
So our future approach when choosing a formwork system
should address the above aspects and how they are
integrated into the formwork system. Only then, in our way
forward, we will be able to live upto the expectations of
the customers and also reach to the level of International
Standards.
Quality
Quality of the finished product is another aspect resulting
from a good and efficient formwork system. For achieving a
good concrete surface, the right kind of sheathing member
should be used in any formwork system, depending on thetype of finish demanded by the client. Invariably, plywood
has been the most commonly used sheathing member
world-wide and has yielded the best results till date with
regards to form finish. Nevertheless considering other
factors in choosing the right kind of formwork system
for the right job, today aluminium formwork has started
penetrating and off late captured the market rapidly with a
share of about 15% of the overall formwork value in India.
Due to its easier handling, good quality surface finish,
repeatability and durability, and best suited for high-rise
residential buildings which are the trend today, aluminium
in future might be a strong contender as far as sheathingis concerned in formwork. Apart from this, to achieve a
good quality product, the formwork system should deal
with critical issues such as Grout tightness, Deformation,
Facilitating Concrete Compaction, Provision of Clean-out
doors and Box-outs etc. Only when all these issues are
addressed along with the selection of the right sheathing
member, a good quality product can be delivered. Looking
into the future, our approach in selection of the system
should keep all these aspects in view to deliver quality
products.
Standardisation
Standardisation of the various formwork systems is also an
aspect to introspect because we cannot afford to have too
many systems at sites which leads to lot of complications
in terms of usage as well as accountability. The formwork
systems should be standardized such that a single system
is adaptable to various structural elements and also across
various projects. Though it has its own limitations, still
standardization can be done to an extent which reduces
the number of components involved in a system, increase
efficiency of the components involved and the flexibility
in usage of these (in terms of sizing and detailing).
This automatically reduces the pain for the engineers /supervisors and also the labour who are the end-users
of the system and gives better results as they can easily
account for the materials and use them efficiently. In this
particular aspect, our future approach should be Using
less for more output through Innovative Solutions.
Green Formwork
Rapid industrialization, growth in population and urbanization
in the two previous millennia and in the current century
have not only taken a heavy toll on non-renewable natural
resources of the planet but also caused unprecedented
Focus Formwork Systems
8/11/2019 Formwork Digest
14/58
10 V1 N1 May 2013
rise in global warming. Most leading business houses
and industries across the world have adopted Corporate
Social Responsibility (CSR) as the roadmap of their current
and future business ethics and principles. Whether this
principle is adhered to while manufacturing of formwork
systems? A confident YES may not be forthcoming.Currently no importance is being given to this aspect of
Green Concept and Sustainability. Stepping into the future,
our approach should be Greener Formwork Systems to
do our part for the betterment of environment. The focus
here can be on some of the important parameters like
Energy Consumption, Wastage, Recycling and Depletion
of Natural Resources. If these aspects are dealt with in the
sourcing of raw materials, manufacturing of the products
involved in the formwork systems as well as utilisation
of the system as a whole, it helps in delivering Greener
Formwork Systems.
(Mobilisation delay, work front delay, delay due to shortage
of other resources & demobilization)
Also the associated costs like the upkeep and maintenance
can be dealt with a central approach by building it up in the
investment cost or with a localized approach to create asense of ownership for the sites using the formwork systems.
The above example clearly indicates that the life of
formwork plays a major role in the Costing of Formwork.
Formwork cannot be a scapegoat for inefficiency within
and across sites which revolve around these time-bound
methods of costing. However if the realistic costing is done
as per the cost incurred per use, it can help construction
companies in India to take a positive call on purchase
or hire of modern formwork systems and change their
approach in future.
Conclusion
Finally to conclude, Formwork Systems cannot be decided
just by suppliers alone as they might not think of all the
related elements in the value chain, instead it has to be
decided by the end-users and engineers who are the future
change-managers. And the guiding principle should be -
Formwork must be approached not in isolation, but in a
comprehensive manner to include the entire Value Chain,
Safety, Quality and Sustainability. Also the thrust should be
on realistic costing of formwork to enable viable usage of
Modern Formwork Systems.
Description Hire charges or WDV method(5% per month)
Cost peruse method
Investment Cost
Apportioned
9960 4800
Fixing and Removing
Cost
3000 3000
Upkeep and
Maintenance Cost
1000 1000
Total Cost 13960 8000
Costing of formwork
With the rapid growth in the construction industry,
introduction of modern formwork systems is essential to
meet the delivery requirements of the customers and at the
same time be competitive. However the modern formwork
systems come with a high-price tag. Hence costing of
formwork for a particular project is very critical for the
engineers. However different costing methods are used
by different contractors. Considering the factors like the
efficiency of formwork being linked to the succeeding &
preceding activities, idling at sites and poor planning; the
time-bound costing method (Written Down Value or Hire-
charges) ends up with higher formwork costs especiallyon materials for no fault of formwork. A small example
below gives a clear picture of how the time-bound costing
methods can be compared:
Sample Calculations of Formwork Costing for Aluminium
Formwork
- Cost of formwork - Rs. 16000 / Sqm. (say)
- Duration of the project - 10 Months (Only for Structure)
- No. of possible re-uses - 100 (say)
- No. of re-uses expected / month - 3
- Actual duration considering all delays - 20 Months (say)
Focus Formwork Systems
8/11/2019 Formwork Digest
15/58
8/11/2019 Formwork Digest
16/58
8/11/2019 Formwork Digest
17/58
8/11/2019 Formwork Digest
18/58
8/11/2019 Formwork Digest
19/58
8/11/2019 Formwork Digest
20/58
8/11/2019 Formwork Digest
21/58
17V1 N1 May 2013
Certain Safety Considerationsfor Formwork
F
ormwork, the temporary mould and support for fresh
concrete until the concrete is strong enough to support
its own weight and other construction loads, itself requiresa support called falsework. In many codes, formwork and
falsework together are called formwork structure or just
formwork - which last will be the terminology used in this paper.
The problem with formwork is that it is temporary. In many
under-developed and even some developing countries, the word
temporary is automatically associated with lack of need for
planning, design and care, and with neglect of appearance,
strength, and safety. As the owner pays only for the finished
permanent structure and not the temporary structure, least cost
(including cheapest labour and materials, and in the worst
case scenario, low compensation for accident and fatality
claims) are often the easiest way to cut costs on this non-
essential item.
In advanced countries however, it is recognised that most
accidents and in fact most fatalities and property damage
occur during the brief construction stage and not during the
long usage phase of a structure. The business case for safety
in these countries also has amply demonstrated the wisdom
of preventing or mitigating the effects of accidents as against
paying for large compensation and work disruption costs due
to accidents. This is exactly why hazards present in formwork
must be identified, and the risks arising from them must be
assessed and controlled.
In this paper, not being sufficiently familiar with Indian practices
in regard to formwork safety - except as a lay observer during
his visits to India - author will focus on his experience with
Singapore practices, in the hope that Indian professionals may
make their own comparisons and draw their own lessons for
local application.
Basic Safety Requirements
The basic safety requirement is set in the Singapore Workplace
Safety and Health Act of 2006 as the responsibility of every
employer, as far as is reasonably practicable, to protect every
employee from injury and ill-health at the workplace.
This aim of providing a safe place to work is achieved by
adopting guidelines provided by the Ministry of Manpower
and Workplace Safety and Health Council, including the
following:
- Risk assessment and control, before work starts [Ref.1].
- Safe Work Procedure for every activity at the workplace
which may involve risk.
- Permit to Work for all hazardous activities such as work at
height.
- Construction Reg. 2007, Sec. 22(2) reads: In a worksite,
every open side or opening into or through which a person
is liable to fall more than 2m, shall be covered or guarded
by effective guard-rails, barriers or other equally effective
means to prevent fall.
- Construction Reg. 2007, Sec. 63(2) reads: Any formwork
structure that (a) exceeds 9m in height; (b) consists of any
formwork which is supported by shores constructed in 2
or more tiers; or (c) consists of any formwork where the
thickness of the slab or beam to be cast in the formwork
exceeds 300mm, shall be designed by a P.E.
Figure 1 depicts formwork for a condominium block in
Singapore.
