Page 1
Facilities Project Management Monthly Report by Building
Monday, August 31, 2015 129Approved Project
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
1 Leavitt Lane Projects in Building 3
2319 1 Leavitt Lane ‐ Warehouse Office, warehouse, and breakroom…
3‐ IN CONSTRUCTION
FCRWOODCOCK, JONATHAN
8/27/15_ Major construction complete, with punchlist being defined. New scope being
scheduled with FCT.
Design Firm: Contractor: FCT Contractor Name:
2015‐2319
1542 1 Leavitt Lane ‐ HVAC Investigation and Evaluation
3‐ IN CONSTRUCTION
RRHENRY, PAUL A
Scheduling re‐cap Sept. 2015
Design Firm: Harriman Contractor: External Contractor Name: TBD
2013‐1542
2714 1 Leavitt Lane ‐ Fire Suppression
3‐ IN CONSTRUCTION
FCRHOUDE, DONALD A
Work is funded, FCT ordering material and setting up the work schedule.FCT and Simplex
presenting to SFMO today. 8‐25‐15
Design Firm: Contractor: FCT Contractor Name:
2015‐2700
10 West Edge Drive Projects in Building 2
2762 10 West Edge Drive ‐ Renovation to support new Fujifilm LED 1600 printer
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
Reviewing project cost with team 8‐21
Design Firm: Harriman Contractor: External Contractor Name: Milestone
2015‐2747
2605 10 West Edge Drive ‐ Rm 102 Est. to install dishwasher
2.5‐ IN PROCUREMENT
FCRWOODCOCK, JONATHAN
8/27/15_ FCT exchanging equipment to suit the original intent. Scheduling construction window
with contractors.
Design Firm: Contractor: FCT Contractor Name:
2015‐2605
121 Technology Drive Projects in Building 2
Monday, August 31, 2015 Page 1 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 2
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2518 Madbury Commons ‐ IOL
2.5‐ IN PROCUREMENT
FCRHECKLER, BARBARA K
Award issued 8/3/2015. Showroom visit planned fro 8/27/2015.
Design Firm: Manypenny Murphy Archite Contractor: External Contractor Name:
2015‐2518
2519 Madbury Commons ‐ UNH Innovation
2.5‐ IN PROCUREMENT
FCRHECKLER, BARBARA K
Award issued 8/3/2015. Showroom visit planned for 8/27/2015.
Design Firm: Manypenny Murphy Archite Contractor: Contractor Name:
2015‐2519
265 MAST ROAD ‐ MAIN HOUSE Projects in Building 1
2876 265/267 Mast Road ‐ Main House/Carriage House ‐ Demolition
1‐ ASSIGNED
FCRHENRY, PAUL A
Design Firm: Contractor: Contractor Name:
2016‐0078
5 Leavitt Lane Projects in Building 1
1387 5 Leavitt Lane ‐ Review of cooling system capacity
2‐ IN DESIGN
FCRCARTABONA, STEPHANI
8/27/15 Harriman is working on 50% design drawings for UNH review. Pending funding
approval this project would be ready for bid November / December 2015.
Design Firm: Harriman Associates Contractor: External Contractor Name: TBD
2013‐1387
6 Leavitt Lane Projects in Building 1
1567 6 Leavitt Lane ‐ Lock Shop and Facilities Office Renovation
3‐ IN CONSTRUCTION
FCRWOODCOCK, JONATHAN
8/27/2015_Punch list items, and controls being finalized for original scope. New scope being
estimated for funding procurement.
Design Firm: Loureiro Engineering Contractor: FCT Contractor Name:
2014‐1567
88 Commercial Street Projects in Building 1
Monday, August 31, 2015 Page 2 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 3
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2583 88 Commercial Street ‐ Installation of 5th Floor Science Labs
3‐ IN CONSTRUCTION
FCRWOODCOCK, JONATHAN
8/27/15_ Labs 95% looking to turn over occupancy by 8/28/15. Final punch and misc scope to be
finalized early September 2015.
Design Firm: Contractor: Contractor Name:
2015‐2583
Babcock Hall Projects in Building 1
2784 Babcock Hall ‐ Volleyball Post
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Scheduled for week of 9/1
Design Firm: Contractor: FCT Contractor Name:
2016‐0005
Barton Hall and Cole Hall Projects in Building 4
1132 Cole Hall ‐ HVAC HU‐3 EQ5389 Cat Walks and Accessibility Modifications
1.1‐ PLAN/EST
RRHOUDE, DONALD A
New, I will appropriate the aid of an engineer to provide a plan for this work.. Have to review
Cole side again. 8‐25‐15
Design Firm: Contractor: Contractor Name:
2011‐1132
2614 Barton Hall and Cole Hall ‐ Bottle Fill Stations
2.5‐ IN PROCUREMENT
FCRHEALEY, RANDY L
8/24/15 Scheduled to begin 9/2/15
Design Firm: Contractor: FCT Contractor Name:
2015‐2614
2611 Barton Hall and Cole Hall ‐ Digital /Sign installation
3‐ IN CONSTRUCTION
FCRHOUDE, DONALD A
Thompson school has sent notice they will proceed with the funding of the Cole Hall digital sign
only, at this time. . Per request of the customer, work has been delayed to after 7‐27‐15, There is
a problem with the bracket provided. A replacement is being approved.Installation is for Friday
8‐28‐15
Design Firm: Contractor: FCT Contractor Name:
2015‐2611
Monday, August 31, 2015 Page 3 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 4
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2740 Cole Hall ‐ Rms 141, 142 Carpeting & Electrical
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
Carpent installed, working on small punch list. 8‐20
Design Firm: Contractor: External Contractor Name: Sprague Flooring
2015‐2730
Chase Ocean Engineering Lab Projects in Building 1
2668 Chase Ocean Engineering Building ‐ Sound Reduction HVAC‐1 and HVAC‐2
2‐ IN DESIGN
FCRCARDOSO, ANDRE W
Construction to take place in early fall 2015 and be completed by October 15, 2015.
