Top Banner
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management Oversight (OPMO) Fall, 2008
51

Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

Dec 27, 2015

Download

Documents

Lee Bradford
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

Fermilab Implementation ofDOE Critical Decision Process

FRA Project Management System Presentation

by L Edward Temple JrHead, Office of Project Management Oversight (OPMO)

Fall, 2008

Page 2: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 2

Outline

• Potential New Projects involving Fermilab• Project Phases• Project Acquisition Process and Critical

Decisions• (DOE Order 413.3; (Manual &) Guides)• [EIA Standards EIA-649 & 748-A]• FRA Project Management System• Conceptual Design• Next Steps

Page 3: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 3

List of Potential New Projects

• Project X – 8 GeV Linac & beamlines

• mu2e – rare symmetry violating process

• MicroBooNE – LArTPC

• DUSEL beamline (and Detector)– Tunnel, beamline, target (near hall)– Large neutrino detector at Homestake

• SNAP - SuperNova Acceleration Probe

Page 4: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 4

Page 5: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 5

~ 5%Conceptual Design

~ 30%Preliminary Design

100%Final Design

Construction

Fermilab’s Office of ProjectManagement Oversight

Page 1

Project Design Phases

CDR

TDR

Bid Package

R&D

Page 6: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 6

~ 5%Conceptual Design

~ 30%Preliminary Design

100%Final Design

Construction

Fermilab’s Office of ProjectManagement Oversight

Page 1

Project Design Phases

CDR

TDR

Bid Package

CD-0

CD-1

CD-2

CD-3

CD-4

R&D

Page 7: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 7

Page 8: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 8

Typical DOE Acquisition Management System for Line Item Projects

• Figure 1 from DOE O 413.3A

Pre-conceptualPlanning

ConceptualDesign

PreliminaryDesign

FinalDesign Construction

(PARS==Project Assessment and Reporting System)(PED==Project Engineering & Design funds)

Page 9: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 9

Critical Decision Authority Thresholds

Page 10: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 10

CD-0 Critical Decision Requirements

Page 11: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 11

CD-1 Requirements

continuessee theOrderDOE O413.3A

Page 12: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 12

Page 13: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 13

Page 14: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 14

Page 15: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 15

DOE Order 413.3; Manual & Guides EIA Standards EIA-649 & 748-A

• Handout Copy– 413 Order, Manual, Guides available at

www.directives.doe.gov

• Standards must be purchased– EIA 649 Configuration Management– EIA 748-B Earned Value Management

Systems

Page 16: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 16

Page 17: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 17

Page 18: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 18

Fermilab Organization Chart

Page 19: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 19

FRA PM System

Available at FRA website:

http://fra-hq.org/about.html

Figure from the FRA Proposal in Section 4b“Achieving Excellence in FNAL Operations Business Management”

Provides FNAL with powerful assets and capabilities including training for managers.

Much of the training is “just in time” and provided in the Project Management Working Group Meetings specific to each project.

Marshall (/ shepherd) the troops to meet the formallyrequired Project Management documents, systems,and prepare for DOE Lehman CD (and other) Reviews

Project Management Working Group Meetings (PM WGM)

Page 20: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 20

OPMO Activities

• Setup, coordinate, lead parts of, run Project Management Working Group Meetings for each project at the request of an Associate Director.

• Conduct Director’s Reviews of Projects as requested by a Director.

• Assist project teams in others ways upon request. Eg Hoffer did Schedule for Spalding on Tevatron Luminosity Upgrade

Page 21: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 21

OPMO Prior Project Document and Review Archive

• http://www.fnal.gov/directorate/OPMO/Projects/home/base.htm

• Fermilab Projects• Dark Energy Survey (DES)• MINERvA• MicroBooNE• NOvA• Proton Plan• Project X• Super NuMI (SNuMI)• Completed Fermilab Projects• Run IIb Upgrade DZero• Non-Fermilab Projects• Argonne Leadership Computing Facility (ALCF)• ITER• National Synchrotron Light Source II (NSLS-II)

Page 22: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 22

Conceptual Design

• Definition from Manual (page A-6)

Conceptual Design. The concept for meeting a mission need. The conceptual design process requires a mission need as an input. Concepts for meeting the need are explored and alternatives considered arriving at the set of alternatives that are technically viable, affordable and sustainable.

