I. INTRODUCTION 1.1 General Water is an inexhaustible commodity. As population and its economic activities go on increasing so is the demand for water. To ensure a reliable water supply at the time of needs, the proper and judicious use and management of water resources is required. Hydropower generation and agriculture is major user of water resources in this world .Hydropower plants, by their nature, require low operating cost and at the same time provide great flexibility (especially reservoir based hydropower) in the use relative to other sources of energy identified so far. Benefits of water resources depends upon mainly on the three factors such as the physical dimension of the system, the scale of development and the operating policies adopted for the system. Hydrological, geo-topographical factors have great influence on the physical dimension of a reservoir. But with the advent of simulation techniques, not only optimal design is achieved but also adverse effects are minimized and maximum benefits are accrued. 1.2 Problem Identification Development of a country can be gauged by the amount of energy it consumes. Energy is very important medium for the overall development of a nation .Hydropower is one of the 1
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
I. INTRODUCTION
1.1 General
Water is an inexhaustible commodity. As population and its economic activities go on
increasing so is the demand for water. To ensure a reliable water supply at the time of
needs, the proper and judicious use and management of water resources is required.
Hydropower generation and agriculture is major user of water resources in this
world .Hydropower plants, by their nature, require low operating cost and at the same
time provide great flexibility (especially reservoir based hydropower) in the use relative
to other sources of energy identified so far.
Benefits of water resources depends upon mainly on the three factors such as the physical
dimension of the system, the scale of development and the operating policies adopted for
the system.
Hydrological, geo-topographical factors have great influence on the physical dimension
of a reservoir. But with the advent of simulation techniques, not only optimal design is
achieved but also adverse effects are minimized and maximum benefits are accrued.
1.2 Problem Identification
Development of a country can be gauged by the amount of energy it consumes. Energy is
very important medium for the overall development of a nation .Hydropower is one of the
main sources of energy in Nepal. It accounts for nearly 90% of installed capacity and
95% of total generation of energy. Except for the firewood and Hydropower, Nepal has to
import all other types of energy paying scarce hard currencies while being extremely rich
in water resources. So, the proper utilization of its water resources is required for the
development.
In spite of potential resources of hydropower, Nepal has faced power crisis for several years
because most of the hydropower projects are based on the river run-off schemes except
Kulekhani-I (60 MW). To meet the power crises, storage scheme will be quite essential for the
country.
The predominant nature of hydroelectric source particularly, run of river type supply in
Integrated Power System(INPS) has exhibited that seasonal deficits of hydro energy is
bound to occur frequently along with seasonal surpluses. This has been the situation of
1
INPS even after the commissioning of Projects like Khimti, Mid Maryshandi
The estimated hydropower potential of Nepal is 83, 000 MW of which 114 projects
having 45,610 MW have been identified economically feasible However, to date, Nepal
has developed less than 1 percent of its vast hydropower potential. The total installed
capacity is about 680MW, of which 635 MW (93%) is generated by hydropower in the
integrated system. Peaking capacity as well as energy output of the power system drops in
the dry season of December to May due to the shortage of available runoff.
The peak power and energy demand is growing by about 11% annually, creating the
electricity shortage in Nepal. Demand has been exceeding supply every year. To meet the
significant difference between demand and supply, NEA had increased power cuts in the
country up to 18 hours a day in January 2009. Greater challenges of the NEA are bridging
the gap between supply and demand of electricity.
All the existing and future (scheduled to be commissioned by next five years)
hydropower plants are run-of-river types except Kulekhani power plant, Proposed Upper
Seti Hydropower Project and some of them are with daily regulating capacity. Therefore,
load shedding hours in the dry season depends on the availability of water in the
Kulekhani reservoir.
Figure 1.1: Contribution of energy in Nepal
1.3 Need of research
Due to limited power supply, optimum operation of water resources is
unavoidable. Latest estimates show, the demand for power in Nepal will be 1500 MW in
2015. Supply of this demand is only possible if more storage type hydropower projects are
constructed. [NEA, 2001]
2
Therefore, it is required that most of research be undertaken toward saving, storage,
management and water demand of water resources in this country. Ingredients include
analyzing various parameters such as population, economy, water use efficiency and etc.
[Siminovic, S.P, 2002].
