Mat'l Labor Total QTY Percentage QTY Percentage QTY Percentage CARRIER DUCTED TYPE 40RM012/38HDS012 2 sets 355,950.00 711,900.00 Php 711,900.00 Php 5.9325% 2 5.6359% 2 0.0000% 2 5.6359% CARRIER WINDOW TYPE WCARP24ED 9 units 31,200.00 280,800.00 280,800.00 2.3400% 9 2.2230% 9 0.0000% 9 2.2230% MITSUBISHI ELECTRIC (SPLIT-TYPE) PK-4FAKLD/ PU-4TJSA.TH 6 sets 102,680.00 616,080.00 616,080.00 5.1340% 6 4.8773% 6 0.0000% 6 4.8773% PC-4GAKD/ PU-4TJSA.TH 2 sets 98,600.00 197,200.00 197,200.00 1.6433% 2 1.5612% 2 0.0000% 2 1.5612% MITSUBISHI ELECTRIC (ACCESSORIES) CMY-Y62-G-E 179 units 7,500.00 1,342,500.00 1,342,500.00 11.1875% 179 10.6281% 179 0.0000% 179 10.6281% BONDS Downpayment Bond 40,067.32 40,067.32 40,067.32 0.3339% 0.3339% 0.3339% Performance Bond 45,778.02 45,778.02 45,778.02 0.3815% 0.3815% 0.3815% Guarantee Bond 20,487.83 20,487.83 20,487.83 0.1707% 0.1707% 0.0000% 0.1707% CARI 58,813.50 58,813.50 58,813.50 0.4901% 0.4901% 0.4901% SUB - TOTAL ( I ) 3,313,626.67 Php 3,313,626.67 Php 27.6136% 26.3017% 0.0000% 26.3017% Descri tion QTY UNIT Amount %Wei ht Mat'l Labor Total QTY Percentage QTY Percentage QTY Percentage Mobilization / Demobilization 1 lot 60,000.00 60,000.00 60,000.00  0.5000% 0.212% 0 0.0000% 0.2121% Temporary Facilities 1 lot 30,000.00 10,000.00 40,000.00 40,000.00  0.3333% 0.141% 0.0000% 0.1414% Representation 1 lot 30,000.00 30,000.00 30,000.00  0.2500% 0.106% 0.0000% 0.1061% Submittals / Shop Drawings 1 lot 70,000.00 70,000.00 70,000.00  0.5833% 0.247% 0.0000% 0.2475% As Built Plans 1 lot 75,000.00 75,000.00 75,000.00  0.6250% 0.265% 0.0000% 0.2652% Utilities (Water / Electricity & Housekeeping) 1 lot 15,000.00 5,000.00 20,000.00 20,000.00  0.1667% 0.071% 0.0000% 0.0707% Testing Commissioning (Labor) 1 lot 70,000.00 70,000.00 70,000.00  0.5833% 0.247% 0.0000% 0.2475% Overhead & Contingecies 1 lot 427,204.45 427,204.45 427,204.45  3.5600% 1.297% 0.0000% 0.6070% SUB - TOTAL ( II ) 792,204.45 Php 792,204.45 Php 6.6017% 2.5871% 0.0000% 1.8974% Mat'l Labor Total QTY Percentage QTY Percentage QTY Percentage 6TH FLOOR Copper Tube 5/8" 340 ft 261.00 88,740.00 88,740.00 0.7395% 340 0.7395% 0 0.0000% 340 0.7395% Copper Tube 1/2" 190 ft 188.40 35,796.00 35,796.00 0.2983% 190 0.2983% 0 0.0000% 190 0.2983% Copper Tube 3/8" 340 ft 109.00 37,060.00 37,060.00 0.3088% 340 0.3088% 0 0.0000% 340 0.3088% Copper Tube 1/4" 190 ft 116.75 22,182.50 22,182.50 0.1849% 190 0.1849% 0 0.0000% 190 0.1849% Copper Elbow 5/8" 48 pcs 93.00 4,464.00 4,464.00 0.0372% 48 0.0372% 0 0.0000% 48 0.0372% Copper Elbow 1/2" 24 pcs 71.64 1,719.36 1,719.36 0.0143% 24 0.0143% 0 0.0000% 24 0.0143% Copper Elbow 3/8" 48 pcs 66.50 3,192.00 3,192.00 0.0266% 48 0.0266% 0 0.0000% 48 0.0266% Copper Elbow 1/4" 24 pcs 62.00 1,488.00 1,488.00 0.0124% 