7/29/2019 Feltes 5
1/61
Power Technologies, Inc.
Testing Methods: An OverviewTesting Methods: An Overview
Machine Measurements
James W. Feltes Power TechnologiesJohnny R. Willis Schenectady, NY
Carlos Grande-Moran
7/29/2019 Feltes 5
2/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
u Introduction
uTest Preparation
uTest Procedures
7/29/2019 Feltes 5
3/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
IntroductionIntroductionuPurpose: More accurate models
Generator
Excitation System
Turbine Governor
uModel Parameters May Be Inaccurate
Not typically verified by field tests
Parameters may change (aging, tuning)
7/29/2019 Feltes 5
4/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Introduction (cont.)Introduction (cont.)
uBenefit: Improved Stability Analysis
Possible increase in power transfercapability
Equally possible decrease in power transfercapability
Increased accuracy in calculation oftransient and dynamic stability limits
7/29/2019 Feltes 5
5/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Introduction (cont.)Introduction (cont.)
uAdvantages of PTI Test Procedure:
Plant and generator protection remainsintact
No interruption of CT signals
Unit instantly available if needed
7/29/2019 Feltes 5
6/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Test PreparationTest PreparationuGather Information
One-line diagram showing metering,protection, and supply to auxiliaries
Generator and turbine nameplate data
Manufacturers data
Reactances and time constants Saturation curves and Vee curves
Reactive capability curve
Exciter and governor models, equipment info
7/29/2019 Feltes 5
7/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Test PreparationTest PreparationuGather Information (cont.)
Plant data
Hydro unit - physical description(measurements) of flow path (penstock, surgetank, tailrace)
Steam unit - heat balance diagram
All units - Allowed operating ranges (localcriteria or practices)
7/29/2019 Feltes 5
8/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Test Preparation (cont.)Test Preparation (cont.)u Select Signals
Accessibility & Location
Preconditioned? Transducers? Timedelay?
Determine location of test equipment
Wire signals to common terminal block Signal electrical isolation
7/29/2019 Feltes 5
9/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Test Preparation (cont.)Test Preparation (cont.)uVisit control room
Note meter locations and signal ranges
Determine feasibility of getting steady statedata from SCADA printouts on demand
Determine method of communications
between operator and test engineers
7/29/2019 Feltes 5
10/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Test Preparation (cont.)Test Preparation (cont.)uDetermine Test Sequence
Open Circuit
Vee Curves
Partial Load Rejections
uDetailed Step-by-Step Test Plan
7/29/2019 Feltes 5
11/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Test Preparation (cont.)Test Preparation (cont.)uDiscuss Test Procedure
Plant Operators and Engineers
Plant Informs System Dispatchers
No operator adjustments during datarecording
Tests typically require 1-2 days, includinginstrumentation setup
7/29/2019 Feltes 5
12/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Test EquipmentTest Equipment -- Dynamic System MonitorDynamic System Monitoru Recording of AC and DC signals
u Phasor measurement and recording of AC signals
u
Captures low frequency dynamic phenomenau Can compute real & reactive power, phase angle,
frequency, etc. in real time
u Comprehensive data analysis and power system simulation
capability through DADiSP and PSS/Eu Provides digital data allowing later comparison with
derived simulation model performance
7/29/2019 Feltes 5
13/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
DSM System 200DSM System 200uPortable Version
7/29/2019 Feltes 5
14/61
Power Technologies, Inc.
Measurement EquipmentMeasurement Equipment
uClamp-on CT
7/29/2019 Feltes 5
15/61
Power Technologies, Inc.
Measurement Equipment (cont.)Measurement Equipment (cont.)
u Split Core CT
7/29/2019 Feltes 5
16/61
Power Technologies, Inc.
Measurement Equipment (cont.)Measurement Equipment (cont.)
uPosition Transducer
7/29/2019 Feltes 5
17/61
Power Technologies, Inc.
Measurement Equipment (cont.)Measurement Equipment (cont.)
uPosition Transducer on a Hydro Unit
7/29/2019 Feltes 5
18/61
Power Technologies, Inc.
Measurement Equipment (cont.)Measurement Equipment (cont.)
uMagnetic Pick-up
7/29/2019 Feltes 5
19/61
Power Technologies, Inc.