Design Firm: Harriman Associates Contractor: TBD Contractor Name: TBD
2015‐2668
Childhood Study & Development Center Projects in Building 1
1428 Childhood Study & Development Center ‐ Playground Rubber Surface Repairs
2.5‐ IN PROCUREMENT
FCRJONES, KATHLEEN M
8/27/15: FCT to install sand slurry below rubber surface during the week of 8/31/15.
Design Firm: Contractor: FCT Contractor Name:
2013‐1428
Combined Heat and Power Plant Projects in Building 1
2582 Combined Heat and Power Plant ‐ Boiler # 4 Replacement
3‐ IN CONSTRUCTION
SIHOUDE, DONALD A
Boiler demolition is 100% complete. Ext, AST removal is complete. Floor prep is complete.
Staging for roof removal in place. #2 Oil piping to begin. New control work for Boiler 1,2,3 to
start this week. . 8‐25‐15
Design Firm: Contractor: Contractor Name:
2014‐2582
Computing Analytics ‐ CHHS Projects in Building 1
2624 10 Pettee Brook Lane ‐ Fit Out Lease Space
2.5‐ IN PROCUREMENT
FCRCARDOSO, ANDRE W
As of August 25, awating pricing from contractor working for landlord. Space to be ready for
occupancy in late October 2015.
Design Firm: Cowan‐Goudreau Contractor: External Contractor Name: Landlord
2015‐2624
Conant Hall Projects in Building 1
Monday, August 31, 2015 Page 4 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 5
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2551 Conant Hall ‐ Rm 204 Installation of Fume Hood Rm 204
3‐ IN CONSTRUCTION
FCRWOODCOCK, JONATHAN
8/27/2015_ Scope is under construction, with HVAC being scheduled once equipment lead times
are defined.
Design Firm: Harriman Contractor: FCT Contractor Name:
2015‐2551
Dairy Teaching and Research Complex Projects in Building 1
2766 Dairy Teaching and Research Complex ‐ Paving
2.5‐ IN PROCUREMENT
FCRJONES, KATHLEEN M
8/27/15: Bell & Flynn is scheduled to begin preparing site for paving September 8, applying
binder course by September 18, T&S will apply loam and seed on edges by September 22, and
final top coat paving will occur by September 23. Invoices to be received from both companies
no later than September 25 to meet funding requirements.
Design Firm: Contractor: External Contractor Name: Bell & Flynn; T&S Construction
2015‐2751
Demeritt Hall Projects in Building 2
1995 Demeritt Hall ‐ Rm 217 Safety Improvements
2.5‐ IN PROCUREMENT
FCRWOODCOCK, JONATHAN
8/27/2015_FCT hired,and defining schedule with subcontractor.
Design Firm: Harriman Associates Contractor: FCT Contractor Name: TBD
2014‐1995
2723 Demeritt Hall ‐ AV Work 251 & 253 etc.
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Majority of work completed, waiting on AV team to remove touch panels to complete
our portion. Work is expected to be done over winter break
Design Firm: Contractor: FCT Contractor Name:
2015‐2711
Dimond Library Projects in Building 8
806 TEAL Classroom
1.1‐ PLAN/EST
SIHENRY, PAUL A
Submitted new budget to the Provost office, waiting for feed back. Still in holding 1‐7‐15
Design Firm: Contractor: Contractor Name:
2012‐0806
Monday, August 31, 2015 Page 5 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 6
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2215 Dimond Library ‐ Ground Lvl compact shelving capacity study
1.1‐ PLAN/EST
FCRWOODCOCK, JONATHAN
8/27/2015_ Scope defined and engineers proposal in for procurement.
Design Firm: Loureiro Engineering Contractor: External Contractor Name: TBD
2015‐2215
624 Dimond Library ‐ Space Repurposing ‐ Phase 2
2‐ IN DESIGN
SIHECKLER, BARBARA K
3/26/15: Per T. Lauder, internal Dimond group working on defining and/or redefining space
uasge and needs. Outcome of those discussions will determine direction project will take.
8/20/2015: Status unchanged.
Design Firm: Contractor: Contractor Name:
2010‐0624
1833 Dimond Library ‐ Level III hall add lighting
2.5‐ IN PROCUREMENT
FCRHOUDE, DONALD A
Client has a quote and FCR, we are waiting on funding. . 8‐25‐15
Design Firm: Contractor: FCT Contractor Name:
2014‐1833
1359 Dimond Library ‐ Rm 301 Redesign and Relocation
2.5‐ IN PROCUREMENT
FCRHECKLER, BARBARA K
Scope increased to include minimal carpet repair. Samples ordered 8/19 and receipt expected on
or before 8/25/2015. Additional scope will be covered by contingency.
Design Firm: Contractor: FCT Contractor Name:
2013‐1359
2612 Dimond Library ‐ Digital Sign Upgrade
3‐ IN CONSTRUCTION
FCRHOUDE, DONALD A
This work is funded the equipment is in. FCT should be complete on this work this week. 8‐25‐15
Design Firm: Contractor: FCT Contractor Name:
2015‐2612
2064 Dimond Library ‐ AHU 1E Replacement
3‐ IN CONSTRUCTION
RRCARDOSO, ANDRE W
The new air handler arrived on August 18. As of August 25, completion is on schedule for
September 18.
Design Firm: Oak Point Contractor: FCT Contractor Name: Palmer and Sicard
2014‐2064
Monday, August 31, 2015 Page 6 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 7
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2325 Dimond Library ‐ Stack Lighting Modifications
3.5‐ WARRANTY REPAIRS
RRCARTABONA, STEPHANI
8/27/15 This work is complete, pending a warranty repair of an existing wattstopper controller
for floor 4 stack lighting.
