Top Banner
INTERNATIONAL FINANCING ON POWER PROJECTS 1 SUMMER TRAINING REPORT On “International Financing On Power Projects”  at For the period 13 June, 2011 to 05 August, 2011 Under the guidance of Shri K. Sreekant Additional General Manager (IF) Submitted By Sandeep Anand 2 nd Year Student of MBA in Power Management Roll no. 79 Batch 9 th (2010-2012) Sector-33, Faridabad-121003, Haryana Affiliated to Maharishi Dayanand University, Rohtak 
99

Final Report Submit 4 Mdu & Clg

Apr 07, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 1/99

INTERNATIONAL FINANCING ON POWER PROJECTS

1

SUMMER TRAINING REPORT 

On

“International Financing On Power Projects” 

at

For the period

13 June, 2011 to 05 August, 2011

Under the guidance of 

Shri K. Sreekant

Additional General Manager (IF)

Submitted By

Sandeep Anand

2nd Year Student of MBA in Power Management

Roll no. 79

Batch 9th

(2010-2012)

Sector-33, Faridabad-121003, Haryana

Affiliated to

Maharishi Dayanand University, Rohtak 

Page 2: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 2/99

INTERNATIONAL FINANCING ON POWER PROJECTS

2

DECLARATION 

I, Sandeep Anand, (Roll No. 79), MBA - Power Management (2010-2012 Batch), of National

Power Training Institute, Faridabad, hereby declare that the summer training report Entitled

“INTERNATIONAL FINANCING ON POWER PROJECTS” 

Is an original work and the same has not been submitted to any other institute for the award of 

Any other degree.

A seminar presentation of the Training report was made on_________________ and the

Suggestions as approved by the faculty were duly incorporated.

K.P.S.Parmar

Presentation in- charge

NPTI, Faridabad M.B.A (9th

Batch), NPTI

Counter signed:-

(Director/ Principle of the institution)

Page 3: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 3/99

INTERNATIONAL FINANCING ON POWER PROJECTS

3

CERTIFICATE

This is to certify that the summer project work of Sandeep Anand titled ―INTERNATIONAL

FINANCING ON POWER PROJECTS” is an original work and that this work has not been

assigned to anybody in any form. The project work was carried from 13-June-2011 till 05-

August-2011 at NTPC Ltd., Corporate Centre, Scope Complex, Core7 Institutional area, Lodi

Road, New Delhi-110003.

Date: August- 05- 2011

Shri K. Sreekant

Additional General Manager (IF)

NTPC Ltd. 

Page 4: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 4/99

INTERNATIONAL FINANCING ON POWER PROJECTS

4

ACKNOWLEDGEMENT

I am having great pleasure to present this report entitled “INTERNATIONAL

FINANCING ON POWER PROJECTS”. I take this opportunity to express my sincere

thanks to all who contributed to make this a success.

First of all I would like to take the opportunity to thanks Shri K. Sreekant, Additional

General Manager, NTPC LTD. for giving me the opportunity to undergo my summer

internship at NTPC LTD., Scope Complex, Core7 Institutional area, Lodi Road, New

Delhi-110003.

I would like to express my sincere thanks to my guide Mr. Sunil Kumar Goyel for

providing me the necessary resources for carrying out the study and for his timely and

continued support and more importantly his guidance without which this report would have

been incomplete.

I wish to thank , Ms. Farida Khan, Mr. K.P.S Parmar (Project guide), Mr. Amit

Kumar Mishra, Mrs. Indu Maheshwari (Dy. Director), Mr. Rohit Verma

(Dy.Director), CAMPS, NPTI (National Power Training Institute) for their valuable

inputs.

I wish to make a special mention of  Mrs. Manju Mam (Dy. Director), Mr. S.K.

Chaudhary (Director), CAMPS, NPTI and  Mr. J.S.S. Rao (Principal Director),

CAMPS, NPTI for providing me an opportunity to do my summer internship at NTPC

Ltd. which was a great learning for me.

I am greatful to my friends who gave me the moral support in my times of difficulties. Last

but not the least I would like to express my special thanks to my family for their

continuous motivation and support.

Sandeep Anand

Page 5: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 5/99

INTERNATIONAL FINANCING ON POWER PROJECTS

5

ABBREVIATIONS 

ADB- Asian Development Bank 

ECA- Economic Credit Agency

AFBD- African Development Fund

EIB- European Investment Bank 

EBRD- European Bank for Reconstruction & Development

JBI- Japan Bank of International Corporation

FERM- Foreign Exchange Risk Management

OCF- Operating Cash Flow

NCF- Free Cash Flow

IBRD- International Bank for Reconstruction & Development

IMF- International Monetary Fund

TASF- Technical Assistance Development Fund

JSF- Japan Special Fund

DMC- Developing Member Countries

FIAS- Foreign Investment Advisory Service

MIGA- Multilateral Investment Guarantee Agency

FIL- Foreign Investment Loan

SIL- Special Investment Loan

SIM- Sector Investment & Maintenance Loan

APL- Adaptable Program Loan

Page 6: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 6/99

INTERNATIONAL FINANCING ON POWER PROJECTS

6

LIL- Learning & Innovation Loan

FIL- Foreign Investment Loan

ERL- Emergency Recovery Loan

SAL- Structural Adjustment Loan

SAL- Sector Adjustment Loan

PSAL- Programmatic Structural Adjustment Loan

SSAL- Special Structural Adjustment Loan

RL- Rehabilitation Loan

DRL- Debt Reduction Loan

IMF- Internationally Monetary Fund

WB- World Bank 

FEMA- Foreign Exchange Management Act

FERV- Foreign Exchange Rate Variation

WACC- Weighted Average Cost of Capital

NPV- Net Present Value

IRR- Interest Rate of Return

UNCITRAL- United Nations Commission on International Trade Law

OPIC- Overseas Private Investment Corporation

Page 7: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 7/99

INTERNATIONAL FINANCING ON POWER PROJECTS

7

Table of Contents

1. EXECUTIVE SUMMARY................................................................................................................. 10

2.  ORGANIZATION PROFILE ............................................................................................................. 11

2.1 Vision ................................................................................................................................................ 11

Mission: - ................................................................................................................................................ 11

Core Value: - ........................................................................................................................................... 11

2.2Diversified Growth: - ......................................................................................................................... 11

2.3 Future Capacity Additions: - ............................................................................................................. 13

2.4 Subsidiaries: - .................................................................................................................................... 14

2.5Business Development: - .................................................................................................................... 15

2.6Balance Sheet: - .................................................................................................................................. 16

2.7 SWOT analysis of NTPC .................................................................................................................. 17

3.  OBJECTIVE OF THE PROJECT....................................................................................................... 19

4.  SIGNIFICANCE OF THE PROJECT ................................................................................................ 20

5.  SCOPE OF THE PROJECT ............................................................................................................... 20

6.  RESEARCH METHODOLOGY OF THE PROJECT ....................................................................... 21

7. INTRODUCTION .............................................................................................................................. 22

8. KEY TERM OF INTERNATIONAL FINANCE............................................................................... 27

9.  DIFFERENCE BETWEEN DOMESTIC FINANCE & INTERNATIONAL FINANCE ............. 33

10.  ROLE OF WORLD BANK, ADB, IFC ......................................................................................... 34

11.  TYPES OF LOAN ...................................................................................................................... 40

11.1 Investment loans ......................................................................................................................... 40

11.2Adjustment loans: - Adjustment loan........................................................................................... 40

11.3Specific Investment Loan............................................................................................................. 40

11.4Sector Investment and Maintenance Loan ................................................................................... 40

11.5Adaptable Program Loan ............................................................................................................. 41

11.6Learning and Innovation Loan ..................................................................................................... 41

11.7Technical Assistance Loan........................................................................................................... 42

11.8Financial Intermediary Loan ........................................................................................................ 42

11.9Emergency Recovery Loan .......................................................................................................... 42

11.10Structural Adjustment Loan ....................................................................................................... 43

11.11Sector Adjustment Loan............................................................................................................. 43

Page 8: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 8/99

INTERNATIONAL FINANCING ON POWER PROJECTS

8

11.12Programmatic Structural Adjustment Loan ............................................................................... 43

11.13Special Structural Adjustment Loan .......................................................................................... 44

11.14Rehabilitation Loan.................................................................................................................... 44

11.15Debt Reduction Loan ................................................................................................................. 44

12.  LOAN AGREEMENT .................................................................................................................... 45

12.1.1 ARTICLE I DEFINITIONS..................................................................................................... 45

12.1.2 ARTICLE II LOAN ACCOUNT - COMMITMENT CHARGE - SPECIAL COMMITMENT

CHARGE AND REPAYMENT ......................................................................................................... 47

12.1.3 ARTICLE III CURRENCY PROVISIONS............................................................................. 50

12.1.4 ARTICLE IV DISBURSEMENT OF THE LOAN ................................................................. 53

12.1.5 ARTICLE V CANCELLATION AND SUSPENSION .......................................................... 55

12.1.6 ARTICLE VI ACCELERATION TO MATURITY................................................................ 60

12.1.7 ARTICLE VII TAXES ............................................................................................................ 61

12.1.8 ARTICLE VIII PROJECT IMPLEMENTATION - COOPERATION AND INFORMATION-

FINANCIAL AND OTHER INFORMATION - NEGATIVE PLEDGE (PARI PASSU) ................ 61

12.1.9 ARTICLE IX - SETTLEMENT OF DISPUTES - APPLICABLE LAW ............................... 64

13.  WHY NTPC IS SUPERIOR THAN OTHERS?............................................................................. 66

14.  REGULATORY FRAMEWORK FOR INTERNATIONAL FINANCE ...................................... 70

14.1 EXTERNAL COMMERCIAL BORROWINGS (ECB) ............................................................ 70

15. RISKS FOR THE INVESTORS..................................................................................................... 78

15.1 Risk mitigation ............................................................................................................................ 78

15.2 Construction risk : - ...................................................................................................................... 78

15.3 Operating risk: - .......................................................................................................................... 78

15.4 Market risk: -............................................................................................................................... 79

15.5 Interest rate risk : - ....................................................................................................................... 79

15.6 Foreign exchange risk : - .............................................................................................................. 80

15.7 Payment risk : - ............................................................................................................................ 80

15.8 Regulatory risk : - ......................................................................................................................... 80

15.9 Political risk : - ............................................................................................................................. 81

15.10 Arrangements for risk mitigation .............................................................................................. 81

16.  DATA ANALYSIS OF THE PROJECT ........................................................................................ 82

17.  CONCLUSION............................................................................................................................... 97

Page 9: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 9/99

INTERNATIONAL FINANCING ON POWER PROJECTS

9

18.  RECOMMENDATION & SUGGESTION .................................................................................... 97

19.  BIBILIOGRAPHY ......................................................................................................................... 98

LIST OF TABLE

Table 6.1:International Financiers of Coal fired plants ............................................................................... 22

Table 6.2: - Capacity Addition Breakup (XIth) power plant ........................................................................ 23

Table 6.3: Financial Closure Scenario For Private Capacity as per 11th plan ............................................. 25

Table 6.4: Investment ................................................................................................................................. 25

Table 15.1: Opening Loan balance sheet of all banks ................................................................................ 82

Table 15.2: Loan wise Allocation of Interest (Net Charge) as on 04/07/2011 ............................................ 83

Table 15.3: Weighted average of KFW Bank ............................................................................................... 87Table 15.4: Guarantee fee payable on IBRD For the period 01/04/2011 to 04/07/2011 .......................... 89

Table 15.5: Guarantee fee of World Bank allocated on different projects ................................................ 89

Table 15.6: Foreign Exchange Rate Variation (FERV) of KFW Bank on different projects .......................... 90

Table 15.7: Interest allocation of KFW Bank on different projects............................................................. 91

Table 15.8: Differential Interest of all banks............................................................................................... 95

LIST OF FIGURE

Figure 6.1: XIth plan Capacity Addition Targets & Achievement ................................................................ 23

Figure 6.2: Capacity Addition Growth in plan wise manner ....................................................................... 24

Figure 6.3: Capacity Addition Private Sector ............................................................................................. 24

Figure 6.4: Investment in Power Sector ...................................................................................................... 25

Figure 6.5: Investment targets by Government .......................................................................................... 26

Page 10: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 10/99

INTERNATIONAL FINANCING ON POWER PROJECTS

10

1.  EXECUTIVE SUMMARY 

The report is all about the Maharatna Company (NTPC Ltd.) which is an integrated power

producer and International Financing on power Projects. The introduction part deals with the

role of public international financial institutions like Multinational Development Bank and

Economic credit agency. Both of them has important role in international financing on coal fired

power plants. The report elaborates various internationally financed projects on coal fired power

plants.

The report shows the increase in the capacity addition during XIth plan of all different sectors

like private sector, state sector, central sector and all conventional & non- conventional sources

of energy .The graph of capacity addition shows relationship between different sectors, its target

& achieved value. A comparison of capacity addition during five year plans is shown with the

help of graph which clearly indicates the amount of capacity added during these plans. The

capacity addition in private sector comprises of different domestic companies which have

different capacity addition values. During study of report we see financial closure of private

capacity of XIth plan; we can calculate the total capital expenditure for conventional & non  – 

conventional source of energy. The report also includes the study of data of investment in

different sector as well as conventional & non-conventional source of energy. The report also

signifies the investments done by govt. and private players in power sector during Xth, XIth and

XIIth plan (projected).

The report includes various key aspects of international finance which have been discussed in the

report for clear understanding of the subject, exchange rate which distinguish the domestic &

international financing, role of Multinational Development Bank (World Bank, Asian

Development Bank, International Finance Corporation & its function), types of loan, loan

agreement which plays a vital role and the risk involved for foreign investors.

Report discusses international financial funding of domestic companies like TATA POWER,

RELIANCE POWER, NTPC, and ADANI POWER.

RBI is the regulatory body responsible for the regulatory framework of international finance on

External commercial Borrowing.

Page 11: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 11/99

INTERNATIONAL FINANCING ON POWER PROJECTS

11

2.  ORGANIZATION PROFILE

NTPC, India's largest power company, was set up in 1975 to accelerate power development in

India. It is emerging as an ‗Integrated Power Major‘, with a significant presence in the entire

value chain of power generation business.

 NTPC ranked 341st in the ‗2010, Forbes Global 2000‘ ranking of the World‘s biggest companies

with a current generating capacity of 34,854 MW. NTPC has embarked on plans to become a

75,000 MW company by 2017.

2.1 Vision: - “To be the world’s largest and best power producer, powering India’s growth.” 

Mission: -  ―Develop and provide reliable power, related products and services at competitive

prices, integrating multiple energy sources with innovative and eco-friendly technologies and

contribute to society.‖ 

Core Value: - BCOMIT

  Business Ethics

  Customer Focus

  Organizational & Professional Pride

  Mutual Respect & Trust

  Innovation & Speed

  Total Quality for Excellence

2.2Diversified Growth: - 

As per new corporate plan, NTPC plans to become a 75 GW company by the year 2017 and

envisages to have an installed capacity of 128 GW by the year 2032 with a well-diversified fuel

mix comprising 56% coal, 16% gas, 11% nuclear energy, 9% renewable energy and 8% hydro

power based capacity.

As such, by the year 2032, 28% of NTPC‘s installed generating capacity will be based on carbon

free energy sources. Further, the coal based capacity will increasingly be based on high-efficient-

low-emission technologies such as Super-critical and Ultra-Super-critical. Along with this

Page 12: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 12/99

INTERNATIONAL FINANCING ON POWER PROJECTS

12

growth, NTPC will utilize a strategic mix of options to ensure fuel security for its fleet of power

stations.

Looking at the opportunities coming its way, due to changes in the business environment, NTPC

made changes in its strategy and diversified in the business adjacencies along the energy value

chain. In its pursuit of diversification NTPC has developed strategic alliances and joint ventures

with leading national and international companies. NTPC has also made long strides in

developing its Ash Utilization business.

Hydro Power: In order to give impetus to hydro power growth in the country and to have a

balanced portfolio of power generation, NTPC entered hydro power business with the 800 MW

Koldam hydro projects in Himachal Pradesh. Two more projects have also been taken up in

Uttarakhand. A wholly owned subsidiary, NTPC Hydro Ltd., is setting up hydro projects of capacities up to 250 MW.

Renewable Energy: In order to broad base its fuel mix NTPC has plan of capacity addition of 

about 1,000 MW through renewable resources by 2017.

Nuclear Power: A Joint Venture Company "Anushakti Vidhyut Nigam Ltd." has been formed

(with 51% stake of NPCIL and 49% stake of NTPC) for development of nuclear power projects

in the country.

Coal Mining: In a major backward integration move to create fuel security, NTPC has ventured

into coal mining business with an aim to meet about 20% of its coal requirement from its captive

mines by 2017. The Government of India has so far allotted 7 coal blocks to NTPC, including 2

blocks to be developed through joint venture route.

Power Trading: 'NTPC Vidyut Vyapar Nigam Ltd.' (NVVN), a wholly owned subsidiary was

created for trading power leading to optimal utilization of NTPC‘s assets. It is the s econd largestpower trading company in the country. In order to facilitate power trading in the country,

‗National Power Exchange Ltd.‘, a JV of NTPC, NHPC, PFC and TCS has been formed for 

operating a Power Exchange.

