Page 1
Facilities Project Management Monthly Report by Building
Monday, March 1, 2021 131Approved Project
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
1 Leavitt Lane Projects in Building 1
1 Leavitt Lane ‐ Convert boiler to natural gas
1.1‐ PLAN/EST
RRGEUTHER, MARK E
02‐24‐2021: Project newly reassigned to me. Getting up to speed.
Design Firm: OPA Contractor: Contractor Name:
2020‐0055
Year Approved:
18 Waterworks Road Projects in Building 1
18 Waterworks Road ‐ Install 2 monitors connected to the UNH system
1.1‐ PLAN/EST
FCRPETERS, NICK E
26 Feb 2021 ‐ Permits received. Receiving materials first week fo March. Scheduling install dates
upon arrival.
Design Firm: N/A Contractor: External Contractor Name: Various
2020‐0170
Year Approved: 2021
2 Leavitt Lane Projects in Building 1
2 Leavitt Lane ‐ new natural gas boiler
1.1‐ PLAN/EST
RRGEUTHER, MARK E
02‐24‐2021: Project newly reassigned to me. Getting up to speed.
Design Firm: Oak Point Assoc. Contractor: External Contractor Name: TBD
2020‐0054
Year Approved:
6 Leavitt Lane Projects in Building 1
6 Leavitt Lane ‐ New Gas Line and Boiler
1.1‐ PLAN/EST
RRGEUTHER, MARK E
02‐24‐2021: Project newly reassigned to me. Getting up to speed.
Design Firm: OPA Contractor: Contractor Name:
2020‐0056
Year Approved:
88 Commercial Street Projects in Building 1
Monday, March 1, 2021 Page 1 of 26University of New Hampshire
Facilities Project Management
Page 2
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
88 Commercial Street ‐ UNH Manchester ‐ Bio‐Manufacturing Innovation Center
Tenant fit‐out
3.1‐ SUBSTANTIAL COMPLETION
FCRROULEAU, RICHARD A
2/26/2021 ‐ Working with Control Tech, Inc. and UNH IT to set up a virtual server for HVAC
controls associated with the 6th floor and the 5th floor lab block. Working with Milestone,
Granite State Plumbing & Heating and Control Tech on adding one oxygen sensor and installing
remote alarms for both oxygen sensors. Otherwise, project is complete. Use and occupancy of
the space is increasing. Lab is being used for COVID testing for UNH Manchester and UNH Law
School.
Design Firm: John Jordan Contractor: External Contractor Name: by landlord (using Milestone)
2018‐0210
Year Approved: 2019
Adams Tower Projects in Building 2
Adams Tower West ‐ Major AC System Repairs
1.1‐ PLAN/EST
FCRGEUTHER, MARK E
02‐24‐2021: Project approved. Work to be scheduled after commencement.
Design Firm: N/A Contractor: External Contractor Name: Carrier
2021‐0083
Year Approved:
Adams Tower ‐ Verizon Wireless Antenna Upgrade
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
3‐2‐21 Version not ready for installation, will have to wait until after commencement.
Design Firm: Contractor: External Contractor Name: Verizon
2018‐0310
Year Approved: 2018
Babcock Hall Projects in Building 2
Babcock Hall ‐ Roof Access Hatch
2‐ IN DESIGN
FCRPETERS, NICK E
26 Feb 2021. Issues with COVID testing has pushed contractors from the project. Site conditions
re‐evaluated, and determined the hatch will operate as functioned until summer.
Design Firm: N/A Contractor: External Contractor Name: Skyline Roofing
2021‐0090
Year Approved:
Babcock Hall ‐ Adams Tower ‐ Electrical Investigation COVID Preparation
3.1‐ SUBSTANTIAL COMPLETION
FCRWEBBER, TODD M
Investigation is complete, no instruction to move forward with the proposed work at this time.
Design Firm: Contractor: Contractor Name:
2021‐0001
Year Approved:
Barton Hall & Cole Hall Projects in Building 4
Monday, March 1, 2021 Page 2 of 26University of New Hampshire
Facilities Project Management
Page 3
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Barton Hall ‐ 2nd Floor Reno for Diagnostic Labs
2‐ IN DESIGN
SIMANCINI, MATTHEW E
3/1/2021: Design effort under way. Early permit review has begun to address egress.
Construction Documents expected by April/May 2021.
Design Firm: H.L. Turner Group Contractor: External Contractor Name:
2020‐0091
Year Approved: 2020
Barton Hall ‐ Utility Distribution ‐ Transformer Replacement
2.5‐ IN PROCUREMENT
RRHEALEY, SCOTT M
1‐29‐21 ‐ Transformer should arrive in the middle of March, and need to be installed before June.
Ordered 10‐20 ‐ 23 week lead time.
Design Firm: Contractor: External Contractor Name: IC Reed
2021‐0040
Year Approved: 2021
Cole Hall ‐ Instructional Space Improvements
3.1‐ SUBSTANTIAL COMPLETION
SIMANCINI, MATTHEW E
3/1/2021: Project is substantially complete. HVAC scope will be deferred.
Design Firm: John L Turner Contractor: External Contractor Name: Multiple
2020‐0092
Year Approved: 2020
Barton Hall & Cole Hall ‐ Bus Shelter Install
3.1‐ SUBSTANTIAL COMPLETION
FCRRINES, DANIEL M
2‐24‐21: Project is substancially complete.
Design Firm: Contractor: External Contractor Name: T&S
2021‐0041
Year Approved:
Campus Projects in Building 9
FY21 Campus Envelope and Interior Painting
1.1‐ PLAN/EST
RRWEBBER, TODD M
Design Firm: N/A Contractor: FCT Contractor Name:
2019‐0369
Year Approved: 2021
Multi Housing Building‐ Hydration Station Installs
1.1‐ PLAN/EST
FCRPETERS, NICK E
26 Feb 2021 ‐ Received proposal from consultants and contractors. Awaiting approval for
funding.
Design Firm: McHenry Architecture Contractor: External Contractor Name: Charters Brothers
2021‐0084
Year Approved: 2021
Monday, March 1, 2021 Page 3 of 26University of New Hampshire
Facilities Project Management
Page 4
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Campus ‐ Parking Lot ‐ Sage Way Visitor Lot ‐ Parking Spot & Drop Box
1.1‐ PLAN/EST
FCRHENRY, PAUL A
3‐2‐21 Looking for more information
Design Firm: Contractor: Contractor Name:
2021‐0064
Year Approved:
Campus ‐ Bus Shelter Solar Lighting Upgrades
1.1‐ PLAN/EST
FCRPETERS, NICK E
26 Feb 2021 ‐ Initial expected contractor does not provide the services requested anymore.
Soliciting to other product manufacturers to locate a source to submit for grant funding.
Design Firm: Contractor: Contractor Name:
2021‐0092
Year Approved:
Campus Wide ‐ OBA COVID Barrier Installations
3‐ IN CONSTRUCTION
FCRPETERS, NICK E
26 Feb 2021 ‐ OBA barriers installed. Broken barriers found in Stillings and Philbrook, and to be
repaired through contractor. Another order to be placed to accommodate winter weather and
expanded dining requirements.