Design Firm: Rist Frost Shumway Contractor: External Contractor Name: Yates Electric
2015‐2325
Elizabeth Demeritt Projects in Building 1
2832 Elizabeth Demeritt ‐ Workspace Layout
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Estimate accepted, working with the customer to schedule after school starts.
Design Firm: Contractor: FCT Contractor Name:
2016‐0042
Field House Projects in Building 8
2469 Field House ‐ Rm 18 Space Reconfiguration/Remodelling
2‐ IN DESIGN
FCRJONES, KATHLEEN M
8/2715: Architect has submitted 4 conceptual designs for the space reconfiguration. PM has sent
conceptual designs to Athletics for review and comment and direction on next steps from
Athletics.
Design Firm: Harriman Contractor: Contractor Name:
2015‐2469
986 Field House ‐ HV Replacements Phase IV of VII ‐ Modifications to HV13
2‐ IN DESIGN
RRCARTABONA, STEPHANI
8/27/15 Harriman has provided plans for this project. Working with athletics to determine
schedule for installation. Anticipate spring construction for this project. Will issue to
purchasing for bid October 2015.
Design Firm: Harriman Assoc. Contractor: External Contractor Name: TBD
2012‐0986
2011 Field House ‐ Room Renumbering
2.5‐ IN PROCUREMENT
FCRHECKLER, BARBARA K
Installation by Portsmouth Sign anticipated fro week of 8/24/2015.
Design Firm: Contractor: External Contractor Name: Portsmouth Sign Co.
2014‐2011
Monday, August 31, 2015 Page 7 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 8
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2596 Field House ‐ Heating Coil Replacements HV 25
3‐ IN CONSTRUCTION
RR
Emergency Repair
CARTABONA, STEPHANI
8/27/15 Granite State Plumbing Heating will schedule installation of this unit to occur during
September 2015
Design Firm: Contractor: External Contractor Name: Granite State Plumbing Heating
2015‐2596
177 Field House ‐ Asphalt parking lot Reconstruction ‐ Design and Improvements
3‐ IN CONSTRUCTION
SIHENRY, PAUL A
Project Potentially back on schedule if the weather corporates.
1‐Base Paving 8‐7
2‐Curbing Starting 8‐11
3‐Final paving 8‐27
4‐Striping 8‐28
Design Firm: Tighe & Bond Contractor: External Contractor Name: Earth Construction
2009‐0177
2342 Field House ‐ Sprinkler Installation ‐ Phase IV
3‐ IN CONSTRUCTION
RRCARTABONA, STEPHANI
Will report with 1159
Design Firm: SFC Engineering Contractor: External Contractor Name: TBD
2015‐2342
1159 Field House ‐ Sprinkler Installation ‐ PHASE III
3‐ IN CONSTRUCTION
RRCARTABONA, STEPHANI
8/27/15 Awaiting submittal review comments from SFC Engineering to evaluate FM Global
comments. Fire pump has been released, anticipate construction to begin October 2015.
Design Firm: SFC Engineering Contractor: External Contractor Name: Careno Construction
2013‐1159
672 Driveway Repair ‐ Emergency Access‐ Field House
3‐ IN CONSTRUCTION
RRHENRY, PAUL A
Project Potentially back on schedule if the weather corporates.
1‐Base Paving 8‐7
2‐Curbing Starting 8‐11
3‐Final paving 8‐27
4‐Striping 8‐30
Design Firm: Tighe& Bond Contractor: External Contractor Name: TBD
2011‐0672
Gregg Hall Projects in Building 1
Monday, August 31, 2015 Page 8 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 9
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2831 Gregg Hall ‐ HVAC Engineering Evaluation
1.1‐ PLAN/EST
RRCARTABONA, STEPHANI
8/27/15 No actiivty at this time.
Design Firm: Contractor: Contractor Name:
2016‐0041
Hamilton Smith Hall Projects in Building 1
2785 Hamilton Smith Hall ‐ Major Renovation Project
3‐ IN CONSTRUCTION
SIROULEAU, RICHARD A
7/27/2015 Update: Abatement and demolition of the rear of the building continues and is
expected to be completed prior to freshmen move‐in on August 28. Bid documents for early
release site/foundations/structural steel package were issued on 7/26 and the associated work is
to occur during the fall semester. Bid documents for the balance of the project are expected in
late‐August. The ESL program moved into swing space on 7/20. The final move into swing
space this summer will be the English Department office on August 17. The balance of Hamilton
Smith will be vacated the first week of January 2016, and the contractor will then fully mobilize.
Construction is expected to be complete such that we can re‐occupy the building in time for fall
2017 classes.
Design Firm: DiMella Shaffer Associates Contractor: FCT Contractor Name: Skanska USA, Inc.
2012‐1851
Health Services Projects in Building 1
2647 Health Services ‐ Retro Commissioning
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
Waiting for final report 8‐20
Design Firm: Contractor: Contractor Name:
2015‐2647
Hewitt Annex Projects in Building 1
2775 Hewitt Annex ‐ Site Restoration and Utility Isolation
3‐ IN CONSTRUCTION
RRCARTABONA, STEPHANI
8/27/15 Working with MannyPennyMurphy for site restoration and entrance to Hewitt basement.
Design Firm: MannyPennyMurphy Contractor: External Contractor Name: TBD
2016‐0003
Hewitt Hall Projects in Building 4
Monday, August 31, 2015 Page 9 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 10
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
1964 Hewitt Hall ‐ Carpet Investigation and Reinstallation
1.1‐ PLAN/EST
RRWOODCOCK, JONATHAN
8/27/15_Estimating costs asoociated with broadloom or carpet square installation.