Page 13: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 13/99

INTERNATIONAL FINANCING ON POWER PROJECTS

13

Ash Business: NTPC has focused on the utilization of ash generated by its power stations to

convert the challenge of ash disposal into an opportunity. Ash is being used as a raw material

input by cement companies and brick manufacturers. NVVN is engaged in the business of Fly

Ash export and sale to domestic customers. Joint ventures with cement companies are being

planned to set up cement grinding units in the vicinity of NTPC stations.

Power Distribution:  ‗NTPC Electric Supply Company Ltd.‘ (NESCL), a wholly owned

subsidiary of NTPC, was set up for distribution of power. NESCL is actively engaged in ‗Rajiv

Gandhi Gramin Vidyutikaran Yojana‘programme for rural electrification. 

Equipment Manufacturing: Enormous growth in power sector necessitates augmentation of 

power equipment manufacturing capacity. NTPC has formed JVs with BHEL and Bharat Forge

Ltd. for power plant equipment manufacturing. NTPC has also acquired stake in Transformersand Electricals Kerala Ltd. (TELK) for manufacturing and repair of transformers.

2.3 Future Capacity Additions: - 

NTPC has formulated a long term Corporate Plan up to 2032. In line with the Corporate Plan, the

capacity addition under implementation stage is presented below:

PROJECT STATE MW

Coal 

1. Indira Gandhi STPP- JV with IPGCL & HPGCL ( 3 x 500) Haryana 1000

2. Sipat I (3 x 660) Chhattisgarh 1980

3. Simhadri II Unit - IV( 500) Andhra Pradesh 500

4. velour I -JV with TNEB ( 2 x 500) Tamilnadu 1000

5. Velour Stage-I Phase-II -JV with TNEB ( 1 x 500) Tamilnadu 500

6. Bongaigaon(3 x 250) Assam 7507. Mauda ( 2 x 500) Maharashtra 1000

8. Rihand III(2X500) Uttar Pradesh 1000

9. Vindhyachal-IV (2X500) Madhya Pradesh 1000

10. Muzaffarpur Expansion (2x195) – JV with BSEB Bihar 390

Page 14: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 14/99

INTERNATIONAL FINANCING ON POWER PROJECTS

14

11. Nabinagar TPP-JV with Railways (4 x 250) Bihar 1000

12. Barh II (2 X 660) Bihar 1320

13. Barh I (3 X 660) Bihar 1980

Hydro 1. Koldam HEPP ( 4 x 200) Himachal Pradesh 800

2. Tapovan Vishnugad HEPP (4 x 130) Uttarakhand 520

3. Singrauli CW Discharge(Small Hydro) Uttar Pradesh 8

Total  14748 

2.4 Subsidiaries: - 

NTPC Electric Supply Company Ltd. (NESCL)

The company was formed on August 21, 2002. It is a wholly owned subsidiary company of 

NTPC with the objective of making a foray into the business of distribution and supply of 

electrical energy, as a sequel to reforms initiated in the power sector.

NTPC Vidyut Vyapar Nigam Ltd. (NVVN)

The company was formed on November 1, 2002, as a wholly owned subsidiary company of 

  NTPC. The company‘s objective is to undertake sale and purchase of electric power, to

effectively utilize installed capacity and thus enable reduction in the cost of power.

NTPC Hydro Ltd. (NHL)

The company was formed on December 12, 2002, as a wholly owned subsidiary company of 

NTPC with an objective to develop small and medium hydroelectric power projects of up to 250

MW.

Pipavav Power Development Co. Ltd. (PPDCL)

A memorandum of understanding was signed between NTPC, Gujarat Power Corporation

Limited (GPCL) and Gujarat Electricity Board (GEB) in 2004 for development of a 1000 MWthermal power project at Pipavav in Gujarat by forming a new joint venture company between

NTPC and GPCL with 50:50 equity participation. Pursuant to the decision of Gujarat

Government, NTPC Ltd. has dissociated itself from this company. PPDCL is under winding up.

Page 15: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 15/99

INTERNATIONAL FINANCING ON POWER PROJECTS

15

Kanti Bijlee Utpadan Nigam Limited, (formerly known as Vaishali Power Generating

Company Limited)

To take over Muzaffarpur Thermal Power Station (2*110MW), a subsidiary company named

‗Vaishali Power Generating Company Limited (VPGCL)‘ was incorporated on September 6,

2006 with NTPC contributing 51% of equity and balance equity was contributed by Bihar State

Electricity Board. This company was formed to renovate the existing unit and run the plant. The

second unit has been successfully re-synchronized on October 17, 2007 after 4 years of being

idle. Renovation and modernization of the first unit is under progress. The company was

rechristened as ‗Kanti Bijlee Utpadan Nigam Limited‘ on April 10, 2008. 

Bharatiya Rail Bijlee Company Limited (BRBCL)

A subsidiary of NTPC under the name of ‗Bharatiya Rail Bijlee Company Limited‘ was

incorporated on November 22, 2007 with 74:26 equity contribution from NTPC and Ministry of 

Railways, Govt. of India respectively for setting up of four units of 250 MW each of coal based

power plant at Nabinagar, Bihar. Investment approval of the project was accorded in January,

2008.

2.5Business Development: - 

NTPC, with a rich experience of engineering, construction and operation of over 30,000 MW of 

thermal generating capacity, is the largest and one of the most efficient power companies inIndia, having operations that match the global standards.

Commensurate with our country‘s growth challenges, NTPC has embarked upon an ambitious

plan to attain a total installed capacity of 75,000 MW by 2017. Towards this end, NTPC has

adopted a multi-pronged strategy such as Greenfield Projects, Brownfield Projects, Joint Venture

and Acquisition route. Apart from this, NTPC has also adopted the Diversification Strategy in

related business areas, such as, Services, Coal Mining, Power Trading, Power Exchange,

Manufacturing to ensure robustness and growth of the company.

Page 16: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 16/99

INTERNATIONAL FINANCING ON POWER PROJECTS

16

2.6Balance Sheet: - 

Mar '11 Mar '10 Mar '09 Mar '08 Mar '07

12 mths 12 mths 12 mths 12 mths 12 mths

Sources Of Funds

Total Share Capital8,245.46 8,245.50 8,245.50 8,245.50 8,245.50

Equity Share Capital 8,245.46 8,245.50 8,245.50 8,245.50 8,245.50

Share Application Money 0.00 0.00 0.00 0.00 0.00

Preference Share Capital 0.00 0.00 0.00 0.00 0.00

Reserves 60,138.66 55,478.60 50,749.40 46,021.90 40,351.30

Revaluation Reserves 0.00 0.00 0.00 0.00 0.00

Net worth 68,384.12 63,724.10 58,994.90 54,267.40 48,596.80

Secured Loans 9,910.68 9,079.90 8,969.60 7,314.70 7,479.60

Unsecured Loans 33,277.56 28,717.10 25,598.20 19,875.90 17,661.50

Total Debt 43,188.24 37,797.00 34,567.80 27,190.60 25,141.10

Total Liabilities 111,572.36 101,521.10 93,562.70 81,458.00 73,737.90

Mar '11 Mar '10 Mar '09 Mar '08 Mar '07

12 mths 12 mths 12 mths 12 mths 12 mths

Application Of Funds

Gross Block 72,583.94 66,663.80 62,353.00 53,368.00 50,604.20

Less: Accum. Depreciation 33,519.19 32,088.80 29,415.30 27,274.30 25,079.20

Net Block 39,064.75 34,575.00 32,937.70 26,093.70 25,525.00

Capital Work in Progress 38,441.84 32,290.60 26,404.90 22,478.30 16,962.30

Investments 12,344.84 14,807.10 13,983.50 15,267.20 16,094.30

Inventories 3,639.12 3,347.70 3,243.40 2,675.70 2,510.20

Sundry Debtors 7,924.31 6,651.40 3,584.20 2,982.70 1,252.30

Cash and Bank Balance 326.34 634.00 271.80 473.00 750.10

Total Current Assets 11,889.77 10,633.10 7,099.40 6,131.40 4,512.60

Loans and Advances 7,648.10 6,357.10 7,826.10 9,936.20 8,781.70

Fixed Deposits 15,858.92 13,825.50 15,999.80 14,460.20 12,564.50

Page 17: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 17/99

INTERNATIONAL FINANCING ON POWER PROJECTS

17

Total CA, Loans & Advances 35,396.79 30,815.70 30,925.30 30,527.80 25,858.80

Deferred Credit 0.00 0.00 0.00 0.00 0.00

Current Liabilities 10,945.55 7,896.80 7,439.20 5,548.40 5,422.20

Provisions 2,730.31 3,070.50 3,249.50 7,360.60 5,280.30

Total CL & Provisions 13,675.86 10,967.30 10,688.70 12,909.00 10,702.50

Net Current Assets 21,720.93 19,848.40 20,236.60 17,618.80 15,156.30

Miscellaneous Expenses 0.00 0.00 0.00 0.00 0.00

Total Assets 111,572.36 101,521.10 93,562.70 81,458.00 73,737.90

Contingent Liabilities 33,227.29 40,044.00 66,083.20 29,361.80 25,218.80

Book Value (Rs) 82.94 77.28 71.55 65.81 58.94

2.7 SWOT analysis of NTPC 

Strengths:

• Core Team of expert professionals.

• Responsive Governance (Across the Board: Cooperation across management).

• Low Operating Costs.

• Excellent work Culture.

• Sound and state of the art Physical Infrastructure.

• Young and Dynamic workforce

• Aggressive toward development.

• Numerous Training Courses for the employees.

Weaknesses:

• High employee turnover.

• Still some departments work in isolation.

Opportunities:

Page 18: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 18/99

INTERNATIONAL FINANCING ON POWER PROJECTS

18

• To compete economically with anybody in the country as well as in the world.

• Take advantage of technological revolution

• Mergers and acquisitions.

• Open access implementation.

• Great numbers of projects are coming up with the organization.

Threats:

• High competition from other companies.

• Change in Govt. policies

• Manpower shortage.

• Fuel availability.

Page 19: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 19/99

INTERNATIONAL FINANCING ON POWER PROJECTS

19

3.  OBJECTIVE OF THE PROJECT

To know about role of the international financial institution or multinational development bank 

like ADB, WORLD BANK, IFC etc. for the financing in power projects.

There are various questions regarding international financing for Indian power projects such as:

How much amount of the foreign currencies invested in Indian power projects?

How international financing is done for power projects?

How foreign currencies are converted into the local currency?

How application of international finance takes place for financing the power projects?

Which factor distinguishes between domestic finance & international finance?

On what condition lenders (multinational development banks) are ready to invest for Indian

power projects?

Which types of loan provided by lenders to the borrower for financing the power projects?

What is the loan agreement between lenders & borrower?

Why NTPC is better than other domestic companies like TATA POWER, ADANI POWER, and

RELIANCE POWER etc.?

What is the role of regulatory framework for international financing on infrastructure (power)

projects?

What are the risks for the foreign investors to finance the projects?

Attempts are made to answer these questions in this report.

Page 20: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 20/99

INTERNATIONAL FINANCING ON POWER PROJECTS

20

4.  SIGNIFICANCE OF THE PROJECT

A major significance of project is to help the borrower for choosing the multinational

development banks, which are better for investment in power projects.

Significance of the projects also lays in the fact the loan agreement between the borrower &lenders are relevant or not. It means all the conditions of borrower as well as lenders are satisfied

to both of them. It includes commitment charges, disbursement fee, and event of default,

repayment and prepayment charges, cancelation and suspensions.

Significance of the project helps to the borrower for at how much interest rate to take loan. The

loan given by lenders wants to give a certain maturity date to the borrower for return back 

currencies to him.

Significance of the project consists to determine the exchange rate of two currencies of two

different countries.

Significance of the projects consist NTPC is superior to other domestic companies like TATA

POWER, ADANI POWER, RELIANCE POWER.

Significance of the projects consists External commercial borrowing guidelines of Reserve bank 

of India.

5.  SCOPE OF THE PROJECT

International financial institution or multinational development banks are investing in power

projects due to government budgetary constraints.

India has huge amount of target installed capacity & NTPC has different target capacity on

different plans.so that NTPC wants to reach at its own target value with the help of 

internationally finance.

International financing does by competitive bidding process.

International financing does takes place due to low interest rate.

Risk of the investor would be reduced then proper financing work place.

Page 21: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 21/99

INTERNATIONAL FINANCING ON POWER PROJECTS

21

6.  RESEARCH METHODOLOGY OF THE PROJECT

In the research methodology of the project determine the foreign exchange rate variation for

different projects of NTPC.

The Foreign Exchange Rate Variation (FERV) comes from Repayment value of Loan.

Determine the whole net charge (interest charge) for all projects of NTPC provided loan from

multinational development banks.

Determine the weighted average of a particular multinational development Bank (KFW Bank)

for different projects of NTPC.

For calculation of weighted average of cost of capital we must have interest rate (coupon rate),

issue price of debt, corporate tax, earning per share value, market price of ordinary share andweight of equity as well as debt.

The formula for WACC is given below:-

WACC=Kd*(1-T)*(D/D+E) + Ke*(E/D+E)

Kd=cost of debt

T=corporate Tax

D=Debt value

E=Equity value

Ke=cost of equity

In the research methodology conversion of External Commercial borrowing into equity occurs.

All the guidelines of ECB consider in the project report.

In the research methodology of the project consider why NTPC is better than other domestic

companies? The Market Cap value of NTPC is 137039.54 crore (BSE), 137245.68 crore (NSE)

and the Market Cap value of ADANI POWER, RELIANCE POWER are 18726 crore, 21852

crore respectively. There are huge difference shows NTPC is better than ADANI POWER &

RELIANCE POWER.

Page 22: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 22/99

INTERNATIONAL FINANCING ON POWER PROJECTS

22

7.  INTRODUCTION 

Public international finance is dominated by two kinds of institutions: - 1. Multilateral

developments banks (MDB) and 2. Economic credit agencies (ECA).

Among the MDBs, the World Bank Group and Asian Development Bank are the two mostimportant for our study, but there are several others, including the Inter-American Development

Bank (IDB), the African Development Bank (AFDB), the European Bank for Reconstruction and

Development (EBRD), and the European Investment Bank (EIB).The largest ECAs among the

30 member nations of the OECD include the U.S. Export Import Bank and the Japan Bank for

International Cooperation (JBIC).

Table7.1: International Financiers of Coal fired plants

EDF identified $37.04 billion in public international financing for some 88 new coal plants and

expansions and life extensions of existing plants since 1994.

Page 23: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 23/99

INTERNATIONAL FINANCING ON POWER PROJECTS

23

United States Export-Import Bank (EXIM) and Overseas Private Investment Corporation

(OPIC), with some $4.164 billion for 19 different coal-fired projects.

World Bank Group and the Asian Development Bank are the second and third largest single

public financing institutions for the expansion of coal-fired power plants since 1994. Theirfinancial commitments total $5.315 billion and $3.623 billion, respectively.

Table7.2: - Capacity Addition Breakup (XIth) power plant

Figure7.1: XIth plan Capacity Addition Targets & Achievement

Page 24: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 24/99

INTERNATIONAL FINANCING ON POWER PROJECTS

24

Figure7.2: Capacity Addition Growth in plan wise manner

Figure7.3: Capacity Addition Private Sector 

Page 25: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 25/99

INTERNATIONAL FINANCING ON POWER PROJECTS

25

Table7.3: Financial Closure Scenario for Private Capacity as per 11th plan

Table7.4: Investment

Source / 

Sector 

Hydro

(MW)

Thermal (MW)  Nuclear (MW)  Total  % age 

Central  8,654 24,840 3,380 36,874 47% 

State  3,482 23,301 26,783 34% 

Private  3,491 11,552 15,043 19% 

Total  15,627 56,693 3,380 78,700 100% 

% age  20%  76%  4%  100% 

Figure7.4: Investment in Power Sector

Page 26: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 26/99

INTERNATIONAL FINANCING ON POWER PROJECTS

26

Figure7.5: Investment targets by Government

Page 27: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 27/99

INTERNATIONAL FINANCING ON POWER PROJECTS

27

8.  KEY TERM OF INTERNATIONAL FINANCE 

International finance is the branch of economics that studies the dynamics of  exchange rates, 

foreign investment, and how these affect international trade. It also studies international projects,

international investments and capital flows, and trade deficits. It includes the study of futures,

options and currency swaps. International finance is a branch of international economics. 

Exchange rates (also known as the foreign-exchange rate or FX rate) between two currencies

specify how much one currency is worth in terms of the other. It is the value of a foreign nation‘s

currency in terms of the home nation‘s currency. For example an exchange rate of 91 Japanese

yen (JPY, ¥) to the United States dollar (USD, $) means that JPY 91 is worth the same as USD 1.

International trade  is exchange of capital, goods, and services across international borders or

territories.

Currency swap involve two parties who agree to pay each other‘s debt obligation denominated

in different currencies.

Interest swap involve exchange of interest obligations between two parties.

Spot rate is the rate of exchange of the day on which the transaction has taken place and of the

days the transaction is executed.

Forward rate is the rate of exchange applicable for delivery of foreign exchange at a future

date.

Forward rate premium foreign currency is at premium when its forward rate is higher than spot

rate.

Forward rate discount foreign currency is at discount when its spot rate is higher than the

forward rate.

Cross rate is the rate of exchange of two currencies on the basis of exchange quotes of other

pairs of currencies.