Design Firm: N/A Contractor: External Contractor Name: Milestone / WB Mason / Malthouse
2021‐0008
Year Approved: 2021
Campus Wide ‐ Academic / E&G Hydration Stations
3‐ IN CONSTRUCTION
FCRPETERS, NICK E
28 Feb 2021 ‐Preliminary construction complete campus‐wide. Awaiting arrival of water bottle
fill stations.
Design Firm: N/A Contractor: External Contractor Name: Milestone / Charters Brothers
2021‐0009
Year Approved: 2021
Campus ‐ Main Street Paving and Crosswalks
3‐ IN CONSTRUCTION
FCRRINES, DANIEL M
2‐24‐21: Project is via the TOD contract with Continental. Main Street Paving will take place after
South sidewalk road impacts are complete,continental and the town planning early June for
paving to begin.
Design Firm: Contractor: Contractor Name: continental
2020‐0276
Year Approved: 2021
Campus – High Voltage Monitoring Sensor Installation
3‐ IN CONSTRUCTION
SIHOUDE, DONALD A
02‐19‐21 All 11 monitors and the 1 gateway are installed with satisfactory signal strength. I will
log in all locations and plot on a UNH Map for the record.
Design Firm: Contractor: Contractor Name:
2021‐0024
Year Approved: 2021
Monday, March 1, 2021 Page 4 of 26University of New Hampshire
Facilities Project Management
Page 5
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Campus Wide ‐ Academic/E&G COVID Barrier Installations
3‐ IN CONSTRUCTION
FCRPETERS, NICK E
28 Feb 2021 ‐Shields have been installed through‐out Durham, Manchester, and Concord
campuses.
Design Firm: Contractor: External Contractor Name: WB Mason, Milestone,
2020‐0279
Year Approved: 2020
Chase Ocean Engineering Laboratory Projects in Building 1
Chase Ocean Engineering Laboratory ‐ Rm S210 HVAC Recommendations and Repair
2‐ IN DESIGN
FCRROULEAU, RICHARD A
2/26/2021 ‐ Final review documents received and review is nearly complete. Construction
estimate received. FCR to be prepared and forwarded to the customer, who has indicated that
they intend to proceed. Due to the fact that we are nearly into heating season, the intent is to
replace RTU‐2 with a smaller unit next cooling season. New RTU will be 100% recirc except
when economizing, able to stage and will have reheat. Energy Office put in place a temporary
solution for this summer making RTU‐1 primary for the server room and RTU‐2 secondary
during unit swap out.
Design Firm: H.L. Turner Group Contractor: External Contractor Name: TBD
2020‐0149
Year Approved: 2020
Child Study & Development Center Projects in Building 2
Child Study & Development Center ‐ Decks
1.1‐ PLAN/EST
FCRGEUTHER, MARK E
02‐24‐2021: Waiting for estimate
Design Firm: Contractor: External Contractor Name: TBD
2020‐0250
Year Approved:
Child Study & Development Center ‐ Playground Repairs
3‐ IN CONSTRUCTION
FCRGEUTHER, MARK E
02‐24‐2021: On site construction has stopped until Spring 2021. Deck building will take place off
site.
Design Firm: Ironwood Contractor: External Contractor Name: T&S Construction
2020‐0173
Year Approved: 2020
Christensen Hall Projects in Building 1
Christensen Hall ‐ T‐Mobile Antenna Upgrades ‐
1.1‐ PLAN/EST
FCRPETERS, NICK E
26 Feb 2021 ‐ Construction documents received and preparing permit applications. EME or RF
study requested from contractor.
Design Firm: Contractor: Contractor Name:
2021‐0093
Year Approved: 2021
Dimond Library Projects in Building 2
Monday, March 1, 2021 Page 5 of 26University of New Hampshire
Facilities Project Management
Page 6
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Dimond Library ‐ Interior Heating Distribution ‐ Design Only
2‐ IN DESIGN
RRMANCINI, MATTHEW E
3/1/2021: Wrapping up final design and material considerations. Construction Documents
expected in April 2021.
Design Firm: Harriman Contractor: External Contractor Name:
2010‐0281
Year Approved: 2021
Dimond Library ‐ Minor Modifications to Shelving/Floor 301
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
3‐2‐21 going to remove shelving and paint room with gift funds
Design Firm: Contractor: Contractor Name:
2021‐0029
Year Approved:
Field House Projects in Building 7
Field House ‐ Indoor Pool North Wall Investigation
1.1‐ PLAN/EST
RR
Emergency Repair
RINES, DANIEL M
2‐24‐21:
Project assigned, Pm to work with stakeholders to identify the trouble areas, and begin
investigation with term structural firm.
Design Firm: Contractor: Contractor Name:
2021‐0101
Year Approved: 2021
Field House ‐ Glass Wall, Outdoor Deck/Roof and Door Replacement Design Only
2‐ IN DESIGN
RRGEUTHER, MARK E
02‐24‐2021: Preliminary to be reviewed by UNH. Goal is to have the design and cost estimate
completed by the end of June. Construction planned FYʹ23.
Design Firm: LaVallee Brensinger Contractor: External Contractor Name: TBD
2013‐1044
Year Approved: 2021
Field House ‐ Pool Chemical Storage ‐ Design Only
2‐ IN DESIGN
RRGEUTHER, MARK E
02‐24‐2021: Design is continuing.
Design Firm: Weston & Sampson Contractor: External Contractor Name: TBD
2020‐0181
Year Approved: 2020
Field House ‐ Indoor Pool Crack Repairs
3‐ IN CONSTRUCTION
RR
Emergency Repair
RINES, DANIEL M
2‐24‐21: Cracks temporarily repaired so pool can be filled, AM to allocated funds for future long
term repair.
Design Firm: Contractor: External Contractor Name: Guarinos Swimming pool service
2021‐0091
Year Approved: 2021
Monday, March 1, 2021 Page 6 of 26University of New Hampshire
Facilities Project Management
Page 7
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Field House ‐ UV Filter Replacement
3.1‐ SUBSTANTIAL COMPLETION
RRGEUTHER, MARK E
02‐24‐2021: Working on close out documentation.
Design Firm: Weston & Sampson Contractor: External Contractor Name: Charters Brothers
2019‐0306
Year Approved: 2019
Field House ‐ 1st Floor AC Installation
3.1‐ SUBSTANTIAL COMPLETION
SIGEUTHER, MARK E
02‐24‐2021: Substantially Complete. Working on close out.
Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers
2011‐0653
Year Approved: 2019
Field House ‐ Indoor Pool Concrete Repairs
3.1‐ SUBSTANTIAL COMPLETION
RRRINES, DANIEL M
2‐24‐21: Work is sunbstancially complete. Campus Rec has added scope for pool maintinance
items, which have been completed, few minor concrete fixes needed for punclist.then closeout.