Design Firm: Contractor: External Contractor Name: TBD
2014‐1964
2735 Hewitt Hall ‐ Rms 125, 115, 111 Painting
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/20/15 Shelves installed, remaining items scheduled to be complete 9/1/15
Design Firm: Contractor: FCT Contractor Name:
2015‐2722
2636 Hewitt Hall ‐ Rm 307 Wall Repairs/Painting
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Original order complete. CO work today and 8/28. AdTech installing today
Design Firm: Contractor: FCT Contractor Name:
2015‐2636
2057 Hewitt Hall ‐ Rms 139, 141 Space Renovation
3‐ IN CONSTRUCTION
FCRWOODCOCK, JONATHAN
8/27/2015_Renovation complete…AV/Tech being installed and programmed.
Design Firm: TBD Contractor: FCT Contractor Name:
2014‐2057
Holloway Commons Projects in Building 2
2397 Holloway Commons ‐ Upgrade Digital Voice Evacuation System
3‐ IN CONSTRUCTION
FCRCARTABONA, STEPHANI
8/27/15 Norris has recommended smoke detectors throughout the building be replaced as they
currently perform weekly inspection of the smoke detector. This proposal will be submitted to
OBA for review and approval.
Design Firm: Contractor: External Contractor Name: Norris Inc.
2015‐2397
Monday, August 31, 2015 Page 10 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 11
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
1657 Holloway Commons ‐ Expansion Project
3‐ IN CONSTRUCTION
CPROULEAU, RICHARD A
8/31/2015 Update: Phase 1 is substantially complete. Holloway Commons is open for business
and the changes implemented have been well‐received. Next to be turned over is the condiment
station south of the new Grill Station, which should be available by 9/11. Work continues on the
additions. The balance of the entry addition including the new public stair and elevator is
expected to be turned over in late‐September. Construction on the dining room addition is to
continue through early‐February 2016.
Design Firm: Miller Dyer Spears Contractor: FCT Contractor Name: North Branch Construction
2014‐1657
Horton Hall Projects in Building 2
2828 Horton Social Science Center ‐ Rm 315 Move Bulletin & White Board
1.1‐ PLAN/EST
FCRHEALEY, RANDY L
8/27/15 Estimate accepted.Working with the customer to schedule after school starts.
Design Firm: Contractor: FCT Contractor Name:
2016‐0038
2865 Horton Social Science Center ‐ A/C Installation 4th floor
3‐ IN CONSTRUCTION
FCRHealey
8/27/15 Project is 75% Complete. Expected to be complete 9/4.
Design Firm: Contractor: Contractor Name:
2016‐0068
Horton Social Science Center Projects in Building 2
2552 Horton Social Science Center ‐ Renovation of 1st Floor
2‐ IN DESIGN
FCRHENRY, PAUL A
Design Funded, first meeting 8‐11, will present egress optons to SFMO at Sept. meeting.8‐20
Design Firm: Harriman Contractor: External Contractor Name: TBD
2015‐2552
2475 Horton Social Science Center ‐ Renovation of 4th floor
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
Project Substantially complete, furniture being installed. SFMO CO walk through 8‐25
Design Firm: Harriman Contractor: External Contractor Name: TBD
2015‐2475
Huddleston Hall Projects in Building 2
Monday, August 31, 2015 Page 11 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 12
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2808 Huddleston Hall ‐ 211 Door & Painting
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/20/15 Lock on order. Expected to arrive Aug 31
Design Firm: Contractor: FCT Contractor Name:
2016‐0019
2585 Huddleston Hall ‐ Mechanical Room Repairs
3‐ IN CONSTRUCTION
RRHENRY, PAUL A
Area way completed, working on MEP 8‐20
Design Firm: Contractor: External Contractor Name: TBD
2015‐2585
Jackson Lab Projects in Building 1
2621 Jackson Lab ‐ Greenhouse Repair and Restoration
2‐ IN DESIGN
RR
Emergency Repair
WOODCOCK, JONATHAN
8/27/2015 Issued PO to engineer for design review.
Design Firm: Contractor: External Contractor Name: Orlando Greenhouse Sales Inc
2015‐2621
Kendall Hall Projects in Building 3
2360 Kendall Hall ‐ Abatement and Planning
1.1‐ PLAN/EST
RRCARDOSO, ANDRE W
Next round of abatement on the third floor, basement level and in the stairwells is scheduled to
begin on September 8.
Design Firm: TBD Contractor: FCT Contractor Name: Dec‐Tam
2015‐2360
2322 Kendall Hall ‐ Swing Space Renovations
2.5‐ IN PROCUREMENT
FCRCARDOSO, ANDRE W
Construction is scheduled to begin to September 8 and be complete by December 1, 2015.
Design Firm: Many‐Penny Murphy Contractor: External Contractor Name: Bauen Corp.
2015‐2322
55 Kendall Hall ‐ Fire Alarm and Emergency Lighting Replacement
3‐ IN CONSTRUCTION
RRCARTABONA, STEPHANI
8/27/15 Emergency battery back up lighting installed by FCT. Scarponi Electric to begin fire
alarm installation for completion prior to December 2015.
Design Firm: SFC Engineering Contractor: FCT Contractor Name: Scarponi Electric
2009‐0055
Monday, August 31, 2015 Page 12 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 13
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Kingsbury Hall Projects in Building 3
2263 Kingsbury Hall ‐ Roof Safety Restraint System Phase II of II
2‐ IN DESIGN
RRWOODCOCK, JONATHAN
8/27/2015 Out for design with ARM & Safe Approach.
Design Firm: ARM Contractor: External Contractor Name: TBD
2015‐2263
2849 Kingsbury Hall ‐ TV Installation 2nd Floor Lobby
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Scheduled to begin and be completed the same day, Monday 8/31/15.
Design Firm: Contractor: FCT Contractor Name:
2016‐0059
1933 Kingsbury Hall ‐ Area of Refuge Project
3‐ IN CONSTRUCTION
FCRWOODCOCK, JONATHAN
8/27/15_ Door modifications complete. Remaining scope is isolated to signage & phones…
Scheduling scope around building programming.
