8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 1/22
Sl No Description Amount
1 Road Part 30062
2 Construction of drain 63424
Sub Total 93486
3 Add VAT @ 4% (PART-B) 3280
4 Provision for QC charges at 0.50% LS 467
5 LS for Unforeseen items 2767
TOTAL 100000
GENERAL ABSTRACT
Name of Work : Flood Damage to the C.D.Works and
C.C.road in B.C.Colony (Balance Work) at Brahmanakokur
of Nandikotkur Mandal.
Assistant Engineer
M.P. Nandikotkur
Page 2
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 2/22
As per MORD (Part-II) specifications Estt.Cost.Rs. 0.3 Lakhs
S
No
Description
of ItemNo
Length
(m)
Width
(m)
Thik
ness
(m)
Quantity Rate (Rs)Amount
(Rs)
1 2 3 4 5 6 8 9 10
GSB Shoulders1
For
Approaches
near Nagaiah
House
2 5.00 3.00 0.15 4.50
ForApproaches
near Boya
Ramudu
House
2 4.80 1.10 0.15 1.58
For
Approaches
near
S.Sankaraiah
House
2 4.80 1.50 0.15 2.16
For Shoulders 2 117.05 0.60 0.15 21.07
29.31 277.52 1 Cum 8135
2
1 10.00 3.10 0.17 5.27
5.27 4160.66 1 Cum 21927
Total
Assistant Engineer
Construction of Granular shoulders using Gravel & Sand by
providing well graded material , spreading in uniform layers
with motor grader on prepared surface, mixing by mix in place
method with rotavator at OMC, and compacting with Static
Roller 80-100 kN capacity to achieve the desired density,
complete as per Technical Specification Clause 402 MORD, But
excluding VAT charges.
Construction of un-reinforced, dowel jointed at expansion and
construction joint only, plain cement concrete pavement,thickness as per design, over a prepared sub base, with 43
grade cement or any other type as per clause 1501.22
M30(Grade), coarse and fine agregates conforming to IS:383
maximum size of coarse agregate not exceeding 25mm, mixed
in a concrete mixer of not less than 0.2cum capacity and
appropriate weigh batcher using approved mix design, laid in
approved fixed side form work (steel channel, laying and fixing
of 125 micron thick polythene film, wedges, steel plates
including levelling the form work as per drawing), spreading the
concrete with shovels, rakes, compacted using needle, screed
and plate vibrators and finished in continous operation
including provision of contraction and expansion, construction
joints, applying debonding strips, primer, sealant, dowel bars,near approachs to bridge/culvert and construction joint,
admixtures as approved, curing of concrete slabs for 14 days,
curing compound (where specified) and water finishing to lines
and grade as per drawing and technical specification clause
1501.22 but excluding VAT charges.
unit
7
30062
DETAILED AND ABSTRACT ESTIMATE
Name of Work : Flood Damage to the C.D.Works and C.C.road in B.C.Colony (Balance Work) at
Brahmanakokur of Nandikotkur Mandal.
Page 3
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 3/22
M.P. Nandikotkur
Page 4
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 4/22
Estt.Cost.Rs. 0.63
Sl.
No.Description of Item No Length (m) Width(m)
Thicknes
s(m)Quantity Rate (Rs)
unit
perAmount (Rs)
1 2 3 4 5 6 7 8 9 10
1
Near Vadde Nagaiah
House
1 5.00 1.50 0.80 6.00
Near Boya Ramudu 1 4.80 1.70 0.80 6.53
Near S.Sankaraiah 1 4.80 1.70 0.80 6.53
NET : 19.06 71.34 1 1359.00
3
Near Vadde Nagaiah 1 5.00 1.50 0.20 1.50
Near Boya Ramudu 1 4.80 1.70 0.20 1.63
Near S.Sankaraiah 1 4.80 1.70 0.20 1.63
NET : 4.76 2354.80 1 11218.00
4
Near Vadde Nagaiah 2 5.00 0.45 0.60 2.70
Construction of 0.60m Vent RCC deck Slab Culverts 3 Nos.Type of CrossDrainage work:
Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing
of sides and bottom and backfilling in trenches with excavatedsuitable material as per Technical Specification 305 MORD / 304
MORTH , but excluding VAT.
Providing concrete for plain concrete M 10 grade for using 40
mm Graded hard stone aggregate, mechanically mixed,
placed in foundation and compacted by vibration includingcuring for 14 days complete as per drawings and technical
specifications Clause 802, 803, 1202 & 1203 MORD and
1500, 1700 & 2100 MORTH ,including overhead charges &
Contractors profit but excluding VAT.
