Site Fencing Managed / Secured Vehicle Gate Pedestrian Access Construction Traffic Movement Site Welfare and Accommodation Materials Storage Area Waste Separation & Recycling Demolition Construction of Building Scaffold Hoist Site Traffic / Plant Hardstandings Site Gate Manned by Banksmen Key / Legend Notes • To be read in conjunction with Master Programme FEBRUARY (1) – Groundworks & Substructure PROJECT: Dover Court, Blocks D, E & G Date: Drawn By: 7 Site Fencing Managed / Secured Vehicle Gate Pedestrian Access Construction Traffic Movement Site Welfare and Accommodation Materials Storage Area Waste Separation & Recycling Demolition Construction of Building Scaffold Hoist Site Traffic / Plant Hardstandings Site Gate Manned by Banksmen Temporary Safe Escape Route November 2018 Robert Rundle To be read in conjunction with Contract Programme (PH2 CP00001) dated 07 November 2018 Spaces Required by Residents Spaces Suspended Spaces Available 25 53 34 Site Fencing Managed / Secured Vehicle Gate Operative Access Construction Traffic Movement Site Welfare and Accommodation Materials / Plant Storage Area Waste Separation & Recycling Demolition Construction of Building Scaffold Hoist Site Traffic / Plant Hardstandings Site Gate Manned by Banksmen Temporary Safe Escape Route Temporary Bin Store