Copper Brass Plant
Copper Brass Plant
1.1Introduction
The plant is the oldest establishment of the company,
responsible for the production copper brass products.
The product range is extensive, having a large number of OE and
Northern products.
The plant follows a batch type manufacturing system.
Most of the components used in the manufacturing process are
produced within the plant.
The work force consists of both permanent and contractual
workers.
1.2Zones of the Shop Floor
Press Shop: The press shop produces tanks, header plates for
copper brass products & header plates for aluminium products.
All operations required for producing these components are carried
out here, which are blank cutting, drawing, trimming &
punching. The press shop has seven press machines, having a
capacity range of 10 to 100 tons. The press shop employs 14-17
workers, depending on the demand. All the dies are labeled, colour
coded & placed on racks. All the components produced here are
heat treated in the stress relieving oven. Inventory is maintained
for production period of about five days.
Side frame & Cowl Storage: The side frame and the cowl are
outsourced. The numbers of items stored are for a production period
of two days. The side frames are stored on racks and the cowls are
stored in stacks. The side frame is welded to the main
assembly.
Painting and Packing: The painting machine is a dominant feature
on the shop floor; it performs drying & painting operations. It
has two painting booths and two drying zones. The radiators are
attached to a slow moving overhead rail which moves throughout the
machine, first through the drying zone then to painting and again
through drying. The painted radiators are then fitted with
accessories and packed. This zone employs two workers for painting
& four to five workers for packing.
Fin and Tube Shop: The fin tube shop produces heat transfer
tubes and air fins. It has two square fin machines, one Z fin
machine, and one straight fin machine. The pre tinning machine,
tube cutting machines & the straight fin machine are located on
an elevated platform. A hoist is present for transferring the
produce down. The pre tinning machine applies a coating of tin on
brass foil, which in turn is machined into heat transfer tubes. The
heat transfer tubes produced are washed in the ultrasonic washing
machine and stored in bins. The straight fins & part of the
heat transfer tubes produced are sent elsewhere for straight fin
core assembly. The fin tube shop employs seven to eight
workers.
Core Assembly: The core assembly primarily deals with two types
of cores, namely the fin& tube type & the straight fin
core. The straight fin core is outsourced; the fin & tube type
is assembled on three manual jigs. Then the header plates are
fitted, fins leveling & combing operations are performed. The
core assembly employs four workers.
Core Baking: This work zone is responsible for fluxing and
baking of the assembled cores. This zone has one furnace, three
flux immersion tanks. The core is immersed in flux; post fluxing
the cores are placed on frames and baked for four minutes. The
baking zone employs three workers.
Welding shop: The welding shop primarily performs three
functions: which are, welding of inlet & outlet pipes to the
tank, tank to header plate welding and side frame welding. The pipe
welding is performed on four work stations, the header plate-tank
welding is done on six workstations, and the side frame welding is
done on five workstations. Rework is performed on two workstations.
The weld shop employs fourteen workers.
Leak Test: This zone is responsible for hydro testing the welded
radiator assembly. The zone has two bays, both having two testing
tanks each. The test rig is bolted onto the inlet and outlet pipe
of the radiator, subjected to the test pressure and checked for
leaks. Faulty radiators are sent for rework. The leak test employs
four people.
Maintenance: The maintenance departments responsibility is to
ensure the operation of all the machines in the plant. The
maintenance department performs preventive as well break down
maintenance.
Store: The store stocks all spares, outsourced components and
raw materials.