COST ESTIMATE FOR ROADS CONSTRUCTION OF CROSS DRAINAGE WORKS
Providing concrete for plain concrete M 7.5 grade in open
foundations using 40 mm nominal size Graded hard stone
aggregate, mechanically mixed, placed in foundation andcompacted by vibration including curing for 14 days complete as
per drawings and technical specifications Clause 802, 803, 1202
& 1203 MORD and 1500, 1700 & 2100 MORTH , but excluding
Name of Work : Flood Damage to the C.D.Works and C.C.road in B.C.Colony (Balance
Work) at Brahmanakokur of Nandikotkur Mandal.
4
Page 5
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 5/22
Sl.
No.Description of Item No Length (m) Width(m)
Thicknes
s(m)Quantity Rate (Rs)
unit
perAmount (Rs)
1 2 3 4 5 6 7 8 9 10
Near Boya Ramudu 2 4.80 0.40 0.60 2.30
Near S.Sankaraiah 2 4.80 0.40 0.60 2.30
NET : 7.31 2684.13 1 19616.00
Near Vadde Nagaiah
House
1 5.00 1.50 0.15 1.13
Near Boya RamuduHouse
1 4.80 1.70 0.15 1.22
Near S.Sankaraiah
House
1 4.80 1.70 0.15 1.22
NET : 3.57 4856.39 1 17352.00
6 0.300 46262.61 1M.T. 13879.00
TOTAL : Rs 63424.00
Assistant Engineer
M.P. Nandikotkur
Supplying, fitting, and placing HYSD bar reinforcement in
superstructure complete as per drawing and technical
specifications Clauses 1002, 1010 and 1202 MORD / 1600
MORTH, for Bars below 36 mm dia including over laps and
wastage, where they are not welded ,including overhead charges
& Contractors profit but excluding VAT.
Providing and laying reinforced cement concrete M25 grade
(Design Mix) using 20 & 10mm metal mechanically mixed in
superstructure as per drawing and technical specifications
Clauses 800, 1205.4 and 1205.5 MORD / Sections 1500, 1600 &
1700 MORTH ,including overhead charges & Contractors profit
but excluding VAT upto 5m height.
5
Page 6
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 6/22
Data Sheet
S.
No.
Ind
ex
Cod
e
Description of item Unit Qty Rate Amount
1
a) Labour
Mazdoor (Skilled) day 2.40 196.00 470.40
Mazdoor (Un-Skilled) day 8.00 196.00 1568.00
b) Machinery
Static Roller 80-100 KN hour 30.00 746.50 22395.00
Water tanker 6kl capacity hour 5.00 345.00 1725.00
Tractor with grader @ 25
cum per hour
hour 12.00 345.00 4140.00
Tractor with rotavator @ 25
cum per hour
hour 12.00 345.00 4140.00
c) Material
Cost of materials
9.5 mm to 4.75 mm @ 66%
(Gravel)
cum 237.60 122.85 29189.37
2.36 mm below @ 34%
(Sand)
cum 122.40 160.35 19626.95
83254.72
a) 277.52
Rate per cum 277.52
277.52
1
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
DATA (ROAD WORK) - SSR 2010-11
Name of Work : Flood Damage to the C.D.Works and C.C.road in B.C.Colony
(Balance Work) at Brahmanakokur of Nandikotkur Mandal.
R B R - C C P V
- 5
Construction of Granular shoulders using Gravel & Sand by providing wellgraded material, spreading in uniform layers with motor grader on prepared
surface, mixing by mix in place method with rotavator at OMC, and compacting
with Static Roller 80-100 kN capacity to achieve the desired density,
complete as per Technical Specification Clause 402 MORD, But excluding VAT
charges.
Basic rate of Granular sub base cum
Taking out put = 300 cum
Cement Concrete Pavement
Rate per cum including conveyance
Construction of un-reinforced, dowel jointed at expansion and construction joint only,
plain cement concrete pavement, thickness as per design, over a prepared sub base,
with 43 grade cement or any other type as per clause 1501.22 M30(Grade), coarse
and fine agregates conforming to IS:383 maximum size of coarse agregate not
exceeding 25mm, mixed in a concrete mixer of not less than 0.2cum capacity and
appropriate weigh batcher using approved mix design, laid in approved fixed side form
work (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel
plates including levelling the form work as per drawing), spreading the concrete with
shovels, rakes, compacted using needle, screed and plate vibrators and finished in
continous operation including provision of contraction and expansion, construction
joints, applying debonding strips, primer, sealant, dowel bars, near approachs to
bridge/culvert and construction joint, admixtures as approved, curing of concrete slabs
for 14 days, curing compound (where specified) and water finishing to lines and grade
Well graded granular sub-base material as per table 400.2
Basic rate of Granular sub base for 300 cum
6
Page 7
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 7/22
Data Sheet
S.
No.
