Page 1
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 1
Table of Contents
Abbreviations .................................................................................................................................. 3
Executive Summary ........................................................................................................................ 4
Introduction ..................................................................................................................................... 5
1 Project Background ................................................................................................................. 6
2 Objectives of the Consultancy Service ................................................................................... 7
3 General .................................................................................................................................... 8
3.1 Physical characteristics ................................................................................................... 8
3.1.1 Location .................................................................................................................. 8
3.1.2 Spatial coverage of the City .................................................................................... 8
3.1.3 Topographic Features ............................................................................................. 8
3.1.1.1 Terrain .................................................................................................................... 8
3.1.4 Climate .................................................................................................................... 8
3.2 Historical Development of solid waste management...................................................... 9
4 Evaluation of the Existing Solid Waste Management System.............................................. 11
4.1 Current Situation Review and Findings .................................................................................. 11
4.1.1 Generation and characteristics ......................................................................................... 11
4.1.2. Handling and primary storage ......................................................................................... 11
4.1.3. Primary collection ........................................................................................................... 11
i. Municipal Tractor-trailer .............................................................................................. 12
4.1.4 Secondary collection and Transportation ......................................................................... 16
4.1.5 Existing Disposal Facility ......................................................................................... 17
4.1.6. Waste Reduction, Recycling and Reuse (3R's) ............................................................... 20
4.1.8. Special and hazardous wastes ......................................................................................... 21
4.2. Organization of the existing system and role of Stakeholders .............................................. 21
Available Resources.................................................................................................................. 21
4.3. Financial aspects ................................................................................................................ 27
4.4. Institutional Structure and Responsibilities ....................................................................... 30
5 Data Collection, Projection of Solid waste generation and composition .............................. 34
5.2.1 Population projection ....................................................................................................... 39
5.2.1.1 Base Data .................................................................................................................. 39
5.2.1.2 Methodology ......................................................................................................... 40
5.3 Results of the survey ..................................................................................................... 42
6 System Analysis, Design and Recommendations ................................................................. 49
6.1 General design approach ............................................................................................... 49
6.3 Secondary Collection Route scenarios .......................................................................... 50
6.4 Design ........................................................................................................................... 51
6.5 MATERIAL RECOVERY FACILITY (MRF) ............................................................ 53
6.5.1 Site selection for MRF .......................................................................................... 53
6.5.2 Engineering aspects of material recovery facility (MRF)..................................... 55
6.5.3 Scope of MRF ....................................................................................................... 55
6.5.4 Lay out and design of physical facilities............................................................... 56
6.6 Proposed landfill ........................................................................................................... 57
6.6.1 Initial Site Selection .............................................................................................. 57
Page 2
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 2
6.6.2 Preliminary design ................................................................................................ 58
6.6.3 Proposed layout ..................................................................................................... 59
6.6.4 Design considerations ........................................................................................... 60
6.7 Access road ................................................................................................................... 63
7 Environmental Impact Assessment ............................................................................... 64
8. Socio-Economic Impact Assessment .................................................................................... 65
9 Recommendations ................................................................................................................. 70
9.2 Proposal on the improvement of household handling and primary collection facility ........... 70
9.3 Recommendation for Financing SWM ............................................................................... 72
Options to recover the solid waste service costs /bill collection .......................................... 72
Willingness To Pay Of The Users ................................................................................................ 75
Model one ................................................................................................................................. 76
Model two ................................................................................................................................. 76
Proposed Sold Waste Management Services In this Model ................................................. 77
1. Street sweeping ..................................................................................................................... 77
3. Collecting and Transfer ......................................................................................................... 78
9.6 Legislative recommendation ............................................................................................. 84
10. Implementation Schedule.................................................................................................... 92
11. Annexes................................................................................................................................... 94
Annex A: Summary of Observation on Primary Collection Services ...................................... 97
Annex B: Analysis of Tractor-Trailer for Primary Collection................................................ 100
Annex C: Assessment of Secondary Storage and Collection Services ................................... 108
i. Annex D: Survey Methodology .......................................................................................... 112
D.1. Solid waste generation .................................................................................................... 112
Solid waste Source Category .................................................................................................. 118
Field Sampling ........................................................................................................................ 119
ANNEX-E: Rates of generation from Municipal Solid Waste (MSW) Sources (City-wise) . 129
ANNEX-F: City-wise Types of composition of Solid Wastes from Municipal Solid Waste
(MSW) Sources ....................................................................................................................... 130
Annex-H: Observations on collection at Land fill site ........................................................... 138
ANNEX-I: INSTITUTION AND LEGISLATION RELATED TO SOLID WASTE
MANAGEMENT .................................................................................................................... 140
ANNEX-L: MANUALLY LOADED AND MECHANICALLY UNLOADED REAR
LOADING COMPACTORS WITH LOADING CAPACITY OF 15.30 CU.M ................... 153
Annex M: Summary of demand projection, component sizing, Operation and Maintenance
Analysis (for achieving 100% collection efficiency in 2020) ................................................ 156
Annex N: Summary of demand projection, component sizing, Operation and Maintenance
Analysis ( for achieving 100% collection efficiency in 2010) ............................................... 157
Annex N: Environmental Impact Assessment ........................................................................ 158
12. REFERENCE ........................................................................................................................ 160
Page 3
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 3
Abbreviations
PLC = Privately Owned Limited Company
ISWM=Integrated Solid Waste Management
EIA= Environmental Impact Assessment
SW=Solid waste
ICHUD=International Course on Housing and Urban Development
NGO=Non Governmental Organization
ICHUD=International Course on Housing and Urban Development
MSEs=Micro and Small Enterprises
SSs=Sanitation Services
CSW=commingled solid waste
3Rs= Reduction, Recycling and Reuse or Reclamation
WMBs=waste material brokers
NSS=non specific sources
SS=specific sources
AHWs=acutely hazardous wastes
NAHW=non-acutely hazardous wastes
LHWs=listed hazardous wastes
CHWs=characteristics hazardous wastes
MHWs=mixture of hazardous and non-hazardous
RHWs=residues hazardous wastes
SSD=Social Service Department
MSAs=municipal service areas
EPA= Environmental Protection Authority
TNRS=Tigrai National Regional State
MSW=municipal solid waste
ISW= Industrial solid waste
ASW=Agricultural solid waste
MRF=Material Recovery Facility
MCPPP= Mekelle city plan preparation project
Page 4
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 4
Executive Summary
Page 5
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 5
Introduction
In general this report is prepared with the intention of describing the overall assessment, findings
and recommendations made in the study and design of solid waste management system of
Mekelle.
This report has tried to identify the problems in the existing solid waste management and
respond accordingly to alleviate the posed threats on the environment and also obviously the
inhabitants of Mekelle city. The whole document is structured in such a way that the existing
system is assessed, alternative approaches are referenced and finally recommendations are
forwarded. Moreover, the report has included the findings of the inception report.
Section one tries to discuss the service delivery targets of the city administration as well as its
relation to the Millennium Development Goals. Sections two and three briefly describe the
objectives of the consultancy service and the general physical characteristics of the city including
the historical development of solid waste management, respectively.
Evaluation of the existing solid waste management system which is dealt under section four as a
function of its components which include generation and characteristics of solid waste, handling
and primary storage, primary collection, secondary collection and transportation, disposal
facilities as well as waste reduction, recycling and reuse and financial and institutional issues is
the initial step to undertake the overall study and design.
It is worth mentioning that in the inception report proposed method of data gap filling and
according to the adopted data filling methods, information that are thought to be indispensable
for the intended output are collected and manipulated. Briefing of the data filling method, survey
organization and the result of the survey are summarized under section five.
On the basis of the outputs of the preceding sections (four and five), system analysis and design
criteria are set to conduct the design of various components of the system. Secondary collection
route scenario analysis and design, material recovery facility site selection and design as well as
design of facilities layout are among the design details described under section six of the this
report.
Sections eight and nine briefly discuss the environmental and socio-economic impact assessment
of the proposed project.
The needed technical, financial, economical and institutional recommendations needed for the
improvement of the system are discussed exhaustively under section ten.
Finally, the implementation schedule for the realization of the project ranging from tendering to
final acceptance is outlined under section eleven.
The main body of the report primarily discusses on the assessment, findings and
recommendations briefly the details of which are attached in the annexes.
Page 6
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 6
1 Project Background
The sanitary condition of Mekele is not in a good situation at present .There is no adequate solid
waste facility with properly prepared dumping site which is causing health problems such as
diarrhea, intestinal parasites, malaria …etc. The poor sanitation conditions are caused by poor
waste management system, lack of adequate sanitation facilities and low level of community
awareness and participation. With the existing facilities the City Administration can only collect
34% of the solid waste.
The Ethiopian Government has agreed on and works towards achieving the eight Millennium
Development Goals (MDGs) by the target date of 2015 – which among other issues include:
Reduce by half the proportion of people living on less than a dollar a day
Halt and begin to reverse the incidence of malaria and other major diseases
Integrate the principles of sustainable development into country policies and programmes;
reverse loss of environmental resources
Halt and begin to reverse the incidence of malaria and other major diseases
Achieve significant improvement in lives of at least 100 million slum dwellers, by 2020
Cognizant of the multifaceted problems caused by poor sanitation service and as part of
achieving the MDG, Mekelle City Administration has given emphasis for the improvement of
sanitation aspect of the city and secured the UDF finance for this purpose targeting at the
following principal objectives:
improving the solid waste management facility of the city
reducing health and environment problems caused by the poor sanitation and keep
the aesthetic value of the city Address the environmental problems caused by the existing disposal site.
contribute to the strategic objectives of increasing disposing capacity of solid
waste as indicated hereunder
Year 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Collection
efficiency
in % 34% 37% 39% 42% 45% 49% 52% 56% 60% 65% 70% 75% 81% 87% 93% 100%
Page 7
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 7
2 Objectives of the Consultancy Service
Mekelle City Administration identified the need for improved SWM system which addresses
each components of ISWM, i.e., reduction, storage, transportation, recovery and disposal in a
cost effective, environmental friendly and sustainable manner. To this effect Mekelle city
Administration in collaboration with Kfw procured this consultancy service of which specific
objectives are:
To prepare an integrated solid waste management system plan
To carry out an environment impact assessment (EIA) and analysis of sensitive
components of the existing and designed facilities, comprising of at least land- filling
disposal sites, transfer stations, and communal storages sites.
To prepare detail design and plan of selected facilities as the most efficient interventions
and environmental solutions for solid waste management
To prepare design and contract cost estimates for the project works and actions
To prepare standard Tender Documents
To examine the financial and economic feasibility of the proposed solutions, establish the
costs of the service charges to the broad public with a view to cost recovery and to review
and develop waste regulations and rules
To undertake Construction Supervision
The service is expected to develop a solid waste master plan that gives a solution to problems
related to Solid Waste services. The consultancy contract is also expected to assist the City
Administration in building its capacity to implement the improved SWM system.
Page 8
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 8
3 General
3.1 Physical characteristics
3.1.1 Location
Mekelle City, seat of Tigray National Regional State, is located at about 783 km from the
nation‘s capital, Addis Ababa. It is situated at 13032 North Latitude and 39
028 East Longitude.
The city is accessible through air and highway.
3.1.2 Spatial coverage of the City
The land demand increase as the population size of the city raise from time to time. Mekelle had
a built up area coverage of 16 KM 2
in 1984 after ten years, in 1994 the size of built up area
reached 23.04 KM 2 adopting a continuous increase with the rise of population size and job
opportunity the city administration has expanded its land holding to 100KM 2in 2004 by
engulfing the vast agricultural lands of neighboring villages and towns.
3.1.3 Topographic Features
3.1.1.1 Terrain
Proper Mekelle is bounded by Endayesus and Choma Mountain to the east side and Mesebo
Mountain to the north. Most of the area with in Mekelle is classified under flat to rolling
formation.
3.1.1.2 Altitude
The altitude of Mekelle varies from 2150 m.a.s.l to 2270 m.a.s.l .This elevation puts the city
under the category of Weinadega type of Agro climatic zone.
3.1.1.3 Drainage
Mekelle city is part of Tekeze river basin. Eilala River which ends up in river Giba is the main
stream flow along with Kalamino river of Aynalem. However, there are many tributaries that
feed both rivers with substantial amount of water during rainy season. These streams are
seasonal where the peak discharge is attained during summer.
3.1.4 Climate
Mekelle Experiences mild climatic condition with annual average maximum temperature of
24.10C and annual average minimum temperature 11.11
0C. June is the hottest month with a
monthly mean maximum temperature of 27.10C and monthly mean minimum temperature of
13.030C. December is the coldest month with a mean monthly maximum temperature of 21.9
0C
and monthly mean minimum temperature of 8.510C.
Page 9
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 9
3.1.4.1 Temperature
Mekelle Experiences mild climatic condition with annual average maximum temperature of
24.10C and annual average minimum temperature 11.11
0C. June is the hottest month with a
monthly mean maximum temperature of 27.10C and monthly mean minimum temperature of
13.030C. December is the coldest month with a mean monthly maximum temperature of 21.9
0C
and monthly mean minimum temperature of 8.510C.
3.1.4.2 Rainfall
There is one short rainy season, which starts on June and lasts on August. The rainy season is
characterized by erratic, unreliable and uneven distribution. The city has annual average rainfall
of 618.3mm/Year of which the substantial amount falls on July and August. The highest monthly
rainfall occurs on August with a monthly rainfall of 229mm (37% of the annual) and July is the
second largest rainy month with a monthly rainfall of 207.7mm (33.5% of the annual).
3.1.4.3 Wind
The prevailing wind direction from the month of September to June is angled at 1100-163
0 i.e., in
the east –west direction, while on July and August the direction of the wind is from 2100 to 250
0
i.e., west-east.
3.2 Historical Development of solid waste management
Emperor Yohannes IV founded Mekelle in 1872 and the Municipality was established in 1934
E.C.
A study was conducted on water supply and sanitation of Mekelle city in August 1993 under the
joint venture project between Devecon Engineers and Architects and Metaferia Consulting
Engineers PLC. In those days, garbage was collected by one municipal ordinary truck and
disposed off at an uncontrolled and non-engineered open dumping site out of the city particularly
5km from the center on the old airport road and then burnt in uncontrolled manner.
Even if the rate of solid waste generation in the city was not very high at that time about 18% of
the generated SW materials were expected to be disposed off in open garbage pits and more than
60% of SW generated was disposed at open fields. The garbage pits and open fields were
considered as good options of disposal inside the city. The currently operating system of solid
waste collection, transportation and disposal started by the year 2000.The system was
commenced with 20 communal containers each with a capacity of 8m3 and two skip loaders. The
existing solid waste disposal site at Messobo also started its function on the same year. The
currently operating system was implemented based on the recommendations of the 1993s study
on Water Supply and Sanitation of Ethiopian Towns by Devecon Engineers and Architects and
Metaferia Consulting Engineers PLC.
Responsibility of SWM used to transfer from one governmental organization to another. In the
1990s the then Works and Urban Development Department of the city, which actually was the
provider of municipal services, was responsible for the city‘s solid waste management. By the
Page 10
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 10
year 2000 the city‘s Health Department took the responsibility of the waste management service
from the Works and Urban Development Department and run the activity for three years.
The then Works and Urban Development Department was restructured and a new organizational
structure of the municipality was developed based on the city proclamation No.65/2002. The
new organizational structure decentralized the municipal functions closer to the residents by
organizing municipal service desks in each Tabia that are made accountable to their respective
municipal service area managers.
The solid waste service was shifted from the city Health Department to the Social Service
Department of the newly reorganized municipality. Since August 2003 this department has been
providing the service at Tabia, municipal service area and at its head quarter.
Page 11
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 11
4 Evaluation of the Existing Solid Waste Management System
4.1 Current Situation Review and Findings
4.1.1 Generation and characteristics
There is no comprehensive study conducted in Mekelle city to investigate the rates of generation
and characteristics of solid waste from different urban activities and sources. Even the sources
and solid waste category are not clearly identified in the existing municipal solid waste (MSW)
management service.
4.1.2. Handling and primary storage
House holds and different solid waste generating units in the city prepare themselves different
types of receptacles such as sacks, plastic bags, metal vessels, card boxes, and so on. Most of the
residents (63.56%), regardless of their income, use sacks for primary storage, followed by plastic
bag (16.73%), metal vessels (13.37%), and card boxes (6.35%). Almost all the receptacles used
by the residents for primary storage are out of the standard set by the Regional State in the
hygiene regulation1
which states that the waste storage facilities should be water proof,
washable, and insect proof covered with a lid and it can be made up of sheet of iron or plastic.
As far as regulation is concerned except service providing institutions like cafeterias, restaurants,
hotels, and the like which are some times inspected by health department of the city, others
(house holds, educational institutions, offices, and the like) are not regulated whether the primary
storage receptacles they use and the way they handle it are as to the required standard set in the
regulation or not.
In relation to solid waste handling at municipal levels, there are waste bins and communal
storages made available by the service provider, i.e..the municipality, in key places in the city.
4.1.3. Primary collection
Primary collection operation enables transfer of solid waste materials handled and stored at the
sources of generation to the communal storage and secondary collection facilities.
The identified operational modes of primary collection in Mekelle city are:
Gojo Hand carts system, Private Sector
Saba Hand carts system(Trolley),Private sector
Manual Adult Labor system , Own forces and Hired labors
Manual Child labor ,Own forces and Hired labors
Tractor-trailer system , Municipal
Street sweeping wheel barrow system, Municipal
Horse cart system, Private sector
1 Proclamation number 4/1997
Page 12
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 12
Neither women nor youth cooperatives are currently engaged in primary collection activities.
Stationary –containers or block collection system with compactors and other garbage lorry
systems do not exist in service areas except the tractor-trailer systems.
The operation of primary collection services in services areas has been investigated at container
sites. The current modes of primary collection, their frequency and distribution in the city and
their various service areas have been identified. . (For the detail, refer to Annex A)
The following observations have been drawn on the activities of each mode of primary collection.
i. Municipal Tractor-trailer
Tractor-trailer system operates in areas where the residents do not have access to communal
storage. The residents wake up & get mobilized for operation when the municipal block
collection workers blow alarms during collection events. The tractors empty the collected waste
to the nearest communal container available. In this collection system households who are not
present in their home during collection hours are urged to wait for a week or more to be served
on the next operation. And due to this some of them are obliged to dump their solid waste on
illegal sites.
The current primary collection service with tractor-trailer system involves four tractor-trailers
with a capacity of 4m3each in block-collection of solid wastes mainly from residential sources.
The tractor-trailers are manually loaded and unloaded with mechanical and manual operations.
They work the whole week including Saturday, Sunday and holidays (Mekelle municipality-
SSD). However, this system of primary collection practice of the city does not have well
designed fleet route and fixed program set based on studies the drawback of which is reflected on
our survey. 76.79% of the sample House holds testified that the service is not rendered on a
regular basis instead the operation quality is based on the interest of the drivers as a result some
residents are believed to be better served than others for instance some residents indicated that
local beer, tella vendors are favored.
According to the result of sample survey, 17.57% of the sample households are visited once or
twice a week while the remaining customers of this service are provided with the service once in
two weeks or in a less frequency.
As can be seen under annex B, the tractors have worked for an average of 300 days, and they
have collected 13,790m3
of solid waste annually in 2004/2005 (1997 E.C) and average daily
likelihood availability of a tractor trailer is 82% this indirectly demonstrates of tractor-trailer
primary collection efficiency. In addition these can be noted:
the total frequency of collection with tractor-trailer system was 26 times in the stated
period and the average coverage of each trailers was 6.5 in the stated period;
the trailers used the HC locations 2.89 times on average;
The poor collection capacity of the current service could be managed either doubling the holding
capacity of all the locations or doubling the number of tractors in the current primary collection
services. These scenarios do not seem economical because of the inefficiency in primary
collection with tractor-trailers as observed in the current municipal service. The other technical
problem is that the holding of generated wastes for a period of two weeks time in households
Page 13
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 13
does not seem technically feasible and it is also hardly possible to mobilize the house holds in
voluntary waste handling practices. For detailed analysis, refer to Annex B.
ii. Gojo Private Service
Gojo plastic and sanitation Services gives door-to door waste collection services for 200
residential and 55 institutions like hotels, restaurants and bars. It also gives janitorial services for
some insurance and banking institutions. It has three wheel carts and one truck with a capacity of
holding 15m3 wastes.
The organization collects the solid waste from its clients and performs waste
separation/segregation. It recycle organic fraction of the solid waste and apply to its own farm
land .The service disposes the remaining collected solid waste fraction into the communal
containers.
The Gojo private service was restricted to the locations: Gotera, Axum Hotel, Kebelle 15, Enda
Mariam Near Wewekema , and Mehiret Bani. The observed frequency of collection was 20
times ,which means on average 4 times to each container site during observation time.
iii. Saba Private Service
Saba Sanitation is the second privately owned sanitation agent established to render door-to-door
sanitary services in the city. The group currently renders services in 20 commercial units like
hotels, bars, restaurants and other units in the city. The services are mainly concentrated on the
streets and squares of the city such as Godena Guna and Selam, Romanat and Bazar Squares. Its
services also cover 328 residential houses in different Tabias of the city some of which are
Adihawsi, Adishunduhun, Mayduba, Aider, Sewhinigus and Hadnet among others. The workers
of the private group disposed off the wastes into the nearby communal collection containers after
collecting from the different sources in the services areas.
iv. PC by Street sweepers with Hand Carts &Wheel Barrows
The municipality provides street sweeping services daily for a total of 23.3Km (10km in the
north and the rest in the south municipal service areas). (Mekelle Municipality -SSD). The whole
service is done manually; the sanitation workers sweep the streets using tools like straw brooms,
Wheel barrow and shovel. On average 30 sanitation workers are engaged in the street cleaning
service out of which 21 are permanent employees and the rest employed on a contractual basis.
Wheel barrow is used for primary collection of wastes from street sweeping. The collected waste
from street sweeping delivered to containers located at: Kebelle 19, Kebelle 20, Adis Alem Bus
Station, Kebelle 15, and WEWEKMA. The observed frequency of collection to the five
containers location was 38 times and the stated locations were used 7.6 times on average by
street sweepers.
Page 14
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 14
The other handling method that gets primary collection service by street sweepers is street side
posted public garbage bins. Currently there are 10 public garbage bins posted on the main streets
of the city, namely Hakfen, Alula, and Selam streets that are located at the center of the city. The
street users and pedestrians are expected to put their solid wastes in the public garbage bins when
they are out of their homes and business offices.
The number of the public garbage bins is inadequate and most of the streets and public places
inside the city do not have public garbage collection bins at all for the public use. The public has
already adapted habit of dropping solid wastes, especially paper and plastic products (festal), on
streets even on these with public garbage bins. For these reasons all the streets and public places
of the city including these with public garbage bins are remained to be untidy and dirty.
v. Private Horse cart
The Horse cart primary collection private service users in the city used the containers located at
Edaga Finjal, Enkodo, and Muslim Cemetery. The observed frequency of collection to the three
containers location was 10 times and the stated locations were used 3.33 times on average by
Private Horse Cart.
vi. Adult manual labor (Hired or own force)
The sample survey conducted by Promise has proved that 10.96% of the sample house holds
fully, and 7.62% sometimes/partially dump their garbage onto illegal sites. (Promise sample
survey)
Adult manual labor primary collection users in the city used the containers located at 13
locations:Enkodo, Mesfin Industry, Denbosco, Kebelle 19, Kebelle 20, Business Taxi Terminal,
Adihawsi Endatsaba, Axum Hotel, Adis Alem Bus Station, Kebelle 15, Near WEWEKMA, Near
Enda Mehiret Bani,and Abreha Castle.
The observed frequency of collection to the thirteen containers locations was 77 times and the
stated locations were used 5.9 times on average by Adult manual labor.
vii. Child manual labor (Hired or own force)
The child manual labor primary collection users in the city used the containers located at 3
locations: Kebelle 15, Kebelle 19, and Kebelle 20. The observed frequency of collection to the
three containers locations was 17 times and the stated locations were used 5.67 times on
average by child manual labor.
Table 4.1 Quantity of waste loads delivered from the stated modes of primary collection to
different hauled container locations during observation time
Page 15
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 15
SN
Modes
of
Primary
Collection
Collection
Frequency
Locations
used
Average
Frequency
(per
location)
Waste*
Quantity
(cu.m/trip)
Estimated
MSW
Quantity
(cu.m)
Average
Primary
collection
Capacity
(cu.m/d)
1 Tractor-
trailer
26
9
2.89
4.00
104.00
10.40
2 Gojo 20 5 4 0.80 16.00 1.60
3 Street
sweepers
38
5
7.6
0.50
19.00
0.95
4 Horse cart 10 3 3.33 1.50 15.00 1.50
5 Matured
manual
labors
77
13
5.9
0.031
2.41
0.241
6 Child
manual
labors
17
3
5.67
0.031
0.53
0.053
7 Saba 0 0 0 0.80 0.00 0.00
* represent the holding capacity of the containers of each modes of primary collection;
Consequences of the poor primary collection
As a result of poor primary collection service, residents in some localities are urged to dump
their primary collected garbage into illegal sites indiscriminately. The streets and open fields in
those areas are covered and filled with commingled solid waste and storm water drains are
blocked by the garbage primarily collected by the residents. The occurrence of the illegal
dumping sites is attributed to the low level municipal service coverage in the localities and
negligence of some residents who perform primary collection of their own garbage for storage in
the containers.
(a) River side (b) Fence and skip sides
Figure 4.1 illegal solid waste dumping sites
Page 16
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
16
4.1.4 Secondary collection and Transportation
Communal storage of primarily collected solid waste allows the safe retention of the solid
waste materials for a sufficient period of time expected between primary collection from
the different sources and secondary collection and disposal of the materials.
In the present context of solid waste management in the city, the municipality is the only
institution that provides communal storages and performs secondary collection of
garbage to disposal sites. The municipality performs the storage task with a total of 64
communal containers, which can be easily mounted on skip loaders for transport and
disposal in land filling sites.
The solid wastes collected through the primary collection activities are taken to
communal containers. 58 of the containers, having a capacity of 8 m3 each, are placed in
different parts of the city, 5 in Quiha and one in Aynalem. The solid wastes collected by
the primary collection systems are delivered to near by communal containers that are
provided by the Municipality on vacant plots and road sides. The containers are picked-
up periodically by the three municipality‘s skip-loaders and transported to the land fill
sites located 15 kms away northeast of the city on the left side of the Mekelle –Wukro
highway and Quiha land fill site.
Due to the topography of the city and lack of proper road network some parts of the city,
especially those on the foot of Chomea and Endaeyesus mountains and the new
settlements established in the peripheries of the city are devoid of the service. However,
they are obliged to pay sanitation service fees for the services that they are not provided.
And some of the residents who are said to have access to the communal containers in the
service areas have been obliged to travel a long distance before reaching at the containers.
Because of lack of access to the service and the long travel distances to skip sites, the
residents commit unauthorized dumping of garbage during night times.
The following observations have been drawn from investigation of existing secondary
collection system. (For the details, refer to Annex C)
The average weekly coverage in the existing collection service=69%
Low service coverage observed at Hadnet and Adi Haki (southern sub-city)
Population to communal container is on average 4981
One communal container position serves an average area of 54Ha.
Weekly Total frequency of collection=44
The highest frequency (4) observed at the location Near WEWEKMA;
The locations which did not get weekly collection service were Abune
Aregawie Church, Red cross, Luis Eye clinic, Edaga Faham, Enda Mehiret
Bani, Arekie Factory,Mekaneyesus church, Trans Ethiopia, May Degene,
Kebelle 18 Taxi Terminal, and Adihawsi Taxi Terminal; a total of 11
locations; this may indicate:
- Inefficient service coverage in a week time;
Page 17
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
17
- Longer period of collection cycle (more than a week time) due to
low rate of solid waste generation at the locations;
- Longer service distance and inconveniency in the use of storage
services;
The data generally show very poor collection coverage and
The effective working hours in collection days are less than 8 hours and
The off-route factor in the existing collection service is high, which indicate
high wastage of resources in the collection routes.
In relation to illegal dumping sites the residents have their own arguments. A few
proportions of the residents (26.66%) believe that the municipality is the responsible
body for the prevailing problems for they do not have access to the service and the only
alternative they have is to dump their wastes illegally. While a large proportion of them
(50.79%) believe that the municipality and the residents are equally responsible for the
prevailing problems, and the rest 22.55% stresses on the residents themselves (promise
sample survey).
4.1.5 Existing Disposal Facility
The other major element in the city‘s solid waste service is the disposal service. There are
two land fill sites outside the administrative boundary of the city. One of these sites is
situated at the top of the Messobo escarpment on the left side of the Mekelle-Wukro road
(having an area of 2.67 ha. (MCPPP,2005) and the other one exists 4 km north of Quiha
sub-city.