24 0.0124% 0 0.0000% 24 0.0124% Copper Coupling 5/8" 34 pcs 66.50 2,261.00 2,261.00 0.0188% 34 0.0188% 0 0.0000% 34 0.0188% Copper Coupling 1/2" 19 pcs 55.00 1,045.00 1,045.00 0.0087% 19 0.0087% 0 0.0000% 19 0.0087% Copper Coupling 3/8" 34 pcs 55.00 1,870.00 1,870.00 0.0156% 34 0.0156% 0 0.0000% 34 0.0156% Rubber Insulation 5/8" x 1' Thickness 57 L/6 711.13 40,534.41 40,534.41 0.3378% 57 0.3378% 0 0.0000% 57 0.3378% Rubber Insulation 1/2" x 1' Thickness 32 L/6 660.71 21,142.72 21,142.72 0.1762% 32 0.1762% 0 0.0000% 32 0.1762% Rubber Insulation 3/8" x 1' Thickness 57 L/6 581.11 33,123.27 33,123.27 0.2760% 57 0.2760% 0 0.0000% 57 0.2760% Rubber Insulation 1/4" x 3/4' Thickness 32 L/6 323.72 10,359.04 10,359.04 0.0863% 32 0.0863% 0 0.0000% 32 0.0863% EMT Pipe 1/2" 53 L/10 399.00 21,147.00 21,147.00 0.1762% 53 0.1762% 0 0.0000% 53 0.1762% EMT Elbow 1/2" 48 pcs 66.34 3,184.32 3,184.32 0.0265% 48 0.0265% 0 0.0000% 48 0.0265% EMT Coupling 1/2" 150 pcs 39.80 5,970.00 5,970.00 0.0498% 150 0.0498% 0 0.0000% 150 0.0498% G.I. Wire # 16 10 Kgs 172.48 1,724.80 1,724.80 0.0144% 10 0.0144% 0 0.0000% 10 0.0144% Tox With Metal screw #8 80 pcs 14.00 1,120.00 1,120.00 0.0093% 80 0.0093% 0 0.0000% 80 0.0093% Fullthread 3/8" 14 L/10 317.49 4,444.86 4,444.86 0.0370% 14 0.0370% 0 0.0000% 14 0.0370% Nuts 3/8" 70 pcs 5.50 385.00 385.00 0.0032% 70 0.0032% 0 0.0000% 70 0.0032% Washer 3/8" 70 pcs 5.50 385.00 385.00 0.0032% 70 0.0032% 0 0.0000% 70 0.0032%  Anchor Grip 3/8" 70 pcs 39.80 2,786.00 2,786.00 0.0232% 70 0.0232% 0 0.0000% 70 0.0232% Flat Bar 1/8" x 1" 4 pcs 400.00 1,600.00 1,600.00 0.0133% 4 0.0133% 0 0.0000% 4 0.0133% Paint 1 Lot 400.00 400.00 400.00 0.0033% 1 0.0033% 0 0.0000% 1 0.0033%  Access Valve 16 pcs 119.50 1,912.00 1,912.00 0.0159% 16 0.0159% 0 0.0000% 16 0.0159% Nitrogen 2 cyl 1,460.00 2,920.00 2,920.00 0.0243% 2 0.0243% 0 0.0000% 2 0.0243% Silver Rod 80 pcs 40.00 3,200.00 3,200.00 0.0267% 80 0.0267% 0 0.0000% 80 0.0267% Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.0232% 1 0.0232% 0 0.0000% 1 0.0232% Hacksaw Blade 2 pcs 172.48 344.96 344.96 0.0029% 2 0.0029% 0 0.0000% 2 0.0029% Junction Box 24 pcs 66.50 1,596.00 1,596.00 0.0133% 24 0.0133% 0 0.0000% 24 0.0133% II GENERAL REQUIREMENTS Itemized Cost Breakdown February 22, 2012 - March 20, 2013 % Weight Description 1 % Weight UNIT 1 Unit Cost Amount THE ADDRESS - Wack Wack Mandaluyong City CP-08A Supply and Delivery of A/C Equipment (Common Areas) & Installation of Piping Works for Residential Areas I EQUIPMENT Previous Accomplishment III INSTALLATION To Date 1 Present Accomplishment 1 lot Description QTY UNIT Unit Cost Unit Cost Amount QTY 25-Feb-13 Previous Accomplishment Present Accomplishment To Date To Date Previous Accomplishment Present Accomplishment
12