Ind
ex
Cod
e
Description of item Unit Qty Rate Amount
a) Labour
Mason (1st class) day 5.00 258.00 1,290.00
Mason (2nd class) day 5.00 237.00 1,185.00
Mazdoor (unskilled) day 150.00 196.00 29,400.00
Mazdoor(skilled) day 6.00 196.00 1,176.00
Surveyor day 2.00 237.00 474.00Mazdoor (semi-skilled) day 6.00 196.00 1,176.00
Black smith for cutting of
dowel bars including
removal of burrs,
fabrications & fixing of dowel
bars
day 1.00 237.00 237.00
34938.00
b) Machinery
Concrete mixer 0.28/0.40
cum capacity ( 6 mixers)
with weight batcher and
suitable capacity calibrated
water tank
Hour 36.00 345.00 12,420.00
Needle vibrator Hour 9.00
Screed vibrator Hour 9.00 40.00 360.00
Plate vibrator Hour 9.00 40.00 360.00
Water tanker 6 Kl. Capacity Hour 5.00 345.00 1,725.00
Air compressor ( 1hour
initial + 1 hour final)
Hour 2.00 370.00 740.00
15,605.00
c) Material
(I)
20mm Cum 44.55 1527.63 68,055.99
10mm Cum 22.95 1172.63 26,911.89
(ii) Sand as per IS:383 and
conforming to clause
1500.2.4.2. @ 0.45 cum of
concrete
cum 33.75 612.63 20,676.32
(iii) Cement @ 310 Kg/cum of
concrete
t 23.250 4600.00 106,950.00
(iv) Polythene sheet 125 micron sqm 412.5 15.00 6,187.50
(v)
(4x20x0.500) + 5 per cent
wastage = 42m @ 2.80 Kg
per m = 117.6 kg.
Kg 117.6 36000.00 4233.6
Bitumen primer @ 200ml.
Per joint for 23 joints
t 0.005 33478.13 167.39
Bitumenous sealant 800 ml.
Per joint for 23 joints
Litre 19.00 58.00 1102.00
Crushed stone coarse aggregates, grading will be as per clause 1501.2.4.1
(Table 1500.1) of specifications @ 0.90 Cum/cum of concrete
Mild steel dowel bar 25mm dia of grade S 240.500 mm long 20 Nos. at
culvert/bridge slab and at construction joiont including 5 percent wastage
7
Page 8
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 8/22
Data Sheet
S.
No.
Ind
ex
Cod
e
Description of item Unit Qty Rate Amount
Jute rope 12mm dia
including 5 per cent wastage
m 90.00 5.00 450.00
Debonding strips 3.75m.
(length) x 10mm (width) x 5
mm (thick) cut-out of rubberfiller board or similar
material including 5 per cent
wastage
m 90.00 9.00 810.00
Polythene sheathing,
covering 2/3rd dowel bars
(20x23) and tight fit
including 5 per cent wastage
No 483.00 0.50 241.50
Plasticizer 0.5 per cent by
weight of cement
Litre 122.00 57.00 6954.00
Curing compound (if used)
@ 0.33 litre per sqm
Litre 131.25 57.00 7481.25
Joint filler board 20mm thick
as per IS:1838
sqm 3.00 732.00 2196.00
(4x3.75x0.200 = 3 sqm) 252417.44
302960.44
(d) Form work @ 3% on (a+b+c) 9088.81
Cost for 75 cum = a+b+c+d 312049.25
Rate per Cum = (a+b+c+d+e)/75 4160.66
Rate per cum 4160.66
Assistant Engineer
M.P. Nandikotkur
8
Page 9
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 9/22
RATE ANALYSIS FOR CD WORKS
Excavation of structures:
1
R B R -
F N D N - 1
Excavation for Structures
Unit Qty Rate Amount
Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
construction of shoring and bracing, removal of stumps
and other deleterious material and disposal upto a lead of50 m, dressing of sides and bottom and backfilling in
trenches with excavated suitable material as per Technical
Specification 305 MORD / 304 MORTH , but excluding
VAT.
Note : Classifications of Earth Work Specification
are as per 302.2.1(a) of MORD and 301.2.1 of
MORT&H
Ordinary soil
Manual Means
i Upto 3 m depth
Unit = cum
Taking output = 10 cum
a)Labour
Mate day -
Mazdoor (Unskilled) day 3.64 196.00 713.44
sub Total 713.44
Cost for 10 cum = a+b+c+d 713.44
sub Total 713.44
Rate per cum = /10 71.34
Note : 1. Cost of dewatering upto 5% of a+b may be
added, where required, up to 10 per cent of labourcost. Assessment for dewatering shall be made as
per site conditions.