Upper Seti Hydroelectric project with installed capacity of 127 MW has storage capacity of
374 million cubic meters [NEA, 2001]. In this study, simulation model was used for
system evaluation. Simulation model is a best way of using physical rules and a series
of operational rules try to simulate genuine phenomena and approach and accurate
scheme to predict the behavior of the system under a specific policy [Yeh W.W-G, 1985].
Input data of simulation model could be classified in three parts: fixed data, design data
and time series data. Fixed data are properties of system such as physical and economic
properties and relationship between them. Design data, in fact, are decision variables
which are determined in modeling process are reservoir capacity and plant generating
power capacity. Inflow to system is in the form of artificial data or time series data.
Simulation models can present efficiency and system performance in different
combination of reservoir, plant powers, reservoir storage, output etc. and in this
manner, they have good flexibility.
In the present study HEC-ResSim simulation model was used to evaluate performance of
Upper Seti storage dam operation and ability of the model to simulate of reservoir system
was studied.
1.4 Objectives of study:
The objective of reservoir simulation is to compute the plant capacity and the
corresponding maximum plant discharge, the reservoir drawdown pattern, the dry season
and the wet season energy and the total annual energy. The available inflow and the
reservoir live storage have to be fully utilized. The output data obtained from the
simulation are to evaluate the energy generations for two scenarios.
In view of the above factors the major objectives of the present study are as follows:
To compute plant capacity and the maximum plant discharge
To compute the dry and wet season energy
To compute the total energy generation
3
To develop a guide curve for computing the reservoir drawdown pattern
and operation of reservoir.
To compare the results obtained from HEC-Res Sim with the results obtained from
other models.
1.5 Scope of study:
This study is mainly focused on the development of reservoir operation model for
USHEP using HEC Res Sim. The study covers the following scope of works.
Literature reviews on Hydropower reservoir and its various aspects.
Review on present energy scenario of Nepal.
Study and collection of all relevant hydrological and topographical data of the
Upper Seti Basin.
Literature review on sediment studies on Upper Seti Basin.
Literature review on history of reservoir simulation.
Literature review on the operation of reservoir in Nepal and aborad.
Literature review on the operation of reservoir using HEC Res Sim models.
Recommend the model to be used for other reservoir operation under various
conditions.
1.6 Limitations:
Following limitations are set for the study:
Due to time and study limitations, sediment analysis for the reservoir has not been
performed.
Due to unavailability of required data seepage loss and hydraulic loss has been
neglected.
Input data used are collected from past study reports of NEA and JICA so that
comparisons of output could be effective and reliable.
If sediment analysis, seepage data and hydraulic loss data are used, the accuracy and
reliability of the results obtained would be increased.
4
1.7 Organization of the Study
This thesis consists of seven chapters. Chapter 1 includes the introduction to the topic
with the need, objective, scope and limitations of the study. Chapter 2 reviews current
power production scenarios. Chapter 3 contains literature reviews .Chapter 4 contains
description of the site area and project. Chapter 5 contains the detailed model description,
research methodology and processes adopted to achieve the objective of the study.
Chapter 6 presents the results, its discussions and validation with tables and figures.
Finally, Chapter 7 presents the final conclusion of this study and recommendations for
further study.
The references and Annexes are incorporated at the end of this thesis while the
acknowledgements and abstract are given in the preface portion.
5
II. HYDROPOWER AND ENERGY SITUATION IN NEPAL
2.1 Hydropower Potential
Nepal's water resource is considered to be abundant. The average annual precipitation is
about 1700mm (80% of which occurs during monsoon season from June to September).
The total annual average run-off from Nepal's 6000 rivers is over 200 billion m 3. [NEA,
2001]
Surface resources are distributed in the river system consisting of four major rivers (viz.
the Mahakali, the Karnali, the Gandaki and the Koshi), seven medium rivers and a large
number of small rivers.