Design Firm: HL Turner Contractor: FCT Contractor Name:
2014‐1933
MacFarlane Greenhouse Projects in Building 1
2538 MacFarlane Greenhouse ‐ Fume Hood Alarm Upgrades
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
Project funded waiting for FCT 8‐20
Design Firm: Contractor: FCT Contractor Name:
2015‐2538
McConnell Hall Projects in Building 1
2810 McConnell Hall ‐ Rm 202 Additional Power Strips
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27//15 Approved 8/12, Scheduling week of 8/31
Design Firm: Contractor: FCT Contractor Name:
2016‐0021
Memorial Union Building Projects in Building 6
Monday, August 31, 2015 Page 13 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 14
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2748 Moving CO2 tank from PPC to MUB
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
Scheduled for 8‐20
Design Firm: Contractor: FCT Contractor Name:
2015‐2733
2607 Memorial Union Building ‐ Rm 18 est to replace lighting fixtures
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Additional electrical requested. Expected completion this week
Design Firm: Contractor: FCT Contractor Name:
2015‐2607
2299 Memorial Union Building ‐ New Deck Railings (rev 3)
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
Stairs under construction 8‐20
Design Firm: Contractor: External Contractor Name: Milestone
2015‐2299
1475 Memorial Union Building ‐ Lactation Room Floor 3
3‐ IN CONSTRUCTION
FCRCARTABONA, STEPHANI
8/27/15 Signage ordered from Portsmouth Sign. Work order issued to FCT for automatic door
opener.
Design Firm: Mannypenny Murphy Contractor: FCT Contractor Name: Milestone
2013‐1475
2606 Memorial Union Building ‐ Refinish 45 Doors
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Approved. Reviewing list of doors and scheduling with customer
Design Firm: Contractor: FCT Contractor Name:
2015‐2606
2816 Memorial Union Building ‐ Rms 221G, 223B Electrical Work
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Scheduled to begin 8/31
Design Firm: Contractor: FCT Contractor Name:
2016‐0026
Mills Hall Projects in Building 1
Monday, August 31, 2015 Page 14 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 15
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2225 Mills Hall ‐ Chiller Plant Retrocommissioning
1.1‐ PLAN/EST
FCRROULEAU, RICHARD A
8/31/2015 Update: Retrocommissioning is complete. With the students back, Holloway in full‐
swing and hot weather expected, final verification should occur the first week of September.
Related Projects: Portal ID#s 1443 and 1657
Design Firm: RFS Commissioning Contractor: External Contractor Name: Rist‐Frost‐Shumway Engineering (commissioning)
2015‐2225
Morrill Hall Projects in Building 2
2864 Morrill Hall ‐ Rm 4 Renovations
1.1‐ PLAN/EST
FCRHENRY, PAUL A
Sent FCR to Stakeholders. 8‐13
Design Firm: Contractor: Contractor Name:
2016‐0067
2609 Morrill Hall ‐ 1st Floor Window Replacement‐ Ice Damage
1.1‐ PLAN/EST
RR
Emergency Repair
WOODCOCK, JONATHAN
8/27/2015_Currently estimating repairs, building secure.
Design Firm: Contractor: Contractor Name:
2015‐2609
Morse Hall Projects in Building 1
2384 Morse Hall ‐ Rm 345 Renovations
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
Project under construction, expected completion Mid Sept. 8‐20
Design Firm: Harriman Contractor: External Contractor Name: TBD
2015‐2384
Nesmith Hall Projects in Building 2
1972 Nesmith Hall ‐ Exterior Brick Wall and Parapet Repointing
2.5‐ IN PROCUREMENT
RRWOODCOCK, JONATHAN
8/27/2015_ Scheduling work with vendor during off hours.
Design Firm: TBD Contractor: External Contractor Name: TBD
2014‐1972
Monday, August 31, 2015 Page 15 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 16
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
1716 Nesmith Hall ‐ Repair and Renovate 8 Classrooms
3‐ IN CONSTRUCTION
RRWOODCOCK, JONATHAN
8/27/2015_ Under construction through FCT. Expected completion by 8/31/15
Design Firm: Contractor: FCT Contractor Name:
2013‐1716
New England Center Projects in Building 2
1683 New England Center ‐ Relocation of Photo Video Department
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
Move is complete, waiting for some furniture items due in August, working on punch list 8‐20
Design Firm: Harriman / Many Penny Contractor: External Contractor Name: Milestone
2014‐1683
2827 New England Center ‐ Picnic Tables
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
Ordered picnic tables on 7/27/15. Expected arrival 9/25/15
Design Firm: Contractor: FCT Contractor Name:
2016‐0037
New Hampshire Hall Projects in Building 1
940 New Hampshire Hall ‐ Major Roof Replacement
2‐ IN DESIGN
RRWOODCOCK, JONATHAN
8/27/2015_ Project to be re‐bid in late fall for a May 2016 start.
Design Firm: TBD Contractor: External Contractor Name: TBD
2013‐0940
Outdoor Pool Projects in Building 1
2059 Outdoor Pool ‐ Reconstruction of Outdoor Pool Facility
3‐ IN CONSTRUCTION
CPHAGSTROM, DONALD P
Working through some DES issues. Construction scheduled for 8/2015
Design Firm: water technologies Contractor: External Contractor Name: Shawmut
2014‐2059
Parking and Transit Center Projects in Building 3
Monday, August 31, 2015 Page 16 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 17
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2718 Parking and Transit Center ‐ Mast Road Gate Replacement
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Our work complete, gate activation due Friday 8/28
Design Firm: Contractor: FCT Contractor Name:
2015‐2705
2379 Parking and Transit Center ‐ Install & Activate CNG Refueling Equipment
3‐ IN CONSTRUCTION
FCRHOUDE, DONALD A
Project plan has been presented to the SFMO. Work will progress with the understanding
engineering to back up any progress will be provided before final inspections.Work is
progressing, we are working on a punch list. 8‐25‐15
Design Firm: Contractor: FCT Contractor Name: Badger Rand / Yates & others
2015‐2379
2396 Parking and Transit Center ‐ Fire Alarm System/Replacement
3‐ IN CONSTRUCTION
FCRCARTABONA, STEPHANI
8/27/15 Norris Inc is preparing submittals and coordination drawings. Anticipated installation
to occur during Holiday break 2015‐2016 due to building occupancy.