1.3Machines in Each zone
1.3.1Press Shop
Ruby Shearing machine
Cut to length machine
Ultrasonic Washing machine
Stress relieving Oven
Bemco Hydraulic Press
Russell Jewelform 100T Press
Godrej 25T Mechanical Press
Rigimax 25T Mechanical Press
10T Hydraulic Press
Isteco Jewel form 100T Press
Ambika 100T
Ambika 100T Mechanical Press
Number Punching Machine
1.3.2Core Assembly
Vibronics Ultrasonic Washing Machine
Fin and Tube Assembly Jig (3 No.s)
1.3.3Fin and Tube Shop
Pre Tinning Machine
Tube Re Cut Machine (New)
Tube Re Cut Machine (Old)
Straight Fin Machine
Electrical Hoist
Square Fin Machine (2 No.s)
Z Fin Machine
1.3.4 Core Baking & End Dipping Baking Oven
Gas Operated End Dipping Bath (2 No.s)
1.3.5Weld Shop & Painting
Gas Oerated Welding Torch (17 No.s)
Thermax Painting Machine
1.3.6Maintenance Generator 180 KVA ( Caterpillar )
Generator 250 KVA ( Caterpillar )
Compressor 360 360 CFM ( IR )
1.3.7Store
Macneil Fork Lift
Sayaji Electrical Hoist
1.4Machines Specifications
SR NO.Machine DescriptionSpecificationsProduction Capacity/
Shift
1Rigimax 25 T PressCapacity: 25 tons, Press Cushion Capacity: 3.
15 tons, Motor: 2.2 KW, 1500 rpm, 56 Strokes/min3750 pcs
2Jewelform 100 T PressMotor: 20 hp, Power: 2900 KW,
Voltage:380/420 V AC, Current: 26 A, Working pressure:140
Kg/cm2.Setup time: 6.5 hrs,25 pcs/hr
3Suresh Seal 25T Press (H.P Trimming)Capacity: 25 tons, Press
Cushion Capacity: 3. 15 tons, Motor: 2.2 KW, 1500 rpm, 56
Strokes/min5200 pcs
410 T Hydraulic Press (Fluid Dynamics Pvt Ltd.)Size:
2150mm*1250mm*530mm(h*l*w), Weight:1150 Kg, System Pressure: 199
Kg/cm2, Motor: 5 HP, 1500 rpm, Voltage:415 V AC .1920 pcs
5Godrej 25 T PressCapacity: 25 tons, Press Cushion Capacity: 3.
15 tons, Motor: 2.2 KW, 1500 rpm, 56 Strokes/min2500 pcs
6Pre- Tinning Machine (F.Gustav Siegmund)1 V Belt 1300*13, 2
Receiving rings,10 scrapers of filt,6 Scrappers of Rubber, 20 Coal
fins, 8 Heating Elements.-
7Ruby Shearing MachineCapacity:3*610mm, Strokes/min:70
Motor: 2.2 KW, 1440 rpm. -
8Bemco Hydraulic PressMotor:25HP, 1470 rpm, Voltage: 415 V
AC.350 pcs
9Vibronics Ultrasonic Washing MachineType VS 2 KW- 2 Stage,
Voltage: 230V AC, 16V DC, Current: 3.7 A, Frequency: 22 KHz.-
10Imeco Washing MachinePower:6000W, No. of Chambers:4, Size:
900mm*700mm*400mm(l*b*h), Capacity/tank:252 l, Power Output:3500 W,
Voltage:415 V AC.-
11Isteco Jewel form 100T PressMotor: 20 hp, Power: 2900 KW,
Voltage:380/420 V AC, Current: 26 A, Working pressure:140
Kg/cm2.Setup time: 6.5 hrs,25 pcs/hr
12Tube Machine Old (F. Gustav Siegmund)Capacity:40 m/min, Cut
Lengths: 200- 1000mm&1500mm, Max. Wall Thickness: 0.20
mm,Weight: 1250 Kg.-
13Gas Operated Solder Bath( End Dipping)Voltage:230 V AC,
Operating Gas Pressure: 0.5 psi, V-800 naturally aspirated
burner.-
14Flameless Stress Relieving FurnaceChamber
Size:1300mm*1400mm*1900mm(w*h*l), Trolley size: 1100mm*1100*1800mm,
Operating Pressure: 0.5 psi, Max. Temp: 400 C, Working
Temperature:250 C, Operation time: 1hr, Voltage: 415 V AC.1400
pcs
15Trimming MachineMotor: 5 HP Induction Motor, 1430 rpm, Air
Pressure: 4.5- 5 Kg/cm2400 pcs
1.5Types of Products
1.5.1Straight Fin Type
ESC-440
Eicher S-325
ESC-335
Farmtrac-50
FT-45
Escort Construction
Terex Vectra
ACE (Radiator Assembly)
Bulls Backhoe
TT-55HP
FT1104D-44T
Eicher 5510
New Holland 55
1.5.2Fin & Tube Type
1.5.2.1
Z Fin
TMTL Genset
FT-60
Izuzu Cross Flow
Eicher 9mm
1.5.2.2
Square Fin TT-70
TT-70- FSC
1.6Observations
1.6.1Safety
1.6.1.1
General Observations
Lacks a loud speaker system for emergency announcements.
