FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION
FEDERAL SPACE AGENCY OF RUSSIAN FEDERATION LAVOCHKIN ASSOCIATION. Moscow Solar System Symposium. " PHOBOS-GRUNT " PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT. M . Martynov Deputy General Designer. IKI , 13 October 2010. - PowerPoint PPT Presentation
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
FEDERAL SPACE AGENCY OF RUSSIAN FEDERATIONLAVOCHKIN ASSOCIATION
""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT
IKI, 13 October 2010
M. MartynovDeputy General Designer
Moscow Solar System Symposium
"PHOBOS-GROUNT" MAIN MISSION PARAMETERS
• Investigation of Phobos's substance delivered to the earth in laboratory conditions;
• Investigation of Phobos and Mars;• Realisation of joint researches with the
Chinese microsatellite
Launch site Baikonur
Launch date November 2011
Launch vehicle "Zenit-2"
Earth-Mars flight duration 10 – 11.5 months
Lift-off from Phobos February – March 2013
Mars-Earth flight duration 10.5 – 11.5 months
Date of arrival to the Earth August 2014
Total mission duration ~ 33-34 months
Mass of scientific equipment 50 kg
Mass of Phobos soil samples 0.2 kg
""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT
MISSION PROFILE
""PHOBOS-GRUNTPHOBOS-GRUNT"" PROJECT PROJECT MISSION CONCEPT & CURRENT STATUS OF DEVELOPMENTMISSION CONCEPT & CURRENT STATUS OF DEVELOPMENT