Arbitrage is an act of buying currency in one market at a lower price and selling it in another

price resulting in equilibrium in exchange rates of different currencies.

Page 28: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 28/99

INTERNATIONAL FINANCING ON POWER PROJECTS

28

Geographical arbitrage is the buying of foreign currency from a foreign exchange market

where it is cheaper and selling in another foreign exchange market where it is costly.

Triangular arbitrage involves three foreign currencies involving three different foreign

exchange markets. It is also known as a three-point arbitrage.

Purchasing power parity (PPP) theory is a theory of long-term equilibrium exchange rates

based on relative price levels of two countries.

Interest rate parity theory is a theory according to which the discount/premium of one

currency in relation to another reflects the interest differentials between them.

International Fisher effect states that the nominal interest rate differential must be equal to the

expected inflation rate differential in two countries.

Balance of payments (BOP) sheet is an accounting record of all monetary transactions between

a country and the rest of the world. These transactions include payments for the country's exports

and imports of goods, services, and financial capital, as well as financial transfers. 

Transaction exposure involves gain/loss arising out of the various types of transactions that

require settlement in a foreign currency.

Translation exposure results from the need to translate foreign currency assets/liabilities into

local currency at the time of finalizing accounts.

Economic exposure implies change in the value of a company that accompanies an anticipated

change in exchange rates.

Operating exposure has impact on firm‘s future operating revenue, costs, and cash flows .  

Foreign exchange risk is the possibility of loss on account of unfavorable movement in foreign

exchange rates.

Page 29: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 29/99

INTERNATIONAL FINANCING ON POWER PROJECTS

29

Foreign exchange risk management (FERM)-internal techniques:-

1. Leading implies collection from designated debtor‘s expeditiously foreign currency before

they are due (when home currency is expected to strengthen) and to initiate lead to pay foreign

currency designated creditors before their due date of payment (when depreciation/devaluationof the home currency is apprehended).

2. Lagging implies delaying receipts from the foreign currency designated receivables whose

currencies are likely to appreciate/strengthen and delaying foreign currency designated payables

whose currencies are likely to depreciate/devalue/weaken.

3. Netting:-Foreign exchange risk exposure of such companies can be substantially reduced if 

foreign designated receivables and payments among them are settled on the net balance basis is

known as netting.

Foreign exchange risk management(FERM)-external techniques:-

1. Forward contracts are widely used by business firms to hedge against volatile/ adverse

exchange market. Business firms enter into a forward contract to buy or sell foreign currency in

exchange for home currency, normally at a specific future date , at a predetermined exchange

conversion rate is known as forward rate.

2. Futures contract is a standardized agreement to buy or sell a pre-specified amount of foreign

currency in the future market at some specified future date between the parties to the contract.

3. Currency option is a financial instrument that provides its holder a right but no obligation to

buy or sell a pre-specified amount of foreign currency at a pre-determined rate in the future.

4. Call option:-The holder has right to buy/call a specific currency at a specific price on a

specific period of time.

5. Put option:-The holder has right to sell a specified amount of currency at a pre-fixed price on

a specified date.

6. Money market operations:-It serves an important hedging function in that uncertainty is

resolved regarding the amount to be paid. The steps involved are as follows:-

Page 30: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 30/99

INTERNATIONAL FINANCING ON POWER PROJECTS

30

Step 1-Determine the amount required in foreign currency, to be paid on a specified date (3-4

months) from now.

Step 2-From an authorized dealer (Bank) ascertain the spot exchange rate at which it is selling

the required foreign currency in exchange for home currency.

Step 3-Borrow home currency from the money market, at the prevailing interest rate. The

quantum of borrowing should be in such a manner that can make the required foreign currency

sums available on the date of payment (3-4 months).

Step 4- The borrowed funds are to be used to buy the required foreign currency from the forex

spot market; once purchased, it is to be invested in forex money market to yield interest in the

desired foreign currency.

Step 5-As per steps 3 and 4, the required amount of foreign currency to be purchased can be

determined.

Multinational capital budgeting decision:-

The major motivating factor in favour of foreign investments:-

(1). Comparative cost

(2). Taxation

(3). Financial diversification

Incremental cash flow of the investment should be discounted at an opportunity cost of capital

appropriate to the risk of investment. The investment should be accepted if the NPV is positive.

Incremental cash outflows to undertake foreign investment decision are to be measured.

Incremental cash inflows the foreign investment project is expected to yield during its projected

economic useful life.

operating cash flow(OCF)cash flow provided by operations or cash flow from operating

activities, refers to the amount of  cash a company generates from the revenues it brings in,

Page 31: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 31/99

INTERNATIONAL FINANCING ON POWER PROJECTS

31

excluding costs associated with long-term investment on capital items or investment in

securities. 

The International Financial Reporting Standards defines operating cash flow as cash generated

from operations less taxation and interest paid, investment income received and less dividendspaid gives rise to operating cash flows.

Free cash flow (NCF) is cash flow available for distribution among all the securities holders of 

an organization. They include equity holders, debt holders, preferred stock holders, convertible

security holders. It should also allow for cash available to pay off the company's short term debt.

It should also take into account any dividends that the company means to pay.

Net Free Cash Flow = Operation Cash flow  –  Capital Expenses to keep current level of operation – dividends – Current Portion of long term debt – Depreciation.

Cannibalization implies lost sales of existing products of a multinational company on account

of proposed foreign investment.

Sales creation implies increased sales on account of proposed foreign investment.

Investment Evaluation

The basic steps involved in evaluation of a project are:-

1. Determine net investment outlay.

2. Estimate net cash flows to be derived from the project over time, including an estimate of 

salvage value.

3. Identify the appropriate discount rate for determining the present value of the expected cash

flows.

4. Apply NPV or IRR techniques to determine the acceptability or priority ranking of potential

projects.

Page 32: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 32/99

INTERNATIONAL FINANCING ON POWER PROJECTS

32

Some of the factors unique to capital budgeting for MNCs are: -

1. Conversion of cash flows from foreign projects into the currency of the parent firm.

2. Restrictions on full remittance of cash flows from foreign projects.

3. Exchange Rate fluctuations.

4. Application of different tax rates in the country of the project and in the parent's country.

5. Amenities and concessions granted by host country.

6. Benefits of international diversification to the shareholders of parent firm.

7. Lost exports.

8. Difficulty in estimating terminal value of foreign projects.

9. Differing rates of national inflation.

10. Knock-on effects of overseas investment projects on other operations elsewhere.

11. Political risk involved in foreign investment.

Page 33: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 33/99

INTERNATIONAL FINANCING ON POWER PROJECTS

33

9.  DIFFERENCE BETWEEN DOMESTIC FINANCE &

INTERNATIONAL FINANCE

International finance is to a great extent, similar to domestic corporate finance.

A domestic company takes up a project for investment only when the net present value of cash

flows is positive and it shapes the working capital policy in a way that maximizes profitability

and ensures desired liquidity. It is not different in case of MNCs.

Again, the financing decisions, in respect of whether a domestic or an international company,

aim at minimizing the overall cost of capital and providing optimum liquidity.

Domestic financial management is concerned with the costs of financing sources and the payoffs

from investment. In domestic arena, movements in exchange rates are substantially ignored.

But In case of international financial management, there is no way that we can analyze

international financing and investment opportunities without an understanding of the impact of 

foreign exchange rates upon the basic model of financial management.

However, international finance has a wider scope than domestic corporate finance and it is

designed to cope with greater range of complexities than the domestic finance.

The reasons are as follows:-

(a) The MNCs operate in different economic, political, legal, cultural and tax environments

(b) They operate across and within varied ranges of product and factor markets which vary in

regard to competition and efficiency.

(c) They trade in a large number of currencies as a result of which their dependence on the

foreign exchange market is quite substantial.

(d) They have easy access not only to varying domestic capital markets but also to unregulated

international capital markets which differ in terms of efficiency and competitiveness.

Page 34: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 34/99

INTERNATIONAL FINANCING ON POWER PROJECTS

34

10. ROLE OF WORLD BANK, ADB, IFC

THE WORLD BANK 

The International Bank for Reconstruction and Development (IBRD), better known as the World

Bank, was established at the same time as the International Monetary Fund (IMF) to tackle theproblem of international investment.

Since the IMF was designed to provide temporary assistance in correcting the balance of 

payments difficulties, an institution was also needed to assist long-term investment purposes.

Thus, IBRD was established for promoting long-term investment loans on reasonable terms.

The World Bank (IBRD) is an inter-governmental institution, corporate in form, whose capital

stock is entirely owned by its member governments.

Initially, only nations that were members of the IMF could be members of the World Bank; this

restriction on membership was subsequently relaxed.

FUNCTIONS:

1. To assist in the reconstruction and development of the territories of its members by facilitating

the investment of capital for productive purposes.

2. To promote private foreign investment by means of guarantee of participation in loans and

other investments made by private investors and when private capital is not available on

reasonable terms, to make loans for productive purposes out of its own resources or from funds

borrowed by it.

3. To promote the long-term balanced growth of international trade and the maintenance of 

equilibrium in balances of payments by encouraging international investment for the

development of the productive resources of members.

Page 35: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 35/99

INTERNATIONAL FINANCING ON POWER PROJECTS

35

4. To arrange loans made or guaranteed by it in relation to international loans through other

channels so that more useful and urgent projects, large and small alike, will be dealt with first. It

appears that the World Bank was created to promote and not to replace private foreign

investment.

The Bank considers its role to be a marginal one, to supplement and assist foreign investment in

the member countries.

A little consideration will show that the objectives of the IMF and IBRD are complementary.

Both aim at increasing the level of national income and standard of living of the member nations.

Both serve as lending institutions, the IMF for short-term and the IBRD for long-term capital.

Both aim at promoting the balanced growth of international trade.

ADB (ASIAN DEVELOPMENT BANK)

ADB had started in 22nd august, 1963. The formalities were completed by mid-1966 and it

started functioning in December 1966.

Its membership was open to the regional countries and the non-regional developed countries

from where resources were to be obtained. Presently, it has 57 members---41 from the region and

16 from outside.

The chairman of the board of director is the president of the ADB. He is assisted by vice-

president and professional and non-professional staff members. In practices, decisions are taken

by consensus, although there is provision for voting.

Every member country has one basic vote plus proportional votes depending upon the number of 

shares held in the capital structure. The regional members carry over two-thirds of the votes.

Page 36: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 36/99

INTERNATIONAL FINANCING ON POWER PROJECTS

36

The financial resource base is divided into two components. One is the ordinary capital resources

(OCR) comprising equity and borrowings. The other is the special funds made up largely of 

contributions from member countries and specially meant for concessional lending and technical

assistance.

Apart from OCR , there are three special funds namely the Asian Development Fund (ADF) , the

Technical Assistance Development Special Fund (TASF) and the Japan Special Fund (JSF).

ADF is replenished by member countries to finance the concessional lending to poorer members

and the replenishment is authorized from time to time by a resolution of the board of governor.

TASF is meant for financing the technical assistance operations. It created out of income from

the ordinary lending operation, replenishments from member countries, direct voluntary

contributions, and income from investment.

JSF was established in 1988 by way of contribution from japan for financing or co-financing on

a grant basis the technical assistance projects and the private sector projects through equity

investment.

FUNCTION

Being a regional development bank, ADB provides the following financial and technical

assistance for economic development of developing member countries (DMC).

The ADB:

1. Makes loan and equity investments;

2. Provides technical assistance for preparing and carrying out development projects and

programmer and advisory services;

Page 37: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 37/99

INTERNATIONAL FINANCING ON POWER PROJECTS

37

3. Helps mobilize additional resources within the region and helps attract investment from

outside it; and

4. Assist regional and sub-regional schemes for the sake of promotion of regional economic

cooperation.

IFC (INTRENATIONAL FINANCE CORPORATION)

Since IFC is an institution of the World Bank group, its organizational set-up is similar to that of 

the World Bank.

This means that the Board of Governor is the apex body.

The Board of Director implements the policies framed by the Board of Governors.

The president of the World Bank is the ex-officio president of the IFC. The president is assisted

by the executive vice president who is in turn assisted by a large number of professional and

non-professional staff.

The resources base of the IFC is similar to that of the IBRD. It presents a mix of equity capital

and borrowed funds.

The IFC started borrowing in 1965 in order to finance its lending activities but only from the

IBRD. In 1984 it began borrowing from the international capital market. During 1990s the size

of borrowing expanded fast.

Apart from borrowings, the earning of the IFC too makes up its resource pool. The earning

comes from interest and financial fees, dividend from equity investment, service fees, and

income from the sale of securities, etc.

Page 38: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 38/99

INTERNATIONAL FINANCING ON POWER PROJECTS

38

FUNCTION

The IFC supplements the financing activities of the World Bank. It seeks to achieve the

objectives through providing and bringing together finance, technical assistance and

management.

This means that it extends not only financial and technical assistance, but also provides equity

capital.

IFC provides loans and makes equity and quasi-equity investment.

Quasi-equity investment includes subordinated loans, convertible debt instruments, and preferred

stock and income notes.

Unlike IBRD loans, these loans do not require government guarantee.

Long-term loans are made either on project cost basis or on corporate-finance basis. Those loans

that are written against IFC‘s own account are known as A-loans.

Maturity ranges normally between 7 and 12 years, although it can be extended to 20 years and

the grace period can go up to 4 years.

The loans are mostly direct loans, but are provided also through financial intermediaries like

banks, leasing companies or financial institutions.

In case where IFC‘s own funds do not permit making big loans, it seeks out commercial banks

and other financial institutions to join in loan syndication and parallel financing. Such loans are

known as B-loans.

IFC‘s Risk Management Services enable firms to access the derivative markets to hedge their

exchange rate exposure or interest rate exposure.

Page 39: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 39/99

INTERNATIONAL FINANCING ON POWER PROJECTS

39

The Foreign Investment Advisory Service (FIAS) is being operated in collaboration with

Multilateral Investment Guarantee Agency (MIGA) to provide technical advice to member

countries on how to formulate policies and programs so as to attract foreign investment.

The Corporation collaborates also with the United Nations Development Program for technical

assistance.

Page 40: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 40/99

INTERNATIONAL FINANCING ON POWER PROJECTS

40

11. TYPES OF LOAN 

11.1 Investment loans: - Investment loan have a long-term focus (5 to 10 years), and finance

goods, works and services in support of economic and social development projects in a broad

range of sectors. Investment loans finance a wide range of activities aimed at creating the

physical and social infrastructure necessary for poverty reduction and sustainable development.

The important lending instruments are:-SIL, SIM, APL, LIL, TAL, FIL, ERL.

11.2Adjustment loans: - Adjustment loan have a short-term focus (1 to 3 years), and provide

quick-disbursing external financing to support policy and institutional reforms. Eligibility for an

adjustment loan also requires agreement on monitor able policy and institutional reform actions,

and satisfactory macroeconomic management.

Coordination with the IMF is an essential part of the preparation of an adjustment loan.

The important lending instruments are:-SAL, SECAL, PSAL, SSAL, RIL, and DRL.

11.3Specific Investment Loan

Specific investment loans (SILs) support the creation, rehabilitation, and maintenance of 

economic, social, and institutional infrastructure. In addition, SILs may finance consultant

services and management and training programs.

The SIL is a flexible lending instrument appropriate for a broad range of projects.

SILs help to ensure the technical, financial, economic, environmental, and institutional

Viability of a specific investment. They also support the reform of policies that affect the

productivity of the investment.

11.4Sector Investment and Maintenance Loan

Sector investment and maintenance loans (SIMs) focus on public expenditure programs inparticular sectors. They aim to bring sector expenditures, policies, and performance in line with a

country‘s development priorities by helping to create an appropriate balance among new capital

investments, rehabilitation, reconstruction, and maintenance.

Page 41: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 41/99

INTERNATIONAL FINANCING ON POWER PROJECTS

41

They also help the borrower develop the institutional capacity to plan, implement, and monitor

expenditure or investment program.

The SIM is most appropriate where a sector expenditure program needs extensive coordination,

particularly if the program involves a large share of donor-financed investments.

Therefore, SIMs typically involves coordinated efforts among the multilateral and bilateral

donors providing assistance to the sector.

11.5Adaptable Program Loan

Adaptable program loans (APLs) provide phased support for long-term development programs.

They involve a series of loans that build on the lessons learned from the previous loan(s) in the

series.

An APL involves agreement on

(1)The phased long-term development program supported by the loan,

(2)Sector policies relevant to the phase being supported, and

(3)Priorities for sector investments and recurrent expenditures.

They can be used to support a phased program of sector restructuring, or systemic reform in the

power, water, health, education, and natural resource management sectors, where time is

required to build consensus and convince diverse actors of the benefits of politically and

Economically difficult reforms.

11.6Learning and Innovation Loan

The learning and innovation loan (LIL) supports small pilot-type investment and capacity-

building projects that, if successful, could lead to larger projects that would mainstream the

learning and results of the LIL.

LILs do not exceed $5 million, and are normally implemented over 2 to 3 years — a much shorter

period than most Bank investment loans. All LILs include an effective monitoring and evaluation

system to capture lessons learned.

Page 42: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 42/99

INTERNATIONAL FINANCING ON POWER PROJECTS

42

11.7Technical Assistance Loan

The technical assistance loan (TAL) is used to build institutional capacity in the borrower

country. It may focus on organizational arrangements, staffing methods, and technical, physical,

or financial resources in key agencies.