Page 23: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 23

Conceptual Design

• Descriptive Paragraph from the Manual (Section 5.2)

5.2 CONCEPTUAL DESIGN

The conceptual design effort is dependent on the nature of the need. While it is normal for solutions to quickly present themselves in response to a need, the conceptual design process must be approached methodically to ensure that the arrived at solution or alternatives are not merely responsive to an approved need, but are within the current technology, are affordable, and provide the best value to the Department. Research, development, testing and other efforts may be required that will contribute to the concept. The conceptual design process may also require negotiation with outside organizations, stakeholders or other legal entities to agree on functional, technical, operational requirements, performance requirements or standards. Value management is a key ingredient in the process that supports reaching the lowest cost alternatives. Value management should be employed as early as possible in the project development and design process so recommendations can be included in the planning and implemented without delaying the progress of the project or causing significant rework of completed designs. Value management conducted during the early phases of capital asset acquisition yields the greatest cost reductions.

Page 24: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 24

Conceptual Design

DOE M 413.3

Page 25: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 25

Conceptual Design

DOE M 413.3

Page 26: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 26

Design Terminology

Page 27: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 27

Possible Project X Schedule

• Near Term Activities / Goals– 2008 Sept / Oct Initial Configuration

Document complete– 2009 Feb Director’s Preliminary Review

supports CD-0– DOE Lehman Review IPR for CD-0

(Independent Project Review)

• Longer Term Goal– FY 2013 “Construction Start”

• See Hoffer / McCluskey presentations for much more detail

Page 28: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 28

CD-0

• DOE G 413.1-17 “Mission Need Statement Guide”– this is a DOE document prepared by the HQ Program

Office (OHEP for Fermilab)– background information is supplied by the lab– occasionally a “draft” document provided to HQ

• CD-0 “package” prepared to support a CD-0 ESAAB (Energy Systems Acquisition Advisory Board) meeting.

Page 29: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 29

Example CD-0 Resource and ScheduleForecast Information

Page 30: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 30

Page 31: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 31

DRAFT NOvA Project Timeline for Critical Decisions & Reviews

Updated 08-Oct-07

Note:· Text in Red indicates change from prior version· Text in Gray indicates activity is complete

7/1/2005 11/30/2008

10/05 1/06 4/06 7/06 10/06 1/07 4/07 7/07 10/07 1/08 4/08 7/08 10/08

Apr 07April 12, 2007 (Actual)

SC1/AE Approves Acquisition Strategy

4/06 DOE CD-1 Review

April 4-6, 2006

2 May 2007AE Approves

CD-1

Oct 07Oct 23-25, 2007

DOE Reviewfor CD-2/3a

Jun 07June 19-29, 2007 Director’s/DOE’s

Performance Management System Review

2/06Director’s Review

for CD-1Feb 28–Mar 2, 2006

12/07Construction Start

1st Qtr FY08

Mar 06 Mission Need

Independent Project Review Report (NuSAG)

Aug 22, 2007EIR Sensitivity

Training

7/05Director’s Preliminary

ReviewJuly 18-20, 2005

29 Nov, 2005 SC1/AE

Approved CD-0

Jun 07June 4-6, 2007

Director’s Reviewfor CD-2/3a

Nov 26, 2007Nov 26-30, 2007

EIR

May 08TBD

AE ApprovesCD-3b

May 08TBD

DOE ReviewCD-3b

Feb 7, 2008AE Approves

CD-2/3a

May 08TBD

Director’s Review for CD-3b

Sep 24, 2007Request

EIR

Oct 8, 2007Lehman

WebpagePosted

Oct 22, 2007EIR

WebpagePosted

Jun 2008OECM EVMSReadiness

Assessment

Aug 2008OECM EVMSCertification

Review

Page 32: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 32

NOvA ProjectDraft Critical Design Prerequisites

Updated 01-Oct-07

Estimated Need by Dates for DOE Approvals

and Documents

Target Completion Dates for NOvA

DocumentsNote:· Text in Red indicates change from prior version· Text in Gray indicates activity is complete