3
R B R - F N D N - 4
Providing concrete for plain concrete M 7.5 grade in open
foundations using 40 mm nominal size Graded hard stone
aggregate, mechanically mixed, placed in foundation and
compacted by vibration including curing for 14 days
complete as per drawings and technical specifications
Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 &
2100 MORTH , but excluding VAT.
P.C.C grade M 7.5
Nominal mix 1:4:8
Unit = cum
(a) Material
Cement t 0.175 4600.00 805.00
Coarse sand cum 0.45 612.63 275.68
40 mm aggregate cum 0.9 787.81 709.03
Water kl 1.2 70 84.00
(b) Labour
Mate day -Mason (1st Class) day 0.10 258.00 25.80
Mazdoor (Unskilled) day 1.39 196.00 272.44
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted with water
measuring device and preferably also with load cell.
hour 0.40 345.00 138.00
Page 10
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 10/22
RATE ANALYSIS FOR CD WORKS
Water tanker 6 kl capacity hour 0.13 345.00 44.85
2354.80
(d) Formwork @ 4% on cost of material, labour and
machinery (a+b+c)4.00% 0.00
2354.80
Rate per cum = a+b+c+d+e+f 2354.80
4 RBR-
FNDN-4
I(iii)
Providing concrete for plain concrete M 10 grade for
using 40 mm Graded hard stone aggregate,
mechanically mixed, placed in foundation andcompacted by vibration including curing for 14 days
complete as per drawings and technical specifications
Clause 802, 803, 1202 & 1203 MORD and 1500,
1700 & 2100 MORTH but excluding VAT.
P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 4600.00 1012.00
Coarse sand cum 0.480 612.63 294.06
40 mm aggregate cum 0.480 787.81 378.15
20 mm aggregate cum 0.240 1527.63 366.63
10 mm aggregate cum 0.080 1172.63 93.81
(b) Labour
Mate day -
Mason (1st Class) day 0.10 258.00 25.80
Mazdoor (Unskilled) day 1.39 196.00 272.44
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity
fitted with water measuring device and preferably also
with load cell.
hour 0.40 345.00 138.00
2580.89(d) Formwork @ 4% on cost of material, labour
and machinery (a+b+c)
4.00% 103.24
2684.13
Rate per cum = a+b+c+d+e+f 2684.13
6
R B R - S P S T - 2
Supplying, fitting, and placing HYSD bar reinforcement in
superstructure complete as per drawing and technical
specifications Clauses 1002, 1010 and 1202 MORD / 1600
MORTH, for Bars below 36 mm dia including over laps and
wastage, where they are not welded ,but excluding VAT.
Unit = t(a) Material
HYSD bars including 5 per cent for laps and wastage t 1.05 36000.00 37800.00
Binding wire kg 8.00 52.00 416.00
(b) Labour for cutting, bending, tying and placing in position
Mate day -
Blacksmith/ Rod Binder day 3.00237.00
711.00
Mazdoor (Unskilled) day 8.44 196.00 1654.24
40581.24
Overheads & Contractors Profit @14% 5681.37
Page 11
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 11/22
RATE ANALYSIS FOR CD WORKS
Rate per t = a+b+c+d 46262.61
7
R B
R - S P S T - 1
Providing and laying reinforced cement concrete M25
grade (Design Mix) using 20 & 10mm metal mechanically
mixed in superstructure as per drawing and technical
specifications Clauses 800, 1205.4 and 1205.5 MORD /
Sections 1500, 1600 & 1700 MORTH , but excluding VAT
upto 5m height.
R.C.C M 25 Grade (Design Mix)
Unit =cum
(i) Height upto 5m
Case I : Using Concrete Mixer.
(a) Material
Cement t 0.40 4600.00 1840.00
Coarse sand cum 0.45 612.63 275.68
20 mm aggregate cum 0.54 1527.63 824.92
10 mm aggregate cum 0.36 1172.63 422.15
(b) Labour
Mate day -
Mason (1st Class) day 0.10 258.00 25.80
Mazdoor (Unskilled) day 1.39 196.00 272.44c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour/cu 0.40 345.00 138.00
Generator 33 KVA hour 0.40 620.00 248.00
4046.99
d) For formwork and staging refer to sub-item I (B) case I above
d) Formwork and staging of (a+b+c) 20.00% 809.40
4856.39
Rate per cum = a+b+c+d+e+f 4856.39
Assistant EngineerM.P. Nandikotkur
Page 12
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 12/22
Sl
No.Description in Material
Name of the
Quarry
Lead in
KmInitial
Conveya
nce
charges
Conveyance
charges
excluding over
head and
Contractors
Profit(6)/1.14
Blasting
Charges
Machine
Crushing
Charges
Seinera
ge
Charges
1 2 3 4 5 6 7 8 9
1 Gravel Local 4.50 50.50 57.40 50.35 0.00 0.00 22.00
2 Sand for Filling Local 4.50 70.00 57.40 50.35 0.00 0.00 40.00
3 Sand for Mortor Sunkesula 48.00 220.00 402.00 352.63 0.00 0.00 40.00
4 40 mm HBT Metal-SS5 Local 3.50 500.00 48.80 42.81 70.00 125.00 50.00
5 20 mm HBG Chips-SS5 Ulindakonda 48.00 844.00 402.00 352.63 70.00 211.00 50.00
6 12 mm HBG Chips-SS5 Ulindakonda 48.00 688.00 402.00 352.63 70.00 172.00 50.00
7 10 mm HBG Metal-SS5 Ulindakonda 48.00 560.00 402.00 352.63 70.00 140.00 50.00
8 Cement (As on Jan.'2011) 4600.00
9 Steel (Fe 415 as on Jan.'2011) 36000.00
LEAD STATEMENT (CSSR2010-11)
Name of Work : Flood Damage to the C.D.Works and C.C.road in B.C.Colony (Balance Work) at Brahmanakokur
Mandal.