Design Firm: Hoyle Tanner Contractor: External Contractor Name: Structural Preservation Systems
2020‐0129
Year Approved: 2021
Future Design and Planning Projects in Building 1
Health Sciences Initiative CHHS Building
3‐ IN CONSTRUCTION
FCRHEISNER, MICHELE
02/24/21 ‐ Simulation wing exterior framed, slab on grade first week of March; office wing
exterior framed. Project scheduled to be complete 8/2021
Design Firm: LVBPA‐DB Contractor: External Contractor Name: Wright Ryan
2020‐0231
Year Approved: 2020
Gregg Hall Projects in Building 2
Gregg Hall ‐ Boiler Plant Replacement
1‐ ASSIGNED
RRROULEAU, RICHARD A
Design Firm: Contractor: Contractor Name:
2018‐0254
Year Approved: 2022
Monday, March 1, 2021 Page 7 of 26University of New Hampshire
Facilities Project Management
Page 8
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Gregg Hall‐ Rm 337‐ Expanded COVID Testing Lab
3.1‐ SUBSTANTIAL COMPLETION
FCRHENRY, PAUL A
3‐2‐2 Lab is substancilly complete, occupants moviing and testing equipment, lab team is still
waiting for some qupipment pror to operation. There is always some small issues to solve prior
to going live.
Design Firm: Harriman Contractor: External Contractor Name: Charter Brothers
2021‐0081
Year Approved:
Haaland Hall Projects in Building 1
Haaland Hall – PVI Tank Replacement
3‐ IN CONSTRUCTION
FCRRINES, DANIEL M
2‐24‐21: Tank has been installed, Same issues with original flue and chimney as Handler Hall
project cited by SFMO. PM working on solutions.
Design Firm: Harriman Contractor: External Contractor Name: United Mechanical
2020‐0253
Year Approved: 2020
Hamel Recreation Center Projects in Building 1
Hamel Recreation Center ‐ Covid‐19 Surge Facility
1.1‐ PLAN/EST
FCRRINES, DANIEL M
2‐24‐21:Site has been demobilized, but may need to be reopened in short notice.
Design Firm: Contractor: Contractor Name:
2020‐0245
Year Approved: 2020
Hamilton Smith Hall Projects in Building 2
Hamilton Smith Hall ‐ Bi‐Directional Amplifier Installation
1‐ ASSIGNED
SIROULEAU, RICHARD A
Design Firm: Norris Inc. Contractor: External Contractor Name: Norris Inc.
2016‐0116
Year Approved: 2021
Monday, March 1, 2021 Page 8 of 26University of New Hampshire
Facilities Project Management
Page 9
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Hamilton Smith Hall ‐ Rms G13, G15 Water Infiltration Investigation and Repair
1.1‐ PLAN/EST
FCRROULEAU, RICHARD A
2/26/2021 ‐ T&S Construction to develop budgetary construction estimate for UNH planning
purposes. ‐ ON HOLD ‐ During recent heavy rain, it was confirmed that water is percolating up
between the foundation wall and the floor slab. This suggests too much water is coming off the
roof for the perimeter drain to handle resulting in hydrostatic pressure pushing water under the
foundation wall and/or footing and up between the wall and slab. While this could possibly be
considered a design error, it does not suggest improper construction by the original contractor.
Logical solution is to intercept and divert roof run‐off rather than trying to upsize existing
perimeter drain, which may not solve the underlying problem of simply too much water. A
solution is to line the perimeter drain with waterproof membrane and drain the resulting bathtub
to an adjacent storm drain manhole. This is the same approach used at Taylor Hall several years
ago. Reached out to term civil engineer Hoyle Tanner & Associates and received a proposal.
However, project is on hold due to the Universityʹs cash flow limitations.
Design Firm: Contractor: External Contractor Name: tbd
2020‐0030
Year Approved: 2020
Handler Hall Projects in Building 1
Handler Hall ‐ Replacement of PVI Hot Water Tanks
3‐ IN CONSTRUCTION
FCRRINES, DANIEL M
2/24/21 ‐ Tanks have been installed, currently running on steam only, as SFMO tagged original
building construction project code violations. PM, NPI and Harriman working on solutions to
code issues from original construction in conjunction with the SFMO. Sizable remediation project
planned for this summer.
Design Firm: Harriman Contractor: External Contractor Name: NPI
2019‐0324
Year Approved: 2020
Health & Wellness Building Projects in Building 1
Health & Wellness Building ‐ COVID‐19 Testing Instrumentation
2‐ IN DESIGN
FCRHENRY, PAUL A
3‐2‐21 Have approval for AC in Lab, CB ordering materials, coordinating with lab for installation
dates, most likely after Gregg Hall Lab is on line.
Design Firm: Contractor: Contractor Name:
2020‐0281
Year Approved: 2020
Hewitt Hall Projects in Building 1
Hewitt Hall ‐ Duel Temperature Mechanical Tie‐In
3.1‐ SUBSTANTIAL COMPLETION
RRRINES, DANIEL M
2‐24‐21: . Commissioning and Balancing complete, minor punchlist, and document closeout
underway.
Design Firm: Harriman Contractor: External Contractor Name: Anderson Welding
2019‐0338
Year Approved: 2020
Holloway Commons Projects in Building 1
Monday, March 1, 2021 Page 9 of 26University of New Hampshire
Facilities Project Management
Page 10
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Holloway Commons/MUB ‐ Verizon Wireless In‐Building Antenna System
3‐ IN CONSTRUCTION
FCRPETERS, NICK E
26 Feb 2021 ‐ Construction through kitchen complete. Contractors are continuing with work as
scheduled.
Design Firm: Verizon Wireless Contractor: Contractor Name: Verizon Wireless
2020‐0267
Year Approved: 2020
Horton Social Science Center Projects in Building 1
Horton Social Science Center ‐ G04 Auditorium – Air Conditioning
3.1‐ SUBSTANTIAL COMPLETION
SIHENRY, PAUL A
3‐2‐21 replaced faulty VFD drives, waiting for final commissioning report.
Design Firm: Harriman Contractor: External Contractor Name: Structuretone
2010‐0411
Year Approved: 2019
James Hall Projects in Building 3
James Hall ‐ Suite 364 Fire Alarm Strobes
1.1‐ PLAN/EST
FCRHEISNER, MICHELE
02/24/21 ‐ Due to the uncertainty and fluctuation of contractor availability and schedule
constraints related to covid, recommend this work be rescheduled
Design Firm: Contractor: Contractor Name:
2020‐0251
Year Approved:
James Hall ‐ Suite 364 Lab Repairs
1.1‐ PLAN/EST
FCRHEISNER, MICHELE
02/24/21 ‐ Due to the uncertainty and fluctuation of contractor availability and schedule
constraints related to covid, recommend this work be rescheduled. Cleanroom lab schedules to
be coordinated with end users.