feb-march BOQ II (1)222222222222222222.xls

Apr 14, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 1/12

Mat'l Labor Total

CARRIER DUCTED TYPE

40RM012/38HDS012 2 sets 355,950.00 711,900.00Php 711,900.00Php 5.9325

CARRIER WINDOW TYPE

WCARP24ED 9 units 31,200.00 280,800.00 280,800.00 2.3400

MITSUBISHI ELECTRIC

(SPLIT-TYPE)

PK-4FAKLD/ PU-4TJSA.TH 6 sets 102,680.00 616,080.00 616,080.00 5.1340

PC-4GAKD/ PU-4TJSA.TH 2 sets 98,600.00 197,200.00 197,200.00 1.6433

MITSUBISHI ELECTRIC

(ACCESSORIES)

CMY-Y62-G-E 179 units 7,500.00 1,342,500.00 1,342,500.00 11.1875

BONDS

Downpayment Bond 40,067.32 40,067.32 40,067.32 0.3339

Performance Bond 45,778.02 45,778.02 45,778.02 0.3815

Guarantee Bond 20,487.83 20,487.83 20,487.83 0.1707

CARI 58,813.50 58,813.50 58,813.50 0.490

SUB - TOTAL ( I ) 3,313,626.67Php 3,313,626.67Php 27.6136

Descri tion QTY UNIT Amount % Wei htMat'l Labor Total

Mobilization / Demobilization 1 lot60,000.00 60,000.00 60,000.00  0.5000

Temporary Facilities 1 lot 30,000.00 10,000.00 40,000.00 40,000.00  0.3333

Representation 1 lot 30,000.00 30,000.00 30,000.00  0.2500

Submittals / Shop Drawings 1 lot70,000.00 70,000.00 70,000.00  0.5833

As Built Plans 1 lot 75,000.00 75,000.00 75,000.00  0.6250

Utilities (Water / Electricity &

Housekeeping)1 lot

15,000.00 5,000.00 20,000.00 20,000.00  0.1667

Testing Commissioning (Labor) 1 lot70,000.00 70,000.00 70,000.00  0.5833

Overhead & Contingecies 1 lot 427,204.45 427,204.45 427,204.45  3.5600

SUB - TOTAL ( II ) 792,204.45Php 792,204.45Php 6.6017

Mat'l Labor Total

6TH FLOOR

Copper Tube 5/8" 340 ft 261.00 88,740.00 88,740.00 0.7395

Copper Tube 1/2" 190 ft 188.40 35,796.00 35,796.00 0.2983

Copper Tube 3/8" 340 ft 109.00 37,060.00 37,060.00 0.3088

Copper Tube 1/4" 190 ft 116.75 22,182.50 22,182.50 0.1849

Copper Elbow 5/8" 48 pcs 93.00 4,464.00 4,464.00 0.0372

Copper Elbow 1/2" 24 pcs 71.64 1,719.36 1,719.36 0.0143

Copper Elbow 3/8" 48 pcs 66.50 3,192.00 3,192.00 0.0266

Copper Elbow 1/4" 24 pcs 62.00 1,488.00 1,488.00 0.0124

Copper Coupling 5/8" 34 pcs 66.50 2,261.00 2,261.00 0.0188

Copper Coupling 1/2" 19 pcs 55.00 1,045.00 1,045.00 0.0087Copper Coupling 3/8" 34 pcs 55.00 1,870.00 1,870.00 0.0156

Rubber Insulation 5/8" x 1' Thickness 57 L/6 711.13 40,534.41 40,534.41 0.3378

Rubber Insulation 1/2" x 1' Thickness 32 L/6 660.71 21,142.72 21,142.72 0.1762

Rubber Insulation 3/8" x 1' Thickness 57 L/6 581.11 33,123.27 33,123.27 0.2760

Rubber Insulation 1/4" x 3/4' Thickness 32 L/6 323.72 10,359.04 10,359.04 0.0863

EMT Pipe 1/2" 53 L/10 399.00 21,147.00 21,147.00 0.1762

EMT Elbow 1/2" 48 pcs 66.34 3,184.32 3,184.32 0.0265

EMT Coupling 1/2" 150 pcs 39.80 5,970.00 5,970.00 0.0498

G.I. Wire # 16 10 Kgs 172.48 1,724.80 1,724.80 0.0144

Tox With Metal screw #8 80 pcs 14.00 1,120.00 1,120.00 0.0093

Fullthread 3/8" 14 L/10 317.49 4,444.86 4,444.86 0.0370

Nuts 3/8" 70 pcs 5.50 385.00 385.00 0.0032

Washer 3/8" 70 pcs 5.50 385.00 385.00 0.0032

 Anchor Grip 3/8" 70 pcs 39.80 2,786.00 2,786.00 0.0232

Flat Bar 1/8" x 1" 4 pcs 400.00 1,600.00 1,600.00 0.0133Paint 1 Lot 400.00 400.00 400.00 0.0033

 Access Valve 16 pcs 119.50 1,912.00 1,912.00 0.0159

Nitrogen 2 cyl 1,460.00 2,920.00 2,920.00 0.0243

Silver Rod 80 pcs 40.00 3,200.00 3,200.00 0.0267

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.0232

Hacksaw Blade 2 pcs 172.48 344.96 344.96 0.0029

Junction Box 24 pcs 66.50 1,596.00 1,596.00 0.0133

II GENERAL REQUIREMENTS

Itemized Cost Breakdown

February 22, 2012 - March 20, 2013

% WeightDescription

% Weight

UNIT

Unit Cost

Amount

THE ADDRESS - Wack Wack Mandaluyong City

CP-08A Supply and Delivery of A/C Equipment (Common Areas) & Installation of Pi

I EQUIPMENT

III INSTALLATION

1 lot

Description QTY UNITUnit Cost

Unit CostAmountQTY

Page 2: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 2/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

Polyethelene Tape 18 rolls 133.00 2,394.00 2,394.00 0.020

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 67,895.98 67,895.98 67,895.98 0.565

431,347.20 PhP 431,347.20 PhP 3.594

7TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

8TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

9TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

SUBTOTAL

SUBTOTAL

SUBTOTAL

Page 3: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 3/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

10TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

11TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

SUBTOTAL

SUBTOTAL

Page 4: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 4/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

12TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

14TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

SUBTOTAL

SUBTOTAL

Page 5: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 5/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

15TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

16TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

17TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

SUBTOTAL

SUBTOTAL

SUBTOTAL

Page 6: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 6/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

18TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

19TH FLOOR

Copper Tube 5/8" 220 ft 261.00 57,420.00 57,420.00 0.478

Copper Tube 1/2" 95 ft 188.40 17,898.00 17,898.00 0.149

Copper Tube 3/8" 220 ft 109.00 23,980.00 23,980.00 0.199

Copper Tube 1/4" 95 ft 116.75 11,091.25 11,091.25 0.092

Copper Elbow 5/8" 21 pcs 93.00 1,953.00 1,953.00 0.016

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 16 L/6 660.71 10,571.36 10,571.36 0.088

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 16 L/6 323.72 5,179.52 5,179.52 0.043

EMT Pipe 1/2" 32 L/10 399.00 12,768.00 12,768.00 0.106

EMT Elbow 1/2" 36 pcs 66.34 2,388.24 2,388.24 0.019

EMT Coupling 1/2" 104 pcs 39.80 4,139.20 4,139.20 0.034

SUBTOTAL

SUBTOTAL

Page 7: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 7/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

