Top Banner
FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE AND COMMODITIES TRANSPORT TECHNOLOGY Fidic Yellow vs Silver Weero Koster Partner Norton Rose LLP February 2012
11

Fidic yellow vs silver

Nov 14, 2014

Download

Business

Weero Koster

Fidic yellow vs fidic silver
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Fidic yellow vs silver

FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE AND COMMODITIES TRANSPORT TECHNOLOGY

Fidic Yellow vs SilverFidic Yellow vs Silver

Weero KosterPartnerNorton Rose LLPFebruary 2012

Weero KosterPartnerNorton Rose LLPFebruary 2012

Page 2: Fidic yellow vs silver

General application• Yellow Book: design/build contract electrical/mechanical

works, including plant supply and construction works; allocation of risk on basis of insurability, project management principles and ability to foresee and mitigate

• Silver Book: fixed-price, date-certain, lump-sum turn-key contract:• Little risk of price increase (but higher price) or delay

for Employer• Shift of risks to Contractor: design and execution

Page 3: Fidic yellow vs silver

General risk profile: Shift of risks

• Employer’s Engineer is Employer’s Representative• Employer’s ‘determinations’• Setting Out• (No) Unforeseeable difficulties & verification/

interpretation of Employer data (incl. sub-surface, hydrological and Employer Requirements)

• General design obligations, design error

Page 4: Fidic yellow vs silver

Shift of risks, cont’d

• No extension of Time for Completion for:• exceptionally adverse climatic conditions

(except FM) • unforeseeable shortages in personnel or goods

by epidemic or government actions• Errors in Employer’s Requirements• Setting Out• Unforeseeable physical conditions

Page 5: Fidic yellow vs silver

Shift of risks, cont’d

• Employer’s Risk excludes:• Use of works by Employer,• Design of works by Employer’s personnel,• Unforeseeable operation of forces of nature

Page 6: Fidic yellow vs silver

General risk profile: key employer issues

• Contractor fully responsible for design and design coordination (including Employer design)

• Full ground condition risk to Contractor• Employer to retain influence over project• Right to Variations• Limited scope for Contractor claims for time/money;

Contractor will:• Price these risks, so increase initial Contract Sum• Do extensive due diligence to mitigate, leading to

delay in execution

Page 7: Fidic yellow vs silver

Payment & security: key employer issues

• Fixed price lump sum payments against schedule of payments & Performance Certificate

• Long payment period• No claim for additional time or money for e.g.

Variations/innovations, ‘in country” Force Majeure, Unforeseen ground conditions, setting out or discovery of fossils

• Robust security package: advance payment bond, performance bond, retention of money

• Warranty bond after Taking Over (> 2yrs)

Page 8: Fidic yellow vs silver

Programme/delay: key employer issues

• Liquidated Damages for delay (10 – 20 %, > ?)• Limited rights for extension of Time for Completion• Suspension by Employer entitles Contractor

extension of time/ costs

Page 9: Fidic yellow vs silver

Testing and defects, insurance: key employer issues• Suitable testing regime• Employer technical advisors to set

performance/reliability standards and regime for testing/ performance guarantee levels

• Liquidated Damages for performance (10 – 20 %, > ?)• Defects liability period (1 – 2 yrs): default is 1 yr• Liability cap, sub-caps and ‘carve-outs’• Project specific insurance provisions; all insurance

monies go in separate insurance proceeds account for benefit Employer

Page 10: Fidic yellow vs silver

Permits, change in law, FM: key employer issues• Employer planning, environmental/ Contractor

construction and transport: permit schedule• Change in law after contract signing/ in force,

EH&S developments• Exhaustive FM list ?• Location of FM, “in country” FM: costs in addition

to EOT ?

Page 11: Fidic yellow vs silver

FINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE AND COMMODITIES TRANSPORT TECHNOLOGY