Design Firm: Contractor: Contractor Name:
2020‐0252
Year Approved:
James Hall ‐ HVAC Modifications Investigation and Design
3.1‐ SUBSTANTIAL COMPLETION
RRROULEAU, RICHARD A
2/26/2021 ‐ No change. Repairs and adjustment complete. The Energy Office is addressing
unrelated hood air flow and hood alarm issues. They have pulled in Cx Agent I.C.O. for
assistance. Once the building has been recommissioned and issues identified have been
corrected, we will run the kiln and, hopefully, confirm no transfer from the exhaust air stream to
the intake/supply air. Failing that, the correct solution and what probably should have been
done originally will be a dedicated hood exhaust.
Design Firm: Contractor: Contractor Name:
2018‐0270
Year Approved: 2018
Kendall Hall Projects in Building 5
Monday, March 1, 2021 Page 10 of 26University of New Hampshire
Facilities Project Management
Page 11
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Kendall Hall ‐ Rms 506 & 506A Improvements rms 506 & 506A
1.1‐ PLAN/EST
FCRGEUTHER, MARK E
02‐24‐2021 ‐ Space not appropriate for the intended use per SFMO.
Design Firm: Contractor: Contractor Name:
2021‐0094
Year Approved:
Kendall Hall ‐ Rm 517 Improvements
1.1‐ PLAN/EST
FCRGEUTHER, MARK E
02‐24‐2021: Space not appropriate for the intended use per SFMO. PI might modify his intent,
waiting to hear.
Design Firm: N/A Contractor: External Contractor Name: TBD
2021‐0095
Year Approved:
Kendall Hall ‐ Rm 409 Sink Installation
1.1‐ PLAN/EST
FCRGEUTHER, MARK E
02‐24‐2021: Met with client, waiting to hear back on need.
Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers
2021‐0097
Year Approved:
Kendall Hall ‐ 3rd Floor Repurposing
3.1‐ SUBSTANTIAL COMPLETION
SIGEUTHER, MARK E
02‐24‐2021: Occupancy approved by SFMO. Working on close out documentation. Hydronic
balancing ongoing.
Design Firm: Manypenny Murphy Contractor: External Contractor Name: Charters Brothers
2019‐0158
Year Approved: 2019
Kendall Hall ‐ 4th Floor Repurposing
3.1‐ SUBSTANTIAL COMPLETION
SIGEUTHER, MARK E
02‐24‐2021: See 2019‐0158
Design Firm: Manypenny Murphy Contractor: External Contractor Name: Charters Brothers
2019‐0161
Year Approved: 2019
Kingsbury Hall Projects in Building 4
Kingsbury Hall ‐ Room Improvements rm W136
1.1‐ PLAN/EST
FCRMANCINI, MATTHEW E
3/1/2021: Scheduling to meet with stakeholders to define scope and then develop an RFP for
Term Contractors.
Design Firm: Contractor: Contractor Name:
2021‐0099
Year Approved:
Monday, March 1, 2021 Page 11 of 26University of New Hampshire
Facilities Project Management
Page 12
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Kingsbury Hall ‐ Retro‐Commissioning
3‐ IN CONSTRUCTION
FCRKOHLER, ADAM S
Design Firm: Contractor: Contractor Name:
2020‐0187
Year Approved: 2020
Kingsbury Hall ‐ Compressor and Air Dryer Replacement
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
HENRY, PAUL A
3‐2‐21 New compressor arrived last week, operations starting installation, will veriify with
oiperations, but believe it is complete.
Design Firm: Contractor: Contractor Name:
2020‐0049
Year Approved: 2021
Kingsbury Hall ‐ Career Services Center
3.1‐ SUBSTANTIAL COMPLETION
FCRPETERS, NICK E
28 Feb 2021 ‐ Tabletops being replaced. Room Signage being ordered.
Design Firm: Placework Contractor: External Contractor Name: Charter Brothers
2020‐0216
Year Approved: 2020
Leavitt Cntr Transportation Center Projects in Building 2
Leavitt Cntr Transportation Center‐ Installation of Safety Harness System
2‐ IN DESIGN
FCRHENRY, PAUL A
3‐2‐21 Awaitng final design and installation schedule, we has provided some dimention
verification two weeks ago.
Design Firm: DFP Contractor: External Contractor Name: DDP
2021‐0006
Year Approved: 2021
Leavitt Cntr Transportation Center ‐ Partial EPDM Roof Replacement
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
PETERS, NICK E
27Feb 2021 ‐ Purchase Order issued. Working with Viking for scheduling.
Design Firm: N/A Contractor: External Contractor Name: Viking
2020‐0287
Year Approved: 2021
Marine Research Facility Projects in Building 1
Monday, March 1, 2021 Page 12 of 26University of New Hampshire
Facilities Project Management
Page 13
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Coastal Marine Lab ‐ Fire Clean‐Up and Repairs
3.1‐ SUBSTANTIAL COMPLETION
FCRROULEAU, RICHARD A
2/26/2021 ‐ No Change ‐ Project suspension due to COVID‐19 said to have been lifted on 4/27;
however, spending restrictions are preventing this project from moving forward. Next steps are
to assemble roofing package for bidding and line up window repairs.
Design Firm: Contractor: External Contractor Name: Careno Construction
2018‐0336
Year Approved: PROJECT SUSPENDED
McGregor Memorial EMS Projects in Building 1
McGregor Memorial EMS ‐ Envelope and Interior Repairs
3‐ IN CONSTRUCTION
RRPETERS, NICK E
26 Feb 2021: Roofing and exterior water treatment completed. Abatement completed. Design
fees accepted and approved. Design package received and submitted to contractor. Awaiting
proposal.
Design Firm: N/A Contractor: External Contractor Name: Careno Const
2020‐0196
Year Approved: 2021
Memorial Union Building Projects in Building 2
Memorial Union Building ‐ 110 Ton Rooftop Chiller ‐ Design Only
2‐ IN DESIGN
FCRROULEAU, RICHARD A
2/26/2021 ‐ 75% complete review documents from SMRT are in hand for review. Comments
received from Adam Kohler and Scott Lindquist.
Design Firm: SMRT Contractor: External Contractor Name: tbd
2021‐0070
Year Approved: 2021
Memorial Union Building ‐ Accessing Systems
3.1‐ SUBSTANTIAL COMPLETION
FCRMANCINI, MATTHEW E
3/1/2021: Project is substantially complete.
Design Firm: Contractor: External Contractor Name: Yates Electric
2021‐0021
Year Approved: 2021
Morse Hall Projects in Building 10
Morse Hall ‐ Rm 331 Renovations
1.1‐ PLAN/EST
FCRGEUTHER, MARK E
02‐24‐2021: Project approved to move forward. Design kick off meeting scheduled for 02‐25‐2021
Design Firm: Harriman Contractor: External Contractor Name: Milestone
2021‐0022
Year Approved: 2021
Monday, March 1, 2021 Page 13 of 26University of New Hampshire
Facilities Project Management
Page 14
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Morse Hall ‐ Rm 119 Fire Suppression ‐ Self Made Room Fabrications
1.1‐ PLAN/EST
FCRROULEAU, RICHARD A
2/26/2021 ‐ No change since last update. The EMI/RFI‐sheilded room, which is used for welding,
was constructed shortly after the original construction due to concerns about electrical issues the
welding might cause the computers of the mid‐80s. At this point, they rarely do any welding. I
asked Phil Demaine whether it could be removed, which would make the issue go away. Mr.