Page 18
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 18
(a) Fence side (b) Uncovered solid waste slope
(c) Farm land (d) Surrounding quarry and bush sites
Figure 4.2 Messobo Disposal site
The method of land filling at Messobo is excavated pit type of land filling and its
standard exists between the Uncontrolled Non-Engineered dump land fill type and the
engineered landfill type. The term land filling simply refers to the process by which the
residual solid waste is placed in landfill. In today‘s solid waste management practices,
some land fill sites satisfy the criteria of sanitary land fill, which means the sites are
provided with an engineered facility for the disposal of MSW designed and operated to
minimize the public health and environmental impacts. The land fill sites serving Mekelle
city do not fully satisfy these criteria of a sanitary landfill disposal sites.
The land fill at Messobo was constructed with a protection impervious clay membrane to
protect the underground aquifer material from chemical pollution and with a rip rap to
protect the scouring and slide of the impervious material on the side slopes during rainy
season and movements of equipments on the land fill.
Page 19
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 19
The other problem with the land fill at Messobo was the insufficient capacity it initially
got as a disposal site for Mekelle city. A land fill with inadequate capacity was
implemented, which could not serve for a period of five and ten years, due to the then
budget constraint in the City Council and opposition from the local farmers to undertake
subsequent years expansion work.. This created land scarcity in the site and the then
proposed capacity was reduced by about 50%. Around 200 m long excavated pit was
proposed and only 100 m was designed and constructed.
The excavated pit method of land filling was proposed and implemented with the
intention that the use of trench and area method would be highly risky in the absence of
efficient and proper land fill management system. In case of poorly managed land filling
sites, the risks on local environment is relatively low in case of excavated pit method of
land filling constructed with protection layers than the other two methods. It is clear that
the problems and risks in the Messobo site would have been worst than what we heard
today with the excavated pit method, if the trench and area method of land filling were
used in the site.
Actually, a second option of excavated pit land filling method was possible. The same
method of land filling could have been used providing embankment fills on the lower
side of the present land fill areas to form the pit. But the embankment method requires
borrow materials for the construction of the embankment, which is costly than pit
excavation for longer hauling distances. The use of embankment walls on the lower side
also need extra cost for compaction and both faces of the earthen embankment require
protection from sliding and scouring. The excavated pit is a cheaper option than earthen
embankment method of land filling at Messobo. The trench and area method of land
filling would have been the best and cheaper methods of land filling provided that
efficient system of land fill operation is laid at the City Administration or private
institutions level.
The other problem with the land fill at Messobo was absence of impermeable cover
materials for the daily fills. The fills were exposed to nuisance animals, scavengers, wind
effects, and direct precipitation of rainfall during rainy seasons. Because of the openness
of the daily land fill, the site was not environmentally safe and threatened the daily living
of the local farmers and animals. It can be said that the local environment was not fully
protected except the underground aquifer material. Nonetheless, there is no any
protection measure taken in the Quhia site, therefore, it can be said as open dumping site.
The existing land fill sites are operating in uncontrolled manner and became reason for
local oppositions from farmers and administrative bodies especially with the Messobo
site. It is also reported that the same opposition existed when the Messobo land fill site
was first proposed to serve as the disposal site for Mekelle city. The local farmers and
administrators argue that the site was promised to be temporary and the city
Administrators entered a promise to relocate the land fill site. They also promised to
promote waste reuse, recycling, and transformation technologies and to make the local
farmers around the land fill site beneficiaries of the waste collected from the city.
According to municipal reports and recent conditions, all the promises have been broken
Page 20
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 20
to date. In general, problems encountered by the local community living around the land
fill sites can be summarized as
Improper construction and operation of the land fill sites,
Absence of working operation and control guideline for the sites with the view of
protecting the public health and the environment,
Litter of wind suspended plastic materials covered the surrounding farmlands,
The cattle population in the area is affected by the ingesting the plastic materials
and significant death toll of cattle population have been recorded in connection
with ingesting the materials,
Land pollution in relation to plastic and other wind suspended solid waste
materials,
The dumping sites attract huge number of hyena, which is the main scavenger
during night time, and threatened the security of the farmers, their family and
cattle during the night time,
the local Children easily enter into the land fill sites as "innocent human
scavengers" and get endangered,
the flies bred on the land fill sites has imposed serious public health threats on
The local community and
The offensive odor from the land fills also caused nuisance in the community and
threatened the community health.
Since there are no permanent equipments provided for the land fill operation, covering
and compaction operations were not regularly executed in the sites. The institutional
capacity in terms of expenditures for operation and maintenance (OM) did not allow the
regular execution of the operations at the City Administration level in the sites.
4.1.6. Waste Reduction, Recycling and Reuse (3R's)
The modern approach in solid waste management involves waste reduction at the sources,
diversion of waste materials or recycling and reuse of diverted materials. The solid waste
in developing countries and our society mostly contains high proportion of organic
matters, which make the solid waste ideal for recycling through waste transformation
technologies such as vermo-, aerobic- and anaerobic composting, and methane
production. There are also waste materials that could be recycled in manufacturing
processes.
From the observation of the consultant the following 3R‘s practices are customarily used
in the city.
Reclaiming paper from households, offices, schools, universities, etc. for
packing.
Bartering of recovered waste materials for manufactured products involving
Waste materials brokers (WMB‘s).
Recovery of metal scraps centering small scale manufacturing business.
Page 21
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 21
4.1.7. Waste transformation (WT)
An integrated solid waste management (ISWM) system involves waste transformation
technologies. This technology employ physical, chemical and biological conversion
process, namely physical compaction, chemical combustion, and biological oxidation and
digestion of the waste materials. These technical options may be applied to different
fractions of the solid wastes in different categories.
The consultant understood the non existence of any technical data on the current WT
practices, technologies and waste transformation centers (WTC‘s) in Mekelle city.
4.1.8. Special and hazardous wastes
These categories of solid wastes require special attention in the whole management
process for the fact that the wastes mostly cause potential hazards on the environment and
local community and also require special techniques for their management.
Special wastes are mainly discharged from residential, commercial, industrial,
automobile servicing facilities and institutional activities in the city. The special wastes
include bulky items, consumer electronics, white goods, oil, grease, batteries, tires, and
separately collected yard wastes in the house hold and other urban establishments.
The hazardous wastes mainly arise from institutional and industrial activities. The
possible sources of hazardous wastes in Mekelle city are Mekelle hospital and the public
and private health clinics.
4.2. Organization of the existing system and role of Stakeholders
4.2.1. City Administration / Municipality
The municipality nearly takes the full responsibility of waste management activities.
Available Resources
The environmental sanitation and hygiene team in the social services department of the
municipality handles the solid waste management of the city. This team is responsible to
conduct the day-to-day solid waste collection, transportation and disposal activities of the
city and has 94 workers (table 4.2).
Page 22
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 22
Table 4.2 Workers employed on Sanitation and Hygiene team of the Municipality
SN Specific job title Number of employees Remark
Male Female Total
1 Sanitarians 3 - 3
2 Drivers 7 - 7
3 Co-drivers 7 - 7
4 Street Sweepers * * 44 * No data on M&F
5 Public toilet and
Container guards
30 - 30
6 Supervisor - 3 3
7
TOTAL
47 94
Source: Mekelle Municipality Social Services Department, 2004
a. Manpower engaged in SWM activities
Table 4.3 Manpower of the Social Services Department engaged in SWM activities
No
Category
Required & existing manpower based on approved structure
Municipal
head office
MSAS
Tabias
Total
R E R E R E R E G
1 Department head 1 1 - - - - 1 1 0
2 Team leader 1 0 - - - - 1 0 -1
3 Experts professionals 1 0 - - - - 1 0 -1
4 Section head - - 3 3 - - 3 3 0
5 Sanitarian (semi-professional) 1 1 - - - - 1 1 0
6 Sanitation team workers 17 17 21 21 - - 38 38 0
7 Minuchipe (municipal police) - 1 - - 14 14 14 15 +1
8 Administration staff 1 1 - - - - 1 1 0
Total 22 21 24 24 14 14 60 59
R= required E=Existing G=Gap/difference
Source: Mekelle Municipality (Compiled from raw data)
According to the report obtained from Mekelle City Administration [2005], the approved
manpower in the fiscal year for all sectors of the Social Service Department (SSD) is
consisting of a total of 60 job positions out of which 22 are in the municipal head office,
24 in the municipal service areas (MSAs) and 14 in the Tabias of the city (table 4.3).
Observations
Out of the 58 of available manpower engaged in SWM activities, only four (4) are
professional with some years of work experience
Page 23
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 23
The environmental sanitation team workers, who are directly responsible for the
overall sanitation activities in the city, don't have team leader and this job position
is still vacant.
b. Equipments
Table 4.4: available municipal equipments engaged in SWM
SN Equipment Existing Quantity
1 Skip loaders 3
2 Tractor trailer 4
3 Containers 64
Given the rapid city expansion and increased rate of waste generation, these equipments
are not sufficient enough. Moreover, the vehicles spent considerable time in garages for
maintenance purposes. As a result, some neighborhoods do not get service coverage and
some communal containers are not picked on time when they get full.
4.2.2. Private actors
There are two private operators working on primary collection of solid wastes in the city
namely, Gojo and Saba Sanitation Services. The scope of these organizations is limited to
collection and disposing of the wastes into the communal containers and to privately
owned farm site for composting purpose.
Gojo Sanitation Service
Gojo plastic and sanitation Services was established on October 18, 1995 E.C. The
organization has six contact workers, one female and five male. It gives door-to door
waste collection services for residential and institutions like hotels, restaurants and bars.
It also gives janitorial services for some insurance and banking institutions. It has three
wheel carts and one truck with a capacity of holding 15m3 wastes.
The organization collects the solid waste from its clients and performs waste
separation/segregation. It recycle organic fraction of the solid waste and apply to its own
farm land .The service disposes the remaining collected solid waste fraction into the
communal containers.
Gojo has 55 institutional and 200 residential clients respectively (2004). The service
group recently got an urban land area of 2,200m2
free of lease to undertake composting
and horticultural activities. Segregation of the organic and inorganic wastes was assumed
to be done in the allotted urban land. The service group is also introducing a new
technique of solid waste separation to be undertaken at the source of waste generation by
providing the clients with separate plastic bags for the same purpose.
The private solid waste service group Gojo has raised the following problems in relation
to their private business.
Page 24
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 24
The absence of strict regulations and strong enforcement mechanisms has
encouraged polluters to dispose off the waste anywhere.
The absence of regular service charges in the municipality solid waste
management service has motivated their clients to seek service from the
municipality only.
The municipality has problems with the use of external resources like the private
actors in some of the waste management services currently run by the municipal
They have faced financial problems associated with loans in their business.
They believe that less attention has been given to private actors as compared to
cooperatives in the present SW service.
The consultant has observed some interesting initiatives on the side of Gojo private
sanitation service.
The service group has claimed the liability of its own clients and sued a file
charge against them for polluting the environment,
The group issue solid waste holding and collecting plastic bags to their clients
free of charge and
They also educate the public about environment and city sanitation through
pamphlets and other Medias.
Saba Sanitation Services
Saba Sanitation is the second privately owned sanitation agent established to render door-
to-door sanitary services in the city. The group currently renders services in 20
commercial units like hotels, bars, restaurants and other units in the city. The services are
mainly concentrated on the streets and squares of the city such as Godena Guna and
Selam, Romanat and Bazar Squares. Its services also cover 328 residential houses in
different Tabias of the city some of which are Adihawsi, Adishunduhun, Mayduba, Aider,
Sewhinigus and Hadnet among others. The workers of the private group disposed off the
wastes into the nearby communal collection containers after collecting from the different
sources in the services areas.
4.2.3. NGOs and Civil Societies
Though NGOs and civil societies have multi-dimensional role in development, their
participation in Mekelle is limited specially in sanitation. The initiative of some of the
civic societies such as ―Tsebqueley Mekelle‖, which is a local non-profitable community
organization, is the most appreciable. However, there has been low advocacy work
undertaken to mobilize the stakeholders in solid waste management issues so far.
4.2.4. Micro and small enterprises
There are about 3 micro and small enterprises (MSE) operating in the present SW service
in the city: Dilet Tseret, Fire Kalise and Martha sanitation services. These enterprises
negotiate the waste collection fee directly with the beneficiaries and the fees are collected
by the enterprises themselves
Page 25
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 25
The service fee varies from place to place. For instance, the fees range from 2 to 5 Birr
per month around Ayder in the low income group. The service charges in the city center
ranges from 10 to 20 Birr per month. In general, the service providers charge 10 to 15
Birr per household per month on average.
Dilet Tseret and Fire Kalise are engaged in primary collection of wastes from households
to the municipal containers. In addition to this, the former one is involved in occasional
cleaning services during festivals and the later is engaged in the collection of by products
from the municipal slaughter house.
The Current situation within the cooperatives can be characterized as:
Lack of well-coordinated effort with in the cooperatives members.
The communal containers are mostly found full to their capacity during service
hours and the cooperative workers are hence forced to transport the collected
waste over long service distances to find emptied ones.
Their business is dependent more on the ability and willingness to pay by the
households. Therefore, they tend to concentrate on areas where the households
can afford the service charges.
The Martha sanitation service is engaged in the collection of wastes from households for
Bio-farm development. The idea behind this initiative is to train about 100 poor women
on practices of bio-farm technology and make them immediately productive.
The municipality has already allotted 2 hectares of urban land for the project to be used
as a vegetable farm. Moreover, the municipality has prepared a pilot area where the
women would collect organic solid wastes from the city and take it to the pilot bio-farm
supposed to produce biogas and at the same time horticultural products using the bio-gas
slurry (by product) as a fertilizer. The municipality expected that if this pilot project is
proven to be successful, other similar projects will be replicated throughout the city. The
city administration has already allocated budget for this purpose. If the project becomes
successful, it is expected to offer two sets of benefits. On one hand, a significant amount
of solid waste will be recycled and on the other hand a number of poor women will get
employment.
The municipality has supported the bio-farm initiative without undertaking the necessary
feasibility study and compromising the low economic capacity of the poor women.
Because of these failures on the side of the promoter of bio-farm technology, which is in
this case the municipality, the cooperative of the poor women has failed to work as
expected. The lack of cooperative capacity in undertaking proper waste collection and as
the task was found to be tiresome for the weak poor members, who are inactive to travel
long distances in search of the solid wastes, made the number of the members to reduce
to 87.
Besides this, the municipality has not developed any mechanism for regulating and
monitoring the performance of the enterprises and their relationship with the beneficiaries.
Page 26
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 26
This failure on the side of the city Administration has also become one factor that made
cooperative members desperate.
4.2.5. Informal sector
Though difficult to differentiate which is formal and informal in solid waste collection
systems of the city, this assessment takes the itinerant buyers, which are locally know as
Quorales, receivers/dealers/ and wholesalers into consideration. These are people who
collect different types of valuable waste materials for different purposes.
There are more than 100 itinerant waste buyers in the city. The itinerant waste buyers
wander through out the city and buy the waste materials from households and sell them to
their clients and dealers. There are five agents legally registered for retail sell business,
who receive the waste materials from the itinerant waste collectors or waste material
brokers (WMBs). From the focus group discussions held with the waste retailers, a single
agent could receive about 50kg plastic shoes, 40kg of plastics and 50 pieces of different
bottles per day on average. The dealers or merchants sort out the recovered waste
materials and sell to the wholesalers.
The itinerant buyers, dealers, and merchants are not well organized and have financial
problems to enhance their business. They simply sell recovered waste materials to the
wholesalers and wholesale brokers, who have direct contact with the recycling enterprises.
Sometimes there might be direct contact of itinerants and retailers with the recycling
enterprises by passing wholesalers. The flow of recovered solid waste materials can be
easily illustrated as follows.
According to the information obtained from the workers operating in the informal sector,
most recovered materials are plastics, bottles, Shoes, and crop residues locally known as
Hasernifay. These waste materials are distributed to different recycling enterprises such
as plastic and beverage factories, and fattening and dairy institutions.
4.2.6 Role of the community
So far no appropriate mechanism was employed to enhance the participation of the
general public effectively in solid waste management at city level. However,
communities are mobilized to clean their surroundings in the form of campaigns during
some public and local holidays and special occasions irregularly. Even so very scant
proportion of the public participates on such occasions. Such collective actions and
campaigns also lack continuity.
Itinerant waste
buyers
Dealers/merchants
Wholesalers
Recycling
Enterprises
Page 27
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 27
Limitations in community participation are also experienced not only from the point of
view of free labour contribution in cleaning campaign, but also in paying the service
charges levied by the municipality and other actors in the service. Only small part of the
city residents pay sanitation service charges when they pay off visits to the municipality
to make some businesses like paying property taxes, buying or selling properties and
requesting construction permits.
4.2.7 Job opportunities created in Primary collection
Table 4.5 Job opportunities through the collection of solid waste
Source: MSE Cooperative Office and Respective institutions
4.3. Financial aspects
The gap between what the public pays for the sanitation service and the actual cost of
collection and disposal is one of the crucial problems in the solid waste management in
Mekelle. First of all, the revenue level collected by the city is very low and as a result the
budget allocated to the solid waste service is minimal. Secondly, the service fee paid by
the residents is very low and most people are not accustomed to paying waste service fees.
4.3.1 Allocated Budget
The average annual quantity of collected and disposed off solid waste between the period
2002 and 2004 was 14255.33m3 and the annual collected sanitation fee was Birr
230,400.00. This means what the public pays for the collection and disposal was about
Birr 16.16 per unit m3
of solid wastes. But it is estimated that the average annual
allocated budget for collecting and disposing off of solid waste was about 690,812.00
Birr. In other words, the actual rate of solid waste collection and disposal was 48.46 Birr
SN
Name MSE/
institution
Members
Average
Family
size
Total
Remark
1 Dilet Tseret 13 2.5 32.5 No report is available
on the existing statues
of these cooperatives
2 Fire Kalise 15 2.5 37.5 >>
3 Martha sanitation
service
100
3.5
350
Now the members are
reduced to 87
Gojo Sanitation
Service
Saba Sanitation
Service
4 Total 128 420
Page 28
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 28
per1m3, i.e. the public pays only one third of the expenditure on solid waste collection
service rendered by the municipal.
A comparison of what the public pays for the municipality and to the private for the solid
waste collection services rendered is indicated in the table below (Table 4.6) .The data on
services charges clearly indicate that the service rates in municipal services is quite lower
than that of the private sectors (Saba and Gojo ). This is one reason that the public prefer
to use municipal services than private services. The private service providers charge
higher rates for primary collection services, which exclude cost of public solid waste
storage, secondary collection, transportation and disposal to landfill sites.
Table 4.6 Comparison of service charges in municipal and private services
Sr.
No.
Name of enterprise
and institution
Monthly Service charges (Birr)
Remark Residence Institution
1 Saba Sanitation 2 to 5 per month 10 to 100 per month Primary
Collection
2 Gojo Sanitation 10 per month 15 to 100 per month Primary
Collection
3 Municipal 2 to 26 per annum *
2 to 26 per annum* Collection
and disposal
* indicate the annual sanitation fee at Mekelle, which is first rank city, in 7th
and 1st
grade urban lands and the figure indicate ranges of sanitation fee rates;
Source: Respective enterprises
The average daily estimated solid waste generated in the city was about 60.52m3 and the
actual cost of collection and disposal was 48.46 Birr per unit m3 of solid waste. Hence,
the average annual budget required to collect and dispose off was amounting around
1,070,497.55 Birr. But the amount actually allocated was 690,812.00 Birr, which is
64.53 % of the actual budget required on average to fully collect and dispose off the solid
waste generated between 2002 and 2004. This indicates that availability of budget for
solid waste collection and disposal was among the main constraint in the period between
2002 and 2004.
4.3.2. Collected service fee versus needed budget
The average annual collected sanitation fee was Birr 230,400.00 and the average annual
budget required to collect and dispose off solid waste generated in the city in three years
period was about Birr 1,070,497.55. Hence, the collected sanitation fee covers only
21.52 % of the total budget required to fully collect and disposed off the generated solid
waste in the three years time (2202 to 2004 G.C.). .
Page 29
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 29
4.3.3. Modes of service payment
Municipal service:
The charge paid by the residents for waste collection service to the municipal is very
nominal, and the criteria used for determining the fee are also vague both to the payers
and the payees. The residents are made to pay the waste collection fee together with the
land rent or land lease fee on the basis of number of rooms owned by the payer and the
rank of the city as categorized in the annual sanitation fee rates in different cities of
Ethiopia.
The regulation on the annual sanitation fee considered four ranks of cities and Mekelle
belongs to the first rank city category. The fees supposed to be settled by sanitation
service users in different grades of land are indicate under the four classes of cities for
comparison (table 4.7). But direct charging of sanitation fees has become difficult to be
implemented when communal system of waste collection is used.
Table 4.7 Annual sanitation fee based on number of rooms and rank of the city
Urban Land
Grade
Ranking
Annual sanitation fee (Birr)
1st rank city 2
nd rank city 3
rd rank city 4
th rank city
1st 26 20 15 10
2nd
24 15 10 6
3rd
18 9 7 4
4th
12 6 4 3
5th
6 3 2 1.5
6th
3 2 1.5 1
7th
2 1.5 1.25 .75
Source: Mekelle Municipality
The sanitation fee regulation declares that the annual sanitation fee in first rank cities
ranges from 2 to 26 Birr per annum. These rates are to be effected in urban land grades
from 7th
grade up to 1st
grade lands. The sanitation fee increases with the grade of land,
the highest in first grade and the least in seventh grade urban.
As the various land uses in the city exist in different grades of land, it is not possible to
determine here the rates of sanitation fees for municipal services separately for the
various sources of solid wastes in the city. But the minimum and maximum rates are
between 2 to 26 Birr per annum.
Private services:
The service fee paid for primary waste collection by private services is based on
negotiation.
Gojo sanitation Service:
Page 30
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 30
The average service rates are 10, 15, 40, and 100 Birr per month for residential houses,
cafeterias, restaurants and hotels respectively.
Saba Sanitation Service:
Solid Wastes are collected once in a week time from residential houses and daily from
the hotels, restaurants and bars. The agent collects three sacks of waste on the average
from hotels, restaurants and bars per day. The monthly service rates range from two to
five Birr for residential houses and ten to hundred Birr for institutions.
Micro and small enterprises (MSEs):
The micro and small enterprises negotiate the waste collection fee directly with the
beneficiaries. The service fee is collected by the enterprises themselves and it varies from
place to place in the city. For instance, the fee ranges from 2 to 5 Birr per month around
Ayder in low income groups and range from 10 to 20 Birr per month in the city center.
Generally, the MSEs charge 10 to 15 Birr per household per month on average.
4.4. Institutional Structure and Responsibilities
4.4.1 Institutional structure
Page 31
Final Feasibility and Preliminary Design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 31
CITY MANAGER
Administration
Support services Internal Audit
Legal Service Planning and
Information Service
Water Supply Service
Town Planning &
Land Adm. Dept
Land admin. &
registration team
Building Design
& Const. Permit
team
Dept
Town planning
& Urban Design
team
Social Services
Department
Construction &
Contract Admin. Dept
Economic
Services
Department
Revenue &
Expenditure
Department
Municipal
Enterprises
team
Dept
Housing &
Public
utilities team
Community
self-help
programs
Revenue
Collection
team
Revenue study
and assessment
team
Dept
Budget &
Accounts
team
Environmental
Sanitation team
Public parks &
Greening team
Public Protective
Services
Construction &
maintenance team
Contract Admin. &
Supervision Team
Machinery &
Equipment Admin.
team
Deputy City Manager
Municipal
Service Areas
Fig. 4.3 Existing Municipality Structure
Page 32
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 32
4.4.2. Institutional responsibilities
4.4.2.1 City Administration:
The three areas of responsibility of the City Administration in relation to waste
management are given below.
Since July 2003, the Municipality of Mekelle has taken the responsibility for
SWM of the city from the health department of the city;
The Social Service Department (SSD)of the municipality is in charge of the
provision of environmental services;
The city's health department is responsible to under take the regulatory activities
of waste management;
Functions of the Social Service Department (SSD) of the Municipality with regard to
solid waste management are the following.
Develops systems, performance indicators, norms, standards and procedures to
execute its tasks and implement same upon approval;
Assures the provision of waste disposal city services to the required standard;
Ensure the cleanliness & attractiveness of the city;
Coordinate the activities of micro & small-scale enterprises, cooperatives and
NGOs operating on SWM;
Collect and compile data for research;
Develop and administer landfills and transfer stations;
Promote the implementation of waste minimization and reduction in the city;
Promote the development of recycling;
Prepare the city's solid waste management status report;
Review and monitor the implementation of Municipality service Areas (MSAs)
SWM;
Provide solid waste collection and disposal activities;
4.4.2.2 Municipal Service Areas (MSAs):
The Municipality has three Municipal service Areas that provide services to the residents.
The main aim of the MSAs is to provide technical and social municipal services as
service Branches of the city Municipal services with no administrative organ attached to
them.
The functions of the MSAs with regard to SWM are:
Provide information to residents about the municipal services within the
area of jurisdiction;
Assure proper implementation of sanitation and greenery activities within
its area of operations;
Ensure the protection of illegal activities in the area of limit, which
includes illegal waste disposal practices;
Page 33
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 33
4.4.2.3 Tabia2 Level:
There are Municipal Service Desks (MSD‘s), which area established to provide
Municipal services much nearer to the residents. Some of the main functions of the
municipal services delivery desks with regard to SWM are:
Mobilize and ensure the participation of residents in safeguarding
environmental hygiene and sanitary activities.
Control of illegal solid waste disposal activities;
The awareness created so far among the users on legislative issues, the institutional
capacity to implement the policies and regulations and the impact of the policies from the
point of view of improving environmental quality in the city and protecting the public
health and the environment need to be the main focus of our study in relation to
environmental policies and regulations. (for details, refer to Annex I)
2 Lowest administrative unit
Page 34
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 34
5 Data Collection, Projection of Solid waste generation and composition
5.1 Data Collection on Existing Solid Waste Generation and Practice
Rationale
Information available on existing SW rate of generation, composition and source of
Mekelle City is deemed to be scant and the consultant has identified that there is a need
to conduct further investigation on the current situation. Because of these limitations
execution of recent and new projects demands the filling up of missing technical data.
Promise consult discovered that basic technical information do not exist in relation to
existing SW rate of generation, composition and source, which is required to undertake
comprehensive study on Integrated Solid Waste Management (ISWM) and good planning
and design of solid waste management infrastructure for improved SW service. It is with
the intent of filling up the missing data that Promise Consult conducted survey on the
existing solid waste generation, composition, source and practices.
The intention of the survey in general is to find out:
Sources of solid waste in the entire city
Percentage composition of solid waste from the various SW category and sources
Proportion of expected solid waste constituents in the SW categories
Per capita rate of generation in liter/capita/day and kg/capita/day
Properties of SW such as unit weigh(loose, as-discarded, as-disposed, as-compacted
from various sources of generation
Generation of hazardous and special wastes
Approach, methodology and organization of survey employed (for detail, refer Annex D.)
Step 1: Before proceeding to fresh data collection, an attempt was made to collect all the
available data by consulting all the relevant stakeholders and secondary sources.
Step 2: After identifying the data gaps, various checklists, question forms, tabular forms
and questionnaires are prepared to fill the data gap with regard to the following
broader issues
Solid waste generation
Primary Handling and Storage
Primary Collection (PC)
Communal storage
Secondary Collection and disposal
Disposal in land fills:
3Rs and Waste transformation (WT)
Step 3: distribute the questionnaires to relevant stakeholders and simultaneously conduct
field investigation to fill the data gap
Step 3.1: definition of solid waste category
Page 35
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 35
The solid waste categories has been identified for the city examining the existing socio-
economic and investment activities, the status of solid waste management within the
service area and land use information.
Step 3.2: identification of sources of solid waste
Step 3.3: determination of type, composition and properties of the SW for each sources of
generation
a. Residential Sources (01MSW)
All the ten Tabias currently existing in the cities of Mekelle are considered as observation
sites for Residential SW sources taking a total sample size of 3% of the total house
holds (i.e. 1162HHs on the basis of the year 2004 population) in each Tabia. The survey
investigates the total and per capita rates of solid waste generations, proportion of various
solid waste materials in household SW samples, and properties of the Residential SW in
four household socio-economic groups. The SW from Residential sources are
characterized based on a total sample households of 1162 collected from all socio-
economic groups in the Tabias.
Selection of sampling households is made in each Tabia in consultation with the Tabia
Administration offices one week ahead of sampling.
