Top Banner

of 61

Feltes 5

Apr 14, 2018

Download

Documents

santoshkumar
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/29/2019 Feltes 5

    1/61

    Power Technologies, Inc.

    Testing Methods: An OverviewTesting Methods: An Overview

    Machine Measurements

    James W. Feltes Power TechnologiesJohnny R. Willis Schenectady, NY

    Carlos Grande-Moran

  • 7/29/2019 Feltes 5

    2/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    u Introduction

    uTest Preparation

    uTest Procedures

  • 7/29/2019 Feltes 5

    3/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    IntroductionIntroductionuPurpose: More accurate models

    Generator

    Excitation System

    Turbine Governor

    uModel Parameters May Be Inaccurate

    Not typically verified by field tests

    Parameters may change (aging, tuning)

  • 7/29/2019 Feltes 5

    4/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Introduction (cont.)Introduction (cont.)

    uBenefit: Improved Stability Analysis

    Possible increase in power transfercapability

    Equally possible decrease in power transfercapability

    Increased accuracy in calculation oftransient and dynamic stability limits

  • 7/29/2019 Feltes 5

    5/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Introduction (cont.)Introduction (cont.)

    uAdvantages of PTI Test Procedure:

    Plant and generator protection remainsintact

    No interruption of CT signals

    Unit instantly available if needed

  • 7/29/2019 Feltes 5

    6/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Test PreparationTest PreparationuGather Information

    One-line diagram showing metering,protection, and supply to auxiliaries

    Generator and turbine nameplate data

    Manufacturers data

    Reactances and time constants Saturation curves and Vee curves

    Reactive capability curve

    Exciter and governor models, equipment info

  • 7/29/2019 Feltes 5

    7/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Test PreparationTest PreparationuGather Information (cont.)

    Plant data

    Hydro unit - physical description(measurements) of flow path (penstock, surgetank, tailrace)

    Steam unit - heat balance diagram

    All units - Allowed operating ranges (localcriteria or practices)

  • 7/29/2019 Feltes 5

    8/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Test Preparation (cont.)Test Preparation (cont.)u Select Signals

    Accessibility & Location

    Preconditioned? Transducers? Timedelay?

    Determine location of test equipment

    Wire signals to common terminal block Signal electrical isolation

  • 7/29/2019 Feltes 5

    9/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Test Preparation (cont.)Test Preparation (cont.)uVisit control room

    Note meter locations and signal ranges

    Determine feasibility of getting steady statedata from SCADA printouts on demand

    Determine method of communications

    between operator and test engineers

  • 7/29/2019 Feltes 5

    10/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Test Preparation (cont.)Test Preparation (cont.)uDetermine Test Sequence

    Open Circuit

    Vee Curves

    Partial Load Rejections

    uDetailed Step-by-Step Test Plan

  • 7/29/2019 Feltes 5

    11/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Test Preparation (cont.)Test Preparation (cont.)uDiscuss Test Procedure

    Plant Operators and Engineers

    Plant Informs System Dispatchers

    No operator adjustments during datarecording

    Tests typically require 1-2 days, includinginstrumentation setup

  • 7/29/2019 Feltes 5

    12/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Test EquipmentTest Equipment -- Dynamic System MonitorDynamic System Monitoru Recording of AC and DC signals

    u Phasor measurement and recording of AC signals

    u

    Captures low frequency dynamic phenomenau Can compute real & reactive power, phase angle,

    frequency, etc. in real time

    u Comprehensive data analysis and power system simulation

    capability through DADiSP and PSS/Eu Provides digital data allowing later comparison with

    derived simulation model performance

  • 7/29/2019 Feltes 5

    13/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    DSM System 200DSM System 200uPortable Version

  • 7/29/2019 Feltes 5

    14/61

    Power Technologies, Inc.

    Measurement EquipmentMeasurement Equipment

    uClamp-on CT

  • 7/29/2019 Feltes 5

    15/61

    Power Technologies, Inc.

    Measurement Equipment (cont.)Measurement Equipment (cont.)

    u Split Core CT

  • 7/29/2019 Feltes 5

    16/61

    Power Technologies, Inc.

    Measurement Equipment (cont.)Measurement Equipment (cont.)

    uPosition Transducer

  • 7/29/2019 Feltes 5

    17/61

    Power Technologies, Inc.

    Measurement Equipment (cont.)Measurement Equipment (cont.)

    uPosition Transducer on a Hydro Unit

  • 7/29/2019 Feltes 5

    18/61

    Power Technologies, Inc.

    Measurement Equipment (cont.)Measurement Equipment (cont.)

    uMagnetic Pick-up

  • 7/29/2019 Feltes 5

    19/61

    Power Technologies, Inc.