No dress code. Different jobs should have different
uniforms.
Low visibility through out the plant, windows to the right is
blocked by the air duct.
Floor Plan is confusing.
Helmets are not in use.
Area under the Fin tube section is a low visibility zone. High
visibility jackets should be provided.
Emergency plan hasnt been displayed.
Emergency doors exist, but are blocked.
Emergency equipment is sparsely located. Places of worship are
present but no safety equipment.
Rubber mats are not present in the press shop. Card board has
been used instead.
No safety briefing given to me, a new employee.
The air circulation system is not adequate.
Most machines have an emergency kill switch.
Both entry and exit of the plant are located at the far ends of
the factory, no exits in near the center of the shop floor.
1.6.1.2
Machine Specific Observations
Slippery surface near the baking furnace.
Exposed motor belts above the furnace,located right under the
fin tube shop.
Hoist alarm is not loud enough.
Proper gas masks for the workers in the painting booth are
required.
Gas masks and safety glasses not in use, the worker working on
the furnace, washing machine, welding need to wear safety
equipment. All these work stations are potential hazard zones due
the presence of hot gases, chemicals and toxic fumes.
Worker at the End Dipping station needs a mask; currently using
a piece of cloth, the hot solder emits fumes.
Better fitting gloves should be provided to workers at the
furnace.
Some of the machines are leaking hydraulic fluid. Slippery
surface around these presses has been covered by card boards.
Godrej 25 T doesnt have an emergency stop button.
Old fin cutting machines have exposed moving parts.
The pre tinning machine emits fumes, the operator should use a
mask.
1.6.2Ergonomics
A short study of man machine relations.
1.6.2.1
General Observations
Most of the tasks performed on the shop floor require the
operator to stand.
Task of the operator is to operate the designated machine,
visually inspect the input and the output.
The working conditions with respect to productivity as well as
ease of operation are different in different sections of the shop
floor.
Most of the machines have been provided with the necessary
auxiliary systems so as to enable the operator to work
efficiently.
1.6.2.2
Machine Specific Observations
Operations such as tank welding , painting , core assembly
,baking, pre tinning, tube cutting, tube washing, end dipping,
annealing, air leak testing require the person to operate the
machine in an erect position.
The press shop work can be performed while sitting on a high
rotating stool, given that the input material & output bins are
located in the correct location.
Some of the press shop workers do have stools for easy and
efficient operation of the machines.
The tools and dies are located on racks near the machine, all
the tools, dies have been coded for easy identification, and proper
lifting mechanism is also provided.
The CTL machine is easy to operate, but the operator could use a
stool.
The straight fin core assembly section feeds the baking furnace,
the assembly is done at one end of the furnace, the worker working
on the other end has to carry the core from this location to the
flux bath and then to the furnace. This setup makes it hard for the
operators to work to their maximum efficiency.