272,883.25 PhP 272,883.25 PhP 2.274

20TH FLOOR

Copper Tube 5/8" 214 ft 261.00 55,854.00 55,854.00 0.465

Copper Tube 1/2" 80 ft 188.40 15,072.00 15,072.00 0.125

Copper Tube 3/8" 214 ft 109.00 23,326.00 23,326.00 0.194

Copper Tube 1/4" 80 ft 116.75 9,340.00 9,340.00 0.077

Copper Elbow 5/8" 30 pcs 93.00 2,790.00 2,790.00 0.023

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 30 pcs 66.50 1,995.00 1,995.00 0.016

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Coupling 1/2" 8 pcs 55.00 440.00 440.00 0.003

Copper Coupling 3/8" 21 pcs 55.00 1,155.00 1,155.00 0.009

Rubber Insulation 5/8" x 1' Thickness 36 L/6 711.13 25,600.68 25,600.68 0.213

Rubber Insulation 1/2" x 1' Thickness 14 L/6 660.71 9,249.94 9,249.94 0.077

Rubber Insulation 3/8" x 1' Thickness 36 L/6 581.11 20,919.96 20,919.96 0.174

Rubber Insulation 1/4" x 3/4' Thickness 14 L/6 323.72 4,532.08 4,532.08 0.037

EMT Pipe 1/2" 30 L/10 399.00 11,970.00 11,970.00 0.099

EMT Elbow 1/2" 51 pcs 66.34 3,383.34 3,383.34 0.028

EMT Coupling 1/2" 132 pcs 39.80 5,253.60 5,253.60 0.043

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 7 pcs 119.50 836.50 836.50 0.007

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

264,558.90 PhP 264,558.90 PhP 2.204

21ST FLOOR

Copper Tube 5/8" 214 ft 261.00 55,854.00 55,854.00 0.465

Copper Tube 1/2" 80 ft 188.40 15,072.00 15,072.00 0.125

Copper Tube 3/8" 214 ft 109.00 23,326.00 23,326.00 0.194

Copper Tube 1/4" 80 ft 116.75 9,340.00 9,340.00 0.077

Copper Elbow 5/8" 30 pcs 93.00 2,790.00 2,790.00 0.023

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 30 pcs 66.50 1,995.00 1,995.00 0.016

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Coupling 1/2" 8 pcs 55.00 440.00 440.00 0.003

Copper Coupling 3/8" 21 pcs 55.00 1,155.00 1,155.00 0.009

Rubber Insulation 5/8" x 1' Thickness 36 L/6 711.13 25,600.68 25,600.68 0.213

Rubber Insulation 1/2" x 1' Thickness 14 L/6 660.71 9,249.94 9,249.94 0.077

Rubber Insulation 3/8" x 1' Thickness 36 L/6 581.11 20,919.96 20,919.96 0.174

Rubber Insulation 1/4" x 3/4' Thickness 14 L/6 323.72 4,532.08 4,532.08 0.037

EMT Pipe 1/2" 30 L/10 399.00 11,970.00 11,970.00 0.099

EMT Elbow 1/2" 51 pcs 66.34 3,383.34 3,383.34 0.028

EMT Coupling 1/2" 132 pcs 39.80 5,253.60 5,253.60 0.043

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 7 pcs 119.50 836.50 836.50 0.007

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

SUBTOTAL

SUBTOTAL

Page 8: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 8/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

264,558.90 PhP 264,558.90 PhP 2.204

22ND FLOOR

Copper Tube 5/8" 214 ft 261.00 55,854.00 55,854.00 0.465

Copper Tube 1/2" 80 ft 188.40 15,072.00 15,072.00 0.125

Copper Tube 3/8" 214 ft 109.00 23,326.00 23,326.00 0.194

Copper Tube 1/4" 80 ft 116.75 9,340.00 9,340.00 0.077

Copper Elbow 5/8" 30 pcs 93.00 2,790.00 2,790.00 0.023

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 30 pcs 66.50 1,995.00 1,995.00 0.016

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Coupling 1/2" 8 pcs 55.00 440.00 440.00 0.003

Copper Coupling 3/8" 21 pcs 55.00 1,155.00 1,155.00 0.009

Rubber Insulation 5/8" x 1' Thickness 36 L/6 711.13 25,600.68 25,600.68 0.213

Rubber Insulation 1/2" x 1' Thickness 14 L/6 660.71 9,249.94 9,249.94 0.077

Rubber Insulation 3/8" x 1' Thickness 36 L/6 581.11 20,919.96 20,919.96 0.174

Rubber Insulation 1/4" x 3/4' Thickness 14 L/6 323.72 4,532.08 4,532.08 0.037

EMT Pipe 1/2" 30 L/10 399.00 11,970.00 11,970.00 0.099

EMT Elbow 1/2" 51 pcs 66.34 3,383.34 3,383.34 0.028

EMT Coupling 1/2" 132 pcs 39.80 5,253.60 5,253.60 0.043

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 7 pcs 119.50 836.50 836.50 0.007

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

264,558.90 PhP 264,558.90 PhP 2.204

23RD FLOOR

Copper Tube 5/8" 214 ft 261.00 55,854.00 55,854.00 0.465

Copper Tube 1/2" 80 ft 188.40 15,072.00 15,072.00 0.125

Copper Tube 3/8" 214 ft 109.00 23,326.00 23,326.00 0.194

Copper Tube 1/4" 80 ft 116.75 9,340.00 9,340.00 0.077

Copper Elbow 5/8" 30 pcs 93.00 2,790.00 2,790.00 0.023

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 30 pcs 66.50 1,995.00 1,995.00 0.016

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Coupling 1/2" 8 pcs 55.00 440.00 440.00 0.003

