Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Jul 21, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

3325 Hilliard Rome Rd.

Hilliard, Ohio 43026

P: 614.798.8828 f: 614.798.8839

www.dejongrichter.com

Final Report

May 19, 2015

Page 2: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community
Page 3: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

1 5/19/2015

Table of Contents

PAGE

Acknowledgements 2

Mission Statement 3

Process 4

Recommendations 5

Appendix 19

Background Report 20

Capacity & Middle/High School Utilization Report 60

Enrollment Projections 201

Facility Assessment Report 309

Live/Attend Analysis 649

Community Dialogue #1 Results 654

Community Dialogue #2 Results 693

Page 4: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

2 5/19/2015

Acknowledgements

DeJONG-RICHTER would like to thank the Sullivan County Department of Education’s students, staff, Board of Education, Steering Committee,

and community for their commitment and dedication to the Facility Master Planning Process.

Sullivan County Department of Education

Dr. Jubal Yennie, Director of Schools

Board of Education

Jack Bales—Vice-Chairman

Todd Broughton

Betty Combs

Jerry Greene

Michael Hughes

Randall Jones

Dan Wells—Chairman

DeJONG-RICHTER

Tracy Richter, REFP, C.E.O.

Ann Hoffsis, REFP, Director of Enrollment Projection Services

Matt Sachs, GIS Analyst

Chloe Anderson

Sarah Aulds

David Bays

Rachel Burdine

Melanie Calhoun

Joey Carico

LaDonna Compton

Cathy Davenport

Dennis Houser

Alesia Dinsmore

Tabitha Ellis

Gary Estepp

Christy Frazier

Doug Giles

Rachel Hall

Mark Harr

Jennifer Hutson

Randall Jones

Brandy Kisner

Lew Kizer

Valerie Lick

Jacob Maine

Mike McQueen

Stephanie Miller

Darrell Moore

Becky Olinger

Melissa Osborn

Sonya Owens

Brent Palmer

Amanda Pitts

Evelyn Rafalowski

Mandy Rupe

Margaret Seale

Mike Smith

Kristy Sproles

Angie Stanley

Angie Sybert

Payton Vaughn

Ron Whitacre

Chayten Williams

Nicole Wolfe

Steering Committee

Page 5: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

3 5/19/2015

Mission Statement

The Sullivan County Board of Education, in partnership with students, families, employees and community, will utilize all available resources to

provide a collaborative learning environment that will enable each student to reach his/her maximum potential as a productive and

successful citizen in an ever changing global and technological environment.

Vision

The vision of the Sullivan County Department of Education is to prepare each student and teacher to meet the challenges of the world

today and tomorrow with the skills and desire for lifelong learning.

Goals

1. Sullivan County will demonstrate sustained growth in student achievement.

2. Sullivan County will allocate resources to increase efficiency and improve quality.

3. Sullivan County will increase and improve stakeholder partnerships and satisfaction.

Page 6: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

4 5/19/2015

Comprehensive Facility Plan Process—September 2014 to May 2015

Community

Engagement

Community Dialogue #1

Nov. 3, 2014

Community Dialogue #2

Jan. 27, 2015

Project Start-

Up

Plan for Planning

Goals

Schedule

Decision Points

Futures Conference

May 16, 2014

Assemble Steering Committee

Guides Process

Review Documents

Includes Parents, Staff & Community Members

Final Report

Background Report

Enrollment Projection Report

Capacity Report

Educational Adequacy Report

Building Condition Report

Options Packet

Recommendations Packet

Final Report

Board Updates

& Work

Sessions

Board Update

Oct. 2, 2014

Options Development Work

Session

Dec. 4, 2014

Board Update

Dec. 4, 2014

Internal Work Session

Feb. 10, 2015

Board Work Session

Mar. 4, 2015

Final Board Presentation

May 4, 2015

Steering

Committee

Steering Committee Mtg. #1

Sept. 25, 2014

Steering Committee Mtg. #2

Oct. 14, 2014

Steering Committee Mtg. #3

Dec. 16, 2014

Steering Committee Mtg. #4

Jan. 12, 2014

Steering Committee Mtg. #5

Mar. 3, 2015

Data

Collection &

Analysis

Background Data

Facility Data

Enrollment

Programs

Geographic Information System

[GIS]