TALs are used to build capacity in entities directly concerned with implementing policies,

strategies, and reforms that promote economic and social development.

They also build capacity related to public sector reform and to the preparation, implementation,

and maintenance of investments.

TALs often complement investment or adjustment operations by supporting specific tasks related

to their preparation or implementation.

11.8Financial Intermediary Loan

Financial intermediary loans (FILs) provide long-term resources to local financial institutions to

finance real sector investment needs. The financial institutions assume credit risk on each

subproject.

FILs help to develop sound financial sector policies and institutions, promote the operational

efficiency of those institutions in a competitive environment, improve the terms of credit to

enterprises and households, and promote private investment.

11.9Emergency Recovery Loan

Emergency recovery loans (ERLs) support the restoration of assets and production

Levels immediately after an extraordinary event — such as war, civil disturbance, or

Natural disaster —that seriously disrupts a borrower‘s economy. 

They are also used to strengthen the management and implementation of reconstruction efforts,

and to develop disaster-resilient technology and early warning systems to prevent or

Page 43: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 43/99

INTERNATIONAL FINANCING ON POWER PROJECTS

43

Mitigate the impact of future emergencies. ERLs focus on the rapid reconstruction of economic,

social, and physical systems within a limited period, normally 2 to 3 years.

They finance investment and productive activities, rather than relief or consumption. For

recurring events such as annual flooding, or for a slow-onset disaster such as drought, a SIL is

usually more appropriate.

11.10Structural Adjustment Loan

The structural adjustment loan (SAL) supports reforms that promote growth, efficient use of 

resources, and sustainable balance of payments over the medium and long term.

SALs typically focus on major macroeconomic and structural issues that cut across sectors, such

as trade policy, resource mobilization, public sector management, private sector development,

and social safety nets.

11.11Sector Adjustment Loan 

The sector adjustment loan (SECAL) supports policy changes and institutional reforms in a

specific sector. SECALs focus on major sectorial issues such as the incentive and regulatory

Frameworks for private sector development, institutional capability, and sector expenditure

programs.

11.12Programmatic Structural Adjustment Loan

The programmatic structural adjustment loan (PSAL) is provided in the context of a multiyear

framework of phased support for a medium-term government program of policy reforms and

institution building.

PSALs respond to country needs for Bank financing and advice in support of structural and

social reforms that involve continuous, incremental policy changes and institution building over

several years.

Page 44: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 44/99

INTERNATIONAL FINANCING ON POWER PROJECTS

44

The focus is on step-by-step capacity building and reform, typically in the public sector, aimed

at strengthening public expenditure management and improving governance, resource allocation,

and public service delivery.

11.13Special Structural Adjustment Loan

The special sector structural adjustment loan (SSAL) supports structural and social reforms by

creditworthy borrowers approaching a possible crisis, or already in crisis, and with exceptional

external financing needs.

These loans help countries to prevent a crisis or, if one occur, to mitigate its adverse economic

and social impacts.

SSALs have different terms than other Bank loans. They carry a 5-year maturity with a 3-year

grace period, and a minimum loan spread of 400 basis points over USD LIBOR equivalent.

There are no waivers of interest or commitment charges.

11.14Rehabilitation Loan

The rehabilitation loan (RIL) supports government policy reform programs aimed at creating an

environment conducive to private sector investment, where foreign exchange is required for

urgent rehabilitation of key infrastructure and productive facilities.

The focus is on key short-term macroeconomic and sector policy reforms needed to reverse

declines in infrastructure capacity and productive assets.

11.15Debt Reduction LoanThe debt reduction loan (DRL) helps eligible highly indebted countries reduce commercial debt

and debt service to a manageable level, as part of a medium-term financing plan in support of 

sustainable growth.

The focus is on rationalizing the country‘s external commercial bank debt, by either converting it

to lower-interest instruments or buying it back at a discount.

Page 45: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 45/99

INTERNATIONAL FINANCING ON POWER PROJECTS

45

12. LOAN AGREEMENT

12.1.1 ARTICLE I DEFINITIONS 

SECTION 1.01 Definitions

"Assets" means all types of assets including property, revenue and claims of any kind.

"Bank" means any Lender who gives the loan to the Borrower like Lender (African

Development Bank).

"Bank Agreement" means the Agreement Establishing the African Development Bank adopted

on the 4th day of August 1963, as amended from time to time.

"Borrower" means the party to the Loan Agreement to whom the Loan is made.

"Category of Expenditure" means any category of goods, works and services of the Project to

be financed from the resources of the Loan.

"Closing Date" means the date specified in the Loan Agreement or such other later date as shall

be agreed upon in writing among the Bank, the Borrower after which the Bank may terminate the

right of the Borrower to request disbursements of the Loan.

“Co-financing” means any financing specified in the Loan Agreement to be provided for theProject by a financier.

"Currency" includes the currency of a country, the Special Drawing Right of the International

Monetary Fund, the Unit of Account of the Bank and any other unit of account which represents

a debt service obligation of the Bank to the extent of such obligation.

"Currency of a Country" means the coin or currency which is legal tender in that country.

"Date of Entry into Force" means the date on which the Loan Agreement shall enter into force.

"Date of the Loan Agreement” means the date specified in the Loan Agreement.

"Executing Agency" means the entity, whether a legal person or not, which is designated for

the implementation of the Project under the Loan Agreement. If more than one such entity is

designated in the Loan Agreement, an ―Executing Agency‖ refers separately to each such entity. 

Page 46: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 46/99

INTERNATIONAL FINANCING ON POWER PROJECTS

46

"Fund" means the African Development Fund.

"Guarantor" means the party to the Guarantee Agreement entered into with the Bank.

"Guarantee Agreement" means the agreement entered into between the Bank and the

Guarantor, to guarantee the Loan; as such agreement may be amended from time to time.

“Hedging Agreement” means any derivative agreement entered into between the Bank and the

Borrower in connection to any financial obligations to the Bank related to a loan.

"Interest Period" means the interest period defined in the Loan Agreement.

"Lien" means any security provided for the payment of a debt, including mortgages, pledges,

charges, privileges and priorities of any kind.

"Loan" means the maximum amount of the resources granted by the Bank as specified in the

Loan Agreement.

"Loan Account" means the account opened by the Bank on its books in the name of the

Borrower to record the Loan as well as disbursements and repayments of the Loan.

"Loan Agreement" means the agreement entered into between the Bank and the Borrower

providing for the Loan; as such agreement may be amended from time to time.

"Loan Currency" means the Currency or Currencies selected by the Borrower for the Loan,

and the payment obligations thereunder.

"Loan Savings" means any undisbursed amount of the Loan available (i) when the Project has

been fully terminated without any significant change from the initial Project description or its

design and disbursements have been effected in respect of all goods, works, and services

thereunder, or (ii) when the Project nearing completion is progressing satisfactorily according to

the implementation schedule with arrangements finalized for procurement of all goods, works

and services and provisions made for outstanding payments.

"Member State" means a member State of the Bank.

Page 47: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 47/99

INTERNATIONAL FINANCING ON POWER PROJECTS

47

"Project" means the Project or Program for which the Loan is granted, as described in the Loan

Agreement and as the description thereof may be amended from time to time by agreement

between the Bank and the Borrower.

"Public Entity" means any Legal Entity in which a Regional Member State and/or its politicalor administrative sub-division hold more than fifty per cent (50%) of the shares and/or of the

voting rights.

"Single Currency Loans" mean the lending products introduced by the Bank with effect from

October 1, 1997, as amended from time to time.

"Special Commitment" means any Special Commitment entered into by the Bank.

"Taxes" means all taxes, imposts, levies, fees and duties of any nature, whether in effect at the

Date of the Loan Agreement imposed.

12.1.2 ARTICLE II LOAN ACCOUNT - COMMITMENT CHARGE - SPECIAL

COMMITMENT CHARGE AND REPAYMENT

SECTION 2.01 Loan Account

The amount of the Loan shall be entered in the books of the Bank and such amount may be

disbursed to the Borrower as provided in the Loan Agreement.

SECTION 2.02 Commitment Charge

(a) The Bank may charge a Commitment Charge on terms and conditions to be provided in the

Loan Agreement.

(b) The Borrower shall pay the Commitment Charge on the undisbursed amount of the Loan at

the rate specified in the Loan Agreement. Such Commitment Charge shall begin to accrue 60

days from the Date of the Loan Agreement, or on such other date as the Bank shall from time to

time determine. With respect to any amount under the Loan, the Commitment Charge shall

accrue until (i) the date on which such amount is disbursed to the Borrower or (ii) the date on

which such amount is cancelled or (iii) the Closing Date, whichever date comes first. The

Commitment Charge shall be payable on each interest payment date commencing on the first

interest payment date following the Date of Entry into Force. The commitment charge shall be

Page 48: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 48/99

INTERNATIONAL FINANCING ON POWER PROJECTS

48

expressed in the Currency loaned.

(c) Any Commitment Charge as stated in paragraph (b) of this Section which has become due

and payable during the provisional effectiveness of the Loan Agreement, shall remain due andpayable to the Bank notwithstanding the non-entry into force, the cancellation or the termination

of the Loan Agreement.

SECTION 2.03 Interests

(a) The Borrower shall pay interest at the rate specified in the Loan Agreement on the amount of 

the Loan disbursed and outstanding from time to time. Interest shall accrue from the respective

dates on which such amounts are disbursed.

(b) The Bank may establish an alternate interest rate which shall be applicable if for any reason,

including, but not limited to, financial market disruption, the Bank determines that it has become

impossible to calculate the interest rate in the manner agreed upon in the Loan Agreement. In

such case, the Borrower shall have the right to prepay the Loan without thereby incurring any

penalty or prepayment costs.

(c) In establishing such alternate interest rate, the Bank shall consult with the Borrower, in order

to decide on a substitution formula allowing the Bank to keep the same margin as the margin

defined in the Loan Agreement. This formula shall apply retroactively from the first day of the

Interest Period during which this impossibility to compute the interest rate has been notified, up

to the total reimbursement of the principal of the Loan, interests, prepayment costs, Special

Commitment Charge, Commitment Charge and other charges due under the Loan Agreement, or

up to the date of notification by the Bank of the cessation of the event which caused the

application of the alternate interest rate.

SECTION 2.04 Application of Payment

Except as the Bank may otherwise decide, all payments by the Borrower shall be applied, as the

case may be, in the following order: Commitment Charge, Special Commitment Charge, other

charges, prepayment costs, interest and principal.

Page 49: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 49/99

INTERNATIONAL FINANCING ON POWER PROJECTS

49

SECTION 2.05 Computations of Interest and Commitment Charge

Interest and Commitment Charge shall be computed on a daily basis in accordance with the

provisions of the Loan Agreement.

SECTION 2.06 Repayments and Prepayment

(a) Except as provided in Section 3.04(e), the Borrower shall repay the principal amount of the

Loan which has been disbursed in accordance with the provisions of the Loan Agreement.

(b) Upon payment of all accrued interest, Commitment Charge, Special Commitment Charge and

other charges, and any prepayment costs calculated in accordance with Section 2.06(c), except as

provided in Section 3.04(d)(ii), and after giving not less than 45 days‘ notice to the Bank . The

Borrower shall have the right to repay, as of a date acceptable to the Bank, in advance of 

maturity: (i) the entire principal amount of the Loan then outstanding, or (ii) the entire principal

amount of any one or more maturities which, unless otherwise specified by the Borrower in the

prepayment notice, shall be applied pro-rata to all outstanding Loan maturities.

(c) The prepayment costs payable under paragraph (b) of this Section on prepayment of any

maturity shall, subject to the specific terms governing Single Currency Loans, be an amount

reasonably determined by the Bank to represent any cost to the Bank of redeploying the amount

to be prepaid from the date of prepayment to the maturity date, provided the Bank may, in its

sole discretion, waive the requirement of payment of any prepayment costs.

(d) Each request for prepayment notified to the Bank by the Borrower in accordance with this

Section shall be irrevocable and the amount to be prepaid shall automatically become due on the

date accepted by the Bank.

SECTION 2.07 Place of Payment

The principal of interest, prepayment costs, Special Commitment Charge, Commitment Charge

and other charges on the Loan shall be paid at such place(s) as the Bank shall indicate.

SECTION 2.08 Payments Falling Due on Public Holidays

Page 50: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 50/99

INTERNATIONAL FINANCING ON POWER PROJECTS

50

Any payment or other obligation which is due under the Loan Agreement to be affected on a

non-working day or a public holiday, according to the relevant local law, shall be considered

made or fulfilled if it is affected on the first working day thereafter, without any penalty or

additional costs to the Borrower.

SECTION 2.09 Promissory Notes

At the request of the Bank, the Borrower shall, within the specified period, execute and deliver to

the Bank, in such form as the Bank shall prescribe, promissory notes or other negotiable

instruments, guaranteed, if necessary, by the Guarantor, representing the obligation of the

Borrower to repay the principal of the Loan together with interest, Special Commitment Charge,

Commitment Charge and other charges.

SECTION 2.10 Restrictions

The repayment of the principal as well as the payment of interest, prepayment costs, Special

Commitment Charge and other charges relating to the Loan shall not be hindered by any

restrictions, regulations, controls of any kind imposed under the legislation of the Borrower.

12.1.3 ARTICLE III CURRENCY PROVISIONS

SECTION3.01. Currencies in which Disbursement is to be made 

(a) Subject to the Bank's right of Currency substitution in accordance with Section 3.04,

disbursements from the Loan Account shall be made in the Loan Currency in an amount

equivalent to the expenditures to be financed out of the proceeds of the Loan.

(b) In the case of expenditures incurred in a Currency other than the Loan Currency, if the

Borrower requests payment in the Currency of the expenditures, the Bank will, provided such

expenditures are in readily available Currency exchange such Currency in such manner as the

Bank may deem appropriate. The equivalent disbursement amount shall be determined by the

Bank including the exchange costs that would have been incurred by the Bank in using the Loan

Currency to meet the request. The costs of such Currency exchange shall be communicated to the

Borrower.

Page 51: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 51/99

INTERNATIONAL FINANCING ON POWER PROJECTS

51

SECTION 3.02 Loan Account Currencies

(a) Except as provided in Section 3.02 (b), the Loan Account shall be maintained in the Loan

Currency and shall record the equivalent as of the date of disbursement and repayment in the

Loan Currency of the amounts in various Currencies disbursed and repaid under the Loan fromtime to time. All amounts so recorded shall be the equivalent in the Loan Currency of the

Currency disbursed or repaid, except that if the Bank has exchanged the Currency disbursed

from another Currency in order to provide for such disbursement, then the equivalent in the Loan

Currency of the amount of such other Currency paid by the Bank shall be recorded in the Loan

Account instead.

(b) For loans made in several Currency tranches, the Loan Account shall be divided into multiple

sub-accounts, each one to be maintained in the Loan Currency of each tranche. Each sub-account

shall record the equivalent as of the date of disbursement and repayment in the respective Loan

Currency of the amounts in various Currencies disbursed or repaid, except that if the Bank has

exchanged the Currency disbursed with another Currency in order to provide for such

disbursement then the equivalent of the amount of such other Currency paid by the Bank shall be

recorded in the sub-account instead.

SECTION3.03. Currencies in which Payments to the Bank are Payable

(a) Except as provided in Section 3.04(g), repayment of principal and payment of prepayment

costs, interest, Special Commitment Charge, Commitment Charge and other charges shall be

made in the Loan Currency.

(b) If the Borrower so requests, the Bank may, acting on behalf of the Borrower, and on such

terms and conditions as the Bank shall determine, purchase the Loan Currency for the purpose of 

the repayment of principal and payment of prepayment costs, interest, Special Commitment

Charge, Commitment Charge and other charges, upon timely payment by the Borrower of sufficient funds for that purpose in a Currency or Currencies acceptable to the Bank. However,

that such repayment or payment shall be deemed to have been paid only when and to the extent

that the Bank has received the payment in the Loan Currency.

Page 52: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 52/99

INTERNATIONAL FINANCING ON POWER PROJECTS

52

SECTION 3.04 Temporary Currency Substitutions

(a) If the Bank reasonably determines that an extraordinary situation, whether factual or legal,

has arisen under which the Bank is unable to provide the Loan Currency for purposes of funding

Single Currency Loans, then the Bank shall promptly notify the Borrower of its inability toaccess or procure the Loan Currency after becoming aware of such inability. If within 60 days

following such notification the Bank and the Borrower cannot agree on a substitute Currency, the

Borrower may cancel the undisbursed portion of the Loan for which an agreement has not been

reached as to the currency of substitution.

(b) For each payment, the date of conversion between the Loan Currency and the substitute

currency shall be the date of disbursement of the substitute currency.

(c) The interest rate applicable to Loan amounts disbursed in the substitute currency shall be the

interest rate applicable to similar single currency loans in such substitute currency at the time of 

disbursement. The Bank shall duly notify the Borrower of such interest rate.

(d) During the period of operation of the Currency substitution:

(i) The substitute Currency shall be deemed to be the Loan Currency for purpose of Loan

Agreement.

(ii) No prepayment costs shall be payable on prepayment of the Loan.

(iii) Repayment of principal and payment of interest, prepayment costs, Special Commitment

Charge, Commitment Charge and other charges shall be made in the Loan Currency and/or in

such temporary substitute Currency as the Bank shall have selected.