Copper Coupling 3/8" 21 pcs 55.00 1,155.00 1,155.00 0.009

Rubber Insulation 5/8" x 1' Thickness 36 L/6 711.13 25,600.68 25,600.68 0.213

Rubber Insulation 1/2" x 1' Thickness 14 L/6 660.71 9,249.94 9,249.94 0.077

Rubber Insulation 3/8" x 1' Thickness 36 L/6 581.11 20,919.96 20,919.96 0.174

Rubber Insulation 1/4" x 3/4' Thickness 14 L/6 323.72 4,532.08 4,532.08 0.037

EMT Pipe 1/2" 30 L/10 399.00 11,970.00 11,970.00 0.099

EMT Elbow 1/2" 51 pcs 66.34 3,383.34 3,383.34 0.028

EMT Coupling 1/2" 132 pcs 39.80 5,253.60 5,253.60 0.043

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 7 pcs 119.50 836.50 836.50 0.007

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

264,558.90 PhP 264,558.90 PhP 2.204

24TH FLOOR

Copper Tube 5/8" 214 ft 261.00 55,854.00 55,854.00 0.465

Copper Tube 1/2" 80 ft 188.40 15,072.00 15,072.00 0.125

Copper Tube 3/8" 214 ft 109.00 23,326.00 23,326.00 0.194

Copper Tube 1/4" 80 ft 116.75 9,340.00 9,340.00 0.077

Copper Elbow 5/8" 30 pcs 93.00 2,790.00 2,790.00 0.023

SUBTOTAL

SUBTOTAL

SUBTOTAL

Page 9: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 9/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 30 pcs 66.50 1,995.00 1,995.00 0.016

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 21 pcs 66.50 1,396.50 1,396.50 0.011

Copper Coupling 1/2" 8 pcs 55.00 440.00 440.00 0.003

Copper Coupling 3/8" 21 pcs 55.00 1,155.00 1,155.00 0.009

Rubber Insulation 5/8" x 1' Thickness 36 L/6 711.13 25,600.68 25,600.68 0.213

Rubber Insulation 1/2" x 1' Thickness 14 L/6 660.71 9,249.94 9,249.94 0.077

Rubber Insulation 3/8" x 1' Thickness 36 L/6 581.11 20,919.96 20,919.96 0.174

Rubber Insulation 1/4" x 3/4' Thickness 14 L/6 323.72 4,532.08 4,532.08 0.037

EMT Pipe 1/2" 30 L/10 399.00 11,970.00 11,970.00 0.099

EMT Elbow 1/2" 51 pcs 66.34 3,383.34 3,383.34 0.028

EMT Coupling 1/2" 132 pcs 39.80 5,253.60 5,253.60 0.043

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 7 pcs 119.50 836.50 836.50 0.007

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

264,558.90 PhP 264,558.90 PhP 2.204

25TH FLOOR

Copper Tube 5/8" 260 ft 261.00 67,860.00 67,860.00 0.565

Copper Tube 1/2" 85 ft 188.40 16,014.00 16,014.00 0.133

Copper Tube 3/8" 260 ft 109.00 28,340.00 28,340.00 0.236

Copper Tube 1/4" 85 ft 116.75 9,923.75 9,923.75 0.082

Copper Elbow 5/8" 36 pcs 93.00 3,348.00 3,348.00 0.027

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 36 pcs 66.50 2,394.00 2,394.00 0.020

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 26 pcs 66.50 1,729.00 1,729.00 0.014

Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 26 pcs 55.00 1,430.00 1,430.00 0.011

Rubber Insulation 5/8" x 1' Thickness 44 L/6 711.13 31,289.72 31,289.72 0.260

Rubber Insulation 1/2" x 1' Thickness 15 L/6 660.71 9,910.65 9,910.65 0.082

Rubber Insulation 3/8" x 1' Thickness 44 L/6 581.11 25,568.84 25,568.84 0.213

Rubber Insulation 1/4" x 3/4' Thickness 15 L/6 323.72 4,855.80 4,855.80 0.040

EMT Pipe 1/2" 35 L/10 399.00 13,965.00 13,965.00 0.116

EMT Elbow 1/2" 51 pcs 66.34 3,383.34 3,383.34 0.028

EMT Coupling 1/2" 137 pcs 39.80 5,452.60 5,452.60 0.045

G.I. Wire # 16 6 Kgs 172.48 1,034.88 1,034.88 0.008

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 12 rolls 133.00 1,596.00 1,596.00 0.013

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

299,515.48 PhP 299,515.48 PhP 2.496

26TH FLOOR

Copper Tube 5/8" 260 ft 261.00 67,860.00 67,860.00 0.565

Copper Tube 1/2" 85 ft 188.40 16,014.00 16,014.00 0.133

Copper Tube 3/8" 260 ft 109.00 28,340.00 28,340.00 0.236

Copper Tube 1/4" 85 ft 116.75 9,923.75 9,923.75 0.082

Copper Elbow 5/8" 36 pcs 93.00 3,348.00 3,348.00 0.027

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 36 pcs 66.50 2,394.00 2,394.00 0.020

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 26 pcs 66.50 1,729.00 1,729.00 0.014Copper Coupling 1/2" 9 pcs 55.00 495.00 495.00 0.004