Design Firm: SFC Engineering Contractor: External Contractor Name: Norris Inc.
2015‐2396
Parsons Hall Projects in Building 5
2845 Parsons Hall ‐ Rm S106 Laboratory Air Dryer Installation
1.1‐ PLAN/EST
RR
Emergency Repair
CARDOSO, ANDRE W
Work to be performed in September, 2015.
Design Firm: TBD Contractor: Contractor Name: TBD
2016‐0055
2626 Parsons Hall ‐ Processed Chiller Modifications
2‐ IN DESIGN
RR
Emergency Repair
CARTABONA, STEPHANI
8/27/15 EYP provided location of pressure sensors, awaiting confirmation from zone 3 if these
have been verified and adjusted.
Design Firm: EYP Contractor: External Contractor Name: TBD
2015‐2626
1704 Parsons Hall ‐ Mechanical Penthouse Waterproofing DESIGN ONLY
2‐ IN DESIGN
RRWOODCOCK, JONATHAN
8/27/2015_ Schematics in for review and estimating.
Design Firm: EYP/ARM Contractor: TBD Contractor Name:
2014‐1704
Monday, August 31, 2015 Page 17 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 18
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
1030 Parsons Hall ‐ Hallway Ductwork Insulation / Ceiling Repairs
2.5‐ IN PROCUREMENT
RRJONES, KATHLEEN M
8/27/15: Adjustments have been made to temperature controls with input from energy office and
mechanical enigneer. We will continue to monitor the ductwork. FCT to seal doorways in
September to prepare for next summer.
Design Firm: Contractor: FCT Contractor Name:
2014‐1030
2751 Parsons Hall ‐ Rm S234 Installation of Drying Racks
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 One Installed, counter modification required for the 2nd one.
Design Firm: Contractor: FCT Contractor Name:
2015‐2736
Paul Creative Arts Center Projects in Building 3
46 Paul Creative Arts Center ‐ Sprinkler Installation and Egress Modifications DESIGN
2.5‐ IN PROCUREMENT
RRCARTABONA, STEPHANI
8/27/15 Awaiting confirmation from Port City Architecture, if less 20% wall coverage installed
tack board solution may be modified.
Design Firm: Port City Architecture/ SFC E Contractor: FCT Contractor Name:
2009‐0046
1157 Paul Creative Arts Center ‐ Egress Modifications Phase 1 of 2
2.5‐ IN PROCUREMENT
RRCARTABONA, STEPHANI
Please refer to ID 46 for ongoing updates ‐ All work will be reported and tracked ID 46.
Design Firm: Port City Architecture / SFC Contractor: FCT Contractor Name: TBD
2013‐1157
2866 Paul Creative Arts Center ‐ Water Line Replacement
2.5‐ IN PROCUREMENT
RR
Emergency Repair
JONES, KATHLEEN M
8/27/15: Small repair was made on August 19, and date of final repair is TBD. This work will be
scheduled for a Saturday in September, exact date TBD.
Design Firm: Contractor: External Contractor Name: RH White
2016‐0069
Pettee Hall Projects in Building 1
Monday, August 31, 2015 Page 18 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 19
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2631 Pettee Hall ‐ Restoration and Recommissioning HV‐1 and HV‐2
3‐ IN CONSTRUCTION
RR
Emergency Repair
CARTABONA, STEPHANI
8/27/15 Determined building dual temp system needs to be fully flushed, valves inspected.
Potentially winter 2015 make ready for summer 2016 building flush. emergency lighting
inverter failed due to moisture in mechanical room, this work will be added to the scope.
Emergency batter back up units in place for emergency lighting. FCT has cleaned and painted
mechanical room. Work near complete on mechanical room.
Design Firm: RFS Contractor: FCT Contractor Name: TBD
2015‐2631
Philbrook Hall Projects in Building 1
2492 Philbrook Hall ‐ Refrigeration Rack System
2.5‐ IN PROCUREMENT
FCRCARTABONA, STEPHANI
8/27/15 FCR submitted to OBA/Dining for funding, awaiting authorization to proceed.
Design Firm: Harriman Assoc. Contractor: External Contractor Name: TBD
2015‐2492
Presidentʹs House Projects in Building 1
2650 Presidents House ‐ Porch Enclosure and ADA Modifications
3‐ IN CONSTRUCTION
RRGEUTHER, MARK E
8‐20: Porch stairs in place, new door installed, flooring complete, ready for paint and millwork.
Completion scheduled for 8/25.