(iv)The Bank shall reasonably determine the guiding principles for the conversion of amounts

from the Loan Currency to the substitute Currency.

(e) The Bank may, by notice to the Borrower, modify the principal amount of any one or more

maturities of the Loan provided for in the Loan Agreement, maturing after the establishment of 

any such substitute Currency to reflect changes in value as provided for in Section 3.04(d) (iv).

Page 53: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 53/99

INTERNATIONAL FINANCING ON POWER PROJECTS

53

(f) The Currency substitution shall be terminated as soon as practicable once the Bank becomes

able to provide again the original Loan Currency.

(g) All funds disbursed in a substitute Currency shall be repaid in the substitute Currency.

Section 3.05 Valuation of Currencies

For the purposes of the Loan Agreement, whenever it shall be necessary to determine the value

of one Currency in terms of another Currency, such value shall be as reasonably determined by

the Bank. The Bank shall notify the Borrower.

12.1.4 ARTICLE IV DISBURSEMENT OF THE LOAN

SECTION 4.01 Disbursement of the Loan

The Borrower shall be entitled to request from the Bank the disbursement of funds for amounts

expended for purposes of the Project, in accordance with the provisions of the Loan Agreement

provided that, except with the consent of the Bank. No disbursements shall be made: (a) on

account of expenditures procured in violation of the Bank‘s procurement rules (b) subject to the

terms of the Loan Agreement, to finance expenditures incurred prior to the Date of the Loan

Agreement.

SECTION 4.02 Special Commitments by the Bank

The Bank may, at the request of the Borrower and upon such terms and conditions as shall be

agreed upon between the Bank and the Borrower enter into special commitments in writing to

pay amounts to the Borrower or others in respect of expenditures to be financed out of the

proceeds of the Loan notwithstanding any subsequent suspension or cancellation by the Bank or

the Borrower. The Borrower shall pay a charge (special commitment charge) at the rate specified

in the Loan Agreement.

SECTION 4.03 Requests for Disbursement or for Special Commitment

If the Borrower seeks disbursement of any amount from the Loan Account the Bank to enter into

a Special Commitment, the Borrower shall deliver to the Bank a written request in such form,

Page 54: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 54/99

INTERNATIONAL FINANCING ON POWER PROJECTS

54

and containing such statements, agreements, undertakings and documents as the Bank shall

reasonably request. Requests for disbursement, including the documentation required pursuant to

this Article, shall be made promptly and in conformity with the disbursement rules and

procedures determined by the Bank from time to time.

SECTION 4.04 Payments by the Bank

The Loan funds disbursed shall be payable by the Bank to, or on the order of, the Borrower in

accordance with the terms of the Loan Agreement.

SECTION 4.05 Reallocation and Loan Savings

(a) The Bank may, at the request of the Borrower, and in accordance with its policies as

applicable from time to time, modify the allocation of expenditures of the Project to be financed

from the Loan.

(b) The reallocation of the Loan funds from one Category of Expenditures to another or within

the same Category of Expenditures shall not, however be made if such reallocation would in the

opinion of the Bank (i) compromise the execution of the Project (ii) substantially modify the

nature or objectives of the Project.

(c) Loan Savings may be allocated in accordance with the policy of the Bank as determined from

time to time.

SECTION 4.06 Evidence of Authority to Sign Requests for Disbursement

The Borrower shall provide the Bank with evidence of the authority of the person or persons

authorized to sign requests for disbursement and the authenticated specimen signature(s) of any

such persons

Page 55: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 55/99

INTERNATIONAL FINANCING ON POWER PROJECTS

55

.

SECTION 4.07Supporting Evidence

The Borrower shall provide the Bank with such documents and other evidence as the Bank shall

request in support of any request for disbursement, in accordance with its disbursement rules and

procedures.

SECTION4.08. Sufficiency of Requests and Documents

Each request for disbursement and the accompanying documents and other evidence shall be

sufficient in form and substance to satisfy the Bank that the Borrower is entitled to obtain the

disbursement of the amount requested for and that the said amount is to be used only for the

purposes specified in the Loan Agreement.

SECTION 4.09 Treatments of Taxes

If permitted by the Loan Agreement, the use of any proceeds of the Loan to pay for Taxes levied

by, or in the territory of, the Member State in respect of the importation, manufacture,

procurement or supply of any goods, works or consultancy services is subject to the Bank‘s

policy of requiring economy and efficiency in the use of the proceeds of its loans. To that end, if 

the Bank at any time determines that the amount of any such Tax is excessive, or that such Tax is

discriminatory or otherwise unreasonable, the Bank may, by notice to the Borrower, decline to

finance any such amount, as required to ensure consistency with such policy of the Bank.

12.1.5 ARTICLE V CANCELLATION AND SUSPENSION

SECTION 5.01 Cancellations by the Borrower

(a) The Borrower may by notice to and after consultation with the Bank, cancel the whole or part

of the Loan which has not been disbursed, except that the Borrower may not so cancel any

amount of the Loan in respect of which the Bank has entered into a Special Commitment.

(b) For purposes of paragraph (a) of this Section, the Borrower shall give 60 day notice to the

Bank of its intention to cancel all or part of the Loan and its reasons for so doing. The Bank shall

notify the Borrower of the date of receipt of such notice and shall consult with the Borrower on

the reasons for its request for cancellation. Unless the parties otherwise agree, the cancellation

Page 56: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 56/99

INTERNATIONAL FINANCING ON POWER PROJECTS

56

shall take effect 60 days from the date of receipt by the Bank of the Borrower‘s cancellation

notice.

SECTION 5.02 Suspensions by the Bank

1) If any of the following events has occurred and is continuing, the Bank may, by notice to the

Borrower, suspend in whole or in part the right of the Borrower to request for and receive

disbursements from the Loan Account:

Payment Failure

(a) The Borrower has failed to make payment when due of principal, interest, prepayment costs,

commitment charge or any other amount due to the Bank: (i) under the Loan Agreement, (ii)

under any other agreement between the Bank and the Borrower, (iii) in consequence of any

guarantee or other financial obligation of any kind extended by the Bank to any third party with

the agreement of the Borrower, or (iv) under any agreement between the Borrower and the Fund

or between the Borrower and any Bank Managed Fund.

(b) The Guarantor has failed to make payment of principal, interest, prepayment costs,

commitment charge or any other amount due to the Bank or the Fund: (i) under the Guarantee

Agreement, (ii) under any other agreement between the Guarantor and the Bank, (iii) in

consequence of any guarantee or other financial obligation of any kind extended by the Bank to

any third party with the agreement of the Guarantor.

Performance Failure

(c) The Borrower has failed to perform any other obligation under the Loan Agreement or any

Hedging Agreement, the Bank determines that the Project objectives cannot be achieved.

Cross-suspension

(d) The Bank has suspended in whole or in part the right of the Borrower to request or receive

disbursements under any agreement with the Bank, because of a failure by the Borrower to

perform any of its obligations under such agreement with the Bank.

Page 57: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 57/99

INTERNATIONAL FINANCING ON POWER PROJECTS

57

Events Prior to Effectiveness

(e) After the Date of the Loan Agreement and prior to the Date of Entry into Force, any event has

occurred which would have entitled the Bank to suspend the Borrower's right to request for and

receive disbursements from the Loan Account if the Loan Agreement had been effective on thedate such event occurred.

Co-financing

(f) Any of the following events occurs with respect to any Co-financing:

(i) If the Loan Agreement specifies a date by which the agreement with such financier providing

for the Co-financing is to become effective, such co-financing agreement has failed to become

effective by that date, or such later date as the Bank has established by notice to the Borrower

provided, however, that the provisions of this sub-paragraph shall not apply if the Borrower

establish to the satisfaction of the Bank that adequate funds for the Project are available from

other sources on terms and conditions consistent with the obligations of the Borrower under the

Loan Agreement .

(ii) Subject to sub-paragraph (iii) of this paragraph: (A) the right to withdraw the proceeds of the

Co-financing has been suspended, cancelled or terminated in whole or in part, pursuant to the

terms of the relevant co-financing agreement; or (B) the Co-financing has become due and

payable prior to its agreed maturity.

(iii) Sub-paragraph (ii) of this subsection shall not apply if the Borrower establish to the

satisfaction of the Bank that: (A) such suspension, cancellation, termination or pre-maturing was

not caused by the failure of the recipient of the Co-financing to perform any of its obligations

under the relevant agreement; and (B) adequate funds for the Project are available from other

sources on terms and conditions consistent with the obligations of the Borrower under the Loan

Agreement.

(g) Condition of Borrower

(i) Any material adverse change in the condition of the Borrower which materially affects the

financial ability of the Borrower to repay the Loan has occurred.

Page 58: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 58/99

INTERNATIONAL FINANCING ON POWER PROJECTS

58

(ii) The Borrower has become unable to pay its debts as they mature or any action has been taken

by the Borrower or by others whereby any of the Assets of the Borrower shall or may be

distributed among its creditors.

(iii) Any action has been taken for or suspension of operations of the Borrower.

(iv) In the opinion of the Bank, the legal character, ownership or control of the Borrower has

changed from that prevailing as of the date of the Loan Agreement so as to materially and

adversely affect the ability of the Borrower to perform any of its obligations arising under or

entered into pursuant to the Loan Agreement, or to achieve the objectives of the Project.

SECTION 5.03 Cancellations by the Bank

1) The Bank may, by notice to the Borrower, cancel the whole or part of the Loan, as the case

may be, if:

(a) Interruption of the Project: Project operations shall be deemed to have ceased if no

disbursement has been made for a continuous period of two years.

(b) Suspension: the right of the Borrower to disbursement of the Loan, has been suspended with

respect to any amount of the Loan for a continuous period of 30 days.

(c) Amount not Required: at any time, the Bank determines, after consultation with the

Borrower, that an amount of the Loan will not be required to finance any Project costs previously

allocated to be financed out of the Loan proceeds;

(d) Closing Date: on the day following the Closing Date, an amount of the Loan shall not have

been disbursed;

(g) Cancellation of Guarantee: the Bank has received prior notice from the Guarantor pursuant

to Section 5.06 (b) with respect to an amount of the Loan.

(h) Modification of the Project: the Borrower has modified the nature or the objectives of the

Project financed from the resources of the Loan.

Page 59: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 59/99

INTERNATIONAL FINANCING ON POWER PROJECTS

59

Upon the giving of such notice, such amount of the Loan shall be cancelled on the date decided

by the Bank and indicated in the notice, provided that : (i) in the case of paragraph (a) above, the

Borrower shall be given not less than three 3 months‘ notice in writing within which it may

submit all or any outstanding disbursement requests for settlement by the Bank prior to Loan

cancellation, and (ii) in the case of paragraph (c) above, a consultation with the Borrower is

carried out as indicated in sub-section (2) below.

2) Consultation as required in paragraph (c) of sub-section (1) above must be carried out within

60 days after the date the Bank gives notice of its intention to cancel such amount of the Loan

not required to finance any Project costs previously allocated to be financed out of the Loan

proceeds. In the absence of an agreement to the contrary within such 60 day period, the

cancellation will become effective on the date of expiry of the above-mentioned period.

SECTION 5.04 Amounts Subject to Special Commitment not Affected by Cancellation or

Suspension by the Bank.

No cancellation or suspension by the Bank shall apply to amounts subject to any Special

Commitment except as expressly provided in such Special Commitment. 

SECTION 5.05Effectiveness of the Provisions of the Loan Agreement after Suspension or

Cancellation

Notwithstanding any cancellation or suspension, as provided for in Sections 5.01, 5.02 and 5.03

above, the provisions of the Loan Agreement shall continue in full force and effect.

SECTION5.06. Cancellation of Guarantee

(a) If the Borrower has failed to make payment of principal or interest or any other payment

required under the Loan Agreement, and such payment has been made by the Guarantor, the

Guarantor may after consultation with the Bank, and by notice to the Bank and the Borrower,

terminate its obligations under the Guarantee Agreement with respect to any amount of the Loan

undisbursed from the Loan Account on the date of receipt of such notice by the Bank and not

Page 60: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 60/99

INTERNATIONAL FINANCING ON POWER PROJECTS

60

subject to any Special Commitment. Upon receipt of such notice by the Bank, and subject to

 paragraph (b) below, the Guarantor‘s obligations in respect of such amount shall terminate. 

(b) For the purposes of paragraph (a) of this Section, the Guarantor shall give prior notice to the

Bank of its intention to terminate its obligations under the Guarantee Agreement. The Bank andthe Guarantor shall have 60 days from the date of receipt of the notice by the Bank to consult

each other. If at the expiry of this notice period there is no agreement between the parties, the

Guarantor may notify the Bank of the termination of its obligations.

12.1.6 ARTICLE VI ACCELERATION TO MATURITY

SECTION 6.01 Events of Acceleration

If any of the following events occurs and continues for the period specified, as the case may be,

the Bank may, at its option, by notice to the Borrower , declare all or part of the principal of the

Loan then outstanding to be due and payable immediately together with the interest, prepayment

costs, Special Commitment Charge, Commitment Charge and other charges thereon and upon

any such notice, such principal together with the interest, prepayment costs, Special

Commitment Charge, Commitment Charge and other charges thereon shall become due and

payable immediately from the date of such notification:

Payment Default

(a) A default occurs in the payment of principal or interest or any other payment required under

the Loan Agreement and such default shall continue for a period of 30 consecutive days.

(b) A default occurs in the payment by the Borrower of principal or interest or any other amount

due to the Bank: (i) under any other loan agreement between the Bank and the Borrower (ii) in

consequence of any guarantee or other financial obligation of any kind extended by the Bank to

any third party with the agreement of the Borrower (iii) under any loan agreement between the

Bank and the Borrower, and such default shall continue for a period of 30 consecutive days.

Page 61: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 61/99

INTERNATIONAL FINANCING ON POWER PROJECTS

61

Performance Default

(c) A default occurs in the performance of any other obligation on the part of the Borrower

under the Loan Agreement or any Hedging Agreement, and such default shall continue for a

period of 60 days after notice thereof has been given by the Bank to the Borrower.

12.1.7 ARTICLE VII TAXES

SECTION 7.01 Taxes

(a) The principal of, and interest, Special Commitment charge, commitment charge and other

charges on, the Loan shall be paid without deduction for, and free from, any taxes levied in the

territory of the country of the Borrower. 

(b) The Loan Agreement shall be free from any taxes levied in the territory of the country of the

Borrower. 

12.1.8 ARTICLE VIII PROJECT IMPLEMENTATION - COOPERATION AND

INFORMATION-FINANCIAL AND OTHER INFORMATION - NEGATIVE PLEDGE

(PARI PASSU)

SECTION 8.01Project Implementation

The Borrower shall carry out the Project and/or cause the Executing Agency to carry out the

Project:

(a) With due diligence and efficiency;

(b) In conformity with all applicable laws and regulations;

(c) In conformity with appropriate administrative, technical, financial, economic, environmental

and social standard and practices; and

(d) In accordance with the provisions of the Loan Agreement, as well as any performance

arrangement to be entered into between the Borrower and the Executing Agency.

SECTION 8.02Cooperation and Information

Page 62: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 62/99

INTERNATIONAL FINANCING ON POWER PROJECTS

62

(a) The Bank and the Borrower, as the case may be, shall cooperate fully to ensure that the

purposes of the Loan will be accomplished. To that end, the Bank, the Borrower shall:

(i) From time to time, at the request of any one of them, exchange views with regard to the

progress of the Project, the purposes of the Loan, and the performance of their respectiveobligations under the Loan Agreement and provide to the other party all such information related

thereto as it shall reasonably request.

(b) The Borrower and the Guarantor shall afford all reasonable opportunity for representatives

of the Bank to visit any part of the territory of their country for purposes related to the Loan and

enable the Bank's representatives to visit any facilities and construction sites included in the

Project and to examine the goods financed out of the proceeds of the Loan and any plants,

installations, sites, works, buildings, property, equipment, records and documents relevant to the

performance of the obligations of the Borrower under the Loan Agreement.

(c) The Borrower shall permit staff and other representatives of the Bank including members of 

the Bank's Compliance Review and Mediation Unit or its Independent Review Mechanism to

perform their functions including conducting investigations, as necessary. In this connection, the

Borrower shall provide such representatives of the Bank relevant information and facilitate the

examination of records, accounts and other documents or interview relevant persons, as

determined by the Bank.

SECTION8.03. Financial and Other Information

The Borrower shall provide to the Bank the information that the Bank shall request relating to

their respective organizational structure, operations, financial situation and, in particular,

financial statements.

SECTION8.04. Negative Pledge

(a) In providing a Loan, the Bank may require that the Regional Member State, or a public

institution of the Regional Member State in whose territory the Borrower is located or

incorporated, provides a Guarantee and/or request that the Borrower provides such other

assurances to the effect that the Borrower shall fulfill its obligations to the Bank. Such securities

may be enforced in accordance with their governing law.

Page 63: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 63/99

INTERNATIONAL FINANCING ON POWER PROJECTS

63

(b) The Borrower undertakes that, except as the Bank shall otherwise agree:

(i) if such Borrower shall create any Lien on any of its Assets as security for any debt, such Lien

will equally secure the payment of the principal of, and interest, prepayment costs, Special

Commitment Charge, Commitment Charge and other charges on, the Loan and in the creation of any such Lien express provision will be made to that effect, at no cost to the Bank.