Hazards in Formwork
Hazards are potential dangers. Hazardous activities in
formwork design, erection, use and dismantling are as follows:
- Incorrect or incomplete formwork design
- Erecting frames and bracing
- Erecting bearers and joists
- Placing deck and beam formwork
- Moving around on formwork during rebar placement,
concreting, and curing
- Dismantling formwork
N. KrishnamurthySafety and Structures Consultant,
Singapore
Formwork Safety
8/11/2019 Formwork Digest
22/58
18 V1 N1 May 2013
In erection, use and dismantling phases, most activitiesinvolve following common hazards:
- Climbing up to or down from formwork, usually by ladders
- Working at height with unprotected edges on platforms
- Tripping and falling at level
- Falling through gaps and holes in formwork
- Falling from incomplete or badly designed formwork
- Hit by formwork components
- Carrying heavy loads
- Struggling with awkward shapes
- Fitting damaged connections and components
- Handling sharp objects and corrosive materials
- Working in harsh (sunny, cold, wet, windy, dusty, noisy
etc.) environments
- Uneven, sloping and cramped work surfaces
- Overloading of formwork
In addition to these, dangers may also arise from inadequate
supervision, material flaws etc. To cover all these in a paper
would be an onerous task. The author will therefore focus only
on the following factors in this paper:
1. Some design considerations,
2. Working safely at height, and,
3. Manual handling of heavy loads.
Some Design Considerations
Factor of safety
India has its own design norms, and they are likely to be world
class. Problems may arise during implementation, and in the
safety culture that may be prevalent in various enterprises.
Author has seen some excellent formwork in big projects in
cities. (Fig. 2.)
But more commonly, especially with formwork for residential
and office building floors, a common sight that greets one is a
forest of supposedly vertical and straight but actually twisted,
bent, de-barked tree branches leaning at all angles some as
much as 20 degrees to the vertical, supporting the beam and
slab formwork. (Fig. 3.)
Other Asian countries also use natural timber for falsework.
In the Far East, bamboo is common, with the advantage that
bamboo is straight and nearly uniform in size along its length,
In India we use all kinds of timber which are twisted, bent, and
non-uniform along their length.
Having just finished an assignment on the formwork code
committee in Singapore, author is very conversant with the
need for strict and conservative design for formwork and other
temporary structures, as already mentioned in the Introduction.
Fig. 1. Author with site engineers in front of extensive formwork for acondominium construction in Singapore.
Fig. 2. A recent picture taken by author in India.
In the past, load factors of 1.5 were commonly used for
falsework design. Often wear and tear in use, and poor field
conditions of connections and erection encroached into this
factor, and in certain cases resulted in accidents involving
injuries including fatalities and property damage.
Formwork Safety
8/11/2019 Formwork Digest
23/58
19V1 N1 May 2013
Current Singapore Formwork Code [Ref. 2] stipulates a
minimum Load safety factor of 2.0 to be applied to all
designs by whatever method, and for all testing, so that the
designed or tested capacity is at least twice the maximum
requirement under the worst combination of loadings.
What is the corresponding design requirement for Indian
construction with such timbers?
Inclined shores
There is another aspect of such ad-hoc arrangement of shoresthat raises the question: If formwork has to be approved to
satisfy design criteria, how are sloping shores handled?
An inclined member AB at an angle to the vertical subjected
to a vertical compressive force V will develop a horizontal
component H, which would be 18% and 36% of V for angles
of 10 and 20. This horizontal component will tend to increase
the angle . (Fig. 4.)
Then, how come we have not had all inclined members slide
and fall down? That is because the horizontal components
have been successfully resisted, as at top they may be nailed
to some boards, and at bottom the friction and random
projections will usually prevent sliding.
If in a particular case everything is fine when erected, but
when wet the friction coefficient vanishes, and/or when the
load increases the slide resistance is inadequate, disaster
may strike.
Smart people may think that they can cancel out the slope
effects by arranging adjacent members AB and AB sloping
in opposite directions. But there will still be the same horizontal
separating force H at the top and bottom, and if the resistance
to opening up at top and bottom is not enough, woe be unto
the formwork! (Fig. 5.) Of course, someone who knows what
is happening can easily take care of this problem by two
simple ties at or near AA and BB - but this is not much in
evidence.
Sloping shores may be the fast and cost-effective way to use
available poles without cutting them down to required size. It
may also be true that they have worked well for decades, and
the permanent structures that emerge from these temporary
structures of whatever shape, have been finished beautifully.
The point author is making here is that any structural resistance
to failure is not by design, but by chance. Contractors have
just been lucky, and professionals have not even considered,let alone provided for the horizontal component. That they
survive is because of modifications by trial and error. Potential
for failure continues to exist.
Author shows special concern about this sloping shore,
because in a court case in which he was involved, he
demonstrated that it was exactly such an undesigned inclined
strut - although it happened to be a straight steel rod - that
might have contributed to the formwork failure.
In this day and age, when India is contributing globally to the cyber
era and space effort, engineers should be a little more scientific,
Fig. 3. A common sight?
Fig. 4. Forces on an inclined prop. Fig.5. Props sloping opposite ways.
Formwork Safety
8/11/2019 Formwork Digest
24/58
20 V1 N1 May 2013
contractors a little more professional, and the owners who
pay for all this a little more considerate of essential expenses
in what they do, at least in the interests of ultimate structural
safety, if not for the sake of appearance.
Working Safely at HeightWorking at height has been the most hazardous activity all
over the world from time immemorial, and continues to attract the
maximum number of accidents and the maximum number of
fatalities. There are many ways in which safety may be ensured
while working at height [ Ref. 3], as follows:
A. Guardrail and toeboard (Fig.6A)
B. Work restraint, attachment to lifeline (Fig. 6B)
C. Retractable lifeline (Fig. 6C)
D. Auxiliary scaffolding (Fig. 6D)
E. Safety net below (Fig. 6E)F. Safety harness (Fig. 6F)
In providing risk control against falling from height, collective
control for all workers (A, D, or E) is better than individual
control (B, C, or F); fall prevention (A, B, C, or D) is better
than fall arrest (meaning termination of a fall before hitting
the base) to reduce the effects of fall impact after one has
fallen (E or F).
In terms of hierarchy of safety then, A or D is the best, and F is
the worst. The full-body harness (E) also comes with a number
of other auxiliary requirements for effective deployment,
including proper fit, sufficient fall distance, strong anchorage,
and prompt rescue. [Ref. 4]
All these requirements are mandatory according to the
Singapore Code of Practice for Working Safely at Height. [Ref. 5]
Manual Handling of Heavy Loads
In formwork - in common with most construction and factory
activities - regularly carrying loads larger than about 25kg is
an insidious risk, not sudden and dramatic like falling from
height, but slowly causing musculoskeletal disorder (MSD)
and escalating to permanent damage of the spine over a period
of about an year.
Musculoskeletal disorders (MSD) are among the most commonworker complaints in the West. In Asia and other under-
developed countries however, it is not reported as much or taken
as seriously, possibly because natives of these countries
are more pain tolerant than citizens of the more developed
countries, or because management will not do anything about
it, or both. It may also be that both management and workforce
do not realise that what starts as a little persistent discomfort
can escalate into a permanent painful problem. In any case,
Fig. 6. Safeguards for working at height.
Formwork Safety
8/11/2019 Formwork Digest
25/58
21V1 N1 May 2013
most do not recognise it as a problem, and even workers who
experience it resign themselves to it as their lot in life, enduring
lifelong discomfort if not suffering as a consequence.
So workers regularly carry heavy loads over long distances
or keep doing repetitive physical activity; supervisors and
bosses let them, expect it from them, and even order them to
do so. The reason is simple: Labourers (by very name) have
always been doing it. If they dont, who will? They are paid for
it, arent they? We are not forcing them against their will!
This topic comes under Ergonomics the science of work
posture. Authors recent paper [Ref.6] covers many aspects
of construction ergonomics.
Why is this important? What do we do about it? The answers
are not simple. It becomes a matter of safety culture in a society,
the concern of the more powerful groups of people for the
weaker and less fortunate sections of society. Author hopesthat once he explains his stand, professionals will rethink about
how we are using or abusing our fellow human beings.
Many do not know that each kilogram of weight we bend and
pick up and carry in front of our body develops a force of
about 12kg on our low back muscle and bone. (Fig. 7.)
So a 50kg cement bag will put a load of 600kg on the back
of a worker. An average Asians back is designed by nature
to carry a maximum force of about half that (after allowing for
the force imposed by our own torso weight), which means
that nobody should be carrying more than 25kg on a regular
basis.