9/1/2005 4/1/2008

9/05 12/05 3/06 6/06 9/06 12/06 3/07 6/07 9/07 12/07 3/08

Jan 2008 DOE Approval of

Final PEP(DOE Document)

Apr 2006Verification of Mission Need

(Lehman CD-1 Review)April 4-6, 2006

Jun 2007CD-2/3a Docs:- Technical Design Report (TDR)- Baseline Cost Est. and Baseline Resource Loaded Schedule- Final Configuration Management Document- Final PMP- NEPA and Approved Safety Documents- Final Design & Procurement Packages for Long Lead Time Items for CD-3a- Updated Value Management Documentation- Final Risk Management Plan

May 2007May 2, 2007 (Actual)

CD-1 DOEApproval

Nov 29, 2005Justification of Mission

Need Document CD-0 Approved

(DOE Document)

Mar 2007DOE Approval ofPreliminary PEP(DOE Document)

Apr 2007April 12, 2007 (Actual)

DOE ApprovesAcquisition Strategy

(DOE Document)

Jun 2007Performance ManagementSystem Document (EVMS)

Feb 2006CD-1 Docs:- Conceptual Design Report (CDR)- Baseline Range and Resource Loaded Schedule- Draft Configuration Management Document- Preliminary PMP- Preliminary Hazard Analysis Report- Value Management Documentation- Draft Risk Management Plan

Mar 6, 2007Submit Updated CD-1 Docs w/Accelerator Work Included

Apr 2008TBD for CD-3b

- Updated CD-2 Documents- Final Design Complete or design is sufficiently mature to start procurement or construction

Oct 8, 2007Lehman

Webpage

Oct 22, 2007EIR

Webpage

Page 33: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 33

External Independent Review (EIR) Process Timeline

Updated (08-Oct-07)

22-Oct-07OECM Receives

Documents(Week 0)

9 - 10Forming

EIR Team~2 Weeks

24-Sep-07EIR

Requested

23-Oct-07Oct. 23-25, 2007

LehmanCD-2/3a Review

26-Nov-07Nov. 26-30, 2007

Conduct EIR(Week 5)

6-Dec-07Draft Report Issued

for Factual Accuracy Review

(Week 6)

12-Dec-07Program/ProjectSubmits Factual

Accuracy Comment(Week 7)

19-Dec-07Final EIR

Report Issued(Week 8)

8-Jan-08Project Submits

Corrective Action Plan to DOE

(~2 Weeks After Report Issued)

24-Jan-08DOE Holds

ESAAB(~4 Weeks After Report Issued)

7-Feb-08 AE Approves

CD-2(~6 Weeks After Report Issued)

Note:· Text in Red indicates change from prior version· Text in Gray indicates activity is complete

1 - 2Resolve

Comments from ESAAB

1 - 1OECM 2w Min. Requirement

12 - 1Project GeneratesCorrective Action

Plan

Page 34: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 34

Action Items(New Items from Oct. 2 WGM)

1) Address Pepin’s request that FNAL Procurement Representative signoff on NOvA’s Acquisition Plan [Ron Ray, Bob Cibic]

2) Determine if DOE FSO can electronically signoff documents in NOvA’s Docdb [Alan Wehmann]

3) Discuss FY2011 shutdown schedule start date with Steve Holmes and Roger Dixon and get back with NOvA. [Hugh Montgomery]

4) Send to Dean the name and contact information of EIR Reviewer that needs access to NOvA’s project file and Open Plan to start process for getting the reviewer access rights. [Pepin Carolin]

(Carryover from Sept. 18 WGM)

5) Develop document that describes assumptions used in building the schedule. [Ron Ray/Bill Freeman]

(Carryover from Sept. 04 WGM)

6) Send copy of updated EA to ES&H (Bill Griffing) and Mike Martens to review prior to notification to Fermi’s nearest neighbors about submittal of EA. [John Cooper]

Page 35: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 35

DOE 413.3 Attachment 1 - CONTRACTOR REQUIREMENTS DOCUMENT

1. Earned Value Management System (Not required if <$20M)2. Monthly Reports3. Acquisition Plan4. Technical performance analyses and corrective action plans5. Critical path schedule and Project Master Schedule6. Cost estimate; (Basis of Estimate)7. Risk identification, quantification and mitigation8. Integrated technical, cost, and schedule baseline9. Configuration Management10. Value Engineering11. Quality Assurance Program12. Integrated Safety Management System13. Sustainable Building Design

Page 36: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 36

DOE O 413.3 Attachment 1CONTRACTOR REQUIREMENTS DOCUMENT

DOE O 413.3, PROJECT MANAGEMENT FOR THE ACQUISITION OF CAPITAL ASSETS

The Department of Energy (DOE) prime contractor’s project management system must satisfy the following requirements.