Design Firm: ManyPenny‐ Murphy Archit Contractor: External Contractor Name: Milestone Construction
2015‐2650
Ritzman Lab Projects in Building 1
1794 Ritzman Lab ‐ Conference Room Technology
3‐ IN CONSTRUCTION
FCRCARTABONA, STEPHANI
8/27/15 Furniture to be delivered September 2015, AV technology to be installed September
2015. Floor 1 and floor 2 conference room to have upgrade.
Design Firm: Contractor: FCT Contractor Name: Adtech / Creative Office Pavillion
2014‐1794
Roads/Grounds Projects in Building 6
184 Signs ‐ Campus wayfinding and University building sign improvements
1.1‐ PLAN/EST
SIBENCKS, DOUGLAS C
Design Firm: Contractor: Contractor Name:
2008‐0184
Monday, August 31, 2015 Page 19 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 20
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
295 Campus ‐ Bike Rack Installations
1.1‐ PLAN/EST
SIPESCI, STEPHEN T
Design Firm: Contractor: Contractor Name:
2010‐0295
1142 Memorial Union Building ‐ Ravine Walkway Replacement ‐ DESIGN ONLY
2‐ IN DESIGN
RRHENRY, PAUL A
Heating Line SOW added to project, and now requires changes in building, Harriman added to
design team, Design will resume this summer , construction Summer 2016. Design back on track
7‐28
Design Firm: Tigh & Bond Contractor: External Contractor Name: TBD
2013‐1142
2767 Ravine Culvert Replacement
2‐ IN DESIGN
RR
Emergency Repair
JONES, KATHLEEN M
8/27/15: Design of culvert repair to be completed and engineer to meet with Durham
Conservation Commission on September 10, then submit application for NHDES wetlands
permit by September 18, then we will wait to receive the necessary permits to continue with
construction of repair. Culvert has a temporary steel plate over it for pedestrian access.
Design Firm: Hoyle Tanner Contractor: External Contractor Name: T&S Construction
2016‐0002
1115 South Drive ‐ Design Advancement
2‐ IN DESIGN
SIHENRY, PAUL A
Permits approved, this phase of the design complete. CP looking for funding options, nothing
scheduled for 2014.
Design Firm: Tigh & Bond Contractor: External Contractor Name:
2013‐1115
75 University Campus Exterior Lighting Improvements
3‐ IN CONSTRUCTION
SIHOUDE, DONALD A
All the exterior lighting has been installed. It needs to be reviewed. , There is a small punch list.
8‐25‐15
Design Firm: Contractor: Contractor Name:
2008‐0075
Rollins Water Treatment Bldg Projects in Building 1
Monday, August 31, 2015 Page 20 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 21
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
38 UNH R&R Water Treatment Plant Improvements
2‐ IN DESIGN
SIHAGSTROM, DONALD P
spring pilot test complete.Met with state. fall testing to start 10/15. will do subsurface
investigation at waterworks site this 8/26
Design Firm: Wright‐Pierce Contractor: External Contractor Name:
2008‐0038
Rudman Hall Projects in Building 4
764 Rudman/Spaulding Hall ‐ Replacement of built in Glass Washers Phase II of II
1.1‐ PLAN/EST
RRHOUDE, DONALD A
The dept has to choose the product, I expect a decision this week will plan on a Winter break
installation. . 8‐25‐15
Design Firm: Contractor: Contractor Name:
2011‐0764
2352 Rudman Hall ‐ Fire Alarm Replacement
1.1‐ PLAN/EST
RRCARTABONA, STEPHANI
Fire alarm installation will occur following design. Coordinate acitivity with building occupants
prior to construction schedule.
Design Firm: Contractor: Contractor Name:
2015‐2352
1149 Rudman Hall ‐ Fire Alarm Replacement
2‐ IN DESIGN
RRCARTABONA, STEPHANI
7/27/15 SFC to provide 50% drawings by end of July 2015
Design Firm: SFC Engineering Contractor: External Contractor Name: TBD
2013‐1149
1787 Rudman Hall ‐ Fume Hood / HVAC Modifications and Repairs
3‐ IN CONSTRUCTION
RRCARTABONA, STEPHANI
8/27/15 Installed new controls in floor 3 labs, reviewing all mechanical equipment in each lab
after controller installation.
Design Firm: RFS Contractor: FCT Contractor Name: TBD
2014‐1787
Service Building Projects in Building 4
Monday, August 31, 2015 Page 21 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 22
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2593 Service Building ‐ Ice Melt System Fire Dept Roof
1.1‐ PLAN/EST
RRWOODCOCK, JONATHAN
8/27/2015_ Ice melt in proposal phase.
Design Firm: Contractor: FCT Contractor Name:
2015‐2593
1465 Service Building ‐ Replacement and Installation of Isolation valves
2‐ IN DESIGN
RRCARDOSO, ANDRE W
Please see ID # 2358 for updates associated with this project.
Design Firm: N/A Contractor: External Contractor Name: TBD
2013‐1465
2358 Service Building ‐ Heating Line Replacement Design
2‐ IN DESIGN
RRCARDOSO, ANDRE W
Harriman Associates has been selected as the design firm. Design is underway with 90%
documents due for review by October 1.
Design Firm: Harriman Associates Contractor: External Contractor Name: TBD
2014‐2358
2331 Service Building ‐ DFD Kitchen new vent hood rm F214
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
Instillation under way, FCT has an issue with the Hood, bad electronics, part on order. 8‐20
Design Firm: Contractor: FCT Contractor Name:
2015‐2331
SPAULDING HALL Projects in Building 3
2878 Spaulding Hall ‐ Steam Condensate Line Replacement
2‐ IN DESIGN
RR
Emergency Repair
JONES, KATHLEEN M
8/27/15: PM has met with mechanical engineer to begin design process. New condensate return
line to be installed between Spaulding and Rudman in lieu of replacing existing line in Conant
Courtyard. Project is procuring design services, then once design is complete a term contractor
will be hired to make the repair, likely in October or November 2015.
Design Firm: Harriman Contractor: Contractor Name:
2016‐0080
2480 Spaulding Hall ‐ Renovations rms 232, 234, 234A
3‐ IN CONSTRUCTION
FCRCARDOSO, ANDRE W
Work is ongoing with completion scheduled for September 25.