Australia, where the average person would be larger in size
and stronger than Asians, legislated a few years ago that no
worker should carry more than 20kg routinely. UK had done
likewise a few years earlier when their workers complained
about 40kg hollow concrete blocks.
Singapore recommends a limit of 25kg for worker loads.
Author is not sure about any limitations mandated in India, but
purely on humanitarian grounds he appeals to employers not
to burden their workers with more than 25kg in their normal
work.
If any activity requires lifting and movement of larger loads,
mechanical aids like trolleys may be provided for moving
the heavier weights around; two or more workers may be
deployed to lift them on to trolleys, or carry them for short
distances. Even the simple expedient of rotating the task
between different workers would reduce exposure to risk tomore tolerable levels. Proper procedure to lift heavy loads by
squatting and getting up with the load is also easily learnt.
Needless to say, this analysis and recommendations for
this particular hazard, apply to white collar non-construction
workers too, such as office and lab assistants.
Conclusion
Author has highlighted a few of the hazards in formwork
design, erection, use and dismantling with which he has
personal experience in Singapore. Not all the hazards may be
perceived as equally critical in India. But in a nation committedto democracy and concern for all citizens, the risks described
and the solutions proffered by the author may serve to trigger
improvement of overall safety culture.
References
1. Krishnamurthy, N., Introduction to Risk Management,(Self-Published), Singapore, May 2007, 86p, ISBN: 978-981-05-7924-1.
2. SS580:2012 (ICS 91.080.99), Code of Practice for Formwork(Formerly CP23), SPRING, Singapore, Nov. 2012, 40p.
3. Figures 5A to 5E sourced from Falls from height during the
floor slab formwork of buildings: Current situation in Spain, byJose M. Adam, Francisco J. Pallars, and Pedro A. Caldern,Copyright 2009 National Safety Council and Elsevier Ltd.
4. Krishnamurthy, N., Full Body Harness - Blessing or Bane?, The
Singapore Engineer, Magazine of the Institution of Engineers,Health and Safety Engineering issue, August 2012, p. 18-22.
5. WSH Council, Code of Practice for Working Safely at Height,Workplace Safety and health Council, Singapore, October 2009,50p.
6. Krishnamurthy, N., Ergonomics at the Construction Sites, TheSingapore Engineer, Magazine of the Institution of Engineers,Health and Safety Engineering issue, February 2013, p. 20-27.Fig. 7. Forces on vertebrae
Formwork Safety
8/11/2019 Formwork Digest
26/58
22 V1 N1 May 2013
Formwork, Insulation, Wall thicknessand Fly Ash: Do They Affect
Concrete Maturity?
Concrete is the most widely used construction material
and its formability is one very important property.
Several different types of formwork are available in
the market. One way of classifying them is based on whether
they are stripped or not: (1) conventional formwork and (2)
stay-in-place (SIP) formwork made using different materials
such as steel, PVC (poly vinyl chloride), FRP (fiber-reinforced
polymers), EPS (expanded polystyrene), etc. Typically, wood
formwork is used to form concrete. However, the amount of
wood that can be harvested has been reduced, increasing
the cost and reducing the availability of wood. In addition, it
is environmentally advantageous to decrease the amount of
wood needed in construction.
New concrete forming technologies designed to reduce
wood consumption include reusable and SIP formwork.
After being used, reusable metal and wood forms must
be removed, cleaned, transported and then stored. These
systems limit design versatility since they generally come
in large, flat panels. Unlike traditional formwork that are
stripped after concrete has gained enough maturity, the SIP
forms remain an integral part of the structure; some even
provide structural strength and ductility (Kuder, Gupta et al.
2009), some provide higher R value and some just provide
a finished surface. Some forming systems such as Insulated
Concrete Forms (ICF) increase the insulative properties and
R value of the concrete walls and some SIP systems also
integrate insulation in the forming system. However, the effect
of such highly insulated walls on concrete hydration at early-
ages is not fully understood. One such category of SIP forms
are the plastic forming systems that are also more versatile
than wood and metal because various shapes can be easilymanufactured given its flexibility.
Since the SIP forms are not stripped, hence never exposing
the surface of concrete, it is very important to ascertain
that concrete in the forms has met or exceeded the project
specifications. One such type of forming system is a SIP
system that utilizes PVC panels and connectors as formwork
(Octaform Systems Inc, 2009). This forming system can be
used with and without insulation and its effect on the maturity
of concrete is not fully understood.
On the material side, fly ash is a commonly used Supplementary
Rishi Gupta1and Katie Kuder21Faculty & Program Coordinator, Department of Civil Engineering,
British Columbia Institute of Technology2Assistant Professor, Dept. of Civil and Environmental Engineering,
Seattle University
Use of different forming material, insulation, and stripping time can significantly affect the maturity and hence the strength gain ofconcrete within such forming systems. This information can be vital in determining the stripping time of scaffolding and formwork.
In this project, maturity and compression tests were performed on specimens (simulating scaled-down walls) formed using a PVCstay-in-place (SIP) forming system with and without insulation. These findings were then compared to data obtained from wallsformed by wood formwork, which is the material typically used in the field. The various parameters studied in this project werewall thickness, type of forming material, insulation, and addition of fly ash. Results indicate that with an increase in wall thickness,the peak temperature and the temperature development index (TDI) increase proportionally. TDI is defined as the area under thetemperature versus time curve measured from the dormant temperature to the peak temperature. The data show that the proposedTDI is a good indicator of the extent of the hydration reaction, and with further research the relationship between temperaturedevelopment and strength gain of concrete could be clearly identified. Both wood forming when compared to the SIP system, andinsulated systems when compared to un-insulated systems, increase the peak temperature and TDI. Use of fly ash in concreteresults in a lower temperature peak and TDI and a delay in reaching peak temperature. However, use of concrete containing flyash in insulated SIP systems has a higher TDI than a conventional concrete mix formed in wood forms, indicating better concrete
maturity at the same age.
FormworkResearch
8/11/2019 Formwork Digest
27/58
23V1 N1 May 2013
Cementing Material (SCM) which enhances the fresh
properties of concrete including increased workability
(Mindess, Young et al. 2003; Malhotra 2006; Mehta 2009).
High volume fly ash contents are now replacing cement
because (1) this results in lower consumption of cement,
hence reducing the energy required to produce cement andalso reducing the associated green house gas emissions,
(2) production of many self consolidating mixes require high
contents of fly ash, and (3) this results in cost-savings and is
a more sustainable process since an industrial by-product (fly
ash) is now being utilized which otherwise would end-up in a
landfill. However, addition of fly ash can decrease the rate of
the hydration reaction, negatively impacting the construction
process as the stripping of forms may be delayed. The effect
of using fly ash in concrete on the maturity of concrete was
studied in this project. During the hydration reaction, heat is
generated and released to the surroundings; the rate of the
reaction is proportional to the heat generated. The dissipationof this heat of hydration to the environment will depend on
the type of forming material used, thickness of the concrete
mass, and use of insulation (Khan, Cook et al. 1998; Wang,
Zhi et al. 2006). The effect of using insulation, wood or a PVC
SIP system on the maturity of concrete was studied in this
project. The maturity of concrete was evaluated by calculating
a Temperature Development Index (TDI), which is described
later.
The TDI is a close function of the hydration process and hence
it is important to note the different stages of the hydration
process. The first stage is the rapid heat evolution, which
occurs very quickly, the concrete then moves into the dormant
stage where the concrete is workable. The dormant stage
ends with the initial set and moves into the acceleration stage
as the reaction begins to accelerate. The concrete remains
workable until the final set where the greatest temperature is
achieved. During the deceleration stage, the reaction slows
down and temperature is reduced, bringing the concrete to
a steady state. A practical and effective way to evaluate this
hydration process is to monitor the temperature released by
the hydration reaction over time. The temperature data also
serves as an indicator of the rate of reaction, as temperature
increase is proportional to the heat generated.
Materials and Forming Systems
Concrete was prepared in a rotary drum mixer using Type I
cement (manufacturer- Lafarge), river sand, coarse aggregate
with maximum size 10 mm, Class F fly ash (Plant- Centralia),
and admixtures including superplasticizer (product- Glenium
3000 NS) and air entrainer (product- MB VR Standard). For
constructing the wood forms, lumber meeting the following
specifications was used: 23/32 inch DF-DF plywood, 48/24
span rated. The forms were oiled using a release agent (WD-
40) before pouring concrete.