1. The industry standard for project control systems described in American National Standards Institute (ANSI) EIA-748, Earned Value Management Systems, must be implemented on all projects with a total project cost (TPC) greater than $20M for control of project performance during the project execution phase.

2. Cost and schedule performance, milestone status, and financial status must be reported to DOE on a monthly basis using DOE-approved work breakdown structure elements and data elements for all projects with a TPC greater than or equal to $20M, except for time-and-materials contracts, firm fixed-priced contracts, or level-of-effort support contracts, for control of project performance during the project execution phase. The report must also include variance analyses and corrective action plans that integrate cost, schedule, and scope if variances exceed DOE-established reporting thresholds. Also reported will be analyses of cost and schedule trends, financial status, and baseline change control activity, including the allocation of management reserve, potential problems, and critical issues.

Qtrly

Page 37: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 37

DOE O 413.3 Attachment 1 (cont.)

3. For project contracts that will be accomplished by M&O/M&I contractors, the contractor must have a written Acquisition Plan that is appropriate for the requirement and dollar value of each contract and consistent with the intent of the FAR. The Acquisition Plan for a project contract to be awarded by an M&O/M&I contractor is developed by a team of contractor employees including, as a minimum, the prospective Project Manager and Contract Negotiator. The Acquisition Plan will also be concurred in by the DOE Contracting Officer.

4. Technical performance analyses and corrective action plans must be reported to DOE for variances to the project baseline objectives resulting from design reviews, component and system tests, and simulations.

5. A critical path schedule and a project master schedule must be developed and maintained.

6. Cost estimating must be an integral part of cost baseline and life-cycle cost development and maintenance, budget request development, and estimates at completion.

7. Project technical, cost, and schedule risks must be identified, quantified, and mitigated (as appropriate). Risk mitigation strategies must be developed and implemented.

8. An integrated contractor technical, cost, and schedule baseline must be developed and maintained through the use of a contractor-level change control board.

Page 38: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 38

DOE O 413.3 Attachment 1 (cont.)

9. A configuration management process must be established that controls changes to the physical configuration of project facilities, structures, systems, and components in compliance with ANSI/EIA-649, National Consensus Standard for Configuration Management. This process must also ensure that the configuration is in agreement with the performance objectives in the technical baseline.

10. A value engineering process must be used that identifies high-cost project activities in order to realize a maximum return on investment through the use of systems engineering trade-offs and functional analyses that identify alternate means of achieving the same function at a lower life-cycle cost.

11. A quality assurance program must be developed and implemented for the contract scope of work in compliance with DOE O 414.1A, QUALITY ASSURANCE, at the beginning of the project and maintained over the project life. This program must assign responsibilities and authority for quality, define policy and requirements, and provide for the performance and assessment of work.

12. An Integrated Safety Management system must be developed and implemented for the contract scope of work in compliance with DEAR 970-5204-2, Integration of Environmental, Safety and Health into Work Planning and Execution.

13. Sustainable building design principles must be applied to the siting, design, and construction of new facilities.

Page 39: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 39

Next StepsRegular Project X PM WGMs

in addition to regular Project X project meetings

Frequency of PX PM WGMs will varysuggest monthly to start

(open for discussion)

Page 40: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 40

Back Up Slides

Page 41: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 41

Page 42: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 42

Page 43: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 43

Page 44: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 44

Page 45: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 45

Page 46: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 46

Page 47: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 47

Page 48: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 48

Page 49: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 49

Page 50: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 50

Page 51: Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.

28-Aug-2008 51

A Scientist’s View

circa Summer 2008

New order(s) just adds more

“crushing bureaucracy, incompetence, apathy and management bloat!!”