The welding station basically performs three operations, welding
of necks and tubes to the tank, welding the tanks to the core and
welding the side frame to the radiator assembly. All these jobs are
done in an erect posture. The workstation is located in a well lit
area of the plant, fans are also provided. The fixtures provided
for welding are swiveling for all direction access to the radiator
assembly. The flux is located in tray next to the worker; the
welding filler lead is conveniently located either in roll or
cylindrical container.
The test tank area has two tanks, and receives welded the
radiators from one end. As the radiators are heavy the operation
becomes a difficult task for the worker working at the second bay.
Also the person working at the second bay is old. Otherwise, the
workstation is effective, the gauges and the test equipment is easy
to read and operate.
Painting booth has been equipped with auxiliary lighting, a
small fan; the painting booth is not crammed and allows free
movement of the radiator as well as the painter.
The finished radiators arrive on conveyor belt which makes it
easy to add the caps and covers to the finished product, the belt
moves at suitable speed i.e in sync with the time taken to perform
the finishing operations. The product is the packed in card board
box with thermacol packing and loaded onto push carts.
1.7Process Flow Chart
The various operations involved in the production were studied,
the result is the following process flow chart.
SHAPE
Aluminium Plant
2.1Introduction
The aluminium plant is responsible for the production of a wide
range of heat exchangers cores.
It is relatively a new establishment. The machinery in the plant
is modern.
Various types of heat exchangers cores are manufactured in this
plant. These are radiators, air coolers, combi coolers, oil coolers
& inter coolers.
It also follows a batch type production system.
The workforce is employed on a contract basis.
2.2Zones of the Shop Floor
Component Production Zone: This zone produces the components
required for the products. The various components produced are
short bar, long bar, separator sheet, heat transfer tubes, air
fins, oil fins. All of the machines require one operator each. The
operations performed in this work zone are cutting, shearing, fin
forming, slitting, deburring and washing. The inventory level is
maintained for a production period of one day. This zone employs
eight workers.
Core Assembly: This zone assembles the cores of basically three
type of heat exchangers, namely plastic tank radiators , charged
air coolers and plate & bar type hear exchangers. The various
operations performed in this work zone are core assembly, leveling,
fluxing, tube flaring and brazing. This work zone employs fifteen
workers.
2.3Machines in Each Zone
2.3.1Component Production Zone
Kawa Shearing Machine
10.2 mm Fin Forming Machine
Sahyog Bar Cutting Machine
Ramani Tube Re Cut Machine
Slitting Machine
Oil Fin Cutting Machine ( 8 pitch )
Square Fin Machine
Paint Flux Conveyor
Component Washing Master Handler
2.3.2Core Assembly
Plate & Bar Jig ( 3 No.s )
Sellecan Brazing Furnace
Drying Oven
Spray Fluxing Machine
PTR Header Setter ( 3 No.s )
9mm Ecko Fin Machine
7.55mm Ecko Fin Machine
Square Fin Machine
Oil Fin Cutting Machine
Tube Flaring Machine
CAC Header Jig ( 2 No.s )
2.4 Machine Specifications
SR NoMachine DescriptionSpecificationsProduction
capacity/Shift
1Sahyog Bar Cutting MachineMotor:1.5 HP, 1440 rpm, Carbide saw,
Speed:35mm/min, Max spindle speed:2100rpmShort Bar:
3000 pcs, Long Bar: 1500pcs.
