Facilities Modernization Program Funded by Measure B Project Report April 19, 2010
8

Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.

Jan 01, 2016

Download

Documents

Elmer Peters
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.

Facilities Modernization ProgramFunded by Measure B

Project Report

April 19, 2010

Page 2: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.

PROJECT PROGRESS REPORTCollege Center for the Arts

Project Team: Architect: John Sergio Fisher & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: C. Overaa & Co

Project Update:• The exterior siding, stucco and windows are 99% complete.• The interior of the building is 97% complete in segment "B" which is the facility offices and the rehearsal rooms. • The Black Box Theater and the Main Auditorium infrastructure elements are continuing and will be completed this month. • The final concrete walk ways and ramp around the building and the Amphitheater are 98% complete. • The total project is 95% complete.

Occupancy Fall Semester 2010

LAS POSITAS COLLEGEApril 19, 2010

Page 3: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.

PROJECT PROGRESS REPORTChild Development Center

Project Team: Architect: Beverly Prior ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction Associates

Project Update:• Exterior plaster complete on all buildings. • Installation of sheetrock continues in building B and has started in building C.• Rough grading for the OLEs has begun.

Occupancy Spring 2011

LAS POSITAS COLLEGEApril 19, 2010

Page 4: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.

PROJECT PROGRESS REPORTPE Phase III (Outside Loop Road)

Project Team: Architect: WLC Architects / Carducci Landscape ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction

Project Update:• Underground & electrical utilities are continuing.

Occupancy: 10/2010

LAS POSITAS COLLEGEApril 19, 2010

Page 5: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.

PROJECT PROGRESS REPORTCollier Creek Storm Water Outfall

Project Team: Engineer of Record: SandisConstruction Manager: Parsons BrinckerhoffContractor: Lathrop Construction

Project Update:• Storm Drain and Retaining wall installation is complete.• Backfill at retaining wall is on going.

Occupancy: 04/2010

LAS POSITAS COLLEGEApril 19, 2010

Page 6: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.

PROJECT PROGRESS REPORTScience Building, Phase II

Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: TBD

Project Update:• Added space for 4 classrooms on second floor.• Site layout and floor plan finalized.• Projected submittal to DSA in March 2010.

Occupancy: Fall 2012

LAS POSITAS COLLEGEApril 19, 2010

Page 7: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.

PROJECT PROGRESS REPORTStudent Services & Central Administration

Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: TBD

Project Update:• 60% design documents were submitted in April• DSA submittal planned for August 2010,• This project will participate in the new DSA Collaborative Process.

Occupancy: Fall 2012

LAS POSITAS COLLEGEApril 19, 2010

Page 8: Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.

PROJECT PROGRESS REPORTCampus Boulevard Phase I-III

Project Team: Architect: RHAA Construction Manager: Parsons BrinckerhoffContractor: TBD

Project Update:• Design stopped to coordinate with SSA design concepts.

Occupancy: Fall 2011

LAS POSITAS COLLEGEApril 19, 2010