    Measurement Equipment (cont.)Measurement Equipment (cont.)

    uOptical Pick-up

  • 7/29/2019 Feltes 5

    20/61

    Power Technologies, Inc.

    Measurement Equipment (cont.)Measurement Equipment (cont.)

  • 7/29/2019 Feltes 5

    21/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Test ProceduresTest Procedures

    u Steady State Tests

    Open Circuit Tests Vee Curves (MW/MVAr variations)

    uDynamic Tests

    Partial Load Rejections

  • 7/29/2019 Feltes 5

    22/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Open Circuit Test ProcedureOpen Circuit Test Procedure

    uGoal: Generator Saturation Curve

    u

    Procedure: Unit at rated speed Main breaker open (unit off-line but at

    rated speed)

    Measure Efd and Ifd over range of Vt

  • 7/29/2019 Feltes 5

    23/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Open Circuit Test Procedure (cont.)Open Circuit Test Procedure (cont.)

    uTerminal voltage measurement range:

    30%, 40%, 50%, 60%, 70%, 75%, 80%, 85%,90%, 95%, 100%, 104%, 108% of rated.

    uTake backup readings (DVM, SCADA)when possible

    uMake sure generator is isolated fromauxiliary loads

  • 7/29/2019 Feltes 5

    24/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Open Circuit Test Coordination RequirementsOpen Circuit Test Coordination Requirements

    uPlant Operators:

    Need to be able to hold unit at rated speed,open circuit (no power)

    Hydro units - vibration, controls

    Steam units - turbine heating, controls

    Gas turbines - generally no problems

    Adjustment of terminal voltage

    AVR control range

    Switch to manual for lower voltages if needed

  • 7/29/2019 Feltes 5

    25/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Open Circuit Test Procedure (cont.)Open Circuit Test Procedure (cont.)

  • 7/29/2019 Feltes 5

    26/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Vee Curve Test ProcedureVee Curve Test Procedure

    uGoal: Steady State Reactances

    u

    Procedure: Main breaker closed (unit on-line)

    Take steady-state readings at various loadlevels (MW) and excitation levels (MVAr)

  • 7/29/2019 Feltes 5

    27/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Vee Curve Test Procedure (cont.)Vee Curve Test Procedure (cont.)uMeasured Values:

    Terminal voltages (from PTs)

    Armature currents (from CTs)

    Generator field voltage (direct) and current (from shunt)

    Exciter field voltage (direct)

    Turbine speed (automatic from DSM)

    Control signal from governor, valve/gate position, etc.

    Power angle (requires special instrumentation) if possibleuCalculated Values:

    Real and Reactive Power (once per electrical cycle)

  • 7/29/2019 Feltes 5

    28/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Vee Curve Test Procedure (cont.)Vee Curve Test Procedure (cont.)uMeasurement Points

    Based on unit reactive capability curve

    Five MW levels (0, 25, 50, 75, 100%) Five MVAr levels at each MW level

    Max (+,-) VARs that you are comfortable with

    50% of maximum (+,-)

    Unity power factor

    Additional MW levels at any MVAr level

  • 7/29/2019 Feltes 5

    29/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Vee Curve Test Procedure (cont.)Vee Curve Test Procedure (cont.)uExample of

    Measurement

    Points (100 MVA,

    0.85 PF Unit)

    A

    50

    50

    MVARS

    ABSORBED

    MVARS

    SUPPLIED

    REACTIVEPOWERINMVAR

    10 50 85 MW 100

    C

    B

    DUNDEREXCITATION REGION

    SAFE OPERATION

    POWER IN MW

    OVEREXCITATION REGION

  • 7/29/2019 Feltes 5

    30/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Vee Curve Test Procedure (cont.)Vee Curve Test Procedure (cont.)uMeasurement

    Points in

    Tabular Form

    T ical V Curve Measurement Points

    500 MW Unit

    MW MVAR

    0 -250 -125 0 125 250

    40 080 0

    125 -250 -125 0 125 250

    170 0

    210 0

    250 -200, -100, 0, 100, 200

    290 0

    330 0

    375 -150, -75, 0, 75, 150

    420 0

    460 0

    500 -100, 0, 100

  • 7/29/2019 Feltes 5

    31/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Vee Curve Coordination RequirementsVee Curve Coordination Requirements

    uPlant Operators:

    Need to go from zero to full load

    Hydro and GT - easy Steam - involved process

    Reverse-power relaying at zero load

    Avoid levels of operating problems

    Hydro - cavitation

    Steam - control or auxiliary problems

    GT - usually no problem areas

  • 7/29/2019 Feltes 5

    32/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Vee Curve Coordination RequirementsVee Curve Coordination Requirements

    u System Operators:

    Small Plant - usually easy

    Large Plant: Requires coordination of dispatch changes with

    output of other units

    Adjustment of reactive output may affect

    system voltages and require reactive powerredispatch (reactors, capacitors, scheduledvoltages on other units)

  • 7/29/2019 Feltes 5

    33/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure

    uGoals:

    Generator transient and subtransientreactances and field time constants

    Turbine-generator inertia

    Excitation system model parameters

    Governor model parameters

  • 7/29/2019 Feltes 5

    34/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure

    uProcedure:

    Five partial load rejections Purpose: provide disturbance to excite unit

    and determine dynamic response

    Tests are designed to isolate parameters in

    order to simplify analysis

  • 7/29/2019 Feltes 5

    35/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Load Rejection Coordination RequirementsLoad Rejection Coordination Requirements

    uPlant Operators:

    Need to go to desired loading (real and reactivepower)

    Isolate generator from auxiliary loads

    Will open main breaker to initiate test

    Coordinate opening with measurement team

    No operator adjustments until recording of testcompleted

    Re-synchronization following test and preparation fornext test

  • 7/29/2019 Feltes 5

    36/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Load Rejection Coordination RequirementsLoad Rejection Coordination Requirements

    u System Operators:

    Inform system operator that test is imminent

    System will see loss in real and/or reactive power

    Change in frequency very small for systems withlarge generating capacity

    Change in line flows or bus voltages may be

    significant

    Preventative dispatch or other operating changes?

  • 7/29/2019 Feltes 5

    37/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure

    uTest #1 (Direct Axis Parameters)

    0 MW

    -30% MVAr

    Excitation system in manual control

    uUnderexcite unit so open circuit voltage

    is lower than operating voltageuGenerator saturation minimized

  • 7/29/2019 Feltes 5

    38/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure

    uTest #1 - typical terminal voltage plot:

    1 2

    1 4

    1 6

    1 8

    2 0

    2 2

    2 4

    2 6

    0 5 1 0 1 5 2 0 2 5 3 0

    T im e ( S e c o n d s )

    TerminalVoltage(kV)

  • 7/29/2019 Feltes 5

    39/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test ProcedureuTest #2 (Excitation System Parameters)

    0 MW -30% MVAR

    Limit var absorption so that field voltage doesnot go below 50% of value at rated voltage, noload.

    Excitation system in AVR control

    uAVR parameters including limits

    uAlternative: Step in AVR reference

  • 7/29/2019 Feltes 5

    40/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure

    uTest #2 - typical terminal voltage plot:

    2 4 . 4

    2 4 . 6

    2 4 . 8

    25

    2 5 . 2

    2 5 . 4

    2 5 . 6

    0 2 4 6 8 1 0

    T i m e ( S e c o n d s )

    TerminalVoltage(kV)

  • 7/29/2019 Feltes 5

    41/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure

    uTest #3 (Excitation system response inopposite direction) 0 MW +25% MVAR

    Var load should not allow terminal voltage toexceed 8% overvoltage (use data from sat.)

    Excitation system in AVR control

    uAVR parameters including limits

  • 7/29/2019 Feltes 5

    42/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test Procedure

    uTest #4 (Quadrature axis and governormodel parameters) 5% to 10% MW (typical) -5%to -15% MVAr (typical)

    Set VARs so power angle matches powerfactor, resulting in all flux on quadrature axis

    Excitation system in manual control

    u Small signal governor response

  • 7/29/2019 Feltes 5

    43/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test ProcedureuTest #5 (Quadrature axis and governor

    model parameters)

    20% MW May use < 20% MW to limit overspeed

    Use results of test #4 to estimate overspeed.

    -5% to -15% MVAR (typical)

    Set Vars so power angle matches power factor Excitation system in AVR control

    uGovernor limit determination

  • 7/29/2019 Feltes 5

    44/61

    Power Technologies, Inc.

    Machine MeasurementsMachine Measurements

    Partial Load Rejection Test ProcedurePartial Load Rejection Test ProcedureuTest #5 - typical speed (frequency) plot

    150 MW Hydro , 40 MW rejection

    5 9 . 8

    6 0

    6 0 . 2

    6 0 . 4

    6 0 . 6

    6 0 . 8

    6 1

    6 1 . 2

    6 1 . 4

    6 1 . 6

    6 1 . 8

    0 1 0 2 0 3 0 4 0 5 0

    T i m e ( S e c o n d s )

    Speed(Hz)

    3% Overspeed

  • 7/29/2019 Feltes 5

    45/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    uExcitationsystem step

    test on anuclear unit

    uPlot ofterminal

    voltageversus time

    Te

    rminalVoltage

    (kV)

    TerminalVoltage

    (kV)

    Time (cycles)Time (cycles)

  • 7/29/2019 Feltes 5

    46/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Sameexcitationsystem step

    test on anuclear unit

    u Plot of fieldvoltage versus

    time

    Fiel

    d

    Fiel

    d

    Time (cycles)Time (cycles)

  • 7/29/2019 Feltes 5

    47/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Governorload rejectiontest.

    u 650 MWsteam unit (70MW rejection)

    u Plot ofgeneratorfrequencyversus time

    Fre que n

    c y

    (Hz)

    Fr e que nc y

    (Hz

    )

    Time (cycles)Time (cycles)

  • 7/29/2019 Feltes 5

    48/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Samegovernor loadrejection test.