Demaine was to check with his superiors. I pinged him again via email but still no response.
Design Firm: Contractor: External Contractor Name: Johnson Controls, possibly Norris
2021‐0014
Year Approved:
Morse Hall ‐ Rm A132 Fire Suppression ‐ Self Made Room Fabrications
1.1‐ PLAN/EST
FCRROULEAU, RICHARD A
2/26/2021 ‐ No change since last update. The chamber is a small constant temperature room. It
appears that it may not be in use except maybe for storage. I have reviewed it with Phil Biron. It
will need a sprinkler head, not frost free because researcher Joe Salisbury tells me it does not go
down below freezing. Given the room is so small, Phil thinks it unlikely anyone would work
inside the room and, therefore, it doesnʹt need a fire alarm notification appliance. I have a price
from Johnson Controls and can now prepare an FCR.
Design Firm: Contractor: External Contractor Name: Johnson Controls
2021‐0018
Year Approved:
Morse Hall ‐ Rm 249 Fire Suppression ‐ Self Made Room Fabrications
1.1‐ PLAN/EST
FCRROULEAU, RICHARD A
2/26/2021 ‐ No change since last update. The chamber in this room requires clean room attire. I
have received a sketch of the chmber from Marc Lessard and am waiting for photos and
response to other questions. There are two rooms within the chamber. One is a control room
and one is an optical calibration room for highly‐sensitive devices used in space. Sprinkler and
fire alarm AV notification are required. Phil Biron suggested an AV in Room 249 itself and
strobe only devices in the rooms within the chamber. However, Marc Lessard tells me any
unplanned light in the enclosure during calibration could damage the equipment being
calibrated. Storage on top of the unit is also an issue. Signage can probably address that issue.
Once scope is established, I will reach out to term sprinkler and fire alarm contractors for pricing.
Design Firm: Contractor: External Contractor Name: Johnson Controls, Norris
2021‐0019
Year Approved:
Morse Hall ‐ Rm 118 Fire Suppression ‐ Anechoic Chamber
1.1‐ PLAN/EST
FCRROULEAU, RICHARD A
2/26/2021 ‐ No change since last update ‐ Room 118: This EMI/RFI‐shielded room is an anechoic
chamber that also needs sprinkler coverage. Per discussion with Phil Biron (SFMO), it does not
need a fire alarm notification appliance because no one is ever enclosed in the chamber with the
door closed as per Nick Kirsh, the researcher responsible for the room,. There are ports in the
top of the chamber for sprinkler and there are specialty extending sprinkler heads made by a
company in Seabrook specifically for this application. I have spoken with Nick Kirsh and
requested information on the foam and coating. I am working with Johnson Controls to get
pricing for the speciality sprinkler heads.
Design Firm: Contractor: External Contractor Name: Johnson Controls
2021‐0025
Year Approved:
Monday, March 1, 2021 Page 14 of 26University of New Hampshire
Facilities Project Management
Page 15
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Morse Hall ‐ Former Clean Rm Renovation
2‐ IN DESIGN
SIMANCINI, MATTHEW E
3/1/2021: Design is under way to support Spaulding swing space. EOS will be primary occupant
when finished. Have funding for Design 2021 and Construction FY2022
Design Firm: Harriman Contractor: External Contractor Name: tbd
2020‐0189
Year Approved: 2020
Morse Hall ‐ Rm 419 Adding New Equipment
3‐ IN CONSTRUCTION
FCRHEISNER, MICHELE
02/24/21 ‐ Temporary utility connections made to allow for partial utilization of lab equipment
and early experimentation for customer to meet early March deadline. Timing of full ʹbuild outʹ
TBD.
Design Firm: SMRT Contractor: Contractor Name:
2020‐0190
Year Approved: 2020
Morse Hall ‐ Emergency Eyewash Installation
3.1‐ SUBSTANTIAL COMPLETION
FCRPETERS, NICK E
28Feb 2021 ‐ Construction completed. Working on commissioning and closeout documentation.
Design Firm: N/A Contractor: External Contractor Name: Milestone Eng & Const, Inc
2020‐0150
Year Approved: 2020
Morse Hall ‐ Interior Main Heating Line Connections
3.1‐ SUBSTANTIAL COMPLETION
RRROULEAU, RICHARD A
2/26/2021 ‐ Work is complete. Final inspection letter received from SFMO. Once this letter and
other project documentation is put into Meridian, this project will be complete and ready to be
closed out.
Design Firm: Harriman Contractor: External Contractor Name: United Mechanical
2020‐0271
Year Approved: 2021
Morse Hall ‐ Stand By Generator and Distribution ‐ Design ONLY
3.1‐ SUBSTANTIAL COMPLETION
SIHOUDE, DONALD A
02‐19‐2021 ‐ Report received on January 22nd. From Harriman A&E.Phase 1 completed.
Design Firm: Contractor: Contractor Name:
2020‐0214
Year Approved: 2020
New England Center Projects in Building 1
New England Center ‐ Boiler Replacement and BAS Controls
3.1‐ SUBSTANTIAL COMPLETION
RRHENRY, PAUL A
3‐2‐21 complete, waiting for final commissioning report, finalizing close out.
Design Firm: Harriman Contractor: Contractor Name:
2016‐0403
Year Approved: 2020
Monday, March 1, 2021 Page 15 of 26University of New Hampshire
Facilities Project Management
Page 16
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Parsons Hall Projects in Building 1
Parsons Hall ‐ Set up Lab Space W202
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
3‐2‐21 have CPR and funding, workign with contractor to start.
Design Firm: Contractor: External Contractor Name: Charter Brothers
2021‐0028
Year Approved: 2021
Paul College Projects in Building 2
Paul College ‐ Roof Membrane and Flashing Investigation ‐ Corrective Plan/Design
1.1‐ PLAN/EST
RRROULEAU, RICHARD A
2/26/2021 ‐ No Change ‐ ARM recommends water testing to determine where/how the water is
getting in. Proposal for testing is in hand. P.O. request will be submitted now that Covid‐19
suspension has been lifted. Depending on the results, we will pursue a warranty claim and/or
involve PC Construction and the roofer. Using remaining funds from original construction for
this effort (ref. 2009‐0980 / 1XT955)
Design Firm: ARM, LLC (roofing consultan Contractor: Contractor Name:
2019‐0331
Year Approved: 2019
Paul College ‐ Investigation of Voltage Fluctuations
3‐ IN CONSTRUCTION
RR
Emergency Repair
HOUDE, DONALD A
02‐19‐2021 ‐ Paul College‐ the Electrical Service for this building from the Hi Voltage 34,500 to
the low 120V has beeen checked and tested. We are still looking at different issues and checking
system loads. We have asked IT to look into the equipment programming and Telecom to check
the LAN..We think the issue has gone away.