A concrete mix design typical of what is used in field
construction with the PVC SIP system was used. The control
concrete mix had a water-cement ratio of 0.49 with 350 kg/
m3 of cement, 1160 kg/m3 coarse aggregate, 700 kg/m3 of
sand, dosage of 600 ml/m3 of superplasticizer and 200 ml/
m3 air entrainer. Another mix was prepared by replacing 40%of the cement with fly ash by weight.
PVC SIP Forming System
The SIP forming system used in this study is briefly described
below. This forming system is composed of PVC panels,
connectors, and braces that form cells. The panels are
typically 150 mm wide and come in variable heights. The
connectors, which are available in various widths, are placed
perpendicular to the panels and have openings that are
provided for placement of rebar and to allow the concrete
to flow through the wall. Figure 1 (a) shows one such cell
of the forming system braced with standard connectors, T-connectors, and the 45 braces to the panels. Insulation is
also available (Figure 1 (b)) for an increased thermal mass,
leading to higher energy efficiency.
The panels that make up the interior and exterior of the
formwork and can be curved to conform to the shape needed
for the specific application, such as an aquaculture tank
shown in Figure 2 (a). Once the vertical formwork has been
assembled and raised, wood bracing is used, as shown in
Figure 2 (b). This bracing is similar to the bracing required
when the wood formwork is used and is removed once
concrete within the forms has gained sufficient strength.
Figure 1. Components of SIP formwork cell (a) Top vies of cell containing allcomponents, (b) Schematic of cell with insulation (Octaform 2009)
Specimen Preparation
To compare the influence of PVC SIP formwork on the heat of
hydration (maturity/temperature release), the results from PVC
SIP system were compared to wood formwork. The SIP test
wall configuration, shown in Figures 3 and 4, was designed to
have three rectangular cells. This configuration was chosen
so that the two extra cells on either side of the middle cell
would eliminate the temperature effects of closeness to the
end of the wall (boundary effects). The sides of the end cells
were filled with wood pieces to prevent concrete from flowing
FormworkResearch
8/11/2019 Formwork Digest
28/58
8/11/2019 Formwork Digest
29/58
25V1 N1 May 2013
Temperature measurements
Before the concrete was mixed and poured into the formwork,
the data acquisition system was started to obtain the initial
ambient temperature. The thermocouple wires were then
placed in the concrete as described earlier. Temperature
readings were collected at a rate of 3 readings per minute,
each reading being an average of 100 scans. Once the test
had run for an amount of time determined by previously
conducted preliminary tests indicating complete hydration,
the data acquisition system was stopped and the data was
saved for analysis.
Compression testing
Cast cylinders
To determine the compressive strength, cylinders (100 x 200
mm) were cast according to ASTM C 31. Cylinders were de-molded after 24 hours and moist cured for 56 days. Testing
was done using a Riehle hydraulic testing machine with a 300
kip load cell. Specimens were loaded by displacement-control
at a rate of 0.085 mm/min. The data acquisition system was
set up to measure the applied load at a rate of 25 readings
per second, each reading being an average of 1000 scans.
Four cylinders were tested for each mix type (NC and FA).
Neoprene caps were used in lieu of capping or grinding of
cylinders.
Cores
To study the effect of the PVC SIP system and insulationon the concrete compressive strength, drilled cores were
extracted after monitoring the temperature for 36 hours.
This was also done to determine if there was any correlation
between temperature and strength development. Cores
were taken from various 200 mm walls and subjected to
compressive testing equipment as described above. The
various configurations from which were extracted are shown
in Table 2.
Results and discussion
Data averaging
The temperature data were recorded from all six
thermocouples over time. After analyzing the data, it was
noted that the temperature readings from the five embedded
thermocouples did not vary significantly with the location of the
thermocouples; therefore the average curves were deemed
suitable for analysis. This finding is illustrated in Figure 7. Note
that the bottom and the top thermocouples reach the second
lowest and the highest temperatures, respectively, even
though these were located approximately the same distancefrom the center of the wall.
Formwork type Concrete type Insulation
SIPNormal Present
Fly Ash Absent
WoodNormal Present
Fly Ash Absent
Table 2: Various specimen types used for extracting core samples
Each wall was cored with a concrete coring machine as
shown in Figure 6, with a 100 mm diameter drill. Three cores
were taken from each wall: one from the middle cell, and
one from each of the two side cells. Each 100 mm diameter
core was then cut down to a height of 200 mm and tested for
compressive strength.
Figure 6. Coring 100 mm diameter sections for compression testing from SIPformed specimens
Figure 7. Typical plot: temperature versus time as a function of thermocouplelocation for a 200 mm thick wall formed with wood
Temperature Development Index (TDI)
From the averaged data, the peak temperature (Tp) was
determined along with the time at which the peak (tp) occurred.
Figure 8 presents a typical plot of average temperature versus
time, indicating the Tp and tp. Throughout the testing program,
FormworkResearch
8/11/2019 Formwork Digest
30/58
26 V1 N1 May 2013
the ambient temperature in the lab fluctuated, resulting in
varying initial temperatures from specimen to specimen. This
situation would also be typical of a construction site where the
ambient conditions will be different from day to day. Figure 8
presents the average temperature versus time for two tests
performed during primary testing. The ambient temperaturerecorded during each test is not presented in the plot for clarity.
The variation in ambient temperature was less than 1C in
each test and hence the effect was considered negligible.
Although it was expected that the 100 mm FA specimen
would achieve a lower peak temperature than the 200 mm FA
specimen because it contained a smaller volume of concrete,
the results show just the opposite. As research has shown,
ambient temperatures affect the rate of the hydration process
(Wang, Zhi et al. 2006); warmer temperatures speed up the
hydration process and contribute to higher peak temperatures,
while colder temperatures slow down the hydration process
and contribute to lower peak temperatures. Because of theeffect of ambient temperatures on the hydration process,
and that ambient temperatures were not controlled during
testing, there was no linear relationship between hydration
and ambient temperature. Therefore this experimental project
cannot directly account for this effect.
the 100 mm specimen with fly ash (Table 3). Refer to Figure 8
for identification of critical points for the temperature analysis
and an illustration of the areas calculated. After analysis it
was seen that the 100 mm FA specimen (shown in Figure 8)
achieved a smaller A1 calculation in comparison to the larger,
200 mm FA specimen. The area calculation was conductedfor each test and the areas were compared. These values
were used as an indication of temperature development
during hydration. The A1 value representing temperature rise
and maturity immediately after the dormant stage was found
to be more relevant than that of A2 and is used extensively
throughout this report. The authors have called this value the
Temperature Development Index (TDI or simply A1). The
results from these comparisons are discussed later.
Figure 8. Average temperature versus time curve for 100 and 200 mm thickwalls
To minimize the effect of the ambient temperature during the
analysis, it was proposed that the area under the hydration
curve be calculated and analyzed. This area was split intotwo smaller areas: A1 being the region bound by the initial
minimum temperature (indicating the dormant period) and
the peak temperature and A2 being the region bound by
the peak temperature and the final temperature at 30 hours.