Design Firm: TBD Contractor: FCT Contractor Name: Shawmut Design and Construction
2015‐2480
Monday, August 31, 2015 Page 22 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 23
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2539 Spaulding Hall ‐ Fume Hood Alarm Upgrades
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
Project funded waiting for FCT 8‐20
Design Firm: Contractor: FCT Contractor Name:
2015‐2539
Thompson Hall Projects in Building 2
2727 Thompson Hall ‐ Presidents/Lubow Conference Rooms AC
2‐ IN DESIGN
RRCARTABONA, STEPHANI
8/27/15 Harriman will review chilled water capacity in the building to install ductless split
system in both conference room.
Design Firm: Harriman Contractor: FCT Contractor Name:
2015‐2714
2764 Thompson Hall ‐ Rm 102C Office Painting
3‐ IN CONSTRUCTION
FCRHEALEY, RANDY L
8/27/15 Original SOW complete. Working on expanded SOW
Design Firm: Contractor: FCT Contractor Name:
2015‐2749
Utility Distribution Projects in Building 2
2362 Quad Way ‐ Utility Line Replacement (Design Only)
2‐ IN DESIGN
RRJONES, KATHLEEN M
8/27/15: Project is in design stage for construction in summer 2016. Design is under contract and
will be completed by October 31, 2015.
Design Firm: Tighe & Bond Contractor: Contractor Name:
2015‐2362
2658 Ravine Electrical Circuit 11B Extension
3‐ IN CONSTRUCTION
SIHOUDE, DONALD A
This project is 70% complete. Temp power has been installed, Ravine work MH & Ducts
complete. To do, HS extend perm ducts instal bases, Install cableing. . 8‐25‐15
Design Firm: Contractor: External Contractor Name: IC Reed & Sons Inc.
2015‐2658
Veterinary Diagnostic Lab Projects in Building 2
Monday, August 31, 2015 Page 23 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 24
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2053 NHVDL ‐ Campus Deferred Repair Costs
3‐ IN CONSTRUCTION
RRCARTABONA, STEPHANI
reported with ID 1537
Design Firm: Port City Architecture Contractor: External Contractor Name: Allied Cook
2014‐2053
1537 NHVDL ‐ Relocation
3‐ IN CONSTRUCTION
SICARTABONA, STEPHANI
7/27/15 Interior finishes ongoing. Lab casework scheduled to arrive early August. Unitil gas line
installation to begin 8/3. Schedule completion / move in August 2015.
Design Firm: Port City Architecture Contractor: External Contractor Name: Allied Cook
2013‐1537
West Stadium Projects in Building 1
1947 West Stadium ‐ Design and Construction of New Facility
3‐ IN CONSTRUCTION
SIGEUTHER, MARK E
8‐20: Utility crossings for tel/data and natural gas scheduled for the week of 8/24 (Colovos Rd &
Sage Way respectively). Building foundations complete and bridge foundations started. Field
light poles have been placed/relocated. Steel erection crane to mobilize on site the week of 8/24,
first shipment of structural steel scheduled for on or about Sept 1st.
Design Firm: Populous/LaVallee Brensinge Contractor: External Contractor Name: PC Construction
2014‐1947
Whittemore Center ‐ Arena Projects in Building 6
2724 Whittemore Center ‐ Arena ‐ Lighting Controller Replacement
2‐ IN DESIGN
FCRHOUDE, DONALD A
Harriman has PO. Working on the Study, should be ready for presentation the first week of
Sept. 8‐25‐15
Design Firm: Harriman A&E Contractor: External Contractor Name: Unknown
2015‐2709
2581 Whittemore Center ‐ Arena ‐ Ice Sensor System Back Up Power
2‐ IN DESIGN
FCRHOUDE, DONALD A
The study has been provided, I am setting up a meeting to review the study.. . 8‐25‐15
Design Firm: OPA Contractor: Contractor Name:
2015‐2581
Monday, August 31, 2015 Page 24 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
Page 25
ID PROJECT TITLEPM
AccountableProject
Code
Project
Number:
2578 Whittemore Center ‐ Arena ‐ Generator Upgrade
2‐ IN DESIGN
FCRHOUDE, DONALD A
The pre ‐ final study report just arrived.I am setting up a meeting to review discuss the Study
results. 8‐25‐15 .
Design Firm: OPA Contractor: Contractor Name:
2015‐2578
2720 Whittemore Center ‐ Arena ‐ Ice Making System Mechanical Replacements
3‐ IN CONSTRUCTION
FCRCARTABONA, STEPHANI
8/27/15 Chiller installation is complete. Start up / test chiller 8/31/15 for operations to begin
making ice 8/6/15. Temporary chiller will be removed from site following new chiller start up
and run time. Operations office reconstruction to begin 9/8 with completion on or before 10/1.
Design Firm: Hoyle Tanner Contractor: FCT Contractor Name: American Refrigeration Company, Inc. / Milestone
2015‐2707
2584 Whittemore Center ‐ Arena ‐ Videoboard
3‐ IN CONSTRUCTION
FCRWOODCOCK, JONATHAN
8/27/15_Ribbon displays installed. Center hung installed between 8/30 ‐9/3/2015. Production
room continues itʹs remodel.
Design Firm: AJP Contractor: External Contractor Name: Daktronics
2015‐2584
2721 Whittemore Center ‐ Arena ‐ Block Wall Removal and Structural Support Installation
3‐ IN CONSTRUCTION
FCRCARTABONA, STEPHANI
6/30/15 ‐‐ Please refer to 2720 for updates
Design Firm: Contractor: Contractor Name:
2015‐2708
Whittemore Center ‐ Hamel Projects in Building 1
1176 Hamel Recreation Center ‐ Renovation and Expansion Project
3‐ IN CONSTRUCTION
CPHAGSTROM, DONALD P
GMP approved. Grade beams complete in August. Steel starting in September.
Design Firm: HGA Contractor: External Contractor Name: Shawmut
2013‐1176
Monday, August 31, 2015 Page 25 of 25University of New Hampshire
Brenda Whitmore, Director Facilities Project Management