Top Banner

of 36

Feasibility Study for ISL Mine

Mar 01, 2018

Download

Documents

kselvan_1
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/25/2019 Feasibility Study for ISL Mine

    1/36

    ISL mine Project

    and Planning- Feasibility Study -

    Vladimir Benes,DIAMO, s.e., Czech Republic

    IAEA /INB Regional Meeting

    Salvador, Brazilia

    24. 28. 11. 2008

  • 7/25/2019 Feasibility Study for ISL Mine

    2/36

    Introduction (1)

    Bringing a uranium operation into production

    involves a sequence of interrelated steps. These areoutlined in the simplified diagram presented below;

    Very important step is detailed feasibility study,

    which :

    is required for permitting and licencing and for

    financing too;

    will be the guide for all actions, and decisions

    leading to production.

  • 7/25/2019 Feasibility Study for ISL Mine

    3/36

    Introduction (2)

    EXPLORATION

    GEOLOGICAL, HYDROGEOLOGICAL INVESTIGATION

    LABORATORY TECHNOLOGICAL RESEARCH

    RESOURCE ESTIMATION

    PILOT PLANT TESTING

    FEASIBILITY STUDY

  • 7/25/2019 Feasibility Study for ISL Mine

    4/36

    Introduction (3)FEASIBILITY STUDY

    PERMITTING AND LICENSING.

    PROJECT PLANNING AND ENGINEERING

    PROCUREMENT AND CONSTRUCTION

    START-UP AND OPERATION

    MINING AND PROCESSING WASTE MANAGEMENT

    DECOMMISSIONING AND RECLAMATION

  • 7/25/2019 Feasibility Study for ISL Mine

    5/36

    Introduction (4)

    The Detailed Feasibility Study is the first step of

    designing ISL facilities.The study or report provides an overview of the

    project and should address all significant issues

    pertaining to construction, operation, financing andfinal closure of the project.

    The Feasibility Study gives a clear view of the scale

    of production, used technology, required

    power/heat/water resources, technical-economicparameters and economic effectiveness of the

    planned facility.

  • 7/25/2019 Feasibility Study for ISL Mine

    6/36

    1. INTRODUCTION Location and Site Description Historical Data Purpose and Scope of Study

    2. CONCLUSIONS AND RECOMMENDATIONS Conclusions Recommendations Summary of Factors Affecting Cost

    3. SUMMARY OF STUDY Conceptual Design

    Capital Costs Financial Analysis

    Typical table of contents (1)

  • 7/25/2019 Feasibility Study for ISL Mine

    7/36

    5. SUMMARY OF EXPLORATION ANDINVESTIGATION RESULTS

    Geology, Hydrogeology Technological research Resource calculation Pilot plan

    6. PRODUCTION CRITERIA Wellfields Processing Plant Conceptual Flow sheet

    7. WELLFIELDS COMPLEX DESIGN Well construction Well patterns Drilling schedule Piping Access roads

    Typical table of contents (2)

  • 7/25/2019 Feasibility Study for ISL Mine

    8/36

    8. PROCESSING PLANT DESIGN General Design Criteria Process Equipment List Plant Layout Process Control Concept Support Services and Facilities

    9. ENVIRONMENTAL PROTECTION Atmosphere Water resources Land

    10. Restoration Well Decommissioning Equipment and Building Dismantling Groudwater restoration Surface reclamatin

    Typical table of contents (3)

  • 7/25/2019 Feasibility Study for ISL Mine

    9/36

    11. ENGINEERING MANAGEMENT Project Execution Approach Preliminary Project Development Schedule Engineering Estimate

    12. DRAWINGS Site Plan - Mine Conceptual Layout

    General Site - Building Location Processing Plant - Preliminary Flowsheets Storage, Shops, Warehouse - General Arrangement Office & Laboratory- General Arrangement

    Typical table of contents (5)

  • 7/25/2019 Feasibility Study for ISL Mine

    10/36

  • 7/25/2019 Feasibility Study for ISL Mine

    11/36

    Summary of exploration and

    investigation results (2)

    Presents the main parameters characterizing:

    Geotechnology of mining, Geological structure of the deposit,

    Confinement of the deposit to certain stratigrafic

    horizons, Location of ore bodies within the product horizon,

    Characteristics of ore bodies in plan and in section

  • 7/25/2019 Feasibility Study for ISL Mine

    12/36

    1. Geological ore reserves in categories, including geotechnological types2. Recoverable reserves in categories, including geotechnological types

    3. Leach field area

    4. Average operational thickness

    5. Workable reserves of ore mass including geotechnological types

    6. Porosity, effective porosity of ores

    7. Kinetics of leaching

    8. Kinetics of reagent consumption

    9. Determination of leading process (transport, chemistry)

    10. Specific consumption of reagents (per 1 kg of ore, both mineralized andbarren)

    11. Leaching agent concentration in operational solutions (average)

    12. Design time for block acidification

    13. Design time for block leaching14. Well pattern, recovery : injection wells ratio

    15. Average design flow rate of operational wells

    16. Total period of facility operation

    17. Working period (days per year, shifts per day)18. Below cut off U-reserves

    Parameters for ISL Mine

  • 7/25/2019 Feasibility Study for ISL Mine

    13/36

    Production criteria

    Annual U-production

    area of simultaneously working blocks number of simultaneously working wells volume of processed solution annual reagent consumption

    Technology of leaching process (acid, alkaline)

    Technology of solution processing (ion exchange,extraction, etc.),

    Pumping technique (submersible pumps, air-lifts),

    Method for under balance of injected solutionvolume,

    Technology of restoration.