(c) The foregoing provisions of paragraph (b) of this Section shall not apply to: (i) any Lien

created on property, at the time of purchase thereof, solely as security for the payment of the

purchase of such property (ii) any Lien arising in the ordinary course of banking transactions and

securing a debt maturing not more than one year after the date on which it is originally incurred.

SECTION8.05. Insurance

The Borrower shall insure or cause to be insured the goods to be financed out of the proceeds of 

the Loan against hazards incidental to the acquisition, transportation, delivery, installation and

use thereof during the entire period of Project implementation until completion. Any indemnity

for such insurance shall be payable in a freely usable Currency to replace or repair such goods.

SECTION8.06. Plans and Schedules

The Borrower shall promptly provide, or cause to be provided, to the Bank upon their

preparation, copies of any plans, specifications, reports, contract documents, construction, and

procurement schedules for the Project, and any material modifications thereof or additions

thereto, in such detail as the Bank shall reasonably request.

SECTION8.07. Accounts, Records and Audit

(a) The Borrower shall cause the Executing Agency to:

(i) Maintain records and procedures adequate to record and monitor the progress of the Project

(including its costs and the benefits to be derived from it, according to indicators acceptable to

the Bank), to identify the goods, works and services financed out of the proceeds of the Loan,

and to disclose their use in the Project;

Page 64: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 64/99

INTERNATIONAL FINANCING ON POWER PROJECTS

64

(ii) Provide to the Bank reports in form and substance satisfactory to the Bank on the execution

of the Project, including recommendations to ensure the continued effective and efficient

execution of the Project with a view to achieve its objective, at such intervals as provided by the

applicable Bank policy and in accordance with the directives which the Bank shall from time to

time issue to that end.

(iii) Provide to the Bank at regular intervals all such information and reports as the Bank shall

reasonably request concerning the Project, its cost and, where appropriate, the benefits to be

derived from it, the participation of Project beneficiaries in the implementation and supervision

of the Project, the expenditure of the proceeds of the Loan and the goods, works and services

financed out of such proceeds.

(b) The Borrower shall provide the audited financial statements to the Bank as promptly as

possible and, in any event, not later than 6 months after the end of the relevant financial year.

(c) The Borrower shall cause the Executing Agency to, keep all records (contracts, orders,

invoices, bills, receipts and other documents) evidencing expenditures financed with the Loan

until the later of: (i) one year after the Bank has received the audited financial statements

covering the period during which the last disbursement of the Loan was made (ii) two years after

the Closing Date. The Borrower shall enable the Bank‘s representatives to examine such records. 

12.1.9 ARTICLE IX - SETTLEMENT OF DISPUTES - APPLICABLE LAW

SECTION 9.01 Settlements of Disputes

(a) Except for liens and other securities taken where the Bank can decide to enforce its rights in

accordance with the law governing the creation of such securities, any controversy between the

parties to the Loan Agreement and any claim by a party against the other party arising under the

Loan Agreement will be settled. If no settlement is reached within 90 days from the date

notification is given by one party of a request for submission of the dispute to settlement, the

dispute may be submitted to arbitration, as provided hereunder, by either party.

Page 65: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 65/99

INTERNATIONAL FINANCING ON POWER PROJECTS

65

(b) Except as otherwise specified in this Section, the arbitration shall be conducted in accordance

with the United Nations Commission on International Trade Law (UNCITRAL) Arbitration

Rules. The parties to such arbitration shall be the Bank on the one side and the Borrower and on

the other side.

(c) The arbitral tribunal shall consist of three arbitrators appointed as follows:

One arbitrator shall be appointed by the Bank; a second arbitrator shall be appointed by the

Borrower, and the third arbitrator (sometimes called the Umpire) shall be appointed by the two

arbitrators first appointed by the parties. If within 30 days from the date of notification of the

submission to arbitration, either side fails to appoint an arbitrator, such arbitrator shall be

appointed by the appointing authority. If within 60 days after the notice instituting the arbitration

proceeding, the two arbitrators shall not have agreed upon an Umpire, any party may request the

appointing authority to designate the Umpire. In case any arbitrator appointed in accordance with

this Section resigns, dies or becomes unable to act, a successor arbitrator shall be appointed in

the same manner as herein prescribed for the appointment of the original arbitrator and such

successor shall have all the powers and duties of such original arbitrator.

SECTION 9.02 Applicable Law

Unless otherwise provided in the Loan Agreement, the law to be applied to the Loan Agreement

shall be public international law, the sources of which shall be taken for these purposes to

include:

(a) Any relevant treaty obligations that are binding reciprocally on the parties to these

agreements;

(b) The provisions of any international conventions and treaties generally recognized as having

codified into binding rules of customary law applicable to states and to international financial

institutions, as appropriate;

(c) International custom, as evidence of a practice accepted as law; and

(d) General principles of law applicable to multilateral economic development activities.

Page 66: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 66/99

INTERNATIONAL FINANCING ON POWER PROJECTS

66

13. WHY NTPC IS SUPERIOR THAN OTHERS?

RELIANCE POWER 

1. RELIANCE POWER & ADANI POWER as well as others domestic & foreign companies

have bid for setting up a Rs 1,025-crore power transmission project connecting Tamil Nadu and

Karnataka even as the central government tightened eligibility rules on 26-07-2011.

Power Finance Corp is coordinating the bidding for the build-own-operate project; which

involves laying two high capacity 250-km transmission lines to connect Nagapattinam with

Madhugiri in Karnataka.

2. RELIANCE POWER is likely to get a loan of $625 million (Rs 2,800 crore) from US Exim

Bank to fund its upcoming 2,400-MW gas-based power project in Samalkot, Andhra Pradesh on

25-07-2011.

Mr. Fred P Hochberg, Chairman President of US Exim Bank told that ―The US Exim Bank is

close to disbursing a loan of $625 million for Reliance Power plant in Samalkot. The approval

should come in 4 to 6 weeks. We have already funded Reliance Power's coal-based power

project in Sasan and its mining venture."

This loan is a part of the $5-billion deal signed with Reliance Power for the purchase of US

manufactured equipment for power projects. This loan is to be disbursed because last year

Reliance Power placed a $750-million equipment contract with GE for the 2,400-MWSamalkot

expansion.

3. RELIANCE POWER aims to earn Rs 5,000 crore from carbon credit from the three ultra-

mega power projects of 4,000 MW on 12-07-2011. 

It seeks to earn almost Rs 2,000 crore in 10 years by registering its 4,000 MW Tilaiya ultra mega

power project for carbon credits after it got two of the other mega projects registered with the

Clean Development Mechanism Executive Board (CDM-EB) of United Nations Framework 

Convention on Climate Change (UNFCCC).

4. The Madhya Pradesh government has asked RELIANCE POWER to sign the power

purchase agreement (PPA) for the 3,960-MW Chitrangi power project by the end of July month.

Page 67: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 67/99

INTERNATIONAL FINANCING ON POWER PROJECTS

67

TATA POWER VS. RELIANCE POWER ON 14-07-2011

The Supreme Court on Wednesday admitted Tata group's plea against the government's decision

to allow RELIANCE POWER to use coal mined from blocks allotted to Sasan Power for other

projects, but the ADAG Company said it is going ahead with implementation of its projects asper schedule. 

A bench of Justice admitted the petition of Tata group company Tata Power and posted the

matter for hearing in February next year.

Tata Power has challenged the Centre's decision to allow Reliance Power to use coal minded

from blocks allotted to the Rs 20,000-crore Sasan Power Project for other power projects.

Tata Power has challenged the decision by the Empowered Group of Ministers to allow Reliance

Power to use excess coal from the captive mines meant for the Sasan project in Madhya Pradesh

for another 4,000 MW project at Chitrangi in the same state.

However, Tata Power had refuted these allegations in its rejoinder and submitted that bidding

process for Sasan UMPP was never meant or intended to vest the successful bidder to extra coal

supply of 9 million ton per annum, which could be used for developing other power projects.

ADANI POWER

1. ADANI POWER may look at bidding for UMPP with capacity 4000 MW on 18-07-2011.

Adani with its subsidiaries having combine capacity 16,500 MW in the coming year.

"The company is in advanced stages of implementing 4,620 MW coal-based power project at

Mundra in Gujarat, 3,300 MW coal- based power project at Tiroda in Maharashtra and 1,320

MW coal-based power project at Kawai in Rajasthan".

Adani Power posted a total income of Rs 2,125.07 crore, including Rs 2,106.43 crore from sale

of power. The entity raked in a profit after tax of Rs 523.75 crore last fiscal.

2. ADANI POWER will merge group firm Grow more Trade and Investment Private Ltd,

Mauritius with itself, the company said on 7-7-2011, in a stock deal worth 23.6 billion rupees

($531 million).

Page 68: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 68/99

INTERNATIONAL FINANCING ON POWER PROJECTS

68

The Merger would be at a share swap ratio of 16,615 shares of Adani Power of 10 rupees each

for every 10,000 ordinary shares of $1 each of Grow more.

A total of 213.2 million shares of Adani will be issued to Grow more as a result of this swap

deal.

NTPC 

1. State-run power major NTPC's trading arm NTPC Vidyut Vypar Nigam Ltd. (NVVN) has

been given the mandate to export 250 MW of power from NTPC to Bangladesh on 18-07-2011.

NVVN has signed the power purchase agreement with the Bangladesh Power Development

Board (BPDB).

The transmission lines between India and Bangladesh are being set up under a pact signed

between Power Grid Corporation of India Ltd and BPDB in July last year.

The links are expected to be in place by early 2013 and are being executed at a cost of around

USD 190 million.

The interconnection between India and Bangladesh is being established through a 500-MW

HVDC (high voltage direct current) link between India's eastern region and the western grid of 

Bangladesh.

2. NTPC will make a final offer for a stake in Australia's Bandanna Energy Ltd on 13-07-2011.

NTPC has cut its generation capacity target to 70,000-mw by March 2017 from 75,000-mw

earlier, due to coal, gas supply and land acquisition issues.

3. Coal supply shortages and environmental hurdles may force state-run NTPC to scale down its

target for ramping up power generation capacity to 75,000 MW by 2017 to 70,000 MW. "We

would be able to do about 70,000 MW by 2017, remaining 5,000 MW looks difficult due to coal

shortage and environment issues" on 13-07-2011.

The company, which requires huge funding for its upcoming and expansion projects, recently

signed a Rs 10,000 crore (over USD 2 billion) loan agreement with State Bank of India for

financing its projects.

Page 69: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 69/99

INTERNATIONAL FINANCING ON POWER PROJECTS

69

4. State-run NTPC has raised USD 500 million through an international bond issue that attracted

commitments worth USD 2.7 billion from foreign investors. The latest fund raising from NTPC

also indicates revival in overseas bond market and could also encourage more Indian entities to

tap the route on 10-07-2011.

NTPC's bond issue elicited response from more than 230 investors, who made commitments to

the tune of USD 2.7 billion.

NTPC's upcoming projects include 1,320 MW Sholapur plant and 4,000 MW mega thermal

power plants in Kudgi, Karnataka. The entity plans to add 1, 28,000 MW capacity by 2032.

In recent times, European debt woes and concerns about health of global economy have cast a

shadow on fund raising activities in international markets.

The bond sale was part of the company's USD 1 billion Medium Term Note (MTN) programme.

These bonds have a coupon of 5.625 per cent per annum payable semi-annually and are due for

maturity on July 14, 2021.

Book runners for the USD 500 million bond issue were Barclays Capital, Citigroup, Deutsche

Bank and The Royal Bank of Scotland.

Page 70: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 70/99

INTERNATIONAL FINANCING ON POWER PROJECTS

70

14. REGULATORY FRAMEWORK FOR INTERNATIONAL FINANCE

14.1 EXTERNAL COMMERCIAL BORROWINGS (ECB) 

External Commercial Borrowings availed of by residents are governed by clause (d) of sub-section 3 of section 6 of the Foreign Exchange Management Act, 1999 read with Notification

No. FEMA 3/ 2000-RB. Foreign Exchange Management Regulations, 2000, dated May 3, 2000,

as amended from time to time.

At present, Indian companies are allowed to access funds from abroad in the following methods:

(a) External Commercial Borrowings (ECB) refer to commercial loans in the form of bank loans,

 buyers‘ credit, suppliers‘ credit, securitized instruments (e.g. floating rate notes and fixed rate

bonds, non-convertible, optionally convertible or partially convertible preference shares) availed

of from non-resident lenders with a minimum average maturity of 3 years.

(b) Foreign Currency Convertible Bonds (FCCBs) mean a bond issued by an Indian company

expressed in foreign currency, and the principal and interest in respect of which is payable in

foreign currency.

(c) Foreign Currency Exchangeable Bond (FCEB) means a bond expressed in foreign currency,

the principal and interest in respect of which is payable in foreign currency, issued by an Issuing

Company and subscribed to by a person who is a resident outside India, in foreign currency and

exchangeable into equity share of another company, to be called the Offered Company, in any

manner, either wholly, or partly or on the basis of any equity related warrants attached to debt

instruments.

ECB can be accessed under two routes:-

(i) Automatic Route (ii) Approval Route

Page 71: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 71/99

INTERNATIONAL FINANCING ON POWER PROJECTS

71

14.1.1 AUTOMATIC ROUTE

The following types of proposals for ECBs are covered under the Automatic Route:-

i) Eligible Borrowers

(a) Corporates and Infrastructure Finance Companies (IFCs) except financial intermediaries,

such as banks, financial institutions (FIs), and Non-Banking Financial Companies (NBFCs) are

eligible to raise ECB. Individuals, Trusts and Non-Profit making organizations are not eligible to

raise ECB.

(b) Units in Special Economic Zones (SEZ) are allowed to raise ECB for their own requirement.

(c) Non-Government Organizations (NGOs) engaged in micro finance activities are eligible to

avail of ECB. Such NGOs should have a satisfactory borrowing relationship for at least 3 years

with a scheduled commercial bank authorized to deal in foreign exchange in India.

ii) Recognized Lenders

Borrowers can raise ECB from internationally recognized sources such as (i) international banks,

(ii) international capital markets, (iii) multilateral financial institutions (such as IFC, ADB, etc.) / 

regional financial institutions and Government owned development financial institutions, (iv)

export credit agencies, (v) suppliers of equipment‘s, (vi) foreign collaborators and (vii) foreign

equity holders (Overseas Corporate Bodies (OCBs)).

A "foreign equity holder" to be eligible as ―recognized lender‖ under the automatic route would

require minimum holding of paid-up equity in the borrower company as set out below:

(a) For ECB up to USD 5 million - minimum paid-up equity of 25 percent held directly by the

lender.

(b) For ECB more than USD 5 million - minimum paid-up equity of 25 percent held directly by

the lender and debt-equity ratio not exceeding 4:1.

Page 72: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 72/99

INTERNATIONAL FINANCING ON POWER PROJECTS

72

iii) Amount and Maturity

a) The maximum amount of ECB which can be raised by a corporate is USD 500 million or its

equivalent during a financial year.

b) Corporates are allowed to avail of ECB up to USD 100 million or its equivalent in a financial

year for meeting foreign currency and/ or Rupee capital expenditure for permissible end-uses.

c) ECB up to USD 20 million or its equivalent in a financial year with minimum average

maturity of three years.

d) ECB above USD 20 million or equivalent and up to USD 500 million or its equivalent with a

minimum average maturity of five years.

iv)All-in-cost ceilings

All-in-cost includes rate of interest, other fees and expenses in foreign currency except

commitment fee, pre-payment fee, and fees payable in Indian Rupees. The payment of 

withholding tax in Indian Rupees is excluded for calculating the all-in-cost. The all-in-cost

ceilings for ECB are reviewed from time to time.

The following ceilings are valid until reviewed:

Average Maturity Period All-in-cost Ceilings over 6 month LIBOR*

Three years and up to five years 300 basis points

More than five years 500 basis points

In the case of fixed rate loans, the swap cost plus margin should be the equivalent of the floating

rate plus the applicable margin.

Page 73: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 73/99

INTERNATIONAL FINANCING ON POWER PROJECTS

73

v) End-use

a) ECB can be raised for investment (such as import of capital goods new projects,

modernization/expansion of existing production units) in real sector - industrial sector including

small and medium enterprises (SME), infrastructure sector in India. 

b) Overseas direct investment in Joint Ventures (JV)/ Wholly Owned Subsidiaries (WOS)

subject to the existing guidelines on Indian Direct Investment in JV/ WOS abroad.

c) Utilization of ECB proceeds is permitted for first stage acquisition of shares in the

disinvestment process and also in the mandatory second stage offer to the public under the

Government‘s disinvestment program of PSU shares. 

d) Infrastructure Finance Companies (IFCs) i.e. Non-Banking Financial Companies (NBFCs)

categorized as IFCs by the Reserve Bank are permitted to avail of ECBs, including the

outstanding ECBs, up to 50 per cent of their owned funds, for on-lending to the infrastructure

sector as defined under the ECB policy.

vi)End-uses not permitted

(a) For on-lending or investment in capital market or acquiring a company in India by a

corporate (investment in Special Purpose Vehicles (SPVs), Money Market Mutual Funds

(MMMFs), etc., are also considered as investment in capital markets).

(b) For real estate sector.