Harnessing the water flowing from the Himalayas is Nepal’s development agenda for
increasing its national wealth. Water storage potential in Nepal is 88 billion m3. Nepal’s
theoretical hydropower potential is estimated at 83, 000 MW. At present altogether 114
projects having 45,610 MW capacity have been identified economically feasible The
country hopes to bring about development through three strategic consideration which
include building large-scale storage projects envisaged primarily for exporting energy,
medium scale projects for meeting national needs and small scale projects for serving
local communities. As such, four major storage projects are proposed as Indo-Nepal co-
operative initiatives. These are the Chisapani Karnali (10,800 MW), the Pancheswor
(7,200 MW), Budhi Gandaki (600 MW) and the Sapta Koshi high dam (3,600 MW)
which in total, would provide 22,200 MW installed capacity. Recent policy promotes
external and domestic private sector initiatives for hydropower development. Some of the
large projects with feasibility study completed are presented in table 2.1.
Table 2.1: Large Hydropower Projects with Feasibility Study
Project Name Capacity (MW)
Cost million USD
Year of Study Type
Karnali (Chisapani)
10,800 7 666 Updated in 2001
Storage
Pancheswor 6,480 2 980 1995 Storage
West Seti 750 1 098 1997 Storage
Arun-III 402 859 1991 Storage
Upper Tamakoshi 309 464 May 2005 PROR
Dudhkoshi 300 690 1998 Storage
6
2.2 Energy Situation
Figure 2.1 shows the location map of power generation and transmission facilities in
Nepal. The power generating facilities in Nepal consists of hydro, diesel and solar power
plants but it is basically a hydropower-oriented system. The total installed capacity is
about 680 MW, which with 635 MW (93%) is generated by hydropower in the integrated
system.
Figure 2.1: Existing Power Stations and Distribution System
2.2.2 Available Energy and Peak Load Demand
NEA published total energy available and peak load demand in NEA annual report
2007/08 from 1999 to 2008. Figure 2.2 and Table 2.4 shows that the peak load demand
before 2001 was only 391 MW which is less than the total capacity of 398 MW including
IPP. Kaligandaki A Power plant was commissioned in 2001 and total capacity after it was
541 MW after the Kaligandaki A there was not any major power plant implemented in
7
Nepal except small power plants developed by IPPs. Significant load shedding started
from year 2005 but energy have always been spilled during wet season
Figure 2.2: Available energy and total peak load demand
Table 2.2:Available energy and total peak load demand
Figure2.3:Monthly energy generation from Kulekhani I
8
Figure2.4:Monthly energy generation from Marsyangdi
Figures 2.3 to 2.5 (Kulekhani I, Marsyangdi and Kaligandaki A) present the energy
generation from major power plants of Nepal. These figures show that Run of river plants
(Marsyangdi and Kaligandaki A) generated with lower capacity (up to 50% of the total
capacity) during the wet season but at the same time reservoir power plants (Kulekhani
A) also generated up to 50% of its total capacity.( Shrestha, 2007)
Figure 2.5: Monthly energy generation from Kaligandaki A
Figure 2.6 shows the system load curve of the peak load demand of the year in 2007
(December 31, 2007) and Figure 2.7 shows a typical system load curve in wet days. Both
figures show that the peak load demand is from 6 PM to 9 PM. Load demand at day time
is only about 60% of the peak demand.
9
Figure 2.6:System load curve on 31 December 2007
Figure 2. 7:Typical system load curve in wet season.
Nepalese are already facing acute shortage of electricity whole year, if proper initiative is
not taken to develop more hydropower projects, it seems that the situation will be more
severe and power cut-off will be increased for more hours per week during dry period as
well as in wet season. Power and energy demand grew by 11.31% and 10.76%
respectively in the year 2008. The system demand of 721.73 MW recorded on December
31 2007 happened to the peak power demand observed in FY 2007/08. Likewise energy
demand over the year 2008 totalled 3490.12 GWh. As this amount of energy was not
available with the system the deficit amounting to 309.46 GWh had to be shedded to keep
the electricity service running. (Shrestha, 2007)
10
Figure 2.8:Energy and peak load demand forecast charts (NEA, 2000)
NEA made the power demand forecast for the further 18 years from 2009 to 2025 as
shown in figure 2.2 and Table 2.4. According to the forecast, the peak load is estimated to
be 1271.7 MW in 2013/14. The average annual growth rate for peak demand is estimated
to be about 10% for next 5 years. The further energy demand is also forecasted to be
5859.9 GWH in 2013.
Table 2.3: Energy and peak load demand forecast.