Preliminary tests (not reported here for maintaining brevity)
had indicated that the internal temperature in specimens
more or less dropped to ambient temperature after 30 hours
(Lowrie, Sommer et al. 2007). In certain specimens the peak
temperature was very similar to the ambient temperature and
sometimes lower than that recorded at 30 hours. In such
cases, the value of A2 would be negative as in the case of
Figure 9. Average temperature versus time for 100, 200 and 300 mm thick
walls formed with SIP formwork with normal concrete (NC) and 40% fly ashreplacement (FA)
Wall TypePeakTemp
(C-hr)
Time atPeak(hrs)
A1 (TDI)(C-hr)
A2(C-hr)
Normal
Concrete
100 mm
200 mm
300 mm
24.08
27.79
29.69
11.9
13.3
15.0
13.91
25.93
40.75
22.36
30.38
60.80
Fly Ash
100 mm
200 mm
300 mm
22.07
25.81
27.39
13.0
15.5
16.4
5.72
24.04
30.08
-0.19
28.95
36.79
Table 3: Temperature at peak and A1 (Temperature Development Index, TDI),
A2 for the SIP system
Wall TypePeakTemp
(C-hr)
Time atPeak(hrs)
A1 (TDI)(C-hr)
A2(C-hr)
Normal
Concrete
100 mm
200 mm
300 mm
25.31
29.12
29.85
15.0
13.5
15.7
24.12
38.71
53.71
34.07
60.93
76.99
Fly Ash
100 mm
200 mm
300 mm
24.09
24.02
26.11
12.1
16.7
18.1
8.44
22.65
32.47
3.99
29.67
37.85
Table 4: Temperature at peak and A1(Temperature Development Index, TDI),
A2 for the Wood formwork
FormworkResearch
8/11/2019 Formwork Digest
31/58
8/11/2019 Formwork Digest
32/58
28 V1 N1 May 2013
used. In general, the
addition of fly ash appears to slow the hydration process,
lowering the total amount of temperature developed, and
cause the specimen to reach a lower peak temperature at a
later time for both the wood and SIP walls. In the case of the
200 mm SIP fly ash specimen, a slightly higher temperature
development was achieved in comparison to the wood
formed specimen. When varying the composition, there is a
greater difference in the TDI for the wood walls, an average
of a 49% difference, than for the SIP walls, with an average
of a 31% difference. This may indicate that the SIP system
may contain more moisture and develop more cumulative
temperature relative to wood formwork during the hydration
process when fly ash is used.
In general, the inclusion of insulation for both wood and SIP
systems increases the peak temperature during hydration, and
contributes to greater temperature development. In generalthe peak temperatures for specimens containing insulation
occur later in comparison to specimens without insulation.
For the specimens tested, the inclusion of insulation with
the SIP system appears to have a more significant effect on
temperature development and peak temperatures achieved
in comparison to the wood system. This finding may be a
result of the wood system itself providing insulation and the
additional insulation having little effect. It is interesting to note
that the SIP system used with the fly ash mix and insulation
achieved a greater temperature development than the wood
forming system used with the normal concrete mix and
no insulation. These results are an indication that the SIPsystem used in combination with fly ash and insulation more
positively contributes to the hydration process in comparison
to standard wood forms used with the normal concrete mix.
The compression test results for cored specimens along with
the analyzed temperature data is presented in Table 5. In
comparing the wood and SIP formed walls, the wood formed
walls generally achieved a higher temperature development
than the SIP formed walls for all size walls. To understand
this correlation, the R-Value of each formwork material was
determined. The R-Value for the PVC SIP is reported as 0.60
(Octaform Systems Inc., 2009) while that for 20 mm ()
plywood is reported as 0.90 (TECO, 2010). The lower R-Value
of the SIP indicates that it is less resistant to thermal change
than wood, and hence may explain why it achieved lower
temperature development overall in non-insulated systems.
Compression Testing
Cast cylinders: When 40% cement was replaced with fly ash,
Sample
Compressive
Strength (fc) (MPa)
Standard
Deviation (MPa) TDI / A1 (Chr)
Avg. Peak Temp
(Tp) (oC)
Avg.Time at
Peak (tp) (hrs)
Normal ConcreteSIP 17.86 4.83 42.24 29.45 14.34
Wood 20.13 7.38 43.50 31.00 11.84
Fly AshSIP 12.07 2.69 24.31 25.42 17.87
Wood 12.41 1.72 34.53 26.57 17.99
NC InsulatedSIP 15.05 0.92 64.01 32.54 16.00
Wood 12.51 7.52 44.52 28.80 17.33
FA InsulatedSIP 20.40 0.35 51.68 35.50 12.80
Wood 5.85 0.24 30.25 28.89 14.87
Table 5: Compressive strength data from cored samples (36 hours after casting) and the corresponding temperature data
Figure 12. Average thermocouple temperature versus time for walls formedwith SIP formwork with NC and FA with and without insulation (Insul)
Figure 13. Average thermocouple temperature versus time for walls formedwith wood formwork with NC and FA with and without insulation (Insul)
FormworkResearch
8/11/2019 Formwork Digest
33/58
29V1 N1 May 2013
the compressive strength decreased from an average of 32 +
3 MPa to 29 + 6 MPa at 56 days.
Cores: Cores were taken from four 200 mm walls and four
250 mm walls with 50 mm insulation (and 200 mm concrete):
two each from SIP NC, SIP FA, Wood NC, and Wood FA.
These cores were tested and averaged for each wall. The
compression testing data is summarized in Table 5. It should
be noted that the compressive strengths reported in Table 5
are at an age of 36 hours and hence significantly lower than
that measured for cast specimens tested after 56 days. One
of the other methods of comparison for these walls was the
TDI (A1 in Table 5), which has been explained already.
Treating the compressive strength for FA insulated wood
specimen as an anomaly, a reasonable correlation between
fc measured for cored samples and TDI was observed.
This correlation existed only when the same concrete type
and formwork configurations were considered. The generaltrend shows that when the TDI increases there is an increase
in compressive strength. However, when comparing the
insulated walls to the non-insulated walls, similar compressive
strengths were measured for dissimilar TDIs. This may be
attributed to limited number of cores and the high standard
deviation observed in the compressive test results; as high
as 60% for the NC insulated wood specimen). Establishing
a straightforward correlation between fc and TDI was difficult
also because TDI corresponded to thermal activity up to
peak (time to peak ranged between 11 and 18 hrs), whereas
all coring occurred at 36 hours, hence making a direct
comparison more difficult. Further research is necessary toclearly establish this correlation.
Conclusions
1. The proposed TDI was an effective method of analyzing
the temperature data. TDI could be effectively used to
minimize the effect of different ambient conditions and to
capture the hydration that occurs immediately after the
dormant hydration stage.
2. The wood forming system contributes to higher peak
temperatures, which occur later when compared to the
PVC SIP forming system. The extent of hydration processdoes appear to be greater in the wood system for a normal
concrete mix. This corroborates well with the R value for
both forming systems.
3. The SIP system used in combination with a high volume
fly ash mix and insulation achieved greater temperature
development in comparison to the non-insulated wood
forming system used with normal concrete. These results
indicate that the insulated SIP system used with fly ash
more positively contributes to the hydration process in
comparison to the noninsulated wood formed system
used with the normal concrete mix.
4. Special attention is required to ensure strength gain before
stripping forms especially for thin wall cast using concrete
containing high volume fly ash.
Further Research
In addition to wood and one type of SIP formwork, furtherresearch should be done to compare the effect of other
forming systems used in the industry on maturity of concrete.
In particular, larger wall sizes should be tested to better
simulate the conditions experienced in the field. Stripping
time variability should be incorporated into this testing. Validity
of TDI should be examined by conducting tests at extreme
ambient conditions to simulate colder winter climates and
warmer summer climates. Further research is suggested
to clearly establish the relationship between concrete
compressive strength and TDI by having a larger sample size
of cored specimens.
Acknowledgements
The authors would like to thank Octaform Systems Inc. for
sponsoring this project and for providing the materials and
technical expertise for this project. The authors would also
like to acknowledge the contributions of the Seattle University
senior design team that was comprised of Kristian Lowrie,
David Sommer, and Nikki Wheeler.
References
- Khan, A. A., W. D. Cook, et al. (1998). Thermal Properties and
Transient Thermal Analysis of Structural Members During Hydration.ACI Materials Journal 95(3), 293-303.
- Kuder, K. G., R. Gupta, et al. (2009). Effect of PVC Stay-in-PlaceFormwork on Mechanical Performance of Concrete. Journal ofMaterials in Civil Engineering 21(7), 309-315.
- Lowrie, K., D. Sommer, et al. (2007). Effect of PVC Stay-In-PlaceFormwork on the Hydration of Concrete, Seattle University: 40.
- Malhotra, M. (2006). Reducing CO2 Emissions: The Role of FlyAsh and Other Supplementary Cementitious Materials. ConcreteInternational, 42-45.
- Mehta, P. K. (2009). Global Concrete Industry Sustainability: Tools forMoving Forward to Cut Carbon Emissions. Concrete International,45-48.
- Mindess, S., F. J. Young, et al. (2003). Concrete. Upper Saddle River,
Prentice Hall.- Octaform Systems Inc., Technical Guide (accessed October, 2009),
- TECO, Panel R Values (accessed June 2010),
- Wang, K., G. Zhi, et al. (2006). Developing a Simple and Rapid Testfor Monitoring the Heat Evolution of Concrete Mixtures for Both
Laboratory and Field Applications. N. C. P. T. Center.
