FACILITIES, PLANNING, AND CONSTRUCTION April 14, 2014 Construction Report
16

Facilities, Planning, and Construction April 14, 2014 Construction Report

Jan 31, 2016

Download

Documents

Gail

Facilities, Planning, and Construction April 14, 2014 Construction Report. Area Currently Under Construction/ Planning. Facilities under Construction: V.R. Eaton High School 540,000 SF __________ - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Facilities, Planning, and Construction April 14, 2014 Construction Report

FACILITIES, PLANNING, AND CONSTRUCTIONApril 14, 2014 Construction Report

Page 2: Facilities, Planning, and Construction April 14, 2014 Construction Report

Facilities under Construction:

V.R. Eaton High School 540,000 SF __________ Total 540,000 SF

Facilities in Planning/Bidding Stage:

Peterson E.S. Addition 14,000 SF Beck E.S. Addition 8,000 SFNHS Chiller Replacement NAPrairie View Drainage Improvement NA ____________ Total 22,000 SF

Total Projects under Construction, Planning and Bidding: 562,000 SF562,000 SF

Area Currently Under Construction/ Planning Area Currently Under Construction/ Planning

Page 3: Facilities, Planning, and Construction April 14, 2014 Construction Report

V. R. Eaton High SchoolV. R. Eaton High SchoolArchitect: Corgan Associates Contractor: Pogue Construction CompanyConst. Start Date: Spring 2013Completion Date: August 2015

Status:Pier drilling is completeGeothermal wells are completeGrade beams are 95% completeFoundation slab is 50% completeRough electrical and plumbing is being installedSite grading and utility installation is underwaySteel erection is approximately 10% complete

(Please note that the aerial photo was taken in March and does not reflect April progress)

Page 4: Facilities, Planning, and Construction April 14, 2014 Construction Report

May 2013

March 2014

Page 5: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 6: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 7: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 8: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 9: Facilities, Planning, and Construction April 14, 2014 Construction Report
Page 10: Facilities, Planning, and Construction April 14, 2014 Construction Report

Peterson Elementary School AdditionPeterson Elementary School AdditionArchitect: SHW ArchitectsContractor: Northstar BuildersConst. Start Date: Spring 2014Completion Date: August 2014

Status:Classroom concrete slabs have been pouredSteel has begun to be erected for classroomsGrade beams have been poured for stage/cafeteria/gym expansion

Page 11: Facilities, Planning, and Construction April 14, 2014 Construction Report

January 2014

April 2014

Page 12: Facilities, Planning, and Construction April 14, 2014 Construction Report

Beck Elementary School AdditionBeck Elementary School AdditionArchitect: SHW ArchitectsContractor: Balfour Beatty ConstructionConst. Start Date: Spring 2014Completion Date: August 2014

Status:Pier drilling is underwaySite work is underway

Page 13: Facilities, Planning, and Construction April 14, 2014 Construction Report

Possible ONCOR Electric Power

Distribution Line

Page 14: Facilities, Planning, and Construction April 14, 2014 Construction Report

Miscellaneous Maintenance Projects

• Prairie View Elementary School Drainage Improvement– Water drains toward the front of the building

during heavy rains and flows into the building– Project will be to route water to a retention pond

and ditch adjacent to FM 3433– Possible replacement of the front driveway

• Northwest High School– Replace a 22 year old chiller– Anticipating a major failure within the next year– Current chiller contains obsolete R-22 refrigerant– The repair cost does not justify the repair– The efficiency of the replacement chiller will

provide reduction in energy cost

Page 15: Facilities, Planning, and Construction April 14, 2014 Construction Report

Pending Project Close-Out Change Orders

• Cox Elementary School• Love Elementary School• Subvarsity Stadium

Page 16: Facilities, Planning, and Construction April 14, 2014 Construction Report

FACILITIES, PLANNING, AND CONSTRUCTIONApril 14, 2014 Construction Report