Certified that the adopted are correct to the best of my knowledge and belief.
Ass
M
Page 13
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 13/22
Earth, Sand,
Gravel
Metal,
Stone
kadapa
SlabsBricks
lead lead Rate lead Rate
0.25 128.70 0.25 106.60
0.5 128.70 0.5 106.60
1 21.50 19.10 28.00 11.90 1 128.70 1 106.60
2 30.20 26.70 39.20 16.70 2 128.70 2 106.603 40.20 40.20 59.10 22.20 3 128.70 3 106.60
4 48.80 48.80 71.80 27.00 4 128.70 4 106.60
5 57.40 57.40 84.50 31.80 5 128.70 5 106.60
6 66.00 66.00 97.20 36.60 6 134.90 6 112.80
7 74.60 74.60 109.90 41.40 7 141.10 7 119.00
8 83.20 83.20 122.60 46.20 8 147.30 8 125.20
9 91.80 91.80 135.30 51.00 9 153.50 9 131.40
10 100.40 100.40 148.00 55.80 10 159.70 10 137.60
11 109.00 109.00 160.70 60.60 11 165.90 11 143.80
12 117.60 117.60 173.40 65.40 12 172.10 12 150.00
13 126.20 126.20 186.10 70.20 13 178.30 13 156.20
14 134.80 134.80 198.80 75.00 14 184.50 14 162.4015 143.40 143.40 211.50 79.80 15 190.70 15 168.60
16 152.00 152.00 224.20 84.60 16 196.90 16 174.80
17 160.60 160.60 236.90 89.40 17 203.10 17 181.00
18 169.20 169.20 249.60 94.20 18 209.30 18 187.20
19 177.80 177.80 262.30 99.00 19 215.50 19 193.40
20 186.40 186.40 275.00 103.80 20 221.70 20 199.60
21 195.00 195.00 287.70 108.60 21 227.90 21 205.80
22 203.60 203.60 300.40 113.40 22 234.10 22 212.00
23 212.20 212.20 313.10 118.20 23 240.30 23 218.20
24 220.80 220.80 325.80 123.00 24 246.50 24 224.40
25 229.40 229.40 338.50 127.80 25 252.70 25 230.60
26 238.00 238.00 351.20 132.60 26 258.90 26 236.8027 246.60 246.60 363.90 137.40 27 265.10 27 243.00
28 255.20 255.20 376.60 142.20 28 271.30 28 249.20
29 263.80 263.80 389.30 147.00 29 277.50 29 255.40
30 272.40 272.40 402.00 151.80 30 283.70 30 261.60
31 279.60 279.60 412.60 155.80 31 289.90 31 267.80
32 286.80 286.80 423.20 159.80 32 296.10 32 274.00
33 294.00 294.00 433.80 163.80 33 302.30 33 280.20
34 301.20 301.20 444.40 167.80 34 308.50 34 286.40
35 308.40 308.40 455.00 171.80 35 314.70 35 292.60
36 315.60 315.60 465.60 175.80 36 320.90 36 298.80
37 322.80 322.80 476.20 179.80 37 327.10 37 305.00
38 330.00 330.00 486.80 183.80 38 333.30 38 311.2039 337.20 337.20 497.40 187.80 39 339.50 39 317.40
40 344.40 344.40 508.00 191.80 40 345.70 40 323.60
41 351.60 351.60 518.60 195.80 41 351.90 41 329.80
42 358.80 358.80 529.20 199.80 42 358.10 42 336.00
43 366.00 366.00 539.80 203.80 43 364.30 43 342.20
44 373.20 373.20 550.40 207.80 44 370.50 44 348.40
45 380.40 380.40 561.00 211.80 45 376.70 45 354.60
Rate
900 mm RCC pipes1000mm dia
Page 14
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 14/22
46 387.60 387.60 571.60 215.80 46 382.90 46 360.80
47 394.80 394.80 582.20 219.80 47 389.10 47 367.00
48 402.00 402.00 592.80 223.80 48 395.30 48 373.20
49 409.20 409.20 603.40 227.80 49 401.50 49 379.40
50 416.40 416.40 614.00 231.80 50 407.70 50 385.60
51 423.60 423.60 624.60 235.80 51 413.90 51 391.80
52 430.80 430.80 635.20 239.80 52 420.10 52 398.0053 438.00 438.00 645.80 243.80 53 426.30 53 404.20
54 445.20 445.20 656.40 247.80 54 432.50 54 410.40
55 452.40 452.40 667.00 251.80 55 438.70 55 416.60
56 459.60 459.60 677.60 255.80 56 444.90 56 422.80
57 466.80 466.80 688.20 259.80 57 451.10 57 429.00
58 474.00 474.00 698.80 263.80 58 457.30 58 435.20
59 481.20 481.20 709.40 267.80 59 463.50 59 441.40
60 488.40 488.40 720.00 271.80 60 469.70 60 447.60