Copper Coupling 3/8" 26 pcs 55.00 1,430.00 1,430.00 0.011

Rubber Insulation 5/8" x 1' Thickness 44 L/6 711.13 31,289.72 31,289.72 0.260

Rubber Insulation 1/2" x 1' Thickness 15 L/6 660.71 9,910.65 9,910.65 0.082

Rubber Insulation 3/8" x 1' Thickness 44 L/6 581.11 25,568.84 25,568.84 0.213

Rubber Insulation 1/4" x 3/4' Thickness 15 L/6 323.72 4,855.80 4,855.80 0.040

EMT Pipe 1/2" 35 L/10 399.00 13,965.00 13,965.00 0.116

EMT Elbow 1/2" 51 pcs 66.34 3,383.34 3,383.34 0.028

SUBTOTAL

SUBTOTAL

Page 10: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 10/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

EMT Coupling 1/2" 137 pcs 39.80 5,452.60 5,452.60 0.045

G.I. Wire # 16 6 Kgs 172.48 1,034.88 1,034.88 0.008

Tox With Metal screw #8 40 pcs 14.00 560.00 560.00 0.004

Fullthread 3/8" 8 L/10 317.49 2,539.92 2,539.92 0.021

Nuts 3/8" 40 pcs 5.50 220.00 220.00 0.001

Washer 3/8" 40 pcs 5.50 220.00 220.00 0.001

 Anchor Grip 3/8" 40 pcs 39.80 1,592.00 1,592.00 0.013

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 12 rolls 133.00 1,596.00 1,596.00 0.013

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

299,515.48 PhP 299,515.48 PhP 2.496

27TH FLOOR

Copper Tube 5/8" 218 ft 261.00 56,898.00 56,898.00 0.474

Copper Tube 1/2" 72 ft 188.40 13,564.80 13,564.80 0.113

Copper Tube 3/8" 218 ft 109.00 23,762.00 23,762.00 0.198

Copper Tube 1/4" 72 ft 116.75 8,406.00 8,406.00 0.070

Copper Elbow 5/8" 36 pcs 93.00 3,348.00 3,348.00 0.027

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 36 pcs 66.50 2,394.00 2,394.00 0.020

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 7 pcs 55.00 385.00 385.00 0.003

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 12 L/6 660.71 7,928.52 7,928.52 0.066

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 12 L/6 323.72 3,884.64 3,884.64 0.032

EMT Pipe 1/2" 29 L/10 399.00 11,571.00 11,571.00 0.096

EMT Elbow 1/2" 42 pcs 66.34 2,786.28 2,786.28 0.023

EMT Coupling 1/2" 113 pcs 39.80 4,497.40 4,497.40 0.037

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 36 pcs 14.00 504.00 504.00 0.004

Fullthread 3/8" 7 L/10 317.49 2,222.43 2,222.43 0.018

Nuts 3/8" 36 pcs 5.50 198.00 198.00 0.001

Washer 3/8" 36 pcs 5.50 198.00 198.00 0.001

 Anchor Grip 3/8" 36 pcs 39.80 1,432.80 1,432.80 0.011

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

262,452.13 PhP 262,452.13 PhP 2.187

28TH FLOOR

Copper Tube 5/8" 218 ft 261.00 56,898.00 56,898.00 0.474

Copper Tube 1/2" 72 ft 188.40 13,564.80 13,564.80 0.113

Copper Tube 3/8" 218 ft 109.00 23,762.00 23,762.00 0.198

Copper Tube 1/4" 72 ft 116.75 8,406.00 8,406.00 0.070

Copper Elbow 5/8" 36 pcs 93.00 3,348.00 3,348.00 0.027

Copper Elbow 1/2" 15 pcs 71.64 1,074.60 1,074.60 0.009

Copper Elbow 3/8" 36 pcs 66.50 2,394.00 2,394.00 0.020

Copper Elbow 1/4" 15 pcs 62.00 930.00 930.00 0.007

Copper Coupling 5/8" 22 pcs 66.50 1,463.00 1,463.00 0.012

Copper Coupling 1/2" 7 pcs 55.00 385.00 385.00 0.003

Copper Coupling 3/8" 22 pcs 55.00 1,210.00 1,210.00 0.010

Rubber Insulation 5/8" x 1' Thickness 37 L/6 711.13 26,311.81 26,311.81 0.219

Rubber Insulation 1/2" x 1' Thickness 12 L/6 660.71 7,928.52 7,928.52 0.066

Rubber Insulation 3/8" x 1' Thickness 37 L/6 581.11 21,501.07 21,501.07 0.179

Rubber Insulation 1/4" x 3/4' Thickness 12 L/6 323.72 3,884.64 3,884.64 0.032

EMT Pipe 1/2" 29 L/10 399.00 11,571.00 11,571.00 0.096

EMT Elbow 1/2" 42 pcs 66.34 2,786.28 2,786.28 0.023

EMT Coupling 1/2" 113 pcs 39.80 4,497.40 4,497.40 0.037

G.I. Wire # 16 5 Kgs 172.48 862.40 862.40 0.007

Tox With Metal screw #8 36 pcs 14.00 504.00 504.00 0.004

Fullthread 3/8" 7 L/10 317.49 2,222.43 2,222.43 0.018

Nuts 3/8" 36 pcs 5.50 198.00 198.00 0.001Washer 3/8" 36 pcs 5.50 198.00 198.00 0.001

 Anchor Grip 3/8" 36 pcs 39.80 1,432.80 1,432.80 0.011

Flat Bar 1/8" x 1" 2 pcs 400.00 800.00 800.00 0.006

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 14 pcs 119.50 1,673.00 1,673.00 0.013

Nitrogen 3 cyl 1,460.00 4,380.00 4,380.00 0.036

Silver Rod 70 pcs 40.00 2,800.00 2,800.00 0.023

SUBTOTAL

SUBTOTAL

Page 11: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 11/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