Publishers Note:This paper was presented at the Proceedings of the One DaySeminar on Modern Formwork Systems for Building Construction Held in IITMadras, Chennai. The Masterbuilder was the official Media Partner for the aboveevent.
FormworkResearch
8/11/2019 Formwork Digest
34/58
30 V1 N1May 2013
Effect of Concrete Temperature andFormwork Width on Variation PressureFormwork of Self-compacting Concrete
1Amir Hosein Bakhtiarain,2Morteza Askari
1The Bsc. Student of Islamic Azad University, Iran2The Faculty Member of Islamic Azad University, Iran
The design of formwork systems for vertically cast elements
is controlled by the lateral pressure developed by the
flesh concrete. It is well established that concrete
consistency, method of placement, consolidation, type
of cement, temperature of concrete, maximum aggregatesize, head of concrete, pore water pressure, rate of
placement, and size and shape of the formwork have all
marked effect on the development of lateral pressure
[3-6-9].
Maxton (from Rodin [9]) studied the coupled effect of the
casting rate and concrete temperature on the lateral
pressure envelope for conventional concrete. Different
series of low-slump concrete mixtures placed at casting
rates varying between 0.6 and 2 m/h were investigated.
The concrete temperature varied from 4.5 to 27C.
Maximum lateral pressure was found to increase with the
increase in the casting rate and/or decrease in concrete
temperature. Irrespective of the tested parameters, the
pressure envelope was reported to be hydrostatic from
the free surface to a certain maximum value, and then
remained constant until the bottom of the formwork.
For formwork design purposes, ACI Committee 622 [2]
proposed the following design equations for column and
wall elements, both of which take into account the rate of
casting and concrete temperature: For columns:
In this article two complete programs about effect of concrete temperature, formwork width, on lateral pressure formwork of Self-Compacting Concrete are discussed. For considering effect of concrete temperature concrete mixtures which are built under 10-30c , are used and the result show that concrete temperature hasn't considerable effect on initial pressure (after casting finishing).But in time passing, pressure reduction is significant for surveying in formwork width effect, two columns with 200 and 920mmdiameter, are applied
For walls:
Where Pmax
: maximum lateral pressure, KPa
R: rate of casting, m/h
T: concrete temperature, C
H: head of concrete, m
Effect of concrete temperature on formwork pressure
For investigation of effect of concrete temperature onlateral formwork pressure, experimental research of Assad
[7] and his colleagues was used and described thosebelow:
Materials
The ternary cement contained 6% silica fume, 22% fly
ash, and 72% CSA Type 10 cement. The Type 30 cement,Type 10 cement, and fly ash had blaine specific surface
values of 600, 325, and 410m2/kg, respectively. The silicafume had a B.E.T specific surface of 20,250m2/kg.
Continuously graded crushed limestone aggregate withnominal size of 10mm and well-graded siliceous sand
Formwork Pressure
8/11/2019 Formwork Digest
35/58
31V1 N1May 2013
were employed. The coarse aggregate and sand hadfineness module of 6.4 and 2.5, bulk specific gravities of
2.71 and 2.69, and absorption values of 0.4% and 1.2%,respectively. Polycarboxylate-based high-range water-
reducing admixture (HRWRA) of 1.1 specific gravity and27% solid content was used. A high molecular weight
cellulosic-based material was employed for the VEA toenhance stability of mixtures proportioned with 0.40 w/cm.
Mixture proportion
As summarized in Table 1, the investigated mixtures were
prepared with 450 kg/m3of binder content and w/cm of
0.40.The effect of concrete temperature on lateral pressure
variations was evaluated by testing mixtures prepared at
10, 20, and 30 2C for the TER-10, TER-20, and TER-30mixtures, respectively. Ambient temperatures during the
sampling and testing were 14, 20, and 27C, respectively,to minimize heat loss of the tested concrete. The effect of
using Type 30 cement and set accelerating admixture onthe variations in lateral pressure was investigated, as they
have marked effect on the rate of cement hydration. The
dosage of the set accelerator was set at 1000 mL/100 kg
of binder. The T30-20 and TER-20-ACC mixtures prepared
with Type30 cement and set accelerating admixture,
respectively, were proportioned at 20 2C and testedat 20C ambient temperature. The VEA dosage was fixedat 260 mL/100 kg of binder, and the sand-to-total
aggregate ratio remained constant at 0.46 for all tested
mixtures. The HRWRA and AEA concentrations were
adjusted to secure initial slump flow of 650 15mm and
air content of 6 2%.
Instrumented column systems
Two experimental columns were used to determine the
lateral pressure exerted by plastic concrete. The firstcolumn measures 2800mm in height and 200mm in
diameter, and was used to evaluate pressure variations ofthe plastic concrete. The lateral pressure was determined
using five pressure sensors mounted at 50, 250, 450, 850,and 1550mm from the base. In order to enable the
evaluation of pressure variation up to the hardening ofthe concrete, a shorter column measuring 1100mm in
height and 200mm in diameter was used. Three pressure
sensors similar to those employed in the former columnwere mounted at 50, 250, and 450mm from the base.
Both experimental columns were made of PVC with asmooth inner face to minimize friction with the concrete.
Fabrication and testing program
The slump flow, concrete temperature, unit weight, airvolume, L-box flow characteristics, surface settlement,and setting time were determined, and the results aresummarized in Table 2.
Table 2. Properties of evaluated SCC mixtures
Fresh concrete properties
All SCC mixtures had L-box blocking ratios (h2/h1) greater
than 0.80 indicating adequate passing ability, andrelatively low surface settlement (
8/11/2019 Formwork Digest
36/58
32 V1 N1May 2013
for the TER-30 mixture is given in Fig.1. The slump flowvalues noted at various times are also indicated. Right
after casting, the concrete is shown to develop lateralpressure close to the theoretical hydrostatic pressure. The
hydrostatic pressure (Phyd
) is calculated as: Phyd
= g
H; where , g, and H refer to the concrete unit weight,gravity constant, and head of concrete in the formwork,
respectively. The relative pressures compared to Phyd
atthe base of the column determined at end of casting and
then after 1, 2, and 3 hours were 91%, 77%, 68%, and 61%respectively.
Fig. 1: Variations of lateral pressure envelope with time for the TER-30 mixture
Fig. 2: Effect of concrete temperature, cement Type 30, and use of set-
accelerating admixture on pressure variations determined at the bottom of the
2800-mm high column
Effect of concrete temperature on variations in lateral
pressure
Variations of the P(maximum)/P(hydrostatic) values
measured along the 2800-mm column of the five SCCmixtures placed at 10 m/h are plotted in Fig.2. Slump
values determined at the end of pressure monitoring arenoted. Mixtures prepared with ternary cement at initial
temperatures of 10, 22, and 30C develop similar relativepressures of 91% at the end of casting. This indicates
that concrete temperature has no significant effect on the
development of initial pressure. The maximum initialpressure is rather affected by the degree of internal frictionthat depends on the coarse aggregate volume andmixture consistency. On the other hand, the rate of
pressure drop with time is significantly affected byconcrete temperature. For example, the time to reduce
the relative pressure by 25% decreased from 400 to 250and 160 minutes for the TER-10, TER-20, and TER-30
mixtures, respectively.
Alexandridis and Gardner [1] reported that concrete cast
at higher initial temperature can exhibit higher cohesionthrough the formation of a gel structure. This can enablethe plastic concrete to develop higher shear strength
capable of carrying a greater fraction of the vertical load,thus resulting in increased rate of pressure drop with time.
It is important to note that higher initial temperature canresult in greater rate of loss in slump flow consistency,
thus reducing the degree of lateral pressure. For example,slump values of 170 and 180mm were measured 5 and
3.5 hours after casting for the TER-10 and TER-30mixtures, respectively.