210.2 mm Fin MachineMax fin Width:140mm,Cutting speed:25-30
m/min,Max coil diameter:1200mm, Min coil diameter: 300mm-
3Ecko 9mm fin Machine.Size:
1352mm*660.4mm*1651mm(l*w*h),Material width range:12.7mm to114.3mm,
FPI:6- 25 fpi, Input speed: upto 500ft/min, Motor:2 HP, Voltage:240
V AC.-
4Kawa Shearing MachineSize: 2000mm*2000mm*1400mm(l*w*h) , Motor:
2 HP, 1400 rpm, Voltage 400/440 V AC.1800 pcs
5Ramani Tube Re Cut MachineLoading Height 1300mm, Operating
Pressure: 6Kg/cm2, Power: 0.5 KW, Voltage: 415 V AC, 24 V DC.5000
pcs
6PTR Head Setter
(3 no.s)Pneumatic, Accepted Core Length: 400-500mm, Core
width:400-500mm, Core thickness: 28-48mm, Fin width: 28,48,49.120
cores
7Paint Flux Machine (Ramani Automation)Sheet size: 40-220 mm,
Sheet thickness: 0.8-1.6mm, Width of Spray zone: 600mm, Power: 10
KW, Operation Temperature:120-150 C, Voltage: 415 V AC.57mm sheet:
4000 pcs
8CAC Assembly Jig
( 2 no.s)Manual operation.140 cores
2.5Types of Products
2.5.1PTR (Plastic Tank Radiators)
E 440
(9mm Louvered Z Fin)
NH 55
(7.55mm 14 Square Wavy)
Piaggio
(7.55mm Louvered Z Fin)
Swaraj Mazda
(7.55mm Louvered Z Fin)
2.5.2P&B (Plate and Bar)
Bulls
(10.2mm, Non Louvered Z Fin)
KPCL 57
(10.2mm Louvered Z Fin)
Axxiom 30KW
(10.2mm Louvered Z Fin)
IR 11KW
(7.55mm Louvered Z Fin)
IR 22 KW
(7.55mm Louvered Z Fin)
IR 37KW
(10.2mm Louvered Z Fin)
Cumitas HOC
(10.2mm, Non Louvered Z Fin)
HP 140
(7.55mm 14 Square Wavy)
Elgie 45
(10.2mm Louvered Z Fin)
2.5.3CAC ( Charge Air Cooler )
Eicher 483
(9mm, Louvered Z Fin)
Eicher 683
(9mm, Louvered Z Fin)
Avtec
(9mm, Louvered Z Fin)
2.6Observations
2.6.1Safety
2.6.1.1
General Observations
Visibility is good.
Floor plan is clearly marked out.
All the machines and equipment are in their respective
locations.
Lack of loud speaker system, fire alarm etc.
No marked out evacuation plan.
Emergency exits are not present.
Fire fighting equipment is not adequate.
The space between the degreasing machine and the wall may be an
issue in an emergency.
Exhaust fans are effective in dispelling gases produced by the
drying oven.
The Nitrogen tank has been properly secured outside with proper
fencing.
The portion of the building housing the RO plant is crammed,
might be problem area in case of an emergency.
2.6.1.2
Machine Specific Observations
10mm Fin forming machine: external cover is present, but moving
gears are exposed.
Control panels for most machines are suitably located suitably
located for both operation & emergency.
Some work areas need to have a mat for better grip.(10mm fin
machine, Bar cutting machine)
The equipment is well designed
Flux machines produce particulate matter, operators should wear
masks.
The shearing machine needs better lighting.
The PTR jigs retract back their original position in the case of
power loss, operators hand might get injured.
The Nitrogen tank has been secured properly.
2.6.2Ergonomics
2.6.2.1
Machine Specific Observations
Almost all operations are performed in an erect position.
Fin forming: There a total of six fin forming machine, all of
them are linear in operation; the operator has to visually inspect
the fin for defects. All the machines are easy to operate. The
control panel is located at suitable height so that operator of any
size can operate the machine without discomfort. The 9mm Ecko fin
machine and the CAC assembly line behaves as a small cellular
manufacturing system. Such a sequence in operation results in
higher productivity in this line.
Tube re cut machine: The input material, control unit are
suitably placed, the output is delivered to the box automatically,
and no inspection is required.
Core Assembly jigs: The operator is required to stand to perform
the job, the input materials are located in bins on both sides of
the machine, and adequate light is present. The assembly of the
cores is efficiently achieved with minimum loss of energy.