61 495.60 495.60 730.60 275.80 61 475.90 61 453.80
62 502.80 502.80 741.20 279.80 62 482.10 62 460.00
63 510.00 510.00 751.80 283.80 63 488.30 63 466.20
64 517.20 517.20 762.40 287.80 64 494.50 64 472.4065 524.40 524.40 773.00 291.80 65 500.70 65 478.60
66 531.60 531.60 783.60 295.80 66 506.90 66 484.80
67 538.80 538.80 794.20 299.80 67 513.10 67 491.00
68 546.00 546.00 804.80 303.80 68 519.30 68 497.20
69 553.20 553.20 815.40 307.80 69 525.50 69 503.40
70 560.40 560.40 826.00 311.80 70 531.70 70 509.60
71 567.60 567.60 836.60 315.80 71 537.90 71 515.80
72 574.80 574.80 847.20 319.80 72 544.10 72 522.00
73 582.00 582.00 857.80 323.80 73 550.30 73 528.20
74 589.20 589.20 868.40 327.80 74 556.50 74 534.40
75 596.40 596.40 879.00 331.80 75 562.70 75 540.60
76 603.60 603.60 889.60 335.80 76 568.90 76 546.8077 610.80 610.80 900.20 339.80 77 575.10 77 553.00
78 618.00 618.00 910.80 343.80 78 581.30 78 559.20
79 625.20 625.20 921.40 347.80 79 587.50 79 565.40
80 632.40 632.40 932.00 351.80 80 593.70 80 571.60
81 639.60 639.60 942.60 355.80 81 599.90 81 577.80
82 646.80 646.80 953.20 359.80 82 606.10 82 584.00
83 654.00 654.00 963.80 363.80 83 612.30 83 590.20
84 661.20 661.20 974.40 367.80 84 618.50 84 596.40
85 668.40 668.40 985.00 371.80 85 624.70 85 602.60
86 675.60 675.60 995.60 375.80 86 630.90 86 608.80
87 682.80 682.80 1006.20 379.80 87 637.10 87 615.00
88 690.00 690.00 1016.80 383.80 88 643.30 88 621.2089 697.20 697.20 1027.40 387.80 89 649.50 89 627.40
90 704.40 704.40 1038.00 391.80 90 655.70 90 633.60
91 711.60 711.60 1048.60 395.80 91 661.90 91 639.80
92 718.80 718.80 1059.20 399.80 92 668.10 92 646.00
93 726.00 726.00 1069.80 403.80 93 674.30 93 652.20
94 733.20 733.20 1080.40 407.80 94 680.50 94 658.40
95 740.40 740.40 1091.00 411.80 95 686.70 95 664.60
Page 15
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 15/22
96 747.60 747.60 1101.60 415.80 96 692.90 96 670.80
97 754.80 754.80 1112.20 419.80 97 699.10 97 677.00
98 762.00 762.00 1122.80 423.80 98 705.30 98 683.20
99 769.20 769.20 1133.40 427.80 99 711.50 99 689.40
100 776.40 776.40 1144.00 431.80 100 717.70 100 695.60
101 783.60 783.60 1154.60 435.80 101 723.90 101 701.80
102 790.80 790.80 1165.20 439.80 102 730.10 102 708.00103 798.00 798.00 1175.80 443.80 103 736.30 103 714.20
104 805.20 805.20 1186.40 447.80 104 742.50 104 720.40
105 812.40 812.40 1197.00 451.80 105 748.70 105 726.60
106 819.60 819.60 1207.60 455.80 106 754.90 106 732.80
107 826.80 826.80 1218.20 459.80 107 761.10 107 739.00
108 834.00 834.00 1228.80 463.80 108 767.30 108 745.20
109 841.20 841.20 1239.40 467.80 109 773.50 109 751.40
110 848.40 848.40 1250.00 471.80 110 779.70 110 757.60
111 855.60 855.60 1260.60 475.80 111 785.90 111 763.80
112 862.80 862.80 1271.20 479.80 112 792.10 112 770.00
113 870.00 870.00 1281.80 483.80 113 798.30 113 776.20
114 877.20 877.20 1292.40 487.80 114 804.50 114 782.40115 884.40 884.40 1303.00 491.80 115 810.70 115 788.60
116 891.60 891.60 1313.60 495.80 116 816.90 116 794.80
117 898.80 898.80 1324.20 499.80 117 823.10 117 801.00
118 906.00 906.00 1334.80 503.80 118 829.30 118 807.20
119 913.20 913.20 1345.40 507.80 119 835.50 119 813.40
120 920.40 920.40 1356.00 511.80 120 841.70 120 819.60
121 927.60 927.60 1366.60 515.80 121 847.90 121 825.80
122 934.80 934.80 1377.20 519.80 122 854.10 122 832.00
123 942.00 942.00 1387.80 523.80 123 860.30 123 838.20
