Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program Fang Cheng, PhD, PE, Dave Bukovac City of Columbus Department of Public Utilities Division of Sewerage and Drainage 8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 1
37

Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Apr 25, 2018

Download

Documents

phamkhuong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program

Fang Cheng, PhD, PE, Dave Bukovac

City of Columbus Department of Public Utilities

Division of Sewerage and Drainage

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 1

Page 2: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Acknowledgement

• Mike Griffith, PE, [email protected]

• John Rubadue, [email protected] • Kevin Abrigg, [email protected]

• Matt Panko, [email protected]

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 2

Page 3: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Outline

• Background • Objectives • Flow Monitoring Equipment • Preliminary Results • Lessons Learned

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 3

Page 4: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Sump Pump Program • One of the four pillars of Blueprint

Columbus Program • Voluntary • Goal is to reduce private source I/I • Plan to install sump pumps in 25% of

homes within Blueprint area • No direct cost to home owners • Prior to full scale implementation, a pilot

sump pump project was performed

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 4

Page 5: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Sump Pump Pilot

• Public outreach team solicited volunteers

• Installation started in Oct. 2016 • ~110 sump pumps installed • Average cost of $6,000 per sump

pump including discharge piping • 29 sump pumps are monitored • Plan monitoring for minimum 12

months per site

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 5

Page 6: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Objectives of Flow Monitoring

• Quantify sump pump effectiveness • Quantify Inflow/Infiltration reduction of sump pump installation • How to improve sump pump effectiveness – regular sump pit vs.

deeper pit • How many sump pump do we need to install?

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 6

Page 7: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Regular Pit (22’’) vs. Deeper Pit (30’’)

• Started with only 22’’ pit • Early 2017, 30’’ pits began to be installed • If foundation drains tie into floor drain – 22’’ pit • If no foundation drains tie into floor drain

• Excavate outside near 4’’ by 6’’ transition to locate external foundation drains

• If no external foundation drain, install 30’’ pit inside • If external foundation drain exists, pipe it to a 30’’ pit

inside

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 7

Page 8: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Monitoring Equipment

• Water meter (totalizer) installed on discharge pipe

• $200 / meter • No time stamp • No remote access ability • Data retrieval by physical access,

phone, and text from residents

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 8

Page 9: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Monitoring Equipment

• Sump pit float switch • $20 /switch • Positioned in between pump

on/off water level • Each switch closure sends a

electric pause to data logger recording one pump cycle

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 9

Page 10: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Monitoring Equipment and Technology

• Retired ADS Flowshark data logger

• No additional cost • Wireless communication

enabled

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 10

Page 11: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Progression of a sump pump install. Ohio Basement Authority (OBA) digs the pit.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 11

Page 12: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

OBA installs the well. We are using pits of 22” and 30” depth.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 12

Page 13: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

OBA prepares submersible pump for install into pit. Note float switch position.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 13

Page 14: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Submersible pump lowered into pit.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 14

Page 15: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Complete install, showing discharge piping, inline ZPM water meter, backup battery, and float switch data logger.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 15

Page 16: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Discharge pipe to be laid from home to curb.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 16

Page 17: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Float switch, made by Wayne Pumps. Switch opens as float rises with water level. When pump kicks on, float falls causing switch closure. Data logger reads and time stamps the switch closure.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 17

Page 18: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

The data logger is a retired ADS Flowshark meter using the rain gauge port to count the float switch closures. Meters are programmed in five minute interval.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 18

Page 19: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Sample Float Switch Data

The big storms on 7/10 and 7/13 greatly impacted the pump cycling at this location. The data logger is programmed as a rain gauge, it displays the switch closures as tipping bucket tips.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 19

Page 20: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

The float switch data alone was not giving us enough information on what was going on in the pits. We began installing retired ADS depth/pressure sensors into the pits as well. Sensors are attached to 1” pvc pipe and mounted at the bottom of the pit.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 20

Page 21: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Sample data from a location with both the float switch and pressure sensor installed. Working well.

This image cannot currently be displayed.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 21

Page 22: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Sump Pump Flow Monitoring Periods

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 22

This image cannot currently be displayed.

Page 23: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Preliminary Results – Water Meter

• Pump discharge volume was normalized by total rainfall between the installation and date of reading

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 23

Page 24: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Sump Pump Discharge Volume per Inch of Rainfall

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 24

This image cannot currently be displayed.

Page 25: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Float Switch with Data Logger

• Each pump cycle discharges 3-5 gal of water

• < 10 secs to drain the sump

• Filling time varies greatly by site and by storm

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 25

This image cannot currently be displayed.

Page 26: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Float Switch Challenges

• Not correlated with water meter readings

• Switch could be stuck in one position

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 26

This image cannot currently be displayed.

Page 27: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Solution - Depth Sensor

• Depth sensors were installed in 8 sites started June, 2017 • Discharge volume can be calculated accurately • More detail information on how sump is filled and emptied

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 27

Page 28: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

This image cannot currently be displayed.

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 28

Page 29: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Sump Pump Peak I/I reduction - July 13, 2017 Event

• 1.94 ‘’ over 1.5 hours • Between 10-year to 25-year

storm • Flow meter Clintonville_0342

• Peak flow 1.1 MGD • 157 parcels • 31 sump pumps installed • 4 sump pumps monitored

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 29

Page 30: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 30

This image cannot currently be displayed.

Page 31: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Sump Pump Discharge Peak Occurred at the same time

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 31

This image cannot currently be displayed.

Page 32: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

What is the sump pump peak discharge?

• Average 1.9 gpm

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 32

This image cannot currently be displayed.

Page 33: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 33

Most effective site : 6 gpm

This image cannot currently be displayed.

Page 34: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

How Much Peak I/I Can Sump Pump Reduce?

Total sump pump discharge = peak discharge rate * Number of pumps 1.9 gpm * 31 = 60.1 gpm Sump pump peak I/I reduction = Total sump pump discharge/(monitored peak I/I +Total sump pump discharge) 60.1 gpm/(1.03 mgd +60.1 gpm) = 7.8%

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 34

This image cannot currently be displayed.

This image cannot currently be displayed.

Page 35: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

How Many Sump Pumps Do We Need?

• With average 1.9 gpm and 25% Sump Pump, I/I peak reduction is

9.7% • 365 sump pumps per 1 MGD I/I reduction

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 35

Page 36: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Conclusions

• Sump pump results are promising • More storms will be analyzed to confirm the effectiveness • Deeper sump pits are more effective • We could develop a specific target number of sump pumps needed

for each Blueprint Area • Lessons Learned

• Water meter without time stamp can be misleading • Remote access if possible • Depth sensor is most reliable

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 36

Page 37: Flow Monitoring of Blueprint Columbus Sump Pump Pilot … · Flow Monitoring of Blueprint Columbus Sump Pump Pilot Program ... • Goal is to reduce private ... 8/17/2017 Flow Monitoring

Questions?

• Fang Cheng, [email protected]

• Dave Bukovac, [email protected]

8/17/2017 Flow Monitoring of Blueprint Columbus Sump Pump Pilot 37