  • 7/25/2019 Feasibility Study for ISL Mine

    14/36

    Wellfields - Basic Design (1)

    The wellfield complex is designated for:

    Pre-conditioning and leaching the U deposit

    Leaching solutions injection into the ore bodies

    The production solution recovery to the surface

    Solutions transport from/to processing plantThis chapter of FS includes:

    Injection, recovery and monitoring wells

    Submersible pumps or airlift system for therecovery wells

    Associated control, piping and power systems

    Access and service roads

  • 7/25/2019 Feasibility Study for ISL Mine

    15/36

    Wellfields - Basic Design (2)

    Requirements on wells:

    The arrangement of wells and their performanceshould provide maximum U recovery from theore with a minimum loss of leaching solution.

    The wells should be designed to operate at the

    maximum possible productivity under theexisting conditions at the site.

    The arrangement of wells should enable themovement of solutions underground to becontrolled.

    The operating life of wells should last as long asrequired for complete extraction of the wellfield.

  • 7/25/2019 Feasibility Study for ISL Mine

    16/36

    Wellfields - Basic Design (3)

    Requirements on wells:

    The number and cost of wells required fortechnical recovery of the ore should also be

    consistent with the economic parameters which

    are defined by the feasibility study.

    The standard quality attained during well

    installation should be sufficient to meet all

    expected operational requirements, including the

    specified equipment and instrumentation.

    The wells must not be allowed to become a

    source of environmental contamination.

  • 7/25/2019 Feasibility Study for ISL Mine

    17/36

    Wellfields - Basic Design (4)

    Well pattern

    Hexagonal (r = 15 - 30 m)

    Tetragonal system (5-spot)

    Line system (20 x 50 m)

    Hexagonal with recovery well in centre, r = 80

    m, distance of injection wells = 20 m

    Line system, distance of lines 60-120 m,distance of recovery wells cca 50-80 m,

    injection wells distance 10-15 m.

  • 7/25/2019 Feasibility Study for ISL Mine

    18/36

    Wellfields - Basic Design (5)

  • 7/25/2019 Feasibility Study for ISL Mine

    19/36

    Wellfields - Basic Design (6)

    Pipelines:

    Subdivided into Mains, Branch and Distribution,

    Geometric consideration,

    Diameters,

    Material, Respect to next development of deposit

    (dimensioning, placement),

    Access roads, maintenance,

    Necessity of re-pumping stations.

  • 7/25/2019 Feasibility Study for ISL Mine

    20/36

    Wellfields - Basic design (7)

    Parameters for the ISL mine design:

    Well patterns, well density, ratio betweenrecovery and injection wells,

    Annual total drilling (average for calculatedyear) including operational and monitoringwells,

    Total drilling for the development period (start-up) including operational and monitoring

    wells, Quantity of operational wells simultaneously

    working (both recovery and injection).

  • 7/25/2019 Feasibility Study for ISL Mine

    21/36

    Wellfields - Basic Design (8)

    Parameters for the ISL mine design (cont.):

    Number of submersible pumps in simultaneousoperation, including types

    Required number of submersible pumps annuallyreplaced

    or

    The air-lifts consumption of pressurized air

    Necessary capacity of pressurized air production,

    and

    Specific consumption of electrical power to pumpone cubic meter solution from the well.

  • 7/25/2019 Feasibility Study for ISL Mine

    22/36

    Processing PlantDesign (1)

    The processing plant is designated for:

    U stripping from recovery solutions and productionof ISL Mine final product,

    Preparing the leaching solution,

    Storage of used chemicals, Production of pressurized air.

    The chapter presents criteria for:

    Choosing and evaluating process equipment,setting its arrangement and layout,

    Setting the construction phases in order tominimize the preparation time for the start-up.

  • 7/25/2019 Feasibility Study for ISL Mine

    23/36

    Processing Plant Design (2)

    Specifications:1. Type of ion exchange resin, loading capacity,

    particle size, volume of resin in operation.