Source: NEA annual report, 2007/8
11
Electricity generation should be increased by more than 10% per year to meet demand,
which is far high additional demand compare to additional generation rate at present.
[NEA,2001]
In February 2008 Government of Nepal formed a Committee for Solving the Load
Shedding Problem. The committee had prepared a report and recommended 25 points for
solving the load shedding problem. Some of them are development of Storage power
project like Upper Seti, speed up the construction of Upper Tama Koshi, Upper Trishuli
A, Upper Trishuli B, Kulekhani III and encourage IPPs for hydropower development.
They have also studied the energy production from existing and forthcoming hydropower
projects up to 2013/14. They have also developed energy and capacity balance per day of
the month from 2009/10 to 2013/14. Figure 2.9 and Table 2.6 presents the energy and
capacity balance per day of the month for year 2013/14. The figures show that capacity
will be surplused in wet season and deficit during the dry season. But the energy surplus
will be in every month.
Figure 2.9:Estimated Capacity and Energy balance in 2013/14
12
Table 2.4:Estimated Capacity and Energy balance in 2013/14
The annual maximum air temperature occurs generally I month of May and ranges from
36 degree Celsius to 41 degree Celsius and slightly decrease in June. The Minimum
temperature occurs in December and January ranging from 1.5 degree Celsius to 7 degree
Celsius.
4.12 Humidity
The maximum and minimum monthly humidity are 100 % and 40%respectively.The
atmosphere is humid with average monthly relative humidity ranging from 77% to 100 %
in Janaury.April is the driest month with relative humidity at 40 %.
4.13 Wind Speed
The average monthly maximum wind speed at the dam site is 3.8 km/hr.
34
V. RESEARCH METHODOLOGY
5.1 Application of the model
HEC-ResSim uses an original rule-based approach to mimic the actual decision-making
process that reservoir operators must use to meet operating requirements for flood
control, power generation, water supply, and environmental quality. Parameters that may
influence flow requirements at a reservoir include time of year, hydrologic conditions,
water temperature, and simultaneous operations by other reservoirs in a system. The
reservoirs designated to meet the flow requirements may have multiple and/or conflicted
constraints on their operation. ResSim describes these flow requirements and constraints
for the operating zones of a reservoir using a separate set of prioritized rules for each
zone. Basic reservoir operating goals are defined by flexible at-site and downstream
control functions. As HEC-ResSim has evolved, advanced features such as multi-
reservoir system constraints, outlet prioritization, scripted state variables, and conditional
rule logic have made it possible to model more complex systems and operational
requirements. The graphical user interface makes HEC-ResSim easy to use and the
customizable plotting and reporting tools facilitate output analysis. [Charalampos
Shaulikaris, 2008]
HEC Res Sim model was used in reservoir simulation for water release for power
production and flood control with different operation policy. This model has three
main modules: Watershed Setup, Reservoir Network and Simulation. In this model we
can make different management in reservoir system by defining scenarios in a time
series data. Model input data are: reservoir properties (Volume-Area and Elevation
Curve, Operation levels, Operation rules and etc) control and operation points and time
series input file. The highest capability of this model was
defining of different operation rules in power plant generation flood control
conditions, creating scenarios for conditional operation, downstream control point,
reservoir system balance to imitate the hydrological condition and
installing of different structures in dam body, comparison of output with observed
data, defining of different operational level, different computational steps (15 min to a
day) and adjustment of output results . [Charalampos Shaulikaris, 2008]
5.2 ResSim Modules
ResSim offers three separate sets of functions called Modules that provide access to specific
35
types of data within a watershed. These modules are Watershed Setup, Reservoir Network,
and Simulation. Each module has a unique purpose and an associated set of functions
accessible through menus, toolbars, and schematic elements.
5.2.1. Watershed Setup Module
The purpose of the Watershed Setup module is to provide a common framework for
watershed creation and definition among different modeling applications. This module is
currently common to HECResSim, HEC-FIA, and the CWMS CAVI.
A watershed is associated with a geographic region for which multiple models and area
coverages can be configured. A watershed may include all of the streams, projects (e.g.,
reservoirs, levees), gauge locations, impact areas, time-series locations, and hydrologic and
hydraulic data for a specific area. All of these details together, once configured, form a
watershed framework.