Student Data

Attendance Boundaries

Housing & Demographics

Geographic Base Layers

Capacity, Educational Adequacy &

Facility Assessments

Master Schedules

Floor Plans

Page 7: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

5 5/19/2015

Recommendations - Concept A

High Schools

Build 2 new high schools - 1,700 capacity, sites TBD

Central HS - Discontinue use

East HS - Convert to middle school

North HS - Discontinue use

South HS - Convert to middle school

Middle Schools

3 grades 6-8 middle schools at current East HS, Holston MS and current South HS

1 grades K-8 school at Ketron - 25,000 Sq. foot addition to increase capacity

Blountville MS - Discontinue use, boundary change to Holston MS

Bluff City MS - Discontinue use, boundary change to East MS

Colonial Heights MS - Discontinue use, boundary change to South MS

Holston Valley MS - Discontinue use, boundary change to East MS

Mary Hughes (6-8) - Discontinue use, boundary change to East MS and Holston MS

Sullivan Gardens MS - Discontinue use, boundary change to South MS

Elementary Schools

2 new construction elementary schools - Blountville and Mary Hughes

Renovation/maintenance to Bluff City ES, Central Heights ES, Emmett ES, Indian Springs ES, Rock Springs ES, Sullivan Gardens ES

Miller Perry ES - Discontinue use, boundary TBD

Holston ES - Discontinue use, boundary change to new Blountville ES

Weaver ES - Discontinue use, boundary change to Bluff City ES and Emmett ES

Page 8: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

6 5/19/2015

Recommendations - Concept A

Close: 1,045,184 Sq. Feet

Central HS - 205,973

North HS - 258,507

Blountville MS - 65,904

Bluff City MS - 81,164

Colonial Heights MS - 59,326

Holston Valley MS - 45,664

Sullivan Gardens MS - 63,500

Blountville ES - 65,439

Holston ES - 0

Mary Hughes ES - 68,934

Miller Perry ES - 83,080

Weaver ES - 48,503

New Square Footage: 710,000 Sq. Feet

New HS - 275,000

New HS - 275,000

Ketron K-8 - 25,000

Blountville ES - 75,000

Mary Hughes ES - 60,000

Net Sq. Footage: -335,184

Previous Building Count: 21

New Building Count: 14

Page 9: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

7 5/19/2015

Recommendations - Concept A

Proposed Feeder Patterns:

New East High School New West High School

Holston MS

New Blountville ES

(Combines Blountville ES & Holston ES)

New Mary Hughes ES

Holston MS

Indian Spring ES

Ketron K-8

Central Heights ES

Ketron ES (K-5) East MS (Old HS Building)

Bluff City ES

Emmett ES South MS (Old HS Building)

Rock Springs ES

Sullivan Gardens ES

Page 10: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

8 5/19/2015

Recommendations - Concept A

Projected Costs:

Project Action Cost

New High School New Construction $65,000,000

New High School New Construction $65,000,000

South HS Renovation for MS $10,000,000

East HS Renovation for MS $10,000,000

Ketron Addition Construction $8,000,000

Blountville ES New Construction $13,500,000

Mary Hughes ES New Construction $11,000,000

Facility Maintenance

& Renovations$13,000,000

Potential Demolition $3,950,000

$199,450,000

Concept A - Recommendation

Estimated Costs

Estimated Total Costs

Estimated Staff Savings: $5,742,000

Estimated Net Utility Savings: $403,425

Total $6,145,425

Estimated Cost Savings:

Page 11: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

9 5/19/2015

Recommendations - Concept B

High Schools

Build 2 new high schools - 1,200 capacity, sites TBD

Renovate South HS

Central HS - Discontinue use

East HS - Convert to middle school

North HS - Discontinue use

Middle Schools

3 grades 6-8 middle schools at current East HS, Holston MS and Rock Springs (renovation and expansion)

1 grades K-8 school at Ketron - 25,000 Sq. foot addition to increase capacity

Blountville MS - Discontinue use, boundary change to Holston MS

Bluff City MS - Discontinue use, boundary change to East MS

Colonial Heights MS - Discontinue use, boundary change to South MS

Holston Valley MS - Discontinue use, boundary change to East MS

Mary Hughes (6-8) - Discontinue use, boundary change to East MS and Holston MS

Sullivan Gardens MS - Discontinue use, boundary change to South MS

Elementary Schools

2 new construction elementary schools - Blountville and Mary Hughes

Renovation/maintenance to Bluff City ES, Central Heights ES, Emmett ES, Indian Springs ES, Miller Perry ES, Sullivan Gardens ES

Rock Springs ES - Renovation to middle school

Holston ES - Discontinue use, boundary change to new Blountville ES

Weaver ES - Discontinue use, boundary change to Bluff City ES and Emmett ES

Page 12: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

10 5/19/2015

Recommendations - Concept B

Close: 962,104 Sq. Feet

Central HS - 205,973

North HS - 258,507

Blountville MS - 65,904

Bluff City MS - 81,164

Colonial Heights MS - 59,326

Holston Valley MS - 45,664

Sullivan Gardens MS - 63,500

Blountville ES - 65,439

Holston ES - 0

Mary Hughes ES - 68,934

Weaver ES - 48,503

New Square Footage: 568,500 Sq. Feet

New HS - 198,000

New HS - 198,000

Ketron K-8 - 25,000

Blountville ES - 87,500

Mary Hughes ES - 60,000

Net Sq. Footage: -393,604

Previous Building Count: 21

New Building Count: 15

Page 13: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

11 5/19/2015

Recommendations - Concept B

Proposed Feeder Patterns:

South High School New East High School

Ketron (K-8)

Ketron (K-5)

East MS (Old HS Building)

Bluff City ES

Emmett ES

New Mary Hughes ES Rock Springs MS

Miller Perry ES

Sullivan Gardens ES

New Central High School

Holston MS

New Blountville ES

(Combines Blountville ES & Holston ES)

Central Heights ES

Indian Springs ES

Page 14: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

12 5/19/2015

Recommendations - Concept B

Projected Costs:

Project Action Cost

New High School New Construction $45,000,000

New High School New Construction $45,000,000

South HS Renovation $10,000,000

East HS Renovation to MS $10,000,000

Rock Springs ES Renovation to MS $10,000,000

Ketron Addition Construction $8,000,000

Blountville ES New Construction $15,500,000

Mary Hughes ES New Construction $11,000,000

Facility Maintenance

& Renovations$14,500,000

Potential Demolition $3,500,000

$172,500,000

Concept B - Recommendation

Estimated Costs

Estimated Total Costs

Estimated Cost Savings:

Estimated Staff Savings: $4,391,000

Estimated Net Utility Savings: $554,086

Total $4,945,086

Page 15: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

13 5/19/2015

Recommendations - Concept C

High Schools

Renovate 3 high schools - Central HS, East HS, South HS

North HS - Convert to MS, boundary change to South HS

Middle Schools

Renovate 4 middle schools- Bluff City MS, Holston MS, Holston Valley MS, North (Current HS)

Colonial Heights MS - Discontinue use, boundary change to North MS

Mary Hughes (6-8) - Discontinue use, boundary change to East MS and Holston MS

Sullivan Gardens MS - Discontinue use, boundary change to North MS

Elementary Schools

2 new construction elementary schools - Blountville and Mary Hughes

Renovation/maintenance to Bluff City ES, Central Heights ES, Emmett ES, Indian Springs ES, Miller Perry ES, Sullivan Gardens ES

Rock Springs ES - Renovation to middle school

Holston ES - Discontinue use, boundary change to new Blountville ES

Weaver ES - Discontinue use, boundary change to Bluff City ES and Emmett ES

Page 16: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

14 5/19/2015

Recommendations - Concept C

Close: 405,373 Sq. Feet

Blountville MS - 65,904

Colonial Heights MS - 59,326

Sullivan Gardens MS - 63,500

Blountville ES - 65,439

Mary Hughes ES - 68,934

Miller Perry ES - 83,080

New Square Footage: 114,000 Sq. Feet

Blountville ES - 65,000

Mary Hughes ES - 49,000

Net Sq. Footage: -291,373

Previous Building Count: 21

New Building Count: 17

Page 17: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

15 5/19/2015

Recommendations - Concept C

Proposed Feeder Patterns:

South High School East High School

North MS (Old HS Building)

Ketron ES

Rock Springs ES

Sullivan Gardens ES

Central Heights ES (1/2)

Bluff City MS

Bluff City ES

New Mary Hughes ES

Weaver ES (1/2)

Holston Valley MS

Emmett ES

Weaver ES (1/2)

Central High School

Holston MS

New Blountville ES

Holston ES

Indian Springs ES

Central Heights ES (1/2)

New Mary Hughes ES (1/2)

Page 18: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

16 5/19/2015

Recommendations - Concept C

Projected Costs:

Project Action Cost

Central HS Renovation $15,000,000

East HS Renovation $15,000,000

South HS Renovation $15,000,000

North HS Renovation to MS $15,000,000

Elementary Schools Program Renovations $15,000,000

Blountville ES New Construction $11,500,000

Mary Hughes ES New Construction $8,500,000

Facility Maintenance

& Renovations$25,000,000

$120,000,000

Concept C - Recommendation

Estimated Costs

Estimated Total Costs

Estimated Cost Savings:

Estimated Staff Savings: $4,213,000

Estimated Net Utility Savings: $362,638

Total $4,575,638

Page 19: Final Report - Sullivan County€¦ · 19/05/2015  · Final Report 4 5/19/2015 Comprehensive Facility Plan Process—September 2014 to May 2015 Final Board Community Engagement Community

Final Report

17 5/19/2015

Appendix