    2. Technology of sorption/desorption:

    fixed bed or continual counter current

    total volume of resin annual loses of resin

    3. Chemistry of resin loading, resin regenerationand chemistry of final product precipitation,

    4. Volume and type of equipment (vessels, pumps,piping),

    5. Volume of storage tanks,

    6. Annual/ daily consumption of chemicals.

  • 7/25/2019 Feasibility Study for ISL Mine

    24/36

    Processing Plant Design (3)

    Specifications (cont.):7. Determination of storage volume type for

    injection and recovery stream:

    basins

    tanks

    8. The design should foresee a potential expansionof any process circuit without halting the plantoperation,

    9. The design should support necessary

    mechanization and automation of operations andmaintenance at the site,

    10. Decision if satellite sorption stations will beerected, their capacity,

  • 7/25/2019 Feasibility Study for ISL Mine

    25/36

    Processing Plant Design(4)

    Parameters for the ISL mine design:

    The volume of solution to be treated is the majorprocess parameter of each processing plant(106m3 per year, m3 per hour),

    Annual consumption of reagents and materials,

    Initial load of expensive agents and materials(adsorbents, extractants, etc.),

    Annual consumption of expensive agents andmaterials,

    Process water consumption,

    Steam consumption,

    Electric power consumption.

  • 7/25/2019 Feasibility Study for ISL Mine

    26/36

    Environmental protection (1)

    Atmosphere

    This section gives characteristics of geographical andclimatic conditions of the construction site, as well as

    the present background baseline concentrations of

    harmful impurities in the near surface layer of the

    atmosphere prior to the facility construction. Pollutionsources are to be determined including estimates of

    harmful materials which may pose health hazards.

  • 7/25/2019 Feasibility Study for ISL Mine

    27/36

    Environmental protection (2)

    Water resources:

    The natural pre-mine conditions of water resourcesare presented. The total water use is to be calculated

    considering both surface and underground sources.

    LandList of measures to be provided for protecting and

    utilizing the Earths surface ( removing and storing

    the fertile top layer of soil, followed with laterutilization; prevention of acid spills, recultivation of

    disturbed land, and planting vegetation in the areas of

    production sites, etc.)

  • 7/25/2019 Feasibility Study for ISL Mine

    28/36

    Restoration technology(1)

    The chapter presents criteria for:

    Decommissioning wells, pipelines, equipment,buildings

    Surface reclamation full/particular,

    Ground water restoration after mining orstarting parallel with operation,

    Waste materials management/technology.

  • 7/25/2019 Feasibility Study for ISL Mine

    29/36

    Restoration technology(2)

    The main parameters for the ISL mine design:

    Technology of contaminated water treatment, Consumption of necessary reagents,

    Power consumption,

    Waste materials management.

  • 7/25/2019 Feasibility Study for ISL Mine

    30/36

    Cost analysis (1)

    Supported by detailed schedules for:

    Initial capital equipment and costs, Annual drilling programmes and costs,

    Annual energy requirements and costs,

    Wellfield installation material and labor,

    Annual manpower requirements and costs,

    Reagents consumption and costs,

    Sustaining capital requirements and costs,

    Decommissioning plans and costs, Surface reclamation plans and costs,

    Ground water restoration plans and costs, etc.

  • 7/25/2019 Feasibility Study for ISL Mine

    31/36

    Cost analysis (2)

    Capital Investment Requirements:

    Drilling,

    Roads,

    Well fields construction,

    Chemical plant construction, Ion exchange resin 1st filling,

    Environmental Monitoring Costs.

    Capital costs

    45%

    26%

    12%

    1%

    8%

    8%

    Drilling, well completion

    Wellfields construction

    Processing plant construction

    Storage services

    Solutions under balance

    General repair/maintanance

  • 7/25/2019 Feasibility Study for ISL Mine

    32/36

    Cost analysis (3)

    Operational Costs:

    Chemicals + resin loses replacement,

    Transportation cost supply of reagents,

    Electrical power,

    Other energy, Manpower labor cost,

    Maintenance of equipment,

    Sustaining capital requirements and cost.

    Operational Costs

    11%

    27%

    29%

    2%

    2%

    3%

    1%

    2%

    3%

    7%

    13%

    Power

    Reagents

    Man power

    Repair and mainatance

    Well maintanance

    Control and monitoring

    Transportation

    Services

    Delivery overhead costs

    Overhead administrative cost

    Solutions underbalance

  • 7/25/2019 Feasibility Study for ISL Mine

    33/36

    Cost analysis (4)

    Closure Costs: Decommissioning

    Surface reclamation

    Ground water restoration

    Summary Unit Cost

    34%

    40%

    26%

    Capital costs

    Operational costs

    Restoration costs

  • 7/25/2019 Feasibility Study for ISL Mine

    34/36

    Summary

    Based on a comparison of experience between

    conventional and ISL uranium mining (bothacid and alkaline), ISL was found to have the

    following advantages:

    low capital and operational project costs, high cash flow within one year,

    rapid payback of investment,

    reduced length of project development,

    low power consumption and less equipment

    required,

  • 7/25/2019 Feasibility Study for ISL Mine

    35/36

    Summary (cont.)

    reduced labour per unit produced,

    reduced radiation exposure and lowerenvironmental impacts (contamination, etc.),

    greatly reduced solid waste (no tails),

    economic recovery of low grade ores, thusincreasing resource utilization,

    possibility of recovering uranium from

    deposit inaccessible by other extraction

    methods.

  • 7/25/2019 Feasibility Study for ISL Mine

    36/36

    Thank you for your attention