Design Firm: Contractor: Contractor Name:
2021‐0079
Year Approved: 2021
Paul Creative Arts Center Projects in Building 6
Paul Creative Arts Center ‐ Building Life Safety Report Update
1.1‐ PLAN/EST
RRHENRY, PAUL A
3‐2‐21 Need to review report and finilize
Addendum to Life Safety plan to be reviewed and approved with the SFMO.
Design Firm: Contractor: Contractor Name:
2019‐0241
Year Approved: 2019
Paul Creative Arts Center ‐ Art Museum ‐ HVAC Design
1.1‐ PLAN/EST
FCRROULEAU, RICHARD A
2/26/2021 ‐ RFS Engineering has walked the site. They are preparing a proposal that will include
a hard number for a study, potential solutions and recommendations and
conservative/budgetary numbers schematic, DD and CD.
Design Firm: RFS Engineering Contractor: Contractor Name:
2021‐0098
Year Approved:
Monday, March 1, 2021 Page 16 of 26University of New Hampshire
Facilities Project Management
Page 17
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Paul Creative Arts Center ‐ Fire Alarm Design Only
2‐ IN DESIGN
RRHENRY, PAUL A
3‐2‐21 design uder review, then handing off to Matt, meeting with Harriman to review.
Design Firm: TBD Contractor: External Contractor Name: TBD
2019‐0055
Year Approved: 2020
Paul Creative Arts Center ‐ Sprinkler Installation ‐ Design Only
2‐ IN DESIGN
RRMANCINI, MATTHEW E
3/1/2021: Design Draft review scheduled for March 4th.
Design Firm: Contractor: Contractor Name:
2016‐0032
Year Approved: 2021
Paul Creative Arts Center ‐ High Voltage Electrical Service Replacement
3‐ IN CONSTRUCTION
RRHOUDE, DONALD A
02‐19‐21 95% of the conduit is in place. I have been asked to complete this work this winter. I
expect to have the transformer base and transformer set in place next Tuesday (2‐23‐21) then
install Hi V cables shortly after and the secondary loads at the same time .
Design Firm: Harriman Contractor: External Contractor Name: ICR
2017‐0106
Year Approved: 2021
Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation
3.5‐ WARRANTY REPAIRS
RRROULEAU, RICHARD A
2/26/2021 ‐ No change. Complete pending equipment list update and O&M upload.
Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.
2018‐0249
Year Approved: 2019
Philbrook Hall Projects in Building 2
Philbrook Hall ‐ Steam Study and Investigation
2‐ IN DESIGN
RRHENRY, PAUL A
3‐2‐21 need to reiew final report and finilize
RFS provided three (3) options for steam study. UNH has decided to proceed with using the
steam boiler at Philbrook for hot water make up, this will allow the local steam boiler to operate
between August ‐ May with continuation operation. During Summer when Philbrook is not
open the boiler will be put in dry layup with service assistance from Blake Engineering. Intend
to have local boiler online January 2019.
Design Firm: RFS Contractor: External Contractor Name: Eckhardt Johnson
2018‐0162
Year Approved: 2019
Monday, March 1, 2021 Page 17 of 26University of New Hampshire
Facilities Project Management
Page 18
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Philbrook Hall ‐ Boiler Replacement
3.1‐ SUBSTANTIAL COMPLETION
FCRHENRY, PAUL A
3‐2‐21 working on final closeout
Design Firm: RFS Contractor: External Contractor Name: Eckardt & Johnson
2019‐0304
Year Approved: 2019
Putnam Hall Projects in Building 2
Putnam Hall ‐ Spaulding Hall Swing Space
1.1‐ PLAN/EST
SIHEISNER, MICHELE
02/24/21 ‐ McGregor EMS to vacate Putnam by mid, late June. Planning is back in motion for
collections temporary relocation from Spaulding. Updated and toured Putnam with new
herbarium collections manager, insectarium collections manager and Chris Neefus.
Design Firm: Contractor: Contractor Name:
2020‐0204
Year Approved:
Putnam Hall ‐ EMS ‐ Covid‐19 Preparations
2‐ IN DESIGN
FCRRINES, DANIEL M
2‐24‐21: EMS to move back to College Road. Code study, and feasibility underway for long term
build out of Putnam.
Design Firm: McHenry Contractor: External Contractor Name: T&S Construction
2020‐0244
Year Approved:
Roads/Grounds Projects in Building 8
South Drive ‐ Design Advancement
2‐ IN DESIGN
SIHENRY, PAUL A
3‐2‐21 Tighe & Bond working on updating the wetland permits with NH DES, looking at
mitigation locations for application.
Design Firm: Tighe & Bond Contractor: External Contractor Name:
2013‐1115
Year Approved: 2013 PROJECT SUSPENDED
FY21 Major Road Repairs ‐ Under Town of Durham Contract
3‐ IN CONSTRUCTION
RRRINES, DANIEL M
2‐24‐21: Paving work complete pending closeout and final invoicing.
Design Firm: Contractor: External Contractor Name: Continental
2019‐0371
Year Approved: 2021
Monday, March 1, 2021 Page 18 of 26University of New Hampshire
Facilities Project Management
Page 19
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Campus ‐ Main Street South Sidewalk
3‐ IN CONSTRUCTION
SIRINES, DANIEL M
2‐24‐21: Project is tracking funding for grant, please see 2017‐0384 for updates on project.
Design Firm: Contractor: Contractor Name:
2019‐0228
Year Approved: 2019
Campus ‐ A‐Lot Fencing Replacement
3.1‐ SUBSTANTIAL COMPLETION
RRHOUDE, DONALD A
02‐19‐2021 Last section of fence to be installed when good weather comes. All tree clearing
completed.
Design Firm: Contractor: Contractor Name:
2021‐0037
Year Approved: 2021
FY21 Sidewalk and Walkway Repairs
3.1‐ SUBSTANTIAL COMPLETION
RRRINES, DANIEL M
2‐24‐21: List complete, keeping open for any pedestrian hazards identified.
Design Firm: N/A Contractor: External Contractor Name: Top Quality Construction
2017‐0275
Year Approved: 2021
FY21 Site Stair Repairs
3.1‐ SUBSTANTIAL COMPLETION
RRRINES, DANIEL M
2‐24‐21; List complete, project remains open in case of pedestrian hazards identified over winter
months.
Design Firm: N/A Contractor: External Contractor Name: Top Quality Construction
2019‐0368
Year Approved: 2021
Campus ‐ South Drive ‐ Temporary Connection to Colovos Road
3.1‐ SUBSTANTIAL COMPLETION
SIGEUTHER, MARK E
02‐24‐2021: Substantially Complete.
Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports
2018‐0267
Year Approved: 2019
Campus ‐ Main Street South Sidewalk
3.1‐ SUBSTANTIAL COMPLETION
SIRINES, DANIEL M
2‐24‐21: Project is underway, punchlist to be completed in the spring.
Design Firm: CMA Engineering Contractor: Contractor Name:
2017‐0384
Year Approved: 2018
Rudman Hall Projects in Building 7
Monday, March 1, 2021 Page 19 of 26University of New Hampshire
Facilities Project Management
Page 20
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Rudman Hall ‐ Steam Absorber #1 Replacement
1.1‐ PLAN/EST
RRMANCINI, MATTHEW E
3/1/2021: A site visit for engineering term contractors has been set for March 4th. Design
documents to be furnished for Besign‐Build delivery.