When a new watershed is created, Res Sim generates a directory structure for all files
associated with the watershed.
In the Watershed Setup module, items are assembled, that describe a watershed’s physical
arrangement. Once a new watershed is created, it is possible to import maps from external
sources, specify the units of measure for viewing the watershed, add layers containing
additional information about the watershed, create a common stream alignment, and configure
elements. Projects can be added and time-series icons can be created within the Watershed
Setup module.
5.2.2. Reservoir Network Module
The purpose of the Reservoir Network module is to isolate the development of the reservoir
model from the output analysis. In the Reservoir Network module, river schematic is built,
physical and operational elements of reservoir model are described, and alternatives are
developed for analyzing. Using configurations that are created in the watershed Setup module
as a template, basis of a reservoir network is created. Routing reaches are and possibly other
network elements to complete the connectivity of your network schematic. Once the schematic
is complete, physical and operational data for each network element are defined. Also,
alternatives are created that specify the reservoir network, operation set(s), initial conditions,
and assignment of DSS pathnames (time-series mapping).
36
5.2.3. Simulation Module
The purpose of the Simulation module is to isolate output analysis from the model
development process. Once the reservoir model is complete and the alternatives have been
defined, the Simulation module is used to configure the simulation. The computations are
performed and results are viewed within the Simulation module. When you create a
simulation you must specify a simulation time window, a computation interval, and the
alternatives to be analyzed. Then, ResSim creates a directory structure within the rss folder of
the watershed that represents the “simulation”. Within this “simulation” tree will be a copy of
the watershed, including only those files needed by the selected alternatives. Also created in
the simulation is a DSS file called simulation. dss, which will ultimately contain all the DSS
records that represent the input and output for the selected alternatives. Additionally, elements
can be edited and saved for subsequent simulations.
Figure: 5.1: Procedural Flow Chart
37
5.3 Model development
The centerline (stream alignment) of the watershed model includes the river
system and the reservoir created by the construction of 140 m high concrete dam.
The current study is performed considering the one and only priority of the
project is the power production and no obligation for downstream release.
However, 10% of stream flow has been targeted as minimum downstream
release. Future development of the model can feature one or more reservoirs and
other water management issues.
5.3.1. Input Data for HEC Res Sim
The reservoir is the key component in the most hydropower projects. It is the reservoir
that makes it possible to store water in periods with a large inflow and less demand, and
release it in periods with less inflow and larger demand. In other words, the reservoir
works as a "buffer" to reduce the problems that show up when inflow and demand do not
occur at the same time.
Following data is provided for each reservoir module to run HEC Resevoir Simulation:
1. Topographic map of the study area.
An AUTOCAD drawing containing physical features of the study area such as stream
alignments, location of reservoir, area of the reservoir, contour, impact area etc was
imported as background map. Then required model was drawn on the basis of the
background map. River alignment, reservoir area, impact area, river junctions,
computational points are the required physical data.
2. Hydrological Data.
Major computational points are included as the inlet and outlet of the reservoir. The
input for the inlet is the average daily stream flow calculated from the data recorded from
1964 to 1999. Mean monthly flow at the dam site is shown in Table 12 at Annex -
III .Similarly Input of Daily Stream Flow is shown in Table 4.4.
The area volume curve of the reservoir has been adopted from the study
conducted by JICA in 2007.Other required data as evaporation data, climate
data have been extracted from the feasibility study report by NEA in 2001.