Measurement Equipment (cont.)Measurement Equipment (cont.)
uOptical Pick-up
7/29/2019 Feltes 5
20/61
Power Technologies, Inc.
Measurement Equipment (cont.)Measurement Equipment (cont.)
7/29/2019 Feltes 5
21/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Test ProceduresTest Procedures
u Steady State Tests
Open Circuit Tests Vee Curves (MW/MVAr variations)
uDynamic Tests
Partial Load Rejections
7/29/2019 Feltes 5
22/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Open Circuit Test ProcedureOpen Circuit Test Procedure
uGoal: Generator Saturation Curve
u
Procedure: Unit at rated speed Main breaker open (unit off-line but at
rated speed)
Measure Efd and Ifd over range of Vt
7/29/2019 Feltes 5
23/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Open Circuit Test Procedure (cont.)Open Circuit Test Procedure (cont.)
uTerminal voltage measurement range:
30%, 40%, 50%, 60%, 70%, 75%, 80%, 85%,90%, 95%, 100%, 104%, 108% of rated.
uTake backup readings (DVM, SCADA)when possible
uMake sure generator is isolated fromauxiliary loads
7/29/2019 Feltes 5
24/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Open Circuit Test Coordination RequirementsOpen Circuit Test Coordination Requirements
uPlant Operators:
Need to be able to hold unit at rated speed,open circuit (no power)
Hydro units - vibration, controls
Steam units - turbine heating, controls
Gas turbines - generally no problems
Adjustment of terminal voltage
AVR control range
Switch to manual for lower voltages if needed
7/29/2019 Feltes 5
25/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Open Circuit Test Procedure (cont.)Open Circuit Test Procedure (cont.)
7/29/2019 Feltes 5
26/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Vee Curve Test ProcedureVee Curve Test Procedure
uGoal: Steady State Reactances
u
Procedure: Main breaker closed (unit on-line)
Take steady-state readings at various loadlevels (MW) and excitation levels (MVAr)
7/29/2019 Feltes 5
27/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Vee Curve Test Procedure (cont.)Vee Curve Test Procedure (cont.)uMeasured Values:
Terminal voltages (from PTs)
Armature currents (from CTs)
Generator field voltage (direct) and current (from shunt)
Exciter field voltage (direct)
Turbine speed (automatic from DSM)
Control signal from governor, valve/gate position, etc.
Power angle (requires special instrumentation) if possibleuCalculated Values:
Real and Reactive Power (once per electrical cycle)
7/29/2019 Feltes 5
28/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Vee Curve Test Procedure (cont.)Vee Curve Test Procedure (cont.)uMeasurement Points
Based on unit reactive capability curve
Five MW levels (0, 25, 50, 75, 100%) Five MVAr levels at each MW level
Max (+,-) VARs that you are comfortable with
50% of maximum (+,-)
Unity power factor
Additional MW levels at any MVAr level
7/29/2019 Feltes 5
29/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Vee Curve Test Procedure (cont.)Vee Curve Test Procedure (cont.)uExample of
Measurement
Points (100 MVA,
0.85 PF Unit)
A
50
50
MVARS
ABSORBED
MVARS
SUPPLIED
REACTIVEPOWERINMVAR
10 50 85 MW 100
C
B
DUNDEREXCITATION REGION
SAFE OPERATION
POWER IN MW
OVEREXCITATION REGION
7/29/2019 Feltes 5
30/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Vee Curve Test Procedure (cont.)Vee Curve Test Procedure (cont.)uMeasurement
Points in
Tabular Form
T ical V Curve Measurement Points
500 MW Unit
MW MVAR
0 -250 -125 0 125 250
40 080 0
125 -250 -125 0 125 250
170 0
210 0
250 -200, -100, 0, 100, 200
290 0
330 0
375 -150, -75, 0, 75, 150
420 0
460 0
500 -100, 0, 100
7/29/2019 Feltes 5
31/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Vee Curve Coordination RequirementsVee Curve Coordination Requirements
uPlant Operators:
Need to go from zero to full load
Hydro and GT - easy Steam - involved process
Reverse-power relaying at zero load
Avoid levels of operating problems
Hydro - cavitation
Steam - control or auxiliary problems
GT - usually no problem areas
7/29/2019 Feltes 5
32/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Vee Curve Coordination RequirementsVee Curve Coordination Requirements
u System Operators:
Small Plant - usually easy
Large Plant: Requires coordination of dispatch changes with
output of other units
Adjustment of reactive output may affect
system voltages and require reactive powerredispatch (reactors, capacitors, scheduledvoltages on other units)
7/29/2019 Feltes 5
33/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure
uGoals:
Generator transient and subtransientreactances and field time constants