Table 5.1 Distribution of sample household sizes in Residential establishments
SN
Locality
Inhabita-
nts
(2004)
Estimated
Households
Sample
HHs
Number of sample
households for
each income group (Monthly average
income in Birr)
0-
500*
500-1000 1000-2000 >2000
A B C D
1 Aider 24300 4959 149 68 36 27 18
2 Hawelti 25125 5128 153 72 36 27 18
3 Adi Haki 25650 5235 157 71 38 29 19
4 Kedamay
Weyane
27157
5542
166
76
40
30
20
5 Hadenet 26106 5328 160 74 38 29 19
6 Sewhi
Niguse
19000
3878
116
53
28
21
14
7 Adise Alem 18000 3673 110 51 26 20 13
8 Industry 11766 2401 72 31 18 14 9
11 Adi-
shumduhun
6376
1301
39
16
10
8
5
12 Ellala 6515 1330 40 17 10 8 5
Total 189995 38775 1162 529 280 213 140
* City Wide proportion of low income group is more than 70%;
Page 36
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 36
Source: MCPPP
Then standard plastic bags of 1m2 minimum area is issued to each sample house holds
and are advised to store their household garbage honestly and carefully for a minimum
generation time of one week.
As the measurement of observations house-to-house is a cumbersome task, convenient
and centralized observation sites are located within the proximity and boundary of the
sample households. The Enumerators collect household samples on each observation
sites and take all the necessary measurements using the standard forms for recording
observations of generation rate, proportion of constituent and properties of SW.
b. Other SW sources
Efforts have been made to take into account all the available information on the urban
activities as collected, compiled and analyzed by the socio-economic and demographic
team of the City Master Plan Development project.
The socio-economic and service data clearly indicate that the manufacturing, construction,
transportation and service sectors have leading share in the urbanization of Mekelle City.
The construction sector mainly represents the housing and industrial development
activities in the City. These activities are expected to generate significant SW quantities
in different parts of the City, which is not known at the moment.
Therefore, field observations need to be conducted in selected sample urban activities and
services.
Table 5.2 Urban activities in Mekelle city
SN Activities/Socio-economic Aspects
1 Investment shares ranking
Industrial (Manufacturing, construction, and transport)=88.08%
Institutional(Social services and real state)=4.93 %
Commercial(hotel & trade) =3.85 %
Agriculture=3.13%
2 Job opportunity ranking
Manufacturing
Construction sector
Transport
Social service
Hotel
Agriculture
Trade
Real state
3 Services coverage
3.1 Government Health services(year 2002):
Hospital=1
Health centers=3
Page 37
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 37
Cont‘d
Clinics=3
Referral hospital=1 very soon
3.2 Educational facilities
Governmental institutions:
Kindergarten=1
Primary school=20
Secondary school=4
Institutions=3
Public university=1 (Main campus + Adi Haki Campus)
Private institutions:
Kindergarten=13
Primary school= 5
Secondary school=1
Institutions=6
No University
NGO‘s:
Kindergarten=4
Primary school=9
Secondary school=4
No institutions ,colleges and universities
3.3 Digital Telephone(May 2004):
Residential areas=7029 in numbers
Government, NGO‘s, Institutions, and Enterprises=1211
Commercial centers=2677
Others=36
3.4 Water service(July 2004):
Distribution pipe=46.5 km
Availability:
House tape users= 43.9 %
Public tape users=7.9 %
Neighborhood & traditional source users=48.4%
3.5 Market places:
Edaga kedamay woyane
Edaga Adi-haki
Edaga Enda-sellassie
Enda Sewhi-Nigus(Edaga Kedam)
Edaga Aider
Edaga Industry (May Duba)
Edaga Adi-Hawsi
Edaga Adi-Shumduhun
Edaga Quiha
Edaga Aynalem
Livestock market (13903m2 fenced area)
3.6 Enkodo Abattoir:60-70 cattles/day design capacity & actual=33
3.7 16-Orthodox churches: Inside Mekelle,Quiha,& Aynalem
3.8 3- Mosques: Inside Mekelle
Page 38
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 38
Source: MCPPP
Table 5.3: Sample Size
SN Source type Sample size Total number
of samples
Remark
1 Commercial Sources
(02MSW)
10% of the total 463 195 and 268
samples from
commercial
sources inside
and outside the
main market
2 Industrial sources (01ISW):
2 from each
categories of
Standard
Industrial
Classification
30
3 Construction and
demolition (02ISW):
two samples
from each
construction
category
18
4 Agriculture Wastes
(01ASW):
A minimum
sample of ten
activities will
be considered
10
Institutional sources (03MSW):
Table 5.4 Distribution of Samples in institutional sources
Sr.
No
Institutional activities Total
units
No. of
Sampl
e
percentage
sample
size
1 Administration
Tabia offices
Wereda offices
Zonal departments
City Council
Regional Bureaus
Regional Government
Security office
12
2
-
1
-
1
1
2
1
2
1
2
1
1
16.67
50
-
100
-
100
100
2 Private and public services
Consulting firms
Telecommunication service
Electric service
-
2
2
2
1
1
-
50
50
Page 39
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 39
Water service 1 1 100
3 Health facilities :
Hospital
Health centers
Clinics
1
3
3
1
1
1
100
33.33
33.33
4
4.1
4.2
4.3
Educational offices:
Governmental
Kindergarten
Primary school
Secondary school
Institutions
Public university
Private
Kindergarten
Primary school
Secondary school
Institutions
NGO‘s:
Kindergarten
Primary school
Secondary school
1
20
4
3
2
13
5
1
6
4
9
4
1
1
1
1
1
1
1
1
1
1
1
1
100
5
25
33.33
50
7.70
20
100
16.67
25
11.11
25
Total institutional samples 30
Communal container and disposal sites
Field survey is carried out in the existing 64 communal containers site to investigate the
impacts of secondary storage and collection services in the city and collect adequate
technical data for the future improvement of the service.
One field enumerator and observer working under the principal investigator (supervisor)
moved in all the containers and collect the desired information.
A second enumerator is assigned for the observations to be taken at the disposal sites and
the contents of the survey are also different for the investigation at the disposal sites.
5.2 Projection of Solid Waste Generation and Composition
5.2.1 Population projection
5.2.1.1 Base Data
According to the recent administrative set-up, the city of Mekelle consists of municipal
areas with respective population as indicated in table 5.4.
Page 40
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 40
Table 5.4: Population Size (as of July 2004)
SN Municipal area Population Size Source
1 Main Mekelle 154,698 CSA,2003
2 Quiha 15,672 CSA,2003
3 Aynalem 4,008 CSA,2003
4 Small villages 32,930 Mekelle
Municipality
Total Population of Mekelle City as of
2004
207,308
Growth trend and average family size
The total average family size for city of Mekelle is 4.9 persons.( Finance and Economic
Development Office, October 2003)
5.2.1.2 Methodology
Table 5.5: Population Trend
SN Year Growth rate
1 1965-1970 4.6%
2 1970-1978 5.1%
3 1978-1984 6.3%
4 1994-2004 4.4%
5 2004+ 4.4%
Source: Finance and Economic Development Office (October 2003)
Assuming that the existing population growth rate would remain the same for the
planning period seems unjustifiable as it is difficult to control and dictate the population
policy, the economic growth rate, cultural attitude, security etc. Therefore to minimize
the risk of over and under estimation of population size, it has been professionally
expedient to assume the medium growth variant which is 5.4 in our case for future
population projections.
Population forecasting scenario
Geometric method:
The kinetics:
Pdt
dPK g
Population:
Ln Pt = Ln P1 + Kg (Tt - T1)
Growth rate:
TTPP
Kt
t
g
LnLn
1
1
Where Kg is population growth rate
Page 41
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 41
Pt is projected population size at time Tt
P1 is base year population (i.e. at time T1)
Table 5.6: Projected Population size of Mekelle from Medium Variant (5.4%)
Year Population size
2004 207308
2005 218810
2006 230951
2007 243765
2008 257290
2009 271566
2010 286634
2011 302538
2012 319324
2013 337042
2014 355743
2015 375481
2016 396314
2017 418303
2018 441512
2019 466009
2020 491865
2021 519156
2022 547961
2023 578364
2024 610454
2025 644325
2026 680075
2027 717809
2028 757636
2029 799673
2030 844043
Page 42
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 42
5.3 Results of the survey
Table 5.7 Generation rate of residential establishments Tabia wise
SN Tabias Per capita per
day volume
Per capita per
day weight
Per capita per
day unit weight
(l/c/d) (Kg/c/d) (Kg/cu.m)
1 Addis Alem 0.989 0.322 434.27
2 Industry 0.641 0.271 573.63
3 Sewhi Negus 0.713 0.171 272.98
4 AddishumDhun 1.276 0.275 242.91
5 Kedamy Weyane 0.936 0.279 456.76
6 Aider 1.115 0.352 362.20
7 Hadnet 1.133 0.325 286.12
8 Hawltie 0.560 0.148 373.62
9 Adi Hakie 0.948 0.267 337.70
10 Mekelle City 0.924 0.268 371.13
Residential Per Capita Rate of
Generation(Volume)
0.989
0.713
1.276
1.115
0.560
0.948
0.641
0.936
1.133
0.924
0.000
0.200
0.400
0.600
0.800
1.000
1.200
1.400
Tabias
Per
capita g
enera
tion(liter/
day)
Addis Alem
Industry
Sewhi Negus
Addishum Dahan
Kedamy Weyane
Aider
Hadnet
Hawltie
Adi Hakie
Mekelle City
Page 43
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 43
Residential Per Capita Rate of
Generation(Weight)
0.322
0.171
0.352
0.148
0.2670.271
0.275
0.279
0.325
0.268
0.000
0.050
0.100
0.150
0.200
0.250
0.300
0.350
0.400
Tabias
Per
capita g
enera
tion(K
g/d
ay) Addis Alem
Industry
Sewhi Negus
Addishum Dahan
Kedamy Weyane
Aider
Hadnet
Hawltie
Adi Hakie
Mekelle City
Unit Weight of Residential Source
434.27
272.98
373.62337.70
573.63
242.91
456.76
362.20
286.12371.13
0.00
100.00
200.00
300.00
400.00
500.00
600.00
700.00
Tabias
Unit W
eig
ht(
Kg/c
u.m
)
Addis Alem
Industry
Sewhi Negus
Addishum Daha
Kedamy Weyane
Aider
Hadnet
Hawltie
Adi Hakie
Mekelle City
The rate of generation is known to be changed through out the service life time of the
project. Among other factors economic status of residents is the main reason. However
due to the difficulty of predicting the dynamics of economic change and lack of previous
records to be used for trend analysis the rate of generation is forecasted using
probabilistic model.
Model Equations for forecasting the rate of generation
per capita rate of generation (l/c/d) Y=0.3215Ln(X)+1.2371 where X is frequency
factor
1
arPlanningYe
arPlanningYeX
per capita rate of generation
(kg/c/d) Y=0.0913Ln(X)+0.3568
unit weight(kg/cu.m) Y=127.61Ln(X)+495.62
Page 44
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 44
Table 5.8 Forecasted rate of generation
Year 2004 2005 2006 2007 2008 2009 2010 ……..…..
Planning year 0 1 2 3 4 5 6
……..
Frequency
factor(X) 0.500 0.667 0.750 0.800 0.833 0.857
…………
Rate of
generation (Y) 0.924 0.924 1.014 1.107 1.145 1.165 1.178
…………
Page 45
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 45
Table 5.9 Constituents of solid waste generated from residential sources
Grass>50mm 5.15 2.47 3800.49 6357.8429 8540.306 532.624 878.6106 1184.8
Grass<50mm 7.24 3.56 5342.82 8938.016 12006.18 767.669 1266.338 1707.65
Food wastes 2.87 3.5 2117.94 3543.1086 4759.355 754.731 1244.995 1678.87
Broken glass 0.02 0.54 14.7592 24.690652 33.16624 116.444 192.0849 259.026
Non-broken 0 1.72 0 0 0 370.896 611.826 825.044
Rubber 1.86 1.37 1372.6 2296.2306 3084.46 295.423 487.3265 657.157
Ceramics 0.61 3.98 450.155 753.06489 1011.57 858.236 1415.737 1909.11
Leather 0.97 1.26 715.82 1197.4966 1608.562 271.703 448.1981 604.393
Garment & Textiles 3.05 5.4 2250.77 3765.3244 5057.851 1164.44 1920.849 2590.26
Paper 9.06 5.06 6685.9 11184.865 15024.3 1091.12 1799.907 2427.17
Tin cans 0.09 0.62 66.4163 111.10793 149.2481 133.695 220.5419 297.4
Catha Edulis 0.66 0.94 487.053 814.79152 1094.486 202.699 334.37 450.896
Ash 20.7 30.92 15275.7 25554.825 34327.05 6667.51 10998.64 14831.6
Ferrous 1.01 0.88 745.338 1246.8779 1674.895 189.761 313.0273 422.116
Fruits & vegetables 8.21 7.02 6058.64 10135.513 13614.74 1513.77 2497.104 3367.33
Bones 0.67 0.43 494.432 827.13684 1111.069 92.724 152.9565 206.261
Special Wastes 0.31 15.27 228.767 382.70511 514.0767 3292.78 5431.734 7324.67
Yard Waste 8.32 6.07 6139.82 10271.311 13797.15 1308.92 2159.177 2911.64
Constituents of MSW from
Residential Sources
Proportion
Yearly volume Yearly weight
2005 2010 2015 2005 2010 2015
% by
Volume
% by
Weight (cu.m) (cu.m) (cu.m) (ton) (ton) (ton)
Page 46
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 46
Bulky items 0 0 0 0 0 0 0 0
Consumer electronics 0 0 0 0 0 0 0 0
Plastics 12.8 5.91 9445.87 15802.017 21226.39 1274.42 2102.263 2834.89
Hazardous wastes 2.57 1.75 1896.55 3172.7488 4261.861 377.365 622.4974 839.435
Other wastes & fines 13.83 7.31 10206 17073.586 22934.45 1576.31 2600.261 3506.44
Total 100 105.98 73795.86 123453.26 165831.18 21563.73 35571.28 47967.70
Cont‘d
Page 47
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS
47
Summaries of rate of generation and composition are presented on table 6.10 and 6.11
respectively.
Table 5.10 Summary of Rate of Generation from Commercial sources
Rates & Quantities of solid waste
2005 2010 2015
Average rate of generation(l/unit/d) 5.52 5.52 5.52
Average rate of generation(kg/unit/d) 1.15 1.15 1.15
Total number of commercial units 2677.00 3265.94 3984.4468
Average annual quantity of (cu.m/yr) 5393.62 6580.22 8027.86
Average annual quantity (kg/yr) 1123670.75 1370878.32 1672471.54
Average monthly quantity cu.m/m) 449.47 548.35 668.99
Average monthly quantity kg/m) 93639.23 114239.86 139372.63
Average weekly quantity (cu.m/wk) 103.72 126.54 154.38
Average weekly quantity (kg/wk) 21609.05 26363.04 32162.91
Average daily quantity (cu.m/d) 14.82 18.08 22.05
Average daily quantity (kg/d) 3087.01 3766.15 4594.70
Table 5.11 Constituents of MSW from commercial sources
Proportion
(% by volume)
Yearly volume
2005 2010 2015
(cu.m) (cu.m) (cu.m)
Grass>50mm 0.00 0.00 0.00 0.00
Grass<50mm 5.17 277.82 340.47 415.37
Food wastes 0.64 34.12 41.82 51.02
Broken glass 0.00 0.00 0.00 0.00
Non-broken 0.00 0.00 0.00 0.00
Rubber 1.00 53.69 65.80 80.28
Ceramics 0.00 0.00 0.00 0.00
Leather 1.66 89.16 109.27 133.31
Garment & Textiles 6.50 349.24 427.99 522.15
Paper 7.80 418.65 513.06 625.93
Tin cans 0.07 3.55 4.35 5.30
Catha Edulis 2.54 136.56 167.35 204.17
Ash 0.88 47.49 58.20 71.01
Ferrous 6.83 366.82 449.54 548.44
Fruits & vegetables 13.52 726.15 889.89 1085.67
Bones 0.00 0.00 0.00 0.00
Special Wastes 0.00 0.00 0.00 0.00
Yard Waste 7.47 401.19 491.66 599.83
Bulky items 1.17 62.88 77.06 94.02
Consumer electronics 0.00 0.00 0.00 0.00
Plastics 12.64 678.53 831.54 1014.47
Page 48
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS
48
Hazardous wastes 2.33 125.20 153.43 187.18
Other wastes & fines 29.69 1594.02 1953.47 2383.23
Total 99.92 5365.09 6574.89 8021.36
% Error 0.08
Table 5.12 Summary of Rate of Generation for Institutional Sources
Rates & Quantities of solid waste
2005 2010 2015
Average rate of generation(l/unit/d) 10.76 10.76 10.76
Total number of Institutional units 233.00 298.00 375.00
Average Total annual quantity 20903.45 30419.92 36142.06
Average monthly quantity of
MSW(cu.m/m) 1741.95 2534.99 3011.84
Average weekly quantity of
MSW(cu.m/wk) 401.99 585.00 695.04
Average daily quantity of
MSW(cu.m/d) 57.43 83.57 99.29
Table 5.13 Constituents of MSW from institutional Sources
Proportion
(% by volume)
Yearly volume
2005 2010 2015
(cu.m) (cu.m) (cu.m)
Mixed MSW(more of organic matters) 20.43 4270.04 4270.04 4270.04
MSW paper 36.36 7600.31 7600.31 7600.31
BMW 43.21 9033.10 9033.10 9033.10
Total 100.00 20903.45 20903.45 20903.45
Page 49
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS
49
6 System Analysis, Design and Recommendations
6.1 General design approach
Sources : 01MSW 02MSW 03MSW 01MSW
Rejects to land fill site
Recyclables to local market & processing
Ferrous Materials to local market
Ash to make blocks & bricks
Manure or cow dung from ASW
Saw dust from Woodworks (01ISW)
Urea from Human and Animals waste or
synthetic
Sewage sludge from liquid waste
collection & treatment; from sludge drying
bed;
Water to adjust moisture content & control
evaporation losses
Watering to adjust
Moisture Content
Receiving area
(Material Recovery Facility, MRF)
Packing Qualified
Compost Mass
Collection
(Hauled-container or
Stationery-container System)
Manual
Waste sorting
Storage
& Pilling
Shredding, grinding or
Crushing
Organic waste materials
(Including paper)
First Phase Aerobic
Composting (Thermophilic)
Second Phase Aerobic
Composting (Mesophilic
Maturing Phase)
Manual Screening Figure 5.1 General
design approaches
Sell to local
market
Page 50
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS
50
6.2 Technical Issues in primary collection services
Important technical issues that need to be addressed in the primary collection service are
listed hereunder.
Prevailing strong-wind of Mekelle and its consequence of blowing light
solid waste materials during primary collection;
Primary collection in low-income group;
Affordable primary collection service charges;
Balanced service charges in private and municipal services;
Efficient primary collection in all service areas;
Collection in alleys ,streets and outskirts;
Improved primary collection in residential , commercial, and institutional
units;
Improved communal storage facility for convenient uses in labor as well
as equipment based primary collections;
Waste brokery in primary collection services;
Waste separation in primary collection operation and
Waste separation ,storage and recycling at drop-off and buy-back centers;
Illegal use of child labors in primary collection;
Monitoring of functions and performance of primary collectors;
Data records in primary collection activities;
6.3 Secondary Collection Route scenarios
Route Scenario-I: Hauled Collection System (HCS) from HC locations to MRF
In this scenario hauled containers will be transported to Material Recovery Facility for
wasted separation, processing and other scopes of MRF stated under section 5.5.3. In this
scenario average Unit cost of operation for an average round trip, i.e., 9.7Km, as derived
from existing performance cost is 4.30 birr. Taking the year 2004 as a base year for every
data, existing system performance, equipment and unit cost of operation when adopting
the proposed systems are presented hereunder.
Route Scenario-II: Hauled Collection System (HCS) from MRF locations to Landfill
Site
In this scenario the rejects from the MRF will be transported to landfill site. The Average
Unit cost of disposal as obtained from valuation of existing collection systems is used to
estimate operational cost of MRF-Landfill transportation round distance of the operation
in concern is 14.6 Km and operational distance and cost are 14.6Km and 6.30 birr
respectively.
Page 51
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS
51
6.4 Design
Under the general design approach two options are considered. In the first approach
100% efficiency of collection is targeted to be achieved on 2020 while in the second
option 100% efficiency is intended to be reached on 2010. The two options are forwarded
to give opportunity for the city administration choices, compare them with its financial
capability and decide on the implementation. In order not to compromise the sanitation
situation of the city different mechanisms are proposed to divert waste at source before
getting far from the generators.
Option 1:
N.B. Proposed soft and hard components of the ISWM SCHEME for years
beyond 2015 should be taken cautiously; since socio-economic, political and
technological dynamics are difficult to predict for more than 10 years.
Furthermore data used on demographic, economic and spatial aspects are
adopted from Mekelle plan preparation project whose planning period is
10years.
Key Assumptions
Existing coverage of SW collection is 34%
Target set is to increase the efficiency to 100% on 2020
Intensive waste reduction scheme has to be followed till maximum
service improvement is attained.
It is Intended to divert waste at source through waste reduction and
transformation practices at low income inhabitants (75% of total)
* Organic components
* Other recyclables (plastics, rubber, paper, tin, ferrous materials, etc.)
* 100% diversion is set to be
attained on 2010
* This scheme launches at 25%
efficiency on 2006
* Role of waste material brokers (WMB), material drop-off and
buy back centers is vital
* Awareness creation and assistance to introduce the system and
encourage WMB's
* Secondary collection of waste for high income group (25% of total)
* 100% collection by private
sector on 2010
* Launches on 2006 with 25%
capacity
* Design life of loaders is 10 years; for existing 3 loaders 5
years is assumed
Page 52
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS
52
Option 2
Key Assumptions: Meeting set coverage, 34% to 100% in a period of 2005-2010, at the same time
keeping the environment clean
* Existing coverage of SW collection is 34%
*Target set is to increase the efficiency to 100% on 2010
* Intensive waste reduction scheme has to be followed till maximum service
improvement is attended.
* It is Intended to diverted waste at source through waste reduction and transformation
practices at low income inhabitants (75% of total) constituents considered are:
* Organic components
* Other recyclables (plastics, rubber, paper, tin, ferrous materials, etc.)
* 100% diversion of each item is set to be attained
on 2010
* This scheme launches at 25%
efficiency on 2006
* Role of waste material brokers (WMB), material drop-off and buy
back centers is vital
* Awareness creation and assistance to introduce the system and
encourage WMB's
* Collection of waste for high income group (25% of total)
* 100% collection by private sector on
2010
* Launches on 2006 with 25% capacity
* Design life of loaders is 10 years; for existing 3 loaders 5 years is
assumed
Page 53
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 53
6.5 MATERIAL RECOVERY FACILITY (MRF)
Labor intensive material recovery facility (LIMRF) is proposed to provide waste
separation for commingled MSW and materials escaping source separation at recovered
and recycling materials drop-off and buy-back centers located in the city. The MRF will
also serve as decentralized composting facility.
6.5.1 Site selection for MRF
For optimum location of material recovery facility Mekelle City Development Plan,
which is now on the verge of finalization, is consulted (Figure 6.1)
The site for such facility is located in the industry zone as shown on figure 6.1. This site
is ideally suitable for the facility because of the following reasons:
According to the national urban planning manual description of compatibility of
land uses, the proposed facility can be sited on the selected area.
The facility is located adjacent to proposed sewage treatment plant hence this
condition presents opportunity of using the sludge from the treatment plant to be
used in compost preparation as one component.
The whole area is shielded from other land uses using green buffer.
As can be witnessed even at recent time, establishment of plastic factories;
factories which have recycling capacity can likely be established in the coming
future in the industry zone. These factories can be potential customers of the MRF.
According to the twenty years development plan, in a reasonable distance from
the MRF location a considerable area is allocated for urban agriculture. Urban
agriculturalists practicing in the area can easily be involved in compost
manufacturing process and they will also be potential users of the out put.
Page 54
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 54
Figure 6.1 Structural map (Source: Mekelle city plan preparation project)
Page 55
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 55
6.5.2 Engineering aspects of material recovery facility (MRF)
The various Engineering considerations used in preliminary design of the MRF for
commingled MSW are discussed in this section.
Material recovery facility will have the following functions:
Separation of all kind of recoverable waste materials from commingled
MSW collected from Residential, commercial and institutional sources;
Diversion of waste from land fill sites;
Production of quality marketable compost from biodegradable organic
fraction and pack the product at the MRF site;
To transfer recyclable materials other than organic waste to desired
processing locations;
To transport non diverted waste to land fill site ;
6.5.3 Scope of MRF
Selection of materials to be separated at the MRF sites;
Scenario-I: Materials Recovery from Commingled MSW and ISW with maximum
organic fraction
The separation and recovery of the following solid waste materials will be considered at
the MRF site.
(a) Organic waste fraction from MSW sources;
(b) HDPE and LDPE plastic materials from MSW sources;
(c) House hold battery from 01MSW & 02MSW;
(d) Granular materials and wood from construction wastes;
(e) Woody materials from MSW;
(f)Glass from MSW;
(g)Rubber from MSW;
(h) Ferrous materials from MSW;
(i)Tin cans
(j) Bulky items
Scenario-II: Materials Recovery from Source separated MSW and ISW with
maximum organic fraction
The separation and recovery of various waste materials such as glass, rubber, plastic
materials, tin cans and ferrous materials could possibly be done at drop-off centers and
buy-back centers. Primary collection and curb side collection systems could be
introduced in waste separation and recovery of recyclable waste materials.
In this scenario, the MRF site could be used for separation and recovery of organic
fractions and construction wastes.
Page 56
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 56
Scenario-III: Materials Recovery from Source separated MSW and ISW with
minimum organic fraction In this scenario, the majority of the organic fraction MSW will be recovered in low
income house holds and only the organic waste from other economic group, commercial
and institutional units reach the MRF site. The MRF also separate and recover
construction wastes.
6.5.4 Lay out and design of physical facilities
6.5.4.1 Components of the MRF
Unloading areas for commingled MSW
Unloading area for source separated MSW materials
Sizing area for presorted and on-site sorted materials where undersized and
oversized organic wastes are removed
Unit operations (conveyors, shredders, and screens);magnetic separators will not
be incorporated; conveyors, screens and shredders should be simple and locally
manufactured equipments; Use of manual labor instead of conveyors, shredders
and screens shall be considered ; labor intensive unit operations are cheaper than
the use of equipments;
Sizing of storage areas and out loading area for recovered materials;
Sizing of parking areas and traffic flow patters in and out of the MRF;
Sizing of Stage-I and Stage-II Composting units;
Sizing of packing and storage area for matured compost;
6.5.4.2 Composting unit design
The selected composting units are open windrow as these units require least resources in
composting practices. The possible materials and geometry of the reactor are:
Rectangular steel tank
Rectangular wooden tank
Triangular steel tank
Triangular wooden tank
Triangular wire mesh tank
Rectangular wire mesh tank
Triangular reactors require more space in terms of plan area than rectangular reactors and
the rectangular ones are suitable in areas where there is space limitation. As there is space
limitation in urban areas, the use of rectangular reactors is highly commendable.
Thermophilic composting unit
In this unit Shredding, blending and seeding of appropriate proportion of MSW with
digested sludge, raw sludge ,cow dung, poultry manure, biogas slurry and sawdust, and
water is considered and the optimum mix proportion of each fractions required for
optimum performance of windrow aerobic composting units are determined. Labour
intensive mixing and turning for a period of 25 to 27 days while maintaining the required
temperature is important.
Mesophilic composting unit
Page 57
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 57
At this stage, which take 24-26 days maturing, screening and packing will be done.
Space requirement (ha.)
Year Termophilic unit
(1)
Mesophilic unit
(2)
Total area(1&2)*1.5
2005 0.171 0.17 0.51
2010 0.278 0.27 0.825
2015 0.336 0.32 0.99
Detail design and specification is presented at Annex-x.
Estimated Cost of capital (excluding land value)
The cost of material high-end MRF with feed stock derived from processing of
commingled wastes; with enclosed building with concrete floors, MRF equipments with
unit operations (shredding, screening and conveying system, and in-vessel composting;
enclosed building for curing of compost product is between 25,000 to 50,000 birr per ton
per day. This is equipment and capita intensive facility and 25 to 50 % cost reduction
could be achieved in labor-intensive windrow composting facility
Estimated cost of MRF (2005-2010):
Capital-intensive MRF: 843375 to 1686750 Eth.Birr
Labor intensive MRF: 421688 to 843375 Eth.Birr
6.6 Proposed landfill
6.6.1 Initial Site Selection
The site selection and proposal was undertaken by Ad hoc committee consisting of
multidisciplinary professionals. The committee adopted the following initial criteria in
selecting two land fill sites west of Mekelle city at Adi Kolomay.