38
Table 5.1: Monthly Average Flow (MAF) -Evaporation Rate (ER)
Source: NEA, 2001
Table 5.2: Reservoir Volume and Elevation
S.N Month MAF(m3/s)ER (mm/month)
1 Jan 27.03 69.09
2 Feb 23.72 91.97
3 Mar 24.01 152
4 April 27.43 176
5 May 41.07 184.5
6 June 113.84 200.7
7 July 287.22 191
8 August 322.61 189.4
9 Sept 225.77 166
10 Oct 112.43 129.4
11 Nov 52.01 80.3
12 Dec 34.36 64.76
39
S.NHeight
(m) Area(km^2) Volume(MCM)
1 310 0.02 0
2 315 0.15 0.42
3 320 0.32 1.59
4 325 0.46 3.54
5 330 0.56 6.1
6 335 0.71 9.29
7 340 1.10 13.82
8 345 1.29 19.81
9 350 1.48 26.74
10 355 1.73 34.77
11 360 2.11 44.38
12 365 2.38 55.6
13 370 2.88 68.74
14 375 3.37 84.35
15 380 3.85 102.4
16 385 4.36 122.93
17 390 4.79 145.78
18 395 5.20 170.74
19 400 5.73 198.06
20 405 6.23 227.95
21 410 6.70 260.25
22 415 7.26 295.14
23 420 7.92 333.08
24 425 8.67 374.57
25 430 9.82 420.79
26 435 11.24 473.45
Source: NEA, 2001
3. Time-Step
40
A daily time-step HEC-ResSim model was developed for the study to simulate the
1964-1999 period-of-records. The monthly average generated daily records have
been taken .This average stream flow data accounts for nearly 45 % probability
of exceedence. (Annex-III, Table 11)
4. Guide curve
A guide curve suggests the level of water at the reservoir at any time of the year.
Rule curves are simply elevations at each reservoir that help guide the operation (i.e.
drafting or filling)
Rule curves specify the highest and the lowest elevation that a reservoir should be
operated to in order to stay within the planning objective.
Intermediate rule curves help determine which projects release water first when
energy is needed.
Flood Control
– defines the drawdown required to assure adequate space to store the
anticipated runoff without causing downstream flooding (Maximum Elevation).
Critical Rule Curve
– defines how deep a reservoir can be drafted in order to meet the firm energy requirements during the poorest water conditions on record (Minimum Elevation).
5.4 Modeling the dams complex
The modeling of the Upper Seti Hydro Electric Project dam using HEC-ResSim is carried
out in a three phase process: the Watershed network setup, the parameterization of the dam's
components and the simulation of the different operational scenarios.
5.4.1 The watershed network setup
The initial phase of the modeling concerns the tracing of the connected flow elements
of the river watercourse between Dhulegauda and the dam site. Apart from the main
course, the modeling includes the placement of stream junctions at the
segments gathering the water drained from the various watersheds nourishing the Seti
River. An inlet computational point (CP3) has been artificially placed at the upstream end of
41
the reservoir in order to simulate the total inflow to the reservoir. Similarly an outlet
computational point (CP4) is placed at the dam outlet to simulate the release. The stream
junction points of the watershed are as follows:
Jyagdi Khola junction
Pirun Khola junction
Wantan Khola junction
Bange Khola junction
Kumle Khola junction
Guhe(Kumle Khola tributary) junction
Kyangdi Khola junction
Figure 5.2: Representation of the watershed in HEC-ResSim
5.4.2. The parameterization of the study dam
42
Following the geographic placement of the HEC-ResSim elements including main stream
segments, inflow point, dams with their connections to the main river stream as well as
outflow point , the next step of the HEC-ResSim set-up is the definition of the technical
parameters defining for dam: the geometric properties of the pool, the capability of the
hydropower plant and the definition of the various management constraints regarding
the electric power production, the regime of released flow and the operation in
conditions of flooding.
5.4.3. Operational Parameters
River flow catchment (Km2) 1502
Maximum discharge (m3/sec) 127
Full Supply level (F.S.L) (m) 425
Minimum operation level (M.O.L) (m) 370
Volume in (F.S.L) 106 m^3 374.57
Volume in (M.O.L) 106 m^3 68.74
Reservoir surface in F.S.L (Km2) 8.67
Tailrace water level (m) 289
Upper spillway level 385.82
Elevation of crest dam (m) 430
Height of dam (m) 140
Number of Turbine units 2
Total installed power (MW) 127
As an illustration of how HEC-ResSim dam parameters have been set, the detailed
process followed for the Upper Seti Dam is presented as follows:
5.4.4 Definition of the pool parameters
For the reservoir characteristics, the minimum operating level is 370 m and upper crest
of the gate is maintained at 320 m. This defines the lowest elevation from which it is
possible to release water. Below this level the storage capacity of the reservoir is considered
to be equal to zero since the stored water cannot be used. When the upper operation level is
reached at 425 m the volume of the stored water is 374.57 million m3 and the area
covered with water is 8.67 km2. HEC-ResSim provides various models of relation