Facilities Modernization Program Funded by Measure B Project Report December 17, 2012
4

Facilities Modernization Program Funded by Measure B Project Report

Feb 23, 2016

Download

Documents

taji

Facilities Modernization Program Funded by Measure B Project Report. December 17, 2012. PROJECT PROGRESS REPORT Student Services & Central Administration. LAS POSITAS COLLEGE December 17, 2012. Project Team: Architect : Steinberg Architects - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization ProgramFunded by Measure B

Project Report

December 17, 2012

Page 2: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTStudent Services & Central Administration

Project Team: Architect: Steinberg ArchitectsConstruction Manager: Parsons BrinckerhoffContractor: Zovich Construction

Project Update:• Ceiling tile is being installed on the 2nd floor. 85% complete.• Tile in the entry corridor is complete and has started in the gallery.• Interior trim is 95% complete. Kitchen Equipment is 90% installed.• Ceilings grid in the dining areas is complete, wood slats to follow within the next 2 weeks.• Site concrete is 95% complete. Irrigation and planting are complete. Paver installation is complete.

Landscape maintenance period has started.

Occupancy: Spring 2013

LAS POSITAS COLLEGEDecember 17, 2012

Page 3: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTCampus Boulevard Phase I-III

Project Team: Architect: Gates & AssociatesConstruction Manager: Parsons BrinckerhoffContractor: Suarez & Munoz Construction, Inc.

Project Update:• Concrete Pathways 100% Complete, with parts of the pathways open. Library and Grand Stairs Complete • Underground Electrical and Lighting are 100% Complete• Boulders for the wet fountain have been placed, with the dry art area completed and are open to students

and faculty• Underground mainlines and laterals are 100% completed.• Grading work is 90% completed with planting continuing with completion to be 12/29/12

Occupancy: 12/31/12

LAS POSITAS COLLEGEDecember 17, 2012

Page 4: Facilities Modernization Program Funded by Measure B Project Report

PROJECT PROGRESS REPORTScience Building, Phase II

Project Team: Architect: Kwan HemniConstruction Manager: Parsons BrinckerhoffContractor: Broward Builders, Inc

Project Update:• New Science Bldg 1850 Complete, Punch List work is 95% complete and in progress• Bldg 1800 Remodel Complete, Punch List work is 95% complete and in progress• Closeout is in progress

Occupancy: 09/2012

LAS POSITAS COLLEGEDecember 17, 2012