Geological conditions
Climate
Accessibility and proximity
Land use and ownership
Safety
Public acceptance
The details of the initial site selection criteria can be referred in Annex-Q. The committee
also submitted site investigation report on the proposed land fill locations at ST-1, figure
5.2. The technical data included in the initial investigation report has been considered in
the preliminary design of the land fill site. The information of the proposed site has also
been used in the assessment of the potential impacts of the land fill project decision.
Page 58
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 58
Quiha, one of the Tabias of the city is located at a distance of 10Km from the center of
―proper Mekelle‖ with a population of 18000, is being served by an open damp which is
situated at 4 Km distance from Quiha.
The other fact that needs attention is the existence of Alula Abanega Airport at that Tabia.
Consultation with Mekelle City Plan Preparation Project revealed that in order to respect
the aviation zone, landfill can not be considered with in 6Km radius.
Taking in to account the issues raised above for a Tabia with a population of 18,000 the
feasibility of establishing another disposal site is unlikely. In the proposed system Quiha
is intended to be served by the disposal facility to be located at Adi Kolomay.
Landfill site investigation report on the geology of the area reveled that the geological
setting of the project area is thick sedimentary sequence exposed by shale with very thin
layer of limestone intercalations. The area exhibit very thick, horizontally bedded, light
yellow, fine grained and highly weathered shale. The dominant geological structure in the
area is bedding structure; the bedding plane is tight.
Though the site selection was conducted before the awarding of the contract, Promise
consult has verified and accepted the recommendation of the ad hoc committee.
Moreover, for detail investigation of the site four test-pits, three at opposite sides of the
periphery and one at the center are dug to a depth of 3m in order to identify the lateral as
well as vertical continuity of the formation. Supporting the geological investigation, in all
the test pits shale-limestone sequence with shale being dominant is observed. Extent of
shale dominance is near to100%. It is also worth mentioning that shale exhibits a
property of water tightness and workability.
6.6.2 Preliminary design
Three different types of land fill can be considered depending on the operation and
engineering aspects of the dump sites. These are Uncontrolled Non-engineered Open
dump landfill, engineered land fill and Highly Engineered Sanitary land fill site. Here the
term land fill simply refer to the placing of solid waste materials into a land disposal site
without prior treatment and preparation. The term land fill also refer to the physical
facilities used for the disposal of solid wastes in the surface soils of the earth. The method
of land filling could be area method, trench method/excavated pit method, embankment
and canyon /depression methods depending up on the suitability of the land area
considered for disposal.
Uncontrolled Non-Engineered dump landfill is the oldest and widely used in most
developing countries. In this type of land fill, provisions are not mostly made for the
control of loss of chemical pollutants mainly leachate into the underground environment.
The Non-Engineered dump landfill does not protect the local environment and not
recommended especially for hazardous solid waste materials. In case of engineered land
fill site, the local environment and the underground aquifers are protected from risks of
pollution and nuisances. The Engineered land fill site has some features to protect the
underground aquifer from risks of chemical pollution due to hazardous chemicals, leach-
ate, and methane.
Page 59
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 59
There are also some other accepted categories of land fill sites. These include
conventional type for commingled MSW, landfills for milled or shredded solid wastes
and monofills for designated or specialized wastes .The monofills type can be used for
individual or mixed hazardous wastes. Land fills can also be designed for special purpose.
These include landfills designed for maximum methane production and land fills
designed for integrated treatment units.
The proposed sanitary land fill sites will serve as final disposal sites for directly
transported hazardous wastes and for non-hazardous materials rejected at material
recovery sites.
The proposed land fill sites will provide waste filling areas during dry and wet seasons.
The dry season filling sites serve from October to May for a total of eight months in any
year. The wet season filling sites will be used between June to September, which are the
rainy seasons in the city, for a period of four months in any service year.
6.6.3 Proposed layout
The proposed sanitary land fill sites will have the following components.
Temporary All-weather Access Road within the site (7-10 m)
Permanent paved or weather Access Road to the land fill site(7-10m)
Equipment Shelter equipments:1-Tractor and 1-bulldozer and a compactor
Employees Shelter(operators and Guard)
Holding area for Special and hazardous wastes
Storm water drainage ditch & flow direction
Wet Weather active filling area
Dry weather active filling area
Future fill area: wet and dry weather
Permanent property fence area
Movable fence to separate completed and active filling sites;
Fence
Gas collection and exhaust line;
Leachate collection system and evaporation pond for its treatment
Stock pile area for earthen cover material
Green area and plants
Gas monitoring wells
Entrance Gate
Weighing bridge
Movable screen walls fixed on metal frames to retain blowing waste
Materials;
Page 60
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 60
These above components are conceptually arranged to form the land fill sites. The
property lines delineate the land fill sites.
6.6.4 Design considerations
The following design factors are considered to produce the preliminary design of the
proposed sanitary land fill site.
(i) Landfill areas
The areas used for filling daily waste loads that will be received at the land fill sites are
computed separately for hazardous and special wastes (HW) and non-hazardous wastes
(NHW).The future filling area requirements are also determined.
The desired land filling areas are determined for each years till the year 2030 and can be
seen on the spread sheet ‗demand projection‘ attached in annex-A.
(ii) Land filling methods
All type of land fill methods are considered in feasibility study. These are area method,
excavated pit method, canyon method, trench method, and depression method. The most
feasible option is chosen considering terrain characteristics and the availability of
covering material at the land fill site.
The possible methods of land filling at the two land fill locations are area Method and
Excavated pit method.
Even though the terrain West and South of ST-2 site allows the use of depression and
canyon methods of land filling, these two methods are not considered as the mountain
slope is protected and conserved terrain. The other three methods of land fill are proposed
at the top of the mountain terrain (Site ST-2).The use of steeped type or terraced type of
land filling will also be considered.
(iii) Intermediate cover material:
The shale materials identified at the sites could be used as covering earthen materials
during the operation of the land fill sites.
The typical waste-to-cover ratio ranges from 5:1 to 10:1 and an average waste-to-cover
ratio of 7.5:1 is considered in preliminary design work.
(iv)Surface drainage
Peripheral paved ditches are proposed to divert upland runoff and runoff occurring within
the land fills areas. The finished grade of the ditch shall be 3 to 6%.
The discharge from storm water ditches will be stored in open ponds and considered for
reuse at the land fill sites. At least the water requirements for the compaction of covering
earthen materials will be satisfied from the storage pond.
Page 61
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 61
(v) Landfill liner
Economical land fill liner materials shall be considered such as single layer clay materials
preferably available on the site and the shale material identified at the land fill site could
be considered as a liner material as well.
The site investigation report suggested that leaching waste materials are not easily
infiltrating the shale to contaminate subsurface flows.
The bed liner material will be constructed to have finished
- Cross slope 1 to5 % and average 3%
- Maximum flow distance in any direction = 30 m
- Slope of drainage channels =0.5 to 1%
(vi) Leachate collection and treatment
Perforated leachate collection pipes will be provided at the bottom of the land fill site and
the collected lechate will be treated with simple evaporation pond.
The preliminary specifications for the perforated collection pipe are the following.
-Slope of lechate collection pipe ranges from 1 to 2%
-Size of perforated leachate collection pipe shall be 100 to150 mm
- the pipe material shall be either UPVC or PVC
-the pipe spacing shall be 6.00 m center to center
The depth of evaporation ponds or soil bed is typically 0.60 to 0.90 m with organic
lechate loading rates of about 1.60 to 4.00 kg/m3 soil.
The evaporation pond should be covered during rainfall seasons (June, July, August and
September months) and uncovered in dry seasons when the solar radiation is sufficient
for evaporation. Thin-film black plastic materials like geo-membranes could be used as
covering materials.
The soil beds should also be provided with liner material to control percolation of organic
leachate into sub-surface environment. Clay liners could be considered as cost-effective
methods than geo-membranes.
The percolation rates through clay liners and existing geological material expected at the
land fill bed grade can be calculated from the water balance for a soil material given by
∆ SLC=P-R-ET-PERSW
Where, ∆ SLC= change in amount of water held in storage in a unit volume of geological
or liner or cover material, mm; P=amount of precipitation per unit land fill area, mm;
R=amount of runoff per unit land fill area, mm; ET=amount of water lost through evapo-
Page 62
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 62
transpiration per unit land fill area, mm; PERSW = amount of water percolating through
unit area of soil bed into
compacted or natural geological stratum, mm
Appropriate values of runoff coefficient and bed slope used to calculate runoff from
monthly values of rainfall at the land fill site. Energy methods like Pen-man and values of
climatic variables of the land fill site will be applied to account for evapotranspiration.
The computed annual percolation rate at the soil beds will be compared with the
coefficient of permeability of clay liners to check for the potential of leachate and other
contaminants percolation through sub-surface geological materials. Liners will be
provided for excess percolation rates above the values observed in natural clay materials.
Analytical computation for the determination of breakthrough time of leachate to
penetrate a clay liner is attached in annex-y.
(vii) Gas management
Minimum gas generation is expected from paper and textile wastes as most of the organic
fraction will be recovered in decentralized material recovery facility (MRF) or
decentralized biogas units (DBU).
The land fill site is designed for land filling of rejected materials at recovery facilities and
there will be no recovery of energy in the form of methane at the proposed land fill sites.
Generated methane will be collected and exhausted to the open atmosphere.
- Collection well and pipes;
- Condensate to trap water vapor;
- Vacuum suction pump with 3.00 m water head(operating pressure);
- Gas Exhaust line ;
There will be no energy recovery facility at the proposed land fill site.
(viii) Ground water protection
The direction of ground water flow is identified from the topography map and diversion
of ground water flow to the land fill site is considered with use of perimeter drains or
other control methods; the two sites exist at highest elevations (2080 m amsl and 2097 m
amsl) than the surrounding location and interception of ground water flow is not expected
at these to locations. The clay liner provides protection for the contamination of ground
water flow.
(ix) Fire protection
Water shall be stored on the site for the following uses.
- protect fire
- for land fill crews
- for compaction
Page 63
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 63
Water for land fill crews and equipments shall be provided with storage tanks and shall
be supplied from the city. The other water demands could be satisfied from storage pond.
(x)Environmental requirements
Continuous monitoring of lechate and gas developments from the site shall be
implemented. The periodic inspection could be made with mobile experts from the city.
(xi) Cell design
The fill cells will be provided for the filling of both hazardous and non-hazardous wastes
delivered to the land fill sites. The specifications for the land fill cells are given here.
-cells provided for daily waste materials and covered with 15.00 cm clay or shale
material;
-Height of lift including cover material ranges from 3.00 to 4.30 m;
A maximum height of lift of 4.30 m is considered to minimize land area requirement at
the proposed landfill locations. See the Annex-M for details.
Fig 4.2 Landfill layout:
6.7 Access road
Access road for the landfill is considered to be for two design phases. In the first phase
existing dry weather road will be up-graded to RR-50 road; the design and survey data
are incorporated in the attached map. In the second phase, when the master plan road
network plan is realized the outer most ring proposed by the master plan is realized, it
will be taken as access for the site.
Page 64
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 64
7 Environmental Impact Assessment
The Leopold matrix method has been used to assess the impacts of project activities and
project decisions proposed on the waste management facilities such as primary collection
and communal storages, sanitary land fill, access road, waste separation at material
recovery facility and drop-off centers, windrow composting reactors, anaerobic digestion
reactors.
All actions and activities that are part of the proposed projects are identified and located
across the top of the matrix. The possible impacts of project activities and project
decision in relation to various environments and conditions such as agricultural lands,
energy and mineral resources, aquatic and terrestrial ecosystems, wet lands, cultural and
religious values, recreational and tourism scenes, endangered species, noise conditions,
surface and ground water resources, socio-economic environments, and employment
situations are also identified and located down wards at the left side of the matrix.
The Leopold matrix has been filled for proposed improvement projects and the existing
land fill site at Messobo indicating the magnitude of the impacts of project activities and
project decision with numbers from 1 to 10 on the left side box. A magnitude of 10
represents the greatest magnitude of impact and 1 the least. Zero indicates no impact
situation. Positive sign before each number has been indicated to represent beneficial
impacts and negative signs undesirable impacts.
Similarly the importance of the impacts has also been indicated on the right-side box
considering local, regional and national importance. Greatest importance is represented
with 10 and least importance 1. Zero values have been used to indicate no importance
situations. The magnitude of impacts and their importance are indicated in Annex-N.
The results of Leopold matrix indicated that adverse effects and undesirable impacts in
relation to project activities and waste management practices will be minimized and the
proposed projects will be beneficial to the community. The project decisions will also
enable to minimize and control the prevalent adverse impacts, which have been
happening on the surrounding environments in relation to unimproved waste management
practices, poor collection of solid wastes and unsanitary land filling methods. For details,
refer Annex-N.
Page 65
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 65
8. Socio-Economic Impact Assessment
One of the issues that make environmental management as a challenge is the complex
relationship of the various impacts posed by human activities on the environment. Rapid
growth of urbanization compounded by the inability of local governments to provide
basic urban services has led to various diseases having complex interrelationship with the
environment. The widespread urban environmental problems in urban areas of Ethiopia
as in many towns of developing countries have grave consequences on the health and life
of society. Environmental problems are particularly serious where there is rapid growth
of population and urban settlements with little or no consideration for the environment.
Absence of a total integrated and sustainable solid waste management approach and the
non-compatibility of its various components have resulted in the accumulation of various
levels of waste at various places and localities of the city. These areas become liable to
various vectors (rodents and insects) and foci for environmental pollution, bad smells and
appearance. The situation in turn contributes to the negative health and environmental
impacts in the city as evidenced by Table 8.1, which indicates that nearly 59.13% of the
ten top diseases in the city are associated with poor environmental quality of the city.
Page 66
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 66
Table 8.1: Ten top diseases in Mekelle City
SN Diagnosis No of cases %
1 Observation with out need of further care/ no
abnormality detected
12,052 13.08
2 Acute upper respiratory infection 10,508 11.41
3 Hypertrophy of tonsillitis and adenoids 6,846 7.43
4 Infections of skin and sub coetaneous tissue 6,205 6.74
5 Helminthes, other 3,896 4.23
6 Gastritis, duodentis 3,633 3.94
7 Dysentery, other unspecified 3,120 3.39
8 Gastroenteritis, colitis; age 4 weeks to 2 years 2,741 2,98
9 Eye inflammatory / except trachoma/ 2,738 2.97
10 ameobiasis/ excluding symptom less carriers/ 2,731 2.96
Total top ten diseases 54,470 59.13
Total all causes of diseases 92,116 100
Source: report compiled from three governmental health centers and clinics, 2004,
Mekelle zone health office
Moreover, as per the survey conducted by Mekelle city plan preparation project office to
assess the prior issues of the city, city sanitation and environmental issue was taken as the
fourth prioritized issue. [Survey result on the prioritized issues of Mekelle; MCPPPO,
2005.]
Since nearly all of the ten top diseases which account 59.13% of the total morbidity [table
8.1] in Mekelle city are associated with poor environmental quality and given the gravity
of the problem as evidenced by the survey result of MCPPPO, the implementation of
integrated solid waste management could have a positive spillover effect on the reduction
Page 67
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 67
of morbidity and mortality rates caused by poor sanitation as well as build the confidence
of the public on the city administration.
Besides improving human health and environmental degradation, proper waste
management has advantages in wealth accumulation. These days waste is considered as
wealth. Proper management to utilize waste can really accumulate wealth and this can be
achieved through creation of job opportunity and introducing reusing and recycling of
wastes into valuable resources. In some cities, properly managed wastes are becoming
sources of energy and natural fertilizers.
Due to its holistic nature, practices in some places of Addis Ababa and cities in other
developing countries make it evident that Integrated Solid Waste Management System
brings about a sustainable solution to address sanitation problems because it eventually
enables the community take over the responsibility to keep their surrounding neat.
Moreover, illegal dumping will be drastically reduced which as a result enhance the
quality of water bodies, appearance of the city and new jobs will be created as a result of
the scheme.
The implementation of this project improves solid waste management system of the city
which in turn improve drainage services as the likely of garbage blocking the drains will
appreciably minimize, clean up the environment thereby open fields and streets will be
neat as well as the prevalence of offensive smell reduced.
Mekelle City, both as transit and destination spots, is rich in tourist attracting sites. The
historical buildings, battlefields and cemeteries, the palaces and monuments, the cultural
and traditional traits are among those that have great potentiality for tourism development
in the city. The magnificent palace, which is believed to be the best of its alike palaces in
the country, is the main tourist-attracting site in the city. Hawelti Semaetat is also the
contemporary modern tourist-attracting landmark of the city. The modern meeting halls
are potentials for the development of conference tourism in the near future. The Italian
cemeteries at Endayesus, the battlefields and the ‗May Anishti‘, an area where Empress
Taitu fought against the Italians, have historic importance and are good tourism potential
Page 68
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 68
sites. Dejat Abraha‘s palaces in Mekelle and Felegdaero have also great tourism
importance.
Besides the sites within the city, other nearby religious and historic sites are assumed to
have an important contribution for the development of Mekelle City. These include the
Geraelta, Tsaeda emba and Atsbi rock hewn churches which are with in a day‘s journey
from Mekelle. These rock-hewn churches have marvellous architectural and natural
panorama, which makes them worth visiting sites in the northern part of the country.
Silassie Chelekot is 17km south of the city. It is an 18th
c religious site where a splendid
architectural design and unique religious heritages are found. It is believed that Empress
Tiru Work, the wife of the late Emperor Tewodros, was buried here. The birthplace of
Raesi Alula Abanega and traditional buildings sited at Menewe has also tourism
significance. The first seat of Yohannes IV at Agulae, the Negash Mosque and the rock-
hewn churches around Wukro are within a day‘s visit from the city. Mekelle has also a
good opportunity to be used as a dispatch centre for voyages to the Dallol depressions.
The camel caravan from Berahle, a place where the Amole salt is traditionally extracted
is also an amazing phenomenon.
Moreover, the Alula Abanega international airport makes these tourism journeys to the
city and its surroundings more easy and comfortable in the northern part of the country.
In this respect, the implementation of the project plays a significant role in maintaining
attractive environment which is the one among other factors needed for tapping the huge
tourism potential of the city. It is obvious that tourists like to visit places which are
natural, clean and safe.
The project is therefore expected to increase the number of tourists stay in the city
thereby the service sector can benefit maximum out of it, opens market for cultural
commodities and articrafts and flourishes conference tourism.
It is therefore evident that the sanitation and environmental situations in Mekelle City
will drastically improve provided the recommended measures are fully attended to
including adequate financing; proper organization of the responsible bodies; encouraging
and promoting of efforts of the other stakeholders that are helpful in alleviation the
Page 69
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 69
problems; arming the municipality with qualified professionals and appropriate
machineries and equipments, among others.
Conclusion
It is believed that the project will provide modern solid waste management system to the
city with new disposal site, leachate collection and treatment evaporation pond. The
primary beneficiaries are city residents mainly the poor urban dwellers living in slums,
which are poorly served. In addition the project benefits rural residents affected by the
existing open waste disposal, the private sector and community-based entrepreneurs.
Improved sanitation in the city has direct implication to the health and working situation
of the residents.
In general, the project will remarkably improve the livelihood of the city residents and
has the following socio-economic benefits:
Reduce environmental pollution and health hazard as well as improve
living condition in the city
Create job opportunity for additional people, both permanent employs and
temporary during the construction as well as implementation phases
The tourist attraction capacity of the city will improve
Reduce mortality rate caused by poor sanitation
Improve service delivery
Page 70
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 70
9. Recommendations
9.1 Proposal on the improvement of household handling and primary collection
facility
The current primary collection service requires immediate and short term service
improvement. There is a need to improve the services of operational private sectors and
introduce new modes of primary collection.
The use of child labor in primary collection activities violate international labor rights
and should be avoided. The existing tractor-trailers primary collection service is not
appropriate technology for solid waste collection in the city. Spillage is one of the
difficulties with the tractor-trailers system. The persistent high-wind effect in the city has
also been observed to disturb the block collection activities and unloading of collected
solid wastes at the containers site. Inefficiency in primary collection is the other major
problem with the tractor-trailer system.
It is advisable to move one of the tractor-trailers to the upcoming sanitary land fill site
as a tipper and exploit the rest in local routine and periodic road maintenance activities.
Various technological options can be considered for primary collection operations in
addition to the already introduced ones with the exception of the tractor-trailer system.
Stationery Collection System with compactors and other garbage collection lorries could
be employed in primary collection operations involving various stakeholders such as
private sectors, women and youth cooperatives, municipal services, households and
other polluters.
The technologies that could be used in primary collection operations in the various parts
of thee city are
b. Satellite Vehicles (Three Wheel drives) equipped with containers of
1.50 cu.m capacity;
Page 71
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 71
The Satellite Vehicles can be locally modified and has been recently introduced as one
mode of public transport in the city. The vehicles are suitable for primary collection in
alleys with narrow local roads and also in service areas with flat and moderately flat
terrains. The satellite vehicles are also suitable for primary collection from street
sweeping and small size curb-side stationery-containers provided only for street uses. The
vehicles can be used in dry as well as rainy seasons.
There is only a need to load the vehicles with containers of maximum 1.50 cu.m holding
capacity in a single trip.
c. Manually loaded and mechanically unloaded rear loading compactors
with loading capacity of 15.30 cu.m
The compactors are suitable for primary collection from blocks and curb-side stationary-
containers in all kind of terrains and roads with the exception of alleys. The compactors
can also be used in all seasons.
d. Manually loaded and mechanically unloaded side loading compactors
with loading capacity of 28.30 cu.m;
e. The Trolley system with improved container
These are suitable for very short service distances in flat terrains and all kind of roads.
High number of collectors are required than the satellite vehicles and hand cart systems.
The hand cart system can be used only during the dry season and not applicable for use in
rainy seasons.
f. The Horse cart system with improved container and cart
The major problem with the prevailing horse cart system is the heaviness of the cart for
most horses engaged in animal labor businesses. The cart is very difficult to be pulled
forward, whether the horse are muscular or weak .Healthier or sick. The weight of the
cart is not appropriate for efficient transport with the horse cart system.
This horse system can be used in primary collection tasks with improved lighter carts
designed for efficient waste collection from areas with local streets and flat and
moderately flat terrains. The carts also require improved containers and seats for the
horse cart riders. The improved carts can be used in all seasons out side major and minor
arterial roads, areas in which high incidence of traffic congestions and high volume of
traffic flow are expected.
g. Voluntary House hold services in primary collection with own
matured labor and hired labors
Page 72
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 72
9.2 Recommendation for Financing SWM
The City Administration shall allocate realistic and rationalized budget and create
an enabling environment for community and private participation in SWM service
delivery as well as for efficient and effective utilization of limited resources.
Cognizant of the fact that SWM is by far a municipal public sector-led service, it
would be, according to different experiences, keep up to 50 percent of the service
and privatize the remaining 50 percent, keeping an eye on the private sector lest
they would overcharge the residents.
Appropriate funding mechanisms for sustainable service delivery will be
developed with attention to effective and efficient utilization of resources.
Options to recover the solid waste service costs /bill collection
Instituting or enhancing garbage taxes,
Collecting tipping fees
Adding a surcharge to electricity
Adding a surcharge to water supply
Adding a surcharge to telephone bill
Relaying on other general revenues (including property tax and business
licensees)
Through community motivators
Selection criteria
revenues are adequate and easily collected
the polluter pays for the damage inflicted,
political acceptability, and
Payment of the revenue can be enforced.
Analysis of available options
a. Adding a surcharge to water supply or telephone bill
In general given the garbage taxes, introducing a bill collection through adding a
surcharge to telephone bill is not feasible as the coverage of water supply services at
household level is low.
b. Relaying on other general revenues
Property tax
Page 73
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 73
Relaying on the property tax such as land or housing tax (off course if it is
introduced) is also inconvenient as the collection is done annually .i.e. collecting the
solid waste on annual base would be in feasible for the user to pay
In addition there are a number of polluter/households/who are not required to pay the
taxes.
Business licensees
Similarly the business tax focuses only to the house holds involved in business
activities
c. Adding a surcharge to electricity
With the exception of the newly built area the electricity services is almost available
at every household in the city. But the problem is there are a number of households
that are dependent on one /single Electric meter. Charging for electricity service
depends on the available electric meter so it would be difficult to add surcharge to
the households with no Electric meter. So the number of house holds that are
dependent on a single electric meter has to be identified. This can be easily handled
at kebelle level as they are nearer to the community. It is estimated that there are
about 20,000 private electric meter/customers
There for as the owner of the electric meter is responsible to collect for the electricity
bill still it is going to be responsible to collect the surcharge.
But the cooperation of the electric power corporation in this aspect is doubtful as it is
a federal institution and the city administration has to seek ways for the facilitation
of bill collection in this manner
d. Through community motivators
This option presupposes the establishment of solid waste team at kebele level which
is responsible to collect the monthly payment directly from the users.
e. Most Feasible Mechanism: Adding a surcharge to unit rate of water
In most cases, there is a direct relationship between the rate of water consumption and
the living standard which indirectly describes the rate of waste generation. As the water
supply service is under the municipality, it would be feasible to add a surcharge to a unit
rate of water and collect the fees in two months time as the water bill is collected once
every two weeks.
COST RECOVERY
Methodology
K
AA o
Where A=Annual payment that must be made to repay the capital costs
AO=initial capital investment
Page 74
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 74
K = (1+I) n
–1/I (1+I)
In order to determine the solid waste service charge the following points are
considered
Identifying the full costs of solid waste service provision –even though a
policy decision is required what portion of the cost recovered through
service users, it is assumed to recover 50% of the cost and subsidize or
cross subsidize the remaining
Scenario 1: assuming equipment rental
Annual Operating and maintenance cost expense: Birr 872,000.00
(2006GC)
initial capital cost : Birr 9,895,000.00
Total (Capital +O-M)= 10,766,000.00
Annual cost to be recovered: Birr 1,076,600.00
Scenario 2: assuming equipments (bulldozer and compactor) purchase
annual operating and maintenance cost: 788,000.00
initial capital cost : Birr 12,334,000.00
Total (Capital +O-M)= 13,122,000.00
Annual cost to be recovered: Birr 1,312,200.00
Sources of Waste
Proportion
(%age)
Annual Cost to be Recovered (%)
0.00% 50.00%
Scenario1 Scenario 2 Scenario1
Scenario
2
Residential 81.00% 872046.00 1062882.00 436023.00 531441.00
commercial 6.00% 64596.00 78732.00 32298.00 39366.00
institutional 10.00% 107660.00 131220.00 53830.00 65610.00
Street sweeping 3.00% 32298.00 39366.00 16149.00 19683.00
Total 100.00% 1076600.00 1312200.00 538300.00 656100.00
Total No. of Households
44521.00
Annual payment of Household (Birr/year)
19.59 23.87 9.79 11.94
Page 75
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 75
Monthly payment of Household(Birr/month)
1.63 1.99 0.82 0.99
Willingness To Pay Of The Users
Willingness to pay (WTP) needs to be established in relation to different levels and type
of service amongst different types of household and business. Once the existing WTP is
known, willingness may be modified by targeted promotion activities. Willingness can
also be assessed by the existence of private operators and the rates they command.
Maintaining willingness to pay involves maintaining the quality or value added of the
service for which customers are paying. In the context of SWM in Mekelle willingness
to pay must also be informed by a better understanding of ability to pay amongst poor
households.
Models public private partnership
There are different ways of partnership arrangement in the Solid Waste Management.
a. Open competition: Private Firms compete for customers in an area but with limitation
on the number of competitors;
b. Franchising: Local government grants a private firm exclusive rights to serve an area
with or without price regulation;
c. Concessions: A private firm finances and owns the service delivery system for a
definite period sufficient enough to depreciate investments; and
d. Contracts: made between local government and private firms for a definite period of
time.
Applicable models for solid waste management in Mekelle
Franchise
Evidences taken from working paper: Building Municipal Capacity For Private Sector
Participation indicates that it is difficult for the private sector to collect fees from the
public directly for solid waste services, particularly when there is low willingness to pay
and limited appreciation that solid waste collection and disposal is an important
municipal function. Low cost recovery and small numbers of customers threaten the
viability of private sector participation when this form of revenue collection is pursued.
This function may be better placed with the municipality as they have the authority for
more meaningful sanctions and thus the capacity to enhance the levels of revenue
collection.
Contracting
Page 76
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 76
Reports on Urban development workshop held in Mekele, Ethiopia (October 2000)
indicates that the most common forms of private/public partnership in Africa is for urban
authorities to contract out solid waste collection and disposal. There are also an
increasing number of instances where informal sector groups of garbage collectors have
been contracted to collect and disposed of solid waste. This mode of privatisation is
considered to be more politically acceptable, as notion of selling public asset is not
popular among African politicians
Two models are proposed
Model one
Micro-enterprises provided services to the local communities, with residents supervising
the process. Residents pay the local authorities for the service, which in turn contracts out
and pays the private enterprise. Limitation: this model may not applicable in practice
because payments from the community to the municipality may lag behind, nor did the
municipality pay the micro-enterprises irregularly. In the end the micro-enterprises would
collapse because of lack of income.