Oxy-Acethylene 1 set 2,787.00 2,787.00 2,787.00 0.023

Hacksaw Blade 1 pcs 172.48 172.48 172.48 0.001

Junction Box 15 pcs 66.50 997.50 997.50 0.008

Polyethelene Tape 10 rolls 133.00 1,330.00 1,330.00 0.011

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 49,605.42 49,605.42 49,605.42 0.413

262,452.13 PhP 262,452.13 PhP 2.187

29TH FLOOR

Copper Tube 5/8" 513 ft 261.00 133,893.00 133,893.00 1.115

Copper Tube 1/2" 135 ft 188.40 25,434.00 25,434.00 0.212

Copper Tube 3/8" 513 ft 109.00 55,917.00 55,917.00 0.466

Copper Tube 1/4" 135 ft 116.75 15,761.25 15,761.25 0.131

Copper Elbow 5/8" 54 pcs 93.00 5,022.00 5,022.00 0.041

Copper Elbow 1/2" 54 pcs 71.64 3,868.56 3,868.56 0.032

Copper Elbow 3/8" 54 pcs 66.50 3,591.00 3,591.00 0.029

Copper Elbow 1/4" 54 pcs 62.00 3,348.00 3,348.00 0.027

Copper Coupling 5/8" 51 pcs 66.50 3,391.50 3,391.50 0.028

Copper Coupling 1/2" 13 pcs 55.00 715.00 715.00 0.006

Copper Coupling 3/8" 51 pcs 55.00 2,805.00 2,805.00 0.023

Rubber Insulation 5/8" x 1' Thickness 86 L/6 711.13 61,157.18 61,157.18 0.509

Rubber Insulation 1/2" x 1' Thickness 23 L/6 660.71 15,196.33 15,196.33 0.126

Rubber Insulation 3/8" x 1' Thickness 86 L/6 581.11 49,975.46 49,975.46 0.416

Rubber Insulation 1/4" x 3/4' Thickness 23 L/6 323.72 7,445.56 7,445.56 0.062

EMT Pipe 1/2" 65 L/10 399.00 25,935.00 25,935.00 0.216

EMT Elbow 1/2" 75 pcs 66.34 4,975.50 4,975.50 0.041

EMT Coupling 1/2" 215 pcs 39.80 8,557.00 8,557.00 0.071

G.I. Wire # 16 10 Kgs 172.48 1,724.80 1,724.80 0.014

Tox With Metal screw #8 80 pcs 14.00 1,120.00 1,120.00 0.009

Fullthread 3/8" 16 L/10 317.49 5,079.84 5,079.84 0.042

Nuts 3/8" 80 pcs 5.50 440.00 440.00 0.003

Washer 3/8" 80 pcs 5.50 440.00 440.00 0.003

 Anchor Grip 3/8" 80 pcs 39.80 3,184.00 3,184.00 0.026

Flat Bar 1/8" x 1" 4 pcs 400.00 1,600.00 1,600.00 0.013

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 30 pcs 119.50 3,585.00 3,585.00 0.029

Nitrogen 5 cyl 1,460.00 7,300.00 7,300.00 0.060

Silver Rod 150 pcs 40.00 6,000.00 6,000.00 0.050

Oxy-Acethylene 2 set 2,787.00 5,574.00 5,574.00 0.046

Hacksaw Blade 2 pcs 172.48 344.96 344.96 0.002

Junction Box 45 pcs 66.50 2,992.50 2,992.50 0.024

Polyethelene Tape 22 rolls 133.00 2,926.00 2,926.00 0.024

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 95,519.88 95,519.88 95,519.88 0.796

565,392.30 PhP 565,392.30 PhP 4.711

30TH FLOOR

Copper Tube 5/8" 514 ft 261.00 134,154.00 134,154.00 1.118

Copper Tube 1/2" 118 ft 188.40 22,231.20 22,231.20 0.185

Copper Tube 3/8" 514 ft 109.00 56,026.00 56,026.00 0.466

Copper Tube 1/4" 118 ft 116.75 13,776.50 13,776.50 0.114

Copper Elbow 5/8" 84 pcs 93.00 7,812.00 7,812.00 0.065

Copper Elbow 1/2" 39 pcs 71.64 2,793.96 2,793.96 0.023

Copper Elbow 3/8" 84 pcs 66.50 5,586.00 5,586.00 0.046

Copper Elbow 1/4" 39 pcs 62.00 2,418.00 2,418.00 0.020

Copper Coupling 5/8" 51 pcs 66.50 3,391.50 3,391.50 0.028

Copper Coupling 1/2" 12 pcs 55.00 660.00 660.00 0.005

Copper Coupling 3/8" 51 pcs 55.00 2,805.00 2,805.00 0.023

Rubber Insulation 5/8" x 1' Thickness 86 L/6 711.13 61,157.18 61,157.18 0.509

Rubber Insulation 1/2" x 1' Thickness 20 L/6 660.71 13,214.20 13,214.20 0.110

Rubber Insulation 3/8" x 1' Thickness 86 L/6 581.11 49,975.46 49,975.46 0.416

Rubber Insulation 1/4" x 3/4' Thickness 20 L/6 323.72 6,474.40 6,474.40 0.054

EMT Pipe 1/2" 64 L/10 399.00 25,536.00 25,536.00 0.212

EMT Elbow 1/2" 129 pcs 66.34 8,557.86 8,557.86 0.071

EMT Coupling 1/2" 322 pcs 39.80 12,815.60 12,815.60 0.106

G.I. Wire # 16 11 Kgs 172.48 1,897.28 1,897.28 0.015

Tox With Metal screw #8 80 pcs 14.00 1,120.00 1,120.00 0.009

Fullthread 3/8" 16 L/10 317.49 5,079.84 5,079.84 0.042

Nuts 3/8" 80 pcs 5.50 440.00 440.00 0.003

Washer 3/8" 80 pcs 5.50 440.00 440.00 0.003

 Anchor Grip 3/8" 80 pcs 39.80 3,184.00 3,184.00 0.026

Flat Bar 1/8" x 1" 4 pcs 400.00 1,600.00 1,600.00 0.013

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 30 pcs 119.50 3,585.00 3,585.00 0.029