124 949.20 949.20 1398.40 527.80 124 866.50 124 844.40
125 956.40 956.40 1409.00 531.80 125 872.70 125 850.60
126 963.60 963.60 1419.60 535.80 126 878.90 126 856.80127 970.80 970.80 1430.20 539.80 127 885.10 127 863.00
128 978.00 978.00 1440.80 543.80 128 891.30 128 869.20
129 985.20 985.20 1451.40 547.80 129 897.50 129 875.40
130 992.40 992.40 1462.00 551.80 130 903.70 130 881.60
131 999.60 999.60 1472.60 555.80 131 909.90 131 887.80
132 1006.80 1006.80 1483.20 559.80 132 916.10 132 894.00
133 1014.00 1014.00 1493.80 563.80 133 922.30 133 900.20
134 1021.20 1021.20 1504.40 567.80 134 928.50 134 906.40
135 1028.40 1028.40 1515.00 571.80 135 934.70 135 912.60
136 1035.60 1035.60 1525.60 575.80 136 940.90 136 918.80
137 1042.80 1042.80 1536.20 579.80 137 947.10 137 925.00
138 1050.00 1050.00 1546.80 583.80 138 953.30 138 931.20139 1057.20 1057.20 1557.40 587.80 139 959.50 139 937.40
140 1064.40 1064.40 1568.00 591.80 140 965.70 140 943.60
141 1071.60 1071.60 1578.60 595.80 141 971.90 141 949.80
142 1078.80 1078.80 1589.20 599.80 142 978.10 142 956.00
143 1086.00 1086.00 1599.80 603.80 143 984.30 143 962.20
144 1093.20 1093.20 1610.40 607.80 144 990.50 144 968.40
145 1100.40 1100.40 1621.00 611.80 145 996.70 145 974.60
Page 16
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 16/22
146 1107.60 1107.60 1631.60 615.80 146 1002.90 146 980.80
147 1114.80 1114.80 1642.20 619.80 147 1009.10 147 987.00
148 1122.00 1122.00 1652.80 623.80 148 1015.30 148 993.20
149 1129.20 1129.20 1663.40 627.80 149 1021.50 149 999.40
150 1136.40 1136.40 1674.00 631.80 150 1027.70 150 1005.60
Loading 34.30 12.80
Unloading 10.90 8.70
Page 17
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 17/22
lead Rate lead Rate
0.25 67.70 0.25 60.90
0.5 67.70 0.5 60.90
1 67.70 1 60.90
2 67.70 2 60.90
3 67.70 3 60.90
4 67.70 4 60.90
5 67.70 5 60.90
6 71.00 6 63.70
7 74.30 7 66.50
8 77.60 8 69.30
9 80.90 9 72.10
10 84.20 10 74.90
11 87.50 11 77.70
12 90.80 12 80.50
13 94.10 13 83.30
14 97.40 14 86.10
15 100.70 15 88.90
16 104.00 16 91.70
17 107.30 17 94.50
18 110.60 18 97.30
19 113.90 19 100.10
20 117.20 20 102.90
21 120.50 21 105.70
22 123.80 22 108.50
23 127.10 23 111.30
24 130.40 24 114.10
25 133.70 25 116.90
26 137.00 26 119.70
27 140.30 27 122.50
28 143.60 28 125.30
29 146.90 29 128.10
30 150.20 30 130.90
31 153.50 31 133.70
32 156.80 32 136.50
33 160.10 33 139.30
34 163.40 34 142.10
35 166.70 35 144.90
36 170.00 36 147.70
37 173.30 37 150.50
38 176.60 38 153.30
39 179.90 39 156.10
40 183.20 40 158.90
41 186.50 41 161.70
42 189.80 42 164.50
43 193.10 43 167.30
44 196.40 44 170.10
45 199.70 45 172.90
600mm dia700mm dia
Page 18
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 18/22
46 203.00 46 175.70
47 206.30 47 178.50
48 209.60 48 181.30
49 212.90 49 184.10
50 216.20 50 186.90
51 219.50 51 189.70
52 222.80 52 192.50
53 226.10 53 195.30
54 229.40 54 198.10
55 232.70 55 200.90
56 236.00 56 203.70
57 239.30 57 206.50
58 242.60 58 209.30
59 245.90 59 212.10
60 249.20 60 214.90
61 252.50 61 217.70
62 255.80 62 220.50
63 259.10 63 223.30
64 262.40 64 226.10
65 265.70 65 228.90
66 269.00 66 231.70
67 272.30 67 234.50
68 275.60 68 237.30
69 278.90 69 240.10
70 282.20 70 242.90
71 285.50 71 245.70
72 288.80 72 248.50
73 292.10 73 251.30
74 295.40 74 254.10
75 298.70 75 256.90
76 302.00 76 259.70
77 305.30 77 262.50