Model two
The second model is based on a closer relation between local community and micro-
enterprises. The community who receives the service not only supervises and contracts
out to the micro-enterprises, but also pays them directly when the waste is collected. The
municipality retains responsibility only concerning the legislative framework of the
private enterprise. These micro-enterprises have been able to survive by the direct
relation with the beneficiaries and by charging the inhabitants affordable fees.
Legislative Technical & Financial
Framework assistance
Fees
Supervision
Contract
This alliance would significant contributions to socio-economic goals. This model would
result in a real improvement of the co-ordination of the SWM services even though it was
based on complicated linkages. The direct relation between micro-enterprises and
community and the financial and organizational support from the NGO, The Mass Media
for raising awareness of the inhabitants with regard to Solid Waste Management and
Local
Authority
Private
Sector
NGO ‗S
Research
oriented
Organization
Mass media
Community
Page 77
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 77
Research-oriented organizations In order to find means and ways to create
environmentally friendly mechanism of disposing especially hazardous solid waste and
better legislation by local authorities resulted in the improvement of the co-ordination of
the service.
Proposed Sold Waste Management Services In this Model
1. Street sweeping
Option one. Contracting the service and investing on the vehicles and equipments
It should be initiated for the following reasons
Firstly the street sweeping contract enables private enterprise, through direct contact with
customers to encourage households to join the household collection scheme. Secondly,
by assuming responsibility for street sweeping in the core city area and providing a more
effective service, it could cut down the incidence of households dumping waste on city
streets. This would, in turn, provide a greater incentive to households to make use of the
household collection service improving their customer base.
But while contracting for the core area street sweeping to the private sector The
municipal street sweepers should seconded to the private sector on the same terms and
conditions (wages, leaves or social benefits) as they had when employed directly by the
municipality.
Option two. Contracting the service and leasing the municipal carts and equipments
This kind of contract can be initiated through the SSE by organizing women from low-
income settlements.
This kind of arrangement became fruitful in developing countries such Nepal .It has
resulted in marked improvements to the cleanliness of the streets, has led to an increased
awareness amongst the public of solid waste issues, increased acceptance of a private
sector role in solid waste services, public acknowledgement that the private sector are
more successful and consequently, improvements in willingness to pay for household
collection. In some areas the numbers of households and shops signing up for private
collection services has doubled since the private sector began the street sweeping service
and that shopkeepers became more willing to pay for the service rendered.
2. Door-To-Door Collection
Contracting the service and Investment by the private sector on the vehicles and
equipments
The contract should initiate in the core areas and the commercial unit where more waste
is generated.
Page 78
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 78
Contracting the different social focal points including the Eddir, Mahiber and similar
Community based organizations need to be encouraged to be engaged in SWM processes
and help improve the situation in their locality
Contracting to the small enterprises in affluent areas because Contracting to the small
enterprises areas where the municipality providing inadequate service and in areas
inaccessible to trucks and less accessible sectors of the city to which the bigger firms
would not be very much attracted.
MUNICIPALITY
Municipality would give service to the lower income households
3. Collecting and Transfer
Contracting the service and Investment by the private sector on the vehicles and equipments
The large scale private sector, which, because of its access to financial resources and its
potential ability to operate efficiently, can play a role in transferring the solid waste to the
The contract should initiate in the core areas and the commercial unit where more waste
is generated.
4. Disposal
The existing practice indicates dumping of waste is free of charge. But if the disposal
costs has to be introduced. There fore the solid waste operations within the town will
require significantly more subsidies or a different financial arrangement for the
partnership to continue once disposal costs are introduced.
5. Recycling facilities
MRF (Material Recover factory)
Contracting out
Privatization
Manual labour
Assistance
Length of contract
The length of contract is also important because it should be long enough to enable the
private firm to depreciate capital expenditures for appropriate technology and equipment.
Municipality Private sector
enterprises, mixed
enterprises
Co-
operatives of
recyclers
NGOs
Page 79
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 79
OTHER FINANCIAL ISSUES AND RECOMMENDATIONS
Primary Collection by MSEs
The micro and small enterprises /MSE/ can possibly engage in primary collection of
wastes from households to the municipal containers and collect waste using door-to-
door method
The collection of waste through MSEs provides job opportunities for many jobless
youth.
Owing to the probable willingness to pay, the majority operates in the middle and
high-income residential houses and pay an average of 12 Birr (10 – 20 Birr) per
month per household.
The experience of Addis gives a good lesson that given the all rounded support to
the MSEs, they would commence collecting and ultimately transporting solid waste
from households to MRF sites.
MRF site
At MRF site, those institutions who bring the waste with their own vehicles are
charged 4.30 birr/m3
Landfill
At Landfill site, those institutions who bring the waste (special waste) with their
own vehicles are charged 6.30 birr/m3
9.3 Recommendations on awareness raising and public participation
1 Actions for increased awareness and change of attitudes/ behavior
Strengthening environmental awareness through mass media, community leaders,
religious institutions, various organizations and associations.
The community expects the municipal to keep the city clean but often fail to
understand how they can contribute to this objective. The main areas where they
can contribute are;
Not to drop the litter in the streets. If there is not a garbage container for them to
use, then the message must be take it home with you,
To understand that there will, in future be regular waste collection service and to
be patient and use it. They must not dump their rubbish on open land,
Make the public aware and understand the garbage problems and how they affect
the environment,
Get support to control illegal dumping,
Get the public involved in waste reduction, recovery, reuse, recycling and
composting,
In school students inculcate the principles and practice of waste minimization,
recovery, segregation at source, recycling and composting, and initiate school
hygiene promotion activity to educate students because of the fact that hygiene
behavior is learned during childhood and youth time.
Page 80
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 80
2 Kebele activation and support
Sanitation is not one time activity, but a continuous process, if we want to see
change, there is a need to develop a system in community, which is community-
based waste management. It is generally more efficient to work community
based waste management at kebele level for several reasons:
Promotion of sorting at source, recycling and community composting are easier
to undertake
It is more efficient to work with the community for cleaning the streets, drains,
rivers and grass cutting,
It will be easier to work on public awareness at local level
It is important to strengthen Kebele Sanitation Committees so that they will be
able to do:
Environmental control with regard to sanitation,
Waste sorting
Waste pre- collection
Recycling
Composting
Environmental cleansing (cleaning of collection points and illegal dump
spots)
9.4 Recommendation on institutional arrangement
Cognizant of the fact that Solid Waste Managements cannot and should not be considered
to be easily privatized and that it is by far a municipal/public sector-led service rendered
to citizens, it would be worthwhile to put the municipality in the forefront in this venture,
to start with. On the other hand, the Municipality needs to have collaborators with
whom it can perform duties and take steps to curb the Solid Waste Management problems.
Hence, in Mekelle‘s case different possible and relevant collaborators have to be
identified to make things clearer and systems more transparent and effective.
The following offices and organization are among the very important collaborators and
actors in the Solid Waste Management‘s working system;
I. Municipal Structure (with regard to SWM)
Proposed Functions of Social and Environmental Services Division (with regard to SWM)
At city level the division act as a regulatory and legislation formulation, set up standards
and procedures, coordination among Kebeles and deal with cross cutting issues,
Page 81
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 81
delivering appropriate technical support, capacity building, administration of landfill and
undertaking public a awareness programme, advocacy and research.
Functions of the Division (with regard to SWM):
Prepare directives and systems for effective implementation of SWM;
Prepare standards criteria, guidelines and manuals on SWM;
Prepare city-level solid waste management framework;
Review and monitor the implementation of Kebele waste management
plans;
Deal with cross cutting issues of Kebeles;
Coordinate the activities of various sectoral agencies and NGOs operating
on SWM;
Develop and prescribe procedures of appropriate permits and licenses for
the private sector;
Review the incentive scheme for effective solid waste management;
Formulate and implement the necessary educational efforts and activities,
promote awareness creation and information campaign strategies, and
develop IEC materials on SWM;
In collaboration with concerned bodies, propose fair, equitable and
reasonable tariffs for SWM service delivery,
Collect and compile data for research;
Encourage and assist the participation of private sector and micro
enterprises in solid waste collection, transportation and disposal,
Propose and adopt regulations requiring the source separation and post
separation collection, segregated collection, processing, marketing and
sale of organic and designated recyclable material generated in the city;
Ensure that SWM programmes conducted by various bodies comply with
SWM rules and regulations;
Establish multi-sectoral technical committees and special task forces as
required to assist in the effective implementation of integrated SWM
programmes;
Establish effective working relationships with international agencies and
donors;
Develop and administer landfill and materials recovery facilities,
Facilitate training and education on integrated solid waste management;
Establish and manage solid waste management information base and
institute a sound information exchange system;
Promote the development of recycling;
Promote the implementation of waste minimization and reduction in
kebeles;
Prepare annual city solid waste management status report;
Recommend measures to generate resources, funding and implementation
of projects and activities.
deal with the day-to-day operation activities including solid waste
collection, transportation, street and urban cleansing; cleanse illegal
dumping sites, conduct sanitation campaign undertake composting and
recycling.
Page 82
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 82
Functions of Kebelle Solid Waste Management Committee
Raise awareness of Kebele residents regarding Solid Waste management
Programming and Collaborating with Stakeholders to make SWM
successful
Monitoring of waste collection, in collaboration with the SWM Division
supervisors, and make the operation follow rules and regulations
Carry out (nominal) fee collection activity to cover SWM expenses
Conduct, from time to time, as felt necessary, campaigns to clean the
Kebele‘s different portions
Penalize dwellers who trespass and pollute the area against rules and
regulations
Present Progress Report to Kebele Administration Office (KAO) and City
Solid Waste Operation Team every month.
Make effort to establish a ―Sanitation Fund‘ in collaboration with residents‘
Social focal points such as Eddir, Mahiber … etc. and other stabke holders.
Proposed Organizational Chart Public Services Department
II. Promote inter-sectoral collaboration
Implementation of SWM in the city will be undertaken in collaboration with a
number of organs under the over all management and coordination of Deputy
City Manager,
CITY MANAGER
D/ CITY MANAGER
FINANCE &
ADMINSTRATION SERVICES
PUBLIC SERVICES
DEPARTMENT
ECONOMIC SERVICES
DIVISION
SOCIAL & ENVIRONMENTAL
SERVICES DIVISION
CODE ENFORCEMENT
DIVISION
MUNICIPAL ENTERPRISES
TEAM
KEBELE SANITATION
SERVICES
SOLID WASTE OPERATION
TEAM
Page 83
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 83
Establish Sanitation Councils at all levels comprising different representation of
the community government bodies MSEs, NGOs, CBOs, etc ,
Work jointly with concerned stakeholders:
Code Enforcement Service: to control cleansing and illegal dumping.
Landuse and Environmental Protection Authority: working together for
improvement and conservation of the environment.
Mekelle Zone Education Office: introduce sanitation in school curricula,
expand hygiene promotion in schools, establish sanitation clubs in schools,
mobilize students in sanitation programmes,
Mekelle Zone Culture and Information Office: Expand IEC in the media
(electronics and print), ensure adequate media coverage on successful SWM,
Mekelle Zone Health Office: Strengthen SWM content in health education
programmes.
Urban Planning and Land Administration Department: give proper
emphasis of SWM in urban development,
Mekelle Zone Agriculture Office: integrate solid waste composting with
urban agriculture and promote hygiene and environmental awareness
through agricultural agents.
Mekelle Zone Trade, Industry and MSEs Office: organizing MSEs for
primary waste collection.
Mekelle Zone Finance and Economic Development Office: ensure
allocation of budget, control of financial matter, ensure project development
with donors,
III. Decentralization
Empower Kebeles with full responsibilities and authorities with regard to SWM
as prposed above
.
IV. Incentives
Rewards for private sector, NGOs, and CBOs for outstanding achievements and
innovative projects, technologies, processes and techniques
V. CBOs and NGOs
Encourage NGOs and CBOs for planning, implementation and management of
SWM programme and projects,
Strong partnership should be developed for multi-sectoral action with CBOs and
NGOs,
It is important to form networking with CBOs and NGOs in the areas of waste
sorting, recycling, composting and disposal methods at household and community
/neighborhood level/.
VI. Strengthening primary collection by micro and small enterprises /MSEs/
Encourage small and micro enterprises to participate in primary waste collection.
Establish appropriate incentives for involvement of MSEs in primary collection ,
Establish MSE licensing and operational procedure
Page 84
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 84
VII. Private sector involvement
It is anticipated that waste collection, transportation and disposal services will be
improved with the privatization of SWM service as privatization relieves the
financial and administrative burden of the government besides facilitating
economic growth with private sector participation,
The private sector will be involved in one of the following ways:
Contracting out solid waste management, through franchise, competitive
contracting, commercialization or public/private competition,
Development of the essential technologies for SWM,
Maintenance of truck, equipment and materials of SWM,
Involved in composting, recycling and materials recovery
Appropriate incentives for private sector involvement in SWM shall be devised.
Human Resource
Implement the civil service reform programme focusing on the creation of
committed and motivated workers. A critical mass of development oriented and
forward looking workforce is crucial,
Bring about an appropriate mix of skill, raise standards, establish acceptable pay
and incentive system.
Supervision and monitoring system will be instituted to improve workers
motivation and performance.
1. Capacity Building and Training
Provide education and training for all levels of workers so as to create teams of
SWM workers who will be responsible for implementing and managing solid
waste service.
Training of community resource people such as religious leaders, school teachers
and students, sanitation committee, CBOs, NGOs, etc
9.5 Legislative recommendation
Develop different kinds of directives, guidelines, operational manuals, code of
practices, which includes but not limited to :
Dust bin standards
Hazardous waste storage, collection and disposal directive
Source reduction and recycling directive
Awareness raising manual
Guideline for MSEs in solid waste collection and transportation
Landfill service delivery manual
Landfill operational manual
Moreover, the city has to establish Code Enforcement Service having code enforcing
agents at grass-root levels. It is envisaged that this institution will ensure strict
compliance of violations according to the existing rules and regulations.
Page 85
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 85
9.6 General recommendations with regard to materials recovery
(a) Recycling
Encourage small-scale entrepreneurs to venture into plastic waste recycling.
Promote community based plastic recycling schemes,
Organizing and support of the development of the following informal sectors:
―Korales‖ recyclable materials collectors
Craftsmen: recyclers of metal, wood, rubber, tire, clay, etc
Vehicle recycler: dealers of those vehicles that are scraped
Landfill scavengers: to reduce waste disposed in landfill
Promotion of
Reducing the use of ―festal‖ in shopping,
Use of bags and baskets made out of environmental friendly and locally
available materials,
Avoid dumping of ―festal‖ with other wastes, but sort it and keep it in one
place for recycling and recovery,
Re-use of plastic bottles and containers,
Re-manufacture of glass,
Re-use of tyres for shoe making,
Plastic bags washed, cut in strips, and knitted into purses and bags,
Re-use of beverage bottle,
Discarded vehicle recycling by selling its parts, this requires participation of the private
sector
Levying tax on plastic bag producers and importers,
Setting up of recycling centers close to shopping areas especially by organizing
waste pickers and ―korales‖,
Formation of recycler‘s network to coordinate and enhance the recycling
activities.
(b) Composting
Encourage individual composting in which the individual makes his own compost
out of his organic waste and use it locally.
Encourage small scale composting by organizing income generation and sale the
product to farmers,
Encourage medium scale composting facilities with simple mechanical equipment
(wheeled loader and portable trammel screen).
Encourage communities and private sector in composting through various incentive
mechanisms.
Addis experience has shown that at household level, especially in the more crowded
areas, there may not be enough space to make compost or only a small amount of
household waste is available /and no garden waste/. In such cases, a local NGO has
promoted basket gardening which uses only a little space.
Page 86
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 86
9.7 Steps required to be taken to improve the solid waste management of Mekelle
1. Reorganization and Strengthening of the Public Services Department
Presently the Social Services Department of the municipality, is in charge of Solid Waste
Management (SWM) . With regard to professionals working in the Department, there is
lack of sufficient well qualified experts in the field to do this crucial job of the city. It is
hence desirable to increase the number of professionals who hold first-degrees and above
to about 4 in the years 2006-2010.
It would be more feasible and dependable to make contract workers permanent
employees based on a job-evaluation scenario since it would increase efficiency. The
annual budget also is inadequate when observed from the point of view of the solid waste
management of the city and hence has to be considerably improve.
The Social service department should be reorganized in such a way that it acts in an
autonomous way but to be supervised by the Municipality depending on the institutional
arrangement put into effect. This would make its engagements faster and more effective.
There is also dire need to provide appropriate incentives for workers in the Solid Waste
Management team to ensure their efficient services and to attract others to the job.
Professionals have thus far not been attracted to the sector due to low salary scales and
this has to be reconsidered because such services are exceptionally favored with regard to
budgetary allowances/per diems… etc. even in other similar developing country cities.
On the other hand, there are some basic motivation options to achieve better performance
of workers and to attain high quality standards of work, i.e.
Giving periodic awards (6 monthly or annually) in the form of money,
gifts/prizes, certificates or a combination of these;
Bonus payments for diligent, punctual and cooperative workers;
Promotion in status and access to training programs for workers with high
performance.
Provided the Social and Environmental Services Division is equipped with the
appropriate facilities and personnel, the city‘s future with regard to overcoming the
existing solid waste management will be bright.
The overall evaluation and recommendation-bearing assumptions for future
reorganization and strengthening of the SWMD is shown in the attached documents
(tables)
The recommendations given could enable the SWMD enhance its full capacity to
improve the frequency of collection and transport system and benefit the inhabitants to a
better level thus ameliorating the existing problems of skips staying full for days.
With regard to the available trucks, the problem of maintenance deserves adequate
attention. It would be advisable to make the agency self-sufficient by establishing a
garage on the same compound. Such a garage would do an efficient job and would have
a capacity for tyre change, air pumps and washing facilities.
Page 87
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 87
2. Reduction of Generated Waste at Source through Composting
The household waste generated could well be reduced if the family members
cooperate to sort waste at that level and use the organic and bio-degradable items
for composting purposes to be applied to their gardens. This requires, in the first
place, awareness raising and finding means to also collect the organic and bio-
degradable materials to be transported to composting stations which should be
established in the city‘s strategic sites
It would also bar imperative for hotels, tea –rooms, bars, restaurants …etc to sort
their generated waste and place them in different containers so that it would be easy
to different containers so that it would be easy to differentiate between the
compostable, recyclable and that part of waste that has to be disposed on to skips
and later on to disposal sites/sanitary landfills.
Waste materials recycling takes a number of forms:
- Sorting the recyclable items out of domestic and commercial waste
collection;
- Converting waste into compost to be used as natural fertilizer;
- Generating heat and energy by burring waste; and.
- Producing bio-gas (methane) from disposed of waste at landfill or at
household level by creating a mini-project to enable this
The ―Koryalew‘ and ―Liwatch‘ seekers travel from door-to-door and collect
reusable items (tins, plastics, old garments and shoes… etc) and this can be
considered as a means to reduce solid waste generated both at household level and
the city level at large. It would hence be helpful to recognize such recyclers and
formalize their activities as legal. There is also need to provide them space/a piece
of land (drop centers) to carry out their recycling activities
As in developed countries, the industries (existing/up comings) in Mekelle also may
reuse the recovered materials such as paper. Plastic, iron and steel rod and pieces
tin…etc. to make new ones. Hence, agreements could be made with such industries
to enable the collectors to sell their items at reasonable prices.
3. Empower the Kebeles and Decentralize Solid Waste Management (SWM) to that
Level
4. Set up a well Organized Base Data on Solid Waste
Establish a Research and Information Center within the division in order to
document the collected (in sorted forms), transported and disposed SW on daily,
monthly and annual basis;
Record and document typed and amounts of recycled and composted materials by
different actors/stakeholders.
Ensure the availability of a well organized base data on SWM for all interested
researchers and practitioners whenever needed.
5. Put in Place Solid Waste Management Regulations
This is a vital step to streamlining the SWM system of the City in general. Hence,
there is need to equip the Municipality with appropriate Rules, Regulations, Laws
and By-Laws so that meaningful results may be achieved.
Page 88
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 88
6. Privatization Effort and Participation Methods/Models
In Mekelle‘s case, collection and progressively transportation could be privatized
simultaneously, depending on the area conditions. collection should ‗be continued as
usual‘ with effort to provide more containers to the Kebeles. This could work in low
income Keblees where small scale business enterprises may not be interested in getting
involved in collection activities.
g. Monitoring and Evaluation
With regard to contract specification and overall supervision, the private sector is
accountable to the City Administration. The day-to-day and week-to-week performance
of the private firm should be monitored, evaluated and recorded by the office to be
established by the City Administration.
The contractors need to be selected based on a fair and sincere system of bid competition
so that they could show a better performance than either the public monopolies or other
private participation methods. The ideal arrangement and approach to private contracting
at first may be a hybrid of public and private service i.e. contracting, for instance, for the
collection of solid waste from some areas of the city, while retaining public service to the
remaining parts.
Monitoring by the City Adminstration ensures quality of service provided by private
hands. On the other hand, the cost accountability that private contractors would deliver a
lower cost than that of public service cannot be attained without a proper monitoring,
articulated contract performance measures and enforceable contract sanctions. Clear
definitions of measurable output of service required of the contract, as it enables
performance monitoring, should be stated. Besides, the local government should be in a
position to get rid of a contractor whose fees are too high and/or service quality is so low
at the end of the contract period.
Evaluation of the private firm‘s service provision based on concrete data collected with
regard to collected, transported and disposed solid waste from time to time is essential to
make decisions regarding continuation or termination of contract with private firms.
Page 89
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 89
SUMMARY OF FINANCIAL AND INSTITUTIONAL RECOMMENDATIONS
The Way Forward: key areas
Following are some of the major key areas to reach at the desired results:
Decentralization of full responsibilities and authorities of SWM to Kebeles and
build their capacity. Give support in terms of training and developing critical
systems,
Improving the collection and transportation: optimizing rotations, container
sitting, collection point facility, improving truck maintenance, and routing system,
Implement the civil service reform programme focusing on the creation of
committed and motivated SWM workers,
Encourage a greater participation in primary waste collection by micro and small
enterprises as well as the participation of NGOs and CBOs, maintain a strong
public- private-community participation,
Encourage involvement of private investors on SWM,
Promote environmental awareness pertaining to SWM, develop a
communication strategy and work vigorously for the behavioral change of the
wider public,
Promote waste segregation at source, waste minimization, recycling, reuse,
recovery, and composting
Institutionalize public participation in the implementation of SWM. Promote
networking, information sharing and cooperation with a number of stakeholders
and collaborators and establish city level Sanitation and Beautification division,
as well as Kebele Sanitation Teams at grass-root levels,
Promote cost recovery and prioritize in public finance,
Establish Code Enforcement Division of which among other duties and
responsibilities include enforcement of strict compliance of existing rules and
regulations on control of illegal dumping and littering the environment.
Short Term Plans
The following are some of immediate improvements and interventions needed
Solid Waste Operation Team shall be established at central level with
multi-disciplinary man power ,
Solid waste management teams shall be established in all Kebeles,
Sufficient number of SWM workers /professionals, truck drivers, assistants,
logistic officers, street sweepers, foremen, container attendants, auto mechanics/
shall be assigned and commence their tasks.
Undertake emergency clean up programmes to remove heaps of refuse in the
city,
Introduce two shift working hour system. The first shift works from 4:00 am to
11:00 am and second shift works from 11:00 am to 6:00 pm. In one truck two
drivers work through shifting,
Because the first shift start at 4:00 pm contractual agreement shall be made for
buses or taxis for transportation of workers as early as possible,
Page 90
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 90
Intensive promotional activities and public education shall be undertaken to raise
public awareness on policies and regulations, waste reduction, recovery, reuse,
recycling and composting,
Introduce improved system of control and supervision of workers for productive
and efficient fleet management,
Introduce waste collection route scheduling and daily work schedule for all
garbage vehicles per week,
Improve fuel filling, tire and vehicles maintenance system to enhance collection
rate from 21.9% to 34.2%. by doing this and add twenty four more containers
with double shift system can enhance the collection rate from 34.2 to 45%
Improve the competence and discipline of drivers through training and close
supervision,
Improve sitting of communal containers with established criteria and
construction of collection point facilities with platform,
Improve street cleaning and close control through effective implementation
programme and schedule,
Orientation of workers at different levels on the improved service delivery,
Development and use of various operational guidelines and manuals
Increase the number of MSEs, encourage as a strategic pre-collectors and support
through training and any assistance required,
Expand community based recycling and composting in kebeles,
Reduce the scatter of garbage by setting dust bins along foot paths for passers by
and pedestrians,
Organizing human scavengers in the dumpsite and deploy them in well organized
recycling and composting activity for their livelihood and improved waste
reduction programme,
Integrating composting scheme with urban agriculture in conjunction with
concerned bodies,
Service delivery improvements :
1. In some kebeles, containers shall be re-located from streets and put within
the community as per the established criteria,
2. identify institutional users and collect service charges with shortened
procedure;
3. outsource maintenance of trucks and make contractual agreement with
companies and improve ways of repairing tyres and filling fuel ;
4. give code number for communal containers for proper identification of
containers;
5. purchase new containers and repair damaged ones,
6. give measured streets to teams of sweepers to monitor their performance;
7. prepare schedules for clean-up campaigns;
8. identify sites for construction of communal collection facilities with platform
and design the facilities;
9. make preparation for awareness raising events
Page 91
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 91
Street sweeping
Improve street cleaning by sweeping the whole street including drains, wall, pole,
etc,
The sweepers will be accountable for a given (measured) streets,
Sweepers shall start work before 6:00 am,
Page 92
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 92
10. Implementation Schedule
Description of Activities Duration in months/weeks
January’06 February’06 March’06 April’06 May’06 June’06 July’06 July’07
2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 1
Finalization and submission of
consultancy completion report
Invitation for tender
Evaluation and award of contract
Mobilization
Construction work
Provisional acceptance
Commencement of operation
Final Acceptance
Page 93
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 93
Page 94
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 94
11. Annexes
Page 95
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 95
Page 96
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULTING ARCHITECTS AND ENGINEERS 96
Page 97
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 97
Annex A: Summary of Observation on Primary Collection Services
The container sites observation was taken in the period from 11-02-1998 to 20-02-1998 E.C. The
current modes of primary collection, their frequency and distribution in the city and their various
service areas have been identified. Summary of the observations are indicated in the table
hereunder.