    (650 MWsteam unit)

    u Plot of controlvalve position

    versus timeCon

    t rol

    Va l v

    e

    Pos it i o

    n

    (%)

    Con

    t rol

    Va l v

    e

    Pos i t

    ion

    ( %) Time (cycles)Time (cycles)

  • 7/29/2019 Feltes 5

    49/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Governor loadrejection test.

    u 44 MVA hydrounit (4.8 MWrejection)

    u Plot of generatorspeed deviationversus time

    (measured andfrom simulationmodel)

    Sp

    ee

    d

    Spe

    ed

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    50/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Same governorload rejectiontest. (44 MVA

    hydro unit)u Plot of gate

    position versus

    time (measuredand from

    simulationmodel)

    Ga t e

    s it ion

    Ga t e

    s i t

    ion

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    51/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Governor loadrejection test.

    u 45 MVA gasturbine unit (5.4MW rejection)

    u Plot of generatorspeed deviationversus time

    (measured andfrom simulationmodel)

    Speed

    Deviation

    (pu)

    Speed

    Deviation

    (pu)

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    52/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Same governorload rejectiontest. (45 MVAgas turbine)

    u Plot of FSR (fuelcommandvoltage) versus

    time (measured

    and fromsimulationmodel)

    FS

    R

    u)

    FSR

    u)

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    53/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Same governorload rejectiontest. (45 MVAgas turbine)

    u Plot of exhausttemperature (oC)

    versus time(measured and

    from simulationmodel) E

    x h

    a us t

    Te m

    pe ra t ure

    (

    Ex h

    a us t

    Te mpe ra t ure

    (

    oC

    ))

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    54/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Governor loadrejection test.

    u Same 45 MVAgas turbine unit

    u 12.9 MW loadrejection

    u Plot of generatorspeed deviation

    versus time(measured andfrom simulationmodel)

    Speed

    Speed

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    55/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Same governorload rejection test.(45 MVA gasturbine - 12.9 MW

    rejection)u Plot of FSR (fuel

    commandvoltage) versustime (measured

    and fromsimulation model)

    FS

    R

    u)

    FSR

    u)

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    56/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Same governorload rejectiontest. (45 MVAgas turbine - 12.9MW rejection)

    u Plot of exhausttemperature (oC)

    versus time

    (measured andfrom simulationmodel)

    Ex h

    a us t

    Te m

    pe ra t ure

    (

    Ex h

    a us t

    Te mpe ra t ure

    (

    oC

    ))

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    57/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Governor loadramp test.

    u Same 45 MVAgas turbine unit

    u Plot of generatorelectric powerversus time(measured and

    from simulationmodel)

    Electric

    Electric

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    58/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Same governorload ramp test.

    u 45 MVA gasturbine unit

    u Plot of FSR (fuelcommandvoltage) versustime (measuredand fromsimulation model)

    FS

    R

    u)

    FSR

    u)

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    59/61

    Power Technologies, Inc.

    Additional Examples of MeasurementsAdditional Examples of Measurements

    u Same governorload ramp test.

    u 45 MVA gasturbine unit

    u Plot of exhausttemperature (oC)

    versus time(measured and

    from simulationmodel) E

    x h

    a us t

    Te m

    pe ra t ure

    (

    Ex h

    a us t

    Te mpe ra t ure

    (

    oC

    ))

    Time (Seconds)Time (Seconds)

  • 7/29/2019 Feltes 5

    60/61

    Power Technologies, Inc.

    Next Step Model DerivationNext Step Model Derivation

    uData processing

    uModel derivation

    - understanding of models and equipment- certain amount of trial and error

    - experience helps

    uComparison with test results

    uTypically requires 1 -2 weeks per unit

  • 7/29/2019 Feltes 5

    61/61

    Power Technologies, Inc.

    Technology Transfer to UtilitiesTechnology Transfer to Utilities

    uTraining of utility staff in testing andmodel derivation

    PTIs experience is that testing is moreeasily learned than model derivation

    Utility staff generally experienced in plantoperations and instrumentation

    May be less experienced in controls andequipment modeling