Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building
29

Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

Mar 29, 2015

Download

Documents

Aileen Dowdell
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

Final Project 7th semesterMaria Amparo Prieto

Project: Svanekøkkenet ÅrhusOffice Building

Page 2: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

Overview

0 Project1 The construction company2 Tendering3 The contract4 Start-up/mobilization5 Construction6 Handing over

Page 3: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

Construction of an office building with 2 storeys and establishment of roads, paths and parking areas.

0. Project

Basement plan

G.F plan

1rst floor plan

Facades

Cross sections

Situation plan

Page 4: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

1. Establishing a company

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1 Organizational chart

Company budget

Employment contract

Company handbook

Quality handbook

Employment dismissal

Application for building permit

Page 5: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

2. Giving a bid

Invitation to tender

Soil works

Sewer works

Concrete works

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Main contract

Elements works

Invitation Main Contractor

Invitation subcontractor

Tender bid

Page 6: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

2. Giving a bid

Invitation to tender

Soil works

Sewer works

Concrete works

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Elements works

Quantities

Machine hours

Calculation

Main contract

Tender bid

Page 7: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

2. Giving a bid

Invitation to tender

Soil works

Sewer works

Concrete works

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Elements works

Quantities

Machine hours

Calculation

Manhours

Main contract

Tender bid

Page 8: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

2. Giving a bid

Invitation to tender

Soil works

Sewer works

Concrete works

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Elements works

Quantities

Calculation

Manhours

Main contract

Tender bid

Page 9: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

2. Giving a bid

Invitation to tender

Soil works

Sewer works

Concrete works

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Elements works

Quantities

Calculation

Manhours

Main contract

Tender bid

Page 10: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

2. Giving a bid

Invitation to tender

Soil works

Sewer works

Concrete works

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Elements works

Main contract

Tender bid

Page 11: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

2. Giving a bid

Invitation to tender

Soil works

Sewer works

Concrete works

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Elements works

Main contract

Tender bid

Page 12: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

3. Making agreements

Subcontractor’s contract

Client’s contract

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Legal timeline

Supplier’s contract

Page 13: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

4. Mobilization

Process control

Production card

Plan health and safety(PSH Schedules)

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Receiving control

Building site plan

Page 14: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

4. Mobilization

Process control

Production card

Plan health and safety(PSH Schedules)

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Receiving control

Building site plan

Receiving control plan

Journal concrete

Journal formworks

Journal Steel

Page 15: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

4. Mobilization

Process control

Production card

Plan health and safety(PSH Schedules)

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Receiving control

Building site plan

Process control plan

Journal concrete

Journal formworks

Journal Steel

Page 16: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

4. Mobilization

Process control

Production card

Plan health and safety(PSH Schedules)

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Receiving control

Building site plan

Page 17: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

4. Mobilization

Process control

Production card

Plan health and safety(PSH Schedules)

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Receiving control

Building site plan

Page 18: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

4. Mobilization

Process control

Production card

Plan health and safety(PSH Schedules)

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Receiving control

Building site plan

Page 19: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

5. Execution

Delivery plan

3 weeks plan

Liquidity budget

Interim certificates

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Work place assessment

Manning and machinery

Formworks

Cut and bending

Page 20: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

5. Execution

Delivery plan

3 weeks plan

Liquidity budget

Interim certificates

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Work place assessment

Manning and machinery

Formworks

Cut and bending

Page 21: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

5. Execution

Delivery plan

3 weeks plan

Liquidity budget

Interim certificates

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Work place assessment

Manning and machinery

Formworks

Cut and bending

Page 22: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

5. Execution

Delivery plan

3 weeks plan

Liquidity budget

Interim certificates

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Work place assessment

Manning and machinery

Formworks

Cut and bending

Page 23: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

5. Execution

Delivery plan

3 weeks plan

Liquidity budget

Interim certificates

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Work place assessment

Manning and machinery

Formworks

Cut and bending

Page 24: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

5. Execution

Delivery plan

3 weeks plan

Liquidity budget

Interim certificates

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Work place assessment

Manning and machinery

Soil and sewer

Concrete

Formworks

Cut and bending

Page 25: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

5. Execution

Delivery plan

3 weeks plan

Liquidity budget

Interim certificates

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Work place assessment

Manning and machinery

Formworks

Cut and bending

Page 26: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

5. Execution

Delivery plan

3 weeks plan

Liquidity budget

Interim certificates

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Work place assessment

Manning and machinery

Formworks

Cut and bending

Page 27: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

5. Execution

Delivery plan

3 weeks plan

Liquidity budget

Interim certificates

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Work place assessment

Manning and machinery

Formworks

Cut and bending

Page 28: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.

6. Handing over

Notification of completion

Guarantee

Handing over protocol

Company

Tendering

Contract

Starting up

Construction

Handover

Group 1

Page 29: Final Project 7th semester Maria Amparo Prieto Project: Svanekøkkenet Århus Office Building.