Par and Bar type leveling station: Lighting is essential for
this job, workers require more lighting to perform their jobs
efficiently, also the work space requires have better tooling
solutions
Paint Flux Station: This machine is operated by two workers,
location of the machine leads to rise in particulate matter when
door next to machine is opened,
Brazing furnace: This machine requires the operator to load the
machine and start the brazing operation, the process take a long
time during which the person can perform other jobs.
PTR tube flaring station requires better tooling solutions
2.7Process Flow Chart
The various operations involved in the production were studied,
the result is the following process flow charts.
Charge Air Cooler
Plastic Tank Radiator
Plate & Bar Type
SHAPE
SHAPE
SHAPE
Wigman Center & Laboratory
3.1Introduction
The Wigman center is responsible for the finishing operations on
the heat exchanger cores produced by the aluminium plant.
It is relatively new establishment.
Tanks for all aluminium cores are welded in this
establishment.
All new products and prototypes of prospective products are
tested in the lab.
The establishment has modern TIG welding machines.
All heat exchangers produced are sent for powder coating to
another company.
3.2Zones of the Shop Floor
Fin & Tube Shop/CAC Shop: The fin & tube shop is
responsible for welding of tanks to the CAC cores. The tanks are
outsourced; they undergo stress relieving and hydro testing before
they are welded to the core. The various operations performed in
this zone are cleaning, welding, inspection and packing. Welding is
performed on four workstations. This work zone employs nine
workers.
Plate & Bar Shop: The plate & bar shop is responsible
for welding of C channel tanks to cores. The tanks are cut from C
section channels, inlet-outlet holes are drilled at the development
center. The operations performed here are welding, grinding,
brushing, inspection and packing. This work zone employs nine
workers.
Plastic Tank Radiator Shop: The PTR Shop is responsible for the
fitting of plastic tanks to the fin and tube type radiators. The
plastic tanks are outsourced. The operations performed in this work
zone are pipe fitting, clinching, crimping, side frame fitting,
accessory fitting, dry testing and packing. The PTR shop employs
ten workers.
Laboratory: All new products and prototypes undergo various
tests at the laboratory. The tests are heat dissipation test,
vibration test, thermal cycle test, corrosion test, internal
cleanliness test and hydraulic pressure test.
3.3 Machines on the Shop Floor
Kemppi TIG Welding Machine (8 No.s)
Dry leak Test Machine (2 No.s)
Top Crimping Machine
Hot Water Generator
Thermic Fluid Heater
Combined Vibration & Pulsation Test Rig
Thermal Cycle Test Rig
Hydraulic Test Machine
Electro Dynamic Vibration Shaker
Corrosion Test Chamber
Internal Corrosion Test
Tensometer
Hydro Test tanks (3 No.s) and Hoist.
3.4Machine Specifications
SR No.Machine DescriptionSpecification
1Kemppi 3500W TIG Welding Machine.Voltage: 400 V AC, Rated
Power: 60% ED: 350A/11.7KVA, 100% ED 280A, Open Circuit Voltage: 70
V DC, Power: 18 W, Efficiency: 80% (350A/34V), Size:
690mm*260mm*870mm(l*w*h), Weight: 74 Kg, Max Pressure of Cooling
Unit: 350 Kpa.
2Electro Dynamics Vibration ShakerVibration: Sine, sweep &
random, Rated force: 1500 Kgf , Acceleration: 10g, Rated
displacement: 35mm, Velocity: Upto1.5 m/sec, Frequency range: 5Hz
to 3 KHz, Payload capacity: 300 Kg, 3D vibrations.
3 Hydraulic Pressure TestHydraulic Pressure: Upto 100 Kg/cm2,
Fluid flow: Upto 10 lpm.
4External Corrosion Resistance TestSolution temperature: Ambient
to 45-55 C, Air pressure: Upto 4 Kg/cm2, Fog rate: 10-20 Ml/hr per
80 cm2,Solution Type: Salt solution spray test( 5 % NaCl soln
prepared in D.M water), Agricultural fertilizer test( 5% fertilizer
soln in D.M water), SWAAT( 42g of synthetic sea salt + 10 ml of
glacial acetic acid/l).