(c) For working capital, general corporate purpose and repayment of existing Rupee loans.

vii) Guarantees

Issuance of guarantee, standby letter of credit or letter of comfort by banks, Financial Institutions

and Non-Banking Financial Companies (NBFCs) from India relating to ECB is not permitted.

Page 74: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 74/99

INTERNATIONAL FINANCING ON POWER PROJECTS

74

viii) Security

The choice of security to be provided to the lender/supplier is left to the borrower. However,

creation of charge over immoveable assets and financial securities, such as shares, in favour of 

the overseas lender is subject to Regulation 8 of Notification No. FEMA 21/RB-2000 dated May

3, 2000 and Regulation 3 of Notification No. FEMA 20/RB-2000 dated May 3, 2000,

respectively, as amended from time to time.

AD Category - I banks have been delegated powers to convey ‗no objection‘ under the Foreign

Exchange Management Act (FEMA), 1999 for creation of charge on immovable assets, financial

securities and issue of corporate or personal guarantees in favour of overseas lender / security

trustee, to secure the ECB to be raised by the borrower.

ix) Parking of ECB proceeds

Borrowers are permitted to either keep ECB proceeds abroad or to remit these funds to India,

pending utilization for permissible end-uses.

x) Prepayment

Prepayment of ECB up to USD 500 million may be allowed by AD banks without prior approval

of Reserve Bank subject to compliance with the stipulated minimum average maturity period as

applicable to the loan.

xi) Refinancing of an existing ECB

The existing ECB may be refinanced by raising a fresh ECB subject to the condition that the

fresh ECB is raised at a lower all-in-cost and the outstanding maturity of the original ECB is

maintained.

Page 75: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 75/99

INTERNATIONAL FINANCING ON POWER PROJECTS

75

xii) Debt Servicing

The designated AD bank has the general permission to make remittances of installments of 

principal, interest and other charges in conformity with the ECB guidelines issued by

Government / Reserve Bank of India from time to time.

xiii) Procedure

Borrowers may enter into loan agreement complying with the ECB guidelines with recognized

lender for raising ECB under Automatic Route without the prior approval of the Reserve Bank.

The borrower must obtain a Loan Registration Number (LRN) from the Reserve Bank of India

before drawing down the ECB.

14.1.2 APPROVAL ROUTE

i) Eligible Borrowers

The following types of proposals for ECB are covered under the Approval Route:-

a) ECB with minimum average maturity of 5 years by Non-Banking Financial Companies

(NBFCs) from multilateral financial institutions, reputable regional financial institutions, official

export credit agencies and international banks to finance import of infrastructure equipment for

leasing to infrastructure projects.

b) Infrastructure Finance Companies (IFCs) i.e. Non-Banking Financial Companies (NBFCs),

categorized as IFCs, by the Reserve Bank, are permitted to avail of ECBs, including theoutstanding ECBs, beyond 50 per cent of their owned funds, for on-lending to the infrastructure

sector as defined under the ECB policy.

Page 76: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 76/99

INTERNATIONAL FINANCING ON POWER PROJECTS

76

c) Special Purpose Vehicles, or any other entity notified by the Reserve Bank, set up to finance

infrastructure companies / projects exclusively, will be treated as Financial Institutions and ECB

by such entities will be considered under the Approval Route.

ii) Recognized Lenders: - Same as Automatic Route for Infrastructure (Power) projects.

iii) Amount and Maturity

Corporates can avail of ECB of an additional amount of USD 250 million with average maturity

of more than 10 years under the approval route, over and above the existing limit of USD 500

million under the automatic route, during a financial year.

iv)All-in-cost ceilings: - Same as Automatic Route for Infrastructure (Power) projects.

v) End-use:- Same as Automatic Route for Infrastructure (Power) projects.

vi)End-uses not permitted: - Same as Automatic Route for Infrastructure (Power) projects.

vii) Guarantee: - Same as Automatic Route for Infrastructure (Power) projects.

viii) Security: - Same as Automatic Route for Infrastructure (Power) projects.

ix) Parking of ECB proceeds: - Same as Automatic Route for Infrastructure (Power) projects.

x) Prepayment

Pre-payment of ECB for amounts exceeding USD 500 million would be considered by the

Reserve Bank under the Approval Route.

xi) Refinancing of an existing ECB: - Same as Automatic Route for Infrastructure (Power)

projects.

Page 77: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 77/99

INTERNATIONAL FINANCING ON POWER PROJECTS

77

xii) Debt Servicing: - Same as Automatic Route for Infrastructure (Power) projects.

xiii) Procedure

Applicants are required to submit an application in form ECB through designated AD bank to the

Chief General Manager-in-Charge, Foreign Exchange Department, Reserve Bank of India,

Central Office, External Commercial Borrowings Division, Mumbai  –  400 001, along with

necessary documents.

14.1.3 TAKE-OUT FINANCE

Refinancing of domestic Rupee loans with ECB is not permitted. Accordingly, take-out

financing arrangement through ECB, under the approval route, has been permitted for

refinancing of Rupee loans availed of from the domestic banks by eligible borrowers in the

power sectors for the development of new projects.

Page 78: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 78/99

INTERNATIONAL FINANCING ON POWER PROJECTS

78

15.  RISKS FOR THE INVESTORS 

15.1 Risk mitigation

Risks are perceived as high partly because projects are typically undertaken not by established

utility companies with strong balance sheets but by special purpose companies executingindividual projects on a build-operate-transfer or build-own-operate basis.

The risks associated with the revenue stream are therefore scrutinized. Equity investors may be

willing to accept higher levels of risk in return for higher expected returns on their equity, but

lenders typically have a lower tolerance for risk and a greater need for risk mitigation

mechanisms.

Different kinds of risk

15.2 Construction risk: -  Construction risk refers to unexpected developments during the

construction period that lead to time and cost overruns or shortfalls in performance parameters of 

the completed project.

High capital intensity and a relatively long construction period make project costs especially

vulnerable to delays and cost overruns. As a result construction risk is generally higher in sectors

such as power and lower in sectors such as telecommunications and urban services.

The reputation and experience of the sponsors and the engineering, procurement, and

construction (EPC) contractor is an important element in assessing construction risk.

While construction risk can be shifted to some extent, it cannot be eliminated entirely, since

penalties for non-performance are typically capped at certain levels and the residual risk has to

be borne by investors.

However, lenders would be satisfied with risk sharing that reduces project risk to a level that can

be absorbed by equity investors without jeopardizing loan repayments.

15.3 Operating risk: - Operating risk is usually low for infrastructure projects and high for

telecommunication sector. Operating risks are typically mitigated by entrusting operation to

experienced operations and maintenance (O & M) contractors.

Page 79: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 79/99

INTERNATIONAL FINANCING ON POWER PROJECTS

79

One source of operating risk that is very important in the power sector is fuel supply risk.

Private financing of power projects depends critically on the ability to negotiate satisfactory fuel

supply agreements, with appropriate penalties payable by the fuel supplier in the event of 

nonperformance.

Fuel supply problems are being tackled in different ways in different private sector power

projects in India.

15.4 Market risk: - Nonfulfillment of demand projections is an obvious example of market risk.

In certain situations investors expect the monopoly purchaser to guarantee a minimum level of 

purchase, thus eliminating market risk for the investor.

This is typically the case when an independent power producer sells power to a monopoly

distributor or a water supply project sells water in bulk to a monopoly urban water distributing

company.

Investors are expected to undertake market studies and satisfy themselves that market demand

projections at feasible levels would yield adequate profitability.

15.5 Interest rate risk: - Interest rate risks arise because interest rates can vary during the life of 

the project. They are particularly important in infrastructure projects because of the high capital

intensity and long payback periods.

High capital intensity implies that interest costs represent a large part of total costs; long payback 

periods mean that financing must be available over a long period, during which interest rates

may change.

One way of handling interest rate risk is to pass it on to consumers, as, for example, in

arrangements in which the impacts of interest rate variations on unit costs are treated as a pass-

through into the tariff.

In the cost-based tariff formula used in many power projects in India, for example, interest costs

are built into the tariff.

Page 80: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 80/99

INTERNATIONAL FINANCING ON POWER PROJECTS

80

Risk to be borne by the investor, who in turn can hedge the risk through devices such as interest

caps and collars.

The feasibility of this option depends on the sophistication of the relevant financial markets and

the availability of hedging instruments.

Typically, it is much easier to hedge interest rate risks in international markets than in domestic

markets.

15.6 Foreign exchange risk: - Two types of foreign exchange risk need to be distinguished. One

relates to exchange convertibility, the assurance that revenues generated in domestic currency

can be converted into foreign exchange for making payments abroad.

This risk must be borne by the government through suitable convertibility guarantees.

The other type of risk is exchange rate risk, the risk that exchange rate changes lead to large

increases in the domestic currency costs of payments denominated in foreign currency.

15.7 Payment risk: -  It becomes very important in situations in which an independent power

producer has to supply electric power to a monopoly buyer, such as a public sector distributor, or

a water purifying company has to supply water to a municipal distributor.

Because the financial condition of public sector utilities in developing countries is often very

weak, investors are naturally concerned about the risk of nonpayment for power or water

delivered to the distributor when the producer has no alternative outlet for the product.

The long-term solution to this problem is to improve the financial standing and creditworthiness

of the utilities or to privatize distribution so that private sector suppliers can deal directly with

private distribution companies or undertake distribution themselves.

15.8 Regulatory risk: - Regulatory risk arises because infrastructure projects have to interface

with various regulatory authorities throughout the life of the project, making them especially

vulnerable to regulatory action.

Another source of regulatory risk is that environmental concerns and standards can become more

stringent during the life of the project, adding to the costs of operation.

Page 81: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 81/99

INTERNATIONAL FINANCING ON POWER PROJECTS

81

Private investors will expect explicit assurances that cost increases imposed because of 

regulatory action will be reflected in a corresponding adjustment in the tariff to project

profitability.

15.9 Political risk: -  These risks can be partially mitigated through political risk insuranceoffered by multilateral organizations, such as the Multilateral Investment Guarantee Agency

(MIGA), or bilateral investment protection agreements.

The World Bank's new partial risk guarantee instrument, which covers debt service payments in

case they are interrupted because of nonperformance of specific government obligations, is

another instrument that can play a useful role in this context.

15.10 Arrangements for risk mitigation

Power projects with suitable off take guarantees may have high construction risks, relatively low

operational and market risks, and high payment risk.

Each project has its own risk profile, and risk mitigation structures will vary depending on the

specific circumstances of each project.

Because of the nature of the risks and the involvement of many participants, including project

sponsors, lenders, government agencies, and regulatory authorities, risk mitigation arrangements

are usually complex.

Page 82: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 82/99

INTERNATIONAL FINANCING ON POWER PROJECTS

82

16. DATA ANALYSIS OF THE PROJECT

Table16.1: Opening Loan balance sheet of all banks

ACCOUNTS CLOSING OPENING DATA

Loan Balance as on 01/04/2011

OPENING LOAN BALANCE

LOAN CODE ERV CODE CURRENCY FC

IBRD-3632-O 2031000 2031002 USD 91,636,958.87

ASIAN DEVEL. BANK 2040050 2040052 JPY 4,267,130,741.00

JBIC-I (IDP-120) 2040040 2040042 JPY 15,110,368,000.00

JBIC-II (IDP-138) 2040040 2040042 JPY 11,894,480,000.00

JBIC-III (IDP-140) 2040040 2040042 JPY 24,631,749,571.00

JBIC-IV (IDP-144) 2040040 2040042 JPY 854,649,867.00

EUROBONDS 2011 2040020 2040022 USD 0.00

KEXIM 2040050 2040052 USD 268,389,075.65

SWEDISH 2040050 2040052 USD 11,884,649.13

EUROBONDS 2016 2040020 2040022 USD 300,000,000.00

ADB II Tranche A 2040050 2040052 USD 75,000,000.00

ADB II Tranche B 2040050 2040052 USD 160,713,000.00

KFW 2040050 2040052 USD 85,714,300.00

JBIC BARH 2040050 2040052 USD 283,610,000.00

NIB 2040050 2040052 EUR 68,563,000.00

BTMU 2040050 2040052 USD 300,000,000.00

Page 83: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 83/99

INTERNATIONAL FINANCING ON POWER PROJECTS

83

Table16.2: Loan wise Allocation of Interest (Net Charge) as on 04/07/2011

Cumulative up to 04/07/2011

LOAN NO. CURR. Account

Code

Total Interest Withholding

Tax

Total

WORLD BANK-MAIN USD 4060001

17,466,883 17,466,883

Project Share

Vindyachal-II 0.682263

11,917,008 11,917,008

Kayamkulam 0.273656

4,779,917 4,779,917

EAP-Singrauli 0.011115194,144 194,144

EAP-Korba 0.008131

142,023 142,023

EAP-Ramagundam 0.005472

95,579 95,579

EAP-Farakka 0.001875

32,750 32,750

EAP-Rihand 0.002263

39,528 39,528

EAP-Kahalgaon 0.001668

29,135 29,135EAP-Unchahar 0.001550

27,074 27,074

EAP-Vindyachal-I 0.005490

95,893 95,893

Korba 0.006517

113,832 113,832

ADB-Unchahr-II USD 4060002

9,798,267 9,798,267

Total ADB interest for

Unchahar

JBIC-I, JAPAN-Simhadri JPY 4060001

4,109,999 4,109,999

JBIC-II, JAPAN-Simhadri JPY 4060001

2,367,719 2,367,719

JBIC-III, JAPAN-Simhadri JPY 4060001

5,243,323 5,243,323

Page 84: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 84/99

INTERNATIONAL FINANCING ON POWER PROJECTS

84

JBIC-IV, JAPAN-Simhadri JPY 4060001

170,127 170,127

Total JBIC Interest for

Simhadri 11,891,168 11,891,168

KEXIM - Sipat I 4060002

9,716,070 934,349 10,650,419

Sipat I

SWEDISH Credit Sipat II 4060002

2,039,563 2,039,563

Sipat II

5.875 % Euro Bonds 2016 USD 4060004

206,526,323 53,939,294 260,465,617

Project ShareKoldam 0.045

9,293,685 2,427,268 11,720,953

VSTPP III 0.1945

40,169,370 10,491,193 50,660,563

Unchahar III 0.0514

10,615,453 2,772,480 13,387,933

Sipat I 0.2021

41,738,970 10,901,131 52,640,101

Sipat II 0.2243

46,323,854 12,098,584 58,422,438

Barh 0.0517

10,677,411 2,788,661 13,466,072

Kahalgaon II 0.1642

33,911,622 8,856,832 42,768,454

Korba III 0.0668

13,795,958 3,603,145 17,399,103

ADB II Tranche A USD 4060002

688,992 688,992

Project Share

Sipat I 0.36667

252,630 252,630

Sipat II 0.32286

222,446 222,446

Kahalgaon II 0.31048

213,915 213,915

ADB II Tranche B USD 4060002

1,272,619 1,272,619

Page 85: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 85/99

INTERNATIONAL FINANCING ON POWER PROJECTS

85

Project Share

Sipat I 0.1133

144,230 144,230

Sipat II 0.3393

431,769 431,769

Kahalgaon II 0.5474 696,620 696,620

KfW 4060002

830,705 830,705

Project Share

Tanda 0.29332

243,660 243,660

Singrauli 0.11806

98,076 98,076

Anta 0.32465

269,685 269,685

TTPS 0.08341

69,288 69,288

Farakka 0.01815

15,081 15,081

Unchahar 0.07712

64,063 64,063

Rihand 0.06676

55,460 55,460

Vindyachal 0.01853

15,393 15,393

JBIC Barh 4060002

(2,010,716) (2,010,716)

NIB Loan 4060002

2,060,093 2,060,093

Project Share

ANTA 0.34522

711,181 711,181

Sipat I 0.38200

786,962 786,962

Dadri- II 0.27278

561,950 561,950

BTMU

1,307,137 167,156 1,474,293

Project

Rihand-III

0.13697 179,039 22,895 201,934

Page 86: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 86/99

INTERNATIONAL FINANCING ON POWER PROJECTS

86

Barh-II

0.14158 185,064 23,666 208,730

Vindhyachal-IV

0.19789 258,663 33,078 291,740

Simhadri-II

0.11118 145,327 18,584 163,912Mauda

0.41239 539,044 68,933 607,976

BTMU

1,175,527 162,964 1,338,491

Project

Rihand-III

0.17939 210,880 29,234 240,114

Barh-II

0.31389 368,987 51,153 420,140

Vindhyachal-IV

0.17780 209,005 28,974 237,979

Simhadri-II

0.07475 87,876 12,182 100,059

Mauda

0.25417 298,779 41,420 340,199

Net Charge

262,762,631 55,203,763 317,966,394

Page 87: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 87/99

INTERNATIONAL FINANCING ON POWER PROJECTS

87

Table16.3: Weighted average of KFW Bank

WEIGHTED AVERAGE - KFW WORKINGS:

TRANCHEDATE OF

DRAWLAMOUNT IN USD PROJECT ROI DATE FROM DATE UPTO NO. OF DAYS

KFW - D I 9/24/2007 3,175,000  TANDA R&M 1.0625% 4/1/2010 9/14/2010 167

9/24/2007 859,000  SINGRAULI R&M 1.0625% 4/1/2010 9/14/2010 167

9/24/2007 5,966,000  ANTA R&M 1.0625% 4/1/2010 9/14/2010 167

KFW - D II 1/8/2008 3,394,272  TANDA R&M 1.0625% 4/1/2010 9/14/2010 167

1/8/2008 1,218,541  SINGRAULI R&M 1.0625% 4/1/2010 9/14/2010 167

1/8/2008 2,626,418  ANTA R&M 1.0625% 4/1/2010 9/14/2010 167

1/8/2008 861,298  TTPS R&M 1.0625% 4/1/2010 9/14/2010 167

1/8/2008 682,784  FARAKKA R&M 1.0625% 4/1/2010 9/14/2010 167

1/8/2008 1,216,687  RIHAND R&M 1.0625% 4/1/2010 9/14/2010 167

KFW - D III 3/10/2008 4,917,388  TANDA R&M 1.0625% 4/1/2010 9/14/2010 167

3/10/2008 1,190,760  ANTA R&M 1.0625% 4/1/2010 9/14/2010 167

3/10/2008 1,450,630  TTPS R&M 1.0625% 4/1/2010 9/14/2010 167

3/10/2008 1,525,023  UNCHAHAR R&M 1.0625% 4/1/2010 9/14/2010 167

3/10/2008 916,199  RIHAND R&M 1.0625% 4/1/2010 9/14/2010 167

KFW - D IV 6/2/2008 2,515,989  TANDA R&M 1.0625% 4/1/2010 9/14/2010 167

6/2/2008 2,199,466  SINGRAULI R&M 1.0625% 4/1/2010 9/14/2010 167

6/2/2008 2,915,527  ANTA R&M 1.0625% 4/1/2010 9/14/2010 1676/2/2008 1,387,321  TTPS R&M 1.0625% 4/1/2010 9/14/2010 167

6/2/2008 575,514  FARAKKA R&M 1.0625% 4/1/2010 9/14/2010 167

6/2/2008 957,170  RIHAND R&M 1.0625% 4/1/2010 9/14/2010 167

6/2/2008 1,203,922  UNCHAHAR R&M 1.0625% 4/1/2010 9/14/2010 167

6/2/2008 1,245,091  VINDHYACHAL R&M 1.0625% 4/1/2010 9/14/2010 167

KFW - D V 9/9/2008 3,904,541  TANDA R&M 1.0625% 4/1/2010 9/14/2010 167

9/9/2008 1,239,497  SINGRAULI R&M 1.0625% 4/1/2010 9/14/2010 167

9/9/2008 2,225,269  ANTA R&M 1.0625% 4/1/2010 9/14/2010 167

9/9/2008 92,112  TTPS R&M 1.0625% 4/1/2010 9/14/2010 167

9/9/2008 271,507  FARAKKA R&M 1.0625% 4/1/2010 9/14/2010 167

9/9/2008 679,261  RIHAND R&M 1.0625% 4/1/2010 9/14/2010 167

9/9/2008 314,603  UNCHAHAR R&M 1.0625% 4/1/2010 9/14/2010 167

9/9/2008 273,210  VINDHYACHAL R&M 1.0625% 4/1/2010 9/14/2010 167

KFW - D VI 3/2/2009 3,481,000  TANDA R&M 1.0625% 4/1/2010 9/14/2010 167

3/2/2009 1,068,000  SINGRAULI R&M 1.0625% 4/1/2010 9/14/2010 167

3/2/2009 528,000  ANTA R&M 1.0625% 4/1/2010 9/14/2010 167

3/2/2009 1,031,000  TTPS R&M 1.0625% 4/1/2010 9/14/2010 167

3/2/2009 1,143,000  RIHAND R&M 1.0625% 4/1/2010 9/14/2010 167

3/2/2009 2,568,000  UNCHAHAR R&M 1.0625% 4/1/2010 9/14/2010 167

3/2/2009 181,000  VINDHYACHAL R&M 1.0625% 4/1/2010 9/14/2010 167

KFW - D VII 8/3/2009 1,336,000  TANDA R&M 1.0625% 4/1/2010 9/14/2010 167

8/3/2009 2,948,000  SINGRAULI R&M 1.0625% 4/1/2010 9/14/2010 167

8/3/2009 7,756,000  ANTA R&M 1.0625% 4/1/2010 9/14/2010 167

8/3/2009 960,000  TTPS R&M 1.0625% 4/1/2010 9/14/2010 167

KFW - D IX 1/27/2010 1,381,000  TANDA R&M 1.0625% 4/1/2010 9/14/2010 167

1/27/2010 561,000  SINGRAULI R&M 1.0625% 4/1/2010 9/14/2010 167

1/27/2010 5,500,000  ANTA R&M 1.0625% 4/1/2010 9/14/2010 167

1/27/2010 670,000  TTPS R&M 1.0625% 4/1/2010 9/14/2010 167

1/27/2010 88,000  FARAKKA R&M 1.0625% 4/1/2010 9/14/2010 167

1/27/2010 600,000  RIHAND R&M 1.0625% 4/1/2010 9/14/2010 167

1/27/2010 1,200,000  UNCHAHAR R&M 1.0625% 4/1/2010 9/14/2010 167

KFW - D IX 3/22/2010 5,226,500  TANDA R&M 1.0625% 4/1/2010 9/14/2010 167

3/22/2010 1,712,900  SINGRAULI R&M 1.0625% 4/1/2010 9/14/2010 167

3/22/2010 3,756,600  ANTA R&M 1.0625% 4/1/2010 9/14/2010 167

3/22/2010 1,888,500  TTPS R&M 1.0625% 4/1/2010 9/14/2010 167

3/22/2010 197,600  FARAKKA R&M 1.0625% 4/1/2010 9/14/2010 167

3/22/2010 1,163,900  RIHAND R&M 1.0625% 4/1/2010 9/14/2010 167

3/22/2010 900,300  UNCHAHAR R&M 1.0625% 4/1/2010 9/14/2010 167

3/22/2010 153,700  VINDHYACHAL R&M 1.0625% 4/1/2010 9/14/2010 167

100,000,000 TOTAL

Ist Interest Period

Page 88: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 88/99

INTERNATIONAL FINANCING ON POWER PROJECTS

88

ROI Outstanding DATE FROM DATE UPTO NO. OF DAYS ROI Outstanding DATE FROM DATE UPTONO. OF

DAYS

1.1250% 2,948,214  9/15/2010 3/14/2011 181 1.1250% 2,721,429  3/15/2011 3/31/2011 17

1.1250% 797,643  9/15/2010 3/14/2011 181 1.1250% 736,286  3/15/2011 3/31/2011 17

1.1250% 5,539,857  9/15/2010 3/14/2011 181 1.1250% 5,113,714  3/15/2011 3/31/2011 17

1.1250% 3,151,824  9/15/2010 3/14/2011 181 1.1250% 2,909,376  3/15/2011 3/31/2011 17

1.1250% 1,131,502  9/15/2010 3/14/2011 181 1.1250% 1,044,464  3/15/2011 3/31/2011 17

1.1250% 2,438,817  9/15/2010 3/14/2011 181 1.1250% 2,251,215  3/15/2011 3/31/2011 17

1.1250% 799,777  9/15/2010 3/14/2011 181 1.1250% 738,255  3/15/2011 3/31/2011 17

1.1250% 634,014  9/15/2010 3/14/2011 181 1.1250% 585,243  3/15/2011 3/31/2011 17

1.1250% 1,129,781  9/15/2010 3/14/2011 181 1.1250% 1,042,875  3/15/2011 3/31/2011 17

1.1250% 4,566,146  9/15/2010 3/14/2011 181 1.1250% 4,214,904  3/15/2011 3/31/2011 17

1.1250% 1,105,706  9/15/2010 3/14/2011 181 1.1250% 1,020,651  3/15/2011 3/31/2011 17

1.1250% 1,347,014  9/15/2010 3/14/2011 181 1.1250% 1,243,397  3/15/2011 3/31/2011 17

1.1250% 1,416,093  9/15/2010 3/14/2011 181 1.1250% 1,307,163  3/15/2011 3/31/2011 17

1.1250% 850,756  9/15/2010 3/14/2011 181 1.1250% 785,313  3/15/2011 3/31/2011 17

1.1250% 2,336,276  9/15/2010 3/14/2011 181 1.1250% 2,156,562  3/15/2011 3/31/2011 17

1.1250% 2,042,361  9/15/2010 3/14/2011 181 1.1250% 1,885,257  3/15/2011 3/31/2011 17

1.1250% 2,707,275  9/15/2010 3/14/2011 181 1.1250% 2,499,023  3/15/2011 3/31/2011 17

1.1250% 1,288,227  9/15/2010 3/14/2011 181 1.1250% 1,189,132  3/15/2011 3/31/2011 17

1.1250% 534,406  9/15/2010 3/14/2011 181 1.1250% 493,298  3/15/2011 3/31/2011 17

1.1250% 888,801  9/15/2010 3/14/2011 181 1.1250% 820,431  3/15/2011 3/31/2011 17

1.1250% 1,117,928  9/15/2010 3/14/2011 181 1.1250% 1,031,933  3/15/2011 3/31/2011 17

1.1250% 1,156,156  9/15/2010 3/14/2011 181 1.1250% 1,067,221  3/15/2011 3/31/2011 17

1.1250% 3,625,645  9/15/2010 3/14/2011 181 1.1250% 3,346,749  3/15/2011 3/31/2011 17

1.1250% 1,150,962  9/15/2010 3/14/2011 181 1.1250% 1,062,426  3/15/2011 3/31/2011 17

1.1250% 2,066,321  9/15/2010 3/14/2011 181 1.1250% 1,907,373  3/15/2011 3/31/2011 17

1.1250% 85,533  9/15/2010 3/14/2011 181 1.1250% 78,953  3/15/2011 3/31/2011 17

1.1250% 252,114  9/15/2010 3/14/2011 181 1.1250% 232,720  3/15/2011 3/31/2011 17

1.1250% 630,742  9/15/2010 3/14/2011 181 1.1250% 582,224  3/15/2011 3/31/2011 17

1.1250% 292,131  9/15/2010 3/14/2011 181 1.1250% 269,660  3/15/2011 3/31/2011 17

1.1250% 253,695  9/15/2010 3/14/2011 181 1.1250% 234,180  3/15/2011 3/31/2011 17

1.1250% 3,232,357  9/15/2010 3/14/2011 181 1.1250% 2,983,714  3/15/2011 3/31/2011 17

1.1250% 991,714  9/15/2010 3/14/2011 181 1.1250% 915,429  3/15/2011 3/31/2011 17

1.1250% 490,286  9/15/2010 3/14/2011 181 1.1250% 452,571  3/15/2011 3/31/2011 17

1.1250% 957,357  9/15/2010 3/14/2011 181 1.1250% 883,714  3/15/2011 3/31/2011 17

1.1250% 1,061,357  9/15/2010 3/14/2011 181 1.1250% 979,714  3/15/2011 3/31/2011 17

1.1250% 2,384,571  9/15/2010 3/14/2011 181 1.1250% 2,201,143  3/15/2011 3/31/2011 17

1.1250% 168,071  9/15/2010 3/14/2011 181 1.1250% 155,143  3/15/2011 3/31/2011 17

1.1250% 1,240,571  9/15/2010 3/14/2011 181 1.1250% 1,145,143  3/15/2011 3/31/2011 17

1.1250% 2,737,429  9/15/2010 3/14/2011 181 1.1250% 2,526,857  3/15/2011 3/31/2011 17

1.1250% 7,202,000  9/15/2010 3/14/2011 181 1.1250% 6,648,000  3/15/2011 3/31/2011 17

1.1250% 891,429  9/15/2010 3/14/2011 181 1.1250% 822,857  3/15/2011 3/31/2011 17

1.1250% 1,282,357  9/15/2010 3/14/2011 181 1.1250% 1,183,714  3/15/2011 3/31/2011 17

1.1250% 520,929  9/15/2010 3/14/2011 181 1.1250% 480,857  3/15/2011 3/31/2011 17

1.1250% 5,107,143  9/15/2010 3/14/2011 181 1.1250% 4,714,286  3/15/2011 3/31/2011 17

1.1250% 622,143  9/15/2010 3/14/2011 181 1.1250% 574,286  3/15/2011 3/31/2011 17

1.1250% 81,714  9/15/2010 3/14/2011 181 1.1250% 75,429  3/15/2011 3/31/2011 17

1.1250% 557,143  9/15/2010 3/14/2011 181 1.1250% 514,286  3/15/2011 3/31/2011 17

1.1250% 1,114,286  9/15/2010 3/14/2011 181 1.1250% 1,028,571  3/15/2011 3/31/2011 17

1.1250% 4,853,179  9/15/2010 3/14/2011 181 1.1250% 4,479,857  3/15/2011 3/31/2011 17

1.1250% 1,590,550  9/15/2010 3/14/2011 181 1.1250% 1,468,200  3/15/2011 3/31/2011 17

1.1250% 3,488,271  9/15/2010 3/14/2011 181 1.1250% 3,219,943  3/15/2011 3/31/2011 17

1.1250% 1,753,607  9/15/2010 3/14/2011 181 1.1250% 1,618,714  3/15/2011 3/31/2011 17

1.1250% 183,486  9/15/2010 3/14/2011 181 1.1250% 169,371  3/15/2011 3/31/2011 17

1.1250% 1,080,764  9/15/2010 3/14/2011 181 1.1250% 997,629  3/15/2011 3/31/2011 17

1.1250% 835,993  9/15/2010 3/14/2011 181 1.1250% 771,686  3/15/2011 3/31/2011 17

1.1250% 142,726  9/15/2010 3/14/2011 181 1.1250% 131,759  3/15/2011 3/31/2011 17

92,857,150 85,714,300 

IInd Interest Period IIIrd Interest Period

Page 89: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 89/99

INTERNATIONAL FINANCING ON POWER PROJECTS

89

Table16.4: Guarantee fee payable on IBRD for the period 01/04/2011 to 04/07/2011

Table16.5: Guarantee fee of World Bank allocated on different projects

Page 90: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 90/99

INTERNATIONAL FINANCING ON POWER PROJECTS

90

Table16.6: Foreign Exchange Rate Variation (FERV) of KFW Bank on different projects

Page 91: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 91/99

INTERNATIONAL FINANCING ON POWER PROJECTS

91

Table16.7: Interest allocation of KFW Bank on different projects

Page 92: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 92/99

INTERNATIONAL FINANCING ON POWER PROJECTS

92

Page 93: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 93/99

INTERNATIONAL FINANCING ON POWER PROJECTS

93

Page 94: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 94/99

INTERNATIONAL FINANCING ON POWER PROJECTS

94

Page 95: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 95/99

INTERNATIONAL FINANCING ON POWER PROJECTS

95

Table16.8: Differential Interest of all banks

Page 96: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 96/99

INTERNATIONAL FINANCING ON POWER PROJECTS

96

Page 97: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 97/99

INTERNATIONAL FINANCING ON POWER PROJECTS

97

17. CONCLUSION

International financing takes place on the basis of competitive bidding process.

NTPC sets a competitive bidding panel. In this panel all the multinational development banks

comes to the panel set.

NTPC sends request for proposal (RFP) or request for qualification (RFQ) letter to all banks of 

that panel set.

The banks read that RFP/RFQ letter then they come to the panel set for competitive bidding.

RFP/RFQ letter include all the terms and condition for investment.

Each multinational development bank has different code for bidding, different loan code, and

different account code.

At last who has lowest bid price wins the bidding process for investment. After the end of 

bidding process, NTPC directly consults to that bank (winner) for investment.

NTPC checks its own balance sheet to know which subsidiary requires financing.

The loan amount which is in foreign currency is converted in local currency (INR) by Indian

commercial banks (State Bank of India, State Bank of Hyderabad etc.).

Selection of Indian commercial banks on the basis of competitive bidding process.

18. RECOMMENDATION & SUGGESTION

The Employee turnover is quite high. Many productive man hours are wasted in order to get the

new employee get accustomed to the working environment of the organization. The company

can look at the root cause of this issue and try to reduce their employee turnover. No doubt that

retaining the talent is not an easy task for the public sector companies but a little appreciation

and remuneration can really boost the morale of the employees.

Page 98: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 98/99

INTERNATIONAL FINANCING ON POWER PROJECTS

98

19. BIBILIOGRAPHY

(1) www.ntpc.co.in 

(2) Fore closing of coal & international finance-www.iea.com

(3) Position paper- power

(4) Financial management-I M PANDEY

(5) Financial management-M Y KHAN

(6) International financial management-V SHARAN

(7)World Bank lending instruments

(8) General Conditions Applicable to the African Development Bank Loan Agreements and

Guarantee Agreements

(9) CPA REVIEWS NOTES- INTERNATIONAL FINANCE

(10) Indian power sector news July 2011

(11) ECB GUIDELINES-RBI

(12) Financing Private Infrastructure: Lessons from India- Montek S. Ahluwalia

(13) www.cercind.gov.in 

(14) www.cea.nic.in 

(15) www.iea.org 

(16)www.powermin.nic.in 

(17)www.crisil.com 

(18)www.moneycontrol.com 

Page 99: Final Report Submit 4 Mdu & Clg

8/4/2019 Final Report Submit 4 Mdu & Clg

http://slidepdf.com/reader/full/final-report-submit-4-mdu-clg 99/99

INTERNATIONAL FINANCING ON POWER PROJECTS