Design Firm: Contractor: Contractor Name:
2013‐0865
Year Approved: 2022
Rudman Hall ‐ Conversion to DDC Controls
3‐ IN CONSTRUCTION
RRMANCINI, MATTHEW E
3/1/2021: Reference ID 2010‐0479 for updates. Work expected to continue with conversion of
office wings following completion of overall HVAC project.
Design Firm: SMRT Contractor: External Contractor Name: StructureTone
2015‐2336
Year Approved: 2018
Rudman Hall ‐ DDC Controls Backstop
3‐ IN CONSTRUCTION
RRMANCINI, MATTHEW E
3/1/2021: Backstop project to support relocation of mass spectrometer. General exhaust to be
added to room per SMRTʹs direction. Additional direct‐exchange cooling to be included.
Awaiting final design. Refer to Project 2017‐0288
Design Firm: SMRT Contractor: External Contractor Name: Structuretone
2021‐0013
Year Approved: 2021
Rudman Hall ‐ Retro‐Commissioning of ARO HVAC System
3‐ IN CONSTRUCTION
FCRMANCINI, MATTHEW E
3/1/2021: Reference ID 2010‐0479 for updates. Project to continue.
Design Firm: SMRT Contractor: Contractor Name: Structuretone
2019‐0305
Year Approved:
Rudman Hall ‐ Laboratory Fume Hood Control System Replacement
3‐ IN CONSTRUCTION
RRMANCINI, MATTHEW E
3/1/2021: Project continues. Currently, Phase 15 of 18 Labs are under way. HVAC work
completion projected for June 2021.
Design Firm: SMRT Contractor: External Contractor Name: StructureTone
2010‐0479
Year Approved: 2017
Rudman Hall ‐ AHU‐3 Replacement
3‐ IN CONSTRUCTION
RRMANCINI, MATTHEW E
3/1/2021: Project to replace air handler is nearing completion.
Design Firm: SMRT Contractor: External Contractor Name: MB Mechanical Contractors Inc.
2020‐0128
Year Approved: 2021
Monday, March 1, 2021 Page 20 of 26University of New Hampshire
Facilities Project Management
Page 21
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Rudman Hall ‐ Fire Alarm Replacement
3.1‐ SUBSTANTIAL COMPLETION
RRMANCINI, MATTHEW E
3/1/2021: Project is substantially complete.
Design Firm: SFC / SMRT Contractor: External Contractor Name: StructureTone
2015‐2352
Year Approved: 2016
Service Building Projects in Building 5
Service Building ‐ Fire Department Sprinkler Installation and Building Envelope
Repairs
2‐ IN DESIGN
RRRINES, DANIEL M
2/24/21 : Design efforts underway.
Design Firm: McHenry Architecture Contractor: External Contractor Name:
2010‐0356
Year Approved: 2021
Service Building – DFD Expansion / SPA renovations
2‐ IN DESIGN
FCRRINES, DANIEL M
2‐24‐21: Code study and design efforts underway, quick transition into permitting and
construction under term contact anticipated.
Design Firm: McHenry Architecture Contractor: External Contractor Name: TBD
2021‐0085
Year Approved: 2021
Service Building ‐ Fire Dept New Vehicle Exhaust Extraction System
2.5‐ IN PROCUREMENT
FCRRINES, DANIEL M
2‐24‐21: PM working with DFD to secure electrical firm contract, work anticipated to begin by the
end of March.
Design Firm: Contractor: Contractor Name:
2021‐0089
Year Approved:
Service Building ‐ Dispatch Center Keltron System
3.1‐ SUBSTANTIAL COMPLETION
FCRHOUDE, DONALD A
01‐27‐21 ‐ Contractors have POʹs and incumbrances. Norris has prepared all new digital circuits.
A schedule with dispatch has been set up to verify transfer of lines. Project progressing about
99% complete. 1 circuit to be relocated.
Design Firm: Contractor: External Contractor Name: Norris / UNH Telecom
2016‐0123
Year Approved: 2018
Monday, March 1, 2021 Page 21 of 26University of New Hampshire
Facilities Project Management
Page 22
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Service Building ‐ Interior Heating Main Connections
3.1‐ SUBSTANTIAL COMPLETION
RRROULEAU, RICHARD A
2/26/2021 ‐ All work complete. Rough and final mechanical inspections complete. Electrical
demo and SFMO final inspections can be scheduled. Somewhat related work in Zais pending
electronic valve replacement by Facilities Operations.
Design Firm: Harriman Contractor: External Contractor Name: Careno / NPI
2020‐0272
Year Approved: 2021
Spaulding Hall Projects in Building 3
Spaulding Hall ‐ Move Coordination and Support
1.1‐ PLAN/EST
FCRHEISNER, MICHELE
02/24/21 ‐Project is part of Spaulding and in support of swing space and move coordination.
Design Firm: Contractor: Contractor Name:
2020‐0249
Year Approved:
Spaulding Hall ‐ Utility and Infrastructure
3‐ IN CONSTRUCTION
FCRBRICKETT, ALEXANDER J
2/26/2021‐ Please see Project #2016‐0278 for updates.
Design Firm: Contractor: Contractor Name:
2020‐0246
Year Approved: 2020
Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative
3‐ IN CONSTRUCTION
CPBRICKETT, ALEXANDER J
2/26/2021‐ Building envelope completed. Final exterior trim in progress. Interior mechanical,
electrical, plumbing , framing, elevator, and sprinkler work in progress.
Design Firm: Ellenzweig Contractor: External Contractor Name: Skanska USA Building
2016‐0278
Year Approved: 2016
Stoke Hall Projects in Building 2
Stoke Hall ‐ Space Improvements in BIP Program Space
1.1‐ PLAN/EST
FCRGEUTHER, MARK E
02‐24‐2021: Met with client and Milestone to define scope. Estimate in progress.
Design Firm: TBD Contractor: External Contractor Name: Milestone
2021‐0096
Year Approved:
Monday, March 1, 2021 Page 22 of 26University of New Hampshire
Facilities Project Management
Page 23
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Stoke Hall ‐ Gas Code Violations
2‐ IN DESIGN
FCRHENRY, PAUL A
3‐2‐21 Looking at reducing the foot print in the laundry rooms, considering an ouside MAU and
ducted into the laundry rooms. Team currently looking into.
Design Firm: Harriman Contractor: External Contractor Name: TBD
2020‐0012
Year Approved: 2021
Telecommunications Center Projects in Building 2
Telecommunications Center ‐ Convert Old Staff Area
1.1‐ PLAN/EST
FCRGEUTHER, MARK E
02‐24‐2021: Requesting approval to move forward with design in FYʹ21 with funds remaining
from the addition.