5Vibration TestAcceleration: 3g fixed, Amplitude: 3mm fixed,
Frequency: Upto 16 Hz, Direction: Vertical, Max. payload: 20
Kg.
6Combined Vibration & Pressure Pulsation TestVibration Test
(Acceleration: 3g max, Amplitude: 5mm max, Frequency: Upto to 25
Hz, Direction: Vertical, Max payload: 15 Kg.), Pressure Pulsation
Test( Fluid Pressure: Upto to 2.0 bar, Fluid Temperature: Upto to
130 C, Frequency: Upto 25 CPM.
7Thermal Cycle TestCold fluid temperature: min 5 C, Hot fluid
tempearature: max 130 C, Chamber temperature: 17-23 C, Cycle time:
Computer control on spray time.
8Heat Dissipation TestAir Velocity: 1- 30 m/s, Coolant flow:
1.5-223 l/m, Coolant heating capacity 130C, Oil flow: 2-225 l/m,
Oil Heating Capacity: 55 C, Test Range (size): 100*100mm to
1350*1350mm
3.5Observations3.5.1Safety
Work area is well marked out.
Lighting is good.
Lack of loud speaker system, fire alarm etc.
All the machines and equipment are in their respective
locations.
Curtains have been provided for all welding stations. All
workers use shields.
Fire fighting equipment is sparsely located.
No emergency exits or plans.
No uniforms.
Only one entry and one exit, both located at ends of the shop
floor. Also, the exit doesnt lead to an open area.
3.5.2Ergonomics
All the operations performed here need the worker to be in an
erect position.
TIG welding station: The operator has been provided with all the
necessary equipment to enable him to work efficiently.
PTR assembly: Plastic tanks are provided next to the machine,
the brazed core a conveniently located on a pallet, bolt guns,
bolts, o rings etc are located in trays. Everything is organized
and labeled.
The inspection and packing area is also well chalked out, the
gauges are easy to read, and all the packing requirements have been
provided. Packed good are placed onto a pallet next to the
workstation.
Development Center
4.1
Introduction
The Development Center is responsible for the development of new
machines, machining of tools & dies and other machining for
maintenance purposes.
It is old part of the factory.
It has both new and old machinery.
Most of the workers are permanent employees of the company.
4.2Machines on the Shop Floor
HMT Surface Grinder
Surface Grinder
Lathe Machine
HMT Milling Machine
Shaping Machine
Power Hacksaw Machine
C Channel Cutting Machine
Radial Drilling Machine
Accumax Drilling Machine
4.3Machine Specification
SR NO.Machine DescriptionSpecification
1Surface Grinding Machine(small)Size:46*9(l*w), Working surface:
18*9, Motor: 1 HP, Spindle speed: 2800 rpm, Working pressure:
120psi, Longitudinal traverse: 19, Cross traverse: 7, Head
Traverse: 11.
2Milling Machine(HMT)Main motor: 7.4 HP/5.5 KW, Rapid traverse
motor: 2.0 HP/1.5 KW, Coolant pump motor: 0.13 HP/0.1KW, Spindle
speeds: 68-1270, Max. payload: 315 Kg, Weight: 2900 Kg., Size:
2300mm*2000mm*1850mm(l*w*h)
3Accumax Drilling MachineDrill motor: 5 KW, Elevating motor:
0.55 KW, Coolant motor: 0.12 KW, Size:
1285mm*1880mm*1925mm(w*d*h)
4Kirloskar Hacksaw MachineMotor: 1 HP, 7200 RPM, Voltage:
400/440 V AC.
5Surface Grinding Machine(HMT)Grinding motor: 5.7 HP, 720 RPM,
Speed: 2880 RPM, Max traverse of grinding wheel: 320mm,
Longitudinal traverse: 1150mm, Grinding length: 1000mm.