The T30-20 and TER-20-ACC mixtures developed thelowest initial relative pressures of 78% and 83%,respectively, compared to 91% for those cast at 10 to30C initial temperatures and placed at similar castingrates of 10 m/h (Fig. 2). The incorporation of set-accelerating admixture in the TER-20-ACC mixtureresulted in the highest rate of pressure drop with time;the elapsed period required to reduce the relativepressure by 25% was 88 minutes. The increased rate ofcement hydration due to the incorporation of set-accelerating admixture can lead to greater cohesiveness,and hence sharper rate of drop in lateral pressure.[4]
Effect of section width on formwork pressure
For investigation of effect of concrete temperature onlateral formwork pressure, experimental research of
Khayat[8] and his colleagues was used and describedthose below:
Materials
A ternary cement made with approximately 6% sil icafume, 22% Class F fly ash, and 72% Type 10 cement wasused. A continuously graded crushed limestoneaggregate with nominal size of 10 mm and well-gradedsiliceous sand were employed. The sand had a finenessmodulus of 2.5. The bulk specific gravities of the aggregateand sand were 2.72 and 2.69, and their absorptions were0.4% and 1.2%, respectively. A naphthalene-based high-
range water reducer (HRWR) with solid content of 41%
Formwork Pressure
8/11/2019 Formwork Digest
37/58
33V1 N1May 2013
and specific gravity of 1.21 was used. A liquid-basedpolysaccharide was used for the viscosity-modifying
admixture (VMA) to enhance stability of the plasticconcrete. A synthetic detergent-based air-entraining
admixture (AEA) and a carboxylic acid-based water-
reducing admixture were incorporated.
Mixture proportion
For the SCC mixture used in this study, a proven mixtureprepared using 490 kg/m3of binder, 0.38 w/cm, and 0.44
sand to-coarse aggregate ratio was used. The VMA wasincorporated at a dosage of 1325 mL/100 kg of water,
and the HRWR dosage was adjusted at 6 L/m3 to secureinitial slump flow of 650 mm. A dosage of 150 mL/100 kg
of cementitious materials of the AEA was used. The unitweight and air content were 2280 kg/m 3 and 6.1%,
respectively.
Instrumented formworks
As already mentioned, two experimental formworks wereused. The first measured 2100 mm in height and 200 mmin diameter. The PVC tube had a wall thickness of 10 mmand a smooth inner face to minimize friction during andafter concrete placement. The stress in the diaphragmcaused by concrete lateral pressure was determinedusing five pressure sensors mounted at 850, 1250, 1650,1850, and 2050 nun from the top. The monitoring ofpressure distribution was stopped once the concrete hadan approximate slump consistency of 100 mm. Thesecond column consisted of a sonotube of 3600 mm inheight and 920 mm in diameter. The column wasadequately braced and reinforced. The lateral pressurewas determined using two pressure sensors located at2050 and 2880 mm from the top.
The monitoring of pressure distribution was stopped oncethe concrete had an approximate slump consistency of100 mm. The second column consisted of a sonotube of3600 mm in height and 920 mm in diameter. The columnwas adequately braced and reinforced. The lateralpressure was determined using two pressure sensorslocated at 2050 and 2880 mm from the top. In this case,the lateral pressure was monitored until the hardening of
the concrete.
Fabrication and testing program
Ready-mixed concrete was delivered to the experimentalsite. The ambient and concrete temperatures were 16
and 19C respectively. The slump flow, air content, JRingand Lbox flow characteristics, and surface settlement weredetermined for the SCC. The measurement correspondsto the mean diameter of the spread concrete at the end offlow. The JRing spread values was 600 mm and for Lboxtest the measure was 0.81 and maximum surfacesettlement was 0.34%.
The concrete was directly discharged from the mixing
truck into the formwork from the top at the desired pouringrate without stoppage or vibration. In the case of the 3600-
ram high column, the concrete was placed at a rate ofrise of 10m/hr. For the 2100-ram high column, the formwork
pressure was evaluated twice; once using a rate of
placement of 10m/hr and then at 25 m/hr for a secondcolumn. The slump flow values determined upon the
arrival on site of the concrete and after 1 and 2 hours were650, 635, and 450 mm, respectively. After 3 and 3.5 hours,
slump consistencies of 180 and 65 mm were measured,respectively.
The initial and final setting times were determined in the
laboratory at 20C in compliance with ASTM C403 andare given in Fig.3. The adiabatic temperature was alsoevaluated in an adiabatic calorimeter on mortar obtained
by sieving fresh concrete through a 4.75-mm sieve. Theheat evolved was determined by deriving the temperaturerise as a function of time. The time between the initial
contact of cement with water and that corresponding tothe beginning of the acceleration of temperature rise was
6 hours, as also shown in Fig.3.
Fig 3: Variations of hydration and stiffening kinetics with time
Lateral pressure variations
The variations of the lateral pressure envelope determined
on the 2100-ram high column along with the consistencyare plotted in Fig.4. Immediately after filling the formwork,
the concrete is shown to act as a fluid exerting almosthydrostatic head. However, a gradual decrease in lateral
pressure takes place with time. The relative pressures atthe base of the column determined initially and after 1, 2
and 3 hours were 98%, 89%, 83% and 76% of hydrostaticpressure respectively.
Results of the section width Influence on formwork
The effect of column diameter (200 vs. 920 mm) onchanges in lateral pressure is illustrated in Fig.5 by plotting
the variations of the P(measured)/P(hydrostatic) valuescalculated at 2050 mm from the top of the formworks as a
function of time. It is important to mention that bothcolumns were cast on the job site at the same casting
Formwork Pressure
8/11/2019 Formwork Digest
38/58
34 V1 N1May 2013
rate of 10 m/hr. Initially, the mixture placed in the largercolumn exhibited slightly greater pressure of 99% of
hydrostatic pressure compared to 96% for the 200-mmdiameter column. However, the rate of drop in pressure
was significantly different. In the case of the former
concrete placed in the 920-mm diameter column, thetime required to reduce lateral pressure by 5% of the
hydrostatic value was 20 minutes, resulting in a slope of5.3 kPa/hr. Conversely, for the 200-mm diameter column,
this period was 38 minutes resulting in a slope of 3.3kPa/hr. In general, the rate of drop in lateral pressure of plastic
concrete depends on the degree of thixotropy or shearrecovery [9]. This phenomenon causes a build-up of the
structure and an increase in cohesiveness soon after the
Fig 4: Variations of hydration and stiffening kinetics with time
material is left standing at rest without any shearing action.In the case of the 200-mm diameter column, the arching
effect can be relatively more pronounced than thatresulting from the 920-ram diameter column.
Conclusions
- Variations in fresh concrete temperature have limitedeffect on the maximum lateral pressure developed by
SCC at the time of casting. However, the rate ofpressure drop with time increases with the concrete
temperature that promotes faster development ofcohesion.
- The use of Type 30 cement or set-acceleratingadmixture can lead to 10% reduction in the initialpressure and accelerate the rate of pressure drop by
two folds compared to similar concrete prepared witha ternary cement.
- The scale effect had an influence on the rate of drop inlateral pressure of SCC with time; however, no
appreciable difference in the maximum initial pressurewas observed.
- Immediately after casting, the SCC placed in the 200-
ram diameter column was found to exert slightly lesspressure than that cast in the 920-ram column. This
can be due to an arching effect in the relativelyrestricted section.
References
[1] ACI Committee 347 (2001) "Guide to formwork for concrete",
Farmington Hills, 32.
[2] ACI Committee 622 (1958)" Pressures on formwork", ACI Journal,
Proceedings, and 55(2):173-190.
[3] ACI Committee 622, "Pressures on formwork", ACI
Journal,Proceedings, 55 (2) (1958) 173-190.
[4] Assaad J, Khayat KH, Mesbah H (2003) "Variation of formwork
pressure with thixotropy of self-consolidating concrete." ACI
Materials Journal, 100(1):29-37.
[5] Bartos, P.J.M., "An appraisal of the orimet test as a method for
on-site assessment of fresh SCC concrete", Int. Workshop on
Self-Compacting Concrete, Japan, (1998) 121-135.
[6] Gardner, N.J. and Ho, P.T.-J., "Lateral pressure of fresh concrete",ACI Journal, Technical Paper, Title No. 76-35 (1979) 809-820.