Design Firm: Oak Point Associates Contractor: External Contractor Name: TBD
2021‐0010
Year Approved: 2022
Telecommunications Center ‐ Addition and Renovation
3.1‐ SUBSTANTIAL COMPLETION
FCRGEUTHER, MARK E
02‐24‐2021: Permission to occupy received. Working on Punch List and close out documentation.
Design Firm: Oak Point Contractor: External Contractor Name: Charters Brothers
2019‐0292
Year Approved: 2019
Thompson Hall Projects in Building 1
Thompson Hall ‐ Rm 203 ‐ Add DW to mini kitchen
1.1‐ PLAN/EST
FCRHEISNER, MICHELE
02/24/21‐ Cost estimate and scope presented for approval. Awaiting approval.
Design Firm: Contractor: Contractor Name:
2021‐0059
Year Approved:
Transportation Garage Projects in Building 1
Transportation Garage ‐ Utility Distribution ‐ Replace Existing transformer
2.5‐ IN PROCUREMENT
RRHEALEY, SCOTT M
1‐29‐21 ‐ Transformer should arrive in the middle of March, and need to be installed before June.
Ordered 10‐20 ‐ 23 week lead time.
Design Firm: Contractor: Contractor Name: IC Reed
2021‐0039
Year Approved: 2021
Utility Distribution Projects in Building 5
Monday, March 1, 2021 Page 23 of 26University of New Hampshire
Facilities Project Management
Page 24
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Utility Distribution ‐ Tunnel Repairs and Utility Line Replacement Leaving Central
Plant ‐ Design Only
2‐ IN DESIGN
RRRINES, DANIEL M
2‐24‐21: Design consulatant awarded to RMF. Inspection and report underway. Phase 2 of
contract, and DD to begin.
Design Firm: RMF Engineering Contractor: Contractor Name:
2020‐0004
Year Approved: 2021
Utility Distribution ‐ Lee Circle Water Line Extension
2‐ IN DESIGN
FCRRINES, DANIEL M
2‐24‐21 Consultant working on design, construction summer 2021 via the TOD
Design Firm: Underwood Eng Contractor: External Contractor Name: TBD
2018‐0256
Year Approved:
Utility Distribution ‐ Sector Cabinet Installation and Cable Replacement
2.5‐ IN PROCUREMENT
RRHEISNER, MICHELE
02/24/21‐ Location coordinated with 2020 0231 HSSC project site utility drawings. Equipment on
order. Installation work to be coordinated with HSSC.
Design Firm: Contractor: Contractor Name:
2021‐0082
Year Approved: 2021
Utility Distribution ‐ Dual Temp Interconnection
3‐ IN CONSTRUCTION
FCRROULEAU, RICHARD A
2/26/2021 ‐ Chilled water pump skid has been installed and has been piped. Work in the
McDaniel Drive Chiller Plant is essentially complete. Other than some controls work and a floor
drain installation, work to wind down until beginning of cooling season in late‐May.
Design Firm: Harriman Associates Contractor: External Contractor Name: Careno Construction
2019‐0022
Year Approved: 2019
Utility Distribution ‐ Piping Replacements from Heating Vault HVT086 to Handler Hall
3.1‐ SUBSTANTIAL COMPLETION
RRRINES, DANIEL M
2‐24‐21: working on minor punchlist, and project closeout. Warranty work identified in pit 4 as
well as valve in Handler Hall to be repaired post commencement.
Design Firm: Harriman Contractor: External Contractor Name: Anderson Welding
2018‐0362
Year Approved: 2021
Verizon Head End Building Projects in Building 1
Monday, March 1, 2021 Page 24 of 26University of New Hampshire
Facilities Project Management
Page 25
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Verizon Wireless Head End Building ‐ Construction
1.1‐ PLAN/EST
FCRPETERS, NICK E
26 Feb 2021 ‐ Pre‐bid walk through with subcontractors held 5 Oct. Contractor selection and
preparing submittals. Awaiting permitting information, which will fall through Town of
Durham, not SFMO. SFMO now responsible for connections between this building and campus.
Design Firm: Verizon Wireless Contractor: Contractor Name: Verizon Wireless
2020‐0270
Year Approved: 2020
Water Treatment Plant Projects in Building 1
Water Treatment Plant ‐ New Construction
3.1‐ SUBSTANTIAL COMPLETION
SIGEUTHER, MARK E
02‐24‐2021: Working on close out documentation.
Design Firm: Woodard & Curran Contractor: External Contractor Name: Waterline Industries
2008‐0038
Year Approved: 2014
Whittemore Center ‐ Arena Projects in Building 4
Whittemore Center ‐ Arena ‐ Section 112R ‐ Clean Air Compliance
1.1‐ PLAN/EST
RRGEUTHER, MARK E
02‐24‐2021: Project approved. Exception to Bid approved. Consultant schedule to be on campus
03‐08‐2021.
Design Firm: HCG Associates Contractor: External Contractor Name: TBD
2021‐0087
Year Approved: 2021
Whittemore Center ‐ Arena ‐ Fire Alarm and Sound System Control Panel Repairs
2‐ IN DESIGN
RR
Emergency Repair
HENRY, PAUL A
3‐2‐21 Installed UPS in equipment rack a the Field House, Jeff Murphy is working on testing
proceedure for training.
Design Firm: SFC Eng. Contractor: External Contractor Name: Norris ‐ Scarponi
2020‐0229
Year Approved: 2021
Whittemore Center ‐ Arena ‐ Verizon Wireless In‐Building Cellular Antenna System
3‐ IN CONSTRUCTION
FCRPETERS, NICK E
28 Feb 2021 ‐ Preliminary runs have been accomplished in telecom rooms. Primary construction
will begin late‐March to early‐April.
Design Firm: Contractor: External Contractor Name: Verizon Wireless
2020‐0269
Year Approved: 2020
Monday, March 1, 2021 Page 25 of 26University of New Hampshire
Facilities Project Management
Page 26
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Whittemore Center ‐ Arena ‐ Dehumidification System
3.1‐ SUBSTANTIAL COMPLETION
FCRBRICKETT, ALEXANDER J
2/26/2021 ‐ New unit has been installed. Commissioning in progress, to be completed when hot
weather returns
Design Firm: Harriman Contractor: External Contractor Name: Careno Construction
2017‐0308
Year Approved: 2019
Wildcat Stadium Projects in Building 1
Wildcat Stadium ‐ Verizon Wireless Distributed Antenna Installation
3‐ IN CONSTRUCTION
FCRPETERS, NICK E
28Feb 2021 ‐ Contractors have begun electrical permitting. Installation has commenced.
Design Firm: Verizon Wireless Contractor: External Contractor Name: Verizon Wireless
2020‐0268
Year Approved: 2020
Woodside Projects in Building 1
Woodside ‐ Mechanical Room Exhaust ‐ Design Only
1.1‐ PLAN/EST
FCRHENRY, PAUL A
3‐2‐21 Submitted CPR for approval still waitng, Design only.
Design Firm: Harriman Contractor: External Contractor Name: TBD
2021‐0086
Year Approved:
Monday, March 1, 2021 Page 26 of 26University of New Hampshire