Nitrogen 5 cyl 1,460.00 7,300.00 7,300.00 0.060

Silver Rod 150 pcs 40.00 6,000.00 6,000.00 0.050

Oxy-Acethylene 3 set 2,787.00 8,361.00 8,361.00 0.069

Hacksaw Blade 2 pcs 172.48 344.96 344.96 0.002

Junction Box 39 pcs 66.50 2,593.50 2,593.50 0.021

Polyethelene Tape 22 rolls 133.00 2,926.00 2,926.00 0.024

Rugby 1 bot 172.98 172.98 172.98 0.001Labor  1 lot 95,519.88 95,519.88 95,519.88 0.796

570,349.30 PhP 570,349.30 PhP 4.752

PENTHOUSE

Copper Tube 5/8" 437 ft 261.00 114,057.00 114,057.00 0.950

Copper Tube 1/2" 269 ft 188.40 50,679.60 50,679.60 0.422

Copper Tube 3/8" 437 ft 109.00 47,633.00 47,633.00 0.396

Copper Tube 1/4" 269 ft 116.75 31,405.75 31,405.75 0.261

SUBTOTAL

SUBTOTAL

SUBTOTAL

Page 12: feb-march BOQ II (1)222222222222222222.xls

7/27/2019 feb-march BOQ II (1)222222222222222222.xls

http://slidepdf.com/reader/full/feb-march-boq-ii-1222222222222222222xls 12/12

Mat'l Labor Total% WeightAmountDescription QTY UNIT

Unit Cost

Copper Elbow 5/8" 126 pcs 93.00 11,718.00 11,718.00 0.097

Copper Elbow 1/2" 42 pcs 71.64 3,008.88 3,008.88 0.025

Copper Elbow 3/8" 126 pcs 66.50 8,379.00 8,379.00 0.069

Copper Elbow 1/4" 42 pcs 62.00 2,604.00 2,604.00 0.021

Copper Coupling 5/8" 43 pcs 66.50 2,859.50 2,859.50 0.023

Copper Coupling 1/2" 27 pcs 55.00 1,485.00 1,485.00 0.012

Copper Coupling 3/8" 43 pcs 55.00 2,365.00 2,365.00 0.019

Rubber Insulation 5/8" x 1' Thickness 73 L/6 711.13 51,912.49 51,912.49 0.432

Rubber Insulation 1/2" x 1' Thickness 45 L/6 660.71 29,731.95 29,731.95 0.247

Rubber Insulation 3/8" x 1' Thickness 73 L/6 581.11 42,421.03 42,421.03 0.353

Rubber Insulation 1/4" x 3/4' Thickness 46 L/6 323.72 14,891.12 14,891.12 0.124

EMT Pipe 1/2" 71 L/10 399.00 28,329.00 28,329.00 0.236

EMT Elbow 1/2" 126 pcs 66.34 8,358.84 8,358.84 0.069

EMT Coupling 1/2" 323 pcs 39.80 12,855.40 12,855.40 0.107

G.I. Wire # 16 12 Kgs 172.48 2,069.76 2,069.76 0.017

Tox With Metal screw #8 88 pcs 14.00 1,232.00 1,232.00 0.010

Fullthread 3/8" 18 L/10 317.49 5,714.82 5,714.82 0.047

Nuts 3/8" 88 pcs 5.50 484.00 484.00 0.004

Washer 3/8" 88 pcs 5.50 484.00 484.00 0.004

 Anchor Grip 3/8" 88 pcs 39.80 3,502.40 3,502.40 0.029

Flat Bar 1/8" x 1" 5 pcs 400.00 2,000.00 2,000.00 0.016

Paint 1 Lot 400.00 400.00 400.00 0.003

 Access Valve 28 pcs 119.50 3,346.00 3,346.00 0.027

Nitrogen 4 cyl 1,460.00 5,840.00 5,840.00 0.048

Silver Rod 140 pcs 40.00 5,600.00 5,600.00 0.046

Oxy-Acethylene 3 set 2,787.00 8,361.00 8,361.00 0.069

Hacksaw Blade 2 pcs 172.48 344.96 344.96 0.002

Junction Box 42 pcs 66.50 2,793.00 2,793.00 0.023

Polyethelene Tape 24 rolls 133.00 3,192.00 3,192.00 0.026

Rugby 1 bot 172.98 172.98 172.98 0.001

Labor  1 lot 95,519.88 95,519.88 95,519.88 0.796

605,751.36 PhP 605,751.36 PhP 5.047

SUB - TOTAL ( III )

GRAND TOTAL 100.00

PREPARED BY: NOTED BY: CONFORMED BY

Ma. Diana Rose D. Japone Francis O. Velarde

7,894,168.88PhP

(Equipment, General requirements & Installation) 12,000,000.00PhP

SUBTOTAL

(Installation)