4.4Observations
4.4.1Safety
Visibility is good.
Floor plan is clearly marked out.
All the machines and equipment are in their respective
locations.
Lack of loud speaker system, fire alarm etc.
No marked out evacuation plan.
Fire fighting equipment is not adequate.
4.4.2Ergonomics
Machining is the primary operation of this work space, hence
upright position is necessary to perform the job.
Platforms have been constructed for better visibility and
access, stools are also available.
All the machines and tools are labeled for easy
identification.
Equipment to lift and place the raw material has been
provided.
Raw Material Storage
Raw Material Storage
Raw Material Storage
Storage
Fin Forming
Fin Forming
Blank Cutting
Blank Cutting
Outsourced Straight Fin Core
Drawing
Trimming
Hole punch
Pipe Seat Dimple Forming
1st Forming
Logo Embossing
2nd Forming
Trimming
Slot Punching
Stress Relieving
Fin Leveling & Combing
Stiffener Insertion
Core Fluxing & Baking
End Dipping
Tank, Side Frame Welding
Core Assembly
Air Fin
Z & Square
Air Fin
Straight Fin
Tank
Header Plate
Protection Cap & Packing
Copper Brass Plant
Inspection
Stress Relieving
Inspection
Temporary Storage
Header Plate Fitting
Raw Material Storage
Pre Tinning
Tube Forming
Tube
Washing
Temporary Storage
Gauging
Pipe Welding
Leak Test
Not OK
Rework
Leak Test
Not OK
Radiator Drying, PRC Application & Painting.
OK
Accessory Fitting
OK
Visual Inspection
Packing
Rejection
Raw Material Storage
Radiator Drying, PRC Application & Painting.
Raw Material Storage
Raw Material Storage
Storage
Raw Material Storage
Storage
Storage
Fin Forming
Washing
Tank Periphery Cleaning
Blank Cutting
Drying
Washing
Corner Cutting
Drying
Forming
Punching
Washing
Drying
Fluxing
Degreasing & Drying
Brazing
Tank Fitting
HP to Tank Welding
Core Assembly
Leak Test
Leak Test
Rework
Rejection
Accessory Fitting
Visual Inspection
Packing
Air Fin
Tube
End Plate
Header Plate
Tanks
Protection Cap & Packing
Charge Air Cooler
OK
Not OK
OK
Not OK
Header Plate Fitting
Washing
Inspection
Raw Material Storage
Raw Material Storage
Raw Material Storage
Raw Material Storage
Raw Material Storage
Raw Material Storage
Fin Forming
Fin Degreasing
Bar Cutting &
Deburring
Bar Washing
Fin Forming
Fin Degreasing
Bar Cutting & Deburring
Bar Washing
Sheet Cutting & Deburring
Sheet Washing
Drying
Sheet Cutting & Deburring
Sheet Washing
Drying
Core Assembly
Material Storage
Clamping
Leveling
Brazing
Visual Inspection
TIG Welding
Rework
Packing
Air Fins
Oil Fins
Long Bar
Short Bar
Separator Sheet
End Plate
Tank
Leak Test
Leak Test
OK
Not OK
OK
Not OK
Plate and Bar Type
Fluxing
Raw Material Storage
Raw Material Storage
Storage
Raw Material Storage
Storage
Storage
Fin Forming
Washing
Blank Cutting
Drying
Washing
Corner Cutting
Drying
Forming
Punching
Washing
Drying
Fluxing
Degreasing & Drying
Brazing
Gasket Fitting
Tank Crimping
Core Assembly
Leak Test
Leak Test
Rework
Rejection
Accessory Fitting
Visual Inspection
Packing
Air Fin
Tube
End Plate
Header Plate
Plastic Tank, Rubber Gasket
Protection Cap & Packing
Plastic Tank Radiator
OK
Not OK
OK
Not OK
Header Plate Fitting
Inspection