Page 98
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 98
Table: Waste Load Frequency (%) of primary collection service providers (11-02-1997 to 20-02-1997)
SN Container Location
Modes of primary collection
Saba Gojo
Adult
labor
Child
labor
Street
sweeping Tractor
Horse
cart
Total
%age
1 Alpha KG 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Edaga Finjal 0.00 0.00 0.00 0.00 0.00 7.69 30.00 37.69 6.28
3 Enkodo 0.00 0.00 9.09 0.00 0.00 7.69 10.00 26.78 4.46
4 Muslim Cemetery 0.00 0.00 0.00 0.00 0.00 0.00 60.00 60.00 10.00
5 Ayder Livestock market 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Mesfin Industry 0.00 0.00 3.90 0.00 0.00 0.00 0.00 3.90 0.65
7 Denbosco 0.00 0.00 3.90 0.00 0.00 0.00 0.00 3.90 0.65
8 Gotera 0.00 10.00 0.00 0.00 0.00 0.00 0.00 10.00 1.67
9 Agricultural office 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
10 Mayduba 0.00 0.00 0.00 0.00 0.00 11.54 0.00 11.54 1.92
11 Red Cross (Moved to L12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
12 Kebelle 19 0.00 0.00 9.09 41.18 18.42 0.00 0.00 68.69 11.45
13 Kebelle 20 0.00 0.00 9.09 41.18 18.42 0.00 0.00 68.69 11.45
14 Luis eye clinic 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
15 Debredamo hotel 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
16 Abune Aregawi Church 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
17 Business Taxi Terminal 0.00 0.00 9.09 0.00 0.00 0.00 0.00 9.09 1.52
18 Adihawsi Endatsaba 0.00 0.00 9.09 0.00 0.00 0.00 0.00 9.09 1.52
19
Edaga Bieray(17-livestock
market) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
20 Edaga Faham 0.00 0.00 0.00 0.00 0.00 15.38 0.00 15.38 2.56
21 Axum Hotel 0.00 35.00 2.60 0.00 0.00 3.85 0.00 41.44 6.91
22 Adis Alem Bus Station 0.00 0.00 9.09 0.00 18.42 0.00 0.00 27.51 4.59
23 Kebelle 15 0.00 15.00 9.09 17.65 18.42 0.00 0.00 60.16 10.03
24 Gebriel church 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Page 99
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 99
27 Near WEWEKMA 0.00 35.00 12.99 0.00 26.32 0.00 0.00 74.30 12.38
28 Near EELPA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
29 At sewhi Nigus 0.00 0.00 0.00 0.00 0.00 7.69 0.00 7.69 1.28
30 Near Enda Mehiret Bani 0.00 5.00 3.90 0.00 0.00 0.00 0.00 8.90 1.48
31 Semein Health center 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
32 Ayder low cost houses 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
33 Areki factory 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
34 Enda Cherkos 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
35 AdishumDuhun 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
40 Dejen 0.00 0.00 0.00 0.00 0.00 26.92 0.00 26.92 4.49
41 Hawlti 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
42 Edaga AdiHaki 0.00 0.00 0.00 0.00 0.00 11.54 0.00 11.54 1.92
43 Mekaneyesus church 0.00 0.00 0.00 0.00 0.00 7.69 0.00 7.69 1.28
44 Abreha Castle 0.00 0.00 9.09 0.00 0.00 0.00 0.00 9.09 1.52
45 Trans Ethiopia 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
46 May Degene 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
47 Kebelle 18 Taxi Terminal 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
48 Adihawsi Taxi Terminal 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total 0.00 100.00 100.00 100.00 100.00 100.00 100.00 600.00 100.00
MIN coverage 0.00
MAX coverage 12.38
MEAN coverage 2.38
Page 100
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 100
Annex B: Analysis of Tractor-Trailer for Primary Collection
The following container locations were getting primary collection services with Municipal tractor-trailer:- Edaga Finjal, Enkodo, Mayduba,
Edaga Faham,Axum Hotel, Sewhi Nigus, Dejen, Edaga AdiHaki,and Mekaneyesus church
Table Average distance covered & Time consumed by the municipal tractors in solid waste collection
Day
No. of
Trips
Time consumed (minutes)
Dispatch
to Blocks Loading
Blocks to
container Unloading
Container
to Blocks
Container
to
Dispatch
Total
time
Total
distance
traveled
(Km)
Day-1 1 5 50 25 105 15
200 10.2
Day-2 3 10 95 30 80 20
45 10 45 10
20 90 30 75
560 22.4
Day-3 3 20 60 70 95 10 30
85 10 95
10 50 25 65
625 24.5
Day-4 2 5 70 10 80 10 35
55 70
335 22.2
Total 9 70 600 210 710 40 90 1720
79.3
Page 101
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS 101
Average unit
value (single
trip) 1.00 7.78 66.67 23.33 78.89 4.44 10.00 191.11 8.81
Time
consumed out
of total (%) 4.07% 34.88% 12.21% 41.28% 2.33% 5.23% 100.00%
Most of the time is spent on unloading
Page 102
Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
102
Table: Tractor-trailer collection frequency and amount collected 2004/2005 (1997 E.C.) SN
Veh
icle
s p
late
no
.
―Mes
ker
em‖
―Tik
imt‖
―Hid
ar‖
―Tah
isas
‖
―Tir
‖
―Yek
atit
‖
―Meg
abit
‖
―My
azia
‖
―Gin
bo
t‖
―Sen
e‖
―Ham
le‖
―Neh
ase‖
―Pu
agm
e‖
Yea
rly
To
tal
Dai
ly l
ikel
y (
%)
Day
s(n
o.)
Vo
lum
e (m
3)
Day
s(n
o.)
Vo
lum
e (m
3)
Day
s(n
o.)
Vo
lum
e(m
3)
Day
s(n
o.)
Vo
lum
e(m
3)
Day
s(n
o.)
Vo
lum
e(m
3)
Day
s(n
o.)
Vo
lum
e (m
3)
Day
s(n
o.)
Vo
lum
e (m
3)
Day
s(n
o.)
Vo
lum
e (m
3)
Day
s(n
o.)
Vo
lum
e(m
3)
Day
s(n
o.)
Vo
lum
e (m
3)
Day
s(n
o.)
Vo
lum
e (m
3)
Day
s(n
o.)
Vo
lum
e(m
3)
Day
s(n
o.)
Vo
lum
e (m
3)
Day
s(n
o.)
vo
lum
e(m
3)
Dai
ly l
ikel
y
(%)
1 Ft 0625 19 216 NA NA 22 264 21 256 28 320 30 348 30 360 30 360 29 344 30 340 25 292 30 336 5 15 299 3451 82
2 Ft 6017 19 208 NA NA 30 392 14 168 28 316 30 364 30 360 30 360 29 340 30 328 26 304 30 336 NA NA 296 3476 81
3 Nathreth
80
19 188 21 224 22 240 20 236 28 312 29 320 30 348 30 360 29 344 30 316 26 296 30 340 5 15 319 3539 87
4 Ft 0612 19 236 NA NA 21 236 23 272 28 304 24 272 30 356 30 360 29 332 26 300 26 276 30 380 NA NA 286 3324 78
5 Total
volume
848 224 1132 932 1252 1304 1424 1440 1360 1284 1168 1392 30 1379
0
6 Total
days
76 21 95 78 112 113 120 120 116 116 103 120 10 1200
Source: Mekelle municipal social services department
Page 103
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
103
Technical Analysis of Tractor-trailer services:
The current primary collection service with tractor-trailer system involves four tractors in
block-collection of solid wastes mainly from residential sources. The tractor-trailers are
manually loaded and unloaded with mechanical and manual operations.
The resource requirements of the stationary-containers manually loaded collection (SCS-
ML) are estimated below.
(a) Time required per day
The time requirement in fixed trip system with known number of trips is given by the
length of day work
H= [(t1+t2) + NT (Tscs)]/ (1-0.15)
t1=service time between dispatch station and first serviced blocks (hrs);
t2=service time between location of last serviced block and dispatch location (hrs);
The unloading, total pick up, and the service times between the dispatch locations and
First and last serviced locations are taken from reported analysis on estimation of
operation and maintenance costs submitted by the Consultant, Promise. These time
values are given for different trips covered by the tractors in primary block collection
operations in the city.
The values are given below for single, double and triple trips.
NT=1, Tscs= 200min, uc=105 min, Total Phcs= 155 min, t1=5min, t2=25 min;
NT=3, Tscs= 360min, uc=100 min, Total Phcs= 76.67 min, t1=15min, t2=35 min;
NT=2, Tscs= 335min, uc=75 min, Total Phcs= 62.5min, t1=5min, t2=10 min;
The estimated lengths of days for the three fixed trips are
H= 4.51 Hours or 270.59 minutes for single trip;
H=13.43 Hours or 805.88 minutes for double trips;
H=22.16 Hours or 1329.41 minutes for triple trips;
The length of day for single fixed trip is less than 8 hours, which is the normal official
working hour in the municipality office. The double and triple fixed trip services require
daily working hours above the indicated office hours.
(b) Average travel speed
The average pick up time in the three fixed trip primary collection operations was 70.60
minutes or 1.176 hours. The total time per trip in stationary-containers manually loaded
collection system is different from the hauled-containers collection system. It includes
Page 104
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
104
average driving time between stationery containers location. The total travel time is given
by
Tscs = Phcs + s+ a + bX
The average at-site time s=at-site time is estimated to be 0.115 hrs and the estimated
hauled times for the three fixed trips become
h= 1.58 Hours or 94.89 minutes for NT=1;
h=4.54 Hours or 272.39 minutes for NT=2;
h=4.72Hours or 283.22 minutes for NT=3;
Then the average travel speeds of the tractors for the three fixed trips as estimated from
the haul times and total distances covered in primary collection become
V= 3.06 km/h for X= 10.2 km and h= 1.58 Hours in single round trip;
V= 2.19km/h for X= 12.2 km and h=4.54 Hours in double round trips;
V= 2.03km/h for X= 12.2 km and h=4.72Hours in triple round trips;
The observed average speed was 2.427 km/h for an average round trip distance of 11.53
km and average double round trips
The observed average speeds in primary collection service were very low and is one
reason for the prevalent inefficiency in primary collection. The low speed problem
together with the problem of spillage of waste materials at the hauled-containers sites
observed during primary collection operation make the municipal tractor-trailer services
inappropriate for primary collection.
(c) Number of pick up locations or blocks
The number of pick up locations per trip is calculated from
NP=Phcs n/tp
Where, Phcs =pick up time per trip (h/trip);
n=number of collectors (2);
tp=pick up time per pick up locations
The pick up time per pick locations in SCS can be expressed in three units. Either in
collectors-h/location or collectors-h/block or collectors-h/stationery container.
Page 105
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
105
Table Labor requirements for manual curbside collection using one-person crew
Average number
of
Stationery containers
and/or boxes
Per pick up locations
Pickup time,
Collector -min/location
1 or 2
3 or more , or
Unlimited service
0.50 -0.60
0.92
The average speed for the average pick time of Phcs =1.176 hours observed in the current
tractors service was V=5.77 km /h. The estimated number of pick up locations for
number of collectors of n=2 and pick up time tp=0.92 and considering unlimited service
from the SC and/or boxes per pick up locations become
NP= 1.176 * 60*2/ 0.92
= 153.39 pick up locations per trip
(d) Volume of solid waste
The number of pick up locations in service area with solid waste collection capacity of
Vp are given by
NP = (Vsw *r)/ Vp
Where, Vsw =volume of collection vehicle (tractor-trailer), cu.m/trip
Vp =volume of solid waste collected per pick up locations, cu.m/location
r =compaction ratio, 2 to 2.5 for manual loading collection method;
The estimated volume of solid waste collected per pick up locations considering a
reported tractor collection capacity in a round of Vsw = 4.00 cu.m/trip becomes
Vp = 4.00*2.25/153.39
=0.059 cu.m/location
OR =59 liter/location
This means only single standard stationary-container with holding capacity of 61 liter
was picked from single location in tractor-trailer collection trips. The commonly used
standard size of containers ranges from 60 to 160 liter.
The quantity of solid waste generated in 2005 from single family in residential sources is
4.508 liter/d. The number of house holds covered in the current primary collection
service is estimated to be 13 house holds per location, which means nearly half of a
standard block containing 20 house holds.
Page 106
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
106
(d) Desired number of locations per trip
The average rate of waste generation in residential sources in 2005 is 0.92 liter/c/d and
the average numbers of households (NHH) served at a location are
NNH=13 house holds per location
(Considering average household size of 4.9 in the city)
The desired number of locations in a daily one trip to cover 44255.1 households (2005) in
the city,
The number of locations in primary collection services that would be required in tractor-
collection services to cover a total of 44255 households in residential areas in 2005 in
whole city
(NP) desired = 44255house holds/ 13 house hold units/ location
= 3405 locations
(Each with 59 liter garbage collection capacity)
The required number of trips in a working day to cover all residential households with a
collection capacity of 153.39 pick up locations per trip in 2005 would be
= 3405 locations / 153.39 pick up locations per trip
= 23 trips per day
The available numbers of tractors are four and the average trips per tractor per day would
be 5.75 trips per day. This means the required time per working day for a single tractor
would be
H= [(0.0694 + 0.194) + 5.75 * 2. 49)/ (1-0.15)
= (0.2634 + 14.32)/ 0.85
= 17.154 hours for single tractor-trailer
The official working hours in a day work are only 8 hours and the remaining 9.154
working hours could not be actually serviced by the tractors. The wastes generated in at
the collection locations in the stated hours without primary collection services could not
be collected. The primary collection service would be late by 9.154 hours behind waste
generation and primary collection operations would be insufficient in all the 3405
estimated locations in the city. This condition would result in accumulation of waste
above the holding capacity of the stationary –containers (SC) that would be located at the
locations or above the holding capacity of household containers.
The poor collection capacity of the current service could be managed either doubling the
holding capacity of all the locations or doubling the number of tractors in the current
primary collection services. These scenarios do not seem economical because of the
inefficiency in primary collection with tractor-trailers as observed in the current
Page 107
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
107
municipal service. The other technical problem is that the holding of generated wastes
for a period of two weeks time in households does not seem technically feasible and it is
also hardly possible to mobilize the house holds in voluntary waste handling practices.
Page 108
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
108
Annex C: Assessment of Secondary Storage and Collection Services
Field survey is carried out on the existing communal containers site to investigate the
impacts of secondary storage and collection services in the city and collect adequate
technical data for the future improvement of the service.
One field enumerator and observer works under the principal investigator (supervisor)
moved in all the containers and collect the desired information. The enumerators handle
29 in Southern sub-city and 23 in Northern sub-city in seven days time. The field
enumerator works closely with the municipality service workers to facilitate the field
observation.
Similar observation was taken from 27/02/1998 to 02/03/1998 at the two disposal sites
currently used by the municipality. A second enumerator was allotted for the
observations to be taken at the disposal sites and the contents of the survey are also
different for the investigation at the disposal sites. The result of field observation is
summarized and displayed on table 3.8.
Page 109
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
109
N
Tabia administration
Addis Alem
Adihausi
Ayder
Hadnet
Haulti
Inustry
Kedamay Weyane
Sewhi Negus
Administrative boundary
þ Container position
Influence area of one
container position
þ
þþ
þ
þþ
þþ
þþ
þ
þ
þ
þ
þ
þ
þ
þþ
þþ
þ
þ
þ
þ
þ
þþ
þ
þ
þ þ
þ
þ
þ
þ
4241
33
40
25
1
5
23
4
29
26
7
22
30
12
35
21
6
3
18
2
939
37
27
24
31
3810
36
20
19
34
17
15
32
14
28
8
13
Container position andInfluence area of single container position
FigureExisting communal container locations, spatial coverage of each container position
and Recent Tabia administration
Page 110
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
110
Table: Assessment existing secondary collection system
Assuming Regular weekly collection
Determination of Storage Capacity and number of HCs for Residential sources
2005 Weekly
(01MSW in 2005)
Existing
storage(cont
ainer)
capaciy (%)
Storage
(Container)
Requirement
indicator
(m3)
Required
container
no.(for
100%effic
iency)
Required
container
no.(for
70%effici
ency)
Require
d
containe
r no.(for
50%effi
ciency)
2005 Size of Weekly Weekly Mean
SN Tabia No. Weekly Container Storage Collected Generated
Container
s Frequency (cu.m)
Capacity(cu.
m) Waste(cu.m)
Waste(cu.
m)
1 Hawltie 8 4 7.2 57.60 28.8 168.24 34.24% 110.64 15 11 8
2
Kedamay
Weyane 6 4 7.2 43.20 28.8 181.85 23.76% 138.65 19 13 10
3 Industry 8 6 7.2 57.60 43.2 118.24 48.71% 60.64 8 6 4
4 Adi Haki 6 4 7.2 43.20 28.8 171.76 25.15% 128.56 18 12 9
5 Hadnet 10 8 7.2 72.00 57.6 174.81 41.19% 102.81 14 10 7
6 Addis Alem 6 3 7.2 43.20 21.6 120.53 35.84% 77.33 11 8 5
7
Adishum
Dahan 3 2 7.2 21.60 14.4 42.70 50.59% 21.10 3 2 1
8 Ayder 6 4 7.2 43.20 28.8 162.72 26.55% 119.52 17 12 8
9
Sewhi
Negus 5 6 7.2 36.00 43.2 127.23 28.29% 91.23 13 9 6
10 Quiha 5 3 7.2 36.00 21.6 120.53 29.87% 84.53 12 8 6
11 Aynalem 1 0 7.2 7.20 3.6 22.47 32.04% 15.27 2 1 1
Total 64 44 460.80 320.4
1411.0782
8
132 92 66
Average existing collection frequency storage
capacity =68.75%
Average existing storage
capacity =34.2%
Attainable collection
efficiency if only frequency of
collection equals no. of
containers
Problem of transportation
Problem of Transportation
Page 111
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
111
Page 112
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
112
i. Annex D: Survey Methodology
It is believed that most SWM practices in Developing countries suffer from absence of the
desired technical information regarding the capacity, operation, management, and
maintenance of public facilities and services. Available information could also be insufficient
for comprehensive studies and may not exist at the desired level of technical details. Because
of these limitations in public services, the execution of recent and new projects demands the
filling up of missing technical data.
The information available on existing SWM services and practices of Mekelle City is deemed
to be scant and the consultant have identified that there is a need to conduct further
investigation on the current situation of solid waste management(SWM) in the city .
Promise consult discovered that the necessary technical information do not exist in relation to
existing SWM practices ,which are considered important to undertake comprehensive study
on Integrated Solid Waste Management (ISWM) of the city and good planning and design of
solid waste management infrastructure for improved SW service.
The data gap discovered within the current situation of the SW system in all the sub-cities
(Northern, Southern, Quiha, and Aynalem) are summarized and briefly citied in the
subsequent sections. Some of the data gaps and the issues of solid waste monitoring are
presented in checklist and question forms and various forms and questionnaires are prepared
to fill the data gap [annex A]. The summary is cited below.
D.1. Solid waste generation
Sources of solid waste in the entire city
Percentage composition of solid waste from the various SW category and sources
Proportion of expected solid waste constituents in the SW categories
Per capita rate of generation in liter/capita/day and kg/capita/day
Properties of SW such as unit weigh(loose, as-discarded, as-disposed, as-compacted),
moisture content, particle size, etc from various sources of generation
Generation of hazardous and special wastes
D.2. Primary Handling and Storage
Current methods of SW handling and primary storage at the source of generation
SW separation and sorting out at the sources of generation
Methods of SW separation (manual or mechanical)
Assess the level of awareness and readiness on part of the residents regarding waste
processing at the sources
Data on current solid waste processing at the sources
Data on solid waste handling at municipal level and in the streets
Availability of street and public solid waste bins in the city and their adequacy
Management of street SW cleaning, storage and collection services
Page 113
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
113
Do the public use the bins? How is the appropriateness of the bin technology (size, height,
material, and comfort in the use of the bins)? Where the bins are provided? How they are
cleaned? Are they protected from vandalism and theft? How is the sense of ownership of the
public? Impacts of the bins on street cleaning and the public user;
D.3. Primary Collection (PC)
♠ Methods of primary collection and primary transfer of SW from the sources of generation
How the other sources of SW such as commercial, institutional, industrial,
construction and demolition, and agricultural activities in the city transfer their SW to
the municipal system except the residential sources (01MSW)?
♠ Primary block collection (PBC) or house-to-house collection with tractor-trailers:
their capacity, coverage, and operation; size of the trailers, operation and
maintenance(OM) cost, collection routes, operation plan and fleet management, man
power , weekly area coverage or coverage of households , efficiency of the PBC
service , service charges and rates in relation to PBC , capital cost of the existing
tractor-trailers PBC service;
♠ Saba Sanitation and Gojo Sanitation Services (SS‘s):
Institutional data of the MSE‘s;
the kind of problems they encountered in their services; how they are rendering
service to the public; how they are working with the public and the City
Administration; their plan in the future in relation to SWM;
their know-how and knowledge on SWM practices;
♠ Performance of micro and small enterprises (MSE‘s) in primary collection activities:
the MSE‘s coverage in terms of service areas, land uses and SW quantity, their daily,
weekly, and yearly performances;
the technologies the MSEs adopt in primary collection of SW;whether the
technologies are appropriate in relation to PC services and the topography of the city;
Fees the MSEs charge the users for providing PC service;
Whether the MSEs were registered and given permit; their know-how on SWM
practices; the sustainability of their current business;
♠ Guidelines for regulating the performance of MSE‘s:
Whether there are guidelines at the municipality or other official level to regulate their
performance, implementation of the guideline (if it exists)
Whether the necessary regulatory frame work is laid at City Administration, State or
Federal Level;
♠ Illegal dumping sites created due to PC
How illegal dumping sites are created in relation to PC, location of the sites in the city,
and whether there are any containers near to the sites, distance of the containers from
Page 114
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
114
the dumping sites, the dominant land use around the sites, the possible reasons for
emergency of the illegal dumping sites ,complete absence of communal containers,
inadequate number of containers, intentional unawareness on the side of the users,
real unawareness regarding the use of the container service, negligence in the use of
the containers, inefficiency in municipal collection services, inconvenience around the
containers, long travel distance to the services or unaffordable service charges;
inefficient regulatory works to implement laws, regulations, proclamation, and
policies issued on waste management;
D.4. Communal storage
♠ Functionality and efficiency in the use of the skips
Are the skips convenient to be used by the four modes of PC‘s (handcarts, horse carts,
tractor-trailor, and manual labor PC‘s)? Are stands provided for the containers? Are
steps provided for manual labor PC‘s? Are the containers secured from vandalism?
Are they protected from unauthorized access? Are the skips protected from
scavengers? Are they fenced? Does litter exist around the storage sites? What is the
dominant material in the litter? Is the facility protected from wind effect? How is the
orientation of the skips relative to other land uses and in relation to wind effect? Do
any nuisance animals exist around and inside the container? Are the skip sites odorous?
What are the activities around the containers? Residents? Commercial activities?
Open field? Open market? Play grounds? Shops? Green areas? What urban activities
are currently disrupted around the containers? What about municipal services? How
many households complained about flies? About scavengers? About offensive odor
(OO)? How much households actually are affected with vector borne communicable
diseases? Are there any waste workers (WW‘s) working on the sites? In what
activities are they engaged? Are they protected from the impacts imposed by the
container service?
♠ Geographical coordinates (X, Y, and Z) of the containers and installation history:
When was the containers provided for service? Who manufactured the containers?
How the containers are initially located? Who located the containers? What was the
estimated spatial coverage of single skip in each location? Was uniform spatial
coverage considered in each land uses and for any number of skips? How are rates of
generation, capacity of skip loaders and location of disposal sites taken in to account
while locating the skips? How is the number of the containers estimated? Are the
containers labeled? Are the skips painted and marked? Are the containers currently
accessible from any side of the service areas? How is the road infrastructure
surrounding the containers?
♠ Collection capacity of the containers and SW composition:
How much waste loads the containers currently receiving? (daily, weekly, monthly
and yearly) What type of SW materials reach to the containers? What materials are
delivered from the different urban activities served with the containers? Which land
uses actively use the containers? How much is the proportion of SW delivery to the
containers from the various SW sources? The percentage proportion of Special,
Hazardous, Residential, Commercial, Institutional, Industrial, Construction and
Page 115
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
115
Demolition and Agricultural solid wastes (daily, weekly, monthly, and yearly)
received by each container in different service areas; Are the containers currently
receiving special and hazardous wastes? From which sources? Which is the dominant
special waste contributor to the containers? Hazardous waste contributor? What are
the special and hazardous waste materials received from different sources? How much
is the proportion of the materials?
D.5. Secondary Collection and disposal
♠ Collection and transportation:
The Hauled-Containers Collection system: Is the hauled –container collection system
conventional mode or exchange container mode? Is there any formal route of
collection? How much total time the skip loaders spend in each route? How much are
pickup time, loading time, and redeposition time in the same station in each route for
conventional mode of collection? How much is pickup time and the redeposition time
in next station in each route for exchange container mode of collection? How much is
the total time per trip in each route for the hauled container collection system , which
is the sum of pickup time, at-site time and haul time? How much is the off-route time
wasted in each trip and routes? How much is the working hours in a day? How much
is the average speed of the skip loaders in each route? How many number of skip
loaders serve each of the four sub-cities (Northern, Southern, Quiha, and Aynalem
sub-cities) in the service? How frequent is the skip loaders ere available in the service?
How efficient are the skip loaders utilized?; How much was the daily, weekly,
monthly, and yearly frequency of collection of each loaders in each sub-cities; How
much quantity of solid waste (volume and weight) collected and transported from
each collection site in all the four sub-cities (daily,weekly,monthly,and yearly)?
♠ Road infrastructure in collection routes:
How is the condition of the roads in the formal and informal collection and
transportation routes?
♠ Performance of the skip loaders:
Is the number of skip loaders adequate in the current collection and disposal service?
Are the existing three loaders efficiently utilized? Are the loaders available every day
in the service? Are they serving regularly? How old are the loaders? What kind of
service maintenance the loaders were getting? Is there any permanently established
maintenance center? Where is its location? How is the institutional capacity of the
center? Is it public or private institute? How much mechanics exist in the center? Are
there any spare part stocks in the center? How is the fuel supply in the service? How
efficiently it undertake service during breakdown of the loaders? In which hours of
the day the maintenance services are commonly done? At what days and time of the
week? How much is the daily, weekly, monthly, and yearly operation and
maintenance costs (OM) of the service (manpower, fuel, spare parts, maintenance
charges to private firms, overheads, etc)? How much is the OM cost per each loader
and per each collection and transportation in each route? How much was the initial
cost of investment on the loaders? What was the source of finance? How much is the
collection and transportation service charge? How was the tariff fixed? Is it affordable
in the service? Was there any service subside scheme in the past?
Page 116
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
116
♠ Private sector involvement:
How was the involvement of private sectors in secondary collection and
transportation service? What was the major obstacle? Was there any request for
permit from private sector to undertake private solid waste secondary collection and
disposal? How much service charges were proposed in the service areas by the private
applicants?
♠ Disposal in land fills:
The quantity of solid waste (volume and weight) received at the Messobo landfill site
so far different locations in the service area? In which operation periods? How much
is the weight and volume of solid waste mounted on skip loaders as it reached at the
land fill site? How was the efficiency in the performance of the land fill sites? Are the
conditions one reason for the inconsistent collection, transportation and disposal
efficiency? How the site was operated after construction? Was the designed method of
land filling suitable for the site? Is there any other best method of land filling? Are
there any maintenance operations undertaken on the site? How much was the cost the
OM on the disposal site? How much the opposition from local community disrupted
the land filling process at the site? Is there any possibility to improve and expanded
the land fill site? What was the actual impact on the local community and the
environment? How much area is covered with suspended litter materials? What is the
actual location of the site in relation to settlement sites, farm lands, and other
activities? What is the present condition of the site? Is there any closure plan
developed for the land fill site?
♠ The other land fill site (north of Quiha):
Is there any technical data on the second site? What was its initial design capacity?
How is the current status of the site? Are there similar environmental and social
problems in the second site like the Messobo (the big site) site? In addition investigate
all the ideas raised under the Messobo land fill site;
♠ Prospective land fill sites:
The proposed land fills sites by the Municipality require field investigation and Initial
Environmental Impact Assessment (EIA).One of the sites is proposed around a village
called Adi Kolomay. The second site is near the existing dump site at Messobo.
It is vital to undertake EIA on the proposed and existing sites before designing and
implementing the land fill sites.
D.6. 3Rs and Waste transformation (WT)
♠ Composition and proportion of materials:
How much of the MSW, ISW, and ASW materials could be considered for the 3R'S
solution? What is the composition of the SW sources in relation to waste reduction,
Page 117
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
117
recycling and reuse? What are the waste diversion and reuse opportunities? Are the
recyclable materials exist in the city? Are there any specifications of buyers of
recovered materials for all type of potential materials in waste streams? Are there any
formally registered drop-off and buy-back centers in the city? How are the recyclable
items collected? Are there any street side collection facilities for the items in the city?
♠ Informal and waste Materials Broker‘s (WMB's) businesses:
How is the performance of the informal sectors in the 3R's practices? What are the
lists of materials recovered, recycled and reused through the informal business? How
much was the annual quantity of the materials? In which sources of SW in the city the
informal sectors actively engaged in the 3R practices? How the informal businesses
earn benefits? Where do they take the recovered materials in the city and else where?
How much is the cost of recovered items in the informal sector?
♠ Local technologies in the 3R practices:
What are the local technologies introduced for the processing and manufacturing of
recovered and recycled waste materials? Who own, promoted and transferred the
technologies? Are there any private companies, cooperatives, and investors involving
in waste recycling business? Is vermo-composting introduced in the city? Is biogas
technology applied in SW management?
♠ Recovery and reuse within households:
What materials were considered for these purposes in the households? What is the
proportion and quantity of the materials? What benefits the households got from the
practices?
♠ Micro and small enterprises (MSE‘s):
How much land allotted to MSE‘s for waste processing? Where is the exact location
of the allotted land? Is it near to Agricultural Land uses? How was the land
requirement estimated? How the proposal of the MSE‘s got approval? Is there
feasibility study on WT technologies? Is the participation of MSE‘s in waste recovery,
reuse and transformation business sustainable? Are they going to be product suppliers?
Is market availability for the MSE‘s products? Are the MSE‘s to be engaged in
agricultural activities and use the processed waste products in their own business and
sell the agricultural products? Are there any guidelines for regulating MSE‘s
performance and products? Will they face the threats in urban agriculture and solid
waste management together? Will they undertake integrated business? Will the
MSE‘s and other stakeholders synchronize in the both urban agriculture and urban
solid waste management?
What aspects of institution in relation to SW services need to be investigated? What
methodology is adopted for this purpose? How these improved institutional aspects
contribute to the realization of improved SW services?
PART II: METHODOLOGY
Page 118
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
118
This section mainly discusses on methodology to fill the data gap and conduct feasibility
study.
METHODOLOGY OF FIELD INVESTIGATION TO FILL THE GAP
This Methodology briefly outline the approaches and techniques to be followed in fulfilling
the missing but necessary solid waste (SW) data as part of the feasibility study of the project.