78 308.60 78 265.30
79 311.90 79 268.10
80 315.20 80 270.90
81 318.50 81 273.70
82 321.80 82 276.50
83 325.10 83 279.30
84 328.40 84 282.10
85 331.70 85 284.90
86 335.00 86 287.70
87 338.30 87 290.50
88 341.60 88 293.30
89 344.90 89 296.10
90 348.20 90 298.90
91 351.50 91 301.70
92 354.80 92 304.50
93 358.10 93 307.30
94 361.40 94 310.10
95 364.70 95 312.90
Page 19
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 19/22
96 368.00 96 315.70
97 371.30 97 318.50
98 374.60 98 321.30
99 377.90 99 324.10
100 381.20 100 326.90
101 384.50 101 329.70
102 387.80 102 332.50
103 391.10 103 335.30
104 394.40 104 338.10
105 397.70 105 340.90
106 401.00 106 343.70
107 404.30 107 346.50
108 407.60 108 349.30
109 410.90 109 352.10
110 414.20 110 354.90
111 417.50 111 357.70
112 420.80 112 360.50
113 424.10 113 363.30
114 427.40 114 366.10
115 430.70 115 368.90
116 434.00 116 371.70
117 437.30 117 374.50
118 440.60 118 377.30
119 443.90 119 380.10
120 447.20 120 382.90
121 450.50 121 385.70
122 453.80 122 388.50
123 457.10 123 391.30
124 460.40 124 394.10
125 463.70 125 396.90
126 467.00 126 399.70
127 470.30 127 402.50
128 473.60 128 405.30
129 476.90 129 408.10
130 480.20 130 410.90
131 483.50 131 413.70
132 486.80 132 416.50
133 490.10 133 419.30
134 493.40 134 422.10
135 496.70 135 424.90
136 500.00 136 427.70
137 503.30 137 430.50
138 506.60 138 433.30
139 509.90 139 436.10
140 513.20 140 438.90
141 516.50 141 441.70
142 519.80 142 444.50
143 523.10 143 447.30
144 526.40 144 450.10
145 529.70 145 452.90
Page 20
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 20/22
146 533.00 146 455.70
147 536.30 147 458.50
148 539.60 148 461.30
149 542.90 149 464.10
150 546.20 150 466.90
Page 21
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 21/22
Estimate Cost Rs:1,00,000
Flood Damage to the C.D.Works and C.C.road in
B.C.Colony (Balance Work) at Brahmanakokur of
Nandikotkur Mandal.
Estimate
Name of the work
Panchayat Raj Engineering
Page 22
8/2/2019 Final_Detailed Estiamte ForB.kotkur FDR
http://slidepdf.com/reader/full/finaldetailed-estiamte-forbkotkur-fdr 22/22
Lakhs
1
2
3
Construction of Granular shoulders using Gravel & Sand by providing well
graded material, spreading in uniform layers with motor grader on prepared
surface, mixing by mix in place method with rotavator at OMC, and
compacting with Static Roller 80-100 kN capacity to achieve the desired
density, complete as per Technical Specification Clause 402 MORD, Butexcluding VAT charges.
Construction of Unreinforced CC pavement with M30 design mix etc complete
Thus providing above items including 0.50% Q C charges, 4.00 % Vat and L.S. for
other unforseen items This estimate is prepared for Rs.1,00,000.The Estimate is prepared
Current S S R (2010-11) and the work will be carried out as per APDSS, .
ASSISTANT ENGINEER
MP, NANDIKOTKUR
Construction of 0.60m Vent RCC deck Slab Culverts 3 Nos.
Specification Report to accompany the work "Flood Damage Repairs
to the C.D.Works and CC road in B.C.Colony (Balance Work) at Brahmanakotkur
of Nandikotkur Mandal
Estimate Rs:1.00
The above work is Proposed under F.D.R. Grant and the same was administratively
sanctioned vide proceedings Rc. No. AEE1/FDR/2009 dated 29.12.2010 of the District Collector
Kurnool.for Rs.1.00 lakhs.
Hence necessary Estimate is prepared with the following provisions
SPECIFICATION REPORT