[7] Joseph J. Assaad Kamal H. Khayat "Effect of casting rate and
concrete temperature on formwork pressure of self-consolidating
concrete",Rilem Materials and Structures (2006) 39:333-341
[8] K. Khayat, J. Assaad, H. Mesbah, and M. Lessard "Effect of
section width and casting rate on variations of formwork pressure
of self-consolidating concrete ", Rilem Materials and Structures
38 (January-February 2005) 73-78
[9] Rodin, S., "Pressure of concrete on formwork", Proceedings
Institution of Civil Engineers (London) 1 Part 1 (6) (1952) 709-
746.Fig. 5: Effect of the section width on lateral pressure
Formwork Pressure
8/11/2019 Formwork Digest
39/58
8/11/2019 Formwork Digest
40/58
36 V1 N1May 2013
Formwork Failure: Cases & Causes
Special Correspondent
Collapse of concrete structures during construction
has been happening since concrete has been
placed in formwork. Cases and causes of these
type of failures have been documented and recorded in
many texts, articles and journals. This article will try and
focus on a few of them from the available reports, starting
with The New York Coliseum on May 9, 1955, 2000
Commonwealth Ave. on January 5,1971, Skyline Plaza in
Bailey's Crossroads on March 2, 1973, The Harbour Cay
Condominium in Cocoa Beach, Florida in March 1981 and
ending with The Tropicana in Atlantic City on October 30,
2003.The focus will be on what has been learned over time
from these failures and what has been done to keep these
type of tradgedies from occurring in the future.
Although there were many cases of concrete failures during
construction prior to the New York Coliseum collapse as
illustrated in (McKaig 13-27, 1962), only a few will be
looked at after this point because of the changes and
progressions being made in the construction industry at
this time in history.
(A) New York Coliseum on May 9, 1955
Pic source: http://www.ppconstructionsafety.com
Formwork Failure
8/11/2019 Formwork Digest
41/58
37V1 N1May 2013
The construction method was a flat plate waffle slab with
solid slabs at the column caps. It was one of the first times
the use of motorized buggies had been used in the pouring
of this type of structure. The floor that collapsed was the
first floor above grade supported on two tiers of shores at
a total of 22' high. It can be seen from Figure 1 how collapse
happened. The buggies weighed about 3000 lb loaded,
ran at about 12 mph, and there were eight of them at the
time of the failure with about 500 cubic yards of concrete
already placed. The investigation that followed put the
blame solely on inadequate provisions in the formwork to
resist lateral forces, it even went on to say that "if there had
been sufficient diagonal, horizontal, and end bacing ofthe temporary supporting structure, the collapse could
have been prevented entirely,...", (McKaig 15-16, 1962).
After the collapse the district attorney called attention to
the lack of inspections and made recommendations to
revising the building code with respect to formwork
because of the new advances.
(B) 2000 Commonwealth Avenue: January 5, 1971
This was a progressive collapse of a cast-in-place
reinforced concrete flat-slab structure. Punching shear was
determined to have been the triggering mechanism but
the real problem was in the numerous errors and omissionsby every party involved in the project (Delatte 133-143).
The investigating committee determined that if the
construction had had a proper building permit and had
followed codes, then the failure could have been avoided
(Delatte 142) (See Figure 2 and 3 how failure occurred).
Some of the problems leading to the collapse are
- Not following the structural engineers specifications
for shoring and formwork
- Lack of concrete design strength
- Lack of shoring or removed too soon
- Improper placement of reinforcement
- Little construction control on site
- Owner changed hands many times
- Almost all jobs were sub contracted
- No architectural opr engineering inspection done
- Inadequate inspection by the city of Boston
- The general contractors representative was not a
licensed builder
- Construction was based on arrangements done by the
subcontractors
- No direct supervision of subcontractors
Figure 2: Typical flatplate with uniform distributed loading
Figure 3: Punching shear failure diagram
Figure 4: Skyline Plaza at Bailey's Crossroads, National Archives
Figure 1: N.Y. Coliseum Collapse, National Archives
Formwork Failure
8/11/2019 Formwork Digest
42/58
38 V1 N1May 2013
(C) Skyline Plaza: March 2,1973
Skyline Plaza (See Figure 4) in Bailey's Crossroads is an
example of a catastrophic collapse of a 30 story cast-in-
place reinforced concrete structure. This was also a flat-
plate design structure that failed due to punching shearon the 23rd floor and resulted in a progressive collapse.
Some of the reasons for this failure again were 1) premature
removal of shores and reshores, 2) insufficient concrete
stength, 3) no preconstruction plans of concrete casting,
formwork plans, removal of formwork schedules, or
reshoring program (Kaminetzky 66-67).
(D) Harbour Cay Condominium: March 1981
Built just 10 years after 2000 Commonwealth Ave. and 8
years after Skyline Plaza, was another cast-in-place
reinforced concrete structure that collapsed during
construction. It was determined that the most importantfactor towards its failure was a design error coupled with a
construction error of the wrong size rebar and chair height.
The designer never performed any calculations to check
for punching shear, the most common form of failure in
these type of structures (Feld & Carper 18).
Figure 5: Tropicana Casino; Parking Garage Picture taken from
www.CTLGroup.com
(E) The Tropicana Casino parking garage in Atlantic
City, N.J.: October 30,2003
The structure collapsed during construction killing another
four construction workers and and leaving more than 30
others injured. Larry Bendesky, Mongeluzzi's partner of the
Philadelphia law firm Saltz, Moongeluzzi, Barrett &
Bendesky, P.C, the lead counsel for the litigation with Paul
D'Amato of the D'Amato Law Office and a member of the
trial team, said that "the simple explanation of the cause of
the collapse is that the floors were not connected to the
walls with the required reinforcing steel. Built without the
necessary steel, it is no wonder it collapsed like a house of
cards." (pr newswire) The vertical columns left standing
and the fact that the floors were not connected implies
that this was another punching. Refer Figure 5 for the
collapse picture.
Codes & Regulations
Codes in Place
ACI, The American Concrete Institute's origins started in
1905 with its first building code published in 1910 and
changing its name to the current designation in 1913. ACI's
first design handbook came out in1939 and the first
building code titled ACI 318 came out in 1941. The
beginning volumes of ACI were less tha fifty pages with
the current code specification being nearly 470 pages of
design specifications and commentaries (ACI 318). Thisclearly shows the history of ACI is closely tied to the ever
changing demands of concrete construction and
technology. The ACI sees itelf as an expanding, alert,and
informed organization prepared to stimulate imaginative
applications of concrete and better knowledge of its
properties and uses, and will take an increasingly active
part in solving problems affecting the public welfare
(History of ACI).
Lessons Learned
(A) New York Coliseum on May 9, 1955
From this failure the construction industry learned that
shoring systems should be well braced to resist lateral
loads and to consider the effect of power or motorized
buggies/carts on the formwork (Auburn University).
(B) 2000 Commonwealth Avenue: January 5, 1971
From 2000 Commonwealth Ave. the industry learned that
this type of failure is a critical failure mechanism for flat-
plate-slab concrete construction. Structural safety
depends on adequate slab thickness, proper placement
of reinforcement, and adequate concrete strength (Delatte144).
(C) Skyline Plaza: March 2,1973
Six lessons learned from the colloapse of Skyline Plaza at
Bailey's Crossroads are listed in (Kaminetzky 67)
- the contractor should prepare formwork drawings
showing details of the formwork, shores, and reshores.
- The contractor should prepare a detailed concrete
testing program, to include cylinder testing, before
stripping forms.
Formwork Failure
8/11/2019 Formwork Digest
43/58
39V1 N1May 2013
- The engineer of record should ascertain that the
contractor has all the pertinent design data (such as
live loads, superimposed dead loads, and any other
information which is unique to the project).
- Inspectors and other quality control agencies should
verify that items 1 and 2 above are being adhered to.
- Uncontrolled acceleration of formwork removal may
lead to serious consquences. 6) Top and bottom rebars
running continuously within the column periphery must
be incorporated in the design.
(D) Harbour Cay Condominium: March 1981
The Harbour Cay Condominiums presented the industry
with six more lessons learned in this type of construction
also listed in (Kaminetzky 77-78). This tradgedy happened
only eight years after the Skyline Plaza tradgedy and yet
some of the same lessons are listed again, they are
- A punching shear strength check s critical to the
success of a flat-slab, since punching shear is the most
common failure mode of concrete slabs.
- Minimum depth of a flat-slab must be checked to
assure proper strength and acceptable deflections.
- Reinforcing bars, both at the top and at the bottom of
the slab, should be placed directly within the column
periphery to avoid progressive collapse. This can easily
be accomplished routinely in all flat-slab jobs at no
additional cost at all.
- Proper construction control must be provided in thefield, including design of formwork by professionals.
This must include shoring and reshoring plans,
procedures, and schedules, with data on minimum
allowable stripping strength of the concrete.
- When there are failure warning signs of any type on a
construction site, work must stop. All aspects of the
project must be carefully evaluated by experienced