Turbine-generator inertia
Excitation system model parameters
Governor model parameters
7/29/2019 Feltes 5
34/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure
uProcedure:
Five partial load rejections Purpose: provide disturbance to excite unit
and determine dynamic response
Tests are designed to isolate parameters in
order to simplify analysis
7/29/2019 Feltes 5
35/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Load Rejection Coordination RequirementsLoad Rejection Coordination Requirements
uPlant Operators:
Need to go to desired loading (real and reactivepower)
Isolate generator from auxiliary loads
Will open main breaker to initiate test
Coordinate opening with measurement team
No operator adjustments until recording of testcompleted
Re-synchronization following test and preparation fornext test
7/29/2019 Feltes 5
36/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Load Rejection Coordination RequirementsLoad Rejection Coordination Requirements
u System Operators:
Inform system operator that test is imminent
System will see loss in real and/or reactive power
Change in frequency very small for systems withlarge generating capacity
Change in line flows or bus voltages may be
significant
Preventative dispatch or other operating changes?
7/29/2019 Feltes 5
37/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure
uTest #1 (Direct Axis Parameters)
0 MW
-30% MVAr
Excitation system in manual control
uUnderexcite unit so open circuit voltage
is lower than operating voltageuGenerator saturation minimized
7/29/2019 Feltes 5
38/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure
uTest #1 - typical terminal voltage plot:
1 2
1 4
1 6
1 8
2 0
2 2
2 4
2 6
0 5 1 0 1 5 2 0 2 5 3 0
T im e ( S e c o n d s )
TerminalVoltage(kV)
7/29/2019 Feltes 5
39/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test ProcedureuTest #2 (Excitation System Parameters)
0 MW -30% MVAR
Limit var absorption so that field voltage doesnot go below 50% of value at rated voltage, noload.
Excitation system in AVR control
uAVR parameters including limits
uAlternative: Step in AVR reference
7/29/2019 Feltes 5
40/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure
uTest #2 - typical terminal voltage plot:
2 4 . 4
2 4 . 6
2 4 . 8
25
2 5 . 2
2 5 . 4
2 5 . 6
0 2 4 6 8 1 0
T i m e ( S e c o n d s )
TerminalVoltage(kV)
7/29/2019 Feltes 5
41/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure
uTest #3 (Excitation system response inopposite direction) 0 MW +25% MVAR
Var load should not allow terminal voltage toexceed 8% overvoltage (use data from sat.)
Excitation system in AVR control
uAVR parameters including limits
7/29/2019 Feltes 5
42/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure
uTest #4 (Quadrature axis and governormodel parameters) 5% to 10% MW (typical) -5%to -15% MVAr (typical)
Set VARs so power angle matches powerfactor, resulting in all flux on quadrature axis
Excitation system in manual control
u Small signal governor response
7/29/2019 Feltes 5
43/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test ProcedureuTest #5 (Quadrature axis and governor
model parameters)
20% MW May use < 20% MW to limit overspeed
Use results of test #4 to estimate overspeed.
-5% to -15% MVAR (typical)
Set Vars so power angle matches power factor Excitation system in AVR control
uGovernor limit determination
7/29/2019 Feltes 5
44/61
Power Technologies, Inc.
Machine MeasurementsMachine Measurements
Partial Load Rejection Test ProcedurePartial Load Rejection Test ProcedureuTest #5 - typical speed (frequency) plot
150 MW Hydro , 40 MW rejection
5 9 . 8
6 0
6 0 . 2
6 0 . 4
6 0 . 6
6 0 . 8
6 1
6 1 . 2
6 1 . 4
6 1 . 6
6 1 . 8
0 1 0 2 0 3 0 4 0 5 0
T i m e ( S e c o n d s )
Speed(Hz)
3% Overspeed
7/29/2019 Feltes 5
45/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
uExcitationsystem step
test on anuclear unit
uPlot ofterminal
voltageversus time
Te
rminalVoltage
(kV)
TerminalVoltage
(kV)
Time (cycles)Time (cycles)
7/29/2019 Feltes 5
46/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Sameexcitationsystem step
test on anuclear unit
u Plot of fieldvoltage versus
time
Fiel
d
Fiel
d
Time (cycles)Time (cycles)
7/29/2019 Feltes 5
47/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Governorload rejectiontest.
u 650 MWsteam unit (70MW rejection)
u Plot ofgeneratorfrequencyversus time
Fre que n
c y
(Hz)
Fr e que nc y
(Hz
)
Time (cycles)Time (cycles)
7/29/2019 Feltes 5
48/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Samegovernor loadrejection test.