The major activity considered here is the filling of technical data gap discovered in the initial
situation analysis.
Solid waste Source Category
The identification of the sources of solid waste in the City is the first engineering task in solid
waste characterization. The type, composition and properties of the SW in Mekelle City then
are determined for each sources of generation. The existing land use data has been used to
identify the urban activities in the city.
The most commonly used solid waste category for urban areas and in municipal solid waste
management services considers three broad classes, namely municipal solid waste (MSW),
Industrial solid waste (ISW) and Agricultural solid waste (ASW). The solid waste categories
has been identified for the City examining the existing socio-economic and investment
activities, the status of solid waste management within the service area and land use
information. The list of the SW sources and category are summarized in table 1.1. The source
identification covers eleven solid waste sources.
Two more sources are included, i.e. Water and waste water treatment facilities (01WWT &
02WWT), considering the need for liquid waste and sludge treatment, and provision of safe
water from reservoir for Mekelle City in the coming decades.
Table: Solid waste categories for the City of Mekelle
Project
Code
Solid waste
Category
SW generating Urban activities
01MSW Residential Dwellings
02MSW Commercial Medium & Small scale enterprises (MSE‘s) ,private
commercial activities(PCA‘s) and market places
03MSW Institutional Public services mainly educational and health services
04MSW Municipal
services
Mainly street sweeping, landscaping and recreational
05MSW Municipal special Residential, commercial, and Institutional activities
06MSW Municipal
Hazardous
Commercial and Institutional(hospital) activities
01ISW Industrial Construction ,manufacturing, demolition, and MSE‘s
02ISW Construction
and demolition
Municipal, private, cooperatives and institutional building
construction and maintenance, municipal and institutional
Page 119
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
119
road construction and maintenance, civil engineering
construction contracts, and city infrastructure offices(mainly
telecommunication and water service installations)
03ISW Industrial special manufacturing and assembling, metal and wood furniture,
food and kindred products (slaughter house oil, and bones ;
food processing and packing factories), lumber and wood
products (bulky items),printing and publishing, and electrical
manufacturing,
04ISW Industrial
Hazardous
Printing and Publishing (printing chemical and inks),Rubber
and miscellaneous plastic products(plastics forming organic
chemicals and dyes) and chemicals and related
products(alcohol factory)
01ASW Agriculture Urban agricultural practices such as planting and harvesting
of row, field, and vine crops; production of milk; rearing of
animals for slaughter;fattening schemes; poultry and other
animals farm; operation of feedlots
02ASW Agricultural
hazardous
Dumps of chemical fertilizers and pesticides
01WWT Waste water &
Sludge
Treatment facility
Unit operations and processes
01WWT Water treatment
facility
Unit operations and processes
Field Sampling
Residential Sources (01MSW)
All the ten Tabias currently existing in the two sub-cities of Mekelle are to be considered as
observation sites for Residential SW sources. The total sample sizes for sampling will be 3%
of the total house holds (HH‘s) in each Tabia. The survey will investigate the total and per
capita rates of solid waste generations, proportion of various solid waste materials in
household SW samples, and properties of the Residential SW in four household socio-
economic groups. The total number of sample households and classification of socio-
economic groups to be considered for the field investigation in each Tabia are given in table
1.2 below. The number of sample households is calculated based on the year 2004 population
of the twelve sampling locations collected from the Mekelle City Master Plan Development
project. The SW from Residential sources will be characterized based on a total sample
households of 1162 collected from all socio-economic groups in the Tabias.
Promise consult will select sample households in each Tabia in consultation with the City and
Tabia Administration offices one week ahead of sampling.
Table: Distribution of sample household sizes in Residential establishments
Sr.
Locality
Inhabita-
nts
estimated
Households
Sample
Number of sample
households for
each income group (Monthly average
income in Birr)
Page 120
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
120
No. (2004) HHs 0-
500*
500-1000 1000-2000 >2000
A B C D
1 Aider 24300 4959 149 68 36 27 18
2 Hawelti 25125 5128 153 72 36 27 18
3 Adi Haki 25650 5235 157 71 38 29 19
4 Kedamay
Weyane
27157
5542
166
76
40
30
20
5 Hadenet 26106 5328 160 74 38 29 19
6 Sewhi
Niguse
19000
3878
116
53
28
21
14
7 Adise Alem 18000 3673 110 51 26 20 13
8 Industry 11766 2401 72 31 18 14 9
11 Adi-
shumduhun
6376
1301
39
16
10
8
5
12 Ellala 6515 1330 40 17 10 8 5
Total 189995 38775 1162 529 280 213 140
* City Wide proportion of low income group is more than 70%;
Source: MCPPP
Then standard plastic bags of 1m2 minimum area will be issued to each sample house holds
and will be advised to store their household garbage honestly and carefully for a minimum
generation time of one week. The sample house holds may alternatively use their own storing
bags or barrel.
The measurement of observations house-to-house will be a cumbersome task. Instead
convenient and centralized observation sites will be located within the proximity and
boundary of the sample households. The Enumerators collect household samples on each
observation sites and take all the necessary measurements. The standard forms for recording
observations of generation rate, proportion of constituent and properties of SW are attached
in Annex A.
Other SW sources
There is scant technical and socio-economic information on the commercial, institutional,
industrial, municipal and agricultural activities of the project city. There is no list of
operational industrial, agro-industrial and commercial activities.
Efforts have been made to take into account all the available information on the urban
activities as collected, compiled and analyzed by the socio-economic and demographic team
of the City Master Plan Development project. The data on the urban activities is summarized
in Table 1.3 below
The socio-economic and service data clearly cite that the manufacturing, construction,
transportation and service sectors have leading share in the urbanization of Mekelle City. The
construction sector mainly represents the housing and industrial development activities in the
City. These activities are expected to generate significant SW quantities in different parts of
the City, which is not known at the moment.
Therefore, field observations need to be conducted in selected sample urban activities and
services.
Page 121
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
121
Commercial Sources (02MSW)
There around 2677 commercial units inside the city. These services include hotels,
restaurants, pastry, super markets, shops, bars, night club (Abyssinia), electronic shops, spare
part shops, tire suppliers, tailors, boutiques, drug shops, fruit vendors, glass workshops, flour
mill, crop selling stores, red pepper shops, Kat vendors, cereals and spice shops, barberry,
open bed markets (Medebe),etc.
Table: Urban activities in Mekelle city
Sr.
No.
Activities/Socio-economic
Aspects
1 Investment shares ranking
Industrial (Manufacturing, construction, and transport)=88.08%
Institutional(Social services and real state)=4.93 %
Commercial(hotel & trade) =3.85 %
Agriculture=3.13%
2 Job opportunity ranking
Manufacturing
Construction sector
Transport
Social service
Hotel
Agriculture
Trade
Real state
3 Services coverage
3.1 Government Health services(year 2002):
Hospital=1
Health centers=3
Clinics=3
Referral hospital=1 very soon
3.2 Educational facilities
Governmental institutions:
Kindergarten=1
Primary school=20
Secondary school=4
Institutions=3
Public university=1 (Main campus + Adi Haki Campus)
Private institutions:
Kindergarten=13
Primary school= 5
Secondary school=1
Institutions=6
No University
NGO‘s:
Kindergarten=4
Primary school=9
Secondary school=4
Page 122
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
122
Cont‘d
No institutions ,colleges and universities
3.3 Digital Telephone(May 2004):
Residential areas=7029 in numbers
Government, NGO‘s, Institutions, and Enterprises=1211
Commercial centers=2677
Others=36
3.4 Water service(July 2004):
Distribution pipe=46.5 km
Availability:
House tape users= 43.9 %
Public tape users=7.9 %
Neighborhood & traditional source users=48.4%
3.5 Market places:
Edaga kedamay woyane
Edaga Adi-haki
Edaga Enda-sellassie
Enda Sewhi-Nigus(Edaga Kedam)
Edaga Aider
Edaga Industry (May Duba)
Edaga Adi-Hawsi
Edaga Adi-Shumduhun
Edaga Quiha
Edaga Aynalem
Livestock market (13903m2 fenced area)
3.6 Enkodo Abattoir:60-70 cattles/day design capacity & actual=33
3.7 16-Orthodox churches: Inside Mekelle,Quiha,& Aynalem
3.8 3- Mosques: Inside Mekelle
Source: MCPPP
Sample size of 10%, i.e.268 commercial units, will be considered to investigate the
characteristics of solid waste from the commercial group. Most of the commercial services
exist at the center or near the centre of the city and more number of samples will be taken
from the center. But this sample size does not include the observation sites within the eleven
market places. Separate samples and observations will be taken in all the market places inside
and outside Mekelle city. The market places lack information regarding the various
commercial specialties and activities and the number of commercial units contained in each
places. Because of this, samples will be collected from the most common commercial
activities and the minimum sample size in the market places of Mekelle except the Livestock
market will be 20.The distribution of sample sizes in commercial SW sources is indicated in
table 1.4.
The field investigation in commercial sources will consider total of 195 samples all the
market places and a total of 269 samples in the commercial activities in all the four sub-cities
(Northern, Southern, Quiha, & Aynalem).The distribution of samples in each observation
sites is given in table 1.4. And the field sampling forms are attached in Annex A.
Table: Distribution of sample in commercial sources
Sr. Commercial units Commercial units
Page 123
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
123
No. Tabia /Place inside markets outside markets
No. of
markets
No.of
Samples
3% Samples
(80)
10% Samples
(268)
1 Aider 1 20 9 31
2 Hawelti(Adi-Hawsi) 1 20 10 32
3 Adi Haki 1 20 10 33
4 Kedamay Weyane 1 30 11 34
5 Hadenet - - 10 33
6 Sewhi Niguse 1 20 7 24
7 Adise Alem - - 7 23
8 Industry 1 20 5 15
11 Addi shumduhun 1 20 3 8
12 Ellala - - 3 8
13 Enda selassie 1 20 - -
14 Samre road livestock 1 5 - -
15 Quiha 1 15 7 23
16 Aynalem 1 5 3 5
Total 195 85 269
The field investigation for institutional sources will be conducted in existing health,
education and administration services in Mekelle, Quiha and Aynalem. The samples
distribution of institutional sources is given in Table 1.5.
Institutional sources (03MSW):
The available data on institutional activities is also little similar to the commercial and
industrial activities. The information obtained from the City Master Plan group covers
education and health services. The number and occupation of the various offices and
administration centers in the city are not included in the available data. The administration
institutes include Tabia, Wereda, Zonal, and Regional Administration offices, Departments,
and Bureaus, private consulting offices, post office, utility offices such as telecommunication,
water, electric service offices, security office (Mekael Guaro),
etc.
The total samples to be taken in institutional activities will be 30 out of ten samples in
Administration offices, five samples in private and public services, three in health facilities,
five in government, four in private and three NGO‘s educational facilities, Mekelle hospital
will be one of the observation sites of heath facilities and Mekelle University (Adi Haki
Campus) will be one observation site of educational facilities. The field sampling forms are
attached in Annex A. The biomedical wastes and their management will be the main focus of
the filed investigation and waste monitoring task in medical and institutional facilities.
Table: Distribution of Samples in institutional sources
Sr.
No
Institutional activities Total
units
No. of
Sampl
e
percentage
sample
size
1 Administration
Page 124
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
124
Tabia offices
Wereda offices
Zonal departments
City Council
Regional Bureaus
Regional Government
Security office
12
2
-
1
-
1
1
2
1
2
1
2
1
1
16.67
50
-
100
-
100
100
2 Private and public services
Consulting firms
Telecommunication service
Electric service
Water service
-
2
2
1
2
1
1
1
-
50
50
100
3 Health facilities :
Hospital
Health centers
Clinics
1
3
3
1
1
1
100
33.33
33.33
4
4.1
4.2
4.3
Educational offices:
Governmental
Kindergarten
Primary school
Secondary school
Institutions
Public university
Private
Kindergarten
Primary school
Secondary school
Institutions
NGO‘s:
Kindergarten
Primary school
Secondary school
1
20
4
3
2
13
5
1
6
4
9
4
1
1
1
1
1
1
1
1
1
1
1
1
100
5
25
33.33
50
7.70
20
100
16.67
25
11.11
25
Total institutional samples 30
Industrial sources (01ISW):
The industrial activities are complex and diversified like the commercial activities. This will
make the field investigation tire some. The other challenge in relation to these two main
urban activities is the absence of complete official registration list and standard local category
of the activities. The third challenge here is that there is no clear distinction between most
commercial and industrial urban activities. Most industrial activities are locally registered as
commercial activities especially small scale industrial activities and micro and small
enterprises engaged in small scale urban industrial activities.
Efforts will be envisaged to outline category for industrial activities and to group the existing
activities in the city related to industry accordingly. The registered permits on the commercial
and urban activities will be collected from local finance and trade offices. Then the registered
urban activities will be group according to their industrial specializations.
Page 125
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
125
The investigation in industrial sources will be undertaken on samples to be taken from the
following fifteen categories of Standard Industrial Classification (SIC), which most are
believed to exist currently in the city.
Food and kindred products(SIC-20): processing, packaging, and shipping; example the
slaughter house service at Enkodo River;
Textile mill products(SIC-22 ) :mainly weaving (local weavers);
Apparel and other finished products(SIC-23): cutting, sewing, sizing, pressing cloth,
fibers, metals, and rubber; Example local tailors and metal work shops;
Wood Furniture(SIC-25a): manufacture of household and office furniture, partitions,
office and store fixtures, mattresses, plus cloth and padding residues), Example wood
works shops
Metal furniture(SIC-25b) :manufacture of household and office furniture, lockers, bed-
springs, frames; Example metal workshops
Printing and Publishing(SIC-27): Newspaper publishing, printing, lithography, engraving
and bookbinding ;
Chemicals and related products(SIC-28):: manufacture and preparation of inorganic
chemicals ranging from drugs and soaps to paints and varnishes, and explosives, alcohols,
organic and inorganic chemicals),
Rubber and miscellaneous plastic products (SIC-30): manufacture of fabricated rubber
and plastic products;
Cement Stone, clay, and glass products(SIC-32) :Manufacture of flat glass, fabrication
and forming of glass; manufacture of concrete, cement, gypsum, and plaster products;
Forming and processing of stone and stone products, abrasive, asbestos, and
miscellaneous non-mineral products; Example Messobo Cement factory and glass work
shops;
Primary metal industries(SIC-33):Melting, casting, forging, drawing, rolling, forming,
extruding operations; Example MIE & Argegawie Korkoro;
Fabricated metals products(SIC-34): Manufacture of metal cans, hand tools, general
hardware, non electric heating apparatus, plumbing fixtures, fabricated structural products,
wire, farm, machinery and equipment, coating and engraving of metal;
Machinery except electrical(SIC-35): Manufacture of equipment for construction, mining,
elevators, moving stairways, conveyors, industrial trucks, trailers, stackers, machine tools,
etc; Example MIE;
Electrical(SIC-36):Manufacture of electric equipment, appliances, and communication
apparatus; machining, drawing, forming, welding, stamping, winding, painting, planting,
baking, firing, operations; Example electric appliances producers like stoves, baking
plates(―Mitad‖), boilers, etc.
Transportation equipment (SIC-37): Manufacture of motor vehicles, truck and bus bodies,
motor vehicle, parts and accessories, aircraft and parts, ship and boat building and
repairing, motorcycles and bicycles and parts, etc. Example. MIE and private bicycle and
motorcycles repair shops;
Miscellaneous manufacturers(SIC-39): Manufacture of jewelery, silverware, plated ware,
toys, amusement, sporting and athletic goods, costume nobilities, buttons, brushes, signs,
and advertising displays; Example jewelery shops;
The consultant will consider the use of local industrial classification, if it exists at all, instead
of SIC. But for the time being, the SIC listed above will be adopted and rectification may be
considered in later works during the analysis of the filed investigation data.
Page 126
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
126
Minimum of two samples will be collected from each industrial category and the large scale
factories in the city such as Messobo Cement factory and Mesfin Industrial Engineering (MIE)
will be taken as sample observation sites under their respective SIC categories. A total of
around 30 samples on industrial activities will be observed in the project city.
Construction and demolition (02ISW):
The most vibrant industrial activity in the city of Mekelle is the private building construction
activities. There are significant numbers of construction projects in various categories, which
have been undertaken in the last five years. The most common categories of construction and
demolition activities under the two major projects, namely buildings and roads construction
and maintenance are private ordinary and storied buildings, government ordinary and storied
buildings, cooperative housing, municipal paved roads construction and maintenance,
unpaved roads construction and maintenances.
These nine categories of construction and demolition sources will be considered for the filed
investigation.
The actual figures on the private and municipal construction projects and activities are not
available at the moment. The field investigation will focus on sampling of live construction
projects. A minimum of two samples from each construction category will be investigated in
the project city. This means a total of around eighty (18) samples will be considered in the
survey.
Special and hazardous wastes:
These two categories will be investigated under all the other categories discussed in the
previous sections.
Agriculture Wastes (01ASW):
The consultant believes that there are some formal and informal UA activities inside and
within the outskirt of the city. The most common practices are milk production, poultry,
animals rearing and fattening, horticulture and fruit farms, and others. These practices may
release significant SW materials into the MSW system. Most SW system in urban places
receives high loads of manure and other animals waste from urban agricultural activities.
The field investigation will cover this category of SW in the project city. A minimum sample
of ten activities will be considered and single observation will be made in ten urban activities.
Communal container and disposal sites
Field survey will be carried out in the existing 58 communal containers site to investigate the
impacts of secondary storage and collection services in the city and collect adequate technical
data for the future improvement of the service.
One field enumerator and observer working under the principal investigator (supervisor) will
move in all the containers and collect the desired information. The enumerators handle 29 in
Page 127
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
127
Southern sub-city and 23 in Northern sub-city in seven days time. The field enumerator
works closely with the municipality service workers to facilitate the filed observation.
Similar observation will be taken from the two disposal sites currently used by the
municipality. A second enumerator will be allotted for the observations to be taken at the
disposal sites and the contents of the survey are also different for the investigation at the
disposal sites.
Page 128
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
128
Page 129
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
129
ANNEX-E: Rates of generation from Municipal Solid Waste (MSW) Sources (City-wise)
Summery of Rate of Generation for MSW
sources Rates & Quantities of solid waste
Years 2005 2010 2015
Master plan population 216850.00 285489.00 335583.00
Average annual quantity (cu.m/yr) 114353.91 129540.33 156238.10
Average annual quantity (kg/yr) 1145041.32 1406307.50 1715342.27
Average monthly quantity (cu.m/m) 9529.49 10795.03 13019.84
Average monthly quantity (kg/m) 95420.11 117192.29 142945.19
Average weekly quantity (cu.m/wk) 2199.11 2491.16 3004.58
Average weekly quantity (kg/wk) 22020.03 27044.37 32987.35
Average daily quantity (cu.m/d) 314.16 355.88 429.23
Average daily quantity (kg/d) 3145.72 3863.48 4712.48
Page 130
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
130
ANNEX-F: City-wise Types of composition of Solid Wastes from Municipal Solid Waste
(MSW) Sources
Type Solid Waste from MSW
Yearly volume (cu.m)
2005 2010 2015
Organic recyclable(including paper + others) 46347.37 75201.63 90761.14
Organic recyclable(excluding paper) 37368.43 61155.88 73788.50
Organic recyclable(excluding paper +others) 26126.11 42721.20 51547.28
Plastic(all) 10002.49 16570.63 19985.63
Special wastes(excluding Yard wastes) 288.84 458.16 553.38
Hazardous waste rejects 2484.15 4022.18 4838.16
Hazardous plus special rejects(excluding yard
waste) 3017.56 4836.26 5814.40
Non-hazardous rejects 10299.71 15770.73 18869.29
Recyclables other than organics & plastic 18335.05 30674.03 36983.93
TOTAL 154269.71 251410.70 303141.71
Note: Rejects are to be transported to Land fill sites;
Page 131
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
131
Page 132
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
132
ii. ANNEX –G: PRELIMINARY COST ESTIMATION
Estimated cost of Decentralized Biogas units(DBU) for MSW feedstock
Table 1 Unit with 1 cu.m capacity(2.01m middle diameter)
Sr.No Item Unit Quantity Rate Amount(Br)
1 Site clearing sq.m 4.41 3 13.23
2 Excavation for structure cu.m 3.205 15 48.075
3 12 mm Brick Masonry wall sq.m 6.59496 70 461.64723
4 12 mm Brick Masonry Mixing Chamber (50cmx50cm) sq.m 1.5725 70 110.075
5 Plastering to internal side of brick wall with 1:3 mix ratio sq.m 3.29748 30 98.924406
6
12 mm Brick masonry Displacement Chamber 50cmX50 cm
internal size sq.m 2.7225 70 190.575
7 8 cm thick RCC cover for displacement chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
8 8 cm thick RCC cover to mixing chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
9 150 mm PVC feeding Inlet pipe LM 2 100 200
10 15-20 mm GPS gas collection & distribution pipe LM 5 30 150
11 Improved stove pcs 1 30 30
Sub Total 1356.6066
10% contingency 135.66066
Total 1492.2673
Estimated cost of capital per house hold(Birr) 1492.3
Page 133
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
133
Estimated cost of Decentralized Biogas units(DBU) for MSW feedstock
Table 2 Unit with 2 cu.m capacity(2.55m middle diameter)
Sr.No Item Unit Quantity Rate Amount(Br)
1 Site clearing sq.m 6.5025 3 19.5075
2 Excavation for structure cu.m 5.25125 15 78.76875
3 12 mm Brick Masonry wall sq.m 10.43252 70 730.27623
4 12 mm Brick Masonry Mixing Chamber sq.m 1.5725 70 110.075
5 Plastering to internal side of brick wall with 1:3 mix ratio sq.m 5.216259 30 156.48776
6
12 mm Brick masonry Displacement Chamber 50cmX50 cm
internal size sq.m 2.7225 70 190.575
7 8 cm thick RCC cover for displacement chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
8 8 cm thick RCC cover to mixing chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
9 150 mm PVC feeding Inlet pipe LM 2 100 200
10 15-20 mm GPS gas collection & distribution pipe LM 10 30 300
11 Improved stove pcs 2 30 60
Sub Total 1899.7702
10% contingency 189.97702
Total 2089.7473
Estimated cost of capital per house hold(Birr) 1044.9
Page 134
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
134
Estimated cost of Decentralized Biogas units(DBU) for MSW feedstock
Table 3 Unit with 3 cu.m capacity(2.90m middle diameter)
Sr.No Item Unit Quantity Rate Amount(Br)
1 Site clearing sq.m 8.41 3 25.23
2 Excavation for structure cu.m 7.205 15 108.075
3 12 mm Brick Masonry wall sq.m 13.37505 70 936.25321
4 12 mm Brick Masonry Mixing Chamber sq.m 1.5725 70 110.075
5 Plastering to internal side of brick wall with 1:3 mix ratio sq.m 6.687523 30 200.62569
6
12 mm Brick masonry Displacement Chamber 50cmX50 cm
internal size sq.m 2.7225 70 190.575
7 8 cm thick RCC cover for displacement chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
8 8 cm thick RCC cover to mixing chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
9 150 mm PVC feeding Inlet pipe LM 2 100 200
10 15-20 mm GPS gas collection & distribution pipe LM 10 30 300
11 Improved stove pcs 2 30 60
Sub Total 2184.9139
10% contingency 218.49139
Total 2403.4053
Estimated cost of capital per house hold(Birr) 1201.7
Page 135
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
135
Estimated cost of Decentralized Biogas units(DBU) for MSW feedstock
Table 4 Unit with 4 cu.m capacity(3.18m middle diameter)
Sr.No Item Unit Quantity Rate Amount(Br)
1 Site clearing sq.m 10.1124 3 30.3372
2 Excavation for structure cu.m 9.0562 15 135.843
3 12 mm Brick Masonry wall sq.m 15.98399 70 1118.8794
4 12 mm Brick Masonry Mixing Chamber sq.m 1.5725 70 110.075
5 Plastering to internal side of brick wall with 1:3 mix ratio sq.m 7.991996 30 239.75987
6
12 mm Brick masonry Displacement Chamber 50cmX50 cm
internal size sq.m 2.7225 70 190.575
7 8 cm thick RCC cover to mixing chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
8 8 cm thick RCC cover for displacement chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
9 150 mm PVC feeding Inlet pipe LM 2 100 200
10 15-20 mm GPS gas collection & distribution pipe LM 15 30 450
11 Improved stove pcs 3 30 90
Sub Total 2619.5494
10% contingency 261.95494
Total 2881.5044
Estimated cost of capital per house hold(Birr) 960.5
Page 136
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
136
Estimated cost of Decentralized Biogas units(DBU) for MSW feedstock
Table 5 Unit with 6 cu.m capacity(3.60 m middle diameter)
Sr.No Item Unit Quantity Rate Amount(Br)
1 Site clearing sq.m 12.96 3 38.88
2 Excavation for structure cu.m 12.48 15 187.2
3 12 mm Brick Masonry wall sq.m 20.31799 70 1422.2594
4 12 mm Brick Masonry Mixing Chamber sq.m 1.5725 70 110.075
5 Plastering to internal side of brick wall with 1:3 mix ratio sq.m 10.159 30 304.76988
6
12 mm Brick masonry Displacement Chamber 50cmX50 cm
internal size sq.m 2.7225 70 190.575
7 8 cm thick RCC cover for displacement chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
8 8 cm thick RCC cover to mixing chamber(65cmx65cm) sq.m 0.4225 64.00 27.04
9 150 mm PVC feeding Inlet pipe LM 2 100 200
10 15-20 mm GPS gas collection & distribution pipe LM 20 30 600
11 Improved stove pcs 4 30 120
Sub Total 3227.8393
10% contingency 322.78393
Total 3550.6233
Estimated cost of capital per house hold(Birr) 887.66
Page 137
Final Feasibility and Preliminary design report for Mekelle City Integrated Solid Waste Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
137
Page 138
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
138
Annex-H: Observations on collection at Land fill site
Day-I (October 27, 2005)
Observation time 3:20 AM local time:
Loader Plate No.00518
Location 22 is the site first serviced by the loader (PN 00518) in the next day 28th
Oct. and
considered as the last redeposition site on the first day (Oct.27); the loader did not transported
loaded container after 3:25 AM on the first day; It was observed to be off-route after it had
redeposited the WEWEKMA (Location 26) container to Adis Alem Bus Station (Location 22)
due to unknown reason;
PN 0075 Loader:
First reached disposal site 8:20 PM local time on Oct.27th
2005;
Returned to city at 11:05 PM to dispatch location;
(Edaga Finjal---D1------- Egrie Hawlti ---- D1------Edaga Bieray - D1---Alpha KG----DL)--
Dispatch location
DAY-2 Oct.28th
2005
PL 0075(Early time 1:30AM-Late time 11:12PM)
(DL--- Alpha KG-----D1-----Mesfin----D1------Dejen-----D1---Kebele 15-- D1----Hadush
Mender Kebele 05-----DL)
PL 00518(Early time 3:33AM-Late time 9:00PM)
(DL--- Addis Alem Bus Station----D1----- Gotera L8----D1------ Kebele 20 L13---DL)
DAY THREE: Oct.29th
2005
PL 0075(Early time 1:22AM-Late time 10:10PM)
(DL---Debre Damo L15--D1----Semein Health center L30----D1---Muslim Cemetery L4--D1--
-Enda Cherkos L33--- D1----Sewhi Negus L28---D1--- Edaga Finjal L2---- D1
---- Edaga Finjal---DL)
PL 00518 (Early time 1:50AM-Late time 5:27PM)
(DL---Kebele 20 L13--D1-------Adihawsi Endatsaba L18 or Adihawsi Taxi Terminal
L47---DL)
DAY FOUR: Oct.30th
2005
PL 0075(Early time 1:22AM-Late time 10:10PM)
(DL--- WEWEKMA L26---D1---- near EELPA L27--- D1----Ayder Livestock market L5- D1-
--- Mayduba L10---- D1------- WEWEKMA L26--- DL);
PL 00518 (Early time 1:05AM-Late time 3:32PM)
(DL--Gebriel church L24---D1--Business Taxi Terminal L17---D1--Business Taxi Terminal
L17---DL)
Page 139
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
139
DAY FIVE: Oct.31th
2005(21-02-98)
PL 0075(Early time 2:08AM-Late time 10:08PM)
(DL---Kebele 19---D1---- Edaga Bieray L19--- D1----Live stock market Kebele 17
D1---- Live stock market Kebele 17----DL)
PL 00518 (Early time 2:35AM-Late time 2:45PM)
(DL---Axum Hotel L21-- D1---- Edaga Adi Haki L41---- D1----- Edaga Adi Haki---DL)
DAY SIX: Nov 1 2005(21-02-98)
PL 0075(Early time 2:52AM-Late time 9:58PM)
(DL--- Enkodo L3--D1--- AdishumDuhun L34--- D1---- Agricultural office L9---D1---
WEWEKMA L26--DL)
PL 00518: No collection service provided on the fifth day; the loader was ideal or on
maintenance service;
DAY SEVEN: Nov 2 2005(21-02-98)
PL 0075(Early time 2:10AM-Late time 10:48PM)
(DL--- Alpha KG--D1--- Edaga Finjal --- D1---- Denbesco---D1---Ayder Low Cost Housing—
D1----Abreha Castel------ D1---- Abreha Castel---DL)
PL 00518: the loader was idle or on maintenance service;
Page 140
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
140
ANNEX-I: INSTITUTION AND LEGISLATION RELATED TO SOLID WASTE
MANAGEMENT
1. At Federal Level
The Institution and Legislation issues related to Environmental security and Solid Waste
Management in Ethiopia at the national level are citied below.