(650 MWsteam unit)
u Plot of controlvalve position
versus timeCon
t rol
Va l v
e
Pos it i o
n
(%)
Con
t rol
Va l v
e
Pos i t
ion
( %) Time (cycles)Time (cycles)
7/29/2019 Feltes 5
49/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Governor loadrejection test.
u 44 MVA hydrounit (4.8 MWrejection)
u Plot of generatorspeed deviationversus time
(measured andfrom simulationmodel)
Sp
ee
d
Spe
ed
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
50/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Same governorload rejectiontest. (44 MVA
hydro unit)u Plot of gate
position versus
time (measuredand from
simulationmodel)
Ga t e
s it ion
Ga t e
s i t
ion
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
51/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Governor loadrejection test.
u 45 MVA gasturbine unit (5.4MW rejection)
u Plot of generatorspeed deviationversus time
(measured andfrom simulationmodel)
Speed
Deviation
(pu)
Speed
Deviation
(pu)
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
52/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Same governorload rejectiontest. (45 MVAgas turbine)
u Plot of FSR (fuelcommandvoltage) versus
time (measured
and fromsimulationmodel)
FS
R
u)
FSR
u)
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
53/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Same governorload rejectiontest. (45 MVAgas turbine)
u Plot of exhausttemperature (oC)
versus time(measured and
from simulationmodel) E
x h
a us t
Te m
pe ra t ure
(
Ex h
a us t
Te mpe ra t ure
(
oC
))
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
54/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Governor loadrejection test.
u Same 45 MVAgas turbine unit
u 12.9 MW loadrejection
u Plot of generatorspeed deviation
versus time(measured andfrom simulationmodel)
Speed
Speed
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
55/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Same governorload rejection test.(45 MVA gasturbine - 12.9 MW
rejection)u Plot of FSR (fuel
commandvoltage) versustime (measured
and fromsimulation model)
FS
R
u)
FSR
u)
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
56/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Same governorload rejectiontest. (45 MVAgas turbine - 12.9MW rejection)
u Plot of exhausttemperature (oC)
versus time
(measured andfrom simulationmodel)
Ex h
a us t
Te m
pe ra t ure
(
Ex h
a us t
Te mpe ra t ure
(
oC
))
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
57/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Governor loadramp test.
u Same 45 MVAgas turbine unit
u Plot of generatorelectric powerversus time(measured and
from simulationmodel)
Electric
Electric
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
58/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Same governorload ramp test.
u 45 MVA gasturbine unit
u Plot of FSR (fuelcommandvoltage) versustime (measuredand fromsimulation model)
FS
R
u)
FSR
u)
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
59/61
Power Technologies, Inc.
Additional Examples of MeasurementsAdditional Examples of Measurements
u Same governorload ramp test.
u 45 MVA gasturbine unit
u Plot of exhausttemperature (oC)
versus time(measured and
from simulationmodel) E
x h
a us t
Te m
pe ra t ure
(
Ex h
a us t
Te mpe ra t ure
(
oC
))
Time (Seconds)Time (Seconds)
7/29/2019 Feltes 5
60/61
Power Technologies, Inc.
Next Step Model DerivationNext Step Model Derivation
uData processing
uModel derivation
- understanding of models and equipment- certain amount of trial and error
- experience helps
uComparison with test results
uTypically requires 1 -2 weeks per unit
7/29/2019 Feltes 5
61/61
Power Technologies, Inc.
Technology Transfer to UtilitiesTechnology Transfer to Utilities
uTraining of utility staff in testing andmodel derivation
PTIs experience is that testing is moreeasily learned than model derivation
Utility staff generally experienced in plantoperations and instrumentation
May be less experienced in controls andequipment modeling