The Ethiopian constitution Article 44 says, ―all persons have the right to a clean and
healthy environment".
Currently, there is no federal legislation dealing comprehensively with all aspects of
solid waste management;
The National Health Policy has given priority to the development of environmental
heath, promotion of intersectoral collaboration in developing safe disposal of human,
household, agricultural and industrial wastes, encouragement of recycling, attention
for healthy environment and prevention of environmental pollution from hazardous
chemical wastes;
At federal level, the Public Health Proclamation No 200/2000 has provisions on waste
handling and disposal;
Environmental Protection Authority (EPA) also deals with solid waste issues for
sustainable use of natural resources in the country. It is mandated to develop
standards and norms for the protection of national environment;
National Environmental Policy gives due attention to sustainable development,
―polluter pays principle‖, recycling and other environmental issues like
Financing
Public awareness and participation
Institutional arrangement
Legal support
At federal level, Ministry of Health plays a leading and direct role in matters related to
Public Health and Sanitation for which solid waste management is part of public health
issues. The provisions stipulated in the federal proclamation No 200/2000 with regard to
solid waste management (SWM) enables the Ministry of Health to plan the way forward
for SWM to meet the challenges of the nation.
1.1 Environmental Protection Policies
Before specifically dealing with the policies and regulations related to waste it would be
better to indicate the highlights of the environmental policy of the country.
The overall goal of the Environmental Policy of Ethiopia is to improve and enhance the
health and quality of life of all Ethiopians and to promote sustainable social and economic
development through sound management and use of natural, human and cultural resources
and the environment as a whole so as to meet the needs of the present generation without
compromising the ability of future generations to meet their own needs.
Page 141
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
141
In the Ethiopian EPA Sectoral Environmental Policies, issues related to urban environment
and solid waste management practices are resolved under Article 3.4 (water
resources),Article 3.5(Energy Resource), Article 3.7 (Human Settlement, Urban Environment
and Environmental Health) , Article 3.8 (control of Hazardous Materials and Pollution From
Industrial Waste ,and Article 3.9( Atmospheric Pollution and Climate Change).
The policies that pertain both to solid and liquid waste are pinpointed here below under each
Sectoral policies.
Article 3.4 Water resources:
d. To promote the protection of the interface between water bodies and land (example lakes
shores, river banks, and wetlands)
Article 3.5 Energy Resource:
b. To promote the development of renewable energy sources and reduce the use of fossil
energy resources for ensuring sustainability and for protecting the environment, as well as for
their continuation into the future;
Article 3.7 Human Settlement, Urban Environment and Environmental Health:
b. To integrate harmoniously, human produced and natural elements in the development and
management of urban areas in order to maintain the natural ecosystems;
c. To ensure that improved environmental sanitation be placed highest on the federal and
regional agendas for achieving sustainable urban development;
e. To recognize the importance of and help bring about behavioral change through education
and public awareness of environmental sanitation problems in trying to achieve demand-
driven community led programs of improved urban environments as well as the sustainable
use and maintenance of sanitation facilities;
f. To bring about a sound partnership between the government and communities in the
development of an integrated sanitation delivery system, and to foster the supplementary role
of NGOs;
g. To ensure that housing and sanitation technologies and regulatory standards are set at a
level and cost that are within reach of the users and flexible enough to be adaptable to the
very varied socio-economic, epidemiological, climatic and physical site conditions, which are
found in urban areas;
h. To give priority to waste collection services and its safe disposal;
m. To undertake studies, which identify suitable sanitary land fill sites in the major cities and
towns of Ethiopia;
Page 142
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
142
p. To the extent possible to recycle liquid and solid wastes from homesteads and
establishments for the production of energy, fertilizer and for other uses;
Article 3.8 Control of Hazardous Materials and Pollution from Industrial Waste:
a. To adhere to the precautionary principle of minimizing and where possible preventing
discharges of substances ,biological materials or their fragments from industrial plants
and personal or communal appliances or any other external sources that could be
harmful, and to disallow the discharge when they are likely to be hazardous;
b. To adopt the ―polluter pays‖ principle while endorsing the precautionary principle
since pollution is likely to occur, and ensure that polluting enterprises and
municipalities and Wereda councils provide their own appropriate pollution control
facilities;
c. To establish clear linkage between the control of pollution and other policy areas
including water resources, agriculture, human settlements, health and disaster
prevention and preparedness;
d. To provide adequate regulation of agriculture (crop and livestock) chemicals and
micro-organisms;
e. To establish safe limits for the location of sanitary land fill sites in the
vicinity of wells, bore holes and dams, and issue regulations to enforce them;
g. To review and develop guidelines for waste disposal, public and industrial hygiene
and technologies to enable the cost effective implementation of defined standards of
control, and to issue regulations to enforce them;
h. To formulate and implement country wide strategy and guidelines on the management
of wastes from the medical, agriculture and other sectors that may use potentially
hazardous biological organisms, their fragments or chemicals, and to issue the
necessary regulations to enforce them;
i. To establish a system for monitoring compliance with land, air, and water pollution
control standards and regulations, the handling and storage of hazardous and
dangerous materials, mining operations, public and industrial hygiene, waste disposal,
and water quality;
j. To maintain an up-to-date register of toxic, hazardous and radioactive substances, and
to make the information available on request;
l. To enforce exhaustive labeling and detailing of the contents usage and expiry date of
foods, drugs, cosmetics, other chemicals, and when any of the contents are poisonous or
dangerous in any other way, the fixing of strikingly visible labels to that effect;
m. To promote waste minimization processes, including the efficient recycling
of materials wherever possible;
n. To create by law an effective system of control, distribution, utilization and disposal
after use of expiry of chemicals, biological organisms or fragments of organisms that
could be hazardous but are required for use;
p. To hold a legally liable an employer who deploys employees in using or handling
hazardous materials without adequately training them on how to deal with the hazard and
without adequate equipment to protect each one of them for physical harm or disease
starts in the place of work or away from it ;
q. To foster better understanding of the dangerous effects of chemicals and
Organisms and their fragments through the provision of information in a form
understandable to users, and provide or enforce the provision of information on appropriate
methods and technologies for the treatment and disposal of wastes;
Page 143
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
143
Article 3.9 Atmospheric Pollution and Climate Change:
d. To actively participate in protecting the ozone layer since, as the highlands of Ethiopia
already have a thin protective atmosphere and are liable to suffer Agricultural losses and
adverse health effects from exposure to ultraviolet rays;
The issues of control of air pollution in relation to modern waste transformation facilities like
incinerators and traditional methods like bonfire and uncontrolled burning of solid waste
materials are raised under Article 3.8. The traditional methods of waste combustion could not
be justified as good practices in any society, but this practice is common in the project city.
1.2 Urban Development policy
The urban development policy of Ethiopia also has given attention to the protection of urban
environmental. The policy focuses on the inevitability of the implementation of the national
and regional environmental protection policy, rules and regulations on urban centers. Some of
the issues that the policy discusses with regard to environmental protection are:
giving attention to environment at city plan preparation stage;
focus on reusing/recycling wastes and encouraging those engaged in such
activities;
build the capacity of institutions in all aspects that can protect/control pollutions
that arise from house hold and institutions;
Making efforts to change the attitude, culture and belief of citizens towards
preventing pollution and protecting the environment; ensuring sustainable and
coordinated community participation with this regard.;
In addition to the above policy, there are relevant proclamations and regulation both at
federal and regional level. Article 12 of proclamation 200/2000 of the public health
proclamation of the Federal state issued on waste handling and disposal declares the
following.
.
Any person shall collect waste in an especially designated place and in a manner
that does not affect the health of the society.
No person shall dispose solid, liquid or any other waste in a manner that
contaminates the environment or affects the health of the society.
Any solid, liquid and other wastes generated from hospitals should be handled
with special care and their disposal procedures should meet the standards set by
the public health authorities.
2. At Regional Level
The constitution of the Tigrai National Regional state article 44 declares that all citizens in
the region have the right to live in a clean and healthy environment. Based on the constitution
and Federals public health proclamation the Regional Government had also issued city
proclamation, hygiene and sanitation regulation. The city proclamation of TNRS declares that
providing or ensuring the provision of environmental services is one of the major functions of
cities.
Page 144
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
144
The Tigrai National Regional State had also issued hygiene and sanitation regulation number
4/1997. According to this regulation, the disposal of solid wastes along roads, avenues, rivers,
ponds, lakes and other unauthorized sites is prohibited. The proclamation also states that
neighborhoods within 20 meters of distance of unauthorized dumpsites are considered as
being disposed by the neighborhoods. This proclamation is also applicable to liquid wastes as
well.
With regard to the solid waste storage equipment, the Regional Hygiene and Sanitation
Regulation stated that the waste storage facilities must be waterproof, washable, and insect-
proof covered with a lid and it can be made up of sheet of iron or plastic.
When we come to the Institutions, at regional level, Bureau of Heath, Environmental
Protection and Land Administration Authority, and Bureau of Urban Development and
Construction are directly involved in solid waste management activities. Bureau of Health
plays a leading and direct role in matters related to public health and sanitation for which
solid waste management is part of public health issues; the recently established
Environmental Protection and Land Administration Authority has also a direct leading role in
matters related to environmental protection for which solid sedate management is part of
environmental issues. And the Bureau of urban Development and Construction is the third
regional body that is responsible to build the over all capacity of cities
Page 145
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
145
iii. ANNEX-J: SPECIFICATION FOR COMPOSTING
i.Particle size distribution
Particle size distribution of organic waste fraction of 25 to 75 mm ;Shred large size organic
waste materials removed at pre-sorting site to the size range from 25 to 75 mm and place the
shredded materials at pilling area; large size particles need to be shredded to desired size;
ii.Carbon-nitrogen (C/N) ratio
Initial values of C/N ratio between 25 and 50 are considered to achieve optimum composting.
Literature values of % N and C/N ratio are used to find out the weight fractions of materials
for blending and seeding.
See values of C/N ratio in table.
iii.Blending and seeding
Bending and seeding of the organic waste materials collected from 01MSW, O2MSW,&
03MSW with digested sludge, raw sludge ,cow dung, poultry manure, biogas slurry and
sawdust and water is considered and the optimum mix proportion of each fractions required
for optimum performance of windrow aerobic composting units are determined.
Weight of water, dry matter, nitrogen and carbon are computed for each 1 kg weight of
organic compost ingredients and 1 kg of seeding matter considered for blending. Then the
required amount of seeding matter is computed to achieve C/N ratio between 25 and 50.
A weighted average amount of 310.88 gram of digested sludge should be blended with 5000
gm of main compost ingredient indicated in the table excluding mixed paper.
The blended mix is composed of
1000 gm Grass >50mm or biomass(Bermuda grass)
1000 gm Grass <50mm or biomas(Bermuda grass)
1000 gm Food wastes
1000 gm Fruits & Vegetables
1000 Yard wastes
310.88 gm of Digested activated sludge
If significant sawdust reaches the MRF, it should be accounted as part of the main organic
ingredients in mix design.
The total weight of mixed MSW composed of grass, food wastes, fruits and vegetables and
yard wastes to be blended with 310.88 gm weighted average weight of digested sludge is 5.00
kg. The mix ratio between sludge to mixed MSW shall be 1 to 16.08, i.e. 1 part of digested
sludge and 16.08 part of mixed MSW by weight.
Page 146
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
146
Similarly, blending mix proportions of waste materials are computed for other seeding
materials such as raw sludge, manure, and urea.
iv.Moisture content
Initial optimum moisture content between 50 to 60% is considered and watering of pilled
mixed and shredded organic waste will be done to achieve desired moisture content (MC).
v.Mixing and turning
Labor intensive mixing and turning is considered to aerate premature compost. Air mainly
oxygen should reach all parts of the compost unit in the thermophilic phase.
vi.Optimum temperature
The optimum temperature for the thermophilic phase is 45 to 750C and optimum 55
0C and 20
to 400C for mesophilic phase with an optimum value of 35
0C.A thermophilic temperature
range from 50 to 550C is also acceptable. No turning and mixing will be done in the
mesophilic phase on regular basis. The thermophilic phase temperature is expected to kill all
pathogens in the compost. Control of pathogens affect use of compost products and
temperature ranges from 60 to 70 oc maintained for 24 hours kills the pathogens.
Degree of decomposition during operation of units may be check measuring temperature
Temperature below 15 o
c will cause psychrophilic conditions and is not desirable for good
performance of composting unit.
vii.PH value
PH value should remain 7 to 7.5.
viii.Composting reactor
The thermophilic reactors are batch flow reactors with periodic mixing and turning where as
the mesophilic reactors are plug flow reactors as there is no turning and mixing in the
maturation phase.
The selected composting units are open windrow as these units require least resources in
composting practices. The possible materials and geometry of the reactor are:
Rectangular steel tank
Rectangular wooden tank
Triangular steel tank
Triangular wooden tank
Triangular wire mesh tank
Rectangular wire mesh tank
Triangular reactors require more space in terms of plan area than rectangular reactors and the
rectangular ones are suitable in areas where there is space limitation. As there is space
limitation in urban areas, the use of rectangular reactors is highly commendable.
ix.Composting period (tc)
Thermophilic phase, ttc =25-27 days;
Page 147
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
147
Pilot plant study should be undertaken to determine the optimum composting periods at the
project site.
x.Volume and area of reactor
High rate windrow composting could be achieved in small size cross-section with height
from 1.80 to 2.2 m & 4.3 to 4.9m wide at the bottom; turning and mixing done twice in a
week or every 84 hours;
H= 2.00 m & W=4.60 m;
Daily Organic loads, Vd (cu.m/d) 126.98 206.03 248.66
Length and number of compost units:
Total length of reactor:
Lt= Vd*ttc/ (W*H) = Vd *27/ (2*4.6) =372.66 m (2005)
= 604.65 m (2010)
= 729.76 m (2015)
1714.24 m2
(2005) or 0.17 ha
= 2781.39 m2
(2010) or 0.28 ha
= 3356.90 m2
(2015) or 0.34 ha
Total area for composting (Phase-I)
At= Lt * W= Lt *4.6 = 1714.24 m2
(2005) or 0.17 ha
= 2781.39 m2
(2010) or 0.28 ha
= 3356.90 m2
(2015) or 0.34 ha
Length of each reactor is given by
L= Daily capacity/ (no.of units*W*H)
(b) Mesophilic composting unit
Activities:
maturing first phase compost
screening and
packing
xi.Composting period
Mesophilic phase=24 to 26 days;
xii.Screening
Screenings of matured compost should be returned to the shredding and pilling stages and re-
processed;
xiii.Optimum temperature
Page 148
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
148
Temperature range from 20 to 400C for mesophilic phase with an optimum value of 35
0C. No
turning and mixing will be done in the mesophilic phase on regular basis.
Degree of decomposition during operation of units may be check measuring temperature
Temperature below 15 o
c will cause psychrophilic conditions and is not desirable for good
performance of composting unit.
xiv.Volume and area of reactor
High rate windrow composting could be achieved in small size cross-section with height
from 1.80 to 2.2 m & 4.3 to 4.9m wide at the bottom; turning and mixing done twice in a
week or very 84 hours;
H= 2.00 m & W=4.60 m;
Daily Organic loads, Vd (cu.m/d) 126.98 206.03 248.66
Length and number of compost units:
Total length of reactor:
Lt= Vd*ttc/(W*H) = Vd *26/(2*4.6)= 358.86 m (2005)
= 582.26 m (2010)
= 702.73 m (2015)
Total area for composting (Phase-II)
At= Lt * W= Lt *4.6 = 1650.76 m2
(2005) or 0.17 ha
= 2678.40 m2
(2010) or 0.27 ha
= 3232.56 m2
(2015) or 0.32 ha
Total area of land required for phase-I and phase-II composting is
At= 3365m2
(2005) or 0.34ha
= 5459.79 m2
(2010) or 0.55ha
= 6589.46 m2
(2015) or 0.66 ha
Length of each reactor is given by
L= Daily capacity/ (no. of units*W*H)
xv.Total area requirement
Land requirement of unit with capacity of 50 ton/d is around 6070.5 to 8094 m2, which means
121.41 to 161.88 m2/ ton/day. The average total area requirement will be 142 m
2/ ton/day or
0.014 ha/ ton/day. The approximate total area for the composting suggested in literatures is
quit lower than the estimated requirements obtained for the design composting periods. This
type of arrangement is suitable for transferring thermophilic compost to Maturation units
provided for Mesophilic phase with manual labor.
Thermophilic units
Adjoining sides with clearance
for aeration and protect contamination of
matured compost
Page 149
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
149
Mesophilic units
Estimated Cost of capital (excluding land value):
The cost of material high-end MRF with feed stock derived from processing of commingled
wastes; with enclosed building with concrete floors, MRF equipments with unit operations
(shredding, screening and conveying system, and in-vessel composting; enclosed building for
curing of compost product =between 25,000 to 50,000 per ton per day. This is equipment and
capita intensive facility and 25 to 50 % cost reduction could be achieved in labor-intensive
windrow composting facility;
Daily Total loads (ton/d) 3.15 3.86 4.71
Estimated cost of MRF (2005-2010):
Capital-intensive MRF: 843375 to 1686750 Eth.Birr
Labor intensive MRF: 421688 to 843375 Eth.Birr
Total land for MRF:
A= 1.5* 0.34ha = 0.51 (2005)
=1.5*0.55ha= 0.825 (2010)
=1.5* 0.66 ha= 0.99 (2015)
Land area of 0.83 ha (2005-2010) & additional land of 0.17 (2010-2015)
Proper selection of equipments, consideration of environmental control and aesthetic aspects
are the additional factors considered in design of MRF.
Page 150
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
150
iv. ANNEX-K: DECENTRALIZED BIOGAS UNITS (DBU)
The generation of energy in the form of methane from house holds organic fraction of
garbage could be considered in low income groups of the city. The feed stock materials could
be mix of
Organic solid waste materials
Cows Manure
Poultry manure
Pit manure or Toilet manure or human waste
Basic toilet services required for the disposal of human feces on-site may not be provided in
the households as the human waste could be used in the production of biogas in the house
holds. The daily human wastes and urine can be fed to the biogas units in a controlled manner
directly from the Toilet superstructure. There is no need to erect the substructure or toilet pit
in case of individual household biogas units.
The contents of toilet pit, which is mainly digested sludge, could also be emptied and applied
to shared decentralized biogas units.
Design parameters:
Average per capita solid waste generations:
Years 2005 2010 2015
Average rate of generation(l/c/d) 0.92 1.18 1.21
Average rate of generation(kg/c/d) 0.27 0.34 0.35
Daily available quantity of organic solid
wastes (liter/d) 0.29 0.38 0.385
Daily per capita available quantity of
organic solid wastes (kg/d) 0.086 0.1081 0.1113
Available organic solid waste in single
family (kg/d) 0.421 0.5296 0.5452
Average daily solid waste feed:
The daily requirements are taken from literature written on biogas units running with cow
dung feed stock materials, which has an estimated organic content ranging fron 48 to 56% in
dry state. More quantities of solid wastes may be required than indicated in table below. The
Page 151
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
151
actual requirements of solid waste need to be determined from pilot plant studies before
implementation of projects in the city.
Gas yield for MSW Solids loading:
The estimated gas yield in low solids anaerobic digestion ranges from 0.25 to 0.45 m3 / kg of
biodegradable volatile solids (bVS) destroyed in anaerobic digestion. The production rate
ranges from 1.5 to 2.5 m3 per m
3 of reactor capacity.
Composition of gas:
The estimated proportion of methane ranges from 50 to 70 % of total gas production in case
of MSW and the rest 30 to 50% represent carbon dioxide gas. The estimated proportion of
methane in case of manure used as fed stock material ranges from 65 to 70% and carbon
dioxide from 30 to 35%.
Design considerations for Decentralized Biogas unit with MSW fed stock (2005)
Standard reactor size (cu.m) <1 1 2 3 4 6
Gas yield in low solids anaerobic
digestion (m3/kg bVS) <0.25 0.25 0.30
0.35
0.40
0.45
Gas yield (m3/ m
3 reactor size ) <1.70 1.70 1.90 2.10 2.30 2.50
Solids retention time(days) 20 20 20 20 20 20
Methane production for 60 %
composition (m3/ m
3 reactor size)
0.90
1.02
1.14
1.26
1.38
1.50
Daily per capita available
quantity of organic solid wastes
(kg/d) 0.086 0.086 0.086
0.086
0.086
0.086
Available organic solid waste in
single family (kg/d) 0.421 0.421 0.421
0.421
0.421
0.421
Available bVS in single family
Within 20 days(kg) 8.42 8.42 8.42
8.42
8.42
8.42
Total gas production for
20 d cycle(m3)
2.11
2.11
2.53
2.95
3.37
3.79
Required reactor volume per family
m3) 1.24 1.24 1.33
1.40
1.47
1.52
Number of HH to share standard
Size reactor 1 1 2
2
3
4
Cont‘d
Daily available organic solid (kg/d) 0.421 0.421
0.842
0.842
1.263
1.684
Daily methane
production(liter/family )
<63.15
63.15
75.78
88.41
101.04
113.67
Average daily water requirement
(liter/kg waste) 0.85 0.85 0.85
0.85
0.85
0.85
Gas holding capacity as % produced
(67% consumed) 33.00 33.00 33.00
33.00
33.00
33.00
Per capita methane generation
(liter/d) <12.89 12.89 15.47
18.04
20.62
23.19
Arch segments side ratio 5:1 5:1 5:1 5:1 5:1 5:1
Page 152
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
152
Capacity of unit:
The use of individual (private) units or shared units could be considered in low income
households. The individual house hold units will have a total capacity of 1 m3 or less. The
shared units may have varying size from 2 upto
6 m3 depending on the number of households sharing the bio gas unit and the availability of
space in the house holds. The optional sizes of the units are 0.25, 0.50, 0.75,1, 2,3,4,5, and 6
m3.
Type of unit:
A biogas unit with maximum possible surface area will be provided. To achieve this
requirement, segmental spherical units buried below ground surface will be considered.
Determination of process loading rates
The loading rates of organic fraction at the composting facility in year 2005 is 3.15 ton/d,
which is 81.60% of the full plant capacity expected in year 2010.The full capacity in 2010
will be 3.86 ton/d. Quantities of MSW and rganic fraction from 01MSW, 02MSW, &
03MSW sources is shown on table 4.1.
Table 4.1 Quantities of MSW from 01MSW, 02MSW, & 03MSW sources
Years 2005 2010 2020
Average weekly quantity (cu.m/wk) 1906.06 2491.16 3004.58
Average weekly quantity (kg/wk) 22020.03 27044.37 32987.35
Average Daily presorting loads (cu.m/d) 272.29 355.88 429.23
Average daily Presorting load of non-organic
wastes (cu.m/d)
145.3 1
149.85
180.57
Average Daily Organic loads (cu.m/d) 126.98 206.03 248.66
Average Total loads (ton/d) 3.15 3.86 4.71
Page 153
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
153
ANNEX-L: MANUALLY LOADED AND MECHANICALLY UNLOADED REAR
LOADING COMPACTORS WITH LOADING CAPACITY OF 15.30 CU.M
Table 3.7 Labor requirements for manual curbside collection using one-person crew;
Average number
of
Stationery containers
and/or boxes
Per pick up locations
Pickup time,
Collector –min/location
1 or 2
3 or more , or
Unlimited service
0.50 -0.60
0.92
The average distance to be covered for average speed =8.00km/h and pick up time o f 1.766
hours is
= 8.88 km/h * 1.766 h= 15.68 km
For V=8 km /h , Phcs =1.176 hours, round trip distance, X=15.68 km, n=1, tp=0.92 and
unlimited service from stationery containers and/or boxes per pick up locations, the number
of pick up locations per trip
NP= 1.176 * 60*2/ 0.92
= 153.39 pick up locations per trip
The number of pick up locations in service area with solid waste collection capacity of Vp
are given by
NP = (Vsw *r)/ Vp
Where, Vsw =volume of collection vehicle (tractor-trailer), cu.m/trip
Page 154
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
154
Vp =volume of solid waste collected per pick up locations, cu.m/location
r =compaction ratio, 2 to 2.5 for manual loading collection method;
The volume of solid waste that will be collected per pick up locations with a compactor
having a holding capacity of 15.30 cu.m is estimated to be
Vp = 15.30*2.25/ 153.39
= 224.43 liter/location
OR = 4 containers each with 60 liter holding capacity
per location
The desired number of locations per trip required to collect waste from 75% of the house
holds in 2205 is determined below. The average rate of waste generation in residential
sources in 2005 is 0.92 liter/c/d and the average numbers of households (NHH) served at a
location will be
NNH= 224.43 liter/location / (0.92 liter/c/d*4.9)
= 49.785 house hold units/ location
(Considering average household size of 4.9 in the city)
This means nearly 2.5 blocks in modern residential areas could be served at a location
provided that the house holds hold generated wastes within their own primes until transferred
to the compactor collection trips.
The total desired number of locations per trip to cover 75 % of the house holds in residential
areas in 2005, i.e 0.75* 44255.1=33191.325 HHs, will be
(NP) desired = 33191.325 house holds/ 49.785 house hold units/ location
= 666.69 locations
Nearly 667 permanent locations in residential land uses are required to collect waste from
75% of the household units with compactor service that will serve 2.5 modern blocks at a
time in 2005.The required number of trips in a working day to cover all residential
households in 2005 will be
= 666.69 locations /153.39 pick up locations per trip
= 4.35 trips per day
The estimated required working hours in a day with average total time of 2.49 h per
compactor trip, average speed of 8 km/h , average t1 value of 0.0694 h and t2 values of
0.194 h becomes
H= [(0.0694 + 0.194) + 4.35 * 2. 49)/ (1-0.15)
= (0.2634 + 10.832)/ 0.85
= 13.054 Hours
The number of compactors required in primary collection fro 75 % service coverage in
residential areas considering normal eight working hours in a day
Page 155
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
155
=13.054/8
= 1.63 compactors (virtually 2 compactors with 15.30 cu.m capacity)
Therefore, it is necessary to engage two manually loaded and mechanically unloaded rear
loading compactors with loading capacity of 15.30 cu.m .Alternatively; it is feasible to
provide the same type of compactor with loading capacity of 28.30 cu.m.
Breakthrough time:
The breakthrough time in years for leachate to penetrate a clay liner of a given thickness can
be estimated from
t= d2 α/ K (d+h)
Where, t= breakthrough time in years (5 years), yr
d=thickness of clay liner, mm
α=effective porosity of clay liner, %
K=Coefficient of permeability or hydraulic conductivity of liner, mm/yr
h=hydraulic head or driving force (maximum depth of leachate in the
pond i.e. 0.90 m), mm
The breakthrough thickness of linear materials can be calculated for minimum design life
time of the land filling sites, which is 5 years. The
coefficient of permeability K value vary from 10-6
to 10-8
cm/s or 3.15 x 102
to 3.15 x 100
mm/yr and the Average value of K for clay liners is 1.59 x102 mm/yr. The effective porosity
for clay materials range from 0.10 to 0.30 and average value is 0.20.
The estimated thickness of clay liner for evaporation pond as well as land filling sites is given
by
5 = d2 *0.20 / 1.59 x10
2 *(900+d)
795(900+d) = 0.20 d2 (=quadratic equation)
d2
-795 d – 3577500 =0; d= (-795+3865.49)/2
=1535.25 mm or 1.54 m clay liner
This thickness value will be determined for site specific soil and permeability values. Series
of ponds will be provided each serving five years time.
Page 156
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
156
Annex M: Summary of demand projection, component sizing, Operation and Maintenance
Analysis (for achieving 100% collection efficiency in 2020)
Page 157
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
157
Annex N: Summary of demand projection, component sizing, Operation and Maintenance
Analysis ( for achieving 100% collection efficiency in 2010)
Page 158
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
158
Annex N: Environmental Impact Assessment
Page 159
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
159
Page 160
Preliminary design report for Mekelle City Integrated Solid Waste
Management
PROMISE CONSULT: CONSULTING ARCHITECTS AND ENGINEERS
160
12. REFERENCE